Lva1 App6892
Lva1 App6892
Team 10
Team 10
Javier Leyva Rico - 4415027 - +31617370757
Agnes van Endhoven - 4174933 - +31627117687
Ameya Thakurdesai - 4411153 - +31617327604
Toon Nieboer - 4114965 - +31641317731
Design Project
in Chemical Engineering
Technical advisor:
Creativity Coach:
Principals:
Dr. P. Hamersma,
Prof. dr. B. Dam,
Ir. A. Didden,
Ir. A. Malhotra,
TU Delft
TU Delft
Frames Group
Frames Group
Preface
For the conceptual design project of the master Chemical Engineering we, a group of four students,
have been put together to work on an assignment for M/s Frames. The main purpose of the project is
to decrease the size and costs of an offshore TEG gas dehydration unit, a widely used technique for gas
dehydration. This has been done by adding new technologies from industry. For the past 10 weeks,
literature studies were performed, contacts with professors and companies have been made and many
simulations and calculations were done.
After a study, some thorough & some brief, out of nine different technologies three were chosen to
be added to the conventional process in order to try to decrease the CAPEX, OPEX and weight of the
unit. Pervoparation membranes, a liquid turbochargers and injection of semi-lean TEG were included.
The conventionally used process has been simulated to set a benchmark and the impact of all
different techniques has been calculated. Thereafter the hybrid process was simulated. This resulted
in a reduction of OPEX of 70,000 per year, but also an increase of 15 million , which means the
CAPEX has doubled. The weight of the unit stayed more or less the same as is shown in the report.
In the end it is concluded that the addition of liquid turbochargers has a positive effect on the total
energy needed for the TEG transport throughout the plant. A reduction of 70% of energy consumption
is achieved. The pervaporation membranes decrease the energy needed for reboiling but turn out to
be very costly in capital expenses. As of now it is not yet beneficial to add these membranes as the
rate of return is too low. It is expected that after more research the price of these membranes can
drop however, as a larger surface area per unit can be achieved. This will cut down the capital costs of
the membranes and make them a viable option in the future. The addition of semi-lean TEG injection
proved a useful addition. It resulted in a size reduction of the still column, reboiler and surge vessel. To
implement this technology in the conventional process however the design of the still column needs to
be altered or the distillation needs to be done in two steps in order to provide a semi-lean TEG stream
to return to the contactor (absorption tower).
Team 10: Javier Leyva, Ameya Thakurdesai, Agnes van Endhoven & Toon Nieboer
Delft, June 2015
iii
Contents
1 Introduction and Project Charter
1.1 Background . . . . . . . . . . . . . . . . . . . . . . .
1.2 Objectives . . . . . . . . . . . . . . . . . . . . . . . .
1.3 Concept Stage. . . . . . . . . . . . . . . . . . . . . .
1.3.1 Process synthesis. . . . . . . . . . . . . . . .
1.3.2 Requirements . . . . . . . . . . . . . . . . . .
1.3.3 Plant capacity and location . . . . . . . . . .
1.4 Database. . . . . . . . . . . . . . . . . . . . . . . . .
1.4.1 Component list . . . . . . . . . . . . . . . . .
1.4.2 Component and thermodynamic properties
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
1
1
2
3
3
3
4
5
5
5
2 Conventional Process
2.1 Process description. . . . . . . . . . . . . . . . .
2.1.1 Contactor (C101) . . . . . . . . . . . . . .
2.1.2 Flash (V201) . . . . . . . . . . . . . . . . .
2.1.3 Filters (S201) . . . . . . . . . . . . . . . .
2.1.4 Reboiler (V202) & Still column (C201) .
2.1.5 Stripping column (C202) . . . . . . . . .
2.1.6 Surge (V203) . . . . . . . . . . . . . . . .
2.2 Mass and energy balance . . . . . . . . . . . . .
2.2.1 Simulation on Aspen Hysys. . . . . . . .
2.3 Equipment sizing . . . . . . . . . . . . . . . . . .
2.4 Total weight . . . . . . . . . . . . . . . . . . . . .
2.5 Health, Safety & Environment . . . . . . . . . .
2.5.1 Preliminary study of risks. . . . . . . . .
2.5.2 Dows Fire and Explosion Index (F&EI) .
2.5.3 Waste . . . . . . . . . . . . . . . . . . . . .
2.6 Bottlenecks and possible improvements . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
7
7
8
9
9
9
9
10
10
10
11
12
13
13
14
17
17
.
.
.
.
.
.
.
.
.
.
.
.
.
19
19
19
19
20
21
21
22
23
23
23
24
25
28
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
3 Innovation Map
3.1 Description of alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.1 Improved TEG injection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.2 Microwave heating . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.3 Super-X packing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.4 Liquid turbochargers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.5 Pervaporation membranes . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.6 Molecular sieves + TEG unit . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.7 Addition of entrainer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.8 Vacuum operation in still column . . . . . . . . . . . . . . . . . . . . . . . .
3.1.9 Rotating packed beds (HiGee) . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2 Selection of alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.1 Turbochargers and split-flow injection . . . . . . . . . . . . . . . . . . . . .
3.2.2 Alternative 1: Process scheme with microwave heating . . . . . . . . . . .
3.2.3 Alternative 2: Process scheme with pervaporation membranes and semi
lean injection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.4 Alternative 3: Process scheme with hybrid system . . . . . . . . . . . . . .
3.3 Selection of the optimized process scheme . . . . . . . . . . . . . . . . . . . . . . .
v
. 30
. 38
. 39
vi
Contents
4 Hybrid Process
4.1 Process description. . . . . . . . . . . . . . . . .
4.2 Material and energy balance . . . . . . . . . . .
4.2.1 Energy demands . . . . . . . . . . . . . .
4.3 Equipment sizing . . . . . . . . . . . . . . . . . .
4.4 Total weight . . . . . . . . . . . . . . . . . . . . .
4.5 Safety, Health & Environment . . . . . . . . . .
4.5.1 Hazard and Operability study (HAZOP) .
4.6 Process control and instrumentation . . . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
41
41
42
43
43
47
47
47
48
5 Economic Analysis
5.1 CAPEX . . . . . . . . . . . . . . . . . .
5.1.1 Conventional . . . . . . . . . .
5.1.2 Hybrid . . . . . . . . . . . . . .
5.1.3 Conclusions regarding CAPEX
5.2 OPEX . . . . . . . . . . . . . . . . . . .
5.2.1 Pumping . . . . . . . . . . . . .
5.2.2 Heating . . . . . . . . . . . . . .
5.2.3 Cooling . . . . . . . . . . . . . .
5.2.4 Conclusion regarding OPEX .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
51
51
51
52
53
53
53
54
55
55
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
57
57
60
61
61
62
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
63
List of Symbols
66
A Unit sizing
A.1 Contactor (C-101) . . . . . . . . . . . . . .
A.2 Vessel sizing (V201, V202 & V203) . . . .
A.3 Heat exchangers (E-201,202 & 203) . . .
A.4 Still Column (C-201) . . . . . . . . . . . . .
A.5 Pumps (P-101 A/B and 202 A/B) . . . . .
A.6 Pervaporation membrane module (S-202)
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
67
67
68
69
70
70
70
B Used graphs
73
77
79
83
87
89
91
93
97
101
105
M Equipment Summary
109
Bibliography
135
1
Introduction and Project Charter
In this first section of the project, it will be described the background of the process as well as the
objectives and requirements of the dehydration unit for the natural gas. Moreover, all relevant data
necessary for further understanding of the process and design will be also displayed.
1.1. Background
During the last 40 years, the production of natural gas has increased by more than a factor 3, resulting
in a fast increase of the amount and size of production plants. This, plus the on going scarcity of oil and
gas, forces companies to place drilling platforms on more remote and violent locations. These offshore
platforms, where huge feeds of oil and gas are processed, must operate with as few equipment as
possible to avoid the extra weight, trying to keep the production as cheap as possible.
In 2010, 4.359 billion (439510 ) cubic meters of natural gas were produced worldwide. Norway is
situated 2nd in the ranking of biggest natural gas producing countries with a production of 114.7 billion
cubic meters. In 2010, production of crude oil, Natural Gas and pipeline services accounted for 50%
of the export value of Norway and 21% of the GDP (gross domestic product). All of the oil and natural
gas fields in Norway are located subsea on the Norwegian Continental Shelf, being the Troll field the
largest single one, representing one-third of the countrys natural gas production. When natural gas is
taken out of the ground it needs to be processed before it can be used commercially. A conventional
gas sweetening process is displayed in figure 1.1.
Figure 1.1: Simplified liquid natural gas plant diagram. Here the purple block indicates the gas well,
the blue ones indicate process steps and the orange ones are the products of this industry.
Natural gas that comes out of a well is saturated water. It often also contains other compounds
such as Hydrogen Sulfide, souring the gas. These components must be removed following the scheme
of figure 1.1. Moreover, several crucial reasons why water need to be taken out are presented below:
It can trigger the production of hydrates and of crystals. When transport of the natural gas is
lead through long pipes, the chance of clogging becomes high and the removal of these plugs is
expensive.
Water can cause corrosion to the pipelines.
It can cause slugging flow conditions which increases the pressure drop over the pipeline.
In presence of water, the heating value of gas decreases radically. [1] [2] [3]
One of the most used dehydration processes is Glycol dehydration, with about 30,000 units in
operation in the USA alone. This method can be performed with any Glycol solvent, but the mostly
tri-ethylene glycol (TEG) is used. This process started to be used in the 1970s and has not changed
much since. In a contactor column of perforated trays or a packing, the wet gas stream and the TEG
stream will meet in counter current. After absorption the TEG rich in water goes to a regenerator,
where the water is taken out in a still column. The pressure difference between these two processes
is usually very high, going from 160-170 bar to atmospheric.
As mentioned before, the dehydration of Natural Gas using TEG has been used for over 40 years.
Not much has changed to the way this process works over all the years. However, with a growing
interest in process intensification and many developments in this field, it could be possible to decrease
the size of the TEG unit while maintaining or even increasing the effectiveness.
Parts of the system in which a potential weight loss can be significant are the TEG inventory and
the size of the regeneration system. Examples of techniques that will be looked into are pervaporation
membranes and microwave heating, among others, having the potential to reduce the size and price
of the unit significantly.
1.2. Objectives
The assignment, provided by Frames group, is to find and design a new dehydration unit by introducing
new innovations in order to lower the CAPEX, OPEX and weight of the conventional TEG dehydration
unit for an offshore platform using recent advances in science.
Therefore, the first task that needs to be done is the definition of the conventional process.Then,
the CAPEX, OPEX and weight of it will be set as benchmark. In the next stage, improvements will be
proposed and their impact will be estimated especially in terms of CAPEX, OPEX and weight. Finally,
conclusions and remarks will be posed about the proposed design of the unit.
Figure 1.2: Block diagram of the process. Orange blocks represent the battery limits of the
dehydration process whereas blue blocks represent steps taken in TEG dehydration.
Hence, the battery limits of the unit are represented by the four orange circles shown in figure 1.2.
There is only one inlet flow to the system, wet gas, and three outlet flows, dry gas product, drain and
overhead gases.
1.3.2. Requirements
The requirements for natural gas after dehydration are presented in table 1.1.
Table 1.1: List of requirements as provided by Frames group
Location
Offshore fixed platform in Norway
Water specification
24 mg/Sm
Turndown
10%
Pressure drop
0.25 bar
Glycol losses contactor 10 l/MMNm (0.07 UGS/MMSCF)
Others
No mercury
Notes. S= Standard Conditions of 1 bar and 15 C
N= Normal Conditions of 1 bar and 0 C.
(As agreed with Frames during Kick-off meeting)
Although the implementation will be on a Norwegian offshore oil plant, the host country regulations
will not be taken into account and the extra costs that come from the installation being on an offshore
location need not have to be considered as this difference works for both the conventional and the
suggested processes.
1.4. Database
1.4. Database
In this section of the project, all relevant data of the compounds involved is tabulated. This is also the
data that is used in the simulations.
Mol. %
@saturation
0.18
3.58
86.49
5.33
2.18
0.49
0.89
0.25
0.24
0.33
Value TEG
C H O
150.17kg/kmol [7]
285 C[8] @ 1 atm
-7 C [8]
1127.4 m @ 15 C [8]
0.00478 Pa.s @ 200 C[8]
<0.001 kPa [7]
61.04 kJ/mol @ 1 atm [8]
Value water
H O
18 kg/kmol
100 C @1 atm
0 C @ 1 atm
998.3 kg/m @ 200 C[9]
0.001003 Pa.s @ 200 C [9]
2337 Pa @ 200 C [9]
2257 kJ/kg @ 1 atm[10]
to the reasons mentioned in section 1. The thermodynamic properties of water are also listed in table
1.3
Natural gas
Table 1.4: Component and thermodynamic properties of natural gas
Property
Molecular Formula
Molecular Weight
Density [11]
Net Heating Value [11]
Natural gas, consisting of predominantly Methane, is a hydrocarbon gas formed due to fossilization
of buried plants and animals. For these species to become natural gas they were below the earths
surface for over a thousand years. It is a non-renewable source of energy and is typically used for
heating (industrial) and cooking (domestic). Some of the properties of Natural gas are given in table
1.4. The specification of the natural gas that comes from the specific well in Norway are given in table
1.2.
2
Conventional Process
In this chapter the conventional process currently used in the industry to dehydrate natural gas is
described. Firstly a process scheme is shown and later every step is explained into detail. A few
remarks on how this process is modelled in Aspen Hysys are given. All equipment sizing is explained
and a safety assessment is done. Lastly a few comments on bottlenecks and areas to improve will be
mentioned.
Figure 2.1: Flowsheet of currently used TEG dehydration process. In green the Absorption unit
(U100) and in purple the Regeneration unit (U200).
2. Conventional Process
Various types of random packing are also used in glycol contactors to achieve a
high surface area for mass transfer. The total height of the packing in the vessel
can be calculated from the number of theoretical stages used in the design.
Typically suppliers of the packings have correlations for packing height needed
per theoretical stage.
Structured Packing
10
2. Conventional Process
11
Energy demands
From the Aspen Hysys simulations the energy demands in pumping and heating can be found.
Table 2.1: Energy demands per type
Location
P101
P202
Reboiler
Total
Cooling
E203
C201
Total
Heat exchanger
E201
E202
Type
Electrical energy
Electrical energy
Gas heating
-103.5
-49.85
-153.35
HX
HX
88.5
168.5
(2.1)
With:
L = length of vessel [m]
= Diameter of the vessel [m]
= Density [kg/m ]
= Wall thickness [m]
Heat exchanger weights are estimated using Aspen Hysys. Only motor weights have been used to
estimate weight of pumps[17].
Contactor
Table 2.2: Size and weight comparison of the conventional contactor column
Name
C-101
Type
Column
Diameter [m]
2.04
Height [m]
12.2
Weight [kg]
143135
12
2. Conventional Process
Vessels
Table 2.3: Vessel volumes
Name
Type
V-201
V-202
V-203
Flash
Reboiler
Surge
Volume
[m ]
0.535
0.465
1.16
Diameter
[m]
0.554
0.529
0.719
Length
[m]
2.217
2.117
2.875
Wall Thickness
[mm]
6
6
6
Weight
[kg]
221
202
371
Heat exchangers
Table 2.4: Total surface area needed per heat exchanger
Heat exchanger
E-201
E-202
E-203
Surface area [m ]
28.45
147.0
17.3
Weight [kg]
1253
3390
800
Basis and method of calculation of the area of heat exchanger is given in Appendix A Section
Still column
Table 2.5: Size of the conventional still column
Name
C-201
Type
Still column
Diameter [m]
0.28
Height [m]
6.5
Weight [kg]
476
Stripping Column
Table 2.6: Size of the conventional stripping column between the reboiler and the surge
Name
C-202
Type
Stripping column
Diameter [m]
0.25
Height [m]
0.5
Weight [kg]
32
Pumps
Table 2.7: Power requirement per pump
Pump
P-101A/B
P-202A/B
Head [mlc]
1370
20
Power [kW]
13.4
0.155
Weight [kg]
564
22
13
Closed cup
Open cup
Upper limit
Lower limit
LD (oral)
TLV
Value
285 C
371 C
177 C
165 C
0.9 %
9.2 %
4700 mg/kg
10 ml/m
Natural gas
Natural gas is highly flammable, creating the risk of explosions, as can be seen in figure 2.5. Table 2.9 shows the
explosion limits of methane, which is a key component of
natural gas. A fire can not be extinguished unless the source
of the gas has been closed. So, it is advisable to let all the
gas burn up and then extinguish the fire with dry chemicals,
foam or CO .
In addition, when the gas is kept under pressure it can lead to the risk of frostbite, which occurs
when high-pressure gas is released, expanding and cooling down. This is however more dangerous
when handling liquefied gas, but in this system the natural gas remains in the gas phase. The gas is
not toxic but when released can be highly dangerous because it can cause asphyxiation by drawing
out all the oxygen. It has been found that up to concentrations of 10 000 ppm no physical changes
occur when a human is exposed. Studies have shown that there are some physical complications in
test animals who are exposed to high concentrations of methane (up to 70%) while having enough
14
2. Conventional Process
oxygen, but not much has been documented on these phenomenon and it seems unlikely that these
circumstances will occur on the plant.[19]
Table 2.9: Explosion limits of methane (key component in natural gas)[20]
Properties of methane
Explosion limits
Lower
Upper
Value
5%
15%
15
16
2. Conventional Process
Table 2.10: List of properties of TEG and Methane for determining the F&EI
Properties
Material Factor
H
N
N
N
Flash point
Boiling point
TEG
4
9.310
1
1
0
350 F
546 F
Methane
21
21.510
1
4
0
Gas
-258 F
plementing a draining system and prevention measures for spills. The total penalty adds up to be
2.70.
Special process hazards
Some of the items that got a penalty in this subject were the pressure, which is high in the contactor,
which receives a penalty of 0.48. Also the quantity of flammable material got a high penalty, 3. The
total penalty for Special Process Hazards adds up to 5.18.
Conclusion
The final Fire & explosion index turns out to be 294 which categorizes this unit in the severe degree of
hazard region. The exposure radius for this F&EI will be 70 m. This will mean that a large part of the
platform will be affected by an explosion. There are no structures around the platform which makes
the consequences for second parties minimal.
Loss control credit factors
The fire and explosion index can be reduced when measures against fire and explosions are present.
Therefor a few thinks need to be present in the final design of the unit itself and the surrounding plant
Emergency power
In case of an emergency there can be a power outage, it can be possible to automatically go to
emergency energy. If we have a power outage there will be no drying of the gas anymore but
there will be no possibility for for instance a runaway reaction or agitation for which it might be
necessary to have a big emergency supply of energy.
Cooling
Our system does now only have one cooling device and no backup, but because there is no
chemical reaction in our system but only separation the consequences of losing a cooler will not
directly cause a fire or explosion.
Emergency shutdown
If something abnormal happens the entire system should be shut down completely. If this happens automatically than the reduction of the F&EI is bigger than when it only sounds an alarm.
Computer control
The bigger part of the system is controlled via computers, the more reduction is given to the
system. The more advanced the system the better.
Material isolation credit factor
In this section items that prevent the build up or spilling of material to places where they should not
be, both within or outside the system.
17
2.5.3. Waste
There are two waste streams leaving the TEG dehydration system, both from the regeneration unit.
One is a liquid outflow from the flash equipment which will prevent buildup from unwanted species.
The second one is a combination of the vapour gas outflow from the flash and the water rich outflow
from the separation units (still column and pervaporation membranes). Because this specific unit is on
an offshore gas platform, using a flair to burn the waist would be too dangerous. Therefore, all waste
streams will be incinerated.
