Drain Plan of Delhi
Drain Plan of Delhi
Drain Plan of Delhi
DRAINS
MASTER PLAN
FOR
DRAINAGE OF STORM WATER
DRAINAGE OF THE MCD & DDA AREA
IN
UNION TERRITORY OF DELHI
1976
1
(ii)
(iii)
(iv)
into three zones viz. Karol Bagh Zone, West Zone and Civil Line Zone. The problem
of drainage in these different zones are described in detail under their respective
headings.
The drains of South Delhi which falls into the Barapulla basin are
described in detail under the South zone heading.
The drains directly falling into the river Yamuna are described mostly
under city zone and a few under Civil Line Zone.
As regards the Shahdara drainage system since the Shahdara basin in
a composite one, consisting of both rural and urban drains, all the drainage systems
in this basin are fully dealt with in a separate volume called Master Plan for
Shahdara basin.
While designing the drains in the MCD areas, surveys were carried out
jointly by MCD & FCD of practically all the drains.
examined during the 1975 monsoon which was a heavy rainfall year. It has been
noticed that, there are no serious water stagnation in those M.C.D. drains, which
are either constructed or remodeled according to the Reddy Committee
recommendation of half inch per acre runoff, during the monsoon 1975, although
the rainfall in 1975 monsoon, in certain automatic rain gauge stations were
recorded as high as that of 10 years frequency. To give an example, the rainfall
recorded at Gurmandi and Badli on 19th June, 1975 were 90.5 and 80 millimeters
respectively. Subsequent to Reddy Committee also two committees were formed
i.e. J.P.Jain Committee and Moti Ram Committee. There was no recommendation to
increase the unit design discharge in urban area in these two reports as well .
During 1975 monsoon, however, the stagnation and erosion problems in
the different reaches of MCD drains were noticed in the following cases.
The
reasons of stagnation were also analyzed and they were found mainly due to (a)
Inadequate capacity (less than half cusecs per acre) (b) Poor maintenance of banks
2
and bed (c) Failure of pumps (d) Chocking of nallas due to dumping of malba etc.
The major problems faced in 1975 are listed below:
S.No.
Name of drain
Causes stagnation
1.
2.
3.
4.
Town)
5.
6.
7.
8.
(Shahdara)
9.
Madanpur Khadar
Inadequate
outfall
and
poor
maintenance
channels.
2.
of
The areas in Karol Bagh and surrounding regions were considered moderate
to densely paved, whereas the other areas were taken as light to moderately paved
according to actual condition.
assumed as moderate to densely paved, since they are mixed type catchments
consisting of partly densely populated and partly open areas around Red Fort etc.
In case of the major arterial drain like Najafgarh drain, Chirag Delhi drain
Barapulla drain etc. the discharge in the different reaches were computed not by
direct run off factors but by rational method, taking into consideration proper time
of concentration, run off factors and areal distribution factors.
The problems of the different drain in the different zones are described
hereafter in details, one by one. The longitudinal sections of all the major drains
are also enclosed, indicating therein all the necessary modifications.
As regards the priority of scheme, the following are considered as of
relatively urgent nature.
S.No.
Name of drain
Zone
1.
South
2.
South
3.
West/Civil Line
4.
5.
Shahdara
6.
Shahdara
7.
Shakurbasti drain
Karol Bagh
8.
Drain No.12-A
City Zone
9.
Drain No.14
City Zone
10.
South
11.
Karol Bagh
12.
Disused Channel
Shahdara
13.
Gita Colony
Shahdara
14.
Shahdara
NAJAFGARH DRAIN:
It collects considerable
storm water from Haryana Territory, crosses Dhansa Bund at the border, flows
through rural Delhi for a length of 38.10 Kms and enters the city area near Nangloi
outfall point.
It traverses across the Karol Bagh zone, West Zone and Civil Line
Zone of the Municipal Corporation area of Delhi.
Master Plan, i.e. the Master plan for Najafgarh basin, the problems of the
Najafgarh drain and its remodeling proposals have been described in detail. It has
been mentioned, that the present capacity of the najafgarh drain is only three
thousand cusecs at the outfall, which is totally inadequate and is being remodeled in
its tail reach to a maximum capacity of 10,400 cusecs by providing lining.
The
Hydrological studies for ultimate remodeling of the Najafgarh drain were carried
out in the Central Water Power Commission under the guidance of Shri J.Tripathi,
Member (Floods), who had recommended that the ultimate possible augmentation of
the capacity of the Najafgarh drain can be upto a figure of 10,000 cusecs. In his
study the design discharges for the different reaches in the urban part of the
Najafgarh drain were also given. His figures are enclosed as statement-I.
In this study, the C.W.C. had accepted a 5 years frequency rainfall of 2.17
inches for the design of this drain. The run off co-efficient were adopted as 0.45
in the moderately paved and 0.60 in densely paved areas. An areal distribution
factor of 70% was adopted in the design.
In this study, it was presumed that the flow from Dhansa will not synchronie
when the actual catchment of Delhi is discharging to its full. In exceptional case
when both the storms coincide, there may be slight congestion in the city for a
very short duration. Shri Tripathi also reiterated the proposal of a supplementary
drain, which will ultimately cope with the discharge from the upper catchments and
Delhi may be independently drained by the Najafgarh drain.
Since the question of constructing supplementary drain cannot be
immediately thought of , on account of financial and other limitations, the proposals
of improving the Najafgarh drain to its ultimate capacity in accordance with the
recommended discharges calculated in Shri J.Tripathis report are taken up as final
and the designs of the Najafgarh drain has been finalized in the urban reach. The
proposed L-Sections are shown in drawing Nos. NGF XXII & XXIII. It may be
mentioned that remodeling in the portion between Bharat Nagar bridge to the
outfall point has already been started according to these proposals,
5
satisfactorily.
Out of the 10 drains examined, three drains e.g. Daryai Nalla (upper part),
industrial nallah and Patel Road barrel are underground. Baljit Nagar drain is also a
covered one. The Shakur Basti drain is also now proposed to be an underground
barrel. A new drain for draining the Jakhira area is also proposed to be of RCC
underground pipe.
Name
o.
drains
1.
of
Shakur
C.A.
Max.
Leng
Lined
Max.
Max.
in
th
Unline
Dept
bed
Acs
Cus
Mts.
d/
width
3850
1790
2440
Barrel
RCC
Mts.
4.00
Mts.
6.00
Yes
in
basti
Box
Drain
2.
Daryai
3385
2370
5718
Lined
2.00
12.00
Yes
2000
670
1830
Brick
1.60
10.00
Yes
RCC
2000
Yes
Barrel
mm.Q
Nos.
