Mds Odtawc Slidebook - 2015
Mds Odtawc Slidebook - 2015
ii
iii
iv
vi
vii
DISCLAIMER
Murchison Drilling Schools (MDS) has a strong reputation around the world for teaching sound drilling
operations and well control practices. MDS employs experienced engineers with extensive operational
backgrounds. MDS teaches recognized best practices in the industry from authorities and regulatory
agencies around the world. MDS materials have been submitted to and approved by the International
Association of Drilling Contractors (IADC) and the International Well Control Forum (IWCF).
Additionally, MDS maintains copies of current publications of Standard Practices and Recommended
Practices from the SPE. MDS regularly updates its materials using all of these best practices.
These training materials may provide guidance supplemental to the requirements of local legislation.
Nothing herein, is intended to replace, amend, supersede or otherwise depart from such requirements. In
the event of any conflict or contradiction between the provisions of these materials and local legislation,
applicable laws shall prevail.
In many cases, an operational procedure or best practice in one area may not be the best or preferred
practice in another location. MDS may offer multiple solutions to some problems, and recommends that
the operators and contractors use the best practice for that area. The use of any particular solution offered
may or may not work. It is the responsibility of the drilling supervisors from the operator and contractor
to determine what course of action should be taken. MDS assumes no liability or responsibility for the
risk for the use or misuse of any drilling practice taught in these materials. Consequently, the recipient of
these training materials is fully liable for the use of any information contained in these courses. The
acceptance of these materials constitutes agreement to the terms of this disclaimer.
viii
Welcome
to
Murchison
Drilling Schools
MDS Facilities
MDS Facilities
Objectives
1. How to supervise a drilling operation.
2. How to preplan field operations.
3. How to analyze and solve drilling
problems.
4. How to prevent unscheduled events.
5. How to communicate on the rig.
Purpose:
To better equip the field man with
background information on Drilling
Operations Technology so that he can
comfortably put a pencil to an operation
prior to performing the job, and be a
better supervisor.
Methods
Course Materials
Day One
Introduction
Things That Do Not Enhance Making Hole
Initial (Entrance) Test
Pre-Spud Meeting, Contractor/Operator Meeting
Problem Solving Model
Trends
Drill String Design
Simulator Instructions
Simulator Problem #1
Logic of Course
Material Sequence
Communication
Drill String Design
Operational Well
Control & Simulator
(Bonus Due Day
Eight)
IWCF Equipment 1
(Bonus Due Day
Eight)
1. Tight hole
Unstable Shales
Mud (Rheology, water
loss, inhibition)
Hole Cleaning
Deviation
2. Surface hole
(shallow gas)
Different
geographical regions
in the world
Production leaks
Poor cement jobs
3. Mechanical Problems
Be alert to symptoms of mechanical problems and
preventive maintenance.
Communicate. Good communication prevents problems
from developing.
Use computerized maintenance programs
Good communication is the key to safe drilling
operations.
Lost Circulation
Secondary Problems
Stuck Pipe
Kicks/Blowouts
Loss of Hole
Lost Circulation
Stuck Pipe
Well Control
8. Mud
9. Hydraulics
Optimization Priorities
1.
2.
3.
4.
Pre-Spud Meeting
Mud
Hydraulics
Bit Selection
Weight and RPM
Good Communication
Good Communication
Good Communication
Verbal Communication:
Is more personal than written communication.
Offers other ways of communicating: tones,
inflections, rate, volume, facial expressions,
body language, etc. (Experts say 90% of
communication is non-verbal.)
Can be easily disputed or denied. If it involves
contracts or decisions, formal meeting notes
should be written and sent out to all parties.
Good Communication
Telephone/Radio Communication:
Is a form of verbal communication.
Immediate responses and decisions can be
reached.
Can be easily disputed or denied. If it involves
contracts or decisions, formal meeting notes
should be written and sent out to all parties.
Good Communication
Good Communication
Written Communication:
Can be formal or informal.
Should be used for all decisions and contracts
as they cannot be easily disputed or denied.
Provide excellent historical documents.
Can be easily copied and distributed.
Can be very exact and precise.
Is better for data and details.
Good Communication
E-mail Communication:
Is a form of written communications.
Fast responses and decisions can be reached.
(E-mails should be answered within two
business days or sooner.)
Cannot be easily disputed or denied.
Provide excellent historical documents.
Many parties can be kept informed (cc, bcc).
Good Communication
Responsiveness In Communication:
Good communication requires a response by
the receiver to acknowledge and verify what
has been transmitted.
Responses need to be timely. A delayed
response is almost as bad as no response.
No response is bad communication.
Good Communication
Good Communication
Good Communication
Good Communication
Good Communication
Good Communication
Conducting Meetings
1. Set an objective for the meeting.
2. Plan a meeting agenda.
3. Make sure the right people are in
attendance.
4. Encourage feedback and ideas from
attendees.
5. Keep meeting moving and on track.
6. Summarize and come to closure on
all points discussed.
7. Keep written meeting notes.
Good Communication
What is a Plan
Must describe in detail the objective of the plan
Must be in writing
Must detail all steps and material required
Must give purpose of each step
Must be understandable by all who must use it
Pre-Spud Meeting
Pre-Spud Meeting
Pre-Spud Meeting
Pre-Spud Meeting
Pre-Spud Meeting
Pre-Spud Meeting
1. Rig Selection
A. Good Solid People (Low Turnover)
Without good people you will have brush fire
operations.
