This document outlines a construction project taking place from August 22, 2014 to October 6, 2014. It involves 14 tasks related to removing and replacing parts of a roof over a 30 day period. Key steps include mobilization on August 22, fabrication from August 21-24, removing the old roof from September 12-23, erecting new rafters and supports from September 20-28, fixing the new roof sheets from September 23-28, and site handover on October 6 after project completion.
This document outlines a construction project taking place from August 22, 2014 to October 6, 2014. It involves 14 tasks related to removing and replacing parts of a roof over a 30 day period. Key steps include mobilization on August 22, fabrication from August 21-24, removing the old roof from September 12-23, erecting new rafters and supports from September 20-28, fixing the new roof sheets from September 23-28, and site handover on October 6 after project completion.
This document outlines a construction project taking place from August 22, 2014 to October 6, 2014. It involves 14 tasks related to removing and replacing parts of a roof over a 30 day period. Key steps include mobilization on August 22, fabrication from August 21-24, removing the old roof from September 12-23, erecting new rafters and supports from September 20-28, fixing the new roof sheets from September 23-28, and site handover on October 6 after project completion.
1 Total construction period 30 days Fri 8/22/14 Sat 9/20/14
2 Mobilization work 1 day Fri 8/22/14 Fri 8/22/14 3 Fabrication work in our work shop 4 days Thu 8/21/14 Sun 8/24/14 4 Removing of roof sheet,glass wool, rafters, columns, purlin, cladding & girtz 12 days Fri 9/12/14 Tue 9/23/14 5 Erection of Rafters, Columns ,Purlin, Tie beam & girts 9 days Sat 9/20/14 Sun 9/28/14 6 Fixing of roof sheets 6 days Tue 9/23/14 Sun 9/28/14 7 Fixing of cladding 10 days Fri 9/26/14 Sun 10/5/14 8 Fixing of Aluminium louvers 8 days Sun 9/28/14 Sun 10/5/14 9 Fixing of Gutter & Down pipes 5 days Fri 9/26/14 Tue 9/30/14 10 Fixing of curve roof canopy frame 4 days Sun 9/28/14 Wed 10/1/14 11 Fixing of curve sheets 4 days Wed 10/1/14 Sat 10/4/14 12 Monitor roof - roof sheet & glass wool removing 2 days Mon 9/29/14 Tue 9/30/14 13 Monitor roof sheet laying 3 days Wed 10/1/14 Fri 10/3/14 14 Site clearing & Hand over 2 days Sun 10/5/14 Mon 10/6/14 8/31 9/7 9/14 9/21 9/28 10/5 Aug 31, '14 Sep 7, '14 Sep 14, '14 Sep 21, '14 Sep 28, '14 Oct 5, '14 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline PROPOSED RECTIFICATION WORK TO WASHING PLANT SMART SHIRTS LANKA LIMITED AT EPZ, KATUNAYAKE Page 1 Project: MSProj11 Date: Fri 9/19/14