PRECIOS UNITARIOS - Michel
PRECIOS UNITARIOS - Michel
Unidad: M2
LIMPIEZA Y DESHIERBE EN EL AREA DE TRABAJO CON UN ESPESOR DE HASTA 15CMS, INC.: RETIRO DEL MATERIAL PRODUCTO
DEL TRABAJO FUERA DE OBRA.
Clave: ICRF-002
Unidad: M2
TRAZO Y NIVELACION EN EL AREA DE TRABAJO, ESTABLECIENDO EJES Y REFERENCIAS.
Mano De Obra
00-0010 PEON JOR 0.01 $344.59 $2.87
01-0310 OFICIAL ALBAÑIL JOR 0.00 $452.72 $1.88
01-1000 CABO JOR 0.00 $452.72 $0.28
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.12
Total de Mano De Obra $5.15
Clave: ICRF-003
Unidad: M3
EXCAVACION A MANO CON PICO Y PALA EN MATERIAL TIPO II A UNA PROFUNDIDAD DE 0.00 A 1.00 MT., INC.: AFINE DE FONDO.
Clave: ICRF-004
Unidad: M2
PLANTILLA DE CONCRETO POBRE F'C = 100 KG/CM2; ESPESOR DE 5 CMS.
Material
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.01 $2,820.00 $40.33
0302-05 AGUA DE TOMA MUNICIPAL M3 0.01 $40.00 $0.54
0302-20 ARENA M3 0.03 $125.00 $3.90
0302-30 GRAVA M3 0.04 $183.33 $6.67
Total de Material $51.44
Mano De Obra
00-0010 PEON JOR 0.05 $344.59 $18.24
01-0310 OFICIAL ALBAÑIL JOR 0.03 $452.72 $14.15
01-1000 CABO JOR 0.00 $452.72 $1.91
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.79
Total de Mano De Obra $35.09
Clave: ICRF-005
Unidad: M3
MAMPOSTERIA DE PIEDRA BRASA ASENTADA CON CEMENTO-CAL-ARENA EN PROP.: 1:1:6 CON UNA SECCION DE 60 CMS DE
BASE, 30 CMS DE CORONA Y HASTA 80 CMS DE ALTURA.
Mano De Obra
00-0010 PEON JOR 0.73 $344.59 $250.59
01-0310 OFICIAL ALBAÑIL JOR 0.36 $452.72 $164.61
01-1000 CABO JOR 0.05 $452.72 $24.69
01-1080 MAESTRO DE OBRA JOR 0.02 $539.68 $10.30
Total de Mano De Obra $450.19
Clave: ICRF-006
Unidad: PZA
BASE PARA CASTILLO CON UNA SECCION DE 30 X 30 X 40 CMS DE CONCRETO F'C = 150 KG/CM2, INC.: ANCLAJE CON ARMEX,
CIMBRA Y DESCIMBRA.
Material
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.13 $26.50 $3.57
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.04 $2,820.00 $103.44
0302-05 AGUA DE TOMA MUNICIPAL M3 0.03 $40.00 $1.13
0302-20 ARENA M3 0.07 $125.00 $8.40
0302-30 GRAVA M3 0.08 $183.33 $14.37
0950-05 DIESEL LT 0.17 $14.63 $2.46
1900-05 MADERA DE PINO DE 3A PT 1.27 $12.60 $15.98
Total de Material $149.35
Mano De Obra
00-0010 PEON JOR 0.09 $344.59 $29.96
01-0310 OFICIAL ALBAÑIL JOR 0.09 $452.72 $39.36
01-1000 CABO JOR 0.01 $452.72 $3.94
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.64
Total de Mano De Obra $74.90
Clave: ICRF-007
Unidad: M3
RELLENO Y COMPACTACION CON PISON DE MANO CON MATERIAL PRODUCTO DE LA EXCAVACION EN CAPAS NO MAYORES DE
20 CMS, INC. INCORPORACION DE AGUA.
Mano De Obra
00-0010 PEON JOR 0.18 $344.59 $61.61
01-1000 CABO JOR 0.01 $452.72 $4.05
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.69
Total de Mano De Obra $67.35
Clave: ICRF-008
Unidad: M3
RELLENO POR MEDIOS MECANICOS CON MATERIAL LIMPIO (TEPETATE) EN CAPAS NO MAYORES DE 20 CMS, INC.
INCORPORACION DE AGUA.
Mano De Obra
00-0010 PEON JOR 0.18 $344.59 $61.61
01-1000 CABO JOR 0.01 $452.72 $4.05
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.69
Total de Mano De Obra $67.35
Clave: ICRF-009
Unidad: M
CADENA DE DESPLANTE CON UNA SECCION DE CONCRETO F'C = 150 KG/CM2, DE 15 X 20 CMS, ARMADA CON ARMEX TIPO 15X20-
4, INC.: CIMBRA Y DESCIMBRA.
Mano De Obra
00-0010 PEON JOR 0.10 $344.59 $33.62
01-0310 OFICIAL ALBAÑIL JOR 0.10 $452.72 $44.17
01-1000 CABO JOR 0.01 $452.72 $4.42
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.84
Total de Mano De Obra $84.05
Clave: 040126
Unidad: M
CADENA DE DESPLANTE CON UNA SECCION DE 15 X 20 CM, CONCRETO F'C=200 KG/CM2, REFORZADA CON 4 VARILLAS DE 3/8"
ESTRIBOS DE 1/4" A/C 20 CM; INCLUYE CIMBRA Y DESCIMBRA
Material
0080-01 ALAMBRON LISO DE 1/4" ( NO. 2 ) KG 0.84 $13.50 $11.38
0082-05 ALAMBRE RECOCIDO NO. 18 KG 0.20 $17.70 $3.54
0084-001 VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) KG 2.34 $13.20 $30.88
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.14 $26.50 $3.58
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.01 $2,820.00 $32.68
0302-05 AGUA DE TOMA MUNICIPAL M3 0.01 $40.00 $0.32
0302-20 ARENA M3 0.02 $125.00 $2.09
0302-30 GRAVA M3 0.02 $183.33 $3.71
0950-05 DIESEL LT 0.60 $14.63 $8.78
1900-05 MADERA DE PINO DE 3A PT 1.20 $12.60 $15.07
Total de Material $112.03
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $6.25 $0.25
00-0010 PEON JOR 0.10 $344.59 $35.01
01-0310 OFICIAL ALBAÑIL JOR 0.09 $452.72 $39.34
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.00 $315.89 $0.66
01-1000 CABO JOR 0.01 $452.72 $4.31
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.79
Total de Mano De Obra $81.36
Clave: ECO0025
Unidad: M3
CONTRATRABE DE CIMENTACION CT-1 DE 20 X 40 CM., FABRICADA CON CONCRETO F'C=200 KG/CM2, R.N. AGREG.MAX. 20 MM.
(3/4"), INCLUYE: PLANTILLA DE CONCRETO H.O. F'C=100 KG/CM2 DE 5 CM. DE ESPESOR, CIMBRA, DESCIMBRA, HABILITADO DE
115 KG DE ACERO DE REFUERZO DE 3/4" ; 1/2" Y 3/8" X M3. DE CONCRETO; INCLUYE: MATERIALES, MANO DE OBRA Y EQUIPO.
Material
A1AAR015 Alambron 1/4" No. 2 t 0.03 $8,500.00 $231.20
A4BAR012 Alambre recocido Calibre 18 kg 4.83 $12.17 $58.76
A4EAR020 Clavo c/cabeza de 2"-4" kg 5.19 $11.00 $57.08
ACACT055 Cemento Tolteca CPC 30 R (cemento portland compuesto) t 0.39 $2,820.00 $1,094.98
ACMXX005 Agua m3 0.29 $85.00 $24.23
AIGFE052 Curafest rojo (Fester) L 1.00 $20.56 $20.56
APAXX005 Arena de mina (por camión 6m3) m3 0.56 $173.91 $97.17
APBXX020 Grava de 3/4" m3 0.68 $173.91 $117.82
CIAMP035 Barrote 1 1/2" x 4" x 8' pt 29.77 $7.25 $215.82
CIAMP055 Duela 3/4" x 4" x 8' pt 33.45 $9.00 $301.03
CIAMP090 Polin de 3 1/2"x3 1/2" regular pt 7.21 $6.77 $48.80
H7BPL005 Diesel L 17.60 $5.03 $88.53
VAR020 Varilla de acero corrugada 1/2" No. 4, marca Aceros San Luis t 0.11 $13,200.00 $1,394.18
VAR025 Varilla de acero corrugada 5/8" No. 5, marca Aceros San Luis t 0.02 $13,200.00 $248.95
Total de Material $3,999.11
Mano De Obra
1AA00 Peón Jor 0.35 $235.60 $82.38
1AABO Albañil Jor 0.31 $379.23 $116.88
1AABY Ayudante de albañil Jor 0.31 $233.40 $71.93
1ACCO Carpintero para cimbras Jor 1.61 $352.72 $567.17
1ACCY Ayudante carpintero para cimbras Jor 1.61 $237.81 $382.40
1AFRO Fierrero Jor 0.72 $352.72 $253.61
1AFRY Ayudante de fierrero Jor 0.72 $235.60 $169.40
1AZC1 Cabo de oficiales jor 0.30 $523.84 $156.36
Total de Mano De Obra $1,800.13
Herramienta
2HER Herramienta menor (%)mo 0.02 $1,800.13 $36.00
Total de Herramienta $36.00
Clave: 030116
Unidad: PZA
ZAPATA AISLADA, SIN DADO Z-1; DE CONCRETO 200 KG/CM2 AGREGADO DE 20 MM, CEMENTO NORMAL REVENIMIENTO 8 A 10
CM., SECCIÓN DE 1.85 X 1.85 MTS, PERALTE DE 0.35 MTS, PLANTILLA DE 0.05 MTS DE ESPESOR, ARMADO CON ACERO DE
REFUERZO # 5 A CADA 16 CMS. EN AMBOS SENTIDOS, INLCUYE: CIMBRA COMUN, MANO DE OBRA, HERRAMIENTA MENOR.
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.26 $344.59 $434.08
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.14 $344.59 $49.72
01-0070 AYUDANTE DE FIERRERO JOR 0.58 $344.59 $198.88
01-0310 OFICIAL ALBAÑIL JOR 0.16 $452.72 $71.24
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.14 $452.72 $65.33
01-0330 FIERRERO OBRA NEGRA JOR 0.58 $452.72 $261.29
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.15 $452.72 $66.31
01-1080 MAESTRO DE OBRA JOR 0.05 $539.68 $27.42
Total de Mano De Obra $1,204.41
Clave: 030115
Unidad: PZA
ZAPATA AISLADA, SIN DADO Z-2; DE CONCRETO 200 KG/CM2 AGREGADO DE 20 MM, CEMENTO NORMAL REVENIMIENTO 8 A 10
CM., SECCIÓN DE 1.70 X 1.70 MTS, PERALTE DE 0.35 MTS, PLANTILLA DE 0.05 MTS DE ESPESOR, ARMADO CON ACERO DE
REFUERZO # 4 A CADA 16 CMS. EN AMBOS SENTIDOS, INLCUYE: CIMBRA COMUN, MANO DE OBRA, HERRAMIENTA MENOR.