Need good training program
B. Drill String
Get independent inspection and pay for it.
Make sure you have the right equipment for
each section of hole you will drill in.
Drill String has great influence on hydraulics
See Page 3, Introduction Chapter of Drilling Manual.
Operator/Contractor Meeting
1. Rig Selection
Operator/Contractor Meeting
2. Good communication.
This should be a
private meeting.
3. Review of
responsibilities.
4. Review of BSEE
regulations.
5. The IADC Report
Operator/Contractor Meeting
Operator/Contractor Meeting
6. Blowout Prevention
Drills (Reaction and Trip
Drills).
Operator/Contractor Meeting
Mishandling of
Primary Problems
will lead to
Associated Problems.
Primary Problems
Associated Problems
2. Improper approach
3. Mishandling lost
circulation causes
Primary Problems
4. Poor tripping practices
can lead to
1. Stuck pipe.
2. Well control kicks.
Primary Problems
Associated Problems
Associated Problems
1. Kicks off bottom related to
swabbing.
2. Lost circulation related to
surge.
3. Shale problems related to
surge and swabbing.
4. Stuck pipe.
5. Drill string problems
related to pipe handling.
6. Costs.
Primary Problems
Associated Problems
1. Shale problems.
2. Stuck pipe.
3. Mud stability.
4. Costs.
1. Lost circulation.
2. Stuck pipe.
3. Blowouts.
Primary Problems
8. Rig mechanical
problems can cause
Associated Problems
Primary Problems
10. Shale ballooning can
lead to
Primary Problems
12. Drill string washouts
lead to
1. Twist off.
2. Tripping complications
14. Communication
problems can cause
Primary Problems
Primary Problems
1.
2.
3.
4.
Associated Problems
Associated Problems
1. Stuck pipe.
1.
2.
3.
4.
5.
Associated Problems
Primary Problems
1. Operational problems.
16. Micro-managing
drilling operations
from city can lead to
10
Associated Problems
Associated Problems
1. High costs.
2. Well problems.
3. Unmotivated rig
supervision.
1. Associated problems
developing.
2. Unsuccessful solution to
problem.
3. Cost.
4. Safety.
Communicating Problems
To The Office
Communicating Problems
To The Office
11
Hole Trends
Hole Trends
P2 P1 (
Hole Trends
SPM 2 2
)
SPM 1
Hole Trends
Hole Trends
P2 P1 (
Hole Trends
SPM 2 2
)
SPM 1
Driller observes:
200 lb. drop in pressure (to 2800)
Strokes stayed at 100 spm.
12
Hole Trends
Drag Trend
Drag Trend
OVER PULL
Pick
up
Set
down
Hole Trends
Hole Trends
Hole Trends
Torque Trend
Torque Trend
This is a measurement of
rotational torque.
Torque affected by:
Hole Trends
Hole Trends
Torque Trend #1
Transition Zone
If this was caused by a
transition zone, you would see:
ROP increase.
Shale cuttings larger
Well control trend changes
Torque Trend #1
Hole Loading
If this was caused by the hole
loading up, you would see:
Pressure stroke change.
Drag down or squat down
increase.
Rate of penetration (ROP)
slow down.
13
Hole Trends
Torque Trend #1
Torque Trend #2
Broken Formation
This is a broken formation
torque trend.
The cause of it is soft and
hard streaks with different
formation compressibility.
Area knowledge will dictate
what driller does.
Bit Under-Gauge
If this was caused by a bit worn
under-gauge:
Would see a drag on pickup.
Look at lithology (example:
abrasive sand)
Look at time on bit
Torque increase is being caused by
stabilizers down in the under gauged
hole.
Hole Trends
Torque Trend #2
Broken Formation
Smooth torque means there is
correct weight on the bit for
the RPMs and hydraulics.
High erratic torque means
there is the wrong weight on
the bit for the RPMs and
hydraulics that are being
drilled with.
Hole Trends
Hole Trends
Torque Trend #3
Bit Locked Up
This was probably caused by
bearing failure, but there is a
possibility that Tuckers wrench
is in the hole.
POH if torque wont drop to
normal range.
Hole Trends
Hole Trends
14
Hole Trends
Hole Trends
Trip Trends
Hole Trends
Hole Trends
Trip Trends
Trip Trends
Hole Trends
Hole Trends
15
Hole Trends
Hole Trends
Hole Trends
Hole Trends
Hole Trends
Hole Trends
16
Hole Trends
Mud Trends
Mud Weight
Yield Point and
Gel Strength
Yield Point
uses: ECD,
MW, Swab,
Surge, Hole
Cleaning
True-Wate Balance
Hole Trends
Hole Trends
Hole Trends
Mud Trends
Mud Weight
Yield Point and
Gel Strength
Solids
Mud Chemistry
Gas Cut
YP 0.1
ECD MWH
D H D DP
YP
MWT MWB
11.7 D H D DP
Hole Trends
Hole Trends
Mud Trends
Mud Trends
Depth 20,000 ft
MW cut from 18 ppg to 9.0 ppg
Depth 20,000 ft
MW cut from 18 ppg to 9.0 ppg
W W2
Ph
PPSI 1
33.81 Log
W2
14.7
W W2
Ph
PPSI 1
33.81 Log
W2
14.7
Where:
Ppsi
W1
W2
Ph
18 9
18, 720
PPSI
33.81 Log
9
14.7
=
=
=
=
17
Vertical Holes
Various Bottom Hole Assemblies with general responses under ideal conditions
(no hole curvature effects) (See Drilling Manual, DS Design, page 47.)
