TAJUK

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM

PWD 203A Standard Form of Contract (Ed.1983)


This form of contract contain no expressed provision that allows the Contractor to
suspend the works if his payment was unduly delayed or he is not getting his
payment at all.
In the PWD203A Form of Contract (2007), it is stipulated that the period for
honouring the certificate is 30 days from the date of the issuance of the certificate.
Clause 30.1 of the PAM Form of Contract (2006) stated that the period of honouring
certificate is within 21 days after the issuance of the certificate. Any payment made
later than the stipulated time frame can be considered as late or delayed payment

PAM Form of Contract 1998


There is no express provision that permits the Contractor to suspend his work when
he is not paid or his payment was not forthcoming in due time after receiving the
Interim Certificate. Clause 25(1) (ii) and Clause 23.4 state that the Contractor is to
proceed regularly and diligently and he is to use his best endeavours to prevent
delay. The clauses clearly demand the Contractor to show a good performance and
continue with the work to prevent disruption to the progress of the project.

PAM Form of Contract 2006


But the new PAM 2006 contains provision that give the Contractor to suspend the
progress of work if the Contractor is faced with problem of delayed or non payment
by the Employer. It is clearly stated in clause 30.7. But it requires the Contractor to
give a written a notice to Employer with reason to suspend the works until the
Employer has paid the amount due to the Contractor

THE DIFFERENCE BETWEEN JKR/PWD AND PAM CONTRACT


JKR/PWD

PAM

- Standard form of contract for government and


public sector project.

- Standard form of contract for private sector


and traditional general contract

- JKR/PWD covered all building and engineering


work.

- PAM covered building work only.

- Standard form for JKR/PWD are :


I.
203 (Rev 10/83) without quantities
II.
203A (Rev 10/83) with quantities
III.
203N (Rev 10/83) for NSC
IV.
203P (Rev 10/83) for nominated
suppliers
V.
PWP Form DB/T (2000 Edn) For Design
And Build Turnkey Contracts
Miscellaneous :
I.
CIDB Form for building contracts 2000
Edn
II.
Modified JKR/PWD Forms, eg LPK, MHA
etc

- PAM contract not covered


I.
Engineering construction contract (other
than building
II.
Package deal / Turnkey
III.
Management type
IV.
Domestic subcontract
V.
Serial contract
VI.
Periodic /Term contract
VII.
Continuation control
VIII.
Other miscellaneous contract
- Standard form for PAM :
(Building Works)
I.
PAM 98 with quantities
II.
PAM 98 without quantities
III.
PAM NSC 98

ISSUE OF
ISSUES PERIOD OF
INTERIM
INTERIM
CERTIFICATE CERTIFICATE
OF SITE
VALUATION

PERIOD OF
ISSUING
HONOURING PERSON
THE
CERTIFICATE

AMOUNT
TO BE
PAID

CONTRACT
FORM

PWD
203A

One month
[Clause 47(a)]

14 days after
site
valuation
[Clause 47 (b)]

30 days from
the
date of the
issuance
of the Interim
Certificate
[Clause 47(d)]

Superintending Value of
Officer (S.O)
Work
Done +
90%
Material On
Site

PAM
1998

One Month
[Clause 30.2)

Upon the
receipt of
Contractors
details
and particulars
[Clause 30.2]

14 days from
the date
of the
issuance of
Interim
Certificate
[Clause 30.2]

Architect

Value of
Work Done
+ 90%
Material On
Site