Professional Documents
Culture Documents
Independent Enterprises Inc. Thomas Lozecki v. Pittsburgh Water and Sewer Authority City of Pittsburgh, 103 F.3d 1165, 3rd Cir. (1997)
Independent Enterprises Inc. Thomas Lozecki v. Pittsburgh Water and Sewer Authority City of Pittsburgh, 103 F.3d 1165, 3rd Cir. (1997)
3d 1165
Alan S. Miller (argued), Picadio, McCall, Kane & Norton, Pittsburgh, PA,
for Appellants.
Kimberly A. Brown (argued), Stacey L. Jarrell, Thorp, Reed &
Armstrong, Pittsburgh, PA, and Craig E. Frischman, Kapetan, Meyers,
Rosen, Louik & Raizman, Pittsburgh, PA, for Appellee Pittsburgh Water
and Sewer Authority.
Virginia S. Scott (argued), City of Pittsburgh Department of Law,
Pittsburgh, PA, for Appellee City of Pittsburgh.
Before: BECKER, STAPLETON and MICHEL,* Circuit Judges.
OPINION OF THE COURT
STAPLETON, Circuit Judge:
1983, and pendent state law claims. All of these claims arose in the context of
the Authority's failure to award Independent three Authority contracts on which
Independent had submitted the lowest bids.
I. The Facts
2
In 1986, Independent sued the City and Authority in the United States District
Court for the Western District of Pennsylvania after the City declared that
Independent was "noncompetent" to bid on any projects in which it had an
interest and the Authority consequently rejected a low bid by Independent. In
settlement of that suit, the parties agreed to a consent decree that was ultimately
entered by the court. The consent decree provided that Independent could not
be "debarred" from bidding on City contracts based on any past performance,
and that if the City or Authority wanted to "disqualify" Independent from City
or Authority work because of problems with future performances, it would first
have to conduct a hearing under the Pennsylvania Local Agency Law. Between
the issuance of the consent decree and the solicitation of bids for the 1995
contracts at issue here, Independent satisfactorily performed "numerous"
contracts for both the City and Authority.
In May 1995, the Authority solicited bids for two projects, the "Annual Water
Line Contract" and the "Grandview Avenue Project." Independent submitted
bids for both projects. In accordance with the Authority's "MBE/WBE
Utilization Requirements," each of Independent's bids included a list of
minority- and women-owned business enterprises ("MBE/WBEs") that
Independent intended to use as subcontractors if awarded the contract. One of
the MBEs Independent listed was Whaley & Sons, a firm that Independent
claims was certified by the Authority as an approved MBE/WBE vendor.
Independent's bids were the lowest for both projects, and an independent
consultant recommended that the Authority award both contracts to
Independent.
Before the Authority made a decision about awarding the contracts, the City's
Deputy Mayor of Government Operations, Salvatore Sirabella, issued a
memorandum (the "Sirabella memorandum") to the Authority's Executive
Director. In the memorandum Sirabella expressed concern about the cost over-
run on a recent Authority project that had been completed by Independent, and
directed the Authority to "temporarily halt awarding any contracts to
Independent...." App. at 87. Shortly after receiving the Sirabella memorandum,
the governing body of the Authority (the "Board") decided that Whaley & Sons
was an unacceptable MBE subcontractor and resolved to reject Independent's
bids for both the Water Line Contract and the Grandview Avenue Project "for
failure to meet the MBE/WBE requirements of the specifications." Auth.Res.
67 & 68, App. at 197-98. The Board then awarded the two contracts to the next
lowest bidders. About a month later, the contracts with those bidders were
rescinded, all bids were rejected, and the Authority resolved to readvertise both
the Water Line and Grandview Avenue projects.
6
In June, 1995, Independent submitted a bid to the Authority for the "Annual
Sewer Improvement Contract." Again, Independent's was the lowest
responsible bid. And again, despite its low bid, Independent was not awarded
the contract. There was apparently some communication between the attorney
for the Authority and Independent regarding the absence of a Power of
Attorney form in Independent's bid package, but ultimately the Authority did
not reject Independent's bid on that basis. Instead, the Authority's Board simply
rejected all of the Sewer Improvement Contract bids without explanation and
readvertised the project.