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.26 $344.59 $434.08
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.14 $344.59 $49.72
01-0070 AYUDANTE DE FIERRERO JOR 0.27 $344.59 $93.97
01-0310 OFICIAL ALBAÑIL JOR 0.16 $452.72 $71.24
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.14 $452.72 $65.33
01-0330 FIERRERO OBRA NEGRA JOR 0.27 $452.72 $123.46
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.12 $452.72 $52.52
01-1080 MAESTRO DE OBRA JOR 0.04 $539.68 $21.66
Total de Mano De Obra $942.12
Clave: ECO0022
Unidad: PZA
ZAPATA AISLADA, SIN DADO Z-3; DE CONCRETO 200 KG/CM2 AGREGADO DE 20 MM, CEMENTO NORMAL REVENIMIENTO 8 A 10
CM., SECCIÓN DE 1.50 X 1.50 MTS, PERALTE DE 0.30 MTS, PLANTILLA DE 0.05 MTS DE ESPESOR, ARMADO CON ACERO DE
REFUERZO # 4 A CADA 16 CMS. EN AMBOS SENTIDOS, INLCUYE: CIMBRA COMUN, MANO DE OBRA, HERRAMIENTA MENOR.
Mano De Obra
1AA00 Peón Jor 0.35 $235.60 $82.78
1AABO Albañil Jor 0.31 $379.23 $118.09
1AABY Ayudante de albañil Jor 0.31 $233.40 $72.68
1ACCO Carpintero para cimbras Jor 0.13 $352.72 $44.27
1ACCY Ayudante carpintero para cimbras Jor 0.13 $237.81 $29.85
1AFRO Fierrero Jor 0.32 $352.72 $111.40
1AFRY Ayudante de fierrero Jor 0.32 $235.60 $74.41
1AZC1 Cabo de oficiales jor 0.11 $523.84 $57.84
Total de Mano De Obra $591.32
Herramienta
2HER Herramienta menor (%)mo 0.02 $591.32 $11.83
Total de Herramienta $11.83
Clave: ECO0023
Unidad: PZA
ZAPATA AISLADA, SIN DADO Z-4; DE CONCRETO 200 KG/CM2 AGREGADO DE 20 MM, CEMENTO NORMAL REVENIMIENTO 8 A 10
CM., SECCIÓN DE 1.00 X 0.90 MTS, PERALTE DE 0.20 MTS, PLANTILLA DE 0.05 MTS DE ESPESOR, ARMADO CON ACERO DE
REFUERZO # 4 A CADA 20 CMS. EN AMBOS SENTIDOS, INLCUYE: CIMBRA COMUN, MANO DE OBRA, HERRAMIENTA MENOR.
Mano De Obra
1AA00 Peón Jor 0.14 $235.60 $31.83
1AABO Albañil Jor 0.31 $379.23 $118.09
1AABY Ayudante de albañil Jor 0.31 $233.40 $72.68
1ACCO Carpintero para cimbras Jor 0.01 $352.72 $4.43
1ACCY Ayudante carpintero para cimbras Jor 0.01 $237.81 $2.98
1AFRO Fierrero Jor 0.06 $352.72 $20.05
1AFRY Ayudante de fierrero Jor 0.06 $235.60 $13.39
1AZC1 Cabo de oficiales jor 0.05 $523.84 $27.02
Total de Mano De Obra $290.47
Herramienta
2HER Herramienta menor (%)mo 0.02 $290.47 $5.81
Total de Herramienta $5.81
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $25.82 $1.03
00-0010 PEON JOR 0.21 $344.59 $72.14
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.01 $344.59 $4.31
01-0070 AYUDANTE DE FIERRERO JOR 0.00 $344.59 $0.15
01-0310 OFICIAL ALBAÑIL JOR 0.03 $452.72 $13.47
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.01 $452.72 $5.66
01-0330 FIERRERO OBRA NEGRA JOR 0.00 $452.72 $0.10
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.01 $315.89 $2.74
01-1000 CABO JOR 0.01 $452.72 $6.19
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $2.55
Total de Mano De Obra $108.34
Clave: ICRF-010
Unidad: M
IMPERMEABILIZACION DE DALAS DE APOYO, INC.: PRIMER IMPERPRIM O SIMILAR Y UNA CAPA DE VAPORQUIM.
Clave Descripción Unidad Cantidad Precio U. Total
Material
1650-15 PRIMER IMPERPRIM LT 0.10 $31.31 $3.13
1652-88 VAPORQUIM M2 0.96 $45.49 $43.67
Total de Material $46.80
Mano De Obra
00-0010 PEON JOR 0.01 $344.59 $4.95
01-0310 OFICIAL ALBAÑIL JOR 0.01 $452.72 $6.50
01-1000 CABO JOR 0.00 $452.72 $0.65
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.27
Total de Mano De Obra $12.37
Clave: ICRF-011
Unidad: M2
MURO DE TABIQUE ROJO RECOCIDO DE 12 A 14 CMS DE ESPESOR ASENTADO CON MORTERO DE CEMENTO-CAL-ARENA
PROP.: 1:1:6, INC.: ANDAMIOS.
Mano De Obra
00-0010 PEON JOR 0.15 $344.59 $51.69
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.16
01-0310 OFICIAL ALBAÑIL JOR 0.15 $452.72 $67.91
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.21
01-1000 CABO JOR 0.02 $452.72 $6.81
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $2.84
Total de Mano De Obra $129.62
Mano De Obra
00-0010 PEON JOR 0.17 $344.59 $58.58
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.21
01-0310 OFICIAL ALBAÑIL JOR 0.17 $452.72 $76.96
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.27
01-1000 CABO JOR 0.02 $452.72 $7.72
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.22
Total de Mano De Obra $146.96
Clave: ICRF-013
Unidad: M
CASTILLO CON UNA SECCION DE CONCRETO F'C = 150 KG/CM2 DE 15 X 25 CMS ARMADOS CON 6 VARILLAS DE 3/8"; ESTRIBOS
DE 1/4" A CADA 15CMS, INC.: CIMBRA Y DESCIMBRA A DOS CARAS.
Mano De Obra
00-0010 PEON JOR 0.00 $344.59 $1.23
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.08 $344.59 $27.71
01-0070 AYUDANTE DE FIERRERO JOR 0.00 $344.59 $0.21
01-0310 OFICIAL ALBAÑIL JOR 0.00 $452.72 $0.18
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.08 $452.72 $36.40
01-0330 FIERRERO OBRA NEGRA JOR 0.00 $452.72 $0.14
01-1000 CABO JOR 0.01 $452.72 $3.75
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.57
Total de Mano De Obra $71.19
Clave: 040521
Unidad: M
CASTILLO K-4 DE CONCRETO SECCION= 15 X 40 CM, CONCRETO F'C=200 KG/CM2-3/4", CIMBRA 3 CARAS REFORZADO CON 6
VARILLAS DE 3/8" ESTRIBOS DE 1/4" A CADA 15 CM
Material
0080-01 ALAMBRON LISO DE 1/4" ( NO. 2 ) KG 1.05 $13.50 $14.23
0082-05 ALAMBRE RECOCIDO NO. 18 KG 0.20 $17.70 $3.54
0084-002 VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) KG 2.34 $13.20 $30.88
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.14 $26.50 $3.67
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.02 $2,820.00 $48.98
0302-05 AGUA DE TOMA MUNICIPAL M3 0.01 $40.00 $0.48
0302-20 ARENA M3 0.03 $125.00 $3.13
0302-30 GRAVA M3 0.03 $183.33 $5.56
0950-05 DIESEL LT 0.60 $14.63 $8.78
1900-05 MADERA DE PINO DE 3A PT 2.06 $12.60 $25.90
Total de Material $145.15
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $9.37 $0.37
00-0010 PEON JOR 0.37 $344.59 $128.19
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.29
01-0310 OFICIAL ALBAÑIL JOR 0.35 $452.72 $158.45
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.38
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.00 $315.89 $0.99
01-1000 CABO JOR 0.04 $452.72 $16.45
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $6.85
Total de Mano De Obra $311.97
Clave: 030205
Unidad: M3
COLUMNA C-1 EN ESTRUCTURA DE SECCION=40 X 40 CM CIMBRA COMUN REFORZADO CON 180 KG/M3 DE ACERO FY'=4200
KG/CM2 CONCRETO F'C=200 KG/CM2-3/4" INCLUYE CIMBRA Y DESCIMBRA
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.67 $344.59 $577.14
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 2.14 $344.59 $738.80
01-0070 AYUDANTE DE FIERRERO JOR 0.67 $344.59 $229.33
01-0310 OFICIAL ALBAÑIL JOR 0.24 $452.72 $107.75
01-0320 CARPINTERO DE OBRA NEGRA JOR 2.14 $452.72 $970.63
01-0330 FIERRERO OBRA NEGRA JOR 0.67 $452.72 $301.22
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.38 $452.72 $172.06
01-1080 MAESTRO DE OBRA JOR 0.13 $539.68 $71.53
Total de Mano De Obra $3,198.60
Clave: 030210
Unidad: M3
COLUMNA C-2 EN ESTRUCTURA DE SECCION=35 X 40 CM CIMBRA APARENTE REFORZADA CON 180 KG/M3 DE ACERO FY'=4200
KG/CM2 CONCRETO F'C=200 KG/CM2-3/4" INCLUYE CIMBRA Y DESCIMBRA
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.67 $344.59 $577.14
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 1.46 $344.59 $504.48
01-0070 AYUDANTE DE FIERRERO JOR 0.67 $344.59 $229.33
01-0310 OFICIAL ALBAÑIL JOR 0.24 $452.72 $107.75
01-0320 CARPINTERO DE OBRA NEGRA JOR 1.46 $452.72 $662.78
01-0330 FIERRERO OBRA NEGRA JOR 0.67 $452.72 $301.22
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.31 $452.72 $141.27
01-1080 MAESTRO DE OBRA JOR 0.11 $539.68 $58.69
Total de Mano De Obra $2,612.80
Clave: 030211
Unidad: M3
COLUMNA C-3 EN ESTRUCTURA DE SECCION=35 X 35 CM CIMBRA COMUN REFORZADA CON 180 KG/M3 DE ACERO FY'=4200
KG/CM2 CONCRETO F'C=250 KG/CM2-3/4" INCLUYE CIMBRA Y DESCIMBRA
Material
0080-01 ALAMBRON LISO DE 1/4" ( NO. 2 ) KG 0.03 $13.50 $0.39
0082-05 ALAMBRE RECOCIDO NO. 18 KG 2.30 $17.70 $40.62
0086-00 VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) TON 0.17 $13,200.00 $2,247.83
0092-00 VARILLA ALTA RESISTENCIA FY=6000 KG/CM2 NO 3 ( 3/8" ) TON 0.03 $13,200.00 $356.40
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 4.82 $26.50 $127.60
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.43 $2,820.00 $1,208.31
0302-05 AGUA DE TOMA MUNICIPAL M3 0.31 $40.00 $12.51
0302-20 ARENA M3 0.56 $125.00 $69.55
0302-30 GRAVA M3 0.66 $183.33 $121.45
0950-05 DIESEL LT 6.00 $14.63 $87.78
1900-05 MADERA DE PINO DE 3A PT 45.34 $12.60 $571.31