Nallah
3.
D.T.U.
Nallah
4.
Patel Road
Lined
(U+R)
850
510
2000
Barrel
.
5.
J.J.Colony
502
251
3220
Lined
1.70
2.80
Yes
475
238
625
Lined
1.20
3.00
Yes
333
233
2100
Lined
1.22
3.66
No.
Drain
6.
Subhadra
Drain
7.
Kanhaiya
Nagar
Remark
S.N
g require Remodelin
Existing drains:
Drain
8.
Industrial
240
120
1003
area nalla
9.
Ranjit
182
91
1100
Nagar
RCC
1200
2 nos.
Yes.
Barrel
mmQ
Brick
0.80
2.50
No.
0.60
1.25
No.
RCC
1200
1 No.
New
Pipe
mm
lined
Drain
10.
Baljit
70
49
900
Brick
nagar
lined
Drain
with
cover
Proposed Drain.
11.
Baljit
110
77
800
nagar
Drain
Drain
Q.
SHAKURBASTI DRAIN:
The Shakurbasti Drain originates at Rampura near the Ring Road and flows
southwards for a length of 625 metres. Thereafter it takes a turn towards east
and runs along the Delhi-Rohtak Railway line and ultimately falls into Najafgarh
drain. This drain has its catchment area to the North of Delhi-Rohtak railway line.
The catchment area is partly industrial and a major portion is being developed by
the DDA. The general slope of the country is towards Najafgarh drain. The total
length of the drain 2440 metres and serves a catchments area of 3580 acres.
The existing drain is underground, which is found to be inadequate to carry
the discharge from its catchment area, which is being considerably developed and
urbanized by DDA in their H4, H5 & H5 (part) zones. The section of the drain is
therefore proposed to be replaced by RCC barrels. The area through which this
drain passes being highly congested, no additional land can possibly be acquired.
Therefore, the proposed barrels are also kept of the same width as that of the
existing covered drain. The catchment of the drain is taken as fully developed,
with moderate density of population.
adopted as 0.5 cusecs per acre. The drain is to outfall into Najafgarh drain bed.
7
DARYAI NALLAH.
This drain at present carries the storm water and sullage discharge from
the urbanized area of Karol Bagh, Rohtak Road etc. the existing drain is barrel type
from the starting point at Shankar Road upto Rohtak Railway Bridge. The reach of
the drain from railway line, as at present, is kacha open drain.
The drains run through moderate to densely populated areas and a unit
discharge of 0.7 cusecs per acres has been adopted for designing the drain. The
drain originates near the Shankar Road and flows through Rajinder nagar for a
length of 800 metres, where it crosses the Pusa Road.
Thereafter, it flows
through Karol Bagh and Sarai Rohilla area for a length of 3000 metres and crosses
Shankar Road. It then flows towards Shastri Nagar and Bharat Nagar areas and
falls into the Najafgarh drain. The total length of a existing drain is 5700 metres
and serves a catchment area of 3386 acres.
The capacity of the barrel portion has been found to be adequate under
full condition with unit discharge 0.7 cusecs per acre all through its length.
Capacity for a small portion between RD.2627 and RD.2816 is slightly less.
However, the inadequacy is very nominal and can be permitted by slight
encroachment of free board. In the open portion of the drain, below the railway
bridge however, considerable silting has been noticed.
logged practically every monsoon. The outfall structure of the Daryai Nallah on the
Najafgarh drain, has been examined and found to be adequate and requires no
remodeling.
L-section of this drain is shown in Drawing No. MPO/KBZ/12.
3.
D.T.U. NALLAH.
The drains starts at he confluence point of Ranjit Nagar and Baljit Nagar
Nallah, near D.T.U. Colony. This is an open drain. Its length is 1830 metres and
serves a drainage area of 2000 acres, of which 1000 acres in Pusa Institute and
surroundings are considered as semi rural. The section of the drain is lined for the
reach 0 to 1465 metres and thereafter the section is Kacha, which is proposed to
be lined. The drain has its outfall into Ramesh Nagar Nallah.
The area served by the drain is lightly built up and a design discharge of 0.5
cusecs/acre has been taken for the urban portion. For the semi rural portion 0.15
cusecs /acres has been adopted.
adequate.
proper energy dissipation. A small size cunnette is provided in the upper section of
the drain, to carry the dry weather flow from the area.
L-section of this drain is shown in Drawing No. MPO/KBZ/7.
4.
of Pusa road and Shankar Road, runs towards North-West along the Patel Road for
a length of 2000 metres before out falling into the D.T.U. Nallah. The total area
covered by this drain is 850 acres. The catchment area is developed two times
moderately populated. The design discharge of 0.6 cusecs per acre has therefore
been assumed for design purposes.
grossly inadequate to cater for the storm water run from the area. Additional
pipes are proposed to be added at different reaches.
L-section of this drain is shown in Drawing No. MPO/KBZ/6.
5.
Link Road for a length of 500 metres where it turns towards South and Flows along
the Delhi Tail distributor and ultimately the drain outfalls into the Najafgarh drain.
The total length of the drain is 3220 metres and the catchment area is 502 acres.
9
The bed level of the drain is to be lowered slightly all through. The bed of the
drain at outfall point is quite above the bed level of the Najafgarh drain and as
such a pucca structure is to be provided with necessary energy dissipation
arrangements to avoid any damage to the Najafgarh drain. This structure is to be
constructed after the proposed remodeling of the Najafgarh drain in this reach.
L-section of this drain is shown in Drawing No. MPO/KBZ/11.
6.
east along the Western Yamuna Canal and falls into Daryai Nallah. There is one
Industrial Nallah which also joins the Subhadra Colony drain at RD.251. The total
length of the drain is 625 metres and covers a catchment area of 475 acres. This
is an open drain having lined section throughout its length. The area served by this
drain is lightly populated and as such the design discharge of 0.5 cusecs per acre
has been adopted for the design of drain. The portion from RD.251 upto outfall
requires remodeling and lining. The water way for the existing structural safety
has to be examined at the time of remodeling of the drain.
L-section of this drain is shown in Drawing No. MPO/KBZ/10.
7.
distributory. It flows through Lawrence Road Colony, Tri Nagar and Ganeshpura
and falls into the Najafgarh drain. The total length of the drain is 2100 metres
and covers a catchment area of 333 acres. The existing drain is an open one with
its bed and sides lined. The section of the drain is found to be adequate to cater
for the discharge from the catchment area. The drainage area being moderate to
densely populated, a design discharge of 0.7 cusecs per acre has been adopted.
The water ways under the existing structures across the drain are also adequate.
