The 2023 Interconnection Process Enhancements (IPE) initiative is focused on enhancing coordination of resource procurement and interconnection, resource planning and transmission planning to achieve state reliability and policy needs. In the 2023 IPE initiative the CAISO intends to consider more fundamental changes to the Generator Interconnection and Deliverability Allocation Procedures than were considered in IPE 2021.
Proposal Development | Decision | Implementation | Completed/Closed | |
---|---|---|---|---|
Phase 2 | ||||
Phase 1 |
Track 2
Aug 01, 2024 Track 2 FERC filing Track 3 Sep 18, 2024 Comments due Oct 21, 2024* Second revised straw proposal posting Oct 28, 2024* Meeting Nov 11, 2024* Comments due Dec 08, 2024* Draft final proposal posting Dec 2024* Meeting Dec 2024* Comments due Feb 10, 2025* Final proposal posting March 2025 Board of Governors meeting |
Track 2
Jun 12, 2024 Board of Governors approval Track 1 Aug 01, 2023 FERC approval (ER23-2058) Jun 02, 2023 Tariff amendment filing (ER23-2058) May 17, 2023 Board of Governors approval |