Total de Material $4,843.75
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.67 $344.59 $577.14
01-0070 AYUDANTE DE FIERRERO JOR 0.67 $344.59 $229.33
01-0310 OFICIAL ALBAÑIL JOR 0.24 $452.72 $107.75
01-0330 FIERRERO OBRA NEGRA JOR 0.67 $452.72 $301.22
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.17 $452.72 $74.99
01-1080 MAESTRO DE OBRA JOR 0.06 $539.68 $31.04
Total de Mano De Obra $1,351.61
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.67 $344.59 $577.14
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.15 $344.59 $50.45
01-0070 AYUDANTE DE FIERRERO JOR 0.65 $344.59 $224.83
01-0310 OFICIAL ALBAÑIL JOR 0.24 $452.72 $107.75
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.15 $452.72 $66.28
01-0330 FIERRERO OBRA NEGRA JOR 0.65 $452.72 $295.32
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.18 $452.72 $81.03
01-1080 MAESTRO DE OBRA JOR 0.06 $539.68 $33.56
Total de Mano De Obra $1,466.50
Clave: 030305
Unidad: M3
TRABE T-1 EN ESTRUCTURA DE SECCION = 0.26 X0. 65 X 20.0 MTS DE CONCRETO F'C=200 KG/CM2-3/4" CIMBRA COMUN
REFORZADA CON 185 KG/M3 DE ACERO FY'=4200 KG/CM2 QUE SE DESGLOSAN EN 4 VARILLAS DE 3/4" EN LECHO SUPERIOR E
INFERIOR; 4 VARILLAS DE 1/2" INTERMEDIAS Y 2 VARILLAS DE 3/4" EN VALLONETA; ESTRIBOS DE 3/8" A CADA 10 Y 15 CMS;
INCLUYE CIMBRA Y DESCIMBRA
Clave Descripción Unidad Cantidad Precio U. Total
Material
0080-01 ALAMBRON LISO DE 1/4" ( NO. 2 ) KG 0.02 $13.50 $0.28
0082-05 ALAMBRE RECOCIDO NO. 18 KG 2.50 $17.70 $44.21
0086-00 VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) TON 0.12 $13,200.00 $1,623.47
0092-00 VARILLA ALTA RESISTENCIA FY=6000 KG/CM2 NO 3 ( 3/8" ) TON 0.02 $13,200.00 $257.40
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 2.21 $26.50 $58.43
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.38 $2,820.00 $1,079.27
0302-05 AGUA DE TOMA MUNICIPAL M3 0.32 $40.00 $12.88
0302-20 ARENA M3 0.55 $125.00 $69.03
0302-30 GRAVA M3 0.67 $183.33 $122.60
0950-05 DIESEL LT 5.25 $14.63 $76.81
1900-05 MADERA DE PINO DE 3A PT 36.75 $12.60 $463.05
1900-10 MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" PT 17.96 $14.76 $265.02
1900-15 MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" PT 33.60 $5.75 $193.20
1900-30 CHAFLAN DE MADERA DE PINO DE 3A. DE 1" M 11.55 $6.00 $69.30
Total de Material $4,334.95
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.62 $344.59 $558.53
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 1.42 $344.59 $488.82
01-0070 AYUDANTE DE FIERRERO JOR 1.38 $344.59 $475.76
01-0310 OFICIAL ALBAÑIL JOR 0.23 $452.72 $102.86
01-0320 CARPINTERO DE OBRA NEGRA JOR 1.42 $452.72 $642.21
01-0330 FIERRERO OBRA NEGRA JOR 1.38 $452.72 $625.00
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.38 $452.72 $170.12
01-1080 MAESTRO DE OBRA JOR 0.13 $539.68 $70.73
Total de Mano De Obra $3,164.17
Clave: 030301
Unidad: M3
TRABE T-2 EN ESTRUCTURA DE SECCION = 0.26 X 0.65 X 16.70 MTS DE CONCRETO F'C=200 KG/CM2-3/4" CIMBRA COMUN
REFORZADA CON 135 KG/M3 DE ACERO FY'=4200 KG/CM2 QUE SE DESGLOSAN EN 3 VARILLAS DE 3/4" EN LECHO SUPERIOR E
INFERIOR; 4 VARILLAS DE 1/2" INTERMEDIAS Y 3 VARILLAS DE 1/2" EN VALLONETA; ESTRIBOS DE 3/8" A CADA 10 Y 15 CMS;
INCLUYE CIMBRA Y DESCIMBRA
Clave Descripción Unidad Cantidad Precio U. Total
Material
0080-01 ALAMBRON LISO DE 1/4" ( NO. 2 ) KG 0.02 $13.50 $0.28
0082-05 ALAMBRE RECOCIDO NO. 18 KG 1.66 $17.70 $29.34
0086-00 VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) TON 0.12 $13,200.00 $1,623.47
0092-00 VARILLA ALTA RESISTENCIA FY=6000 KG/CM2 NO 3 ( 3/8" ) TON 0.02 $13,200.00 $257.40
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 4.91 $26.50 $130.15
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.38 $2,820.00 $1,079.27
0302-05 AGUA DE TOMA MUNICIPAL M3 0.32 $40.00 $12.88
0302-20 ARENA M3 0.55 $125.00 $69.03
0302-30 GRAVA M3 0.67 $183.33 $122.60
0950-05 DIESEL LT 6.12 $14.63 $89.54
1900-05 MADERA DE PINO DE 3A PT 46.25 $12.60 $582.74
Total de Material $3,996.70
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.62 $344.59 $558.53
01-0070 AYUDANTE DE FIERRERO JOR 0.48 $344.59 $165.63
01-0310 OFICIAL ALBAÑIL JOR 0.23 $452.72 $102.86
01-0330 FIERRERO OBRA NEGRA JOR 0.48 $452.72 $217.55
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.14 $452.72 $65.16
01-1080 MAESTRO DE OBRA JOR 0.05 $539.68 $26.94
Total de Mano De Obra $1,166.81
Clave: 030306
Unidad: M3
TRABE T-3 EN ESTRUCTURA DE SECCION = 0.20 X 0.40 X 30.00 MTS DE CONCRETO F'C=200 KG/CM2-3/4" CIMBRA COMUN
REFORZADA CON 110 KG/M3 DE ACERO FY'=4200 KG/CM2 QUE SE DESGLOSAN EN 3 VARILLAS DE 1/2" EN LECHO SUPERIOR; 2
VARILLAS DE 3/8" INTERMEDIAS; 1 VARILLA DE 1/2" EN VALLONETA Y 2 VARILLAS DE 1/2" EN LECHO INFERIOR; ESTRIBOS DE
ALAMBRON A CADA 10 Y 15 CMS; INCLUYE CIMBRA Y DESCIMBRA
Clave Descripción Unidad Cantidad Precio U. Total
Material
0082-05 ALAMBRE RECOCIDO NO. 18 KG 3.69 $17.70 $65.39
0086-00 VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) TON 0.24 $13,200.00 $3,124.97
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 1.32 $26.50 $35.06
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.38 $2,820.00 $1,079.27
0302-05 AGUA DE TOMA MUNICIPAL M3 0.32 $40.00 $12.88
0302-20 ARENA M3 0.55 $125.00 $69.03
0302-30 GRAVA M3 0.67 $183.33 $122.60
0950-05 DIESEL LT 3.15 $14.63 $46.08
1900-05 MADERA DE PINO DE 3A PT 7.62 $12.60 $96.05
1900-10 MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" PT 10.77 $14.76 $159.01
1900-15 MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" PT 20.16 $5.75 $115.92
1900-30 CHAFLAN DE MADERA DE PINO DE 3A. DE 1" M 6.93 $6.00 $41.58
1900-80 TRIPLAY DE PINO DE 16 MM 1 CARA HOJA 0.36 $366.45 $132.52
Total de Material $5,100.36
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.62 $344.59 $558.53
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.85 $344.59 $293.29
01-0070 AYUDANTE DE FIERRERO JOR 0.92 $344.59 $318.67
01-0310 OFICIAL ALBAÑIL JOR 0.23 $452.72 $102.86
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.85 $452.72 $385.32
01-0330 FIERRERO OBRA NEGRA JOR 0.92 $452.72 $418.67
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.27 $452.72 $123.80
01-1080 MAESTRO DE OBRA JOR 0.10 $539.68 $51.40
Total de Mano De Obra $2,282.68
Clave: 030308
Unidad: M3
TRABE T-4 EN ESTRUCTURA DE SECCION = 0.20 X 0.40 X 30.20 MTS DE CONCRETO F'C=200 KG/CM2-3/4" CIMBRA COMUN
REFORZADA CON 110 KG/M3 DE ACERO FY'=4200 KG/CM2 QUE SE DESGLOSAN EN 3 VARILLAS DE 1/2" EN LECHO SUPERIOR; 2
VARILLAS DE 3/8" INTERMEDIAS; 1 VARILLA DE 1/2" EN VALLONETA Y 2 VARILLAS DE 1/2" EN LECHO INFERIOR; ESTRIBOS DE
ALAMBRON A CADA 10 Y 15 CMS; INCLUYE CIMBRA Y DESCIMBRA
Clave Descripción Unidad Cantidad Precio U. Total
Material
0082-05 ALAMBRE RECOCIDO NO. 18 KG 4.06 $17.70 $71.81
0086-00 VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) TON 0.30 $13,200.00 $3,917.89
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.15 $26.50 $3.95
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.43 $2,820.00 $1,208.31
0302-05 AGUA DE TOMA MUNICIPAL M3 0.31 $40.00 $12.51
0302-20 ARENA M3 0.56 $125.00 $69.55
0302-30 GRAVA M3 0.66 $183.33 $121.45
0950-05 DIESEL LT 0.36 $14.63 $5.19
1900-05 MADERA DE PINO DE 3A PT 0.86 $12.60 $10.82
1900-10 MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" PT 1.21 $14.76 $17.92
1900-15 MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" PT 2.27 $5.75 $13.06
1900-30 CHAFLAN DE MADERA DE PINO DE 3A. DE 1" M 0.78 $6.00 $4.69
1900-80 TRIPLAY DE PINO DE 16 MM 1 CARA HOJA 0.04 $366.45 $14.93
Total de Material $5,472.08
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.62 $344.59 $558.53
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.10 $344.59 $33.05
01-0070 AYUDANTE DE FIERRERO JOR 1.16 $344.59 $399.54
01-0310 OFICIAL ALBAÑIL JOR 0.23 $452.72 $102.86
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.10 $452.72 $43.42
01-0330 FIERRERO OBRA NEGRA JOR 1.16 $452.72 $524.92
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.22 $452.72 $100.23
01-1080 MAESTRO DE OBRA JOR 0.08 $539.68 $41.57
Total de Mano De Obra $1,834.26
Clave: 030303
Unidad: M3
TRABE T-5 EN ESTRUCTURA DE SECCION = 0.20 X 0.50 X 18.35 MTS DE CONCRETO F'C=200 KG/CM2-3/4" CIMBRA COMUN
REFORZADA CON 130 KG/M3 DE ACERO FY'=4200 KG/CM2 QUE SE DESGLOSAN EN 2 VARILLAS DE 3/4" EN LECHO SUPERIOR E
INFERIOR; 2 VARILLAS DE 3/8" INTERMEDIAS Y 3 VARILLAS DE 1/2" EN VALLONETA; ESTRIBOS DE 3/8" A CADA 10 Y 15 CMS;