The bed of the stair at its outfall into the Najafgarh drain is at about 5 metres
above. Therefore, suitable energy dissipation structure requires to be constructed
at the outfall.
The existing drain passes through a closely built up area and it is suggested to
cover the drain throughout its length to avoid falling of children in the drain as well
as to avoid dumping of house-wastes in the drain, which may choke the water way
and create insanitary conditions for the surrounding locality.
L-section of this drain is shown in Drawing No. MPO/KBZ/3.
8.
This drain starts from New Rohtak road and after passing through the
railway protection force area, flows towards North and outfalls into Subhadra
Colony Drain. The entire system is under ground, except for some portion falling
within the R.P.F. area. The existing section of the drain is found/to be adequate
except for a reach between RD.580 to 850 where an additional pipe of 600mm dia
meter has been proposed to be laid. The total length of the drain is 1003 metres
and it covers a catchment area of 240 acres. The drain passes through built-up
areas and a design discharge of 0.5 cusec. per accre has been assumed for the
design purposes.
L-section of this drain is shown in Drawing No. MPO/KBZ/9.
9.
of South Pater Nagar and Shadipur, etc. The drain after traversing a distance of
100m. outfalls into the D.T.U. Nallah near D.T.U. Colony. The total catchment area
for the drain is 182 acres. The existing section of the drain is found adequate and
remodeling of the drain is not necessary. At the outfall point it is proposed to
provide suitable pitching to prevent retrogression.
L-section of this drain is shown in Drawing No. MPO/KBZ/4.
10.
flows south west for a length of 900m. Where it meets the D.T.U. drain. The drain
caters for a catchment area of 70 acres. The catchment is semi-hilly and moderate
populated and a design discharge of 0.7 cusecs per acre has been assumed. The
existing section of the drain is lined throughout its length and is quite adequate.
There are a number of falls in the bed of drain and suitable pucca structures are
required to be provided. The outfall point is also to be provided with suitable
pitching.
L-section of this drain is shown in Drawing No. MPO/KBZ/.
11
11.
JAKHIRA DRAIN
The area around Jakhira chowk is low lying and suffers drainage congestion
during the monsoon season. It is proposed to provide a covered drain starting from
upstream of Jakhira chowk. It is to run along the New Rohtak Road and will fall
into Najafgarh drain. The total length of the proposed drain is 800m. and caters
for a catchment area of 110 acres. The design discharge from the catchment is
taken as 0.7 cusecs per acre as the area served by the drain is moderate to densely
paved. As the difference of the bed levels at the outfall is 6.3 metres, adequate
brick masonry wall outfall structure requires to be constructed.
L-section of this drain is shown in Drawing No. MPO/KBZ/8.
Name
Length of
Catchment
drain
area
Km.
in
hectares
Maximum
in
Remarks
anticipated
discharge
in cumecs
West
Zone
drainage
(Existing)
1.
4.72
823
28.5
Existing
sections
adequate.
12
2.
3.23
1380
61.3
sections
Urban
inadequate.
to
+635(Rural)
3.
2.23
426
Existing
be
remodeled.
14.70
Require
extensive
remodeling
4.
Rajouri Garden
0.82
646
2.27
Existing
section
adequate.
5.
1.94
106
3.72
Existing
single
48
inch
dia
barrel
inadequate
open drains
proposed.
6.
Tatarpur drain
1.68
130
4.45
Existing
section
adequate.
7.
1.07
316
11.20
Existing
section
adequate.
1.14
64.6
2.27
New
Section
9.
0.50
61
2.12
New
Section
10.
1.34
204
7.15
New
Section
Wazirpur
Complex
(Existing)
11.
Wazirpur Drain
3.99
13
822
28.8
Inadequate
section
being
reivised.
Wazirpur
Complex
(Now
proposed)(only alternative 1
listed)
12.
7.14
705 (Urban)
+
27.85
1140
New
Section
(Rural)
13.
Sabzimandi drain
2.10
220
7.70
-do-
14.
2.70
248(urban)
10.40
-do-
II
674
(rural)
15.
1.68
127
4.45
-do-
16.
3.60
440
15.34
-do-
17.
2.55
450
15.60
-do-
This drain is of
section of size sufficient to carry the anticipated discharge. Thus no reasons could
be attributed to the reports that the colony is vulnerable for flooding, except that
the existing link drains may not be functioning properly.
The details of the drain are shown in the Drawing at appendix WZ-2.
RING ROAD DRAIN:
This is one of the major drain in West Zone, which has a direct outfall into
Najafgarh drain. The drain runs parallel to Ring Road, and Pusa North, draining
Colonies likes Manas Sarovar,Sharda Puri, Rajouri Garden etc.
14
a shallow basin in its catchment area and these area are liable for flooding due to
the inadequate functioning of cross/distributary drams/
The drain is about 2.3 km long, and having a catchment area of 420 hectares
and a maximum anticipated discharge of 14.7 cumecs at the outfall point.
existing section in the entire reach is lined section with brick-work.
The
But the
existing sections are found inadequate to carry anticipated discharge and revised
sections are proposed for the entire length.
Though the drain runs in a congested area, still there is sufficient land
available for proposed widening of drain. At the outfall point, a masonry structure
will be essential in view of the large difference in bed level of Ring Road drain and
Najafgarh drain. But this outfall structure will have to be taken up only after the
proposed widening of Najafgarh drain is completed. Also the existing culverts need
remodeling.
The details of the drain are shown in the Drawing at appendix WZ-3.
15
TATARPUR DRAIN:
This is another drain having a direct outfall into Najafgarh drain and by its
catchment area it could be treated as a minor drain. The drain is having a length of
1.7 K.M., a catchment area of 130 hectares and a maximum anticipated discharge of
4.45 cumecs at the outfall point. The drain caters for storm water drainage of
Tagore Garden and J.J. Colony behind it.
The section of drain, as existing, is built up with masonry side walls and bed
to the full length. The section is in a good condition, except at places desilting may
have to be done. No structure exists at the outfall point into Najafgarh drain. It
is recommended that a proper masonry outfall structure be built, after the
proposed widening of Najafgarh drain.
The details of the drain are show in the Drawing at appendix WZ-5.
Considerable portion is
highly urbanized area, certain portion is from the ridges of Central Delhi and
another portion which can considered as rural. The drain is about 3.25km. long, has
a total catchment area of 2015 hectares (1368 hectares urban and 635 hectares
rural) and a discharge of 61.3 cumecs at the outfall point. The drain outfalls into
Najafgarh drain. Except for the ridge area with rocky outcrops like Anand Parbat,
Shankar Road and upper ridge road, the catchment area is generally flat.
