Rustcraft Rd Sewer Improvements Project In Dedham

For up-to-date information regarding this project, please be sure to subscribe to Engineering Project Updates by clicking at the below link.

June 19, 2020

For the week of June 22nd, RJV Construction Corp. (Contractor) will performing the following activities:

Find out what's happening in Dedhamwith free, real-time updates from Patch.

  • Excavation for and installation of the 10" force main starting at Station 46+86 (Near #105 Rustcraft Road) to Station 38+86 (Near concession stand at Fairbanks Field)

Police details will be present to direct traffic around the work area.

For up-to-date information regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.

Find out what's happening in Dedhamwith free, real-time updates from Patch.

You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here.