INCLUYE CIMBRA Y DESCIMBRA
Clave Descripción Unidad Cantidad Precio U. Total
Material
0082-05 ALAMBRE RECOCIDO NO. 18 KG 4.04 $17.70 $71.42
0086-00 VARILLA FY=4200 KG/CM2 NO. 5 ( 5/8" ) TON 0.30 $13,200.00 $3,952.08
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.05 $26.50 $1.28
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.43 $2,820.00 $1,208.31
0302-05 AGUA DE TOMA MUNICIPAL M3 0.31 $40.00 $12.51
0302-20 ARENA M3 0.56 $125.00 $69.55
0302-30 GRAVA M3 0.66 $183.33 $121.45
0950-05 DIESEL LT 0.06 $14.63 $0.88
1900-05 MADERA DE PINO DE 3A PT 0.45 $12.60 $5.71
Total de Material $5,443.19
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.62 $344.59 $558.53
01-0070 AYUDANTE DE FIERRERO JOR 1.17 $344.59 $403.02
01-0310 OFICIAL ALBAÑIL JOR 0.23 $452.72 $102.86
01-0330 FIERRERO OBRA NEGRA JOR 1.17 $452.72 $529.48
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.21 $452.72 $96.35
01-1080 MAESTRO DE OBRA JOR 0.07 $539.68 $39.95
Total de Mano De Obra $1,760.33
Clave: 030307
Unidad: M3
TRABE T-6 EN ESTRUCTURA DE SECCION = 0.32 X 0.20 X 15.10 MTS DE CONCRETO F'C=200 KG/CM2-3/4" CIMBRA COMUN
REFORZADA CON 216.17 KG/M3 DE ACERO FY'=4200 KG/CM2 QUE SE DESGLOSAN EN 3 VARILLAS DE 1/2"" EN LECHO SUPERIOR
E INFERIOR;2 VARILLAS DE 1/2" EN VALLONETA; ESTRIBOS DE ALAMBRON A CADA 10 Y 15 CMS; INCLUYE CIMBRA Y DESCIMBRA
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $206.47 $8.26
00-0010 PEON JOR 1.62 $344.59 $558.53
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 2.16 $344.59 $744.87
01-0070 AYUDANTE DE FIERRERO JOR 0.91 $344.59 $312.98
01-0310 OFICIAL ALBAÑIL JOR 0.23 $452.72 $102.86
01-0320 CARPINTERO DE OBRA NEGRA JOR 2.16 $452.72 $978.60
01-0330 FIERRERO OBRA NEGRA JOR 0.91 $452.72 $411.19
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.07 $315.89 $21.88
01-1000 CABO JOR 0.40 $452.72 $182.38
01-1080 MAESTRO DE OBRA JOR 0.14 $539.68 $75.84
Total de Mano De Obra $3,397.39
Precio Unitario
$11,364.96
Clave: ICRF-017
Unidad: KG
REFUERZO CON VARILLA DEL No 4 EN DALAS PARA CONEXIÓN DE ESCALERA, COLUMNA Y SEGUNDO PISO, INC.: SOLO
SUMINISTRO, HABILITADO Y COLOCACION DE ACERO DE REFUERZO SEGÚN PLANO.
Mano De Obra
01-0070 AYUDANTE DE FIERRERO JOR 0.01 $344.59 $3.45
01-0330 FIERRERO OBRA NEGRA JOR 0.01 $452.72 $2.26
01-1000 CABO JOR 0.00 $452.72 $0.34
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.14
Total de Mano De Obra $6.19
Clave: ICRF-015
Unidad: M
DALA DE CERRAMIENTO EN PUERTAS Y VENTANAS CON UNA SECCION DE CONCRETO F'C = 150 KG/CM2 DE 15 X 20 CMS
ARMADA CON ARMEX 15X 20-4, INCLUYE: CIMBRA Y DESCIMBRA A DOS Y TRES CARAS.
Mano De Obra
00-0010 PEON JOR 0.09 $344.59 $29.63
01-0070 AYUDANTE DE FIERRERO JOR 0.01 $344.59 $2.41
01-0310 OFICIAL ALBAÑIL JOR 0.07 $452.72 $32.60
01-0330 FIERRERO OBRA NEGRA JOR 0.01 $452.72 $3.17
01-1000 CABO JOR 0.01 $452.72 $3.89
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.62
Total de Mano De Obra $73.32
Clave: 040126
Unidad: M
CADENA PARA RECIBIR LOSA DE VIGUETA Y BOVEDILLA, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 20 CM, CONCRETO
F'C=200 KG/CM2-3/4", REFORZADA CON 4 VARILLAS R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 30 CM
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $6.25 $0.25
00-0010 PEON JOR 0.10 $344.59 $35.01
01-0310 OFICIAL ALBAÑIL JOR 0.09 $452.72 $39.34
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.00 $315.89 $0.66
01-1000 CABO JOR 0.01 $452.72 $4.31
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.79
Total de Mano De Obra $81.36
Clave: ICRF-019
Unidad: M2
LOSA AUTOSUSTENTABLE A BASE DE VIGUETA Y BOVEDILLA EN CLAROS NO MAYORES A 3.00 MTS (VIGUETAS TIPO 14-85), INC.:
CAPA DE COMPRESION DE 5.00 CMS DE ESPESOR DE CONCRETO F'C = 200 KG/CM2 HECHO EN OBRA, MALLA ELECTROSOLDADA
PARA REFUERZO DE TEMPERATURA, CIMBRA
Clave Descripción Unidad Cantidad Precio U. Total
Material
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.00 $2,820.00 $8.21
0302-05 AGUA DE TOMA MUNICIPAL M3 0.08 $40.00 $3.10
0302-20 ARENA M3 0.00 $125.00 $0.59
0302-30 GRAVA M3 0.01 $183.33 $1.01
1300-15 VIGUETA 15/15/75 M 1.37 $110.00 $150.40
1301-55 BOVEDILLA PRETENSA 16/70 PZA 5.68 $20.00 $113.51
1302-00 MALLA ELECTROSOLDADA PRETENSA 6 X 6 10/10 M2 1.13 $17.10 $19.32
1900-05 MADERA DE PINO DE 3A PT 1.73 $12.60 $21.75
Total de Material $317.89
Mano De Obra
00-0010 PEON JOR 0.56 $344.59 $192.01
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.04 $344.59 $12.06
01-0310 OFICIAL ALBAÑIL JOR 0.11 $452.72 $50.16
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.04 $452.72 $15.85
01-1000 CABO JOR 0.04 $452.72 $16.71
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $6.97
Total de Mano De Obra $293.76
Clave: ICRF-020
Unidad: M2
CHAROLA DE CONCRETO DE 10CMS DE ESPESOR DE CONCRETO F'C=200 KG/CM2 ARMADA CON VRS DEL No 3 A CADA 20CMS
EN AMBAS DIRECCIONES, INC.: CIMBRA Y DESCIMBRA.
Mano De Obra
00-0010 PEON JOR 0.06 $344.59 $20.31
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.16 $344.59 $55.41
01-0070 AYUDANTE DE FIERRERO JOR 0.00 $344.59 $0.10
01-0310 OFICIAL ALBAÑIL JOR 0.01 $452.72 $2.91
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.16 $452.72 $72.80
01-0330 FIERRERO OBRA NEGRA JOR 0.00 $452.72 $0.07
01-1000 CABO JOR 0.02 $452.72 $8.77
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.66
Total de Mano De Obra $164.03
Clave: ICRF-ESC
Unidad: M2
RAMPA PARA ESCALERA DE CONCRETO F'C=200 KG/CM2 DE 10CMS DE ESPESOR ARMADA CON VARILLA DEL No 3 A CADA
20CMS EN AMBAS DIRECCIONES, INCLUYE CIMBRA Y DESCIMBRA.
Material
0082-00 ALAMBRE RECOCIDO NO. 16 KG 1.40 $17.70 $24.85
0084-00 VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) TON 0.02 $13,200.00 $277.99
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.02 $2,820.00 $68.81
0302-05 AGUA DE TOMA MUNICIPAL M3 0.65 $40.00 $25.98
0302-20 ARENA M3 0.04 $125.00 $4.95
0302-30 GRAVA M3 0.05 $183.33 $8.47
Total de Material $411.05
Mano De Obra
00-0010 PEON JOR 0.07 $344.59 $24.29
01-0070 AYUDANTE DE FIERRERO JOR 0.00 $344.59 $0.32
01-0310 OFICIAL ALBAÑIL JOR 0.01 $452.72 $2.99
01-0330 FIERRERO OBRA NEGRA JOR 0.00 $452.72 $0.21
01-1000 CABO JOR 0.00 $452.72 $1.77
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.74
Total de Mano De Obra $30.32
Clave: ICRF-FES
Unidad: PZA
FORJADO DE ESCALONES A BASE DE TABIQUE ROJO RECOCIDO Y MORTERO CON 17 CMS DE PERALTE Y 30CMS DE HUELLA.
Mano De Obra
00-0010 PEON JOR 0.04 $344.59 $14.47
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.04
01-0310 OFICIAL ALBAÑIL JOR 0.04 $452.72 $19.01
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.06
01-1000 CABO JOR 0.00 $452.72 $1.91
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.79
Total de Mano De Obra $36.28
Clave: 040805
Unidad: M2
MURO DE TABIQUE DE BARRO ROJO RECOCIDO DE 7 X 14 X 28 CM DE ESPESOR, ASENTADO CON MORTERO CEMENTO-
CALHIDRA-ARENA 1:1:6 JUNTAS DE 1.5 CM, ACABADO COMUN
Material
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.00 $26.50 $0.04
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.03 $2,820.00 $70.78
0300-60 CALHIDRA EN SACO TON 0.01 $1,420.00 $17.74
0302-05 AGUA DE TOMA MUNICIPAL M3 0.05 $40.00 $1.92
0302-20 ARENA M3 0.11 $125.00 $13.19
1900-05 MADERA DE PINO DE 3A PT 0.05 $12.60 $0.59
3150-03 TABIQUE COMUN DE BARRO ROJO RECOCIDO DE 6 X 12 X 24 CM MIL 0.05 $2,850.00 $151.05
Mano De Obra
00-0010 PEON JOR 0.17 $344.59 $57.41
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.12
01-0310 OFICIAL ALBAÑIL JOR 0.17 $452.72 $75.42
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.16
01-1000 CABO JOR 0.02 $452.72 $7.56
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.15
Total de Mano De Obra $143.82
Clave: 040497
Unidad: M
CASTILLO DE CONCRETO SECCION= 15 X 20 CM, CONCRETO F'C=150 KG/CM2-3/4", CIMBRA 2 CARAS, REFORZADO CON ARMEX
DE 15 X 20 - 4
Mano De Obra
00-0010 PEON JOR 0.11 $344.59 $38.28
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.13
01-0310 OFICIAL ALBAÑIL JOR 0.11 $452.72 $50.30
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.18
01-1000 CABO JOR 0.01 $452.72 $5.05
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $2.10
Total de Mano De Obra $96.04
Clave: ICRF-025
Unidad: M2
RELLENO EN AZOTEA PARA DAR PENDIENTE A LA LOSA PARA SU IMPERMEABILIZACION A BASE DE TEPEZIL-CAL EN PROP. 1:8
CON UN ESPESOR PROMEDIO DE 10.00 CMS, INC.: MAESTRAS, ACARREOS Y ELEVACION DE MATERIAL.