The link drains which are attributing to the storm flow are as under, which
have been discussed in detail:
(a)
(b)
(c)
(d)
D.T.U. drain
(e)
Inderpuri drain
(f)
Naraina drain
Patel Road drain, as existing consists of a barrel, laid underground
The
and side wall and the existing section is adequate to carry the anticipated
discharge.
The DTU Nallah collects the storm water from the above mentioned
drains, meanders through Pusa Agricultural Institute and joins Ramesh
Nagar drain.
treated as green area for purposes of contribution storm water from its
catchment area to the drain. (A net discharge of 0.30 cusecs per acre is
considered from the Green area, which is arrived at the using a runoff
factor of 0.20).
Inderpuri drain has its origin in the rocky ridges of central Delhi,
flows near Inderpuri collecting the storm water and joins the drain from
Naraina area.
Naraina area between Ring Road and circular railway line disposes of
the storm water into a pitched drain laid by DDA. This drain outfalls into
Ramesh Nagar drain, after collecting the storm water from Naraina
Industrial area and J.J.Colony.
The existing Ramesh Nagar drain is a built up section to its entire
length of drains i.e. upto its outfall point into Najafgarh drain. Though the
drain has well defined section with masonry bed and side walls, still the
section is inadequate to carry the anticipated discharge. Hence, a revised
section is proposed, to cater for the discharge.
At present, there is no proper structure at the outfall point into
Najafgarh drain.
proposed bed level of Ramesh Nagar drain and Najafgarh drain, a proper
masonry structure is recommended to be built at the outfall point after
widening of Najafgarh drain is completed.
The details of the drain are shown in the Drawing at appendix WZ-6.
17
activities were relatively non-existing as such the water logging of areas was
not as seriously viewed as it is now, in view of residential accommodation
springing up.
In view of proper drainage of the area, it is found that existing pipe drain is
inadequate to carry the anticipated storm water and hence it is now
proposed to run a open surface drain parallel to Jail Road upto the outfall
point to Subhash Nagar. This drain has additional catchment area through a
proposed link drain called Prem Nagar Link drain. The proposed link drain
has to cross the Najafgarh road and from this covered drain in view of the
developments which has already taken place.
The drain, as proposed is about 1.1 K.M. long, has a catchment area of
64.6 hectares and a maximum anticipated discharge of 3.7 cumecs at the
outfall point. The proposed drain is stone pitched section in its open reach
and will have a suitable masonry outfall structure.
The details of the drain are shown in the Drawing at appendix WZ-7.
18
topography of the area is virtually flat, this area is prone for flooding and
requires immediate attention for drainage.
The proposed drain is about 1.3 km. long, has an urban catchment area
of 204 hectares and a maximum anticipated discharge of 7.15 cumecs at the
outfall point. The drain is proposed to be stone pitched.
The details of the drain are shown in the Drawing at appendix WZ-9.
19
WAZIRPUR COMPLEX.
The drainage scheme in this complex is of considerable importance,
as Wazirpur is being developed by DDA to an urban area (areas North of
Ring Road) and the already developed areas in Model town and Azadpur do
not have a proper drainage scheme. Area North-West of Model Town is
already marshy land, causing health hazard to the population in this area.
The marshy land is almost at the bed level of Najafgarh drain as such the
storm water disposal of this area by gravity is ruled out. Due to the fact
that this area is low lying, the area also gets water logged very easily.
Hence drainage of this area is a primary problem, which had to be studied in
great detail.
The topography of the entire area has been studied before a suitable
scheme is envisaged.
drains including their alignment. The area has been roughly categorized in
three zones.
(a)
(b)
(c)
The name of the proposed drain in this zone is Model Town drain.
Under zone (c) the existing marshy land is being considered for
drainage purposes.
Shahalam Bund beyond Radio Colony and outfalls into Burari Creek.
As
Burari Creek it self is below the normal flood level of Yamuna (at 50,000
cusecs) the performance of this drain is very poor.
21
parallel to G.T. Road and it is contended that this does not involve land
acquisition problem for purposes of construction of drain.
The proposed
23
three drains, a drain running parallel to Karnal road & intercepting the
catchment area of Shalimar Bagh area, Model Town drain with the
catchment of Subzimandi, Adarsh Nagar etc. and the Radio Colony drain.
The main feature of the scheme is that the main drain having
maximum catchment area is being carried parallel to Karnal Road, out falling
into Najafgarh drain. This drain has to be basically covered in its entire
length (parallel to Karnal Road) as there is very limited space existing for an
open drain.
The RCC cover slab at top will function as the space for
24
The Khyber pass drain at present starts from Alipur Road near Civil
Lines police Station, traverses a distance of about 545 metres and
discharges into an open low-lying area, causing stagnation of water there.
It is now proposed, that the drain which at present, finishes into a
low-lying area, shall be excavated further upto Yamuna River for a length of
375 metres along a suitable alignment and as per the pitched section
required for passing the requisite amount of discharge, as shown in the
drawing of this drain. There is an existing culvert at the proposed crossing
of this drain with Ring Road but a regulator is required to be constructed
near Ring Road, so as to avoid the back water effects of Yamuna river during
high floods.
The total length of the drain when completed shall be about 920
metres. It shall cater to a total drainage area of about 128 acres (51.82Ha)
upto its outfall point. The discharge at outfall works out to be 64 cusecs as
per the Experts Committees recommendations of cusecs/Acre for lightly
paved area.
The drain in general will dispose of the storm water of the localities
of Khyber Pass market, Old Sectt. And Civil Lines area, etc.
The existing initial reaches of this drain are pitched but their
capacities are insufficient and hence, it is proposed to widen this drain by
about 0.5m (from 0.8m. to 1.4m between RD.0 and RD.290, from 2m. to 2.5m
in the balance reach). The bed of the drain also needs lowering nominally as
per the proposal L-section of this drain.
from start to finish are found to be adequate to carry the design discharge
and hence, no widening is proposed except that the drain should be properly
reshaped to the designed bed levels. The drain is found to be considerably
silted upto in the upper reaches and must be properly maintained and
desilted every year. The existing regulator is adequate and no change is
suggested. However, a proper outfall structure needs to be constructed as
out falling water at present, is causing erosion on d/s of Ring Road and may
endanger the Ring Road embankment.
The quidsia Bagh drain starts from the opposite side of St. Stephens
Colleges play ground & runs by the side of Qudsia Marg, till it outfalls into
Yamuna River through an existing regulator. Two drains namely Bela Road
drain and Morigate drain join Qudsia Bagh drain at Ring Road culvert, just
before the Qudsia Bagh drain outfalls into Yamuna river.
