City Of Glendora: March 2022 Gold Line Update

See the latest announcement from the City of Glendora.

(City of Glendora)

03/07/2022 8:34 AM

IMPORTANT: Coronavirus (COVID-19) Information

"As the Glendora to Pomona project segment enters the 20th month of major construction, the project is already 43% complete. As March begins, 95% of the freight track relocation, 80% of the utility relocation, and 74% of the grade crossing reconstruction is now behind us. These are the activities that involve the most risk for the project, so having the majority of these tasks complete provides confidence that the project will be able to reach substantial completion in early 2025, on schedule."