In response to the Authority's failure to award it the Water Line Contract, the
Grandview Avenue Project, and the Sewer Improvement Contract, Independent
filed this suit. Its complaint alleged that: (1) the Authority and City violated the
terms of the consent decree by "disqualifying" Independent from Authority and
City contracts; (2) the Authority's MBE/WBE Utilization Requirements
discriminate against Independent and other construction companies on the basis
of race, ethnicity, national origin, and/or sex, thereby denying them the equal
protection of the laws; and (3) the Authority's and the City's disqualification of
Independent, and the Authority's resulting refusal to award it the Water Line
Contract, the Grandview Avenue Project, and the Sewer Improvement
Contract, deprived Independent of property without procedural and substantive
due process.
The district court dismissed all of Independent's federal claims. First, the court
dismissed the 1983 claims against the Authority on the ground that the
Authority is not a "person" within the meaning of 1983. The district court
then dismissed the civil contempt claim on the ground that Independent had not
been "debarred" from bidding on City or Authority contracts.
Turning to Independent's procedural due process claim, the district court held
With respect to the equal protection claim, the court held that Independent
lacked standing because the complaint failed to allege a causal connection
between the MBE/WBE requirements and the injury Independent had suffered
from the rejection of its bids.3
11
In Count I of its complaint, Independent alleges that the Authority and City are
in civil contempt of court because their disqualification of Independent pursuant
to the Sirabella memorandum and the Authority's resulting rejection of
Independent's three low bids violated the terms of the 1986 consent decree. The
district court dismissed the contempt claim because it found that the facts
alleged did not show a violation of the terms of the consent decree. We
disagree.
The 1986 consent decree provided in part:
16
(b) cooperate with consultants and officials of the City and Authority in regard
to problems that occur at the job site and administrative matters; and
17
(c) move quickly to resolve any disputes with adjoining property owners as a
App. at 138-39.
20
At the time the consent decree was entered, the Pittsburgh Code contained a
provision entitled "Debarment from Bidding On and Participating in City
Contracts." 161.22. This provision states that any person or enterprise that
had committed an "offense," as defined therein, will not be allowed to bid and
will not be "a responsible bidder on any city contract." "Offense" is defined in a
non-exclusive list to include sixteen different categories of conduct ranging
from fraud in connection with the obtaining or performance of a contract to the
following:
Pittsburgh Code 161.22(b). Debarments under this provision are to last for "a
reasonable, definitely stated period ... commensurate with the seriousness of the
cause therefore," but "as a general rule [are not to] exceed three years." Id.
161.22(d)(3). Debarment proceedings are initiated at the discretion of the
Mayor and the City's Director of the Department of General Services. The
stipulated process includes a notice to the contractor and a right to a hearing
before the Director at which the cause for the debarment has to be established
by a preponderance of the evidence.
26
In the context of these statutory provisions and the litigation that produced the
consent decree, the intent of paragraph 4 seems clear and unambiguous.
Independent was concerned about being foreclosed from doing City and
Authority work based on complaints about its conduct and contract
performance. In the interest of settling the pending lawsuit, the City was
willing to assure that there would be no foreclosure based on past conduct or
performance. While it and the Authority were not willing to give the same
assurance with respect to future contract performance, they were willing to
commit to hearing Independent's side of the story regarding any alleged
deficiency in its performance before foreclosing it from City and Authority
work. Independent would be able to give its side in a hearing to be held in
accordance with the Pennsylvania Local Agency Law. This reading of
paragraph 4 gives the word "disqualified" its commonly understood meaning.
"Disqualify," according to Webster, means "to deprive of a power, right or
privilege" or make "ineligible ... for further competition because of violations
of the rules," Webster's Ninth New Collegiate Dictionary 366 (1990); Black
defines "disqualify" as "to render ineligible." Black's Law Dictionary 472 (6th
ed. 1990).
28
Given this intent, we further think it clear that if Independent can prove its
allegations, it will have established a violation of paragraph 4 of the consent
decree. If the Sirabella directive, as alleged, resulted in Independent's not being
considered for City or Authority work for a period of time because of a cost
overrun on a contract entered after the consent decree, the failure to give
Independent a hearing on the overruns was a violation of paragraph 4.
29
In reaching its contrary conclusion, the district court reasoned that (1)
"debarred" in paragraph 2 was intended to include only disqualifications for
City work pursuant to the "formal procedure" spelled out in 161.22 of the
City Code; (2) "disqualify" in paragraph 4 is synonymous with the concept of
"debar" in paragraph 2; (3) there was no "formal procedure" under 161.22
conducted in connection with the Sirabella directive; and (4) therefore, there
was no disqualification of Independent and no need for a hearing. We believe
this approach leaves paragraphs 2 and 4 virtually without effect.