The total
catchment area of the drain is about 954 acres (386 hectares) and the
discharge at outfall works out to be 477 cusecs (13.5 cumecs) as per a
discharge factor of cusecs/acre for the lightly paved urban areas.
This drain disposes of the storm water of the localities of the Moti
Bagh, Rly Colony, Rajpur Road, part of Civil Lines, Ludlow Castle, etc., in
addition to the localities which fall in the catchment of Morigate drain and
Bela Road drain.
The total length of the drain is about 1215m. The existing sections
of the drain right from the beginning are inadequate to carry the design
discharges.
Proposed sections as per requirements have been suggested, proposed, in
addition to the lowering of the bed in the tail reaches. The drain, in general,
requires sufficient remodeling in addition to the culvert at RD.0, RD.100,
RD.250, which require remodeling.
present manually operated with needles (Karies etc.) which may be equipped
with a mechanically operated gate.
The existing mori Gate drain which is a covered drain starts from the
crossing of Gokhale Market, Passes through Jhuggi Jhopdi Colony and then
from Mori Gate Chowk it runs along the old city wall near ISBT and finally
outfalls into a sump near Nigambodh ghat on the Ring Road.
26
This
combined storm water sewage is than, lifted from the sump well of Nigam
Bodh Ghat to the Delhi Gate Trunk Sewer.
It is very necessary that the disposal of sewage be separated from
the storm water by removing all the existing sewage connections. For the
disposal lf the storm water, it is suggested that the existing drain be cut
off from near the Inter State Bus Terminus and then taken to Qudsia Bagh
drain, along Ring Road where an abandoned drain is already existing. This
drain can thus dispose off its storm water into Yamuna river through Qudsia
Bagh drain and there is no necessity of taking it to the Trunk Sewer &
unnecessarily increasing the load on the sewage treatment plant.
The
catchment area of this drain is 435 acres (176 hectares) which caters to
the storm water from Rly Colony, Gokhale Market, Morigate, ISBT etc. and
the anticipated discharge is 217.5 cusecs (6.16 cumecs) as per the discharge
factor of cusecs/acres for lightly paved urban catchment.
The existing section are sufficient to carry the design discharge
upto I.S.B.T. crossing from where the drain is to be diverted along an old
abandoned drain whose bed & banks may have to be remodeled slightly upto
the required levels as shown in the drawing of this drain.
TONGA STAND DRAIN: (Refer Drg. No. MPO/CLG/6)
The Tonga Stand drain, which is a covered drain, starts from the Crossing of
Netajee-Subhash Marg & Shyama Prasad Mukherjee Road, crosses the
Railway Line at Calcutta Gate, then crosses Ring Road and finally outfalls
into Yamuna river.
A branch pipe of 36 starting from behind the G.P.O. outfalls into the
main Tonga-stand drain near Calcutta Gate.
The total catchment area of this drain is 200 acres (80 hec.) and it
cater to the localities like Kashmiri Gate, Yamuna Bazar, Nigam Bodh Ghat,
etc. The anticipated discharge at outfall works out to be 100 cusecs as per a
discharge factor of Cusecs/acre for lightly paved urban catchment. The
existing rectangular section of the drain in the tail reaches i.e. from RD.330
to outfall are sufficient to carry the design discharge and as such no
remodeling is suggested. While in the initial reaches, there are two 36 dia
pipes along two different alignments which together are unable to carry the
design discharge. It is therefore, suggested that either one of these pipes
be replaced by 48 dia pipe or one more pipe of 36 dia along suitable
27
alignment be laid in the reach of RD.0 to RD.330. Further the drain bed
must be desilted properly every year.
Moreover, the Sluice Valve regulator leaks during floods and needs
proper repairs.
Proper outfall structure should also be constructed at the outfall
point of the drain as the out falling water at present, is causing erosion of
the soil and may endanger the adjacent roadway.
GUR MANDI DRAIN
Gurmandi drain which is a covered drain starts from the D.T.C. Staff
quarters and runs along the G.T. Road, thus crossing C.C .Colony, Rajpur
Village, etc. till it finally outfalls into Najafgarh drain.
The catchment area of the drain is 216 acres (87.5ha), which caters
to the localities lime Gujaranwala colony, State Bank Colony, D.T.C. Colony,
portion of Vijay Nagar and Gurmandi, etc.
The Hansraj drain which is a covered drain starts by the side of Hans
Raj College, passes through Maurice Nagar, runs along the imperial Avenue
and outfalls into Najafgarh drain. The length of the drain is about 1530m.
The catchment area of this drain is 182 acres and the design discharge
works out to be 91 cusecs as per a discharge factor of cusecs/acre for
lightly paved urban areas. Hansraj drain, drains out the storm water from
colonies like Malka Ganj & Maurice Nagar etc.
The existing section for this drain are adequate to carry the design
discharge and no major remodeling is suggested except that the drain bed
shall be desilted & smoothened as per the L-section of the drain.
The
proper maintenance & desilting must be carried out every year since the
available free board in this covered drain is only 0.2 metres. The existing
outfall structure consists of steps in stone masonary which is adequate and
as such no change and no repairs are needed.
28
The Mall Road drain starts from near the crossing of Alipur road and
mall road, then runs by the side of Mall Road, it then crosses Vishavidalaya
Marg, Chhatra Marg, Vikramaditya Road, Sardar Patel Road, etc. and finally
out falls into Najafgarh drain. The total length of the drain is about 1034M.
The catchment area of the drain upto its outfall is about 89 acres
and the design discharge works out to be 44.5 cusecs as per a discharge
factor of cusec/acre for lightly paved urban areas.
storm water from the surrounding of Mall Road and University area such as
Khalsa College, Miranda House, etc.
The existing section of the drain from RD.0 to RD.750 is sufficient
to carry the design discharge from RD.750 to outfall, the existing section
of the drain is insufficient. So, it is proposed that the section from RD.750
to outfall be widened from an existing bed width of 1.0m. to 2.0m., as shown
in the drawing of this drain.
A proper outfall structure consisting of steps in stone or brick
masonary needs to be constructed along with widening in the tail reaches.
TIMARPUR DRAIN:
The Timarpur drain starts from Timarpur near Govt. quarters and
outfalls into Najafgarh Drain. The catchment area of the drain is 90 acres
and the design discharge works out to be 45 cusecs as per a discharge
factor of cusec/acre for the lightly paved urban catchment. The drain
caters to the storm water of localities like Timarpur, etc. The length of the
drain is 420m. The existing section of the drain is sufficient to drain out
the design discharge of 45 cusecs and hence, no remodeling is suggested but
it is stressed that proper desilting must be carried out every year. This
drain outfall into that reach of Najafgarh drain which at present is being
widened and lined. Hence, a proper outfall structure of brick or stone steps
must be constructed at the time of widening Najafgarh drain.
