Dedham's Rustcraft Rd Sewer Improvements Project - Work Schedule For Week Of August 3

Police details will be present to direct traffic around the work area.

July 31, 2020

To date, RJV has installed approximately 2,500 LF (approx 51% of the total 4,885 LF to be installed) of the 10" Ductile Iron Force Main.

Find out what's happening in Dedhamwith free, real-time updates from Patch.

For the week of August 3rd, RJV Construction Corp. (Contractor) will performing the following activities:

  • Excavation for and installation of the 10" force main continuing near Station 25+00 to Station 17+00.

Police details will be present to direct traffic around the work area.

Find out what's happening in Dedhamwith free, real-time updates from Patch.

For up-to-date information and photos regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.

You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here.


This press release was produced by the Town of Dedham. The views expressed here are the author’s own.