Assembly
Number
1.
2.
3.
4.
5.
Response
Build
10
90
(2)
Build
60
(3)
Build
60
(4)
Build
7-3
(5)
Build
7-5
(6)
Build
5-3
(7)
Build
4-2
(8)
Build
3-2
45
30
(10)
Hold
Bit
15
30
30
30
(11)
Hold
15
(12)
Hold
15
(13)
Hold
5-8
5-10
30
(14)
Hold
1-3
30
30
(15)
Drop
10
30
30
30
30
30
30
Assembly
Number
Response
(16)
Drop
Relative Response
Strength
5-10
45
(Smaller holes
can be better
than #15)
30
(17)
(18)
30
30
30
(19)
60-70
Drop or Build
(Drop or build dependent on collar OD)
60-70
30
45
15
30
Various Bottom Hole Assemblies with general responses under ideal conditions
(no hole curvature effects)
(Approx. 3-5 from bit
Near Bit
Stabilizer
10
Build or Drop
Various Bottom Hole Assemblies with general responses under ideal conditions
(no hole curvature effects)
Relative Response
Strength
Near Bit
Stabilizer
Bit
Response
Relative Response
Strength
(1)
(9)
Assembly
Number
Horizontal Holes
30
18
90 Foot Build
Drill Collar
60 Foot Build
Drill Collar
Full Gauge String Stabilizer
Drill Collar
2.5 to 3 / 100 ft
Drill Collar
Drill Collar
Drill Collar
Drill Collar
Full Gauge Near Bit Stabilizer
Bit
Bit
Gradual Build
Drill Collar
Under Gauge String Stabilizer
Drill Collar
Full Gauge Near Bit Stabilizer
Bit
Drill Collar
Full Gauge Stabilizer
Drill Collar
Under Gauge String Stabilizer
Short Drill Collar
Full Gauge Near Bit Stabilizer
Bit
19
Standard Packed
DROP ASSEMBLY
DROP ASSEMBLY
Drill Collar
Drill Collar
Drill Collar
Less than 1/100*
2/100* Collar
Drill Collar
* At 45 inclination
Bit
Bit
Drill Collar
Drill Collar
Holes 9 or smaller
1. Run stabilizer at the top of second DC.
2. Make sure the two bottom collars are the
largest you can use.
Non-magnetic
components and
survey tools
should be
positioned
according to
local
requirements
Bit
* At 45 inclination
Substitute near bit and
30 ft collar to bring
down rate of drop
35
35
Hole inclination = 30
Hole inclination = 0
= 35
20
45
Hole inclination = 45
Real dip angle = 45
Effective dip angle = 0
There will be no deviation force.
Hole
6
8
12
1. Improved ROP.
2. Improved capability of positioning wells more precisely in
the reservoir.
3. Less casing wear in complex multilateral wells.
4. Increased reach in horizontal wells.
5. Allows economic access to trapped reserves.
6. Reduces operational risk in slim-hole drilling.
16
22
Hole Direction
(High Side) Build and
Maximum Build 0
Build and
Right Turn
Left Turn
Maximum
Left Turn
90 Left
Drop and
Left Turn
90 Right
180
Maximum
Right Turn
Drop and
Right Turn
Maximum Drop
Rule of thumb for orientation of tool face at lower inclinations (less than 30)
21
Maximum Build 0
Drop and
turn left
CHECK LIST
Hold inclination
and turn left
Hold inclination
and turn right
90
90
Drop and
turn right
Hole Direction
(High Side)
Connections
DC:
7 Reg
5 FH
4 FH
NC 50
(6) 9 3
(6) 7 213/16
(24) 6 2
HW: (6) 5 3
BHA Summary
DP: 5, 19.5, Grade E
Premium
5, 19.5 Grade S
Premium
Totals
8. DP Description
9. DP Design Formula
3. Tapered DC Length
10. DP Design
4. Non-Tapered DC
Calculations
5. Stiffness Ratio
7. DC Torque
See Drilling Manual, DS Design, page 58.
Rule of thumb for tool face orientation of a motor and bent sub
assembly at high inclinations (over 30) in soft to medium formations.
Example Problem
TD
= 12,000
Mud Weight
= 11 ppg
Hole Size
= 12
Bit Weight
= 50,000 lbs.
SF
= 15%
Margin of Overpull = 120,000
NC 50 (XH)
NC 50 (XH)
See Drilling Manual, DS Design, page 58.
22
XRED
CHECK LIST
1. Benefits of Tapered String
2. Air Weight Calculations
BF:
Buoyancy Factor
(factor to convert pipe
air weight to pipe
weight in mud.)
SF:
Safety Factor
BF =
% SF
SF = 1+
100
BF =
(6 5 .4 4 - M W )p p g
6 5 .4 4 p p g
% SF
SF = 1+
100
BF =
(65.44 - 11)
65.44
SF = 1.15
DCair
50,000 1.15
0.8319
CHECK LIST
1. Benefits of Tapered String
W.O.B. SF
=
BF
DCair =
15
SF = 1+
100
BF = 0.8319
(6 5 .4 4 - M W )p p g
6 5 .4 4 p p g
= 69,118 lb.