T.B. HOSPITAL DRAIN: (Refer Drg. No. MPO/CLG/11)
T.B.Hospital drain at present starts from near Babu Rajinder Prasad
T.B. Hospital (Silver Jublee T.B. Hospital), run parallel to Ring road, passes
near Bangali Co-operative Society Colony and Naini Lake reservoir and finally
disposes off its storm water into the open low lying area being Model Town.
It is now proposed that this drain will be intercepted halfway & Model Town
29
drain. The T.B.Hospital drain will, therefore, functioning a link drain to the
proposed Model Town drain.
The total length of the drain shall be about 1600 metres and will be
serving a catchment area of acres upto its outfall. The total discharge at
the outfall works out to be about 45 cusecs as per a discharge factor of
cusec./acre for lightly paved urban catchments.
Red Fort drain is a link drain to Civil military drain. This drain carries
water from the premises of Red Fort and runs by the side of Red Fort wall
facing Ring Road. After traversing a distance of about 366 metres from its
starting point (i.e. the point at which water from inside the Red Fort, falls
outside into the drain), the drain finally outfalls into the Civil military drain.
The total catchment area of this drain is 95 acres (38.45 hectares) and the
total discharge at the outfall works out to be 1.35 cumecs (47.5 cusecs) as
per the Experts Committees recommendation of cusecs per acre for such
lightly paved areas.
No major remodeling is suggested on this earthen drain except that
slight desilting and reshaping of bed may be required for giving a uniform
bed slope.
30
Civil Military Drain originates from the Chandni Chowk crossing taking
the storm water of the adjoining areas and passes through Red Fort. It
runs for a length of about 559 metres in the shape of a trunk sewer from
Chandni Chowk crossing to slightly d/s of Khas Road Barracks; from RD.559
to RD.1180 the drain becomes in the shape of a covered arch section and
crosses through a few roads such as Khas Road, Link Road etc. in its way.
Beyond RD.1281 the Drain becomes an open drain & finally outfalls into
amuna River, after crossing the Ring Road through a regulator at Mughal
Bund. Slightly upstream of the Ring Road culvert, near a mandir, another
drain called Red Fort drain joins this particular drain.
The total length of Civil Military drain is about 1913 metres and the
total catchment drained upto its outfall point consists of 325 acres highly
paved+135 acres lightly paved urban areas.
The outfall
structure and regulator at the outfall are sufficient to cater the design
discharge and no remodeling is, therefore, suggested in them. Further, it
appears that MCD is discharging certain sewage connections into this drain
which should be stopped hence with as it is absolutely necessary to separate
the sewage and storm water disposals.
31
Jawahar Lal Nehru Marg near Football stadium & crosses Ring Road near Raj
Ghat.
After crossing the Ring Road, it runs parallel to Ring Road just
distance of about 220 metres when it cross the internal railway track
system of C.Power House. Just D/S of this crossing there is an existing
regulator through which the drain finally outfalls into Yamuna River.
32
existing bed width of 2.5 metres to 6.5 metres as shown in the drawing of
this drain.
On account of the very low ground levels of the Tilak Bridge Railway
Colony, this drain has to run at considerably low elevation and the F.S.L. at
its outfall has to be at about 50,000 cusecs flood level of Yamuna. The
gates of the outfall regulator has, therefore, to be lowered, whenever there
33
Drain No.14 starts from the junction of Purana Quila Road and
Mathura Road, where the system No.12 of N.D.M.C. and one more M.C.D.
nallah join it. The drain traverses a distance of about 900 metres through
the exhibition ground (C.P.W.D. reach) . Thereafter, (in the M.C.D. reach) it
crosses a couple of road culverts and a couple of railway culverts and finally
outfalls into Yamuna river through the Ring Road culvert. A regulator just
downstream of Ring Road is required to be constructed so as to avoid the
back water effects of Yamuna river during high floods.
The drain caters upto its outfall point, to an urban catchment of 500
acres (202.43 hectares) and the total discharge at outfall, therefore, works
out to be 250 cusecs (i.e. 7.08 cumecs) as per the Experts Committees
recommendation of cusecs/acre for lightly paved areas.
The bed of the drain from Rd.0 to RD.150 needs a slight lowering but
from RD.150 to RD.630, the existing drain bed is lower than the proposed
and hence, no lowering of bed is required in this reach. The existing lower
levels can be left as they are and shall be silted up in due course. Beyond
RD.630, the drain has been covered upto RD.780 and from where onwards it
again becomes an open drain. The bed of the covered drain is almost at the
designed levels and can be left as it is Beyond RD.900 to outfall, the
existing drain bed is much higher than what is proposed and hence needs
lowering of the order of 1 meter or so.
The existing drain section between RD.0 and RD. 1000 are wider
than what are required and hence do not need any widening and can be left
as they are. From RD. 1000 to outfall the existing sections are somewhat
smaller than proposed and hence needs widening as per the drawing of this
drain o as to carry the design discharge.
The culvert across Mathura Road, which connects the N.D.M.C.
system No.12 and this M.C.D. drain No.14 is a very old one whose
construction drawing and details are not known even to the M.C.D. (General
Wing) under whose maintenance it is. This culvert is a heavily choked one,
with a few pipes crossing at several points. As a result, every year, it blocks
up the N.D.M.C. discharges at this point and allow overflow on the Mathura
34
Road causing serious traffic jam. The required sections of this culvert from
the proposed remodeled drain are also shown in the drawing of this drain.
The bed levels of the culverts at Rly. and road bridges which at
present are at higher levels need to be lowered or desilted from 0.6m. to
0.90m as shown in the drawing. The existing structure will most probably be
safe if the lowered bed is protected with stone in mortar or concrete slab.
However, the safety of the foundation must be confirmed before lowering
their pucca beds if at all required.
KUSHAK NALLAHBARAPULLA NALLAH
The Kushak Nallah- Barapulla Nallah system enters MCD area behind I.N.A.
market After this, a very important tributary, called the Defense Colony
Nallah joins. Thereafter sunehri Pul Nallah, bringing considerable discharge
from New Delhi area also gets connected to it. Actually from this point the
Kushak Nallah gets the name barapulla Nallah.
Lajpat Nagar drain also joins on the right bank, slightly above the
Suneharipul Nallah.
The Barapulla Nallah problems have been described in detail under
the N.D.M.C. system of drains.
health hazard to the areas like Nizamudding, Bhogal, Jangpura, etc. It is essential
that W.S.S.D.U. makes all arrangements to stop discharging sullage and sewage
from their jhuggie jhompries and other unauthorized colonies.