30
31
Giving the word "disqualify" and the phrase "because of problems with future
performances" in paragraph 4 their commonly understood meaning, we find
paragraph 4 broad enough to include a blanket foreclosure of Independent from
City or Authority work because of an overrun on a post-consent decree
contract. Moreover, it seems to us that the stated causes for debarment under
161.22 are broad enough to include such a foreclosure. Accordingly, our
conclusion would not be different even if we regarded the term "disqualify" in
paragraph 4 as limited by the use of "debarred" in paragraph 2.
Independent brought its equal protection and due process claims against the
City and Authority under 42 U.S.C. 1983, which provides that:
33
Every
person who, under color of any statute, ordinance, regulation, custom, or
usage, of any State ... subjects, or causes to be subjected, any citizen of the United
States or other person within the jurisdiction thereof to be deprived of any rights,
privileges, or immunities secured by the Constitution or laws, shall be liable to the
party injured in an action at law, suit in equity, or other proper proceeding for
redress.
34
42 U.S.C. 1983.
35
In support of its conclusion that the Authority "is not a 'person' within the
meaning of section 1983," Op. at 4, the district court cited Will v. Michigan
Department of State Police, 491 U.S. 58, 109 S.Ct. 2304, 105 L.Ed.2d 45
(1989). Will held that "neither a State nor its officials acting in their official
capacities are 'persons' under 1983." Id. at 71, 109 S.Ct. at 2312. We cannot
accept the district court's conclusion that Will compels a finding that the
Authority is not a "person" under 1983. Indeed, the limited record presently
available on the issue indicates that the Authority, in all likelihood, is a
"person" under 1983.6
36
37
In Will, the Court gave effect to the limitation expressed in Monell. Relying on
the ordinary meaning of the term "person," the legislative history of 1983,
and federalism concerns, the Court held that "neither a State nor its officials
acting in their official capacities are 'persons' under 1983." 491 U.S. at 71,
109 S.Ct. at 2312. The Will Court emphasized the continuing validity of
Monell, however, and limited Will 's holding "only to States or governmental
entities that are considered 'arms of the State' for Eleventh Amendment
purposes." Id. at 70, 109 S.Ct. at 2312.
38
The limitations that define the boundaries of the holdings in Monell and Will
establish that the most important inquiry in determining whether a
governmental entity is a "person" within the meaning of 1983 is whether the
entity is an " 'arm[ ] of the State' for Eleventh Amendment purposes." Id.; see
also Monell, 436 U.S. at 690 n. 54, 98 S.Ct. at 2035 n. 54. In Fitchik v. New
Jersey Transit Rail Operations, Inc., this court summarized the factors to be
considered in analyzing an entity's status as an "arm of the State" entitled to
Eleventh Amendment immunity:
39 Whether the money that would pay the judgment would come from the state (this
(1)
includes three ... factors--whether payment would come from the state's treasury,
whether the agency has the money to satisfy the judgment, and whether the
sovereign has immunized itself from responsibility for the agency's debts);
40 The status of the agency under state law (this includes four factors--how state law
(2)
treats the agency generally, whether the entity is separately incorporated, whether
the agency can sue or be sued in its own right, and whether it is immune from state
taxation); and
873 F.2d at 659 (summarizing more detailed list of factors set forth in Urbano
v. Board of Managers, 415 F.2d 247 (3d Cir.1969), cert. denied, 397 U.S. 948,
90 S.Ct. 967, 25 L.Ed.2d 128 (1970)). See also Bolden, 953 F.2d at 814-16.
43
We have repeatedly held that the most important factor in determining whether
an entity is an "arm of the State" for purposes of the Eleventh Amendment is
"whether any judgment would be paid from the state treasury." Fitchik, 873
F.2d at 659; see also Christy v. Pennsylvania Turnpike Comm'n, 54 F.3d 1140,
1145 (3d Cir.), cert. denied, --- U.S. ----, 116 S.Ct. 340, 133 L.Ed.2d 238
(1995); Bolden, 953 F.2d at 818; Urbano, 415 F.2d at 251. According to
Pennsylvania's Municipal Authorities Act of 1945 (the "MAA"), under which
the Authority is organized, the Authority "shall have no power ... to pledge the
credit or taxing power of the Commonwealth of Pennsylvania ..., nor shall any
of its obligations be deemed to be obligations of the Commonwealth ..., nor
shall the Commonwealth ... be liable for the payment of principal or interest on
such obligations." 53 P.S. 306(C). The MAA also grants the Authority the
power "[t]o fix, alter, charge and collect rates and other charges ... for the
purpose of providing for the payment of the expenses of the Authority, ... [and]
the payment of the principal and of interest on its obligations...." Id. 306(B)
(h). Because the Authority also has the power "[t]o sue and be sued," id.
