United States Court of Appeals, Fourth Circuit
United States Court of Appeals, Fourth Circuit
2d 254
22 Envtl. L. Rep. 20,566
* James City County lies next to the City of Williamsburg on the York-James
Peninsula. Although the County contains no large cities, it is the second fastest
growing county in Virginia and has many summer visitors. In 1981, the County
had approximately 24,000 residents. By 1987, the County's population had
grown to approximately 31,000 residents. Projections indicate that, by the year
2030, the County's population will grow to over 50,000.
The County's current population consumes 9.3 million gallons of water per day
("mgd") provided from three sources. The City of Newport News sells 5.4 mgd
to residents in part of the County, groundwater wells within the County provide
3.6 mgd, and the remaining 0.3 mgd is purchased from the City of
Williamsburg. The EPA, the Corps, and the County have accepted that, based
on the County's projected future population, the County's water requirements
for the year 2030 will be 18.2 mgd.
Several factors limit the County's ability to satisfy its increasing need for water
with its current sources. Williamsburg refuses to supply water to the County
after 1999. In addition, Newport News will not expand delivery beyond 7.7
mgd. The County also claims that its supply of groundwater is unreliable. It
contends that levels of groundwater are falling, that the County's groundwater
contains impurities in violation of the EPA standards under the Federal Safe
Drinking Water Act, and that the groundwater has been called "adverse to
public health, welfare, and safety" by the Virginia State Water Control Board
(the "SWCB"). The County therefore contends that it must develop a new
source of water which could supply 10.5 mgd, the amount of the County's
projected demand in excess of the 7.7 mgd Newport News would supply.
5
After various water supply studies by federal, state, and private organizations,
the County decided that the best way to meet the projected excess demand was
to construct a reservoir by building a dam in Ware Creek. The resulting lake
would extend into adjacent New Kent County, flooding 425 acres of wetlands,
and would reliably yield approximately 9.4 mgd of water. This reservoir could
also be connected to the Newport News water system. Because of the steep
topography of the proposed reservoir site, connection with Newport News
could double the reservoir's yield without inundating additional wetlands.
Before construction of the reservoir could begin, however, the County was
required to first obtain a permit to place fill for the dam. See 33 U.S.C.
1311(a). As developed in greater detail below, the Clean Water Act gives the
Army Corps of Engineers primary responsibility for evaluating the County's
application and issuing the appropriate permit, see Clean Water Act 404(a),
33 U.S.C. 1344(a), although the Act also authorizes the EPA to veto the
Corps' decision under certain circumstances. See Clean Water Act 404(c), 33
U.S.C. 1344(c).
In 1984, the County formally applied to the Corps for a permit to place fill to
construct the dam. The Corps, the United States Fish and Wildlife Service, the
National Marine Fisheries Service, and the EPA jointly completed an
Environmental Impact Statement in September 1987, and the Corps
subsequently issued a notice of intent to issue the permit on July 11, 1988. The
EPA's Regional Administrator then reviewed the Corps' decision.1 After further
hearings, comments, and consultations with the Corps, the Regional
Administrator recommended on February 17, 1989, that the EPA veto the
Corps' decision. This recommendation was referred to the national EPA
Administrator in Washington, D.C., where, on July 10, 1989, the EPA's
Assistant Administrator for Water issued the EPA's Final Determination,
vetoing the Corps' decision to issue the permit.
The County then filed suit against the EPA and the Corps in the Eastern District
of Virginia, challenging the EPA's veto. On November 6, 1990, the district
court granted summary judgment to the County. The court overturned the
EPA's veto, ordered the Corps to issue the permit, and denied the EPA's request
for a remand to the EPA for further proceedings. The EPA subsequently filed
this appeal.
The complex statutory and regulatory scheme involved here requires some
preliminary discussion. Section 404(a) of the Clean Water Act gives the Army
Corps of Engineers primary responsibility for issuing the permit required by the
County. It states that "The Secretary [of the Army, acting through the Corps of
Engineers,] may issue permits, after notice and opportunity for public
hearings[,] for the discharge of dredged or fill material into the navigable
waters at specified disposal sites." 33 U.S.C. 1344(a).