18
2. Conventional Process
Thus, it was identified that the majority of changes according to the objectives of the project can
be done in the regeneration subsystem, because it contains more pieces of equipment, almost all the
TEG stored and the conditions on the TEG are more strict in this section (i.e. 150-200 C). For these
reasons the focus of the alternative technologies will be in this unit of the system.
Furthermore, the TEG inventory and regeneration loop can provide also some weight loss. By using
a more effective separation in the contactor the TEG circulation rate can be lowered. This leads then
to a reduction of TEG inventory, which leads to smaller equipment especially in the form of the reboiler
and the surge (V-202) & (V-203), with volume of respectively 0.667 m and 1.16m . This will lead to
a weight reduction as less steal is needed. Also different techniques of TEG dehydration need to be
considered to reduce the size and costs of the total regeneration loop.
Finally, the biggest energy demand is identified from the reboiler which requires 194 kW to run
efficiently. Also the injection pump of 13.4 kW contributes to the total energy demand. By reducing
both, the total operational costs can be cut down and more efficient and cheap operations can be carried
out. This reduction in energy demands can also be achieved using a completely different technique of
TEG dehydration, as mentioned before.
In the next chapters recent advances from science will be discussed and reviewed in order to check
its usability in this process. From these concepts, a new system will be then proposed and the possible
optimization and improvements achieved will be calculated and reviewed.
3
Innovation Map
All innovation and improvement opportunities are described in this chapter. First all considered alternatives are described in a technological and more qualitative way and their beneficial effects are touched
upon. After that a preliminary cut will be made to discard technologies which have too many downsides. Later different process schemes are proposed and studied quantitatively and then researched for
beneficial effects on this system, regarding CAPEX, OPEX & weight. Here calculations and simulations
are tried upon the new technologies which were earlier proposed. Lastly the final system is chosen
which will be modeled and designed in the rest of this report.
20
3. Innovation Map
Advantages of this technique are that there is no heat transfer zone so the heating occurs in the entire
volume that is being irradiated. The waves are selectively being absorbed and a rapid heating can
occur.
The dielectric component in the TEG regenerator is water, this is the species that needs to evaporate
out of the TEG. This will also be the target specie of the microwaves generating the heat, which means
that the water in the mixture can become warmer than the TEG, which will lead to faster evaporation.
TEG however has an interaction with water molecules as it contains alcohol groups. This can lead to
the TEG heating up as well. No test regarding this specific process to check if only the water heats has
been done as of now. The molar fraction of water molecules of the feed stream is 32 mol%. Regarding
this high molar concentration it can be expected that there is a lot of contact between water and glcyol
and therefor energy transfer. A different benefit is however, while there is no heat transfer area, the
total volume of TEG and water can be heated at once and uniformly.
Experiments showed that only heating up the liquid will not benefit the separation of the binary
mixture[22] and the stirring will also create a uniform temperature in the liquid phase which takes
away the advantages of the selective heating. However, when also the surface is irradiated with
microwaves the separation of the more volatile species is more effective than in a separation without
microwave heating. One explanation of this is that very locally high temperatures will occur, resulting
in a smaller column with fewer trays. These so called hot-spots can lead to a fouling in TEG, as TEG
thermally degrades at temperatures above 210 C.[7] Discussion with professor Stankiewicz and Dr.
Guido Sturm however provided a different outlook as they mentioned new ways of heating which was
very controllable an predictable and therefor those hot-spots can be avoided.
The uniformity of microwave heating however is debatable. In literature it is described that by
absorption in the medium the intensity of the field will drop quickly. This leads to a large part of the
volume not heated and parts of the volume overly heated [23]. Dr. Guido Sturm mentioned however
that this effect can be reduced a lot, because the behaviour of microwaves can be described quite
good. By altering the field and radiation techniques these hot spots can be minimized. This is not done
on a larger scale then lab, but shows good promise.
The currents hurdles in the use of microwaves in industry are the yet unreliable scale up of the
process, which can be helped by modeling the field and design it that way. Another hurdle is the
implementation of microwave equipment into conventional chemical equipment.
21
As 50% of the total cost of gas refining is represented by energy costs, the addition of a turbocharger
can provide a significant cut down in operational costs. By using a liquid charger less investments
need to be done regarding pressurising the glycol, therefore a cut down in capital expenditure is also
expected. The company Energy Recovery claims an energy efficiency of up to 80%. On the other
hand, this technology reduces the degrees of freedom of the system, as it combines different streams
of the process. These Glycol powered pumps are currently sold skid mounted by companies such as
Kimray and Rotor-Tech.
22
3. Innovation Map
to the vapour phase (see figure 3.4). Therefore, the water of TEG-water mixture in our regeneration
system might be taken out using a hydrophilic membrane as a selective barrier between the liquid
phase feed and the vapour phase permeate allowing the desired molecules to diffuse through it by
vaporization.
One of its main benefits is not being a pressure driven process. Instead, the driving force is due
to a higher chemical potential on the feed side than on the permeate side. The gradient in chemical
potential is then maximized by using high feed temperatures and low pressures on the permeate side
as well as combining polymer properties for membrane. [27].
By replacing distillation by the pervaporation membranes for the Glycol regeneration subsystem,
according to Pervatech company savings up to 75% on regeneration equipment and 30 to 50% reduction on energy usage can be achieved. However, membrane units, including the need for vacuum, are
currently relatively expensive. Also, if the supply contains suspended matter or dissolved salts membrane pollution may be encountered. In this case, an effective pretreatment must be implemented.
e.g. filtration.[28]
23
24
3. Innovation Map
working fluid. Also, one unit can not be competent for continuous distillation owing to incapability of
feeding the rotor at radial position, equivalent to middle plate of traditional distillation column. Thus two
units of rotating bed are required for continuous distillation; one as rectifying and the other stripping.
HiGee technology can both be used in the contactor part of the process as well as the TEG regeneration. By using rotating bed reactors the size and weight of the contactor and still column and therefor
the total unit can decrease significantly.
Figure 3.6: HiGee distillation: (a) RPB integrated with reboiler and condenser; (b) RPB with off center
feed and integrated with reboiler [34]
25
Strengths
Less lean TEG inventory
Microwave heating
Super-X Packing
Liquid Turbochargers
Pervaporation membranes
Addition of entrainer
Vacuum operation
HiGee distillation
High Efficiency
Smaller equipment (5-10 fold)
Weaknesses
More complex design
No reduction of size
Design into conventional equipment
Clogging
Fouling
No commercialization
No experience
Less system flexibility
Availability of companies
Expensive
No solids allowed
Availability of companies
Expensive
Higher CAPEX
Heavy & big
More equipment
More components
Heavy & big
Complexity
More equipment
Possible TEG degradation
Moving parts
Very unknown technology
More maintenance
Also, the addition of the entrainer is rejected as it will increase the size of the unit as well as it is not an
innovative solution, which is in conflict with the objectives of the project. Also earlier proposed toluene
will dissolve into TEG as well, working against all benefits as proposed earlier. Finally, the vacuum
operation in a conventional equipment setup in the regeneration part is not investigated anymore as
an alternative, because to gain energy savings, the vacuum was meant to be created by ejectors that
work with existing flash gases going out. However, this will result in a pressure drop avoiding these
gases to reach the flare header which takes them into the incineration flame. The HiGee distillation
is discarded as the introduction of moving parts and such an unknown technology is hard to achieve
offshore. Several onshore application should be achieved first to look at the effects it will have on the
structure of the platform. If it will change the integrity of the drilling platform and question like that
need to be answered first.
For the other four technologies, a full study and design was done, resulting in three combined new
process schemes shown below, stating the several assumptions used in each.
26
3. Innovation Map
Figure 3.7: Process scheme with turbocharger and semi-lean TEG split flow injection, shown in yellow
boxes
Turbochargers
The size, and therefore weight, of the injection pump system can be lowered by using a turbocharger,
because as mentioned, this device interchanges the energy of a high pressure stream with a low
pressure one. This can also decrease the total energy needed for the pumps as well as the number of
them.
The total operational costs for pumping, assuming a total cost of 10 ct per kWh[36], is 1.34 per
hour [37]. Assuming 24/7 operation the total costs per year of this pump will be 11.738. Using
calculation tools provided by Energy Recoverya recovery of 70 % of energy can be achieved. This
will result in a evenly large reduction of operational costs. So a reduction of 8.216 on a yearly basis
can be achieved. Not only that, also a reduction of 9.38 kW is achieved at the pumping section. This
leads to a reduction of approximately 79.866 kg CO which is released on a yearly basis[38]. The
total energy requirement for the plant is 205 kW. By adding a liquid turbocharger into the conventional
process a reduction of 4,6 % can be achieved without increasing the capital expenses which will be a
real benefit.
Split Flow injection
This alternative is studied with an intention of reducing the TEG inventory in the recirculation system.
Following is the discussion of the study.
The incoming lean TEG is fed to the top-most stage of the contactor. As per the design of the
conventional process in section 2.2, the contactor has 6 theoretical stages, therefore, it is possible to
study injection of TEG ranging from 2 to 6 splits, simultaneously varying the percentage of flow flowing
through each split branch. However, it should be noted that while injections with 2 and 3 splits can
be studied extensively for symmetric arrangements between theoretical plates, for higher number of
splits(eg:4-6) there would be too many combinations possible.
27
Hence, to restrict ourselves, we study only injections with 2 and 3 split flows with varying percentage
of flow through each split branch. Since the intention is to reduce TEG inventory, simulation was started
with lower conservative estimate for the lean TEG flow in order to check whether it is possible to still
achieve the desired specifications in the outlet dry gas. As it was found that it is indeed possible to
meet the outlet water requirements, all the simulations for split flow were started with lower estimate
of TEG flow, that of 1580 kg/h. The maximum outlet water content as per specification turns out to
be 8.5 kg/h. If the specification was found to be well within limits, TEG flow was reduced even further
for the split flow to an extent that the outlet water concentration never rises above maximum 7.7 kg/h.
On the other hand, if the specification was barely met, no further adjustments were done in that case.
Figure 3.8 summarizes the observations of the simulation modelled in Aspen Hysys G.1 which form
the basis of this study. Different types of splits were tested to see if adding more TEG in the beginning
or end has an advantage. Entries in bold represent lowest possible flow of TEG that can be achieved
for that particular split combination to achieve the water specification as mentioned above.
Figure 3.8: Results of calculations on split flow injection made in Aspen Hysys.
It can be seen that the lowest achievable flow of lean TEG in both 2-split and 3-split schemes is
1225 kg/h. There is no significant reduction of TEG on increasing the number of splits form 2 to 3. To
check whether this really adds value to the conventional process with no splits, the flow of lean TEG
was reduced to as low as possible in Hysys still ensuring that the above specs were met. This flow was
28
3. Innovation Map
found to be 1150 kg/h. This is a result contradictory to our expectation that split flow reduces TEG
inventory.
From the above study, it can also be seen that with Hysys simulations, it is possible to reduce
the lean TEG flow even below the theoretical minimum of 12 times the amount of water removed.
However,it must be understood that such reduction may not be practically feasible. Moreover, we
cannot completely trust the thermodynamic models in Aspen Hysys to be totally accurate in their
prediction. Hence, we limit ourselves to the theoretical minimum flow of 12 times the water removed
of lean TEG as mentioned above.
Microwave heating
Microwave heating has several benefits as mentioned before, including that it can be more efficient
and requires a smaller device than conventional heating with a reboiler. In some cases it can even be
replaced in total. It can also decrease the amount of stages needed for the regeneration.
The technology for continuous operation is now in the pilot plant stage. The company Sairem
(France) is working on this. Their reactor design has a flow capacity up to 1 L/min and has a microwave
generator that generates waves of 2450 MHz. 6 kW of power is generated and there is a significant
29
part of the design devoted to cooling. The unit is a metallic vessel which assures pressure containment
and allows for fast thermal transfer.[39]
However, heating volatile, often flammable organic solvents, under well-controlled conditions is
not trivial on the large scale, but it can be done. Lastly, another Sairem 915 MHz batch reactor
was changed in the strategy to microwave scale-up through the use of a different wavelength, since
penetration depths, dielectric constants and loss factors vary with wave length as well as solvent nature
and temperature. In this case, the energy savings were due to a decrease in heating time and not in
energy efficiency, because normal household microwaves (central component of any microwave device)
has an efficiency of 50-65% transforming electricity into electromagnetic irradiation[40]. However dr.
Guido Sturm of TU Delft, a expert in microwave heating, mentioned an efficiency off up to 80 %.
Overall, there are reasons to think that together with the use of the stripping technique for glycol
regeneration, with a gas normally flowing upward counter currently to the descending liquid TEG, the
unit can achieve the requirements and reductions proposed. Depending on the stripping agent used,
i.e. outlet gas from the flash (V201), water, hydrocarbons, or both are absorbed from the glycol into
the stripping gas, thus regenerating the glycol for reuse in dehydrating the natural gas. But the reality
is that these processes produce an additional gaseous or aqueous waste stream that requires off-site
attention such as incineration, disposal, or further treatment.
An attempt has been made to model microwave in Aspen Hysys, but a working model is has not yet
been achieved. The column is split into three stages, modeled as flashes and a condenser and reboiler
part. At each stage a specific temperature is set, as is used with microwave distillation. These are all
separately heated. The feed enters the column at the middle stage, this because it gave the lowest
energy use. This model however leads to very high and fluctuating energy demands per stage. Three
different settings were used. Firstly the natural gradient occurring in the still column has been taken.
Secondly a linear decrease between the top and bottom stage has been tested and lastly the inverse
of the natural gradient is tested. This is displayed in table 3.2 and the model used is added in appendix
F.1.
Table 3.2: Energy demands from the different setting of the model described in appendix F.1
Stage
Condenser
3
2
1
Reboiler
Stage
Condenser
3
2
1
Reboiler
Setting 1
Set
Temperature (C)
97
99.26
101.9
150.7
204
Setting 3
Set
Temperature (C)
97
145
165
185
204
Energy
Demand (kW)
-17.05
-162.6
-16230
16370
192.8
Energy
Demand (kW)
-7139
7136
32.69
63.91
55.17
Setting 2
Set
Temperature (C)
97
125
150
175
204
Conventional
Set
Temperature (C)
97
204
Energy
Demand (kW)
-6004
5999
-30.85
92.66
87.83
Energy
Demand (kW)
-49.85
191.5
As this model did not achieve realistic values different professionals in the field of modeling microwave heated column were contacted. From these conversations, it became apparent that, as this
is a very young field of research no real simulation models are achieved as for now.
The main fields in which microwave heated columns are used are pharmaceutical and food processing technologies. Outside of these fields the benefits have not been sufficient enough to take the risk
of entering a new technology. To estimate the costs, the energy needed by a conventional still column
is used.
When designing the new column a few constraints should be kept in mind however. No magnetic
30
3. Innovation Map
materials can be used around microwave heated volumes. These magnetic properties cause extensive
heating effects on the magnetic walls and equipment. A still column made of carbon steel as proposed
earlier in this report is not feasible anymore as the microwaves will heat the carbon steel. A still column
of stainless steel or a copper coating on the carbon steel are needed to evade this effect. To power the
microwave a cable of 8000 Volts needs to be added to the plant. These high voltages impose a new
risk to the plant as well, as there were no high voltage operations present before. Microwave units
themselves are also an additional risk as, when they are displaced, can cause severe burning into the
skin. That way not only the skin is burnt but it will penetrate the skin and burn internally as well.
Moreover, an economic evaluation has been done. By adding microwave heating in the column the
total CAPEX will increase. A rough cost estimation is provided by Dr Guido Sturm. A 6 kW microwave
unit costs around 20,000, which scales more or less linearly. From Aspen Hysys the energy requirement is calculated for a conventional unit. The figure found there is 141 kW for heating. Therefore an
investment of around 470,000 is needed for the energy requirement leading from the conventional
process. Contact with the French company Sairem was also made. They are currently investigating
the use of microwave heated still columns. Their cost estimation is around 550,000 for the internals
of such a column. The column itself will cost 147,850 if it is made from stainless steel (SS316). This
is a significant rise in capital expenses, as the initial capital expenses, as will be calculated in chapter 5
are almost 10 times less. The weight of one 6 kW microwave unit is around 15 kg, so the total weight
of a column with this duty will be 352.5 kg which is in the same ballpark as a gas fire heater.
Using microwave heating an efficiency of 80% can be expected. If the system stays unaltered and
the energy demands are more or less and a cost of 0.1 per kWh is used the total yearly cost of
reboiling with microwave technology is 264,278. This is almost 100,000 more then a gas fired
heater.
Dr. Guido Sturm also mentioned that microwave heating is only beneficial when a stream needs to
a lot of heating. Regarding this system, due to good heat integration, the inlet stream in the column
already is 170 C. The additional 30 C needed for distillation are presumably not enough to favor
microwave heating.
Considering all these additional costs and no guarantee that the reboiler can be taken out of the
system it is decided not to pursue this technology any further. The investment is 10 times higher then
a conventional still column and in OPEX no savings can be expected either. The presence of natural
gas at the platform makes a gas fired reboiler a better substitute for heating in the still column.
31
For a specific organic mixture (in this case TEG with water) one has to test to determine selectivity
and fluxes during the process of dehydration, because the binding force of TEG to water is high, so
fluxes will be lower compared to some other organics e.g. ethanol or IPA. In addition, it is more
difficult to dehydrate to such low water concentrations. Then a preliminary study of different types of
membranes was carried out to find out these fluxes on basis of the conventional process outlet vapour
stream from the flash.
First of all, apart from company claims, a paper was found which states that with commercial silica
membrane modules of the company Pervatech, if a feed of 0.054 wt water, 0.936 wt TEG and 0.005
wt Toluene and 0.005 wt Hexane at 150 C, a 99.99+% wt of water purity in the permeate can be
achieved, at an average flux of 0.255 kg/m h [41].
In addition, an experiment performed to determine the water flux of a zeolite membrane module
from Mitsui USA was tested at 100 C with a TEG mixture containing 5% wt water resulting in 0.13
kg/m h as permeate.
Other sources say that 95% wt water purity can be achieved with NaA zeolite membranes exhibiting
high separation performance and fluxes of 0.5 kg/m h for 5% wt feed water content at 120 C. [42]
Also, a realistic research with improved membranes such as Sulfonated Poly-ether-ether Ketone
(SPEEK) was carried, resulting in only 98% of water purity the permeate side with 5% wt water content
in the feed at 32 C and flux of 0.2 kg/m h as depicted in Huang et al (2002) [43].
In other words, in order to estimate the area required for a complete separation we carried this
analysis. It means roughly, avoiding pressure drops, no TEG losses in permeate, constant flux, 100%
water permeation and no membrane size limitation, that if our stream of 1657 kg/h (0.0033 wt others,
32
3. Innovation Map
0.912 wt TEG and 0.0847 wt water, see figure 3.11) from the flash is fed to a membrane unit we will
obtain the results shown in table 3.3 and explained with two examples below.
Figure 3.11: Schematic representation of pervaporation membrane unit with inflow of 1657 kg/h
coming from liquid stream of flash unit.
Example calculation for silica membranes:
All water in feed goes into permeate
1657 0.0847 = 140.35 kg/h, representing the 0.9999+ wt water in that stream, because this is
the maximum for this membrane.
Therefore, 1657 - 140.35 = 1516.65 kg/h of TEG plus other compounds in retentate. All TEG in
feed goes to retentate,
1657 0.912 = 1511.18 kg/h, representing the 1511.18 / 1516.65 = 0.996 wt TEG and 0.004 wt
of others in that stream.
Hence, if the average flux of permeate is 0.255 kg/m h, we need 140.35 / 0.255 = 550 m of
membrane.