306(B)(b), the "obligations" which the Authority will pay from the funds
collected through "rates and other charges" presumably include judgments.
Under these provisions, it appears that the Authority's funding does not come
primarily from the State, and that any judgment against the Authority would not
be "paid from the state treasury." This would weigh heavily against the
Authority's being considered "an arm of the State" for Eleventh Amendment
purposes.
44
The second factor, the Authority's status under state law, also appears to weigh
against a finding that the Authority is an "arm of the State," if less clearly. Like
SEPTA, which we held in Bolden is a "person" under 1983, 953 F.2d at 820,
the Authority appears to exhibit some attributes not characteristic of an arm of
the State and other attributes that are associated with the State. On the one
hand, a municipal authority is "a body politic and corporate," 53 P.S. 302,
with the power to sue and be sued. Id. 306(B)(b). In addition, municipal
agencies are not entitled to sovereign immunity from state tort actions under 42
Pa.C.S.A. 8521, but instead are "local agencies" entitled only to governmental
immunity under 42 Pa.C.S.A. 8541. See Miller v. McKeesport Mun. Water
Auth., 521 Pa. 77, 555 A.2d 790 (1989); E-Z Parks, Inc. v. Larson, 91
Pa.Cmwlth. 600, 498 A.2d 1364, 1369 (1985), aff'd per curiam, 509 Pa. 496,
On the other hand, municipal authorities have the power of eminent domain, 53
P.S. 306(B)(l ), and have been held to be "agencies of the Commonwealth"
independent from their incorporating municipality and not governed by laws
empowering local municipalities. Whitemarsh Township Auth. v. Elwert, 413
Pa. 329, 196 A.2d 843, 845-46 (1964); Forney v. State Ethics Comm'n, 56
Pa.Cmwlth. 539, 425 A.2d 66, 68 (1981); Highland Sewer & Water Auth. v.
Engelbach, 208 Pa.Super. 1, 220 A.2d 390, 392 (1966).
46
Like the first two, the third factor, the Authority's "degree of autonomy" from
the state, seems to weigh against a finding that the Authority is an "arm of the
State." The provisions of the MAA afford the Authority a high degree of
autonomy from the Commonwealth of Pennsylvania. For example, the
members of the Board--which exercises all of the Authority's powers--are
appointed not by the State but by the governing body of the City of Pittsburgh,
the incorporating municipality. 53 P.S. 309(A)(a). The Authority is granted
"all powers necessary or convenient" for carrying out its purposes, including,
inter alia, the power to sue and be sued, to purchase property, to make by-laws,
to appoint officers and define their duties, and to make contracts. Id. 306(B).
47
We have thus far discussed only the most significant inquiry identified by Will
and Monell, i.e., whether an entity is an "arm of the State" for Eleventh
Amendment purposes. Will also relied on two additional factors in reaching the
conclusion that a State is not a "person" within the meaning of 1983--(1) "the
language of Section 1983 and the meaning of the word 'person' " and (2) the
fact that "states enjoyed sovereign immunity from suit at common law, and ...
Section 1983 was not intended to override 'well established immunities or
defenses under common law.' " Bolden, 953 F.2d at 816. We note that neither
of these factors supports the district court's finding that the Authority is not a
"person" under 1983.
48
First, although the term "person" in common usage does not include the
"sovereign," Will, 491 U.S. at 64, 109 S.Ct. at 2308-09, the term does refer to
"bodies corporate and politic," meaning "corporations, both private and public
(municipal)." Id. at 70, 109 S.Ct. at 2311-12. Because the Authority is
expressly identified under the MAA as a "body politic and corporate," 53 P.S.
302, and appears to be the sort of "public corporation" that is included in the
"common usage" of the term "person," the linguistic rationale underlying Will
's exclusion of States from the "persons" suable under 1983 does not apply to
the Authority.