As regards the
35
season, these karries will be removed, to allow free flow of the Barapulla discharge.
Otherwise serious afflux will occur at the railway bridge point, very near to the
tailend
catchment areas of drains are shown in drawings SZ-1 & SZ-2 respectively.
In South Zone drainage system, the following are the important existing
drains which have been taken up for the study. The general feature of the drains
are shown against them:
Name of drain
Length
Km.
in
Catchment
area
Maximum
in
hectares
Remarks
anticipate
d
discharge
in cumecs.
1
Chirag
Delhi
8.19
5300
Existing
36
section
drain
adequate.
Andrews
Gunj
2.51
503
16.41
-do-
Greater Kailash
1.43
482.50
27.33
Existing section in
Drain
drain
adequates to be
remodeled.
Malviya
Nagar
1.50
269
12.30
-do-
Nagar
5.40
1700
59.50
Existing
Drain
Nauroji
Drain
section
adequate
A.I.I.M.S. drain
2.65
2060
66.00
-do-
Lajpat
Nagar
3.29
460
16.15
-do-
Bagh
3.71
554
19.48
-do-
4.26
706
25.00
Existing
drain
Maharani
drain
Kalkaji drain
section
adequate
upto
Mathura
Road.
Section
downstream to be
remodeled.
Sunehripul
1.43
1918
67.00
Nallah
Existing
section
adequate.
As brought out, South Delhi area has good ground slopes and is the aristo
ceratic zone of Delhi, as such there are no pockets of areas which have been
referred as Vulnerable for flooding zone. The area is highly urbanized and hence
virtually no scope exists for widening of drains. The drains in general are also built
up to the requisite size pitched/lined in their entire lengths and covered in many
areas.
Generally, all the drains are having their outfalls into another drainage
channelization of the upland discharges towards the culvert under the Mehrauli
Badarpur Road.
completely spreads over the surrounding juggi development areas and MES farms.
The channelization is proposed to be started, only from the point upto which the
juggi resettlement works are at present in progress. This is about 600 metres
above the culvert point.
present in their natural condition, so that there may be some moderation of the
flood discharges in the rural area. In case the DDA development works extend
further upstream, the channel may also have to be extended simultaneously.
The arched culvert under the Mehrauli Badarpur Road having three spans of
7.80 metres each was constructed in the British period but is still in a good
condition. However, the bed of this culvert has been considerably silted upto a
depth of at least 1.5m. (5 feet). As a result, the storm runoff from the upper
portion of the culvert, spreads out into these surrounding juggi resettlement areas
and MES farms, overflows the Mehrauli Badarpur Road to a depth of 6 inches to 1
feet, traverses across the fields downstream and reaches back the Chirag Delhi
drain with considerable silt carried from the fields. This reach of the drain from
the Mehrauli-Badarpur road culvert upto Khirki bridge, has been heavily silted up,
also for two other reasons.
brings very heavy quantum of sullage and sewage, that drops into the Chirag Delhi
drain. The cultivators on the left side of the drain in this reach also construct
38
cross bunds at different places of the drain, for pumping out this sullage water, for
irrigation in their fields.
The vast tract of about 800 acres between Mehrauli Badarpur Road and
Khirki Road, which is at present being cultivated, although acquired by DDA, will
ultimately be fully developed into a colony by the DDA. The Chirag Delhi drain in
this reach will therefore from the main arterial drain of this future developed
area. It has been noticed that a number of serious rain cuts and gully formation
have taken place on the sides of the drain in this reach, eroding valuable land that
needs to be replaced afterwards at considerable cost.
It is therefore very
important that the DDA should immediately stop this wastage of land due to gullies
and rain cuts, which can be done by constructing cross bunds across these gullies,
until final development of the area is taking places.
It may be pointed out that, this tract of flat land was formed due to the
construction of the Khirki bund in the Mughal period, which was very well regulated
by a stone built regulator with provisions for gate arrangements.
Unfortunately today there is no regulation across the Khirki bund and the
Chirag Delhi drain is having a free flow from under the Khirki bridge and causes
severe land erosion.
This reach of the Chirag Delhi drain is, therefore, proposed to be
completely remodeled from the Mehrauli Badarpur Road bridge upto Khirki Bridge.
The section of this proposed drain is given in drawing No.SZ (Sheet-I). As the land
will be valuable after development the section is proposed to be pitched.
The
existing waterway of both the Mehrauli badarpur bridge and Khirki bridge appears
to be adequate. Only the foundation of the Mehrauli Badarpur bridge has to be
first checked by means of digging open trench as before the remodeling of the
drain under this bridge. Downstream of Khirki bridge there is an existing drop of
about 6 metres, in a distance of about 300 metres. Thereafter, the Chirag Delhi
drain runs in a meandering course through fields and reaches the Chirag Delhi
bridge, where actual urbanization starts today.
There is a very flat low land on the left side of the drain just after the
Khirki bridge. It is proposed to construct two pucca masonry falls below the Khirki
bridge, with complete energy dissipation arrangements, to kill the energy of the 6
metres drop in this reach. The earth available from remodeling the drain in the
reach from Mehrauli Badarpur Road to Khirki Road bridge can be utilized in the
reach down stream of Khirki bridge for improving the land undulations.
Alternatively, it may also be studied if across bund can be constructed somewhere
down below, thereby forming a pond, in the vast shallow area mentioned above. This
pond may have a moderation effect on the flood discharge that will traverse down
39
below. But a danger in constructing this lake is that, it may get filled up with
sewage and sullage which is at present coming from Dakhasin Puri area, through this
drain. Therefore, the question of this lake formation should not be considered,
until the WSSDU ensure omission of any sewage or sullage disposal, through this
drain.
A major tributary to the Chirag Delhi drain is existing in this reach that is
the Malviya Nagar drain. Although the Malviya Nagar drain near its outfall point is
having considerable width along natural depression, it is having a very narrow and
shallow brick lined section at the reach, where it emerges out of the Malviya Nagar
Colony. As a result, the complete drainage of Malviya Nagar gets choked and three
to four feet of water stagnate in the colony. This actually happened in the year
1975 on 5th August. The Malviya Nagar drain requires complete remodeling and the
proposed sections are given in the drawing No.SZ-4. The Chirag Delhi drain, at the
crossing of the Chirrag Delhi bridge is very narrow. As a result, the Chirag Delhi
bridge was by-passed in 1975. This bridge, therefore, needs considerable widening
with spans metres earch. The road level also should be raised to RL. After the
Chirag Delhi bridge, the nallah is having adequate sections for some distance which
needs only proper trimming and pitching. These are indicated in drawing No.SZ-2
(sheet-II).