Example calculation for SPEEK membranes:
All water in feed goes into permeate
1657 0.084 = 140.35 kg/h, representing the 0.98 wt water in that stream, because that is the
maximum for this membrane. It means that the total permeate flow is 140.35/0.98=143.21 kg/h,
where 143.21 - 140.35 = 2.86 kg/h are other compounds except from TEG.
Therefore, if in the feed there were 1657 0.0033 = 5.47 kg/h of others, 5.47 - 2.86 = 2.61 kg/h
go to retentate. Hence, if all TEG in feed goes to retentate,
1657 0.912 = 1511.18 kg/h plus 2.61 kg/h results into 1513.79 kg/h of TEG plus other compounds in permeate, representing the 1511.18/1513.79= 0.998 wt TEG and 0.002 wt of others
in that stream.
Finally, if the average flux of permeate is 0.2 kg/m h, we need 143.21 / 0.2 = 716 m of membrane.
Following the same reasoning, the results shown in table 3.3 were calculated, which in all cases is
33
Temperature
C
130-150
92-100
120
30-70
TEG in retentate
wt
0.996
0.996
1.00
0.998
water in permeate
wt
0.999
0.999
0.950
0.980
Area
m
562
1080
295
716
It is observed that nowadays there is a lot of research on new membranes and that most of them
fulfill the requirements for our dehydration purpose. However, there are not many supplier companies.
Examples are Sulzer Chemtech Membrane Systems, based in Heinitz, Germany; and Pervatech BV of
Enter, The Netherlands, allowing a wide range of different temperatures, modules and flows.
Furthermore, although the major component in the over head vent is water stream, as shown, this
stream may contain organic compounds, including aromatic and non-aromatic organic vapours, such
as BTEX. The emissions of them are now classified as Hazardous Air Pollutants (HAPs), and are subject
to regulations which can be better handled by these membranes.
This is, therefore, a simple and reliable method to reduce or eliminate the release of these components, basically caused by the hydrophilic membranes which in one step both regenerate the solvent
and capture any hazardous components. Despite efforts, a cost-effective regeneration technology that
truly minimizes or eliminates HAP emissions has not yet been developed.
To finish, also a comparison of the energy consumption based on the heat requirement for evaporation for the removal of 1 kg water from feed mixtures can be seen in the following figure 3.12,
extracted from Huang et al (2002) [43].
It is clear in figure 3.12 that the advantage of applying pervaporation for dehydration of Glycol
becomes significant when the water content in the feed is significantly low. It should also be pointed
out that this simple comparison was based only on the theoretical energy consumption at a constant
pressure. Many other factors such as cooling of distillation, thermodynamic heat effectiveness, and
capital cost are not considered, all of which are important for the economic evaluation of these two
separation technologies.
To maintain more realism in the design, Pervatech membranes were selected for further considerations. In the following study, a commercial Pervatech module PVM-080 SS 316 374-tube (120cm)
with 3,7 m membrane surface was used with these assumptions and characteristics[44] [45] [46].
In the following images 3.13 and 3.14, a commercial Pervatech module is presented to get an overall
impression of the module we are using. In our case, instead of 7 elements of 4 channels each, we will
used 37 elements of 4 channels each.
Membrane element characteristics:
Size: 1200 x 25 mm (LxD), effective area 0,10 m (standard). Each element has 4 channels
with 7 mm inside diameter.
Membrane type: Hybrid silica hydrophilic membrane.
Substrate material: -Al2O3.
Intermediate layer: Gamma alumina.
Top layer: Hybrid Silica coated on inside of the support tube.
Pore Size: 0.30.5 nm.
Limits of membrane:
Temperature: limit max. 150 C.
Pressure: limit max. 50 bar.
34
3. Innovation Map
Figure 3.12: Theoretical comparison of the energy consumption of pervaporation against distillation.
Energy consumption (P) based on the heat requirement for evaporation for the removal of 1 kg water
from feed mixtures using = + ((1/ ) 1) where H and H represent the
evaporation heat (kcal/kg) of water and Ethylene Glycol, respectively.
pH: 2-8.5.
Limits of operation:
Maximal allowable working pressure 20 bar at 175 C.
Minimum design material temperate -20 C at 20 bar.
Vacuum: Level of vacuum depends on the application.
Feed pump capacity: Linear velocity of the feed to be high enough to guarantee turbulent flow inside the tubes (Re 19000), this to prevent concentration polarization and limit
fouling.
Assumptions:
3.7 m of membrane/module (37 elements).
TEG composition of 0.9895 wt in retentate, because it is needed for the semi-lean TEG split
strategy.
Water composition of 1.0000 wt in permeate (only water permeates).
Temperature: 150C.
35
Pressure: 3 bar inlet feed, 20 mbar in permeate side and 1.5 bar retentate side.
Permeate flux 0.255 kg/m h from the sensitivity analysis over a range between 120C150C explained below 3.15.
The reason to do is analysis is helping to decide the optimum temperature conditions of our
membrane system. Therefore, it was tested the temperature effect versus different water
compositions for different temperatures which are presented in the following figure 3.15.
Due to the fact that the flux depends on the water content along the length of the membrane
because the chemical potential changes with water concentration in the TEG, a logarithmic average of
the inlet value of water and the outlet was taken into account at 8.5% wt of water at the inlet and
0.7% wt of water at the outlet. Hence, taking into account the assumptions mentioned, it led to the
results in table 3.4. One example of calculation has been provided below.
36
3. Innovation Map
Figure 3.15: Feed water concentration against water flux in permeate for Ethylene Glycol- water
mixtures [41]. In red is represented extrapolated data.
37
Table 3.4: Results of number of modules estimation with PVM-080 SS 316 374-tube
Temp.
C
150
140
130
120
Flux
kg/m h
0.255
0.206
0.255
0.255
Retent.
kg/h
1527.22
1527.22
1527.22
1527.22
TEG
wt
0.9895
0.9895
0.9895
0.9895
Water
wt
0.0069
0.0069
0.0069
0.0069
Others
wt
0.0036
0.0036
0.0036
0.0036
Perm.
kg/h
129.8
129.8
129.8
129.8
Water
wt
1.00
1.00
1.00
1.00
Area
m
509
629
828
1350
Modules
Nr
138
170
224
365
To conclude with the temperature selection sensitivity analysis, it was decided to follow with 150C,
because it is the maximum allowed temperature for such a module as well as it gives the minimum
number of modules. Furthermore, this temperature will be achieve thanks to a heater before the
pervaporation module and not before the flash for the already mentioned high TEG losses in the flash
at 150C.
It is also very instructive and valuable to follow a sensitivity analysis about the maximum purity
that can be achieved with these membranes modules at 150C if the semi lean split technique is
neglected. Hence, taking into account the previous considerations and way of calculate the purity, the
results shown below were obtained for an inlet feed of 1657 kg/h (0.0033 wt others, 0.912 wt TEG
and 0.0847 wt water, see figure 3.11) and a flux of 0.255 kg/m h .
Table 3.5: Results of TEG purity estimation in retentate with PVM-080 SS 316 374-tube
Retentate
kg/h
1557.9
1542.0
1527.2
1523.4
1516.7
TEG
wt
0.9700
0.9800
0.9895
0.9920
0.9964
Water
wt
0.02649
0.01645
0.00692
0.00441
0.00000
Others
wt
0.00351
0.00355
0.00358
0.00359
0.00361
Permeate
kg/h
99.1
115.0
129.8
133.6
140.3
Water
wt
1.00
1.00
1.00
1.00
1.00
Area
m
389
451
509
524
550
Modules
nr
105
122
138
142
149
In table 3.5 it can be observed how the TEG purity increases as the membrane area increases and
therefore the number of modules, due to an increment in permeate flow. Three important values of
the study should be noticed:
The first one is 98.95% wt TEG purity, which would be the value that allows the removal of the
still column, resulting in only one unit where a stripper increases the purity further from 98.95% till
99.2%. This scheme is discarded however as TEG losses in the stripper column will be higher than the
specified limit, as shown in the proposed scheme 3.10.
Secondly, 523 m representing 142 modules would be the theoretical value needed to directly
achieve the minimum purity required for the process (99.2 %wt of TEG), with the removal of the still
column and stripper too.
Finally, with 149 modules would achieve the maximum of 99.64% wt TEG purity with only pervaporation modules, which is above the minimum.
However, as conservative criteria are always more intelligent in design-wise thinking it is decided
not to go for the maximum purity, so the 98.95 %wt purity of TEG as the outlet stream unit is selected.
The rest of the water needs to be taken out using a still and stripping column.
To check if the process can still be improvised with the lean TEG flow at theoretical minimum,
another strategy was studied, called semi-lean TEG split flow.
38
3. Innovation Map
Here, a part (50%) of incompletely regenerated TEG (98.95% wt TEG) exiting the Pervaporation
is fed back to the contactor in the middle (above 4 stage).The choice of this flow and the stage in
the contactor to which it is sent is completely arbitrary. To maintain the total flow to contactor at the
theoretical minimum, the lean TEG flow is also reduced accordingly. Furthermore, these flows have
not been studied by splitting them to different contactor stages. This is based on the fact that we are
restricting ourselves to the theoretical minimum flow based on the findings of study of TEG split flow
study done earlier in section 3.2.1.
It was observed that by using the above strategy, the stripping gas to the regeneration section
can be reduced by up to 20% of the conventional process without affecting the quality of lean TEG
regenerated. The remaining 80% can be sent to overhead treatment or used somewhere else. By
reducing the flow to 50% after the Pervaporation membranes, the still column and surge vessel size
can be reduced. The power requirement for the booster pump and the high pressure injection pump
would also reduce in this case. But, in order to pump the 98.95% wt TEG to the contactor, an additional
high pressure pump would then be required. So to conclude with, this suggestion is added into the
final different proposals shown below.
Figure 3.16: Process scheme with hybrid system (turbocharge plus semi-lean split injection and
pervaporation module (yellow boxes))
A pervaporation unit can be added to the still column heated with a gas fired reboiler. Pervaporation
39
membranes can reduce the size of that still column as well as the reboiler, as they will separate the
majority of the water (until reaching a purity of 98.98% wt TEG) from TEG and therefore reduce the
weight of the unit. Also, it will reduce the emissions of BTEX and HAP gases. However, a pump
(P201) must be added between these two pieces of equipment to overcome the head loss between
pervaporation membranes and the still column as well as the pipes. Therefore, there will be two extra
subunits to maintain.
It should be mentioned that it was decided to firstly set the pervaporation membranes before the
still column due to the fact that these membrane modules work better with higher water content in the
feed. Thus, a stripping column before will reduce the percentage of water, avoiding a good performance
of the hybrid unit. Furthermore, as mentioned before, the pervaporation unit will be connected to the
vacuum pump P-203 and also a heat exchanger E-204 is added to reach 150 C before this unit. It was
decided not to connect the still column to the vacuum pump P-203, because it was enough to add a
stripping column in which 20% of the vapour outlet stream from flash (V201) is used as stripping gas
and a still column operating at atmospheric pressure to achieve the needed 99.2% wt TEG purity.
Semi-lean TEG will be taken out of the outlet stream of the membrane modules unit, representing
50% of the flow, and injected halfway the absorption column. This will add a new injection pump
(P-103) before the column. Also a turbocharger pressurizing both streams is added to the system to
cut down on size of that pump.
4
Hybrid Process
As was done in chapter 2 the total process will be walked through, describing it step by step. This time
however the newly proposed hybrid system from chapter 3 are added. The new hybrid system will be
sized and designed. Also some comments and schemes about process control are added.
42
4. Hybrid Process
Total
OUT
Stream No
<Dry Gas>
<OVHD-1>
<OVHD>
<Permeate>
3.37 10
Table 4.2: Overall energy balance for the hybrid design case obtained from Aspen Hysys
IN
Stream No
<102>
<Make Up>
<P-102>
<P-103>
<P-201>
<P-202>
<V-203>
<E-204>
Total
OUT
Stream No
<Dry Gas>
<OVHD-1>
<OVHD>
<E-203>
<Permeate>
1.47 10
It was observed that in the case of turndown flow, all the gases from flash Vessel V-201 can be
sent to the overhead treatment. This makes the stripper column C-202 redundant in this case.
43
A/B
A/B
A/B
A/B
A/B
Head [mLc]
692.9
758.2
7.9
15.5
-
Power [kW]
2.04
2.17
0.027
0.045
49
Heating
Table 4.4: Heating duties for the hybrid system
Name
E204
V202
Type
Steam
Gas fired
Power [kW]
61.31
35.56
Cooling
Table 4.5: Cooling duties for the hybrid system
Name
E203
Type
Sea water
Power [kW]
11.37
4. Hybrid Process
44
Figure 4.1: The total flowsheet of the contactor part of the dehydration system. The size of all the equipment shown in the figure has been calculated.
Figure 4.2: The total flowsheet of the regeneration part the dehydration system. The size of all the equipment shown in the figure has been calculated.
46
4. Hybrid Process
Contactor (C-101)
The height of the column in the hybrid system is assumed to be the same as the conventional. This
is because the estimation has been done with trays which later on will be packed. There is significant
space between packing levels for an additional sparger so here there is no gain nor a loss in size.
Table 4.6: Size and weight comparison of both conventional and hybrid contactor column
Type
Conventional
Hybrid
Diameter [m]
2.04
2.04
Height [m]
12.19
12.19
Thickness [mm]
190
190
Weight [kg]
143135
143135
Type
Flash (V-201)
Conventional
Hybrid
Conventional
Hybrid
Conventional
Hybrid
Reboiler (V-202)
Surge (V-203)
Volume
[m ]
0.535
0.313
0.465
0.132
1.16
0.342
Diameter
[m]
0.554
0.46
0.529
0.347
0.719
0.476
Length
[m]
2.217
1.85
2.117
1.392
2.875
1.906
Thickness
[mm]
6
6
6
6
6
6
Weight
[kg]
220
154
201
87.6
370
164
Diameter [m]
0.28
0.145
Height [m]
6.5
6
Thickness [mm]
10
13
Weight [kg]
476
310
47
Table 4.9: Pervaporation membrane module size and weight
Module
Type
Pervap. memb.
Hybrid
Flange
[m]
0.302
Diameter
[m]
0.260
Length
[m]
1.405
Thickness
[mm]
6
Weight
[kg]
97
Type
Pervap. (S-202)
Hybrid
Modules
[Nr]
138
Width
[m]
7
Length
[m]
1.405
Height
[m]
5
Weight
[kg]
13386
the pervaporation membranes. The other added pump, P-201, is used to transport the TEG from the
pervaporation membranes to the still column. The duties of all the pumps are in table 4.11. The duties
of P-102 & P-103 can be lowered however due to the addition of a liquid turbocharger. This will be
discussed further in 5.2.1.
Table 4.11: Pump duties for the hybrid system
Type
P-102 A/B
P-103 A/B
P-201 A/B
P-202 A/B
P-203 A/B
Head [mLc]
692
758.2
7.9
15.5
-
Power [kW]
2.04
2.17
0.027
0.045
49
Weight [kg]
88
88
22
22
1666
48
4. Hybrid Process
The first one is the TEG flow coming from the pervaporation membranes. The second point is the
natural gas outflow from the contactor. The last point is the TEG outflow from the surge. At these point
the consequences and solutions for problems like too much flow or no flow have been considered. The
results of the HAZOP can be found in appendix L.
Resulting the HAZOP, a few actions need to be taken. In the pipeline of point one, after the
pervaporation membranes should be a concentration and a flow meter which need to be connected to
an alarm. If there are inconsistencies in the values that these controls show then there is something
wrong with either the membranes or the pumps. Also there should be a reverse flow prevention in this
pipe. At point 2, after the contactor there should be a flow meter, for when the flow is too little big or
too little either water is not removed from the gas or gas is leaving via an other route. This controller
should also be connected to an alarm. In order to prevent flow problems at point 3, after the surge, a
level controller has been put on the surge and has been connected to the valves controlling the in and
outflow of TEG from the entire system.
The meters that are only connected to an alarm have not been added to the control scheme in
order to keep the figure clear and readable.
Figure 4.3: The total flowsheet with controls for the contactor part of the system.
4. Hybrid Process
50
Figure 4.4: The total flowsheet with controls for the regeneration part of the system.
5
Economic Analysis
In this chapter all investments for both the conventional as the hybrid system are estimated. The
sizes are taken from appendix A. First the total investment costs are estimated using Langs method
and secondly the OPEX is estimated. All economic reduction achieved by the new process are in this
chapter.
5.1. CAPEX
All prices are estimated using the Prijzenboekje of the Dutch Association of Cost Engineers [47]. Except
from C-101, P-101 & P-202. These are estimated using the Matches website [48]. All prices have been
adjusted to 2014 using CEPCI numbers. If a price was found in US dollars an exchange rate of 1.25
euros per dollar was used to convert it [49]. Finally, a factor of 1.25 is used to transform this prices
from USA to EU displacement.
5.1.1. Conventional
Vessels & columns
Table 5.1: CAPEX for all vessels and columns in the conventional process
Equipment
C-101
C-201
C-202
S-201 A/B
V-201
V-202
V-203
Number
1
1
1
2
1
1
1
Diameter (m)
2.04
0.27
0.25
0.0254
0.55
0.53
0.72
Length (m)
12.2
6.5
0.5
2.22
2.12
2.88
Thickness (mm)
190
10
6
6
6
6
Price (Euro)
1,160,000
68,738
27,236
6,459
23,750
23,594
25,781
Pumps
Prices of pumps were estimated with the Prijzenboekje [47].
Table 5.2: CAPEX for all pumps inside the conventional process
Equipment
P-101
P-202 A/B
Number
2
2
Capacity (m /h)
2.3
2.7
Head mLc
1370
20
51
Price (Euro)
19,973
11,932
52
5. Economic Analysis
Number
1
1
1
Area (m )
28.45
147
17.3
Price (Euro)
35,017
89,489
33,720
Total costs
The total investment costs for equipment can be calculated now by adding all these prices. As this
is a fluid and gas plant a Lang factor for process equipment and installation of 5.93 is estimated[50].
This gives a final investment of 9,047,332. As mentioned by frames a conventional unit has a price
between 5-10 million euros, so this estimate seems to be accurate.
5.1.2. Hybrid
Vessels & Columns
For the calculation of a membrane module price, the following assumptions were take into account:
The module is considered as a vessel of SS 316. Therefore with 0.26 m diameter, 1.402 m of
length and 6 mm thickness.
The price of SS 316 is calculated by its weight (97 kg obtained in unit sizing, Chapter 4) following
Matches web page [48]. Then a factor of 1.5 of security is added to account the price of the
membrane elements.
The results for the estimated price of one module are presented in the following table 5.4.
Table 5.4: CAPEX for a pervaporation membrane module
Equipment
PV module
Number
138
Diameter (m)
0.26
Length (m)
1.402
Thickness (mm)
6
Price (Euro)
20,156
From contact with Pervatech, it was given that a module of 4 elements on 50 cm length with a
weight of 10 kg costs about 5,000. Thus, having a module of around 20,000 is totally feasible. The
other vessels are estimated using the same methods as with the conventional process.
Table 5.5: CAPEX for all vessels and columns in the hybrid process
Equipment
C-101
C-201
C-202
S-201 A/B
S-202
V-201
V-202
V-203
Number
1
1
1
2
1
1
1
1
Dimension (m)
D=2.04
D=0.145
D= 0.25
D=0.0254
W=7 and H=5
D=0.46
D=0.35
D=0.48
Length (m)
12.2
6
0.5
1.402
1.85
1.39
1.91
Thickness (mm)
190
13
6
6
6
6
Price (Euro)
1,160,000
73,925
27,236
6,459
2,781,000
22,813
21,563
22,969
5.2. OPEX
53
Pumps
Prices of pumps were estimated with the Prijzenboekje [47].