49
Second, the Will Court also recognized that "in enacting 1983, Congress did
not intend to override well-established immunities under the common law." 491
U.S. at 67, 109 S.Ct. at 2310. Therefore, because the sovereign immunity to
which States are entitled was a well-recognized principle of the common law at
the time 1983 was enacted, the Court was unwilling to extend 1983 liability
to States. Id. The Authority, however, cannot claim the same common law
immunity from suit historically enjoyed by States. In Owen v. City of
Independence, 445 U.S. 622, 646, 100 S.Ct. 1398, 1413, 63 L.Ed.2d 673
(1980), the Supreme Court noted that municipalities had lost their entitlement
to sovereign immunity by the end of the 19th century. In addition, Pennsylvania
courts have explicitly held that local municipal authorities such as a public
parking authority and a local redevelopment authority are not entitled to the
sovereign immunity enjoyed by the Commonwealth. See, e.g., Trustees of
Second Presbyterian Congregation v. Public Parking Auth. of Pittsburgh, 383
Pa. 383, 119 A.2d 79 (1956); Greer v. Metropolitan Hosp., 235 Pa.Super. 266,
341 A.2d 520, 528 (1975). Therefore, treating the Authority as a "person"
under 1983 would not override any common law immunity to which the
Authority is entitled.
50
Having concluded that it was error to dismiss the 1983 claims against the
Authority on the ground that it is not a "person," we now turn to Independent's
equal protection claim. It alleges that the Authority's MBE/WBE Utilization
Requirements, which were the asserted basis for the Authority's rejection of
Independent's bids for the Water Line Contract and Grandview Avenue Project,
discriminate against Independent and its owners on the basis of race, sex, or
national origin, thereby violating their right to equal protection. The district
court dismissed the claim for lack of standing because it found that
Independent "fail[ed] to allege facts that establish a causal relationship between
the injury--its rejected bids--and the challenged conduct--the minority
utilization requirement." Op. at 11. It reached this conclusion by focusing on
those portions of the complaint alleging that Independent had submitted bids in
compliance with the utilization requirements and that those bids were rejected
because of the Sirabella memorandum.
52
53
54party may set forth two or more statements of a claim or defense alternatively or
A
hypothetically, either in one count or defense or in separate counts or defenses.... A
party may also state as many separate claims or defenses as the party has, regardless
of consistency....
55
This Rule permits inconsistency in both legal and factual allegations, see, e.g.,
Babcock & Wilcox Co. v. Parsons Corp., 430 F.2d 531, 536 (8th Cir.1970);
Dugan v. Bell Telephone of Pa., 876 F.Supp. 713, 722 (W.D.Pa.1994); 5
Wright & Miller, Federal Practice & Procedure 1283, at 533 (1990), and has
been interpreted to mean that a court "may not construe [a plaintiff's] first claim
as an admission against another alternative or inconsistent claim." Henry v.
Daytop Village, 42 F.3d 89, 95 (2d Cir.1994); Molsbergen v. United States, 757
F.2d 1016, 1019 (9th Cir.), cert. dismissed, 473 U.S. 934, 106 S.Ct. 30, 87
L.Ed.2d 706 (1985). This is especially the case in circumstances in which
proving the plaintiff's alternative claims may require "complex inquiries into
the parties' intent." Henry, 42 F.3d at 95.
56
The district court here failed to afford Independent the privilege of asserting
alternative and inconsistent claims. Independent's complaint alleges, inter alia,
two inconsistent claims: First, Independent claims that the Authority and the
City disqualified it from Authority work, per the instruction in the Sirabella
memorandum, in violation of the 1986 consent decree. In connection with this
claim, Independent claims that the Authority's asserted reason for rejecting it's
Water Line and Grandview Avenue bids, i.e., the alleged failure to comply with
the MBE/WBE requirements, was a pretext intended to mask the Authority's
Independent's equal protection claim does allege facts satisfying all of the
requirements of standing. The complaint alleges an injury in fact (the rejection
of Independent's bids); causation (that the rejection resulted, according to the
Authority, from Independent's inability to meet satisfactorily the Authority's
MBE/WBE Utilization Requirements)7 ; and redressability (that the injury can
be remedied through the award of the contracts or damages and an injunction
against future enforcement of the Utilization Requirements).
58
Turning from standing to the issue of whether Independent has stated a claim
on which relief could be granted, we conclude that it has. Independent's
complaint alleges that the Authority has established MBE/WBE Utilization
Requirements which require that all bidders on certain contracts provide with
their bids a "utilization plan" that identifies the portion of work under the
contract that will be subcontracted to "certified" minority- or women-owned
firms. According to the complaint, bids that do not meet the MBE/WBE
utilization goals are rejected. Finally, the complaint alleges that the MBE/WBE
Utilization Requirements were not established to remedy past discrimination or
passive participation in discrimination by the City or Authority against
minority- or women-owned construction companies. These allegations support
an equal protection claim under City of Richmond v. J.A. Croson Co., 488 U.S.