10
While the Clean Water Act contains no particular provision detailing the
standards to be used by the Corps in determining whether to issue a permit, it
contains instructions for the Corps to follow in "specifying" sites where
dredged or fill material may be placed. Section 404(b) of the Clean Water Act
states:
11
Subject to subsection (c) of this section, each such disposal site shall be
specified for each such permit by the Secretary
33 U.S.C. 1344(b).
14
Pursuant to this mandate, the EPA and the Corps have jointly issued guidelines
to be followed by both agencies in making their respective determinations under
section 404. See 40 C.F.R. 230 (1991). These guidelines state that a permit
should not be issued if: (1) practicable, environmentally superior alternatives
are available, (2) the discharge would result in a violation of various
environmental laws, (3) the discharge would result in significant degradation to
the waters of the United States, or (4) appropriate and practicable steps have
not been taken to minimize potential adverse impacts of the proposed
discharge. 40 C.F.R. 230.10(a)-(d).
15
In deciding to issue the permit, the Corps found that the project did not violate
any of these provisions. It found specifically that there were no practicable,
environmentally superior alternatives to the Ware Creek Reservoir. It also
found that the proposed reservoir would not cause or contribute to violations of
water quality or toxic effluent standards, that it would not affect any threatened
or endangered species or marine sanctuaries, that the project would not cause or
contribute to significant degradation of waters of the United States, and that the
County had made all appropriate and practicable efforts to minimize potential
adverse effects.
16
As noted above, however, approval by the Corps is not the end of the permit
process. Section 404(c) of the statute authorizes the EPA to veto a Corps'
decision to issue a permit when the EPA Administrator "determines, after
notice and opportunity for public hearings, that the discharge of such materials
into such area will have an unacceptable adverse effect on municipal water
supplies, shellfish beds and fishery areas (including spawning and breeding
areas), wildlife, or recreational areas." 33 U.S.C. 1344(c) (emphasis added). It
requires the Administrator to consult with the Corps before making a final
determination and to "set forth in writing and make public his findings and his
reasons for making any determination under this subsection." Id.
17
In the regulations the EPA has issued to govern its veto determinations,
"unacceptable adverse effect" is defined as an "impact on an aquatic or wetland
ecosystem which is likely to result in significant degradation of municipal water
supplies (including surface or ground water) or significant loss of or damage to
fisheries, shellfishing, or wildlife habitat or recreation areas." 40 C.F.R.
231.2(e). This regulation also provides that, "In evaluating the unacceptability
of such impacts, consideration should be given to the relevant portions of the
section 404(b)(1) guidelines...." Id.
18
The Regional Administrator conducts the first step in the EPA veto process.
After the Corps published its notice of intent to issue the permit, the Regional
Administrator in this case issued a Proposed Determination which would veto
the Corps' decision. After holding a hearing, the Regional Administrator issued
a Recommended Determination that the EPA veto the Corps' decision. The
decision included findings that viable alternative water supplies were available
to the County. These alternatives included a possible pipeline to the County
from the James River, conservation, use of additional groundwater (including
desalinized groundwater), and the construction of three smaller dams on a
different site on Ware Creek.2
19
20
would
result in a severe direct and cumulative loss of wildlife habitat and would
result in serious impacts to and/or losses of involved wildlife species. In addition, the
record reveals that there are practicable, less environmentally damaging alternatives
that are available to James City County that would provide sufficient water supplies
for its projected local needs. EPA therefore concludes that construction of the
proposed Ware Creek impoundment would result in unacceptable adverse effects to
wildlife.
21
22
23
After the EPA issued its Final Determination, the County brought this action in
the district court under 5 U.S.C. 702, as well as 28 U.S.C. 1331 and 2201,
seeking to overturn the EPA's action. The district court granted summary
judgment to the County, finding that the County had no practicable alternatives
to the construction of the Ware Creek Reservoir and that the EPA had
incorrectly presumed that alternatives existed. After holding that the EPA's veto
was improper, the district court ordered the Corps to issue the permit and
rejected the EPA's request for a remand.
II
24
While the EPA does not abandon its challenge to the district court's finding that
the County had no practicable alternatives to the construction of the dam, its
primary claim on appeal is that the district court should have remanded the
case to the EPA in order to provide the EPA with an opportunity to consider
whether the project's environmental effects alone justified a veto. The EPA also
We first consider whether the district court properly concluded that there were
no practicable alternatives to the proposed reservoir. We find no error in that
decision of the district court. However, because we do not believe that the EPA
has in fact decided not to veto the permit even in the absence of practicable
alternatives, we find that the district court should have remanded this issue to
the EPA for its further consideration.
26
* In our review of the district court's conclusion that there were no practicable
alternatives, we are guided by the same standards that controlled the district
court's evaluation of the EPA's Final Determination. The Administrative
Procedures Act provides that when a court reviews an administrative agency's
action on the record of a hearing provided by statute, that action can only be set
aside if it is "unsupported by substantial evidence." 5 U.S.C. 706(2)(E).5
Since, in our view, the EPA's finding that the County had practicable alternative
water sources was not supported by substantial evidence, we affirm the district
court's holding in this respect.