Mano De Obra
00-0010 PEON JOR 0.05 $344.59 $17.23
01-0310 OFICIAL ALBAÑIL JOR 0.01 $452.72 $4.53
01-1000 CABO JOR 0.00 $452.72 $1.36
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.57
Total de Mano De Obra $23.69
Clave: ICRF-026
Unidad: M2
ENTORTADO EN AZOTEA DE 3.00 CMS DE ESPESOR PARA RECIBIR IMPERMEABILIZACION A BASE DE MORTERO CEMENTO-
ARENA 1:5 CON UN ESPESOR PROMEDIO DE 5.00 CMS, INC.: MAESTRAS, ACARREOS Y ELEVACION DE MATERIAL.
Mano De Obra
00-0010 PEON JOR 0.05 $344.59 $16.99
01-0310 OFICIAL ALBAÑIL JOR 0.05 $452.72 $22.32
01-1000 CABO JOR 0.00 $452.72 $2.23
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.93
Total de Mano De Obra $42.47
Clave: ICRF-027
Unidad: M
CHAFLAN 10X10CMS CON MORTERO DE CEMENTO-ARENA EN PROPORCION 1:5.
Mano De Obra
00-0010 PEON JOR 0.03 $344.59 $8.79
01-0310 OFICIAL ALBAÑIL JOR 0.03 $452.72 $11.54
01-1000 CABO JOR 0.00 $452.72 $1.15
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.48
Total de Mano De Obra $21.96
Clave: ICRF-028
Unidad: M
SUMINISTRO Y COLOCACION DE BAJADAS DE AGUA PLUVIAL A BASE DE TUBO P.V.C. DE 4".
Clave: ICRF-029
Unidad: M2
IMPERMEABILIZACION DE AZOTEA A BASE DE MEMBRANA , INC.: APLICACIÓN DE PRIMARIO IMPERPRIM SL, SELLO DE GRIETAS Y
FISURAS CON CEMENTO PLASTICO BITUPLASTIC N Y APLICACIÓN POR TERMOFUSION DE MANTO FLEXOPLY SBS ROJO ORO.
Mano De Obra
00-0010 PEON JOR 0.06 $344.59 $19.71
01-0310 OFICIAL ALBAÑIL JOR 0.06 $452.72 $25.90
01-1000 CABO JOR 0.01 $452.72 $2.59
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.08
Total de Mano De Obra $49.28
Clave: ICRF-030
Unidad: M2
REPELLADO EN MUROS INTERIORES ZONAS HUMEDAS PARA RECIBIR AZULEJO EN COCINA, BAÑOS Y PATIO DE SERVICIO CON
MORTERO DE CEMENTO-ARENA PROP.: 1:5 A PLOMO Y REGLA, INC.: ANDAMIOS.
Mano De Obra
00-0010 PEON JOR 0.11 $344.59 $38.19
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.09
01-0310 OFICIAL ALBAÑIL JOR 0.08 $452.72 $37.73
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.12
01-1000 CABO JOR 0.01 $452.72 $4.40
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.84
Total de Mano De Obra $82.37
Clave: ICRF-031
Unidad: M2
REPELLADO EN MUROS EXTERIORES CON MORTERO DE CEMENTO-ARENA PROP. 1:5 A PLOMO Y REGLA PARA RECIBIR
AZULEJO; INCLUYE TODO LO NECESARIO PARA SU CORRECTA EJECUCION.
Mano De Obra
00-0010 PEON JOR 0.11 $344.59 $38.19
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.09
01-0310 OFICIAL ALBAÑIL JOR 0.08 $452.72 $37.73
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.12
01-1000 CABO JOR 0.01 $452.72 $4.40
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.84
Total de Mano De Obra $82.37
Mano De Obra
00-0010 PEON JOR 0.10 $344.59 $34.46
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.07
01-0310 OFICIAL ALBAÑIL JOR 0.10 $452.72 $45.27
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.09
01-1000 CABO JOR 0.01 $452.72 $4.54
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.89
Total de Mano De Obra $86.32
Clave: 041767
Unidad: M2
APLANADO FINO EN PLAFONES A REGLA Y NIVEL CON MORTERO CEMENTO-ARENA 1:3 ESPESOR PROMEDIO = 2.5 CM INCLUYE
REPELLADO PULIDO CON LLANA METALICA
Mano De Obra
00-0010 PEON JOR 0.11 $344.59 $38.28
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.08
01-0310 OFICIAL ALBAÑIL JOR 0.11 $452.72 $50.30
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.10
01-1000 CABO JOR 0.01 $452.72 $5.04
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $2.10
Total de Mano De Obra $95.90
Clave: 041812
Unidad: M
EMBOQUILLADO EN APLANADO PERFILADO UNA ARISTA CON MORTERO HIDRAULICO-ARENA 1:6 PULIDO CON LLANA METALICA
Mano De Obra
00-0010 PEON JOR 0.08 $344.59 $26.50
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.06
01-0310 OFICIAL ALBAÑIL JOR 0.08 $452.72 $34.81
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.07
01-1000 CABO JOR 0.01 $452.72 $3.49
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.46
Total de Mano De Obra $66.39
Clave: ICRF-036
Unidad: M
FORJADO DE GOTERO DE 1" CON MORTERO DE CEMENTO-ARENA.
Mano De Obra
00-0010 PEON JOR 0.05 $344.59 $16.99
01-0310 OFICIAL ALBAÑIL JOR 0.05 $452.72 $22.32
01-1000 CABO JOR 0.00 $452.72 $2.23
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.93
Total de Mano De Obra $42.47
Clave: ICRF-038
Unidad: M2
FIRME DE CONCRETO F'C = 100 KG/CM2 DE 8 CMS DE ESPESOR PARA RECIBIR LOSETA, INC.: TERRACEO DE LA SUPERFICIE.
Mano De Obra
00-0010 PEON JOR 0.10 $344.59 $34.18
01-0310 OFICIAL ALBAÑIL JOR 0.06 $452.72 $27.93
01-1000 CABO JOR 0.01 $452.72 $3.64
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.52
Total de Mano De Obra $67.27
Mano De Obra
00-0010 PEON JOR 0.10 $344.59 $36.15
01-0310 OFICIAL ALBAÑIL JOR 0.06 $452.72 $27.89
01-1000 CABO JOR 0.01 $452.72 $3.77
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.57
Total de Mano De Obra $69.38
Clave: 041415
Unidad: M2
PISO DE CONCRETO SIMPLE DE 8 CM DE ESPESOR CONCRETO HECHO EN OBRA F'C=150 KG/CM2, ACABADO DESLAVADO CON
GRANZON Y/O GRANITO
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $23.83 $0.95
00-0010 PEON JOR 0.17 $344.59 $59.80
01-0310 OFICIAL ALBAÑIL JOR 0.12 $452.72 $53.24
01-0780 OPERADOR DE REVOLVEDORA DE 1 SACO JOR 0.01 $315.89 $2.52
01-1000 CABO JOR 0.01 $452.72 $6.77
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $2.80
Total de Mano De Obra $126.08
Clave: ICRF-041
Unidad: PZA
ESCALONES DE ACCESO A BASE DE CONCRETO F'C=150KG/CM2 DE 30CMS DE ANCHO Y 90.00 CMS DE LARGO, y 15CMS DE
ALTO, INC.: FORJADO DE NARIZ Y MARTELINADO.
Mano De Obra
00-0010 PEON JOR 0.97 $344.59 $334.81
01-0310 OFICIAL ALBAÑIL JOR 0.01 $452.72 $3.09
01-1000 CABO JOR 0.05 $452.72 $22.15
01-1080 MAESTRO DE OBRA JOR 0.02 $539.68 $9.24
Total de Mano De Obra $369.29
Clave: ICRF-044
Unidad: PZA
HUELLAS DE CONCRETO SIMPLE F'C = 150 KG/CM2 DE 10 CMS DE ESPESOR Y UNA SECCION DE 1.05 X 0.85 CMS ACABADDO
ESCOBILLADO Y/O RAYADO, INC.: CIMBRA Y DESCIMBRA.
Material
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.16 $26.50 $4.34
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.03 $2,820.00 $72.28
0302-05 AGUA DE TOMA MUNICIPAL M3 0.07 $40.00 $2.69
0302-20 ARENA M3 0.04 $125.00 $5.62
0302-30 GRAVA M3 0.05 $183.33 $9.61
0950-05 DIESEL LT 0.20 $14.63 $2.98
1900-05 MADERA DE PINO DE 3A PT 1.54 $12.60 $19.42
Total de Material $116.94
Mano De Obra
00-0010 PEON JOR 0.08 $344.59 $26.03
01-0310 OFICIAL ALBAÑIL JOR 0.04 $452.72 $20.08
01-1000 CABO JOR 0.01 $452.72 $2.71
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.13
Total de Mano De Obra $49.95
Clave: ICRF-046
Unidad: M2
PISO PORCELANATO CASTEL MODELO SILK BLANCO 60 X 60 CMS ASENTADA CON ADHESIVO MARCA PERDURA, INCLUYE:
CORTES Y DESPERDICIOS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION.
Material
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.01 $2,820.00 $26.90
0300-40 CEMENTO BLANCO EN SACO TON 0.00 $4,119.80 $6.10
0300-83 CEMENTO CREST BLANCO BTO. 0.24 $98.00 $23.60
0302-05 AGUA DE TOMA MUNICIPAL M3 0.01 $40.00 $0.34
0302-20 ARENA M3 0.03 $125.00 $3.32
1502-75 DISCO DE CARBURO DE 14" MODELO 535 PZA 0.01 $90.00 $1.19
1850-80 LOSETA 1.5 X 30 X 30 CM M2 1.05 $285.00 $299.25
Total de Material $360.70
Mano De Obra
00-0010 PEON JOR 0.16 $344.59 $55.24
01-0310 OFICIAL ALBAÑIL JOR 0.16 $452.72 $72.57
01-1000 CABO JOR 0.02 $452.72 $7.26
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.03
Total de Mano De Obra $138.10
Costo Renta de Equipo
03-4270 PULIDORA Y CORTADORA DE PISO Hora 0.10 $25.02 $2.56
Total de Costo Renta de Equipo $2.56
Clave: ICRF-048
Unidad: M
SUMINISTRO Y COLOCACION DE ZOCLO DE 10.00 CMS DE ANCHO DE PORCELANATO CASTEL MODELO SILK BLANCO ASENTADA
CON ADHESIVO MARCA PERDURA, INCLUYE: CORTES Y DESPERDICIOS Y TODO LO NECESARIO PARA SU CORRECTA
EJECUCION.