Table 5.6: CAPEX for all pumps inside the hybrid process
Equipment
P-101
P-102 A/B
P-103 A/B
P-201 A/B
P-202 A/B
P-203
Number
1
2
2
2
2
Capacity (m /h)
2.5/0.8/0.7
0.7
0.7
1.2
0.8
252.3
Head mLc
692
758
7.9
15.5
-
Price (Euro)
12,813
25,625
25.625
13,229
13,229
28.750
Number
1
1
1
1
Area (m )
4.424
24.35
2.64
2.44
Price (Euro)
33,720
35,017
27,236
27,236
5.2. OPEX
As this process only represents one step in a whole offshore process the OPEX is only calculated
regarding the pumping, heating, cooling and some remarks about maintenance will be done. It is
expected that only these factors are changed with the introduction of new technologies.
5.2.1. Pumping
Conventional
In the conventional process two pumps are present, P-101 and P-202. With the specification given in
table 5.7. These were taken from Aspen Hysys simulations.
Table 5.7: Specifications of both pumps in the conventional
Equipment
P-101
P-202 A/B
Total
Number
1
2
3
Capacity (m /h)
2.3
2.7
-
Head mLc
1370
20
-
Hybrid
As pump P-202 is used to compensate the pressure drop in the system it is a vital and unchangeable
part of the process. P-101 however can be powered by using the pressure which is released from
54
5. Economic Analysis
the rich Glycol stream. The total operational costs, assuming a total cost of 10 ct per kWh[36], is
1.34 per hour [37]. Assuming 24/7 operation the total costs per year of this pump will be 11,738.
Using calculation tools provided by Energy Recoverya recovery of 70 % of energy can be achieved.
This will result in a evenly large reduction of operational costs. So a reduction of 8,216 on a yearly
basis can be achieved. Not only that, also a reduction of 9.38 kW is achieved at the pumping section.
This leads to a reduction of approximately 79,866 kg CO which is released on a yearly basis[38]. By
adding a split injection system however the injection pumps change. An additional pump is needed
because of the addition of an extra stream. An extra pump is also needed to transport the TEG from
the pervaporation membranes to the still column. The power duties are displayed in Table 4.11. The
second injection pump makes it harder to have the same beneficial effects of the turbocharger as in
the conventional process as not one stream with more or less the same needs to be pressurized, but
two streams with half the size. Contact has been made with Energy Recovery regarding this. They
mentioned that it is possible to use the power released and transfer it to two separate streams, but
it makes the system less efficient and harder to control. A maximum efficiency of 50% of recovery is
assumed to use in calculations.
Table 5.8: Pump duties for the hybrid system
Type
P-102
P-103
P-201
P-202
P-203
Total
A/B
A/B
A/B
A/B
A/B
Head [mLc]
1426
1647
7.9
15.5
-
Power [kW]
2.040
2.168
0.027
0.045
49
5.2.2. Heating
Conventional
A large energy consumer in this process is the reboiler. From Aspen Hysys the energy requirement is
calculated. The figure found there is 241.35 kW for heating. Assuming an efficiency of 90% for a gas
fired heater and a gas price of 0.07 per kWh a total yearly cost of 164,439 for natural is needed[36].
This figure can drop however as the natural gas coming from the flash can be used as a free source
of natural gas.
Table 5.9: Heating duties for the conventional system
Name
V-202
Type
Gas fired
Power [kW]
241.35
Hybrid
In the hybrid system heating is done at two places. Firstly before the pervaporation membranes and
secondly in the reboiler section. It is chosen, for weight limiting reasons, to use heat exchange with
steam before the pervaporation. The amount of steam needed is calculated via the total flux needed.
A price of 25 per ton is assumed[51] [52]. The reboiler will still be heated using a gas fired heater.
Table 5.10: Heating duties for the hybrid system
Name
E-204
V-202
Type
Steam
Gas fired
Power [kW]
61.31
35.56
5.2. OPEX
55
5.2.3. Cooling
Conventional
Table 5.11: Energy duties needed for cooling in conventional
Location
E-203
C-201
Type
Sea water cooler
TEG condenser
kg/h needed
8,988 kg/h seawater
-
The condenser is cooled using the rich TEG before flash. By using this heat integration the heating
duty of the reboiler is lowered and this cooling can be performed for free. For the cooling of the lean
TEG before entering the absorption column sea water is used. As the process is done off shore this
water can be gained for free as well. The water needed is calculated using the method as described in
A.
Hybrid
Table 5.12: Energy duties needed for cooling in hybrid
Location
E203
C201
Type
Sea water cooler
TEG condenser
kg/h needed
978.3 kg/h seawater
-
As shown in Table 5.13 the total expenses towards energy are reduced. Yearly almost 70,000 is
saved due to better energy use. The introduction of pervaporation membranes and the use of a split
flow has decreased the energy needed for the reboiler with 85%. Furthermore the introduction of a
liquid turbocharger and the overall lower TEG inventory has decreased the total kWh per year needed for
pumping of TEG with 70%. The addition of a vacuum pump at the pervaporation membranes however
has a relatively high duty in comparison with the other pumps of 49 kW needed. The introduction
of these new innovation has a positive effect on OPEX and total energy consumption making this a
greener alternative to the conventional process.
6
Creativity & Group Process Methods
In the following chapter of the project, several strategies for improving the teams development and
creativity have been carried out in order to facilitate the communication, coherence and connection
within the team as well as generation of new technological ideas. The results are shown below ordered
by date. After this the project planning and creativity methods used are described.
58
weaknesses of each member are known in the whole group, so everyone try to overcome his/her own
problems with the help and support of the others. It must be taken into account also all the feedback
received from the people involved in the project, creating a ping-pong information chain where all
information, advises and critics were considered. For those reasons, some activities were done as
mentioned below:
(27-04-2015) Creation of an online database: All the files and documents related to the project
were shared with team members and supervisors. In this way, information was available for
everyone anytime.
(27-04-2015) Creation of a calendar: Definition of task distribution according to team members
allocation, main milestones and tentative deadlines, in order to define a structured planning of
the whole project.
(27-04-2015) Creation central mail account: This was used as the main communication hub. In
that way everyone could look back in previous contact with whomever and have always a clear
view of what was going on.
Everydays meeting in the morning: Revision of the calendar and project development, what
had been done, needed to be improved or changed. Below, it is shown a summary of the main
decisions taken in each week because of these meetings.
Week 1 (from 27-05 to 01-05): After having the first meeting with the technical supervisor
and with the creativity coach in this week, we defined the main points to be discussed in the
kick-off meeting with Frames principals as well as the tools we were going to use for the
generation of new alternatives of the process (See section 6.2 Creativity tools and results).
Week 2 (from 04-05 to 08-05): Visiting our principals in Frames building situated in Alphen
aan den Rijn resulted in a enriching and valuable experience. It gave us the opportunity to
get to know each other and discuss several points that were unclear. For instance, the scope
of the project, the alternatives to be investigated and the conditions used as reference were
defined. In addition, two of the alternatives shown were criticized (Molecular sieves + TEG
unit and Super X-packing) due to the fact that they do not meet the objectives. A tentative
planning was also proposed and approved. (See section 6.3 Process planning).
Week 3 (from 11-05 to 15-05): With all the feedback and the points clear we made a series
of creativity activities in order to generate more alternatives apart from the ones Frames
principals gave us. The result was the finding of three realistic technologies that can be used
in this unit, and that will be presented in the Basics of Design (BoD) meeting scheduled for
week 5. In this week 3, we also had a meeting with P. Hamersma, where some questions
were posed, clarifying that we need to be more specific and consistent in our selection of
alternatives, including quantitative descriptions and equipment functioning principles and
fundamentals. In this way, knowing how the piece of equipment really works, we would
understand how to improve it and why one alternative is more suitable than other. Hence,
we started the (BoD) with all the input required.
Week 4 (from 18-05 to 22-05): We still worked in the BoD and the design of the process
in Aspen Plus, scheduled to be handed-in on 22nd May. We had a meeting with B. Dam
to discuss about the results of the creativity tools. It was pointed out that more images
and tables would be used, because they are the best option to shown a list of alternatives,
instead so much text. The BoD report was given to all implicates for review and feedback.
Week 5 (from 25-05 to 29-05): In the BoD meeting, where all people involved in the project
were present, the final 8 technological possibilities were shown. It was decided to follow
with hybrid one, in which it would be used split injection, turbochargers and a combination of
still column heated by microwaves and pervaporation membranes (See section 3 Innovation
map). It was also settle the conventional process that would work as benchmark as well as
the change into Aspen Hysys to simulate the process, because Aspen Plus does not fulfill
some requirements. Furthermore, some professors and specialists in microwave heating
and pervaporation membranes were contacted such as PhD. Guido Sturm.
59
Week 6 (from 01-06 to 05-06): It was introduced an important change in the simulation.
Now the feed of wet natural gas is saturated before entering the column, which will be the
worst scenario possible for the unit. Then, the conventional process was finished. The size
and price of the unit is decided as benchmark. The project follows as scheduled and not
more important changes are made.
Week 7 (from 08-06 to 12-06): The company Sairem was contacted regarding microwaves
generators and prices of them were obtained and incorporated to the unit.
Also, Mr. Sturm gave us his advice about microwaves, stating that they are feasible in
concept, but no company has tried yet.
Week 8 (from 15-06 to 19-06): On Monday the 15th June, the final draft report was submitted to all the parts involved in the project in order to get feedback of it.
Furthermore, an important change was introduced. Finally, all results led to bad performance as well as an increment of the unit price when microwaves are incorporated due to
the immaturity of this devices yet. Therefore, it was decided to erase them of the hybrid
proposed solution.
Finally, Pervatech was asked to provide details of the membranes modules used in the design.
Week 9 (from 22-06 to 26-06): The comments on the draft report were given and included
in the final report. It was submitted on Friday 26th.
Meetings with creativity coach, technical supervisor, professors or experts: Discussion of main
doubts and problems as well as forecasts for the next steps.
Dr. P. J. Hamersma, Technical supervisor: Thanks to the experience of the technical supervisor, we were able to go on with the project every time a problem arose, especially in
the selection of improvements for the conventional process. He pointed out that the best
way to overcome any problem is understanding the chemistry behinds it. This advice was
followed in every piece of equipment in order to come up with new technologies that will
improve the performance of the unit. Moreover, he mentioned that every figure, graph
or image should contribute with valuable information and should be followed by extensive
explanatory description.
Dr. B. Dam, Creativity coach: His contribution was very important in the generation of new
ideas. He provided us with another approach of the project where the technical rules were
not the most important aspect, implementing the creativity of new designs. Team division,
progression and the roles of each member were followed by him with relevant feedback
about our behaviour within the team.
(18-05-2015) Ir. S. Groenendijk, Process Eng. at Fluor: He solved our doubts about the
turndown case, ending in decreasing only 50% the amount TEG compared to the design
case, because less can create cavitation and the still column can start weeping. After consulting principals from Frames, it was decided to maintain only 33% of the TEG.
(28-05-2015) Pr. A. Stankiewicz, Professor: As process intensification expert, he helped
us in the definition of our improved process, giving tips and boundaries such as realistic
temperatures for microwave heating that could not be found in literature. He also proposed
a radical new design based on rotating packed beds.
(28-05-2015) J. James, PDeng: Mr. James shared with us his knowledge about Aspen and
tips on the relationship between high pressure systems and the thermodynamic model used
in the simulation, resulting in different model for each piece of equipment that simulates
better the process.
(29-05-2015) M. Radiou, R&D Eng at Sairem: Always ready to help regarding to microwave
systems, she gave us some useful information as well as prices for such devices.
(9-06-2015) G. Sturm, PhD: As a PhD in P&E institute at TU Delft, he shared with us his
microwave related thesis where we could find information about how this equipment works
intrinsically.
(14-06-2015) Prof. Dr. Ir. Anton A. Kiss, R&D Eng at AkzoNobel: With his advise over the
pervaporation membranes, we were able to complete the Aspen Hysys simulation.
60
Besides those activities, we do believe that productivity and efficiency can be enhanced if there is
a relax atmosphere in the group. So, we also take into account the relationships between us:
Weekly dinner: Taking advantage of our international team, we decided that everyone needs to
hold a dinner with food of his/her own country, and it seems it is working perfectly.
Card games: During breaks, we play different card games to chill out and rest from the project
itself, resulting in a better work environment.
61
Eventually, it came that among the last 4 selected ideas, 1 was of each member. The most
probable reason for this can be that each of us strives for his/her own ideas, while also we
support other choices, always maintaining the balance in the group.
(15-05-2015) Collage: This method is the way to view your problem in a total overview of what
you know about it. By printing out images and facts about the problem, new connections, previously unseen, can arise. This was the last approach used in the basic of design and generation
of ideas. In our case the problem of size is a nice one to try to observe in this manner. By looking for connection between different process steps, maybe a scale down or a potential different
connection which we have not seen before could be found.
The team members needed to collect data and 5 images about the problem we are struggling
with. The process of choosing images should be totally random and nothing should be hold back
because it does not seem to fit in the scope of your problem. Everything was hang upon the wall
in our office and after the group started arranging everything in one way or another to look for
new plans or methods to implement in the system.
Figure 6.1: Planning used during the project. There are three main phases: Preparation stage(left
orange line), conceptual stage (middle orange line) and feasibility & development stage (right orange
line).
Preparation stage
The main focus is laid upon the question if this project is worth pursuing. Initial goals and deadlines
were stated and planned as shown in Figure 7.1. The first alternatives would be briefly researched to
62
get a preliminary feeling about them all. The preparation stage ended on the 7th of May, and the kick
off meeting was conducted on that day, too.
Concept stage
During the concept stage the work revolved around the process itself, what are customer requirements
and how to get there. The existing process was worked out to provide a benchmark for later improvements. All different improvements suggested before were divided between the team and everyone did
a more extensive research into them. The first Aspen Plus simulation was made to provide a benchmark for calculation of the impact of the different technological improvements in the feasibility stage.
Furthermore all the data needed to calculate later on was searched and inventoried for later use. This
phase would lead to a BoD report which will be finished 22nd May, whereas, on 27 May the report was
presented.
Feasibility & Development stage
Last stage of the project. The team worked on implementing the new technologies selected and seeing
the impact they would have upon the process. Financial calculation was done to estimate the CAPEX
and OPEX of the new and old system to see demonstrate the way improvements helped. Weight
estimates needed to be made to compare them as well. Also, the final report was produced in this
stage, ending on 30th June with the final presentation.
7
Conclusions & Recommendations
When taking in account all the information given throughout the report, it can be concluded that the
introduction of semi-lean TEG injection, pervaporation membranes modules and liquid turbochargers
leads to a lot of changes in CAPEX and OPEX, while the weight of the total new unit does not change
too much, but remaining within the same range. This can however be due to error margins of the
calculations done.
First of all, by introducing the specific combination of techniques, the CAPEX has doubled. All existing equipment from the conventional process, except the absorption column, have been reduced.
However, the investment costs for the special kind of membranes used for pervaporation is so large
that the benefits from using smaller equipment are counteracted. So, this separation technology may
become interesting in terms of CAPEX if in coming years it matures, achieving more effective membrane area per module with the same water selectivity, leading to higher permeate fluxes. Then this
investment price will drop drastically. It should be pointed out that the price estimation for pervaporation membrane modules a very crude one, due to the lack of reliable information and the scale of the
project. For instance, Pervatech themselves did not know the possible prices of this proposed large
pervaporation system. Hence, because of this uncertainty, the margin of error in cost estimation of
the hybrid process is much larger than that of the conventional.
On the other hand, the OPEX has been lowered a lot in comparison to the conventional system.
A total saving of almost 70,000 per year has been achieved. This was solely done by savings in
energy, which makes the hybrid system a more energy efficient and greener alternative compared to
the conventional process.
Furthermore, as mentioned, the weight of the total unit has increased from 150 tons for the conventional dehydration system to 160 for the hybrid system. But as mentioned before, this approximately
10,000 kilograms gain is so low that it lies within the calculation error.
To sum up, the introduction of pervaporation membranes has decreased the total energy consumption, but it increased the total capital expenses, leading to a rate of return for all the changes introduced
of around 200 years, which is too long for this kind of industry. As stated, if the surface area of the
membranes increases and so the total capital expenses decreases, then membranes can be a good
option for improving TEG dehydration. However, as these membranes are currently too expensive, it
is not advisable to add them to the process now.
Liquid turbochargers however have decreased 70% of the power needed for TEG transport. Accordingly, this decrease is a feasible help in energy demand reduction, as for TEG pumps the energy
consumption in the conventional system is really high. For this reason, they are already being deployed
in process industry. The recommendation is to add these TEG turbochargers to newly developed processes and to implement them in already existing plants since this is also possible.
Finally, the injection of semi-lean TEG into the absorption column has sized down the reboiler and
surge vessel with 30% even when it has not been optimized yet. Thus, room for improvement are
analyzing different injection points in the column, purity of semi-lean TEG and flow of split optimizing
63
64
the gain of this setting. However, because the pervaporation membranes are not present in the conventional process, there is not an easy way of getting semi-lean TEG from the regeneration unit. For
instance, the still column needs to have an additional middle outlet altering the design of the distillation equipment. For this purpose, a distillation column can be considered first to achieve the necessary
semi-lean TEG purity, sending afterwards the stream to other possible technologies such as molecular
sieves where to reach the total lean purity required (99.2% in our Hybrid case). To find out if this is
beneficial will requires a completely new research project.
List of Symbols
P
Density [kg/m ]
Surface [m ]
Downcomer are [m ]
f*U
Height [m]
Length [m]
66
Volume of vessel [m ]
wt%
Weight percent
A
Unit sizing
In this appendix all different technique for size estimation are explained. To enhance readability example calculations regarding the conventional process are included.
4
( )
(A.1)
With:
G = Mass flow rate of gas [kg/s]
f*U = fraction of the vapor flooding velocity [m/s]
= Density of vapor [kg/m ]
The vapor flooding velocity is calculated using the correlation proposed by Fair et al [53], which
was edited by Seider et al [16]. This results in a contactor diameter of 2.04 m. Aspen Hysys gives
an estimate of 2.3 meters. The height of packing coming from Aspen Hysys simulations is 3.5 meters.
For Mellapack packing from Sulzur Corp. the HETP is defined in the range of 0.5 to 0.7 meters[54].
Using 6 theoretical stages this results in a range of 2.1 to 4.2 meters of packing height. For this project
a packing height of 3 meters is used and a diameter of 2.3 meters. As the packing is assumed to be
25% of the contactor the total height is estimated to be 12 meters. The wall thickness t is calculated
to be 20 cm using the Sieder et al [16] method which uses equation A.3. In this equation the design
pressure is considered to be 1.1 times the operating pressure since the operating pressure is above
1000 psig. For vertical columns wind and seismic loads are to be taken into account,too. The thickness
of vessel required to withstand these effects have been calculated using the following equation[16]:
=
0.22 ( + 18)
(A.2)
With:
D = external vessel diameter [inches]
t =Wall thickness of vessel [inches]
S = maximum allowable stress of the shell material at design temperature [pounds/inch ]
L = tangent-to-tangent height of the column[inches].
Where the term 18 ( in inches) accounts for the column cage ladders. This method assumes a wind
load based on the wind velocity of 140 miles/hr acting uniformly over the height of the column.