469, 109 S.Ct. 706, 102 L.Ed.2d 854 (1989), in which the Supreme Court held
that a race-based MBE utilization program was unconstitutional because it was
not narrowly tailored to remedy specific discrimination or "passive
participation" in discrimination by the enacting government unit.8 See also
Contractors Ass'n of Eastern Pa., Inc. v. City of Phila., 91 F.3d 586, 596 (3d
Cir.1996).9 C. The Due Process Claims
59
an injunction barring the Authority from awarding the three contracts to anyone
other than Independent, an injunction barring the City and the Authority from
refusing to consider Independent a competent bidder on future City contracts,
and an award of compensatory and punitive damages. We will affirm the
district court's dismissal of Independent's substantive and procedural due
process claims, albeit for a reason different from that given by the district
court.
60
The district court dismissed Independent's procedural due process claim on the
ground that Pennsylvania law provided a post-deprivation remedy that afforded
all the "due process" required by the Fourteenth Amendment. According to the
district court, the post-deprivation remedy, of which Independent had attempted
to avail itself, consisted of "a judicial procedure for unsuccessful bidders to
challenge whether a local contracting authority has violated a bidder's rights
under the Municipal Authority Act." Op. at 7-8. The district court apparently
reached this conclusion based on a statement in the Authority's Motion to
Dismiss that there was a pending state action between the parties. On appeal,
however, the parties agree that Pennsylvania law in fact provides no such
procedure. Nonetheless, the Authority and the City argue that the district
court's dismissal of Independent's procedural due process claim should be
affirmed on the alternative ground that their actions did not deprive Independent
of any property interest protected by the due process clause.
61
62 have a property interest in a benefit, a person clearly must have more than an
"To
abstract need or desire for it. He must have more than a unilateral expectation of it.
He must, instead, have a legitimate claim of entitlement to it."
63
Id. at 577, 92 S.Ct. at 2709 (emphasis added). Finally, the Court identified the
sources to which courts should look to determine a plaintiff's "entitlement" to a
claimed property interest. Property interests, the Court declared, "are created
and their dimensions are defined by existing rules or understandings that stem
from an independent source such as state law." Id.
64
According to the teachings of Roth, therefore, Independent may not pursue its
procedural due process claims against the City and Authority unless "an
independent source such as state law" affords it a "legitimate claim of
entitlement" to be awarded a municipal contract for which it was the lowest
responsible bidder. Independent relies only on state competitive bidding law as
the "independent source" providing its "legitimate claim of entitlement."10
65
66
These Pennsylvania cases demonstrate that one who bids on a public contract
has no legitimate expectation of receiving it until the contract is actually
awarded. See Highway Express Lines v. Winter, 414 Pa. 340, 200 A.2d 300,
303 (1964) ("By their bid [the unsuccessful bidders] proposed to contract for
certain work; that bid was not accepted. It was a mere proposal that bound
neither party, and as it was never consummated by a contract, the city acquired
no right against the [bidders] nor they against the city."). Since Independent's
bids were never accepted, it never acquired an enforceable right with respect to
the contract being awarded. It, therefore, has not been deprived of a property
interest that warrants procedural due process protection.
67
As Independent stresses, the law of this circuit recognizes that "an entitlement
may exist for a benefit sought but not yet obtained if state law limits the
exercise of discretion by the state official responsible for conferring the
benefit." Midnight Sessions, Ltd. v. City of Phila., 945 F.2d 667, 679 (3d
Cir.1991) (citing Winsett v. McGinnes, 617 F.2d 996, 1007 (3d Cir.1980) (in
banc), cert. denied, 449 U.S. 1093, 101 S.Ct. 891, 66 L.Ed.2d 822 (1981)).
Relying on this authority, Independent urges that the limitations placed on the
Authority's discretion by the competitive bidding laws rendered Independent
"entitled" to receive the contracts for which it was the low bidder as soon as it
submitted its low bids and the Authority decided to award the contracts.
Midnight Sessions and Winsett are inapposite here, however. Midnight
Sessions involved the deprivation of a portion of a property owner's interest in
the use of his real property. Winsett involved prison regulations that mandated
work release for an inmate when he satisfied certain criteria. We held that state
regulations conferred on the inmate a legally enforceable right to work release.
