d. A and C
13. Projects and operation differs in that projects are ongoing and produce repetitive products, services
or results
a. True
b. False (PMBOK 4th edition Page 22, Chapter 2, 2.2)
14. Which of the following stakeholders interest is best served by impeding the project (choose the
best answer)?
a. An assembly-line worker whose future employment depends on the outcome of a new
product design
b. A positive stakeholder
c. A business leader from a community that will benefit from an industrial expansion project
by positive economic benefit
d. A negative stakeholder (PMBOK 4th edition Page 24, Chapter 2, 2.3)
15. Which of the following organizational process asset belongs to the processes and procedure
category
a. Historical information and lesson learned
b. Database containing labor hours, incurred cost, budget and any project cost overruns
c. Templates (e.g. risk, work breakdown structure, network diagrams) (PMBOK 4th edition
Page 32, Chapter 2, 2.4.3)
d. Project files (e.g. scope, cost, schedule and performance measurement baselines)
16. Which of the following is considered to be an organizational cultural norm?
a. Work ethics work hours and view of authority relationships.
b. Shared vision, values, norms, beliefs and expectations
c. Policies, methods and procedures
d. All of the above (PMBOK 4th edition Page 27, Chapter 2, 2.4.1)
17. On a construction project, after completion of the foundation a building inspector reviews the
foundation to determine if it satisfies building codes. After the inspector approves the installation of
the foundation, the contractors begin framing the structure. After framing is complete, the inspector
reviews the frame of the building to ensure it meets all guidelines. Which of the following phase
relationship type does this represent? (choose the best answer)
a. Iterative relationship
b. Overlapping relationship
c. Phase to phase relationship (PMBOK 4th edition Page 21-22, Chapter 2, 2.1.3)
d. Sequential relationship