67
68
A. Unit sizing
The wall thickness to withstand pressure is calculated using the ASME pressure vessel code formula
[16]:
=
2 1.2
(A.3)
With:
P = internal design pressure [psig]
S = maximum allowable stress of the shell material at design temperature [pounds/inch ]
E = Fractional weld efficiency
With the following assumptions:
For pressures between 0-5 psig, P has been taken to be 10psig.[16]
For pressures between 10 psig to 1000 psig, the following equation has been used: P
exp{0.60608+ 0.91615[ln(P )]+0.0015655[ln(P )] }[16]
Maximum allowable stress of carbon steel has been taken to be 15000 pounds/inch [16]
Minimum thickness has been assumed in all cases to be 6mm. [16]
The average vessel thickness t is calculated as the average of t and t +t as described in Seider
et al [16]. The t will be needed at the top of the vessel and t +t at the bottom. A linear gradient of
wall thickness is assumed.
1
)(
)
(A.4)
With:
F = liquid flowrate [kg/hr] V =Volume of vessel [m ]
= residence time [hr]
= Density liquid [kg/m ]
With the following assumptions:
For V-201 and V-203, the liquid fraction has been assumed to be 0.8, whereas that for V-202 the
same has been considered to be 0.5.
The residence times for vessels V-201,202 and 203 have been taken as 10, 5 and 20 min respectively.
The flowrates and the densities for the respective streams have been taken from Aspen Hysys.
See Appendix C.
Which gives the following results for the surge, flash & reboiler.
The aspect ratio,
Which gives the following results for the flash, reboiler & surge.
69
Volume [m ]
0.535
0.465
1.16
Vessel
V-201
V-202
V-203
Diameter [m]
0.554
0.529
0.719
Length [m]
2.217
2.117
2.875
[58]
Surface area [m ]
28.45
147.0
17.3
(A.5)
(A.6)
70
A. Unit sizing
4
( ) (1
(A.7)
With:
A = Downcomer area,
A = Tower inside cross-sectional area,
The fraction A /A is calculated as per the following equations:
= 0.1
(A.8)
= 0.1 +
if 0.1<= F
0.1
9
(A.9)
=2
(A.10)
if F >= 1.0. This results in Still Column Diameter of 0.277 m or 27.7 cm and height of 6.5 m (which
includes tray spacing height, height for disengagement at the top and height of holdup of 5min at the
bottom assuming it is not mounted directly on reboiler).
The wall thickness for the still column has been calculated on the same lines as that of the contactor,
but by using criteria of lower operating pressures. The average column thickness is thus estimated to
be 10 mm.
(A.11)
With:
P = Pressure rise in the pump[kPa],
h = height of liquid column [m],
=density of the liquid [kg/m ].
The power requirement for the two- pumps was obtained as a result of Hysys simulation.
Finally, all of this has been tabulated in table A.4:
Pump
P-101A/B
P-202A/B
Head [mlc]
1370
20
Power [kW]
13.4
0.155
71
(pi/4)0.1143 =0.01 m . Hence, if there are 7 elements, each element (plus the space needed surrounding it for the water vapour flow) is 0.01/7=0.0014 m .
In our case, it is required a number of 37 elements per module, so 0.001437=0.053 m of circular
surface, which transformed into diameter is 0.260 m (260mm) of vessel tube.
Then, as stated in table 3.5, 509 m are needed. The module designed will provide 3.7 m of
effective membrane are, representing 509 / 3.7 = 138 modules. It is assumed that there is no especial
requirements for the space such as a particular length or height. Hence, it was selected a rectangular
14x10 modules disposition in parallel. As we only need 138 modules, there is space for 2 more modules.
The separation between modules is calculated as follows. The figure A.1 shows that for a PVM-094
SS 316 74-tube module the height is 100 mm from the center of the tube. From those 100 mm, we
subtract 114.3 / 2 = 57.15 mm of radius, leading to 42.85 mm of height taken from the outer part of
the vessel circumference until the highest point of the tube to be added to the diameter. Therefore,
260 mm + 42.85 mm = 302.85 mm, around 0.302 m of actual diameter of flange. If 14 modules are
set in parallel, the total width is 14 0.302 = 4.24 m. However, a security factor of 50% is taken in
order to count the pipes needed between modules for the vapour flow as well as maintenance duties,
resulting in 6.36 m, which is normalized to 7 m width.
For the height, we have 10 modules in parallel resulting in 10 0.302 = 3.02 m. Following the same
reasoning, the security factor of 50% is taken. The total height is 4.53 m, which is normalized to 5 m.
Furthermore, the length will be taken as equal due to the fact that the membrane length and type
is the same (silica membrane of 120 cm) as in the PVM-094 SS 316 74-tube module. Hence, the
length will be 1.405 m.
72
A. Unit sizing
= 1.3 (
(A.12)
With:
D = outside diameter [inches]
E = modulus of elasticity [psi], 27.610 for SS 316. [60]
P = internal design pressure [psig] for operating pressures between 0 and 5, 10 psig should be taken
[16]. L = vessel length [inches]
However, to the value of t the following correction, t
must be added
= (0.18 2.2) 10
0.19
(A.13)
(A.14)
t [mm]
1.4
t [mm]
4.6
t [mm]
6.0
B
Used graphs
73
74
B. Used graphs
The incoming lean TEG is assumed to be in equilibrium with the outgoing dry gas. This graph, therefore, provides the minimum concentration of lean TEG required for dehydration when the Contactor
temperature (which is inlet gas temperature assuming the contactor to be isothermal) and Equilibrium
water dew point of gas obtainable at temperature is known.
Figure B.1: Equilibrium Water Dew Point in C versus Inlet Gas Temperature [15]
75
From the water content of the outgoing dehydrated gas, its dew point at the contactor temperature
and pressure is calculated using this graph. A conservative approach of about 8.5 C [15]is subtracted
from the dew point estimated from the graph.
Figure B.2: Water Content of Sweet Natural Gas , kg/(10 std m ) (100 kPa and 15 C) vs Water Dew
point in C [15]
C
Flow sheet conventional design
77
Figure C.1: The total flowsheet and model used in hysys, the mass balances are in the following appendices
D
Stream Summary - Conventional
Design Case
Table D.1: Stream Summary - Conventional Design
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liq Volume Flow [m3/h]
Heat Flow [kJ/h] (*10^5)
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liq Volume Flow [m3/h]
Heat Flow [kJ/h]
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liq Volume Flow [m3/h]
Heat Flow [kJ/h]
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liq Volume Flow [m3/h]
Heat Flow [kJ/h]
<001>
0
35
157
555090
9999999
10020
-158126,43
<201>
0
55
156
26
2717
2
-16,07
<207>
0
170
3
25
2707
2
-15,10
<214>
0
82
2
18
2594
2
-13,91
<002>
0
35
157
556744
10043330
10110
-158436,62
<202>
0
94
156
26
2717
2
-15,75
<208>
0
204
1
19
2587
2
-13,01
<215>
0
34
1
18
2594
2
-14,28
79
<101>
1
35
157
19438
380657
1112
-1783,75
<203>
1,56E-02
98
4
26
2717
2
-15,75
<209>
1
201
1
1
30
0
-0,22
Make Up
0
35
1
0
24
0
-0,13
<102>
1
35
157
17784
337325
1022
-1473,70
<204>
1
98
4
0
10
0
-0,05
<210>
0
201
1
18
2567
2
-12,84
OVHD
1
98
1
8
149
0
-1,80
<103>
0
35
157
18
2594
2
-14,23
Waste
0
98
4
0
0
0
0,00
<211>
0
199
1
18
2592
2
-12,97
<104>
0
35
157
26
2717
2
-16,23
<205>
0
98
4
25
2707
2
-15,70
<212>
0
199
3
18
2592
2
-12,97
DRY GAS
1
35
156
17776
337203
1021
-1471,69
<206>
1,99E-04
98
3
25
2707
2
-15,70
<213>
0
123
2
18
2594
2
-13,59
80
<001>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
1,0000
0,0000
0,0000
0,0000
0,0000
<201>
0,0016
0,0002
0,0004
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9385
0,0547
0,0000
0,0008
0,0009
0,0007
<207>
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9420
0,0548
0,0000
0,0003
0,0005
0,0005
<002>
0,0017
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9957
0,0000
0,0025
0,0000
0,0000
<202>
0,0016
0,0002
0,0004
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9385
0,0547
0,0000
0,0008
0,0009
0,0007
<208>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9895
0,0105
0,0000
0,0000
0,0000
0,0000
<101>
0,7087
0,0819
0,0491
0,0264
0,0089
0,0033
0,0038
0,0044
0,0049
0,0003
0,0004
0,0005
0,0005
0,0000
0,0000
0,0026
0,0805
0,0146
0,0092
<203>
0,0016
0,0002
0,0004
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9385
0,0547
0,0000
0,0008
0,0009
0,0007
<209>
0,1443
0,0186
0,0272
0,0129
0,0062
0,0000
0,0000
0,0000
0,0000
0,0004
0,0007
0,0014
0,0013
0,3378
0,3467
0,0005
0,0483
0,0351
0,0185
<102>
0,7501
0,0892
0,0545
0,0296
0,0100
0,0037
0,0043
0,0049
0,0055
0,0002
0,0003
0,0005
0,0005
0,0000
0,0004
0,0028
0,0166
0,0164
0,0104
<204>
0,4325
0,0564
0,0837
0,0412
0,0192
0,0000
0,0000
0,0000
0,0000
0,0017
0,0023
0,0020
0,0018
0,0004
0,0398
0,0014
0,1479
0,1103
0,0592
<210>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9931
0,0067
0,0000
0,0000
0,0000
0,0000
<103>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9932
0,0067
0,0000
0,0000
0,0000
0,0000
Waste
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9420
0,0548
0,0000
0,0003
0,0005
0,0005
<211>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9932
0,0067
0,0000
0,0000
0,0000
0,0000
<104>
0,0016
0,0002
0,0004
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9385
0,0547
0,0000
0,0008
0,0009
0,0007
<205>
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9420
0,0548
0,0000
0,0003
0,0005
0,0005
<212>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9932
0,0067
0,0000
0,0000
0,0000
0,0000
DRY GAS
0,7504
0,0892
0,0545
0,0296
0,0100
0,0037
0,0043
0,0049
0,0055
0,0002
0,0003
0,0005
0,0005
0,0001
0,0000
0,0028
0,0166
0,0164
0,0104
<206>
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9420
0,0548
0,0000
0,0003
0,0005
0,0005
<213>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9932
0,0067
0,0000
0,0000
0,0000
0,0000
81
<214>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9932
0,0067
0,0000
0,0000
0,0000
0,0000
<215>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9932
0,0067
0,0000
0,0000
0,0000
0,0000
Make Up
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9940
0,0060
0,0000
0,0000
0,0000
0,0000
OVHD
0,0296
0,0040
0,0068
0,0037
0,0023
0,0000
0,0000
0,0000
0,0000
0,0025
0,0058
0,0124
0,0110
0,0000
0,8797
0,0001
0,0142
0,0154
0,0125
E
Stream Summary - Turndown Case
Table E.1: Stream summary turndown case hybrid
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liquid Volume Flow [m3/h]
Heat Flow [kJ/h] [*10^5]
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liquid Volume Flow [m3/h]
Heat Flow [kJ/h] [*10^5]
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liquid Volume Flow [m3/h]
Heat Flow [kJ/h] [*10^5]
Name
Vapour Fraction
Temperature [C]
Pressure [bar]
Molar Flow [kgmole/h]
Mass Flow [kg/h]
Liquid Volume Flow [m3/h]
Heat Flow [kJ/h] [*10^5]
<001>
0
35
157
55509
1000000
1002
-158126,45
<201>
0
55
156
7
897
1
-49,75
<207>
0
176
3
7
891
1
-46,35
<214>
0
80
2
6
877
1
-46,98
<002>
0
35
157
55674
1004333
1011
-158437,17
<202>
0
92
156
7
897
1
-48,77
<208>
0
204
1
6
884
1
-44,42
<215>
0
31
2
6
877
1
-48,27
83
<101>
1
35
157
1944
38062
111
-1783,58
<203>
0
96
4
7
897
1
-48,77
<209>
1
199
1
1
15
0
-1,01
MAKE UP
0
35
1
0
7
0
-0,40
<102>
1
35
157
1778
33729
102
-1473,56
<204>
1
96
4
0
6
0
-0,25
<210>
0
199
1
6
875
1
-43,66
OVHD
1
90
1
1
22
0
-2,04
<103>
0
32
157
6
877
1
-48,10
WASTE
0
96
4
0
0
0
0,00
<211>
0
198
1
6
882
1
-44,06
<104>
0
35
157
7
897
1
-50,29
<205>
0
96
4
7
891
1
-48,52
<212>
0
198
3
6
882
1
-44,06
DRY GAS
1
35
156
1777
33709
102
-1471,37
<206>
0
96
3
7
891
1
-48,52
<213>
0
117
2
6
877
1
-46,00
84
<001>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
1,0000
0,0000
0,0000
0,0000
0,0000
<201>
0,0033
0,0006
0,0007
0,0003
0,0002
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9692
0,0202
0,0000
0,0010
0,0012
0,0010
<207>
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9756
0,0203
0,0000
0,0002
0,0006
0,0006
<002>
0,0017
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9957
0,0000
0,0025
0,0000
0,0000
<202>
0,0033
0,0006
0,0007
0,0003
0,0002
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9692
0,0202
0,0000
0,0010
0,0012
0,0010
<208>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9893
0,0104
0,0000
0,0000
0,0000
0,0000
<101>
0,7088
0,0819
0,0491
0,0264
0,0089
0,0033
0,0038
0,0044
0,0049
0,0003
0,0004
0,0005
0,0005
0,0000
0,0000
0,0026
0,0805
0,0145
0,0092
<203>
0,0033
0,0006
0,0007
0,0003
0,0002
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9692
0,0202
0,0000
0,0010
0,0012
0,0010
<209>
0,1886
0,0332
0,0318
0,0129
0,0059
0,0000
0,0000
0,0000
0,0000
0,0008
0,0017
0,0045
0,0042
0,3262
0,2878
0,0003
0,0450
0,0368
0,0202
<102>
0,7502
0,0892
0,0545
0,0296
0,0100
0,0037
0,0043
0,0049
0,0055
0,0002
0,0003
0,0005
0,0005
0,0000
0,0004
0,0028
0,0165
0,0164
0,0104
<204>
0,4854
0,0859
0,0832
0,0346
0,0154
0,0001
0,0001
0,0001
0,0000
0,0018
0,0024
0,0020
0,0018
0,0005
0,0161
0,0009
0,1174
0,0978
0,0544
<210>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9941
0,0056
0,0000
0,0000
0,0000
0,0000
<103>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9941
0,0056
0,0000
0,0000
0,0000
0,0000
WASTE
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9756
0,0203
0,0000
0,0002
0,0006
0,0006
<211>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9941
0,0057
0,0000
0,0000
0,0000
0,0000
<104>
0,0033
0,0006
0,0007
0,0003
0,0002
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9692
0,0202
0,0000
0,0010
0,0012
0,0010
<205>
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9756
0,0203
0,0000
0,0002
0,0006
0,0006
<212>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9941
0,0057
0,0000
0,0000
0,0000
0,0000
DRY GAS
0,7506
0,0892
0,0545
0,0296
0,0100
0,0037
0,0043
0,0049
0,0055
0,0002
0,0003
0,0004
0,0005
0,0001
0,0000
0,0028
0,0165
0,0164
0,0103
<206>
0,0001
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0002
0,0005
0,0008
0,0007
0,9756
0,0203
0,0000
0,0002
0,0006
0,0006
<213>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9941
0,0056
0,0000
0,0000
0,0000
0,0000
85
<214>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9941
0,0056
0,0000
0,0000
0,0000
0,0000
<215>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0001
0,0001
0,9941
0,0056
0,0000
0,0000
0,0000
0,0000
MAKE UP
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9940
0,0060
0,0000
0,0000
0,0000
0,0000
OVHD
0,1314
0,0242
0,0259
0,0112
0,0061
0,0000
0,0000
0,0000
0,0000
0,0091
0,0193
0,0304
0,0270
0,0000
0,5889
0,0002
0,0398
0,0488
0,0376
F
Microwave heating model
Figure F.1: Model used in Hysys to estimate energy consumption in a microwave heated column
87
G
Split flow model
89
Figure G.1: Model used in Hysys to model split flow injection in the absorption column
H
Model used for hybrid system
91
Figure H.1: The total flowsheet and model used in hysys, the mass balances are in the following appendices
I
Stream Summary - Hybrid: Design
Flow
93
94
<102>
1,0000
35
157
17784
337306
1022
-1,47E+09
Waste
0,0000
42
4
0
0
0
0,00E+00
<208>
0,0000
204
1
5
763
1
-3,81E+06
<211>
0,0000
198
1
5
785
1
-3,93E+06
<101>
1,0000
35
157
19438
380629
1112
-1,78E+09
<207.6>
5,64E-03
150
2
5
764
1
-3,93E+06
DRY GAS
1,0000
36
156
17777
337197
1021
-1,47E+09
<205>
0
42
4
18
1657
1
-1,04E+07
<209>
1,0000
203
1
0
3
0
-1,84E+04
<214>
0
52
2
5
786
1
-4,28E+06
<207.1>
0,0048
150
3
18
1657
1
-9,86E+06
<207.7>
4,75E-03
150
2
5
764
1
-3,93E+06
<104>
0,0000
35
157
18
1660
1
-1,04E+07
<203>
8,14E-03
42
4
18
1660
1
-1,04E+07
<210>
0,0000
203
1
5
761
1
-3,79E+06
<215>
0
35
2
5
786
1
-4,32E+06
<207.2>
0,0056
150
2
11
1527
1
-7,86E+06
<201>
0,0000
36
156
18
1660
1
-1,04E+07
<206>
9,35E-05
42
3
18
1657
1
-1,04E+07
<213>
0,0000
57
2
5
786
1
-4,27E+06
<103>
0
37
156
5
786
1
-4,30E+06
<207.3>
5,64E-03
150
2
5
764
1
-3,93E+06
<202>
0,0000
38
156
18
1660
1
-1,04E+07
<207>
4,14E-04
108
3
18
1657
1
-1,01E+07
<212>
0,0000
198
3
5
785
1
-3,93E+06
<204.2>
1
42
4
0
1
0
-3,07E+03
<207.4>
0,0000
159
157
5
764
1
-3,90E+06
<204>
1,0000
42
4
0
3
0
-1,53E+04
OVHD
1
70
1
0
3
0
-1,54E+04
Make Up
0,0000
35
1
0
24
0
-1,33E+05
OVHD-1
1
42
4
0
3
0
-1,23E+04
<207.5>
0,0000
159
157
5
765
1
-3,91E+06
95
Table I.2: Mass fraction design case 1/2
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
<102>
0,7502
0,0892
