Projects Analysis and Implementation Assignment-Ii: Group No: 4
Projects Analysis and Implementation Assignment-Ii: Group No: 4
AND IMPLEMENTATION
ASSIGNMENT-ii
Group no: 4
Maneesha (09yacma038)
Madhumeetha (09yacma036)
Jyoti malpani (09yacmao26)
Vinutha.s (09yacma100)
Bindu shree.b (09yacma012)
Date: 11-04-2011
1
MEANING OF CONTRACT:
An agreement between two or more competent parties in which an offer
is made and accepted, and each party benefits. The agreement can be formal,
informal, written, oral or just plain understood. Some contracts are required to
be in writing in order to be enforced.
DEFINITION:
1) An agreement between two or more parties, especially one that is written and
enforceable by law.
2) The branch of law dealing with formal agreements between parties
TYPES OF CONTRACT:
Types of contract operational for the execution of project :
1) Turnkey Contract
2) Non-turnkey Contract
Turnkey Basis –
2
D. The execution on turnkey basis is decided, when the knowhow is not
available.
E. Turnkey mode is also preferred to fix the single point responsibility for
the execution and completion of entire activities of a unit/package
F. It may be pointed out that the cost of execution on turnkey basis is
generally high as compared to the non turnkey approach. Therefore, the
decision to adopt the turnkey basis should be after the examination and
evaluation of all related aspects.
Non-Turnkey Basis –
Supply Contract:
3
Supply-cum-Erection and Commissioning Contract:
Works Contracts:
Work contract for civil engineering work, structural fabrication work and
erection and commissioning work are executed immediately after the tender are
finalised and approval of competent authorities obtained.
i. Quality & grade of material like steel, cement, bricks, flooring material &
timber, etc.
ii. Workmanship
iii. Norms of consumption of cement & steel
iv. Dimensional tolerance
v. Method of measurement
vi. Safety requirement for construction work
vii. List of IS & IRS codes to be referred
4
Solution:
Financial Management and control is an important segment in the project
life cycle. It deals with all the financial aspects beyond the financial appraisal
and evaluation. The important activities associated are:
Thus, financial management and Control make the project management and
control a total job for the main objective of completing the project in time and
without any cost overrun.
Accounting codes will represent the type of asset being procured. The
asset may be a building, machinery, carne, truck, etc.
5
Monitoring of the insurance policy for validity period and extension
before the expiry dates.
1) Indigenous Contract
a) Design & Engineering
b) Supply of Equipments
c) Erection & Commissioning
2) Foreign Contract
a) Design & Engineering
b) Supply of plant & Equipments
c) Commissioning Spares
Payments:
Payments are made according to the stipulation made in the regard in the
respective A/T’s. The payments are generally of the following three categories:
6
Main jobs for which consultants are appointed are:
This section in project finance & accounts sections does the functions of
overall accounting for all the projects separately & watches in completion of
each scheme so as to transfer the work-in-progress balances to the assets section
in the main accounts section of the finance & accounts department for passing
the entry of capitalisation.
7
Capital budget is prepared every year for the current year based on the
requirement of funds. In case of public sector companies, capital budget is
prepared each year in respect of current year as well as for next year.
8
When the project is completed and contractor fulfilled all his obligations
including defects liability period, the next stage in the project life cycle is to
close the contract. By closure it is meant that financial closure of the contract.
There are two types of closure of contract: physical closure and financial
closure.
9
a. For the extra items or additional work over and above the scope of
work of the contract.
b. Escalations based on the price variation clause (PVC) in the
contract.
c. Statutory variations for excise duty, sales tax, commercial tax,
entry tax, customs duty, exchange rate variation.
vi. Approval of final deviation and extra items statement by the competent
authority.
vii. Delay analysis for delay in completion of work if any and fixing the
responsibility for delay due to contractor or due to purchaser.
viii. Settlement of recovery of liquidated damages or payment of bonus for
early successful completion.
ix. Submission of material account for free issues, issues on recovery basis.
Materials may be steel, cement, equipment, structures, refactories, cables,
pipes etc...
x. To finalize recoveries on account of hire charges, electricity charges,
demurrage, port rent and other charges, if any.
xi. Extension of validity of insurance policy, bank guarantee for security
deposit and performance guarantee etc…
xii. Constitution of standing committee for finalization of closure of
contracts.
xiii. To organize the meetings of standing committee members.
xiv. Finalization of claims of the contractors and other issues like recovery of
LD, deduction for penalty for non-performance of guarantee parameter
and any other issue by the committee.
xv. Processing of recommendation of standing closure committee for the
approval of competent authority.
10
c. In turnkey contracts where performance guarantee test is not
conducted for want of inputs arising out of operational constraints,
head of the user department shall issue final acceptance certificate
(FAC) based on continuous satisfactory operation of the unit or
suggest alternative methodology and duration of performance test
in lieu of 72 hours continuous run.
d. Constitution of standing committee:
a. General Manager (Projects)- Chairman
b. Chief Engineer (Contracts)- Member
c. Head of Construction Zone- Member
d. In-charge Officer (Finance-Project)-Member
e. Consultants Representative-Invitee
f. Head of operation unit-Member
e. After all the contractual formalities have been completed and the
stipulations, the closure of the contract will be formalized by chief
engineer (contracts).
f. Status of the cases pending for closure shall be reviewed by the
executive director on quarterly basis.
l) Dates of -
Preliminary acceptance test
Hot trial
11
Commissioning
Performance guarantee test
Final acceptance test
Completion of defect liability period
m) Performance guarantees details.
Performance guarantee parameter as per contract
Actual result of performance guarantee test
n) Whether material account settled.
o) Whether terminal benefits paid & Employee Provident Fund
clearance received.
p) Whether final discharge certificates furnished by the contractor.
q) Whether No demand certificates received from all concerned.
r) Payment position
s) Whether any extra item claim is made by the party, if yes:
Amount claim by the party
Approval obtained at the time of execution, if any.
Consultant’s view, if it constitutes extra item and is not
covered in the original scope.
Justification as to why the item could not be included in the
original scope.
Consultant’s/operation’s view as to admissibility of extra
claim.
t) Whether there is any delay in completion of the work, if yes:
Total delay
Delay for which contractor is not liable.
Delay for which contractor is liable & liquidated damage is
leviable.
u) Whether party has claimed any escalation, if yes:
Amount claimed by the party.
Amount of escalation within the contract period.
Amount of escalation beyond the contract period.
12
w) Recommendation
13