The next serious problem in this drain starts from the point where Greater
Kailash drain outfalls at RD.4710. The Greater Kailash drain collects considerable
storm water from the undulating areas on the South side of Greater Kailash. The
section of this drain being inadequate and badly maintained, the storm water spills
over and stagnates to a depth of to 1 metre in the highly developed area of
Greater Kailash S-Block. A proposed remodeled section of the drain is therefore,
indicated in drawing No.SZ-5.
The Chirag Delhi drain also downstream of this point, is extremely narrow.
Thus, with a slightly high rainfall, the drain overflows and spills into the buildings
and basements on its right side. In 1975 monsoon, heavy damages occurred on both
the banks of this drain as well as on the bed in this reach. There is ample scope of
widening the drain on the left side, which is part of the old Siri Fort area. The
proposed section of the drain in this reach is indicated in drawing No.SZ-2 (sheetII). The remodeling will be in the shape of widening, providing pucca cunnette,
providing dry stone pitching on the banks, remodeling the bridge behind Archna
Cinema and providing masonry falls as indicted in the drawing No.SZ-2. The bank
pitchings must be laid on proper filter material to prevent soil erosion. The slope
of the banks should be 1v in 1.25H.
40
Some distance above the Ring Road, a pucca drain joins Chirag Delhi drain
from Andrews Ganj side. The section of this drain has been examined & found to
be adequate. It is indicated in the drawing No.SZ-3.
In the reach below Ring Road, upto its junction with the Kushak Nallah
across the Railway line, the section of this drain appears to be more or less
adequate except it needs some desilting of the bed and repairing of the cunnettee
wherever necessary. The foundation of a few foot bridges appears to have scoured
out and the bridges are standing in the dangerious condition.
calculated for Mehrauli area, by analyzing the rainfall data from the rain gauges in
this area.
41
The drain
originates in Kalkaji area and flows east and outfalls into Agra Canal. The general
ground level towards
congestions are found. The existing drain is well defined in the upper reaches viz.
upto the crossing of Mathura Road and is pitched with stone bricks. The urban
area drained is mainly Okhla Industrial estate, apart from Kalkaji area.
Beyond Mathura Road and upto agra Canal the drain is at present meandering
in the present day rural fields. The drain is well formed though not built-up in the
area. The natural surface here is basically an agricultural land (mainly due to Okhla
sewage disposal works) upto Agra Canal, except for a small stretch of land to the
east of Mathura Road which is being developed by DDA and along the periphery on
which runs the proposed drain. On enquiry with the people cultivating in the fields
at the lower reaches, it is understood that there has never been flooding of the
area, through the existing drain is not well defined.
The existing sections of drains are generally adequate in the reach from
Kalkaji upto Delhi Agra Railway line. The culverts across Mathura Road and one
line of Railway track needs remodeling.
Since the area downstream is not urbanized, land acquisition may not pose a
problem, and this stretch of drain has to be constructed as per the drawings. An
outfall structure of masonry exists at the tail end of the drain near Agra Canal,
which requires remodeling, after the scheme of drainage is finalized.
The details of the drain are shown in drawing No. SZ-8.
42
Since the
topography, in general, is steep almost upto its outfall the drain is well defined in
its course and because of the drain flowing through urbanized area, the drain is
built up almost in its entire reach (except in the last half km. length where its
banks are not defined.
The existing section of the drain in its upper reaches are pitched both on its
bed and sides and the drain is totally covered on the downstream side beyond
Mathura Road (From RD.2256 to 3093) and for a portion in Srinivas Puri (from
RD.1174 to 1220). The existing section of the drain is found adequate to carry the
anticipated discharge upto 3093 and also the existing culverts and bridge are
adequate.
The last stretch of drain (0.5 km. from the outfall point) requires
remodeling on two scores viz. the existing banks are not defined and too shallow a
drain exists and secondly during high floods in Yamuna, a large area on this stretch
get inundated. Since there is no proposal to extend a marginal bund south of Ring
Road, the inundation is inescapable. However, it is recommended to raise the banks
of the drain in this reach upto river Yamuna and provide pitching on either sides of
these embankments so that the course of the drain is maintained.
The details of the drain are shown in drawing No. SZ-9.
SUNHERI PULLA DRAIN.
This may be termed as one of the most important drains as the catchment
area of this drain includes Rashtrapati Bhawan, North-South Blocks, Connaught
Place other important areas South of India Gate upto Lodhi Colony. But the entire
drainage system (storm water) of this area is led through underground covered
drains and the main artery of this system outfalls to an open drain near Dayal Singh
College. The stretch of this open drain upto its confluence with Kushak Nallah is
called Sunheri Pulla drain, which in reality is only a link drain to Barapulla (Kushak
Nallah) drain.
The drain has well defined embankment upto its outfall point, with a
cunnette sections in the middle. The length of the drain is about 1.4 km. and has a
catchment area of 1918 hectares.
43
This system of drain has one link drain, discharging the storm water from
Lodhi colony area. There are no other link drains of importance.
The existing section of this drain is found quite adequate to take the
anticipated discharge. Hence no modifications need be taken for the culverts and
bridges, except that a small portion of left embankment of the drain at the
confluence point with Kushak Nallah needs proper embankment to prevent storm
water back flow into the West Nizamuddin Colony area, where natural surface
levels are below full supply level of the drain.
The details of the drain are shown in drawing No. SZ-10.
LAJPAT NAGAR DRAIN:
This drain also originates on the same high grounds as of Maharani Bagh
drain and this drain runs due North, collecting the storm water of densely
urbanized areas of Amar Colony and Lajpat Nagar, before out falling into Barapulla
drain. The drain is about 3.3 km. long drains a catchment area of 460 hectares
giving a maximum anticipated discharge of 16.15 cumecs at the outfall point.
The drain is an open drain throughout the length, with well defined banks.
The catchment area so highly dense, has not been indicated as flood prone. The
existing cross-section of drain, it is observed, is having brick-lined sides and
because of considerable silting (which is unform) the bed through lined is not
visible except in certain reaches. The existing section is found adequate to carry
anticipated discharge, through lined is not visible except in certain reaches. The
existing section is found adequate to carry anticipated discharge, through it is
considered that by desilting of the drain.
Except at the tailend of the drains, the side banks of the drain are free,
with a dwarf masonry walls built at its periphery in considerable reaches.
The existing. Bridges and culverts across the drain are found adequate and
no remodeling is considered necessary. The bed levels of Barapulla drain and Lajpat
Nagar drain are same, at the confluence outfall structure is existing nor is it
considered necessary.
The details of the drain are showing in drawing No.SZ-11
44