23
Ldc(S3) =
Ldc(S3) =
Ldc(S3) = 121 ft
= 11,850 lb
8,874 lb
DCair BF
SFc =
1 100
(W.O.B.)
Description
71,430 .8319
SFc =
1 100
50,000
Grade E DP
Length
Airweight
Buoy
Weight
Accum.
Weight
690
80,304
66,805
66,805
Grade S DP
SFC = 18.85%
Summary
Note: Lengths on the rig are usually shown in joints of DC, HW and DP.
24
CHECK LIST
1. Benefits of Tapered String
Ldc
W.O.B. SF
WBHA
or Ldc
BF DCWT
BF DCWT
4. Non-Tapered DC Calculations
= 45,000
= 18.0 ppg
= 0.725
= 6 213/16 91 lb/Ft
= 15%
= 300 feet
Ldc
L HW =
L HW
(784 - 300)91
50.38
25
WBHA WOB JT
WBHA 45,000 6,000 51,000 lbs
WBHA WOB JT
L DC
WBHA
BF WDC
L DC
51,000
773 ft
0.725 91
WOB JT
Cos Drift Angle
45,000 10,000
Cos 35
67,143 lbs
WBHA in Mud
WBHA in Mud
WBHA in Mud
BHA in Mud
BF
67,143
0.725
92,610 lbs
WBHA in Air
L Air
WBHA in Air
L Air
WBHA in Air
WBHA
BF WDC
L DC
L Air
BHA in Air
WDC in Air
92,610
91
1,018 ft
26
CHECK LIST
L HW L DC in Air L MDC
L HW
L HW
WDC
WHW
91
1,018 300
50.38
1, 297 ft (approx. 42 jts)
4. Non-Tapered DC Calculations
5. Stiffness Ratio
BHA
93
7 213/16
6 2
POD 4 - PID 4
I/C Large Pipe
I/C 0.0982
* I/C Ratio
I/C Small Pipe
POD
LEN
180
180
300
I/C
71.00
44.80
20.57
OK < 3.5
OK < 3.5
OK < 3.5
CHECK LIST
27
Bending
Strength
Drilling and Well
Control Training
Ratio (BSR)
Bending
Strength
Drilling and Well
Control Training
Ratio (BSR)
To have a BSR of
greater than 2.5,
a 7 H-90
connection could
be used.
CHECK LIST
1. Benefits of Tapered String
4. Non-Tapered DC Calculations
5. Stiffness Ratio
6. BSR
7. DC Torque
28
60
Make-Up Torque
(Drill Collars)
Tong Arm 4 Ft
DC = 9 3 (7 API Reg.)
Torque 84,442 ft-lb (See tables, pages 89-96.)
Line Pull = (84,442 ft-lb) (4 ft sin 90)
Line Pull = 21,110 lb
1.
2.
3.
4.
90
21,110 lb
= 23,220 lb
19.5
Tube Nominal
OD
Weight
8. DP Description
XH
NC50
Premium
Classification
(wear)
Size
Grade
Tooljoint OD/ID
Nom. Weight
Adj. Weight
5
5
5
5
E
X
G
S
6 3
6 3
6 3
6 2
19.5
19.5
19.5
19.5
20.89
21.44
21.92
22.60
Tool Joint
E
X
G
S
OD/ID
63
63
63
62
Adj. Weight
20.89
21.44
21.92
22.60
Ym = 75,000 5.2746
= 395,595 (New)
Ym = 75,000 5.2746 0.7875 = 311,535 (Premium)
Ym = 75,000 5.2746 0.6836 = 270,432 (Class 2)
29
Extra hole (XH) is the same as IEU (Internally and Externally Upset)
5,
19.5,
NC 50
4,
16.60,
EU,
NC50,
5,
19.5,
IEU, NC50,
Numbered Connection
(Pin End)
IF
XH
pages 81-88
page 80
page 78
page 125
page 123
page 141
page 6
page 117
CHECK LIST
1.
2.
3.
4.
Known
8. DP Description
9. DP Design Formula
10. DP Design
YM 0.9
MOP
WTA
120,000
Calculated
Len DPOP
Unknown
30
SF = 0.9
BF:
Buoyancy Factor
MOP: Margin of overpull, lb.
Ldpop: Length of drillpipe that can be used based on a margin of
overpull, ft.
Ym: Working strength based on minimum yield, lb.
WTA: The buoyancy weight of all pipe hanging below the pipe
being designed, lb.
DPAW: The approximate weight, adjusted for upsets, lb/ft.
