Method Statement For Plunge Column
Method Statement For Plunge Column
CONTRACT UG1B
LOCATION: JAIPUR
Page 1
CEC - UG1B
Project
Manager
RV AKASH
GANGA
INFRASTRU
CTURE
Constructio
n Pvt. Ltd.
CONTRACT UG1B
DGMPlanning
Department
,
CEC
DPM
STATION,
CEC
Senior
Manager
QA/QC
Department
,
CEC
Chief
Manager
HSE
Department
,
CEC
Project
Leader
CEC
Table of Contents
Sr. No.
1.0
2.0
3.0
4.0
4.1
4.2
5.0
6.0
7.0
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
Description
Purpose
Scope of Work
Site Establishment & Setting Out
Major Resources to be Deployed
Equipment to be Deployed
Manpower to be deployed
Materials
Responsibility and Authority
Construction Procedure
Traffic Management and Barricading
SHE Measures
Design & Drawings
Site Establishment
Surveying
Pre Trench
Plunge column boring
Muck Disposal
Preparation of Rebar Cage
Page 2
Page No.
03
03
03
04
04
04
04
05
06
06
06
07
07
07
08
08
09
10
CEC - UG1B
7.10
8.0
9.0
10.0
11.0
CONTRACT UG1B
Concreting
Quality Control / Control Assurance
Environmental Management
Safety and Emergency Procedure
Attachments
12
12
12
13
13
1.0 PURPOSE
This Method Statement describes the construction process of 1500 mm
diameter Plunge columns in station areas.
2.0
SCOPE OF WORK
The scope of work and the Construction Sequence for installation of permanent
Plunge Column shall be as mentioned below:
a. Traffic Management and Barricading
b. SHE Measures.
c.Design and Drawings
d. Site Establishment
e. Surveying
f. Pre-excavation
g. Boring into soil to the design depth
h. Muck Removal
Page 3
CEC - UG1B
CONTRACT UG1B
4.0
4.1
- 1 no
2. Supporting crane(70Ton)
- 1 no
-1 no
4. Polymer setup
-1 unit
-1 unit
-4 no
-2 no
Page 4
CEC - UG1B
CONTRACT UG1B
8. Transit Mixer
- 8 no
- 1 no
4.2
Manpower to be deployed
Sr.
No.
Construction Manager
Site Engineer
Mechanical Engineer
Surveyor
Foreman
Supervisor
Electrician
Safety Officer
Mechanic
10
MATERIALS
Concrete as per Approved mix design M35 Grade.
Reinforcement Steel conforming to specification
Polymer (from approved supplier)
6.0
6.1
Number
5.0
Category
DPM-Stations
CEC - UG1B
CONTRACT UG1B
o Quality Manuals
o Construction Methodology
Overall responsible for the whole operation.
6.2
Station Manager
He shall be overall responsible for the whole procurement of Men, Material and
Machinery at site, including operation planning and adhered with works
program. He shall be liaison with Utility Owning Agency for approval of Utilities
Diversion Plans (if any).
6.3
6.4
Site Engineer
Responsible for site operation.
Material and equipment planning.
Ensure works are carried out in accordance with the method statement.
Ensure works follow approved drawings and specification.
Ensure works are carried out in a safe manner.
Field control and supervise all site activities.
Apply and issue relevant work permits.
Design Engineer
He shall be responsible to issue controlled copies of all drawings to the site
personnel and return back all obsolete copies. He shall provide detailed design
specifications to carry out the work.
6.5
Planning Engineer
He Shall be Responsible for arrangement of all external resources
Page 6
CEC - UG1B
6.6
6.7
CONTRACT UG1B
Safety Personnel
Ensure works are carried out in a safe manner and in accordance with the
safety requirements stipulated in the SHE plan.
Conduct tool box talks on the safety requirements, construction risks and its
control measures etc.
Surveyor
Carry out setting up works and locate as per submission drawings.
Carry out inspection for location and level of structure.
Keep monitoring the movement of ground and structure.
6.8
7.
QC Engineer
Ensure works are carried out in accordance with specification.
Carry out inspection for all activities in accordance with the Inspection and
Test plan.
He shall be responsible to prepare the method statement in co-ordination
with Design, Safety & Quality and enclose Inspection and Test Plan and risk
assessment. He shall review the method statement as per site requirement.
