United States Ex Rel. Noland Co. v. Irwin, 316 U.S. 23 (1942)
United States Ex Rel. Noland Co. v. Irwin, 316 U.S. 23 (1942)
23
62 S.Ct. 899
86 L.Ed. 1241
By Act of February 14, 1931,1 making appropriations for the Department of the
Interior, Congress authorized the construction of a library building at Howard
University in the District of Columbia. The cost was not to exceed $800,000, of
which sum $400,000 was made immediately available. Only a small part of this
money had been used for architects' fees when the President, shortly after his
inauguration in 1933, ordered impounded these and all other funds appropriated
for construction.
Title II of the National Industrial Recovery Act of June 16, 1933,2 created a
Federal Emergency Administration of Public Works, with all of its powers
vested in an Administrator. By 202 the Administrator was directed to 'prepare
a comprehensive program of public works, which shall include among other
things the following: * * * (c) any projects of the character heretofore
constructed or carried on either directly by public authority or with public aid to
serve the interests of the general public; * * *.' And 203 provided that 'with a
view to increasing employment quickly * * * the President is authorized and
On August 24, 1935, Congress passed the Miller Act. 3 By the terms of this
statute, 'before any contract, exceeding $2,000 in amount, for the construction,
alteration, or repair of any public building or public work of the United States is
awarded to any person, such person shall furnish to the United States * * * a
payment bond with a surety or sureties satisfactory to such officer for the
protection of all persons supplying labor and material in the prosecution of the
work provided for in said contract for the use of each such person.' The Act
also permitted persons who supplied materials and labor to bring suit on the
bond in the name of the United States.
After the passage of the National Industrial Recovery Act, the Secretary of the
Interior (who had been named Administrator pursuant to Title II) approved the
library building at Howard University as a part of the public works program
and allotted $1,120,811.58 for its construction. On December 5, 1936 the
Assistant Secretary of the Interior, on behalf of the United States, entered into a
contract with respondent, Irwin & Leighton, for the construction of the library
building. As a condition of the contract, Irwin & Leighton was required to
furnish a bond to secure the laborers and material men, under provisions of the
Miller Act.4 Accordingly, it posted such a bond in the amount of $408,618,
with respondent United States Guarantee Company as surety.
The question before us therefore is whether the construction of the library was
a 'public work' as that term is used in the Miller Act. We think that it is, that the
In Maiatico Construction Co. v. United States, supra, upon which the Court of
Appeals principally relied in reaching an opposite conclusion, the same court
had construed a different statute, the Heard Act of August 13, 1894.6 That Act
required that 'any person or persons entering into a formal contract with the
United States for the construction of any public building, or the prosecution and
completion of any public work, or for repairs upon any public building or
public work, shall be required' to post a bond for the security of both the United
States and the suppliers of labor and materials. It permitted the laborers and
material men to enforce their claims by intervening in any suit by the United
States on the bond. The plaintiffs in the Maiatico case supplied labor and
materials in the construction of three dormitory buildings at Howard
University, the contract for which had been let to the defendant construction
company by the United States in November, 1930. The Court of Appeals
decided that the plaintiffs could not recover on the defendant's bond because
the dormitories were not 'public buildings' and their construction was not a
'public work.' It based this conclusion on the theory that 'public buildings' or
'public works', within the meaning of the Heard Act, included only buildings
which belonged to the United States. Since Howard University is a private
institution and since it held title to the dormitories, recovery on the bond was
denied to the suppliers of materials and labor.7
10
Whatever may have been the validity of this narrow formula when applied to
the Heard Act, we cannot approve its application to this suit under the Miller
Act. In the first place, the whole concept of 'public works' has been
considerably altered since the enactment of the Heard Act in 1894 and
particularly within the last dozen years, and the question of title to the buildings
We have no doubt that the Miller Act was intended to apply to the 'public
works' authorized by the Administrator under the National Industrial Recovery
Act. The National Industrial Recovery Act did not leave to speculation the
nature of the 'public works' that Congress envisaged. Its language was not
technical but plain and specific. Expressly included were 'projects of the
character heretofore constructed or carried on * * * with public aid to serve the
interests of the general public.' Beyond question the library at Howard
University was such a project.
12
13
We hold that the Administrator had the authority to require the bond and that
petitioner was entitled to bring this action on it. Holding this view, we find it
unnecessary to consider the other questions raised by petitioner.
14
Reversed.
2
3
by him or material was furnished or supplied by him for which such claim is
made, shall have the right to sue on such payment bond for the amount, or the
balance thereof, unpaid at the time of institution of such suit and to prosecute
said action to final execution and judgment for the sum or sums justly due him:
Provided, however, That any person having direct contractual relationship with
a subcontractor but no contractual relationship express or implied with the
contractor furnishing said payment bond shall have a right of action upon the
said payment bond upon giving written notice to said contractor within ninety
days from the date on which such person did or performed the last of the labor
or furnished or supplied the last of the material for which such claim is made,
stating with substantial accuracy the amount claimed and the name of the party
to whom the material was furnished or supplied or for whom the labor was
done or performed. Such notice shall be served by mailing the same by
registered mail, postage prepaid, in an envelop addressed to the contractor at
any place he maintains an office or conducts his business, or his residence, or in
any manner in which the United States marshal of the district in which the
public improvement is situated is authorized by law to serve summons.
'(b) Every suit instituted under this section shall be brought in the name of the
United States for the use of the person suing, in the United States District Court
for any district in which the contract was to be performed and executed and not
elsewhere, irrespective of the amount in controversy in such suit, but no such
suit shall be commenced after the expiration of one year after the date of final
settlement of such contract. The United States shall not be liable for the
payment of any costs or expenses of any such suit.
'* * *.'ses
4
14 Stat. 438.
28 Stat. 278, as amended by the Act of Feb. 24, 1905, 33 Stat. 811 and the Act
of March 3, 1911, 36 Stat. 1167, 40 U.S.C.A. 270.
This emphasis upon title to the building or project or to the land on which it is
situated finds support, as far as the Heard Act is concerned, in Title Guaranty &
Trust Co. v. Crane Co., 219 U.S. 24, 31 S.Ct. 140, 55 L.Ed. 72; 23
Op.Atty.Gen. 174.
8
See Peterson v. United States, 6 Cir., 119 F.2d 145, at pages 147, 148.
Hearings on H.R. 2068, H.R. 4027, H.R. 4231, H.R. 4461, H.R. 5054, H.R.
6018, H.R. 6115, H.R. 6677, H.R. 8519 (March 8, 22, April 26, and May 3,
1935), Committee on the Judiciary, House of Representatives, 74th Cong., 1st
Sess., p. 71.