Public Sector Undertaking: National Buildings Construction Corporation Limited
Public Sector Undertaking: National Buildings Construction Corporation Limited
2001-2002
1.
of
Memorandum
Understanding
The MOU for the year 2001-02 provides for the following targets :
(Rs. Crore)
*
Business
Development
* Turnover
* Gross Margin (Home)
* Net Profit
400.00
350.00
32.00
9.00
2.
* Business Development
* Turnover
l
Gross Margin
* Net Profit
3.
Unit
Target
Achievements
Rs.Cr.
Rs.Cr.
Rs. Cr.
Rs.Cr.
285.00
215.00
436.56
239.66
15.00
16.03
4.00
4.53
* Turnover
** Gross Margin
* Net Profit
The turnover achievement trend for the last five years is given as under :
TURNOVER
SINCE
1997-98
350
97-98
98-99
99-2000
2000-01
2001-02
(up to Dec. 2001)
97-98
DEVELOPMENT
98-99
99-2000
105
SINCE
2000-01
1997.98
2001-02
,up to Dec '2001,
The major projects secured during 2001-02 (upto Dec.2001) are as under:
.
Civil Works Package of Main Plant Area Unit 3 & 4 of Rihand Super Thermal
Power Plant Stage-II (2 x 500 MW) in U.P. for NTPC, valuing Rs. 66.96 crore.
Construction of ONGC Office Complex at Dharavi, Mumabi for Oil & Natural Gas
Commission (ONGC), valuing Rs. 29.32 crore.
Improvement of Water Supply System for Agartala (Assam) for MOUD&PA, valuing Rs.14.90 crore. Civil & Electrical Works of DTC Bus Stand in various parts of
Delhi (on Deposit Terms ) for Delhi Transport Corpn., valuing Rs. 14.00 crore.
Laying of optical Fibre Cable in West Bengal Telecom Circle (WB) of Bharat
Sanchar Nigam Ltd. (BSNL) valuing Rs. 12.53 crore.
Special repairs, construction and Maintenance works comprising of civil & electrical work of various DTC Depots & Colonies at various locations in Delhi for
Delhi Transport Corporation (DTC), valuing Rs. 12.50 crore.
Construction of Income Tax Office Complex at Guwahati for Income Tax Deptt.,
valuing Rs. 12.00 crore.
valuing
REAL ESTATE
The Real Estate sector was adversely hit due to slump in the real estate prices and
the business in this sector is on decline at the present. In the hope that the market will
improve in future, the Corporation is planning to undertake development of some Commercial Complexes as under :
106
Commercial Complex in Vadodara on about 3 acres of land. This land was purchased by NBCC in public auction from the Vadodara Municipality and propose to
commence the work very soon.
Others
Project Magmt
Institutional
Housing
4%
6%
Environmental
14%
Telecommunication
10%
Real Estate
3%
The work for construction of Staff Quarters and Hostel Building at LBSCAMSAR
Campus, Mumbai awarded to the Corporation at an estimated cost of Rs.22.50 crore is
progressing satisfactorily.
l
The work for construction of 220 M high single-flue brick lined RCC Chimney, structural work of pot line, civil works of Boiler, Turbo Generator(TG) and Ancillary Equipments,
foundations etc. for expansion of NALCO Captive Power Plant (CPP) unit-8 at Angul, Orissa
awarded to the Corporation at an estimated cost of Rs. 18.40 crore is progressing satisfactorily. The project is about 56 % complete and is likely to be completed by September, 2002.
l
The work for design and construction of 2 Nos. Natural Draughi Cooling Towers for
Simhadari Thermal Power Plant (2 x 500 MW unit) awarded to the Corporation by National
Thermal Power Corporation (NTPC) at a cost of Rs.79.13 crore is progressing as per
schedule.
.
The project comprises construction of Station Building, Platform covering, railway track
supporting structures, concourse, parking facilities, architectural finishes, station illumination, fire fighting works, land scapping, water supply and drainage arrangement etc. was
awarded to the Corporation by Delhi Metro Railway Corporation (DMRC) at a value of
Rs. 17.26 crore. The station building is comprise ground, concourse level and platform
level. The design of Station Building is unique in the country. The platform roof covering is
supported on the special kind of arches. The entire complex has extra ordinary special
finishings. The railway track girder has been supported on piers/columns of 1.5 m dia. The
piers/columns of the track girder rests on 1.25 m dia and 25 M deep piles. The entire works
related to the station building, railway track, platform aicngwith roof covering etc. have been
completed. The VDC and Granite flooring, stair case steel railing and other misc. works are
in progress. The project is about 90% complete and is likely to be completed by March,
2002.
.
The work for construction of 275 M high twin-flue RCC Chimney at Talchar (Orissa)
awarded to the Corporation at an estimated cost of Rs.8.31 crore is progressing satisfactorily. The Chimney is being constructed for Talchar Super Thermal Power Project Stage-II
(4 X 500 MW). The bottom outer dia of the chimney is 33.70 M and the top outer dia is 20.00
M with wall thickness of 1.05 M at the bottom and 0.37 M at the top of the Chimney. The
construction of Chimney involves 12600 M3 of concreting 2150 MT of Steel reinforcement
and 1900 MT of structural Steel works. The project is about 70% complete and is likely to be
completed by July, 2002.
SOME OF THE MAJOR PROJECTS COMPLETED
.
The work for construction of 275 M high Multi-flue RCC Chimney for Simhadri Super
Thermal Power Plant, Vishakhapatnam for NTPC has successfully been completed at a
cost of Rs.10.50 crore.
.
The work for construction of Krishi Anusandhan Bhawan (KAB)-II at Pusa, New Delhi
for Indian Council of Agricultural Research has successfully been completed at a cost of
Rs.16.56 crore.
.
The work for construction of Flood Diversion Canal at Simhadri Thermal Power Plant
Stage-l has successfully been completed at a cost of Rs.6.21 crore.
The work for construction of Engineering Colleges at Ferozpur and Gurdaspur (Punjab)
have successfully been completed by the Corporation at a cost of Rs.25.20 crore and
R.s.23.21 crore respectively.
l
MANUALS
Accounts and Works Manuals which contain Accounting Policies, Working Policies
Procedures and various instructions issued from time to time has been prepared and put
into use at the projects.
Both the above manuals are of great help in smooth working at the projects.
(ii) Updation of Corporate Plan 1998-2003 & prospective plan for next five years
thereafter
The Corporate Plan for a period of five year i.e. from 1998-2003, defining the long term
and short term goals, corporate strategies for optimum utilisation of its resources with an
eyes for using new and advanced technologies etc. have been updated. The updated Corporate Plan also provide the prospective plan for next five years thereafter. The above plan
is being followed in planning/ implementation process.
WELFARE OF SCs & STs IN SERVICE
A special cell to look after the welfare of SCs/STs is functioning in the Corporation
under the control of Addl. General Manager (Pers)-I. He is also the Liaison Officer of this
Cell. This cell ensures the compliance of instructions issued by the Government from time
to time. The grievances of SCs/STs employees are attended to promptly. Rosters are also
maintained in the Corporate Office as per instructions issued by the Government from time
to time.
The Corporation has nine zonal offices, all the Zonal Heads are functioning as Liaison
Officers of their respective zone.
NBCC HOSTS ITS WEB SITE BOTH IN HINDI 8 ENGLISH
NBCC has hosted its Website both in Hindi and English with the domain name
www.nbccindia.com on the internet, to provide latest information to its customers.