CONSTRUCTION PROCEDURE
7.1
Traffic Management and Barricading
Traffic management shall be carried out as per the approved Traffic Diversion
Plan. For heavy equipment mobilization, necessary precautions shall be taken to
bring the required items within the work area boundary by carefully managing
the traffic. The work location shall be barricaded as per the site requirement and
all the equipment shall be installed inside barricaded area.
Page 7
CEC - UG1B
7.2
CONTRACT UG1B
SHE Measures
1) All the workers shall be provided with required PPE (safety jacket, shoes, helmet,
hand gloves etc.) before they are engaged in the work.
2) Safety induction shall be provided to the supervisors, engineers and workers.
3) Tool box meetings shall be organized every day by site supervisor before start of
work in order to keep workers aware of associated risks and safe working in
order to avoid accidents/injuries.
4) Unauthorized/outsiders shall not be allowed to enter inside/stay near the area
barricaded during work in progress.
5) First aid facilities shall be made available at site and male nurse shall be
available at principal work spot to render the first aid services, if so required.
6) Proper Lighting arrangement shall be maintained during night work (or in day
time in case of low visibility).
7) Housekeeping shall be maintained at work spot to avoid any undesirable
incident.
8) Emergency contact number shall be available and displayed at the designated
locations near the work spot to tackle any emergency situation occurring at site.
9) All the machines shall be inspected before deploying to the work and proper
guarding for moving parts
Shall be in place prior to commencement of work. Operators with valid licence
(where applicable) shall be allowed.
10) Silent type DG sets shall be deployed at work location.
11) Drip tray shall be provided underneath the machineries to avoid land
contaminations.
12)
Dust bins shall be available at prominent locations of work site to collect
generated waste out of site activities.
13) Risk assessment shall be discussed among all concerned prior to start of the
activity.
14) After completion of work at a particular stretch required back filling shall be
taken up depending upon site requirement.
15) After completion of work post inspection shall be carried out to ensure that the
tidiness has been maintained and the work location has been restored to
Page 8
CEC - UG1B
CONTRACT UG1B
original condition.
7.3 Design & Drawings
A. The work shall be carried out as per the approved design and drawing.
B. Controlled copies of relevant drawings shall be made available at site and shall
remain available with site engineer throughout the work.
7.4
Site Establishment
Before starting any activities, a site utilization plan is drawn showing the various
establishments at site such as location of Panel formation, Putting DGs, Polymer
tanks, Muck bin, office etc. through a detailed survey. The site area shall be then
cleaned properly and made free from any on and over ground obstruction and
necessary barricading shall be installed. All plant and equipment shall be placed
as per this plan.
7.5 Surveying
Upon clearing the site area, the setting outpoints shall be marked for the
subjected Plunge Column panel and with reference to that guide wall, points
shall be marked through requisite survey. Reference pillars shall be always
preserved for checking of constructed guide wall at later stage. All the survey
points/coordinates shall be maintained in survey sheet and checked/approved
by Engineer prior to construction work.
7.6 Pre Trench
During this pre excavation process, investigation and verification of
underground utilities shall be done at the subjected location. Manual excavation
shall be done for finding the underground utilities. In case of any utilities found,
the mapping shall be done through requisite survey and a drawing shall be
drawn. In order to construct the Plunge Column such utilities if required to be
shifted marginally, the same shall be done either through local shifting or
providing the local diversion as agreed upon by the utility owner. The diversion
Page 9
CEC - UG1B
CONTRACT UG1B
CEC - UG1B
CONTRACT UG1B
lowering the Casing with crane. Vertically shall be checked and ensured
during installation.
The casing shall then be driven into the ground with rotary machine until
about 300 mm is left protruding above the ground.
Drilling rig is then used to progress the excavation to the bottom of the
casing pipe and then polymer shall be added before any further excavation
is made.
During excavation polymer shall be added continually from the storage tank
such that level is maintained with in 1000mm below top of casing pipe.
Excavation depth shall be found by sounding tape.
(e)Polymer Slurry Preparation, Storage and circulation
Dry polymer powder shall be tested and approved prior to the use. The
batching plant shall be erected on adequate impermeable slab. Dry
polymer powder shall be mixed in the mixing tank with the water. The
mixing shall be achieved by dedicating a pump and compressed air system.
The mixing tank capacity may be 1.5 times the excavation's volume. The
mixing tank shall be connected to the slurry storage tank with appropriate
routing valves. Thus polymer slurry is made ready for use with required
properties.