As a result, the inmate had a liberty interest that warranted due process
protection. Here, however, under Pennsylvania law Independent clearly had no
legally enforceable interest in receiving the contracts and thus had no
"entitlement" to the benefit sought.
68
70
We will leave for another day definition of the precise contours of the
"particular quality of property interest" entitled to substantive due process
protection. We have no difficulty in concluding that the property interest
alleged to have been infringed here, which we have concluded is not entitled to
procedural due process protection, is not the sort of "fundamental" interest
entitled to the protection of substantive due process. Accordingly, we conclude
that Independent has failed to state either a procedural due process claim or a
substantive due process claim upon which relief can be granted.
IV. Conclusion
71
We will reverse the judgment of the district court and remand for further
proceedings consistent with this opinion.
Hon. Paul R. Michel, United States Circuit Judge for the Federal Circuit, sitting
by designation
The district court, having dismissed the federal claims, declined to exercise
supplemental jurisdiction over Independent's state claims and dismissed them
without prejudice. It may reconsider that decision on remand in light of our
disposition of the federal claims
In its opinion, the district court commented that, even assuming there had been
a violation of the consent decree, the appropriate remedy would have been to
file an application in the earlier suit. In response to the district court's
suggestion, Independent stresses that the judge who presided over the former
civil action had retired before the present action was commenced. Therefore,
Independent argues, nothing should preclude it from including the contempt of
court claim with its other claims against Appellees, and indeed that "[t]he
assertion of all claims in one action serves the interests of judicial economy of
resources. Moreover, even if the civil action was required to be brought at the
old docket number, the proper action would be to transfer the matter rather than
dismissal [sic]." Appellant's Brief at 21 n. 6. We agree that Independent should
not be precluded from pursuing its contempt claim merely because it, for
apparently logical reasons, failed to file that claim under the docket number
under which the consent decree was entered
At oral argument, counsel for the Authority informed us that the Authority had
not argued before the district court that it was not a "person" under 1983.
Counsel further candidly acknowledged that she could cite no case in which a
public entity had been held not to be a "person" on the basis of a record similar
to the one before us. Counsel stopped short of conceding, however, that the
Authority is a "person" under 1983. As a result, the district court, on remand,
will have to determine whether the Authority is a "person." This will require it
to afford the parties the opportunity to develop a record and to then weigh, with
the assistance of the parties, the factors identified by this court in Fitchik v.
New Jersey Transit Rail Operations, Inc., 873 F.2d 655 (3d Cir.) (in banc), cert.
denied, 493 U.S. 850, 110 S.Ct. 148, 107 L.Ed.2d 107 (1989), and Bolden v.
Southeastern Pennsylvania Transportation Authority, 953 F.2d 807 (3d
Cir.1991) (in banc), cert. denied, 504 U.S. 943, 112 S.Ct. 2281, 119 L.Ed.2d
206 (1992)
The Authority argues that Independent's allegation that its bids were rejected
"ostensibly" because of its failure to satisfy the MBE/WBE requirements does
not constitute an "affirmative allegation" that Independent was precluded from
getting the contracts because of the allegedly discriminatory requirements.
However, reading the complaint as a whole and clarifying any ambiguities in
Independent's favor, it is clear that Independent "affirmatively alleged" that the
Authority rejected Independent's bids on the ground that Independent did not
satisfy the MBE/WBE requirements. In accordance with Rule 8(e)(2), if that
ground was a pretense for the Authority's impermissible disqualification of
Independent from the bidding process, Independent should be allowed to
pursue its civil contempt claim. On the other hand, if failure to satisfy the
MBE/WBE requirements was the actual ground for the Authority's rejection of
the bids, Independent should be allowed to pursue its claim that rejection on
such grounds violates its right to equal protection
Statement that must be submitted with each bid "itself does not require the use
of minority or women subcontractors but merely requests information regarding
the percentage of such subcontractors that the bidder intends to use on the
project," and thus "does not create a discriminatory set-aside or quota program"
but "serves merely to identify and guard against discrimination." Appellees'
Brief at 16-17 (emphasis added). We agree with Independent that this assertion
of the facial validity of the Authority's MBE/WBE policy "is an argument on
the merits inappropriate at the Rule 12(b)(6) motion to dismiss stage."
