I-59/20 Construction: ALDOT Eyes January Completion

The Alabama Department of Transportation says the I-59/20 rebuilding project could be completed by the end of January.

The I-59/20 bridge rebuilding project could be completed in January.
The I-59/20 bridge rebuilding project could be completed in January. (Michael Seale/Patch)

BIRMINGHAM, AL β€” What has been one of the most extensive and β€” unfortunately disruptive β€” traffic projects in Birmingham in decades may finally be completed in the next several weeks. During a monthly media briefing Thursday morning, Alabama Department of Transportation officials said a January completion for the project is possible.

The project, which was expected to last 14 months when construction began in January of 2019, could possibly see the bridges open by by January 21, according to ALDOT spokesman DeJarvis Leonard.

If the project finishes by the end of January, the contractor, Johnson Brothers Corp., earns a $15 million bonus, and Leonard said work is being done around the clock. ALDOT gave Johnson Brothers until March 21 to have the bridges open, or be fined $250,000 each day the bridge opening was delayed.

Find out what's happening in Birminghamwith free, real-time updates from Patch.

Conversely, the contractor will receive a $250,000 bonus for each day the project is finished before March 21.

Leonard said the bulk of the work remaining on the project includes grinding and grooving the bridges and completing the installation of lighting.