L dpop
L dpop
Drilling
Well
Slip and
Coefficient
Control Training
Length
L dpsc
Of
Inches Friction
12
(Ym 0.9)
- (WTA )
S h /S T constant
[
]
(DPAW )(BF)
16
31
Transverse
Load
Factor
.06
4.36
1.27
1.34
.08
.10
.12
.14
4.00
3.68
3.42
3.18
1.25
1.22
1.21
1.19
1.31
1.28
1.26
1.24
1.39
1.35
1.32
1.30
.06
4.36
1.20
1.24
.08
.10
.12
.14
4.00
3.68
3.42
3.18
1.18
1.16
1.15
1.14
1.22
1.20
1.18
1.17
1.28
1.25
1.23
1.21
1.45
1.41
1.38
1.34
1.32
1.29
1.27
1.25
1.52
1.47
1.43
1.40
1.37
1.34
1.31
1.28
1.66 1.73
1.59
1.54
1.49
1.45
1.66
1.60
1.55
1.50
1.47 1.52
1.42
1.38
1.35
1.32
1.47
1.43
1.39
1.36
(Ym 0.9)
- (WTA )
Sh /ST constant
=[
]
(DPAW )(BF)
Ldpsc
L dpsc
Description
BHA (DC + HW)
311,535 0.9
-66805
1.42
=
20.89 0.8319
Grade E DP
Length
Airweight
Buoy
Weight
Accum.
Weight
690
80,304
66,805
66,805
5,383
112,451
93,547
160,352
Grade S DP
Summary
L dpop
L dpop
Summary Table
8.
9.
10.
11.
Buoy
Weight
Accum.
Weight
690
80,304
66,805
66,805
Grade E DP
5,383
112,451
93,547
160,352
Grade S DP
*5,927
133,950
111,433
271,785
Summary
12,000
271,785
271,785
CHECK LIST
Benefits of Tapered String
Air Weight Calculations
Tapered DC Length
Non-Tapered DC
Calculations
5. Stiffness Ratio
6. BSR
7. DC Torque
Airweight
1.
2.
3.
4.
Length
Description
22.60 0.832
DP Description
DP Design Formula
DP Design
MOP Check
32
CHECK LIST
tensile strength
ya
ym
FD.O.I. 100
tensile strength
DP Description
DP Design Formula
DP Design
MOP Check
Collapse Correction
FD.O.I. 100
% yield used
8.
9.
10.
11.
12.
ya
ym
50,000 100
% yield used
85,000
311,535
75,000
% yield used = 14.16%
33
LH2O =
(HP Ce SF )
(0.052 MWW)
LH2O =
(HP Ce SF )
(0.052 MWW)
LH2O =
In previous illustration, if
differential pressure across the
packer is limited to 2,500 psi, how
much water cushion is required?
L H 2O
LH2O = 2,924 ft
L H 2O
HP - Pdiff
HP - Pdiff
0.052 MWW
0.052 MWW
5600 - 2500
LH O
0.052 8.33
1.
2.
3.
4.
LH2O = 7,157 ft
34
8.
9.
10.
11.
12.
13.
DP Description
DP Design Formula
DP Design
MOP Check
Collapse Correction
Workshop Explanation
I. Administrative Details
II. Possible problems while
circulating out a kick
Vertical Holes
1. Drill Strings in Tension
2. Not in Compression
3. Stay Below 5 Dogleg Severity
* In this course we will look at vertical
holes.
Simulator Instructions
Simulator Instructions
I. Administrative Details
Simulator Instructions
I. Administrative Details
Simulator Instructions
E. Position Responsibilities
Simulator Instructions
E. Position Responsibilities
35
Simulator Instructions
E. Position Responsibilities
Simulator Instructions
I. Administrative Details
Simulator Instructions
I. Administrative Details
Simulator Instructions
Choke Operation
Technical Plan
Teamwork &
Communication
Organization
Supervision
Number of Kicks
36
Day Two
Review homework
Drillout Considerations Casing testing
Leak-Off and Formation Capability Tests
Limitations to Control Capability
Salt Water Flows
Kill Sheet-Rig Math for Well Control, Formulas &
units, Kill Sheet for Simulator Problem #2, Wait &
Weight Method
Other Well Control Considerations
Simulator ExercisesSimulator Problem #2
Drillout
Considerations
Drillout Considerations
Pre-Drillout Meeting
Best place is on the rig.
1. Review what you
want to accomplish.
2. Review what problems
you anticipate
(prevention).
3. Review how you are
going to handle them.
Drillout
Considerations
Drillout
Considerations
Drillout
Considerations
The table in this section describes the minimum test pressures for
each string of casing. You may not resume drilling or other downhole operations until you obtain a satisfactory pressure test. If the
pressure declines more than 10 percent in a 30-minute test or if there
is another indication of a leak, you must re-cement, repair the casing,
or run additional casing to provide a proper seal. The District
Supervisor may approve or require other casing test pressures.
Different types of
cement require varying
amounts of time to
reach their
compressive strength.
Salt saturated cement
takes a long time to
reach its compressive
strength.
Drillout Considerations
Casing Type
(a) Drive or Structural ....
Drillout Considerations
200 psi
Drillout Considerations
Drillout Considerations
Drillout Considerations
PT 2700 psi
Drillout Considerations
Subsea
When performing casing
or formation test using a
motion compensator, it is
necessary to:
Hang off on a ram
Hang off enough
weight to prevent
hydraulic forces from
pushing the drill string
up the hole.
Data:
Casing: 9, P-110,
47#, Burst 9440 psi,
70% - 6608 psi
DP: 5, 19.5, S
F PA
F 6608 5 0.7854
2
Drillout Considerations
300,000
Note: Oil mud is about
Note: Cv = 8.0 barrels if 100% mud.
twice as compressible.
Drillout Considerations
Drillout Considerations
7920 0.0732
Vc 7200' 23.89 720' 91
2748
Vc = 493.4 bbls
Cv
Drillout Considerations
1. Casing Integrity
2. Establish compressibility of mud during casing
pressure test (use curve for future leak-off test).