0,0545
0,0296
0,0100
0,0037
0,0043
0,0049
0,0055
0,0002
0,0003
0,0005
0,0005
0,0000
0,0004
0,0028
0,0166
0,0164
0,0104
<203>
0,0011
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9101
0,0845
0,0000
0,0007
0,0007
0,0006
<213>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0002
0,0002
0,0003
0,9928
0,0062
0,0000
0,0000
0,0000
0,0000
<104>
0,0011
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9101
0,0845
0,0000
0,0007
0,0007
0,0006
<206>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9119
0,0847
0,0000
0,0004
0,0006
0,0005
<212>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0002
0,0002
0,0003
0,9928
0,0062
0,0000
0,0000
0,0000
0,0000
<201>
0,0011
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9101
0,0845
0,0000
0,0007
0,0007
0,0006
<207>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9119
0,0847
0,0000
0,0004
0,0006
0,0005
Make Up
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9920
0,0080
0,0000
0,0000
0,0000
0,0000
<202>
0,0011
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9101
0,0845
0,0000
0,0007
0,0007
0,0006
OVHD
0,1184
0,0129
0,0871
0,0761
0,0721
0,0000
0,0000
0,0000
0,0000
0,0273
0,0220
0,0174
0,0197
0,0000
0,1793
0,0847
0,1109
0,0904
0,0816
<211>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0002
0,0002
0,0003
0,9928
0,0062
0,0000
0,0000
0,0000
0,0000
<204>
0,5557
0,0585
0,0933
0,0455
0,0139
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0003
0,0002
0,0000
0,0050
0,0028
0,1503
0,0531
0,0207
<208>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,0003
0,0003
0,0003
0,9912
0,0073
0,0000
0,0000
0,0001
0,0001
<214>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0002
0,0002
0,0003
0,9928
0,0062
0,0000
0,0000
0,0000
0,0000
Waste
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9119
0,0847
0,0000
0,0004
0,0006
0,0005
<209>
0,1250
0,0128
0,0242
0,0178
0,0114
0,0000
0,0000
0,0000
0,0000
0,0222
0,0189
0,0161
0,0183
0,3358
0,3070
0,0007
0,0374
0,0257
0,0268
<215>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0002
0,0002
0,0003
0,9928
0,0062
0,0000
0,0000
0,0000
0,0000
<205>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9119
0,0847
0,0000
0,0004
0,0006
0,0005
<210>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0002
0,0002
0,0003
0,9928
0,0062
0,0000
0,0000
0,0000
0,0000
<103>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0002
0,0002
0,0003
0,9928
0,0062
0,0000
0,0000
0,0000
0,0000
96
<204.2>
0,5554
0,0585
0,0933
0,0455
0,0139
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0003
0,0002
0,0000
0,0050
0,0028
0,1504
0,0532
0,0207
<207.5>
0,0000
0,0000
0,0003
0,0003
0,0003
0,0000
0,0000
0,0000
0,0000
0,0003
0,0003
0,0003
0,0004
0,9895
0,0069
0,0004
0,0004
0,0004
0,0004
OVHD-1
0,5557
0,0585
0,0933
0,0455
0,0139
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0003
0,0002
0,0000
0,0050
0,0028
0,1503
0,0531
0,0207
<207.6>
0,0000
0,0000
0,0003
0,0003
0,0003
0,0000
0,0000
0,0000
0,0000
0,0003
0,0003
0,0003
0,0004
0,9895
0,0069
0,0004
0,0004
0,0004
0,0004
<101>
0,7088
0,0819
0,0491
0,0264
0,0089
0,0033
0,0038
0,0044
0,0049
0,0003
0,0004
0,0005
0,0005
0,0000
0,0000
0,0026
0,0805
0,0145
0,0092
<207.7>
0,0000
0,0000
0,0003
0,0003
0,0003
0,0000
0,0000
0,0000
0,0000
0,0003
0,0003
0,0003
0,0004
0,9895
0,0069
0,0004
0,0004
0,0004
0,0004
<207.1>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0002
0,0007
0,0006
0,9119
0,0847
0,0000
0,0004
0,0006
0,0005
DRY GAS
0,7504
0,0892
0,0545
0,0296
0,0100
0,0037
0,0043
0,0049
0,0055
0,0002
0,0003
0,0005
0,0005
0,0001
0,0000
0,0028
0,0166
0,0164
0,0104
<207.2>
0,0000
0,0000
0,0003
0,0003
0,0003
0,0000
0,0000
0,0000
0,0000
0,0003
0,0003
0,0003
0,0004
0,9895
0,0069
0,0004
0,0004
0,0004
0,0004
<001>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
1,0000
0,0000
0,0000
0,0000
0,0000
<207.3>
0,0000
0,0000
0,0003
0,0003
0,0003
0,0000
0,0000
0,0000
0,0000
0,0003
0,0003
0,0003
0,0004
0,9895
0,0069
0,0004
0,0004
0,0004
0,0004
<002>
0,0017
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9957
0,0000
0,0025
0,0000
0,0000
<207.4>
0,0000
0,0000
0,0003
0,0003
0,0003
0,0000
0,0000
0,0000
0,0000
0,0003
0,0003
0,0003
0,0004
0,9895
0,0069
0,0004
0,0004
0,0004
0,0004
J
Stream Summary - Hybrid:
Turndown Case
97
98
<102>
1,0000
35
157
755
16189
46
-6,39E+07
Waste
0
45
4
0
0
0
0,00E+00
<208>
0,0000
204
1
2
221
0
-1,10E+06
<204.1>
1,0000
45
4
0
0
0
0,00E+00
<204.2>
1
45
4
0
0
0
0,00E+00
<207.5>
0,0000
166
157
2
223
0
-1,13E+06
Dry Gas
1,0000
37
156
755
16183
46
-6,38E+07
<205>
0
45
4
3
449
0
-2,51E+06
<209>
1
204
1
0
0
0
-1,90E-02
<101>
1,0000
35
157
1944
38063
111
-1,78E+08
<OVHD-1>
1
45
4
0
3
0
-9,80E+03
<207.6>
1,19E-02
150
2
2
222
0
-1,14E+06
<104>
0,0000
35
157
4
452
0
-2,53E+06
<203>
3,34E-02
45
4
4
452
0
-2,52E+06
<210>
0,00E+00
204
1
2
221
0
-1,10E+06
<103>
0
37
156
2
223
0
-1,22E+06
<207.1>
3,84E-03
146
2
3
449
0
-2,38E+06
<207.7>
1,06E-02
150
2
2
222
0
-1,14E+06
<201>
0,0000
36
156
4
452
0
-2,53E+06
<206>
3,84E-04
45
3
3
449
0
-2,51E+06
Make Up
0,00E+00
35
1
0
2
0
-1,10E+04
<213>
0
51
2
2
223
0
-1,21E+06
<207.2>
1,19E-02
150
2
3
444
0
-2,28E+06
<202>
0,0000
41
156
4
452
0
-2,52E+06
<207>
1,51E-03
121
2,994208
3
449
0
-2,41E+06
<211>
4,33E-04
203
1
2
223
0
-1,11E+06
<214>
0
41
2
2
223
0
-1,22E+06
<207.3>
1,19E-02
150
2
2
222
0
-1,14E+06
<204>
1,0000
45
4
0
3
0
-9,80E+03
OVHD
1
35
1
0
1
0
-2,13E+03
<212>
0
203
3
2
223
0
-1,11E+06
<215>
0
35
1
2
223
0
-1,23E+06
<207.4>
0,0000
166
157
2
222
0
-1,13E+06
99
Table J.2: Mass fraction hybrid turndown 1/2
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
<102>
0,6052
0,1238
0,0959
0,0581
0,0203
0,0077
0,0090
0,0103
0,0115
0,0000
0,0000
0,0000
0,0003
0,0000
0,0004
0,0032
0,0000
0,0334
0,0210
<205>
0,0001
0,0001
0,0003
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9763
0,0195
0,0000
0,0000
0,0017
0,0014
<210>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
Dry Gas
0,6054
0,1238
0,0959
0,0581
0,0203
0,0077
0,0090
0,0103
0,0115
0,0000
0,0000
0,0000
0,0003
0,0002
0,0000
0,0032
0,0000
0,0333
0,0210
<203>
0,0032
0,0009
0,0011
0,0005
0,0003
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9704
0,0194
0,0000
0,0000
0,0023
0,0016
Make Up
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9920
0,0080
0,0000
0,0000
0,0000
0,0000
<104>
0,0032
0,0009
0,0011
0,0005
0,0003
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9704
0,0194
0,0000
0,0000
0,0023
0,0016
<206>
0,0001
0,0001
0,0003
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9763
0,0195
0,0000
0,0000
0,0017
0,0014
<211>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
<201>
0,0032
0,0009
0,0011
0,0005
0,0003
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9704
0,0194
0,0000
0,0000
0,0023
0,0016
<207>
0,0001
0,0001
0,0003
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9763
0,0195
0,0000
0,0000
0,0017
0,0014
<212>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
<202>
0,0032
0,0009
0,0011
0,0005
0,0003
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9704
0,0194
0,0000
0,0000
0,0023
0,0016
OVHD
0,1520
0,1494
0,1437
0,1351
0,1367
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0009
0,0126
0,0000
0,0284
0,0000
0,0000
0,1277
0,1134
<213>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
<204>
0,5065
0,1351
0,1409
0,0575
0,0192
0,0003
0,0002
0,0001
0,0001
0,0000
0,0000
0,0000
0,0001
0,0000
0,0017
0,0014
0,0000
0,0987
0,0380
<208>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
<214>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
Waste
0,0001
0,0001
0,0003
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9763
0,0195
0,0000
0,0000
0,0017
0,0014
<209>
0,0209
0,0367
0,0511
0,0501
0,0729
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0020
0,0256
0,2852
0,2632
0,0000
0,0000
0,0907
0,1017
<215>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
100
<103>
0,0000
0,0000
0,0000
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9928
0,0064
0,0000
0,0000
0,0001
0,0001
<207.4>
0,0005
0,0005
0,0005
0,0005
0,0005
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9895
0,0064
0,0000
0,0000
0,0005
0,0005
<204.2>
0,5065
0,1351
0,1409
0,0575
0,0192
0,0003
0,0002
0,0001
0,0001
0,0000
0,0000
0,0000
0,0001
0,0000
0,0017
0,0014
0,0000
0,0988
0,0381
<207.5>
0,0005
0,0005
0,0005
0,0005
0,0005
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9895
0,0064
0,0000
0,0000
0,0005
0,0005
<OVHD-1>
0,5065
0,1351
0,1409
0,0575
0,0192
0,0003
0,0002
0,0001
0,0001
0,0000
0,0000
0,0000
0,0001
0,0000
0,0017
0,0014
0,0000
0,0987
0,0380
<207.6>
0,0005
0,0005
0,0005
0,0005
0,0005
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9895
0,0064
0,0000
0,0000
0,0005
0,0005
<101>
0,7088
0,0819
0,0491
0,0264
0,0089
0,0033
0,0038
0,0044
0,0049
0,0003
0,0004
0,0005
0,0005
0,0000
0,0000
0,0026
0,0805
0,0145
0,0092
<207.7>
0,0005
0,0005
0,0005
0,0005
0,0005
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9895
0,0064
0,0000
0,0000
0,0005
0,0005
<207.1>
0,0001
0,0001
0,0003
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0003
0,9763
0,0195
0,0000
0,0000
0,0017
0,0014
<207.2>
0,0005
0,0005
0,0005
0,0005
0,0005
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9895
0,0064
0,0000
0,0000
0,0005
0,0005
<207.3>
0,0005
0,0005
0,0005
0,0005
0,0005
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0005
0,9895
0,0064
0,0000
0,0000
0,0005
0,0005
K
Stream Summary - Hybrid: Max
Flow Case
101
102
Dry Gas
1,0000
36
156
21664
413320
1244
-1,83E+09
<205>
0,0000
45
4
22
2038
2
-1,28E+07
<209>
1,0000
203
1
0
4
0
-2,32E+04
<214>
0,0000
37
2
7
974
1
-5,34E+06
<102>
1,0000
35
157
21673
413455
1244
-1,83E+09
<207.6>
0,0034
150
2
7
938
1
-4,82E+06
<104>
0,0000
35
157
22
2042
2
-1,28E+07
<203>
8,95E-03
45
4
22
2042
2
-1,28E+07
<210>
0,0000
203
1
6
935
1
-4,65E+06
<215>
0
19
1
7
974
1
-5,39E+06
<207.1>
0,0053
143
2
22
2038
2
-1,22E+07
<207.7>
1,98E-03
150
2
7
938
1
-4,82E+06
<201>
0,0000
36
156
22
2042
2
-1,28E+07
<206>
1,06E-04
45
3
22
2038
2
-1,28E+07
<211>
0,0000
197
1
7
974
1
-4,87E+06
<103>
0
20
156
7
974
1
-5,37E+06
<207.2>
0,0034
150
2
13
1876
2
-9,64E+06
<202>
0,0000
41
156
22
2042
2
-1,28E+07
<207>
8,37E-04
115
3
22
2038
2
-1,23E+07
Make up
0,0000
35
157
0
39
0
-2,14E+05
<204.2>
1
45
4
0
1
0
-4,92E+03
<207.3>
0,0034
150
2
7
938
1
-4,82E+06
<204>
1,0000
45
4
0
5
0
-2,46E+04
OVHD
1
70
1
0
4
0
-2,06E+04
<212>
0,0000
197
3
7
974
1
-4,87E+06
OVHD-1
1
45
4
0
4
0
-1,97E+04
<207.4>
0,0000
156
157
7
938
1
-4,79E+06
Waste
0,0000
45
4
0
0
0
0,00E+00
<208>
0
204
1
7
937
1
-4,67E+06
<213>
0,0000
47
2
7
974
1
-5,31E+06
<101>
1,0000
35
157
23325
456755
1334
-2,14E+09
<207.5>
0
156
157
7
934
1
-4,77E+06
103
Table K.2: Mass fraction max flow case 1/2
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
Name
Methane
Ethane
Propane
n-Butane
n-Pentane
n-Hexane
n-Heptane
n-Octane
n-Nonane
Benzene
Toluene
m-Xylene
E-Benzene
TEGlycol
H2O
Nitrogen
CO2
i-Butane
i-Pentane
Dry Gas
0,7428
0,0879
0,0535
0,0290
0,0098
0,0036
0,0042
0,0048
0,0054
0,0003
0,0004
0,0005
0,0005
0,0001
0,0000
0,0028
0,0283
0,0160
0,0102
<203>
0,0012
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9102
0,0839
0,0000
0,0012
0,0007
0,0006
<211>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0003
0,0003
0,0003
0,9932
0,0056
0,0000
0,0000
0,0000
0,0000
<104>
0,0012
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9102
0,0839
0,0000
0,0012
0,0007
0,0006
<206>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9123
0,0841
0,0000
0,0006
0,0005
0,0005
Make up
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,9990
0,0010
0,0000
0,0000
0,0000
0,0000
<201>
0,0012
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9102
0,0839
0,0000
0,0012
0,0007
0,0006
<207>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9123
0,0841
0,0000
0,0006
0,0005
0,0005
<212>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0003
0,0003
0,0003
0,9932
0,0056
0,0000
0,0000
0,0000
0,0000
<202>
0,0012
0,0001
0,0003
0,0002
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9102
0,0839
0,0000
0,0012
0,0007
0,0006
OVHD
0,1116
0,0122
0,1048
0,0938
0,0900
0,0000
0,0000
0,0000
0,0000
0,0339
0,0273
0,0216
0,0207
0,0000
0,1617
0,0006
0,1387
0,0964
0,0868
<213>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0003
0,0003
0,0003
0,9932
0,0056
0,0000
0,0000
0,0000
0,0000
<204>
0,4740
0,0502
0,0836
0,0424
0,0139
0,0000
0,0000
0,0000
0,0000
0,0005
0,0004
0,0003
0,0003
0,0000
0,0059
0,0023
0,2485
0,0554
0,0222
<208>
0,0000
0,0000
0,0000
0,0001
0,0000
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0004
0,0004
0,9913
0,0068
0,0000
0,0000
0,0001
0,0001
<214>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0003
0,0003
0,0003
0,9932
0,0056
0,0000
0,0000
0,0000
0,0000
Waste
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9123
0,0841
0,0000
0,0006
0,0005
0,0005
<209>
0,1183
0,0122
0,0250
0,0202
0,0133
0,0000
0,0000
0,0000
0,0000
0,0283
0,0241
0,0206
0,0196
0,3223
0,2757
0,0006
0,0636
0,0276
0,0285
<215>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0003
0,0003
0,0003
0,9932
0,0056
0,0000
0,0000
0,0000
0,0000
<205>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9123
0,0841
0,0000
0,0006
0,0005
0,0005
<210>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0003
0,0003
0,0003
0,9929
0,0058
0,0000
0,0000
0,0000
0,0000
<103>
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0000
0,0002
0,0003
0,0003
0,0003
0,9932
0,0056
0,0000
0,0000
0,0000
0,0000
104
<204.2>
0,4740
0,0502
0,0836
0,0424
0,0140
0,0000
0,0000
0,0000
0,0000
0,0005
0,0004
0,0003
0,0003
0,0000
0,0059
0,0023
0,2486
0,0555
0,0222
<207.4>
0,0000
0,0000
0,0004
0,0004
0,0004
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0004
0,0004
0,9895
0,0065
0,0000
0,0004
0,0004
0,0004
OVHD-1
0,4740
0,0502
0,0836
0,0424
0,0139
0,0000
0,0000
0,0000
0,0000
0,0005
0,0004
0,0003
0,0003
0,0000
0,0059
0,0023
0,2485
0,0554
0,0222
<207.5>
0,0000
0,0000
0,0004
0,0004
0,0004
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0004
0,0004
0,9895
0,0065
0,0000
0,0004
0,0004
0,0004
<101>
0,7088
0,0819
0,0491
0,0264
0,0089
0,0033
0,0038
0,0044
0,0049
0,0003
0,0004
0,0005
0,0005
0,0000
0,0000
0,0026
0,0805
0,0145
0,0092
<207.6>
0,0000
0,0000
0,0004
0,0004
0,0004
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0004
0,0004
0,9895
0,0065
0,0000
0,0004
0,0004
0,0004
<102>
0,7425
0,0878
0,0535
0,0290
0,0098
0,0036
0,0042
0,0048
0,0054
0,0003
0,0004
0,0005
0,0005
0,0000
0,0004
0,0028
0,0283
0,0160
0,0102
<207.7>
0,0000
0,0000
0,0004
0,0004
0,0004
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0004
0,0004
0,9895
0,0065
0,0000
0,0004
0,0004
0,0004
<207.1>
0,0000
0,0000
0,0001
0,0001
0,0001
0,0000
0,0000
0,0000
0,0000
0,0001
0,0003
0,0007
0,0006
0,9123
0,0841
0,0000
0,0006
0,0005
0,0005
<207.2>
0,0000
0,0000
0,0004
0,0004
0,0004
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0004
0,0004
0,9895
0,0065
0,0000
0,0004
0,0004
0,0004
<207.3>
0,0000
0,0000
0,0004
0,0004
0,0004
0,0000
0,0000
0,0000
0,0000
0,0004
0,0004
0,0004
0,0004
0,9895
0,0065
0,0000
0,0004
0,0004
0,0004
L
HAZOP and FEI
Figure L.1: Point 2 op the HAZOP is at the natural gas outflow from the contactor
Figure L.2: Point 1 op the HAZOP is between the pervaporation membranes and the pumps. Point 3
is at the TEG outflow of the Surge.
105
No.
1
More
No
Less
As well as
Less
No
Reverse
Less
More
Guide word
No
More Flow
No flow
Less flow
No flow
Reverse flow
Less flow
More flow
Deviation
No flow
No regeneration
Safeguardaction
Backup pump present
Regular flushing of the pipes
Concentration control
FLow controler with alarm
Leak detection
Flow measurement to detect losses
valves that prevent reverse flow
Consequences
No separation in the membranes
No dehydration at all
Loss of gas
107
Location
Process Unit
Contactor
Date
Material Factor
Penalty Factor
Range
1,00
0.30 - 1.25
0.20 - 0.40
0.25 - 1.05
0.25 - 0.90
0.20 - 0.35
0.25 - 0.50
21
Penalty
Used
1,00
0,00
0,00
0,85
0,00
0,35
0,50
Penalty Factor
Range
1,00
0.20 - 0.80
0,50
2,70
Penalty
Used
1,00
0,20
0,00
0,50
0,30
0,80
0.25 - 2.00
0,00
0,00
0,00
0,00
0,48
0.20 - 0.30
0,00
0.10 - 0.75
0.10 - 1.50
0.15 - 1.15
0,50
3,00
0,00
0,00
0,10
0,30
0,10
0,00
0,00
5,18
13,99
294
M
Equipment Summary
109
Pressure [bara]
Temp.