In the second phase the polymer slurry shall be pumped to the trench and
circulated continuously till excavation is over. While the panel excavation is
going on the polymer slurry continuously flows to the trench and thus
stabilizes the trench throughout its depth. While excavation, the polymer
slurry get mixed with soil and loses its properties. Continuous circulation of
fresh polymer shall help to keep the properties of the polymer slurry even
then it is mixed with the soil. The return slurry shall be pumped into the
sedimentation tank. The sedimentation tank shall be kept open to the top
to allow an easy cleaning and removal of sediments. As sedimentation tank
is included with three deflector vertical plates, continuous flow of slurry
Page 11
CEC - UG1B
CONTRACT UG1B
shall occur in "cascade" like mode and increase the speed of the
sedimentation occurring between different compartments. The final de
sanded slurry shall be connected to the storage tank with after being
treated properly to achieved required property and sent to storage tank
with proper pumping arrangement.
CEC - UG1B
CONTRACT UG1B
thoroughly and be made free from muck before the truck exits the site. After
removing all the muck the area shall be cleaned using water through the water
pipe line arrangement at site.
7.9
Preparation of
Rebar Cage
7.9.1 Reinforcement Steel Cage Cutting, Bending
The reinforcement cage shall be in single piece or two pieces depending upon
the site condition and equipment availability, the cage may be fabricated and
lowered into Bore Pile. The reinforcement should be cut and bend at the steel
yard or at site as per bar bending schedule and the cages shall be prepared at
site over a level ground. Necessary spacer bars, fixtures, inserts and cover
blocks shall be provided along with the reinforcement cage. Care shall be taken
to fabricate the cage in true line and level with cover blocks fixed with proper
supports and brought to the panel by crane. Cover blocks shall be provided at
close spacing of 1.5m to 2.0m. While cage fabrication, roller cover block shall be
introduced to the outer rebars before fixing.
Page 13
CEC - UG1B
CONTRACT UG1B
Cutting / Shearing of Rebars : The bars with improper ends like bent, too much heated, improper
manufactured ends etc., are cut with Bandsaw machine or sheared with shearing machine. This is
done in order to achieve a flat surface for further forging of the rebar. Also the face of the rebar
becomes perpendicular to the axis of the bar. This flat face also helps in abutment of two rebar when
in contact with each other.
CEC - UG1B
CONTRACT UG1B
After lowering of reinforcement cage, tremie of minimum 200mm dia and length
of 1.2 to 2m shall be lowered in pieces and connected while lowering for full
depth of trench with the help of service crane and hopper of approximately 1.5
cum capacity shall be attached to the top of tremie pipes.
7.10 Concreting
Concrete of required grade M35 shall be batched in the batching plant and same
shall be transported through the transit mixer and poured to the hopper/tremie
pipe. Initial setting and final setting time of concrete shall be 5-6 hrs and 1314hr respectively. The concrete shall be directly discharged into the
hopper/tremie. Before initial discharge there shall be at least 2 nos. delivery
trucks on site. Uniform rising shall be ensured by periodically measuring the rise
of concrete adjacent to the tremie location not less than once per concrete truck
per tremie. There must be a minimum 1.0m immersion of the tremie pipes in
the concrete. This is necessary to avoid polymer inclusions in the concrete.
Tremie pipes shall be shortening depending on the rise of level of concrete. The
tremie lengths and concrete rise shall also be monitored / recorded.
Concrete shall continue to a minimum cut-off level at Bottom of base slab as per
the Drawing No. OKICPL-JM1B-C-SC-72A (typical elevation of pile with plunge
column) as required to ensure sound homogenous concrete at cut-off level. Any
significant remaining portion of Plunge Column from bottom of base slab to top
of concourse slab shall be filled with M5 /M10 Grade slurry Mortar Design
Mentioned Below:Cemen Fly ash Sand
Water
Admixt
t
ure
90 KG
100 KG 1625
310 KG 1 KG
KG
The next remain level of plunge column from concourse slab to the top slab
shall be filled with backfill soil and sand as required.
8 Quality Control / Control Assurance
Quality Control and Quality Assurance of Plunge Column operations at different
stages shall be done using the following ITP & Formats.
Particular care must be shown with respect to control of polymer slurry. Drip
Page 15
CEC - UG1B
CONTRACT UG1B
CEC - UG1B
CONTRACT UG1B
Page 17