Clave Descripción Unidad Cantidad Precio U. Total
Material
1852-35 ZOCLO DE 7 CM M 1.05 $63.53 $66.71
Total de Material $66.71
Mano De Obra
01-0265 AYUDANTE CLASE A JOR 0.02 $344.59 $7.21
01-0740 COLOCADOR JOR 0.02 $452.72 $9.47
01-1000 CABO JOR 0.00 $452.72 $0.95
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.39
Total de Mano De Obra $18.02
Clave: ICRF-049
Unidad: M2
PISO ANTIDERRAPANTE ASENTADA CON MORTERO DE CEMENTO-ARENA PROP.: 1:6 Y/O CEMENTO CREST, INC.: CORTES Y
DESPERDICIOS.
Mano De Obra
00-0010 PEON JOR 0.16 $344.59 $55.24
01-0310 OFICIAL ALBAÑIL JOR 0.16 $452.72 $72.57
01-1000 CABO JOR 0.02 $452.72 $7.26
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.03
Total de Mano De Obra $138.10
Clave: ICRF-050
Unidad: M2
AZULEJO EN AREAS HUMEDAS (BAÑO) ASENTADO CON CEMENTO CREST, INC.: CORTES Y DESPERDICIOS.
Mano De Obra
00-0010 PEON JOR 0.16 $344.59 $55.24
01-0310 OFICIAL ALBAÑIL JOR 0.16 $452.72 $72.57
01-1000 CABO JOR 0.02 $452.72 $7.26
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.03
Total de Mano De Obra $138.10
Mano De Obra
00-0010 PEON JOR 0.00 $344.59 $1.03
01-0310 OFICIAL ALBAÑIL JOR 0.00 $452.72 $1.36
01-1000 CABO JOR 0.00 $452.72 $0.14
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.06
Total de Mano De Obra $2.59
Clave: ICRF-053
Unidad: M
FABRICACION DE SARDINEL EN BAÑO, INC.: FORJADO DE SARDINEL CON CONCRETO F'C=150KG/CM2, RECUBRIMENTO CON
AZULEJO Y TIRATRIM.
Mano De Obra
00-0010 PEON JOR 0.10 $344.59 $34.95
01-0310 OFICIAL ALBAÑIL JOR 0.08 $452.72 $37.73
01-1000 CABO JOR 0.01 $452.72 $4.18
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $1.74
Total de Mano De Obra $78.60
Clave: ICRF-054
Unidad: M2
PINTURA VINILICA EN MUROS Y PLAFONES INTERIORES Y EXTERIORES INC.: PREPARACION DE LA SUPERFICIE, UNA MANO DE
SELLADOR VINILICA Y DOS MANOS DE PINTURA.
Mano De Obra
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.06
01-0100 AYUDANTE DE PINTOR JOR 0.02 $344.59 $8.06
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.07
01-0360 PINTOR JOR 0.02 $452.72 $10.59
01-1000 CABO JOR 0.00 $452.72 $1.07
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.44
Total de Mano De Obra $20.29
Mano De Obra
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.06
01-0100 AYUDANTE DE PINTOR JOR 0.02 $344.59 $8.06
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.07
01-0360 PINTOR JOR 0.02 $452.72 $10.59
01-1000 CABO JOR 0.00 $452.72 $1.07
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.44
Total de Mano De Obra $20.29
Clave: ICRF-064
Unidad: M
SUMINISTRO Y TENDIDO DE TUBERIA DE PVC SANITARIO 6", INCLUYE: EXCAVACION, RELLENOS, ACARREOS, MATERIAL,
PEGAMENTO, PASOS POR CIMENTACION O PREPARACIONES, HERRAMIENTA, MANO DE OBRA, CONEXIONES Y DESPERDICIOS.
Material
0302-20 ARENA M3 0.03 $125.00 $3.75
3025-68 TUBO P.V.C. SANITARIO LISO DE 150 MM TUBO 0.18 $361.00 $63.18
IGRFPB-02 TUBO DE COBRE TIPO "L" 13 MM DE 3mts pza 0.13 $185.00 $24.42
Total de Material $91.35
Mano De Obra
01-0400 PLOMERO JOR 0.20 $343.89 $68.78
Total de Mano De Obra $68.78
Clave: ICRF-065
Unidad: PZA
REGISTRO DE 40 x 60 x 100 CMS MEDIDA INTERIOR CON TABIQUE ROJO RECOCIDO DE 14 CM. DE ESPESOR, JUNTEADO CON
MORTERO CEMENTO ARENA EN PROPORCION 1:5. PLANTILLA DE CONCRETO F'C = 150 KG/CM2. DE 10 CM. DE ESPESOR,
ACABADO INTERIOR APLANADO PULIDO MARCO; CONTRAMARCO Y TAPA
Clave Descripción Unidad Cantidad Precio U. Total
Material
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 0.01 $26.50 $0.15
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.08 $2,820.00 $234.34
0300-60 CALHIDRA EN SACO TON 0.02 $1,420.00 $28.14
0302-05 AGUA DE TOMA MUNICIPAL M3 0.36 $40.00 $14.34
0302-20 ARENA M3 0.25 $125.00 $30.85
0302-30 GRAVA M3 0.09 $183.33 $17.08
1550-05 MARCO Y CONTRAMARCO PARA TAPA DE REGISTRO PZA 1.00 $345.00 $345.00
1900-05 MADERA DE PINO DE 3A PT 0.18 $12.60 $2.29
3150-03 TABIQUE COMUN DE BARRO ROJO RECOCIDO DE 6 X 12 X 24 CM MIL 0.10 $2,850.00 $296.40
Mano De Obra
00-0010 PEON JOR 0.93 $344.59 $319.42
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.00 $344.59 $0.46
01-0310 OFICIAL ALBAÑIL JOR 0.40 $452.72 $182.99
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.00 $452.72 $0.60
01-1000 CABO JOR 0.07 $452.72 $30.19
01-1080 MAESTRO DE OBRA JOR 0.02 $539.68 $12.60
Total de Mano De Obra $546.26
Clave: 080102
Unidad: SALIDA
SALIDA HIDRÁULICA, SANITARIA PARA W.C. A BASE DE TUBERÍA DE TUBOPLUS Y PVC SANITARIO, EL PRECIO INCLUYE:
MATERIALES, CONEXIONES, MANO DE OBRA Y TODO LO NECESARIO PARA LA CORRECTA EJECUCIÓN DEL P.U.O.T.
Mano De Obra
01-1000 CABO JOR 0.10 $452.72 $45.27
MOCA-016 Plomero jor 1.00 $441.86 $441.86
MOCA-038 Ayudante plomero jor 1.00 $277.24 $277.24
Total de Mano De Obra $764.37
Herramienta
FACHEME Herramienta menor (%)mo 0.03 $764.37 $22.93
Total de Herramienta $22.93
Clave: 080101
Unidad: SALIDA
SALIDA HIDRÁULICA, SANITARIA PARA LAVABO A BASE DE TUBERÍA TUBOPLUS Y PVC SANITARIO, EL PRECIO INCLUYE:
MATERIALES, CONEXIONES, MANO DE OBRA Y TODO LO NECESARIO PARA LA CORRECTA EJECUCIÓN DEL P.U.O.T.
Mano De Obra
01-1000 CABO JOR 0.10 $452.72 $45.27
MOCA-016 Plomero jor 1.00 $441.86 $441.86
MOCA-038 Ayudante plomero jor 1.00 $277.24 $277.24
Total de Mano De Obra $764.37
Herramienta
FACHEME Herramienta menor (%)mo 0.03 $764.37 $22.93
Total de Herramienta $22.93
Clave: 080110
Unidad: SALIDA
SALIDA SANITARIA PARA COLADERA DE ASEO A BASE PVC SANITARIO, EL PRECIO INCLUYE: COLADERA, MATERIALES,
CONEXIONES, MANO DE OBRA Y TODO LO NECESARIO PARA LA CORRECTA EJECUCIÓN DEL P.U.O.T.
Mano De Obra
01-1000 CABO JOR 0.04 $452.72 $19.92
MOCA-016 Plomero jor 0.44 $441.86 $194.42
MOCA-038 Ayudante plomero jor 0.44 $277.24 $121.99
Total de Mano De Obra $336.33
Herramienta
FACHEME Herramienta menor (%)mo 0.03 $336.33 $10.09
Total de Herramienta $10.09
Clave: 091208
Unidad: PIEZA
SUMINISTRO Y COLOCACION DE TINACO MARCA ROTOPLAS DE 1100 LTS INCLUYE: FLOTADOR, VALVULA, TAPA , ELEVACION Y
MANO DE OBRA DE COLOCACION
Mano De Obra
01-1000 CABO JOR 0.10 $452.72 $45.27
MOCA-016 Plomero jor 1.00 $441.86 $441.86
MOCA-038 Ayudante plomero jor 1.00 $277.24 $277.24
Total de Mano De Obra $764.37
Herramienta
FACHEME Herramienta menor (%)mo 0.03 $764.37 $22.93
Total de Herramienta $22.93
Clave: HID15
Unidad: LOTE
ALIMENTACION DE TOMA MUNICIPAL A CISTERNA, INCLUYE: TUBERIA DE ALIMENTACION DE RED EXISTENTE A CISTERNA,
EXCAVACION, TENDIDO DE TUBERIA; INCLUYE RANURADO, COLOCACION DE TUBERIA Y TODO LO NECESARIO PARA SU
CORRECTO FUNCIONAMIENTO.
Clave Descripción Unidad Cantidad Precio U. Total
Material
CMC-00079 Tubo tuboplus de 1/2" (13mm) TUBO 8.00 $50.93 $407.44
M0040 AGUA DE TOMA. M3 1.44 $35.00 $50.40
MHPV-390 Codo de 90° tuboplus de 13 mm, pieza 6.00 $22.63 $135.78
MHPV-537 Conector tuboplus a rosca interior de 13 mm pieza 1.00 $19.33 $19.33
Total de Material $612.95
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $55.90 $2.24
01-0150 AYUDANTE DE PLOMERO JOR 0.09 $277.24 $24.95
01-0400 PLOMERO JOR 0.09 $343.89 $30.95
01-1000 CABO JOR 0.19 $452.72 $86.70
MOCA-001 Peón jor 3.83 $344.59 $1,319.92
Total de Mano De Obra $1,464.76
Herramienta
FACHEME Herramienta menor (%)mo 0.04 $1,406.62 $56.26
Total de Herramienta $56.26
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $614.92 $24.60
01-0150 AYUDANTE DE PLOMERO JOR 0.99 $277.24 $274.47
01-0400 PLOMERO JOR 0.99 $343.89 $340.45
Total de Mano De Obra $639.52
Clave: 980955
Unidad: PZA
SUMINISTRO Y COLOCACIÓN DE LAVABOS MCA.CATO MODELO JAZMIN BLANCO, ACCESORIOS, HERRAJES, LLAVE ANGULAR, Y
TODO LO NECESARIO PARA SU BUEN FUNCIONAMIENTO.