[oC]
Volume [m3]
Diameter [m]
L or H [m]
Internals
:
:
:
:
:
- Tray Type
:
- Tray Number :
- Fixed Packing
Type
:
Shape
:
- Catalyst
Type
:
Shape
:
Number
- Series
:
- Parallel
:
Materials of
Construction (3) :
Other
C-101
Contactor
C-201
Still Column
:
Packed
Column
156.25/156.5
35
Tray Column
2.04
12.2
0.15
6
n.a.
n.a.
1/1.1
70.3/204
C-202
Stripping
:
Column
Packed
Column
1.1
204
SUMMARY
V-201
Flash Vessel
:
Horizontal
V-202
Reboiler :
Horizontal
0.25
0.5
4.5
42
0.31 (1)
0.46
1.85
1.1
204
0.14 (2)
0.35
1.4
Sieve Tray
2
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
Mellapack.
n.a.
n.a.
n.a.
Mellapack
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
Gas Fired
1
Column: SS
1
Column: CS
Tray: SS
1
Column: CS
1
CS
1
Shell: CS
Tubes:
CS/Inconel
Remarks:
(1) V-201: For Residence time of 10 min and 80% Liquid filled.
(2) V-202: For Residence time of 5 min and 50% Liquid filled.
(3) SS = Stainless Steel; CS = Carbon Steel
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
Pressure [bara]
Temp.
[oC]
Volume [m3]
Diameter [m]
L or H [m]
Internals
:
:
:
:
:
V-203
Surge Vessel
S-201 A/B
Filter :
Horizontal
1
202
0.34 (1)
0.48
1.9
In Line
4.5/3.5
42
0.0254
-
SUMMARY
S-202
Pervaporation
(3)
Horizontal
(4)
150
0.074
0.26
1.402
n.a.
n.a.
n.a.
- Tray Type
:
n.a.
n.a.
n.a.
- Tray Number :
- Fixed Packing
n.a.
n.a.
n.a.
Type
:
n.a.
n.a.
n.a.
Shape
:
- Catalyst
n.a.
n.a.
n.a.
Type
:
n.a.
n.a.
n.a.
Shape
:
- Tubes
Type
:
Inline Strainer
- Type
Number
1
1
- Series
:
138
- Parallel
:
CS
SS
SS
Materials of
Construction (2) :
Other
:
Remarks:
(1) SS = Stainless Steel; CS = Carbon Steel
(2) V-203: For residence time of 20 min and 80% liquid filled.
(3) Data for pervaporation membrane module only.
(4) 3 bar in feed, 20 mbar in permeate side and 1.5 bar in retentate.
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
Substance
- Tubes
:
- Shell
:
Duty
[kW] :
Heat Exchange
area
[m2] :
Number
- Series
:
- Parallel
:
Pressure
[bara]
- Tubes
:
- Shell
:
Temperature
In / Out
[oC]
- Tubes
:
- Shell
:
Special Materials of
Construction (2) :
Other
:
Remarks:
(1) Bare tube surface.
(2) CS = Carbon Steel;
Designers :
SUMMARY
E-201
E-202
Glycol/Glycol Glycol/Glycol
Preheater
Heater :
Shell and
Shell and
Tube
Tube
E-203
Sea-Water
Cooler
:
Shell and Tube
E-204
Pervaporation
Heater:
Shell and Tube
Rich TEG
Lean TEG
2.8
Cooling Water.
Lean TEG
11.37
Rich TEG
LP Steam
61.31
4.24
Rich TEG
Lean TEG
93.36
(1)
1
-
5
2.5
36 / 38
57 / 52
Tubes : CS
Shell : CS
24.35(1)
2.6(1)
2.44(1)
1
-
1
-
1
-
3.5
2.5
4
2
3
6.5
42 / 107.8
198/ 57
Tubes : CS
Shell : CS
10/20
53 / 35
Tubes : CS
Shell : CS
107.8/150
162
Tubes : CS
Shell : CS
Project ID-Number :
Date
:
CPD3425
June 2015
Type
Number
Medium
transferred
P-101
Turbocharger
SUMMARY
P-102 A/B
High
Pressure
Pump
Centrifugal
2
P-103 A/B
Semi-Lean
Injection
Pump
Centrifugal
2
P-201 A/B
Intermediate
Pump
:
Centrifugal
2
P-202 A/B
Booster
Pump
:
:
:
Centrifugal
2
Lean TEG
Semi-Lean
TEG
Semi-Lean
TEG
Lean TEG
2.5/0.8/0.7
705.1/1133/1042
0.8
1133
0.7
1042
1.2
636.3
0.8
969.6
(156.5-4.5)
&(1.5-78)&
(1.5-77.5)
78 / 156.5
1.1/156.5
1.5/2
1/2.5
42/37/160
36/37
150/160
150/150
198
2.04
2.17
0.027
0.045
2 (1)
2 (1)
2 (1)
2 (1)
Capacity
[kg/s]
[m3/h]
Density [kg/m3]
Pressure [bara]
Suct. / Disch.
:
:
:
:
Temperature
In / Out [oC]
:
Power
[kW]
- Theor.
:
- Actual
:
Number
- Theor.
:
- Actual
:
Special Materials of
Construction
:
Other
:
1
SS 316
Double
mechanical seals
SS 316
Double
mechanical
seals
SS 316
Double
mechanical
seals
SS 316
Double
mechanical
seals
SS 316
Double
mechanical
seals
Remarks:
(1) One installed spare included.
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
P-203 A/B
Vacuum Pump
Type
:
Number
:
Medium
transferred
:
Capacity
[kg/s]
:
[m3/h]
:
3
Density [kg/m ] :
Pressure [bara]
Suct. / Disch.
:
Temperature
In / Out [oC]
:
Power
[kW]
- Theor.
:
- Actual
:
Number
- Theor.
:
- Actual
:
Special Materials of
Construction
:
Other
:
SUMMARY
Water Vapour
252.3
1
0.02/1
150/150
49
2 (1)
SS 316
Double
mechanical seals
Remarks:
(1) One installed spare included.
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
SPECIFICATION SHEET
COLUMN
EQUIPMENT NUMBER :
NAME
:
Service
Column Type
Tray Type
Tray Number (1)
- Theoretical
- Actual
- Feed (actual)
Tray Distance (HETP) [m]
Column Diameter
[m]
Column Height
[m]
Heating
Stream Details
C-101
Contactor
:
:
:
General Data
- distillation / extraction /
- packed / tray / spray /
- cap
/ sieve / valve /
:
6
:
: Top and Middle (1st and 4th theoretical trays)
: 0.61
Tray Material
: SS314
: 2.04
Column Material : SS
: 12.2
: - none
/ open steam / reboiler /
Process Conditions
Feed Gas
Feed Liquid
Lean
TEG
Temp.
[oC]
Pressure
[bara]
Density
[kg/m3]
Mass Flow [kg/hr]
Composition
TEG
Water
Other
absorption
: 35
156.5
159.5
380617
mol% wt%
0
0.4
99.6
:36.5
156.5
1133
786.4
wt%
99.2
0.62
0.18
Semi
Lean
TEG
160
156.5
1042
764.8
wt%
98.95
0.69
0.33
Dry Gas
: 35.7
156.3
158.7
3.372E+05
mol% wt%
(2)
(2)
Rich Liquid
: 35.4
156.5
1125
1660
mol%
0.01
0
99.99
wt%
Extractant /
side stream
mol%
91.01
8.45
0.54
Column Internals
(3)
Trays
Not Applicable
Packing
Number of
Type
: Mellapack
caps / sieve holes /
: Material
:
2
3
Active Tray Area
[m ] : Volume [m ] : 9.8 (Total)
Weir Length
[mm] : Length [m] :Diameter of
Width
[m] :chute pipe / hole /
[mm] : Height [m] : 3 (2 beds of 1.5 m)
Remarks:
(1) Tray numbering from top to bottom.
(2) SS = Stainless Steel;
CS = Carbon Steel.
(3) Sketch & measures of Column & Tray layout should have been provided.
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
wt%
C-201
Still Column
Service
Column Type
Tray Type
Tray Number (1)
- Theoretical
- Actual
- Feed (actual)
Tray Distance (HETP) [m]
Column Diameter
[m]
Column Height
[m]
Heating
Stream Details
o
Temp.
[ C]
Pressure
[bara]
Density
[kg/m3]
Mass Flow [kg/hr]
Composition
TEG
Water
Other
General Data
- distillation / extraction /
- packed / tray / spray /
- cap
/ sieve / valve /
:
:
:
:
2
:
2
:
2
: 0.61
: 0.145
: 6
: - none
Feed
Tray Material
Column Material
/ open steam /
Process Conditions
Top
Liq
: 150
2
636.3
763.6
wt%
Gas
202.9
1.1
0.9
2.811
wt%
98.95
0.69
0.36
33.6
30.71
35.7
absorption
: 70.3
1
1.13
3.23
mol%
:
:
wt%
0
17.93
82.07
: 204
1.1
962.4
763.2
mol%
SS314
CS
reboiler /
Bottom
wt%
(2)
(2)
Natural Gas
Reflux /
Absorbent
: 70.3
1
972.6
1.018
mol% wt%
99.12
0.73
0.15
Extractant /
side stream
mol%
0.01
99.88
0.02
Column Internals
(4)
Trays
(5)
Packing
Not Applicable
Number of
Type
:
caps / sieve holes /
: Material
:
2
3
Active Tray Area
[m ] : Volume [m ] :
Weir Length
[mm] : Length [m] :
Diameter of
Width
[m] :
chute pipe / hole /
[mm] : Height [m] :
Remarks:
(1) Tray numbering from top to bottom.
(2) SS = Stainless Steel;
CS = Carbon Steel.
(3) Reboiler is V-202; operates with Natural Gas
(4) Sketch & measures of Column & Tray layout should have been provided.
(5) Tray layout valid for whole column.
Designers :
Project ID-Number :
Date
:
(3)
CPD3425
June 2015
wt%
SPECIFICATION SHEET
COLUMN
EQUIPMENT NUMBER :
NAME
:
C-202
Stripping Column
General Data
: - distillation / extraction /
: - packed / tray / spray /
: - cap
/ sieve / valve /
Service
Column Type
Tray Type
Tray Number (1)
- Theoretical
- Actual
- Feed (actual)
Tray Distance (HETP) [m]
Column Diameter
[m]
Column Height
[m]
Heating
Stream Details
o
Temp.
[ C]
Pressure
[bara]
Density
[kg/m3]
Mass Flow [kg/hr]
Composition
TEG
Water
Other
:
1
:
1
:
1
: : 0.25
: 0.5
: - none
Feed
Tray Material
Column Material
/ open steam /
Process Conditions
Top
Liq
: 204
1.1
962.4
763.2
wt%
Gas
42.14
4.5
3.86
0.7
wt%
99.12
0.73
0.15
0
0.5
99.5
absorption
: 203
1.1
0.9
2.8
mol%
:
:
SS314
CS
reboiler /
wt%
33.58
30.7
35.72
(2)
(2)
Natural Gas
Reflux /
Absorbent
Bottom
: 203
1.1
964.2
761
mol%
Extractant /
side stream
wt%
mol%
wt%
mol%
99.2
0.6
0.2
Column Internals
(3)
Trays
Not Applicable
Packing
Number of
Type
: Mellapack
caps / sieve holes /
: Material
:2
3
Active Tray Area
[m ] : Volume [m ] :0.012
Weir Length
[mm] : Length [m] :Diameter of
Width
[m] :chute pipe / hole /
[mm] : Height [m] :0.25
Remarks:
(1) Tray numbering from top to bottom.
(2) SS = Stainless Steel;
CS = Carbon Steel.
(3) Sketch & measures of Column & Tray layout should have been provided.
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
wt%
E-201
In Series
: 1
Glycol/Glycol Preheater
In Parallel : none
General Data
Service
: - Heat Exchanger
- Vaporizer
- Cooler
- Reboiler
- Condenser (Air cooled)
(1), (2), (3)
Type
: - Fixed Tube Sheets - Plate Heat Exchanger
- Floating Head
- Finned Tubes
- Hair Pin
- Thermosyphon
- Double Tube
Position
: - Horizontal
- Vertical
Capacity
[kW]
: 2.85
(1)
Heat Exchange Area
[m2]
: 4.24
(1)
2o
Overall Heat Transfer Coefficient
[W/m C] : 333.28
(1)
o
Log. Mean Temperature Diff. (LMTD) [ C]
:
Passes Tube Side
Passes Shell Side
Correction Factor LMTD (min. 0.75)
Corrected LMTD
: 1
: n.a.
:
[oC]
: 7.257
Process Conditions
Medium
Mass Stream
Mass Stream to
- Evaporize
- Condense
(1)
Shell Side
Lean TEG solution
Tube Side
Rich TEG solution
[kg/hr]
787
1660
[kg/s]
[kg/s]
:
:
n.a.
n.a
[kJ/kg C]
[kJ/kg]
:
:
3
-
3
-
Temperature IN
Temperature OUT
[oC]
[oC]
:
:
57
52
36
38
2.5
5
Pressure
[bara]
:
C.S
CS
Material
:
Remarks:
(1) Calculation of Air Cooler: Applied Chemical Process Design, F. Aerstin and G. Street.
(2) Cooler requires 40 x 40 meters plot space, which may not be available.
(3) Requires Fan(s) for forced air circulation with 960 kW for electrical drive(s).
(1) As simulated in Aspen Hysys.
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
E-202
Glycol/Glycol Heater
General Data
Service
: - Heat Exchanger
- Cooler
- Condenser
Type
: - Fixed Tube Sheets
- Floating Head
- Hair Pin
- Double Tube
Position
: - Horizontal
- Vertical
Capacity
[kW]
: 93.36
2
Heat Exchange Area
[m ]
: 24.35
2o
Overall Heat Transfer Coefficient
[W/m C] : 327.8
Log. Mean Temperature Diff. (LMTD) [oC]
:
Passes Tube Side
Passes Shell Side
Correction Factor LMTD (min. 0.75)
Corrected LMTD
Medium
:
:
In Series
In Parallel
:
:
1
none
- Vaporizer
- Reboiler
- Plate Heat Exchanger
- Finned Tubes
- Thermosyphon
-
(1)
(1)
(1)
1
n.a
:
[ C]
:
42.13
Process Conditions
Shell Side
:
Rich TEG
o
(1)
Tube Side
Lean TEG
Mass Stream
Mass Stream to
- Evaporize
- Condense
[kg/hr]
786.4
1657
[kg/s]
[kg/s]
:
:
[kJ/kgoC]
[kJ/kg]
:
:
3
-
3
-
Temperature IN
Temperature OUT
[oC]
[oC]
:
:
198.0
57.0
42
107.8
Pressure
Material
Remarks:
(1) As simulated in Aspen Hysys.
[bara]
2.5
CS
3.5
CS
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
E-203
Sea Water Cooler
General Data
Service
: - Heat Exchanger
- Cooler
- Condenser
Type
: - Fixed Tube Sheets
- Floating Head
- Hair Pin
- Double Tube
Position
: - Horizontal
- Vertical
Capacity
[kW]
: 11.37
Heat Exchange Area
[m2]
: 2.64
2o
Overall Heat Transfer Coefficient
[W/m C] : 150
Log. Mean Temperature Diff. (LMTD) [oC]
: 28.68
Passes Tube Side
Passes Shell Side
Correction Factor LMTD (min. 0.75)
Corrected LMTD
:
:
In Series
In Parallel
:
:
1
none
- Vaporizer
- Reboiler
- Plate Heat Exchanger
- Finned Tubes
- Thermosyphon
-
(Aspen)
(Calc.)
(Assumed).
(Calc.)
1
n.a
:
[oC]
:
Process Conditions
Medium
Shell Side
Lean TEG solution
Tube Side
Sea Water
Mass Stream
Mass Stream to
- Evaporize
- Condense
[kg/hr]
786.4
978.03
[kg/s]
[kg/s]
:
:
[kJ/kgoC]
[kJ/kg]
:
:
3
-
4.18
-
Temperature IN
Temperature OUT
[oC]
[oC]
:
:
53
35
10
20
Pressure
Material
(1)
Remarks:
(1) CS = Carbon Steel;
[bara]
:
:
2
CS
4
C.S
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
E-204
Pervaporation Heater
General Data
Service
: - Heat Exchanger
- Cooler
- Condenser
Type
: - Fixed Tube Sheets
- Floating Head
- Hair Pin
- Double Tube
Position
: - Horizontal
- Vertical
Capacity
[kW]
: 61.31
Heat Exchange Area
[m2]
: 2.44
2o
Overall Heat Transfer Coefficient
[W/m C] : 900
Log. Mean Temperature Diff. (LMTD) [oC]
: 27.8
Passes Tube Side
Passes Shell Side
Correction Factor LMTD (min. 0.75)
Corrected LMTD
:
:
In Series
In Parallel
:
:
1
none
- Vaporizer
- Reboiler
- Plate Heat Exchanger
- Finned Tubes
- Thermosyphon
-
(Aspen)
(Calc.)
(Assumed).
(Calc.)
1
n.a
:
[oC]
:
Process Conditions
Medium
Tube Side
Rich TEG solution
106.02
-
2075.11
3
-
Mass Stream
Mass Stream to
- Condense
- Evaporate
Average Specific Heat
Heat of Evap. / Condensation
[kg/hr]
[kg/hr]
[kg/s]
[kJ/kgoC]
[kJ/kg]
:
:
:
Temperature IN
Temperature OUT
[oC]
[oC]
:
:
162.06
162.06
107.8
150
Pressure
Material
[bara]
:
:
6.5
CS
3
CS
(1)
Shell Side
Steam
106.02
1657
Remarks:
(1) CS = Carbon Steel;
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
(T)
()
()
(pv)
Capacity
Pressure Levels
(v)
(ps)
P-101
Turbocharger
[kW]
Pump Efficiency
Power at Shaft
[-]
[kW]
[V]
Foundation Plate
Flexible Coupling
Pressure Gauge Suction
Pressure Gauge Discharge
Min. Overpressure above
pv/pm
[bar]
Pump House
Pump Rotor
Shaft
Special provisions
1
0
Theoretical Power
RPM
Drive
Type electrical motor
Tension
Rotational direction
Operating
:
Installed Spare :
none
{ = v( pd - ps)102 }
:
:
Construction Details (1)
:
Nominal diameter
Suction Nozzle
[]
:
Discharge Nozzle []
:
:
Cooled Bearings
: Clock /
Cooled Stuffing Box
Counter Cl. Smothering Gland
: Combined /
If yes
two parts
- Seal Liquid
: Yes
- Splash Rings
: No
- Packing Type
: Yes
- Mechanical Seal
- N.P.S.H.
[m]
:
{ = pmg }
Construction Materials (2)
:
Wear Rings
:
Shaft Box
:
: none
:
:
:
:
:
:
:
:
:
:
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
:
:
Operating Pressure
[bara] : 156.5/78
Test Pressure
[bara] :
Remarks:
(1) Double mechanical seals and seal fluid required for LPG service. Further details to be specified by
Rotating Equipment specialist.
(2) MS = Mild Steel; HT Steel = High Tensile Steel
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
(T)
()
()
(pv)
Capacity
Suction
Discharge
(v)
(ps)
(pd)
P-102 A/B
High Pressure Pump
Theoretical Power
[kW]
Pump Efficiency
Power at Shaft
[-]
[kW]
RPM
Drive
Type electrical motor
Tension
Rotational direction
[V]
Foundation Plate
Flexible Coupling
Pressure Gauge Suction
Pressure Gauge Discharge
Min. Overpressure above
pv/pm
[bar]
Pump House
Pump Rotor
Shaft
Special provisions
Operating
:
Installed Spare :
2.037
1
1
:37.8
{ = v( pd - ps)102 }
:
:
Construction Details (1)
:
Nominal diameter
Suction Nozzle
[]
:
Discharge Nozzle []
:
:
Cooled Bearings
: Clock /
Cooled Stuffing Box
Counter Cl. Smothering Gland
: Combined /
If yes
two parts
- Seal Liquid
: Yes
- Splash Rings
: No
- Packing Type
: Yes
- Mechanical Seal
- N.P.S.H.