Appellant's Reply Brief at 12. At this stage in the proceedings, particularly in
light of the Authority Resolutions that expressly rejected Independent's Water
Line and Grandview Avenue bids "for failure to meet the MBE/WBE
requirements," Auth.Res. 67 & 68, App. at 197-98 (emphasis added),
"Independent's allegation that the [Authority] rejects bids which do not meet
the MBE/WBE goals must be taken as true, and forecloses [the Authority's]
assertion that they are not requirements but merely informational." Appellant's
Reply Brief at 12 (citations omitted)
10
At oral argument, Independent's counsel suggested for the first time that
paragraph 4 of the consent decree may have created a property interest for
Independent. This suggestion mistakes a right to a particular process for a
substantive right in a contract. The right to a particular process does not alone
create a property interest. Olim v. Wakinekona, 461 U.S. 238, 250, 103 S.Ct.
1741, 1748, 75 L.Ed.2d 813 (1983). Paragraph 4 gives Independent only a right
to a particular kind of hearing; it does not give Independent any more legitimate
expectation of receiving a contract than it has without this portion of the
consent decree
11
Although the Pennsylvania Supreme Court has dealt only with challenges
brought under the bidding statutes themselves, the Pennsylvania
Commonwealth Court recently directly addressed the issue of the applicability
of the R.S. Noonan standing principle to a due process challenge to the
rejection of a low bid. J.P. Mascaro & Sons, Inc. v. Township of Bristol, 95
Pa.Cmwlth. 376, 505 A.2d 1071 (1986). There, the court concluded that a
disappointed bidder "has no standing to assert violations of its due process
rights under either the federal or state constitutions as it has no legitimate claim
of entitlement to the [municipality's] contract." Id. 505 A.2d at 1074. The
United States District Court for the Eastern District of Pennsylvania reached
the same conclusion in ARA Servs., Inc. v. School District of Phila., 590
F.Supp. 622, 629 (E.D.Pa.1984), and J.P. Mascaro & Sons, Inc. v. Township of
Bristol, 497 F.Supp. 625, 627 (E.D.Pa.1980). A line of cases from the Western
District of Pennsylvania reached a contrary conclusion. E.g., Teleprompter of
Erie, Inc. v. City of Erie, 537 F.Supp. 6, 10-11 (W.D.Pa.1981) and 567 F.Supp.
1277, 1289 (W.D.Pa.1983); Three Rivers Cablevision, Inc. v. City of
Although Bello and Midnight Sessions both contained language indicating that
substantive due process is violated whenever a governmental entity deliberately
or arbitrarily abuses government power by, for example, taking actions that are
motivated by bias, bad faith, or partisan or personal motives unrelated to the
merits of the matter before it, Midnight Sessions, 945 F.2d at 683; Bello, 840
F.2d at 1129; see also Blanche Rd. Corp. v. Bensalem Township, 57 F.3d 253,
267-68 (3d Cir.), cert. denied, --- U.S. ----, 116 S.Ct. 303, 133 L.Ed.2d 208
(1995); Neiderhiser v. Borough of Berwick, 840 F.2d 213, 217 (3d Cir.), cert.
denied, 488 U.S. 822, 109 S.Ct. 67, 102 L.Ed.2d 44 (1988), we do not read the
cases to stand for that broad principle. The court in Midnight Sessions
expressly stated that it was assuming, without deciding, that the plaintiffs were
entitled to substantive due process in the consideration of their applications for
dance hall licenses. 945 F.2d at 682 n. 11. Moreover, all of the cases involved
zoning decisions, building permits, or other governmental permission required
for some intended use of land owned by the plaintiffs, matters which were
recognized in DeBlasio as implicating the "fundamental" property interest in
the ownership of land. 53 F.3d at 600. Thus, in light of the court's explicit
statement in DeBlasio that some "particular quality of property interest" must
be infringed before substantive due process protection may be invoked, id. at
600, these cases cannot be understood as affording substantive due process
protection from every arbitrary and irrational governmental act, but only for
those that deprive the plaintiff of a fundamental property right "implicitly
protected by the Constitution." Id. at 599; see also Blanche Rd., 57 F.3d at 268
(plaintiffs stated a substantive due process claim because they claimed that
defendants "acted deliberately and under color of state law to deprive them of
their property rights by interfering in and delaying the issuance of permits")
(emphasis added); Neiderhiser, 840 F.2d at 218 ("[I]f [plaintiff] can
successfully demonstrate that the [town] arbitrarily and irrationally denied the
[zoning] exemption, visiting a constitutional deprivation on [plaintiff], then
[plaintiff] may prevail on its due process claim.") (emphasis added)