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $223.61 $8.94
01-0150 AYUDANTE DE PLOMERO JOR 0.36 $277.24 $99.81
01-0400 PLOMERO JOR 0.36 $343.89 $123.80
Total de Mano De Obra $232.55
Clave: 981028
Unidad: PZA
SUMINISTRO Y COLOCACION DE WC Y/O MINGITORIO MARCA CATO MODELO JAZMIN ALARGADO BLANCO, INCLUYE: ASIENTO,
ACCESORIOS, HERRAJES, LLAVE ANGULAR, ASIENTO Y TODO LO NECESARIO PARA SU BUEN FUNCIONAMIENTO.
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $223.61 $8.94
01-0150 AYUDANTE DE PLOMERO JOR 0.36 $277.24 $99.81
01-0400 PLOMERO JOR 0.36 $343.89 $123.80
Total de Mano De Obra $232.55
Clave: ACC035
Unidad: PZA
SUMINISTRO Y COLOCACION DE MEZCLADORA PARA LAVABO MARCA DICA ECOLOGICA
Material
11-0472 MEZCLADORA PARA LAVABO. JGO 1.00 $244.14 $244.14
Total de Material $244.14
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $139.76 $5.59
01-0150 AYUDANTE DE PLOMERO JOR 0.23 $277.24 $62.38
01-0400 PLOMERO JOR 0.23 $343.89 $77.38
Total de Mano De Obra $145.35
Clave: ACC063
Unidad: PZA
SUMINISTRO Y COLOCACION DE LLAVE DE NARIZ PARA TARJA, INCLUYE: TODO LO NECESARIO PARA SU BUEN
FUNCIONAMIENTO.
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $83.86 $3.35
01-0150 AYUDANTE DE PLOMERO JOR 0.14 $277.24 $37.43
01-0400 PLOMERO JOR 0.14 $343.89 $46.43
Total de Mano De Obra $87.21
Clave: ICRF-066
Unidad: LOTE
INSTALACION DE ACCESORIOS PARA BAÑO MARCA DICA; INCLUYE PARA 6 MUEBLES DE BAÑO; SUJECCION, PEGADO Y TODO
LO NECESARIO PARA SU CORRECTO FUNCIONAMIENTO
Mano De Obra
01-0380 PLOMERO JOR 1.00 $452.72 $452.72
01-0390 AYUDANTE DE PLOMERO JOR 1.00 $344.59 $344.59
01-1000 CABO JOR 0.10 $452.72 $45.27
01-1080 MAESTRO DE OBRA JOR 0.04 $539.68 $18.89
Total de Mano De Obra $861.47
Costo directo $6,561.47
Indirectos de oficina 8.00 % $524.92
Indirectos de campo 0.00 % $0.00
Financiamiento 0.00 % $0.00
Utilidad 8.00 % $566.91
Cargos adicionales 0.00 % $0.00
Otros porcentajes 0.00 % $0.00
Total sobrecostos $1,091.83
Clave: ELEC009
Unidad: PZA
SUMINISTRO Y COLOCACION DE CENTRO DE CARGA SD QOD-8, 8 CIRCUITOS.
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $444.74 $17.79
01-0140 AYUDANTE DE ELECTRICISTA JOR 0.67 $277.24 $184.83
01-0390 AYUDANTE DE PLOMERO JOR 0.67 $344.59 $229.73
01-1000 CABO JOR 0.07 $452.72 $30.18
Total de Mano De Obra $462.53
Clave: INEL243
Unidad: SAL
SALIDA ELECTRICA DE ILUMINACION EN PLAFON, EL PRECIO INCLUYE: CABLE THW CAL. 12,POLIDUCTO DE 13 MM,APAGADOR
SENCILLO Y PLACA COLOR BLANCO O NARFIL, CHALUPA, CAJA DE REGISTRO DE 1/2", CONO BLANCO SIN CRISTAL, MANO DE
OBRA Y TODOS LOS MATERIALES PARA LA CORRECTA EJECUCION DEL P.U.O.T.
Clave Descripción Unidad Cantidad Precio U. Total
Material
E1BIU010 Cable thw antillama cal. 12 105 oc m 16.00 $6.20 $99.20
E1DIU005 Cable de cobre desnudo cal 14 mca. Condumex m 18.00 $6.20 $111.60
E3APG035 Poliducto de 13 mm, marca Poliflex m 6.00 $3.60 $21.60
E9KCE004 Bote para spot galvanizado, marca Acuario pza 1.00 $11.00 $11.00
E9KCE015 Caja chalupa galvanizada 1/2, marca Impulsora y Troquelados. pza 1.00 $2.55 $2.55
E9KCE096 Sobre tapa sencilla galv. de 19mm para caja de 4", marca Impulsora y pza 1.00 $3.84 $3.84
Troquelados
EDCIU020 Apagador Evolucion senc.porcelana abs negro 211 pza 1.00 $47.20 $47.20
EDPCE005 Placa linea Evolucion resina marfil 1 unidad pza 1.00 $61.67 $61.67
Total de Material $358.66
Mano De Obra
01-1000 CABO JOR 0.04 $452.72 $18.11
1AEBO Electricista en baja tensión Jor 0.40 $441.86 $176.74
1AEBY Ayudante electricista en baja tensión Jor 0.40 $277.24 $110.90
Total de Mano De Obra $305.75
Herramienta
2HER Herramienta menor (%)mo 0.00 $305.75 $0.06
Total de Herramienta $0.06
Clave: EL-ARB
Unidad: SAL
SUMINISTRO Y COLOCACION DE ARBOTANTE, INCLUYE: CABLE THW CAL. 12,POLIDUCTO DE 13 MM,APAGADOR SENCILLO Y
PLACA COLOR BLANCO O NARFIL, CHALUPA, MANO DE OBRA Y TODOS LOS MATERIALES PARA LA CORRECTA EJECUCION
Material
1043-20 CABLE ( ECONOMICO ) TW CALIBRE 12 M 8.80 $6.20 $54.56
1043-24 CABLE ( ECONOMICO ) TW CALIBRE 14 M 8.80 $4.20 $36.96
1044-24 CABLE ( NORMAL ) THW 600 VOLTS 90 GRADOS C CALIBRE 14 M 8.80 $4.20 $36.96
ELARB SUMINISTRO Y COLOCACION DE ARBOTANTE MCA. TECNOLITE SAL 1.30 $368.83 $479.48
VASO YD 1500 EP/M, INCLUYE: MANO DE OBRA Y TODOS LOS
MATERIALES PARA SU CORRECTO FUNCIONAMIENTO.
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $71.51 $2.86
01-0140 AYUDANTE DE ELECTRICISTA JOR 0.11 $277.24 $29.72
01-0390 AYUDANTE DE PLOMERO JOR 0.11 $344.59 $36.94
01-1000 CABO JOR 0.01 $452.72 $4.85
Total de Mano De Obra $74.37
Clave: INEL233
Unidad: SAL
SALIDA PARA CONTACTO DOBLE POLARIZADO, CABLE THW CAL. 12, POLIDUCTO DE 13 MM, MARCA POLIFLEX CONTACTO
EVOLUCION MARFIL DOBLE, CHALUPA, MANO DE OBRA Y TODOS LOS MATERIALES PARA LA CORRECTA EJECUCION DEL
P.U.O.T.
Clave Descripción Unidad Cantidad Precio U. Total
Material
D2AIU035 Cinta aislante de vinilo 19mmx18.0mts. pza 0.05 $4.56 $0.23
E1BIU040 Cable THW-LS cal. 10, marca Iusa. m 16.00 $12.43 $198.88
E1DIU005 Cable de cobre desnudo cal 14 mca. Condumex m 8.00 $6.20 $49.60
E3APG035 Poliducto de 13 mm, marca Poliflex m 6.00 $3.60 $21.60
E9KCE015 Caja chalupa galvanizada 1/2, marca Impulsora y Troquelados. pza 1.00 $2.55 $2.55
E9KCE096 Sobre tapa sencilla galv. de 19mm para caja de 4", marca Impulsora y pza 1.00 $3.84 $3.84
Troquelados
EDECE010 Contacto duplex aterrizado color marfil cat. 198, marca Royer pza 1.00 $33.27 $33.27
EDPCE005 Placa linea Evolucion resina marfil 1 unidad pza 1.00 $61.67 $61.67
Total de Material $371.64
Mano De Obra
01-1000 CABO JOR 0.04 $452.72 $16.65
1AEBO Electricista en baja tensión Jor 0.37 $441.86 $162.45
1AEBY Ayudante electricista en baja tensión Jor 0.37 $277.24 $101.93
Total de Mano De Obra $281.03
Herramienta
2HER Herramienta menor (%)mo 0.00 $281.03 $0.06
Total de Herramienta $0.06
Clave: EL-LUM-S
Unidad: SAL
SUMINISTRO Y COLOCACION DE LUMINARIA ASCENDENTE PARA EMPOTRAR EN PISO; INCLUYE, CABLE THW CAL. 12,
POLIDUCTO DE 13 MM, MARCA POLIFLEX , CHALUPA, MANO DE OBRA Y TODOS LOS MATERIALES PARA LA CORRECTA
EJECUCION
Clave Descripción Unidad Cantidad Precio U. Total
Material
ELLUMS-M SUMINISTRO Y COLOCACION DE LUMINARIA PARA SOBREPONER SAL 1.20 $739.64 $887.57
POLICARBNATO M. EST-228, INCLUYE: MANO DE OBRA Y TODOS
LOS MATERIALES PARA SU CORRECTO FUNCIONAMIENTO
Mano De Obra
01-1000 CABO JOR 0.05 $452.72 $22.64
1AEBO Electricista en baja tensión Jor 0.50 $441.86 $220.93
1AEBY Ayudante electricista en baja tensión Jor 0.50 $277.24 $138.62
Total de Mano De Obra $382.19
Herramienta
2HER Herramienta menor (%)mo 0.00 $382.19 $0.08
Total de Herramienta $0.08
Clave: ELECLUM
Unidad: SAL
SUMINISTRO Y COLOCACION TIMBRE O ZUMBADOR
Mano De Obra
01-1000 CABO JOR 0.03 $452.72 $13.58
1AEBO Electricista en baja tensión Jor 0.30 $441.86 $132.56
1AEBY Ayudante electricista en baja tensión Jor 0.30 $277.24 $83.17
Total de Mano De Obra $229.31
Herramienta
2HER Herramienta menor (%)mo 0.00 $229.31 $0.05
Total de Herramienta $0.05
Clave: ELEC001
Unidad: LOTE
ALIMENTACION DE REGISTRO ELECTRICO EXISTENTE A CENTRO DE CARGA CON POLIDUCTO CONDUIT Y CABLE DEL No. 8,
INCLUYE EXCAVACION COLOCACION DE DUCTO, RELLENO, CABLEADO Y TODO LO NECESARIO PARA SU CORRECTO
FUNCIONAMIENTO.
