Project Name:
Build of park and playground for children in community.
Project Start Date: September 1, 2013 Project est. End Date: January 1, 2014
Project Type: Urban Development Project Leadership Project Sponsor:Puneet Sharma Subject Matter Expert: Ministry of Parks Project Member Ministry of the environment
3.
The project will include: Design and building of a park and playground for children Getting community approval Getting proper permissions Conducting Soil Contamination Study
Page 1
The project will not include: Demolishing of the existing building on site and removal of the debris
4.
Project Milestones
Start of project Building Demolition Project completed Approval of soil contamination study Approval of the design and approval of the community Design vendor selection completed Design selection with community preview Completion of design Construction vendor selection Start of construction Completion of Construction Opening of the playground and park event
5.
Assumptions: The old building will be successfully removed without any issues The city utilities water is currently serving the park area The land is free of claims. The weather will allow construction Budget of the project is maximum of 5cr. Constraints: The playground must be suitable and safe for 5 to 12 years old children The weather during the project period could stop construction Budget of the project is maximum of 5cr. Dependencies: Building Demolition Project is completed on time Approval to build from the soil contamination study is received Approval of the design and approval to build from the community
6.
The project budget is 5cr. but the current estimate cost is 2.5cr
Benefits:
The park and playground will improve community involvement The park will provide the community a place for social events The playground will promote physical activity for children The construction of the park and playground will provide two months worth of construction jobs
Page 2
7.
Identify the key stakeholders and team members by function, name and role. Function Project Manager Sponsor Children of the community Community Leaders Representative Ministry of Parks and environment Construction Project Manager Design Project Manager Police Liaison Name Puneet Sharma Puneet Sharma Age 5-12 Mr. ABC Mr. xyz Mr.xyz Role Leads the project Project Sponsor Tester of the playground Provides input on the design of the park Sponsor rep on the project and reviews budget Manages the construction staff assigned to build the Park and Playground Manages the design of the park Provides security input to the project