Drillout Considerations
15
= 115 psi/20 spm with 15 ppg
13
Drillout Considerations
Drillout Considerations
Drillout Considerations
Drillout Considerations
Drillout Considerations
Drillout Considerations
Warning:
When preparing to run a liner with your
drill string, remove the sub (profile)
from your drill string.
Drillout Considerations
Size
Bit Weight
RPM
9,200 lbs
30
12,800 lbs
40
14,800 lbs
50
12
18,800 lbs
50
1. Poor cement
2. Casing set off
bottom
3. Not bumping plugs
4. Not using both plugs
(a) You must use the pressure integrity test and related
hole-behavior observations, such as pore-pressure test
results, gas-cut drilling fluid, and well kicks to adjust the
drilling fluid program and the setting depth of the next
casing string. You must record all test results and holebehavior observations made during the course of drilling
related to formation integrity and pore pressure in the
drillers report.
(b) While drilling, you must maintain the safe drilling
margin identified the approved APD. When you cannot
maintain this safe margin, you must suspend drilling
operations and remedy the situation.
Test 2
Pressure Integrity Test (PIT):
PIT = (16-13)0.052 8000
Test 1
Leak Off Test (LOT):
LOT 13
1539
0.052 8000
When Pressuring Up
Stop at leakoff
Or stop @ 1248 psi
LOT = 16.6
When Pressuring Up
Stop @ leakoff
Measure bleed-back to confirm leakoff
U-Tube Principle
Understanding the
U-Tube principle is
foundational to well
control.
U-Tube Principle
U-Tube Principle
Two important
formulas that relate
to this principle are
shown below the
illustration.
The shoe pressure
is the formation
pressure minus the
hydrostatic
pressure of all the
fluids below the
shoe.
U-Tube Principle
U-Tube Principle
The surface
pressure is the
Formation Pressure
minus the
hydrostatic
pressure of all the
fluids below the
surface.
U-Tube Principle
U-Tube Principle
U-Tube Principle
Limitations To
Control Capability
1. Kick size.
TVD 0.052
650
MWK 14
15.0
12,500
0.052
a. 10 bbl
b. 30 bbl
Limitations To
Control Capability
1. Kick size.
1. Kick size.
Cap DCAnn
(DBit - OD DC )
1029.4
(8.52 - 6.52 )
0.02914 bbl / ft
1029.4
Cap DCAnn
Limitations To
Control Capability
(D Bit 2 - OD DC 2 )
L DC
1029.4
720 0.029 = 20.98 bbl
(D Bit 2 - OD DP 2 )
1029.4
(8.52 - 52 )
0.0459 bbl / ft
1029.4
Cap DPAnn
Cap DPAnn
Limitations To
Control Capability
1. Kick size.
Limitations To
Control Capability
21.0 bbl
L KDCAnn
L KDCAnn
(VPG )
Cap DCAnn
(10)
343
0.02914
Limitations To
Control Capability
1. Kick size.
Limitations To
Control Capability
21.0 bbl
343 ft
L KDPAnn
(VPG - VDCAnn )
+L DC
(Cap DPAnn )
L KDPAnn
(30 - 21)
+720 = 916 ft
(0.0459)
Limitations To
Control Capability
1. Kick size.
Limitations To
Control Capability
21.0 bbl
343 ft
916 ft
Limitations To
Drilling and Well
Control Training
Control
Capability
Limitations To
Control Capability
Additional formulas
that are important to
know:
Limitations To
Control Capability
Note: There are two ways to derive the pressure at the shoe.
10
Limitations To
Control Capability
6689
8000 0.052
30 Barrel Kick
PShoe
MWE
TVD 0.052
MWE
1. DC Annular Volume
2. Length Influx (10 bbl)
3. Length Influx (30 bbl)
4. SICP (10 bbl)
5. SICP (30 bbl)
7050
8000 0.052
Limitations To
Control Capability
1. DC Annular Volume
2. Length Influx (10 bbl)
3. Length Influx (30 bbl)
4. SICP (10 bbl)
5. SICP (30 bbl)
6. MAASP
Limitations To
Control Capability
21.0 bbl
343 ft
916 ft
865 psi
1225 psi
1123 psi
Limitations To
Control Capability
1. Kick size.
1. Kick size.
Pit Gain
21.0 bbl
343 ft
916 ft
865 psi
1225 psi
Limitations To
Control Capability
1. Kick size.
Limitations To
Control Capability
Kick Tolerance
Pit Gain
BHP Max
TVD 0.052
BHP MWE
10
10,008
10
10,008
15.4
20
9,792
20
9,792
15.1
30
9,651
30
9,651
14.8
11
10,008
15.4
12,500 0.052
Kick Tolerance
Limitations To
Control Capability
1. Kick size.
See Well
Control
Manual,
pages 367382.
Kick Tolerance
10
10,008
15.4
1.4
20
9,792
15.1
1.1
30
9,651
14.8
0.8
Limitations To
Control Capability
See Well
Control
Manual,
pages 367382.
Limitations To
Control Capability
Ann.Vel.(ft / min)
Limitations To
Control Capability
FlowRate 20 bbl/min
Ann.Vol. 0.049 bbl/ft
1
(Va ) MW
2.72
1
(408.2) 13 541 psi
2.72
PHammer
PHammer
12
Limitations To
Control Capability
3. Gas Percolation
It can be extremely
dangerous if:
You dont bleed the
pressure out of the
bubble while the bubble
is percolating.