Clave Descripción Unidad Cantidad Precio U. Total
Material
0082-01 ALAMBRE GALVANIZADO NO. 14 KG 6.00 $15.00 $90.00
1001-04 TUBO POLIDUCTO CONDUIT 19 MM M 157.50 $3.60 $567.00
1043-12 CABLE (NORMAL) THW 600 VOLTS 90 GRADOS C CALIBRE 8 M 242.00 $14.15 $3,424.30
Total de Material $4,081.30
Mano De Obra
00-0001 HERRAMIENTA MENOR (%)mo 0.04 $4,720.28 $188.81
01-0140 AYUDANTE DE ELECTRICISTA JOR 7.08 $277.24 $1,961.69
01-0390 AYUDANTE DE PLOMERO JOR 7.08 $344.59 $2,438.25
01-1000 CABO JOR 0.75 $452.72 $340.71
MOCA-001 Peón jor 0.90 $344.59 $310.13
Total de Mano De Obra $5,239.59
Herramienta
FACHEME Herramienta menor (%)mo 0.04 $330.50 $13.22
Total de Herramienta $13.22
Precio Unitario
$10,887.70
Clave: CONC58
Unidad: PZA.
ALIMENTACION DE BOMBA CENTRIFUGA; INCLUYE CABLE DEL No. 10, INCLUYE EXCAVACION COLOCACION DE DUCTO,
RELLENO, CABLEADO Y TODO LO NECESARIO PARA SU CORRECTO FUNCIONAMIENTO.
Mano De Obra
01-1000 CABO JOR 0.07 $452.72 $32.53
MOCA-001 Peón jor 0.91 $344.59 $313.96
OM002 OFICIAL ALBAÑIL. jor 0.53 $452.72 $238.19
Total de Mano De Obra $584.68
Herramienta
FACHEME Herramienta menor (%)mo 0.04 $584.68 $23.39
Total de Herramienta $23.39
Clave: ICRF-069
Unidad: PZA
CISTERNA, INCLUYE: EXCAVACION, PISO DE CONCRETO F'C=200KG/CM2 DE 10CMS DE ESPESOR ARMADA CON MALLA 6X6/10-10,
DALA DE APOYO Y CERRAMIENTO DE 15X20CMS DE SECCION, CASTILLOS DE 15X20CMS DE SECCION, MURO DE TABICON EN
14CMS DE ESPESOR; ACABADO FINO EN EL INTERIOR
Clave Descripción Unidad Cantidad Precio U. Total
Material
0100-00 CLAVO DE 2 1/2" A 3 1/2" KG 7.02 $26.50 $186.16
0111-00 ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 20 - 4 M 39.82 $19.33 $769.72
0300-03 CEMENTO NORMAL GRIS TIPO I EN SACO TON 0.87 $2,820.00 $2,454.89
0300-60 CALHIDRA EN SACO TON 0.08 $1,420.00 $114.08
0302-05 AGUA DE TOMA MUNICIPAL M3 5.03 $40.00 $201.01
0302-20 ARENA M3 2.21 $125.00 $275.89
0302-30 GRAVA M3 1.00 $183.33 $183.35
0950-05 DIESEL LT 8.69 $14.63 $127.11
1300-15 VIGUETA 15/15/75 M 26.66 $110.00 $2,932.86
1301-55 BOVEDILLA PRETENSA 16/70 PZA 110.67 $20.00 $2,213.37
1302-00 MALLA ELECTROSOLDADA PRETENSA 6 X 6 10/10 M2 37.45 $17.10 $640.38
1900-05 MADERA DE PINO DE 3A PT 101.06 $12.60 $1,273.38
BHAAB090 TABICON 9X14X28CM. MIL 0.64 $2,600.00 $1,674.66
CA5SA005 TAPA DE LAMINA PZA 1.00 $437.00 $437.00
Total de Material $13,483.86
Mano De Obra
00-0010 PEON JOR 24.02 $344.59 $8,278.24
01-0060 AYUDANTE DE CARPINTERO DE OBRA NEGRA JOR 0.70 $344.59 $239.60
01-0310 OFICIAL ALBAÑIL JOR 8.95 $452.72 $4,050.53
01-0320 CARPINTERO DE OBRA NEGRA JOR 0.70 $452.72 $314.79
01-1000 CABO JOR 1.72 $452.72 $777.80
01-1080 MAESTRO DE OBRA JOR 0.60 $539.68 $324.52
Total de Mano De Obra $13,985.48
Precio Unitario
$32,208.83
Clave: HERR-04
Unidad: LOTE
TRABAJOS DE BALCONERIA
Mano De Obra
01-1000 CABO JOR 0.08 $452.72 $35.86
01-1080 MAESTRO DE OBRA JOR 0.03 $539.68 $14.97
JOSB18 AYUDANTE DE VIDRIERO JOR 0.40 $344.59 $137.84
JOSB19 AYUDANTE DE ALUMINIERO JOR 0.39 $344.59 $135.13
JOSB56 ALUMINIERO JOR 0.39 $452.72 $177.54
JOSB62 VIDRIERO JOR 0.40 $452.72 $181.09
Total de Mano De Obra $682.43
Precio Unitario
$13,743.01
Clave: CANC_001
Unidad: PZA
SUMINISTRO Y COLOCACION DE CANCEL DE ALUMINIO BLANCO DE 3" Y CRISTAL TRANSPARENTE DE 6MM; DE 2.00 X 2.70; CON 1
FIJO Y 1 CORREDIZO; INCLUYE HERRAJES; SOPORTES;CORREDERAS Y TODO LO NECESARIO PRA SU CORRECTA INSTALACION.
Clave Descripción Unidad Cantidad Precio U. Total
Material
CANC001 CANCEL DE ALUMINIO BLANCO EN BAÑO PZA 1.00 $6,500.00 $6,500.00
Total de Material $6,500.00
Clave: HERR-02
Unidad: PZA
SUMINISTRO Y COLOCACION DE CANCEL DE ALUMINIO BLANCO DE 3" Y CRISTAL TRANSPARENTE DE 6MM; DE 4.00 X 2.70; CON 1
FIJO Y 1 CORREDIZO; INCLUYE HERRAJES; SOPORTES;CORREDERAS Y TODO LO NECESARIO PRA SU CORRECTA INSTALACION.
Mano De Obra
01-1000 CABO JOR 0.03 $452.72 $12.89
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $5.38
JOSB18 AYUDANTE DE VIDRIERO JOR 0.13 $344.59 $46.45
JOSB19 AYUDANTE DE ALUMINIERO JOR 0.15 $344.59 $51.69
JOSB56 ALUMINIERO JOR 0.15 $452.72 $67.91
JOSB62 VIDRIERO JOR 0.13 $452.72 $61.03
Total de Mano De Obra $245.35
Precio Unitario
$16,615.78
Clave: HERR-06
Unidad: PZA
SUMINISTRO Y COLOCACION DE CANCEL DE ALUMINIO BLANCO DE 3" Y CRISTAL TRANSPARENTE DE 6MM; DE 4.60 X 3.00; CON 1
FIJO; INCLUYE HERRAJES; SOPORTES;CORREDERAS Y TODO LO NECESARIO PRA SU CORRECTA INSTALACION.
Mano De Obra
01-1000 CABO JOR 0.04 $452.72 $18.11
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $7.56
JOSB18 AYUDANTE DE VIDRIERO JOR 0.20 $344.59 $68.92
JOSB19 AYUDANTE DE ALUMINIERO JOR 0.20 $344.59 $68.92
JOSB56 ALUMINIERO JOR 0.20 $452.72 $90.54
JOSB62 VIDRIERO JOR 0.20 $452.72 $90.54
Total de Mano De Obra $344.59
Precio Unitario
$21,057.08
Clave: HERR-01
Unidad: PZA
SUMINISTRO Y COLOCACION DE VENTANA DE ALUMINIO BLANCO DE 3" Y CRISTAL TRANSPARENTE DE 6MM; DE 0.80 X 2.10; EN
TIPO GUILLOTINA ; INCLUYE HERRAJES; SOPORTES;CORREDERAS Y TODO LO NECESARIO PRA SU CORRECTA INSTALACION.
Mano De Obra
01-1000 CABO JOR 0.00 $452.72 $1.81
01-1080 MAESTRO DE OBRA JOR 0.00 $539.68 $0.76
JOSB18 AYUDANTE DE VIDRIERO JOR 0.02 $344.59 $6.89
JOSB19 AYUDANTE DE ALUMINIERO JOR 0.02 $344.59 $6.89
JOSB56 ALUMINIERO JOR 0.02 $452.72 $9.05
JOSB62 VIDRIERO JOR 0.02 $452.72 $9.05
Total de Mano De Obra $34.45
Mano De Obra
01-1000 CABO JOR 0.02 $452.72 $9.05
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.78
JOSB18 AYUDANTE DE VIDRIERO JOR 0.10 $344.59 $34.46
JOSB19 AYUDANTE DE ALUMINIERO JOR 0.10 $344.59 $34.46
JOSB56 ALUMINIERO JOR 0.10 $452.72 $45.27
JOSB62 VIDRIERO JOR 0.10 $452.72 $45.27
Total de Mano De Obra $172.29
Clave: HERR-07
Unidad: PZA
DOMO DE FABRICA CON VENTILACION DE 2.00 X 1.20 M. INC. ACRILICO, VENTILACION Y COLOCACION.
Material
VEN-09-101 DOMO DE FABRICA CON VENTILACION DE 1.10 X 1.10 M.INC. PZA 2.10 $1,350.00 $2,835.00
ACRILICO Y VENTILACION
Total de Material $2,835.00
Mano De Obra
01-1000 CABO JOR 0.02 $452.72 $9.05
01-1080 MAESTRO DE OBRA JOR 0.01 $539.68 $3.78
JOSB18 AYUDANTE DE VIDRIERO JOR 0.10 $344.59 $34.46
JOSB19 AYUDANTE DE ALUMINIERO JOR 0.10 $344.59 $34.46
JOSB56 ALUMINIERO JOR 0.10 $452.72 $45.27
JOSB62 VIDRIERO JOR 0.10 $452.72 $45.27
Total de Mano De Obra $172.29
Clave: LIMGM02
Unidad: M2
LIMPIEZA GENERAL DURANTE LA OBRA INCLUYE ACARREO DE MATERIAL A LA 1a. ESTACION.
Mano De Obra
01-1000 CABO JOR 0.00 $452.72 $0.34
MOCA-001 Peón jor 0.02 $344.59 $5.18
OM005 CARPINTERO. jor 0.00 $398.49 $0.01
Total de Mano De Obra $5.53
Herramienta
FACHEME Herramienta menor (%)mo 0.04 $5.53 $0.22
Total de Herramienta $0.22
Clave: 1001
Unidad: M2
LIMPIEZA GENERAL PARA ENTREGA DE OBRA EN ÁREA EDIFICABLE, INCLUYE. MATERIALES, DESPERDICIO, ACARREOS, RETIRO
DE SOBRANTE FUERA DE LA OBRA, HERRAMIENTA, EQUIPO Y MANO DE OBRA.
Herramienta
00-001 HERRAMIENTA MENOR (%)mo 0.03 $1.75 $0.05
Total de Herramienta $0.05