27
28
Except
as provided under section 404(b)(2), no discharge of dredged or fill material
shall be permitted if there is a practicable alternative to the proposed discharge
which would have less adverse impact on the aquatic ecosystem, so long as the
alternative does not have other significant adverse environmental consequences.
29
30
The three dam project is the primary alternative suggested by the EPA in its
Final Determination. As the EPA recognized, however, part of the three dam
project would be built in New Kent County. The record demonstrates that New
Kent County categorically opposes the project and will not consent to its
construction. Moreover, the three dam project also requires a section 404
permit, but the EPA did not find that the County could obtain a permit for the
project. In fact, various statements by the EPA in the record indicate that the
EPA itself would likely veto a permit for the three dam project. Finally, water
from the three dam project would cost fifty percent more than water from the
proposed reservoir. We are persuaded, therefore, that the three dam project is
not a practicable alternative for the County.
31
32
33
34
Despite uncontroverted evidence to the contrary, the EPA found that the
County had practicable water supply alternatives. We conclude that, giving the
appropriate deference to the agency, there was not substantial evidence to
support the EPA's conclusion that the County had practicable alternatives.6
Since we feel that the record makes this conclusion unavoidable, on remand the
EPA will not be permitted to revisit this issue.
B
35
The County concedes, as it must, that remands are generally appropriate when a
court finds that the stated basis for an agency's action is inadequate. See
Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council,
435 U.S. 519, 524-25, 98 S.Ct. 1197, 1202, 55 L.Ed.2d 460 (1978). It argues,
however, that a remand is not appropriate in this case for several reasons.
36
36
37
The County also contends that the EPA's veto rights under the statute provide
merely a single "opportunity" to veto, which, when exercised improperly, is
waived. While theoretically Congress could create a scheme providing an
agency with only one opportunity to make such a determination, we do not
discern a congressional intent to implant that radical procedure in section
404(c). Accordingly, we reject the argument that the EPA has waived its right
to veto the permit based on adverse effects alone.
38
Finally, the County argues that the EPA's delay in acting, as well as the
prejudice the County will suffer as a result of a remand and further delay,
justify the decision of the district court not to remand. We recognize that when
Congress enacted section 404, it was concerned about the possibility of
harmful delays in permit and veto decisions. See 118 Cong. Rec. 533699
(remarks of Sen. Muskie) ("The Conferees expect the Administrator to be
expeditious in his determinations as to whether a site is acceptable...."). In this
context, our decision to remand was heavily influenced by the unequivocal
representation of the EPA's counsel at oral argument that the EPA could
complete its determination on remand within sixty days of our decision. We
would view seriously any failure to comply with that representation.
39
In view of the above, the judgment of the district court is affirmed in part. The
case is, however, remanded to the district court for further remand to the EPA
for action consistent with the views expressed in this opinion.
40
For procedures established and followed by EPA in making its section 404(c)
determinations, see 40 C.F.R. 231
Although the EPA vetoed the permit, the Final Determination only vetoed the
project as a local water supply source. The EPA apparently reserved the right to
permit the reservoir as a regional water source
In our view, this is the proper standard of review for the EPA's section 404(c)
determination, in light of the statutory requirements of notice and opportunity
for public hearings, as well as the requirement that "The Administrator shall set
forth in writing and make public his findings and his reasons for making any
determination under this subsection." 33 U.S.C. 1344(c). But see Bersani v.
Robichaud, 850 F.2d 36, 46 (2d Cir.1988), cert. denied, 489 U.S. 1089, 109
S.Ct. 1556, 103 L.Ed.2d 859 (1989) (reviewing a section 404(c) veto decision
by the EPA under the arbitrary and capricious standard). Even were we to
review EPA's action under the "arbitrary and capricious" standard, however, we
would reach the same conclusions that we reach herein
The district court concluded that EPA had relied upon a presumption that
practicable alternatives exist because of a mistaken belief that the proposed
reservoir would "not require access or proximity to or siting within the special
aquatic site in question to fulfill its basic purpose (i.e., is not 'water
dependent')...." 40 C.F.R. 230.10(a)(3). After reviewing the EPA's Final
Determination, we are not persuaded that EPA applied the presumption in this
case. While parts of the Final Determination seem to require the County to
prove that alternatives are not available, EPA makes its findings without
explicitly invoking the presumption. Moreover, like the district court, we are
persuaded that this project is water dependent, and conclude that the
presumption does not apply