You confuse DP
Pressure stabilization
with percolation.
Limitations To
Control Capability
Limitations To
Control Capability
3. Gas Percolation
Discussion Topics
1. Rate
2. Surface Pressure due to percolation
3. How to control bottom hole pressure
a. With connection between DP & Annulus.
b. When you do not have connection between
DP & Annulus.
4. Volumetric Formula
Limitations To
Control Capability
3. Gas Percolation
Rate of percolation
can be estimated:
600psi/hr
0.728psi/ft
Ft/hr 824ft/hr
Time
0100
0110
SIDPP
650
750
Ft/hr
Limitations To
Control Capability
3. Gas Percolation
FP
SIDPP
MW
TVD
=
=
=
=
Limitations To
Control Capability
3. Gas Percolation
FP = (SIDPP+MW0.052TVD)
Formation Pressure
Shut In Drill Pipe Pressure
Mud Weight
True Vertical Depth
FP = 650+140.05212,500
FP = 9750 psi
13
SICP
865
965
Limitations To
Control Capability
Limitations To
Control Capability
3. Gas
Percolation
3. Gas Percolation
Formula 25 from Workbook
Surface Pressure =
(Formation Pressure - (Hydrostatic of all * fluids))
* Fluids include all fluids below surface
(Original Mud, Influx and sometimes Kill Mud)
PSurf = (9750 psi - ((12,157 - 824) 14 0.052 + 34.3))*
PSurf = 1,465 psi
Limitations To
Control Capability
Limitations To
Control Capability
3. Gas Percolation
3. Gas Percolation
Limitations To
Control Capability
3. Gas Percolation
Volumetric Method
(Formula 28, Step 1)
Limitations To
Control Capability
3. Gas Percolation
Volumetric Method
(Formula 28, Step 2)
psi/bbl =
Vol/100psi=
Press. increment
psi/bbl
100psi
= 6.3 bbls/100 psi
15.86 psi/bbl
See Well Control Manual, page 324, 482-485.
See Workbook, Well Control, pages 46-47.
14
Limitations To
Control Capability
Limitations To
Control Capability
Limitations To
Control Capability
Limitations To
Control Capability
Limitations To
Control Capability
15
Limitations To
Control Capability
Limitations To
Control Capability
Limitations To
Control Capability
Bp = 5,982 psi
See Workbook, Well Control, page 48.
Limitations To
Control Capability
Limitations To
Control Capability
Formula 31
(Fp - Bp)
Bubble Depth (Bd) = TVD -
MW0.052
Where: Bp = bubble pressure, psi
Bd = bubble depth (btm) ft
Fp = formation pressure, psi
Kv = kick volume, bbl
Bv = bleed volume, bbl
TVD = original TVD, ft
(Fp-Bp)
Bubble Depth (Bd) = TVD -
MW0.052
(9750-5982)
Bd = 12,500 -
0.728
Bd = 7,324 ft
16
Limitations To
Control Capability
Limitations To
Control Capability
4. Method of Reaching
Initial Circulating
Pressure (ICP).
(Bringing Pump up
to ICP).
Limitations To
Control Capability
Limitations To
Control Capability
5. Stroke Fluctuation
SPM 2
P2 = P1
SPM1
2
18
P2 = 800 = 648
20
Limitations To
Control Capability
5. Stroke Fluctuation
Example: Kill operation has reached FCP. FCP is
800 psi, SPM is 20. Driller slows pump down to 18
SPM. Toolpusher maintains 800 psi on DP by
adjusting choke.
What will BHP do?
A. Stay the same
C. Decrease
B. Increase
D. Ride the fence
See Percolation Table on page 477 of the Well Control Manual. Also,
see page 324 (Volumetric Plan).
ICP = (SRP+SIDPP)
SRP = (ICP-SIDPP)
Where:
Limitations To
Control Capability
6. Drillers Method
where:
Note: To change
strokes, look at the
casing pressure, then
read the drill pipe
pressure. That is the
new relationship.
Assumptions are
incorrectly made that the
annulus is clean after one
circulation.
17
API Method
Circulate influx out
keeping ICP constant
1st circulation.
Pump kill MW to bit,
holding casing pressure
constant.
Read FCP with kill mud
at bit.
Hold FCP constant while
circ. kill weight in hole.
Limitations To
Control Capability
If Casing Pressure
is held constant
with a little gas
moving in Annulus,
while pumping kill
mud to bit, the BHP
will change and
possibly more
influx will feed in.
Limitations To
Control Capability
Kick Recognition
Kick Recognition
While Tripping
1. Hole not taking the right
amount of fluid.
Compare the actual
amount of fluid in the
Trip Tank with the Trip
Schedule.
While Drilling
1. Flow Increase
2. Pit Gain
3. Pump Pressure Decrease
Kick Recognition
Kick Recognition
18
Kick Recognition
Kick Recognition In
Horizontal Holes
Kick Recognition In
Horizontal Holes
Kick Recognition
Kick Recognition In
Horizontal Holes
8. Pressure changes
can occur early in
the circulation
process as the kick
is pumped into the
vertical section of
well.