[m]
:
{ = pmg }
Construction Materials (2)
:
Wear Rings
:
Shaft Box
:
: none
:
:
:
:
:
:
:
:
:
:
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
:
:
Operating Pressure
[bara] : 156.5
Test Pressure
[bara] :
Remarks:
(1) Double mechanical seals and seal fluid required for LPG service. Further details to be specified by
Rotating Equipment specialist.
(2) MS = Mild Steel; HT Steel = High Tensile Steel
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
(T)
()
()
(pv)
Capacity
Suction
Discharge
(v)
(ps)
(pd)
P-103 A/B
Semi-Lean Injection Pump
Theoretical Power
[kW]
Pump Efficiency
Power at Shaft
[-]
[kW]
RPM
Drive
Type electrical motor
Tension
Rotational direction
[V]
Foundation Plate
Flexible Coupling
Pressure Gauge Suction
Pressure Gauge Discharge
Min. Overpressure above
pv/pm
[bar]
Pump House
Pump Rotor
Shaft
Special provisions
Operating
:
Installed Spare :
2.17
1
1
:37.8
{ = v( pd - ps)102 }
:
:
Construction Details (1)
:
Nominal diameter
Suction Nozzle
[]
:
Discharge Nozzle []
:
:
Cooled Bearings
: Clock /
Cooled Stuffing Box
Counter Cl. Smothering Gland
: Combined /
If yes
two parts
- Seal Liquid
: Yes
- Splash Rings
: No
- Packing Type
: Yes
- Mechanical Seal
- N.P.S.H.
[m]
:
{ = pmg }
Construction Materials (2)
:
Wear Rings
:
Shaft Box
:
: none
:
:
:
:
:
:
:
:
:
:
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
:
:
Operating Pressure
[bara] : 156.5
Test Pressure
[bara] :
Remarks:
(3) Double mechanical seals and seal fluid required for LPG service. Further details to be specified by
Rotating Equipment specialist.
(4) MS = Mild Steel; HT Steel = High Tensile Steel
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
(T)
()
()
(pv)
Capacity
Suction
Discharge
(v)
(ps)
(pd)
P-201 A/B
Intermediate Pump
Theoretical Power
[kW]
Pump Efficiency
Power at Shaft
[-]
[kW]
RPM
Drive
Type electrical motor
Tension
Rotational direction
[V]
Foundation Plate
Flexible Coupling
Pressure Gauge Suction
Pressure Gauge Discharge
Min. Overpressure above
pv/pm
[bar]
Pump House
Pump Rotor
Shaft
Special provisions
Operating
:
Installed Spare :
0.027
1
1
37.8
{ = v( pd - ps)102 }
:
:
Construction Details (1)
:
Nominal diameter
Suction Nozzle
[]
:
Discharge Nozzle []
:
:
Cooled Bearings
: Clock /
Cooled Stuffing Box
Counter Cl. Smothering Gland
: Combined /
If yes
two parts
- Seal Liquid
: Yes
- Splash Rings
: No
- Packing Type
: Yes
- Mechanical Seal
- N.P.S.H.
[m]
:
{ = pmg }
Construction Materials (2)
:
Wear Rings
:
Shaft Box
:
: none
:
:
:
:
:
:
:
:
:
:
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
:
:
Operating Pressure
[bara] :
Test Pressure
[bara] :
Remarks:
(5) Double mechanical seals and seal fluid required for LPG service. Further details to be specified by
Rotating Equipment specialist.
(6) MS = Mild Steel; HT Steel = High Tensile Steel
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
(T)
()
()
(pv)
Capacity
Suction
Discharge
(v)
(ps)
(pd)
P-202 A/B
Booster Pump
Theoretical Power
[kW]
Pump Efficiency
Power at Shaft
[-]
[kW]
RPM
Drive
Type electrical motor
Tension
Rotational direction
[V]
Foundation Plate
Flexible Coupling
Pressure Gauge Suction
Pressure Gauge Discharge
Min. Overpressure above
pv/pm
[bar]
Pump House
Pump Rotor
Shaft
Special provisions
Operating
Installed Spare
0.045
:
:
1
1
37.8
{ = v( pd - ps)102 }
:
:
Construction Details (1)
:
Nominal diameter
Suction Nozzle
[]
:
Discharge Nozzle []
:
:
Cooled Bearings
: Clock /
Cooled Stuffing Box
Counter Cl. Smothering Gland
: Combined /
If yes
two parts
- Seal Liquid
: Yes
- Splash Rings
: No
- Packing Type
: Yes
- Mechanical Seal
- N.P.S.H.
[m]
:
{ = pmg }
Construction Materials (2)
:
Wear Rings
:
Shaft Box
:
: none
:
:
:
:
:
:
:
:
:
:
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
:
:
Operating Pressure
[bara] : 2.5
Test Pressure
[bara] :
Remarks:
(7) Double mechanical seals and seal fluid required for LPG service. Further details to be specified by
Rotating Equipment specialist.
(8) MS = Mild Steel; HT Steel = High Tensile Steel
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
(T)
()
()
(pv)
Capacity
Suction
Discharge
(v)
(ps)
(pd)
P-203 A/B
Vacuum Pump
Theoretical Power
[kW]
Pump Efficiency
Power at Shaft
[-]
[kW]
RPM
Drive
Type electrical motor
Tension
Rotational direction
[V]
Foundation Plate
Flexible Coupling
Pressure Gauge Suction
Pressure Gauge Discharge
Min. Overpressure above
pv/pm
[bar]
Pump House
Pump Rotor
Shaft
Special provisions
Operating
Installed Spare
49
:
:
1
1
{ = v( pd - ps)102 }
:
:
Construction Details (1)
:
Nominal diameter
Suction Nozzle
[]
:
Discharge Nozzle []
:
:
Cooled Bearings
: Clock /
Cooled Stuffing Box
Counter Cl. Smothering Gland
: Combined /
If yes
two parts
- Seal Liquid
: Yes
- Splash Rings
: No
- Packing Type
: Yes
- Mechanical Seal
- N.P.S.H.
[m]
:
{ = pmg }
Construction Materials (2)
:
Wear Rings
:
Shaft Box
:
: none
:
:
:
:
:
:
:
:
:
:
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
:
:
Operating Pressure
[bara] : 0.02/1
Test Pressure
[bara] :
Remarks:
(9) Double mechanical seals and seal fluid required for LPG service. Further details to be specified by
Rotating Equipment specialist.
(10) MS = Mild Steel;
HT Steel = High Tensile Steel
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
V-201
Flash Vessel
In Series
In Parallel
:
:
1
none
General Data
- Buffer / Storage / Separation / Reaction
Service
Type
: Vessel
Position
: - Horizontal
- Vertical
: - Demister / Plate / Coil / _________
: - none / Open / Closed / External Hxgr /________
: n.a.
: n.a.
: n.a.
: 0.46
: 1.85
: 0.31
: C.S.
:
Internals
Heating/Cooling medium
- Type
- Quantity
- Press./Temp.s
Vessel Diameter (ID)
Vessel Height
Vessel Tot. Volume
Vessel Material
Other
[kg/s]
[bara/oC]
[m]
[m]
[m3]
Process Conditions
Feed
Stream Data
Top
Bottom
Temperature
[oC]
: 42.05
: 42.05
: 42.05
Pressure
[bara]
: 4.5
: 4.5
: 4.5
Density
[kg/m3]
:686
:3.86
:1104
Mass Flow
[kg/hr]
:1660
:3.3
:1657
Composition
TEG
Water
Others
mol%
wt%
mol%
91.01
8.45
0.54
wt%
mol%
0
0.5
99.5
Remarks:
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
wt%
91.19
8.47
0.34
V-202
Reboiler
In Series
In Parallel
:
:
1
none
General Data
- Buffer / Storage / Separation / Reaction
Service
Type
: Vessel
Position
: - Horizontal
- Vertical
: - Demister / Plate / Coil /Tubes
: - none / Open / Closed / External Hxgr /Natural Gas
: Fuel
: 2.66
: n.a.
: 0.35
: 1.4
: 0.14
: C.S.
:
Internals
Heating/Cooling medium
- Type
- Quantity
- Press./Temp.s
Vessel Diameter (ID)
Vessel Height
Vessel Tot. Volume
Vessel Material
Other
[kg/hr]
[bara/oC]
[m]
[m]
[m3]
Process Conditions
Feed
Stream Data
Top
Bottom
Temperature
[oC]
: 150.3
: 204
: 204
Pressure
[bara]
: 1.1
: 1.1
: 1.1
Density
[kg/m3]
:1012
:1.104
:962.4
Mass Flow
[kg/hr]
:764.3
:1.12
:763.2
Composition
TEG
Water
Others
mol%
wt%
mol%
99.02
0.77
0.28
wt%
mol%
28.37
30.03
41.6
Remarks:
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
wt%
99.12
0.7
0.18
V-203
Surge Vessel
In Series
In Parallel
Type
: Vessel
Position
: - Horizontal
- Vertical
: - Demister / Plate / Coil /Tubes
: - none / Open / Closed / External Hxgr /
: n.a
: n.a
: n.a.
: 0.48
: 1.9
: 0.34
: C.S.
:
[kg/hr]
[bara/oC]
[m]
[m]
[m3]
Process Conditions
Feed
Stream Data
1
none
General Data
- Buffer / Storage / Separation / Reaction
Service
Internals
Heating/Cooling medium
- Type
- Quantity
- Press./Temp.s
Vessel Diameter (ID)
Vessel Height
Vessel Tot. Volume
Vessel Material
Other
:
:
Make up
Bottom
Temperature
[oC]
: 202.9
35
: 198.0
Pressure
[bara]
: 1.1
: 2.5
Density
[kg/m3]
:964.2
1110
:969.6
Mass Flow
[kg/hr]
:761
24.11
:785.2
Composition
TEG
Water
Others
mol%
wt%
mol%
99.2
0.06
0.2
wt%
mol%
99.2
0.8
0
Remarks:
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
wt%
99.2
0.06
0.2
FILTERSPECIFICATION SHEET
EQUIPMENT NUMBER :
NAME
:
S-201A/B
Filter
In Series
In Parallel
:
Type
: Filter
Position
: - Horizontal In-Line
- Vertical
: Strainer
: 1657
: 3.5/42.
: 0.48
: S.S.
:
[kg/hr]
[bara/oC]
[m]
1
1
General Data
- Buffer / Storage / Separation / Reaction/Filtration
Service
- Type
- Quantity
- Press./Temp.s
Strainer Diameter (ID)
Strainer Material
Other
:
:
Remarks:
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
SPECIFICATION SHEET
S-202 (1)
In Series
: none
Pervaporation membrane module
In Parallel : 138
General Data
: - Buffer / Storage / Separation / Reaction
Type
: Vessel
Position
: - Horizontal
- Vertical
: - Demister / Plate / Coil / Tubes / Membranes tubes
: - none / Open / Closed / External Hxgr / Natural Gas
: n.a
: n.a
: n.a.
: 0.26
: 1.402
: 0.074
: S.S.
:
Internals
Heating/Cooling medium
- Type
- Quantity
- Press./Temp.s
Vessel Diameter (ID)
Vessel Length
Vessel Tot. Volume
Vessel Material
Other
[kg/hr]
[bara/oC]
[m]
[m]
[m3]
Process Conditions
Feed
Stream Data
Retentate
Permeate
Temperature
[oC]
: 150.3
: 150.3
: 150.3
Pressure
[bara]
: 3.0
: 1.5
: 0.02
Density
[kg/m3]
: 621
: 522
:1
Mass Flow
[kg/hr]
: 1657
: 1529
: 128
Composition
TEG
Water
Others
mol%
wt%
mol%
91.20
8.47
0.33
wt%
mol%
98.95
0.69
0.36
Designers :
Project ID-Number :
Date
:
CPD3425
June 2015
wt%
100
-
Bibliography
[1] J. Pettersen, Natural gas fundamentals (2006).
[2] E. Kirk-Othmer, of chem, Tech., 1, 733 (1983).
[3] S. Mokhatab and M. J. Economides, Process selection is critical to onshore lng economics, World
oil 227, 95 (2006).
[4] Opening the area around jan mayen for petroleum activities public hearhttps://www.regjeringen.no/en/aktuelt/
ing
on
impact
assessment,
opening-the-area-around-jan-mayen-for-pe/id705121/, (Visited on 06/01/2015).
[5] Oil and gas - invest in norway, http://www.invinor.no/no/Industries/Oil-and-Gas/,
(Visited on 06/01/2015).
[6] Status
of
norwegian
natural
gas
and
a
forecast
towards
2025
http://fractionalflow.com/2014/10/05/
fractional
flow,
(Visited
status-of-norwegian-natural-gas-and-a-forecast-towards-2025/,
on 06/01/2015).
136
Bibliography
[19] C. O. TOXICOLOGY, EMERGENCY AND CONTINUOUS EXPOSURE LIMITS FOR SELECTED AIRBORNE CONTAMINANTS, Vol. 1 (National Academy Press, Washington, D.C., 1984).
[20] Gases - explosive and flammability concentration limits, http://www.engineeringtoolbox.
com/explosive-concentration-limits-d_423.html, (Visited on 06/10/2015).
[21] T. I. A. of Oil & Gas Producers, Monday accident & lessons learned: Ogp safety alert teg fire
at gas dehydration unit, http://www.taproot.com/archives/40586 (2013), (Visited on
06/10/2015).
[22] E. Altman, P. Kreis, T. van Gerven, G. Stefanidis, A. Stankiewicz, and A. Grak, Experimental,
modeling and simulation of reactive distillation, Microwave Enhanced Reactive Distillation 49, 95
(2010).
[23] J. Robinson, S. Kingman, D. Irvine, P. Licence, A. Smith, G. Dimitrakis, D. Obermayer, and
C. O. Kappe, Understanding microwave heating effects in single mode type cavities theory and
experiment, Physical Chemistry Chemical Physics 12, 4750 (2010).
[24] A. Stankiewicz and J. A. Moulijn, Re-engineering the chemical processing plant: process intensification (CRC Press, 2003).
[25] Automobile technology:
Turbocharger, http://automobiletechinfo.blogspot.nl/
2013/09/turbocharger.html, (Visited on 06/26/2015).
[26] Energy recovery turbocharger energy analysis - energy recovery,
energyrecovery.com/resource/turbocharger-energy-analysis/,
06/11/2015).
http://www.
(Visited
on
[29] P. Kraychy and A. Masuda, Molecular sieves dehydrate high-acid gas at pine creek, Oil and Gas
Journal (1966).
[30] M. F. Doherty and M. F. Malone, Conceptual design of distillation systems (McGraw-Hill Science/Engineering/Math, 2001).
[31] W. L. Luyben and I.-L. Chien, Design and control of distillation systems for separating azeotropes
(John Wiley & Sons, 2011).
[32] www.graham-mfg.com/usr/pdf/techlibvacuum/210.pdf,
http://www.graham-mfg.com/
usr/pdf/techlibvacuum/210.pdf, (Visited on 06/11/2015).
[33] C. Ramshaw and R. H. Mallinson, Mass transfer apparatus and process,
4,400,275.
(1983), uS Patent
[34] L. Agarwal, V. Pavani, D. Rao, and N. Kaistha, Process intensification in higee absorption and
distillation: design procedure and applications, Industrial & Engineering Chemistry Research 49,
10046 (2010).
[35] T. Kelleher and J. R. Fair, Distillation studies in a high-gravity contactor, Industrial & engineering
chemistry research 35, 4646 (1996).
Bibliography
137
[36] File:half-yearly electricity and gas prices, second half of year, 201214 (eur per kwh) yb15.png statistics explained, http://ec.europa.eu/eurostat/statistics-explained/index.
php/File:Half-yearly_electricity_and_gas_prices,_second_half_of_year,
(Visited on 06/10/2015).
[37] Pumping costs, http://www.engineeringtoolbox.com/water-pumping-costs-d_
1527.html, (Visited on 06/08/2015).
[38] How much carbon dioxide is produced per kilowatthour when generating electricity with fossil
fuels - faq - u.s. energy information administration (eia), http://www.eia.gov/tools/
faqs/faq.cfm?id=74&t=11, (Visited on 06/10/2015).
[39] N. E. Leadbeater, Microwave heating as a tool for sustainable chemistry (CRC Press, 2010).
[40] C. O. Kappe, A. Stadler, and D. Dallinger, Microwaves in organic and medicinal chemistry (John
Wiley & Sons, 2012).
[41] J. Wijmans, A. Ng, and A. Mairal, Natural gas dehydration process and apparatus, (2004), uS
Patent App. 10/280,147.
[42] C. Yu, C. Zhong, Y. Liu, X. Gu, G. Yang, W. Xing, and N. Xu, Pervaporation dehydration of ethylene
glycol by naa zeolite membranes, Chemical Engineering Research and Design 90, 1372 (2012).
[43] R. Huang, P. Shao, X. Feng, and W. Anderson, Separation of ethylene glycol-water mixtures
using sulfonated poly (ether ether ketone) pervaporation membranes: membrane relaxation and
separation performance analysis, Industrial & engineering chemistry research 41, 2957 (2002).
[44] pervaporation-membranes.com/wp-content/uploads/2014/10/datasheet-pvm-094-version-1610-2014.pdf, http://pervaporation-membranes.com/wp-content/uploads/2014/
10/Datasheet-PVM-094-version-16-10-2014.pdf (), (Visited on 06/11/2015).
[45] pervaporation-membranes.com/wp-content/uploads/2014/10/datasheet4-channel-hybrid-silica-membranes-version-23-9-2014.pdf,
http://
pervaporation-membranes.com/wp-content/uploads/2014/10/
Datasheet-4-Channel-Hybrid-Silica-membranes-Version-23-9-2014.pdf
(),
(Visited on 06/15/2015).
[46] pervaporation-membranes.com/wp-content/uploads/2014/10/datasheet-pvm-094-version-1610-2014.pdf, http://pervaporation-membranes.com/wp-content/uploads/2014/
10/Datasheet-PVM-094-version-16-10-2014.pdf (), (Visited on 06/15/2015).
[47] W. U. W. Werkgroep Begrotingsproblemen in de Chemische Industrie (Webci), Dace prijzenboekje,
Kostengegevens tbv ramingen , 254 (2005).
[48] Matches engineering to chemical energy manufacturing metallurgical industries, http://www.
matche.com/, (Visited on 06/08/2015).
[49] Eur to usd exchange rate - bloomberg markets, http://www.bloomberg.com/quote/
EURUSD:CUR, (Visited on 06/23/2015).
[50] J. R. Couper, W. R. Penney, and J. R. Fair, Chemical Process Equipment revised 2E: Selection and
Design (Gulf Professional Publishing, 2009).
[51] Calculator: Saturated steam table by pressure tlv, http://www.tlv.com/global/TI/
calculator/steam-table-pressure.html (), (Visited on 06/25/2015).
[52] Heat transfer coefficients in heat exchangers, http://www.engineeringtoolbox.com/
heat-transfer-coefficients-exchangers-d_450.html (), (Visited on 06/25/2015).
[53] J. Fair, How to predict sieve tray entrainment and flooding, Petro/Chem Eng 33, 45 (1961).
138
Bibliography
limited,
www.aquacoolct.com/articles.htm,
(Visited
on