Kick Recognition In
Horizontal Holes
9. Casing pressure
continues to rise
until kick is out of
the horizontal
section.
19
Kick Recognition In
Horizontal Holes
10.The recommended
method of Well Control
for horizontal holes is
the drillers method for
two reasons:
a. Most kicks are related
to swabbing or lost
circulation (and are
not underbalanced).
Kick Recognition In
Horizontal Holes
Kick Recognition In
Horizontal Holes
Saltwater Flows
(SICP SIDPP)
GI = GM -
LI
or
SICP SIDPP
WI MW
L I 0.052
Saltwater Flows
(SICP-SIDPP)
GI = GM -
LI
Saltwater Flows
(SICP-SIDPP)
WI = MW -
L I 0.052
Low MW
(500-520)
= 0.50
G I = 0.468 -
600
Low MW
(500-520)
WI = 9.0 -
9.6
600 0.052
High MW
(778-624)
= 0.47
G I = 0.728 -
600
High MW
(778-624)
WI = 14.0 -
9.06
600 0.052
20
Saltwater Flows
A graphical
approach to kick
identification can
be used.
Plot the P
(SICP-SIDPP)
with the length of
the influx.
Saltwater Flows
Saltwater Flows
Saltwater Flows
2. Sandstone
Stuck Pipe
3. Common to both:
Interfering with logging program
Well control
21
1. Depth:
2. Bit & Hole:
3. Casing:
4. Drill Pipe:
5. Drill Collars:
700 ft., 7 2,
Capacity = 0.0073 bbl/ft
National 10-P-160, Triplex,
Pump Output = 0.10853 bbl/stk
645 psi @ 30 spm (3.24 bpm)
9.8 ppg
12.5 ppg @ 8,000 TVD with 750 psi
surface pressure (14.3 ppg)
650 psi
5 bbls
Baker Solid Float installed
6. Pumps:
7. SRP:
8. Mud:
9. L.O.T.
10. SIDPP:
11. Surface Line:
12. Float:
Surface #2
750
12.5
14.3
9.8
10.75
8000
8000
9.875
11000
30
645
40
1180
11000
Calculate
Maximum Allowable Annular Surface Pressure
750
12.5
Surface #2
Usually the Leak Off Test (L.O.T.) is given in a mud weight equivalent
(e.g. 14.3 ppg).
750
12.5
14.3
14.3
Sometimes L.O.T. is given with the conditions of the test, e.g.:
9.8
Mud weight used = 12.5 ppg
Surface pressure = 750 psi
Then, a mud weight equivalent must be calculated.
1872
10.75
8000
10.75
8000
8000
L.O.T. = MWLOT +
REMEMBER for L.O.T:
Round DOWN to one decimal
30
645
40
1180
= 12.5 +
8000
PSurface
TVDLOT 0.052
9.875
11000750
11000
8000
0.052
= 14.30
40
1180
Surface #2
750
12.5
14.3
9.8
1872
2191
10.75
8000
8000
22
1180
Surface #2
P.O.
P.O.
1872
25 bbl
P.O.
0.10853 bbl/stk
230 stk
2191
10.75
8000
8000
0.10853
9.875
11000
11000
30
645
40
1180
These are just two different terms for the same thing:
the circulating pressure at a given slow pump rate
Dynamic Pressure Loss (PL) is the term used by the IWCF.
23
Depth of well
Diameter of drillpipe
Length and diameter of Collars
Minimum Pump Output
Casing Shoe Depth
Open hole annular volume
Diameter of casing and open hole
Surface #2
Notes:
If a surface line volume is given, it will not be
included in the pump-down plan from surface to
bit.
750
12.5
5
46
14.3
9.8
1872
2191
10.75
8000
8000
0.10853
9.875
11000
24
30
645
40
1180
11000
VADPCH
OHID 2 DCOD 2
1029.4
OHID 2 DPOD 2
LDPOH
1029.4
CID 2 DPOD 2
L DPCH
1029.4
VADCOH L DC
VADPOH
VADPCH
Given:
Length of DCs
Length of HWDP
MD
Incorrect DS Volume
Correct DS Volume
* For Grade S, 5
* For Grade S, 5
= (Tube
=
= (Equiv.ID)2/1029.4
= (4.1845)2/1029.4
= 0.0170099
Use the Equivalent ID
from the table to
calculate DS Volume.
Refer to WC Manual,
pages 617-621.
ID)2/1029.4
(4.276)2/1029.4
= 0.01776 bbls/ft
This is not correct
because DP has upsets,
which change the
equivalent ID of the
DP.
Note: If we are at 10,000 and we used the 0.017762 instead of the correct
number of 0.01701, we would be 7.5 barrels off. This could lead to bad
displacement mistakes.
Calculate Drill
750 String Volume (VDS)
5
46
12.5
14.3
9.8
1872
10.75
2191
VDS =8000
VDP + VDC
8000
= 145.92 + 5.11
0.10853
=9.875151.03 bbl
11000
30
645
40
1180
11000
10300
700
25
0.014167
145.92
0.0073
5.11
151.03
Calculate Drill
750 String Strokes (StkDS)
5
46
12.5
14.3
9.8
1872
0.10853
Given:
Length of DCs OH
Length of HWDP OH
Length of DP CH
MD
151.0 bbl
9.875
0.10853 bbl/stk
11000
30
645
40
1180
= 1392 stk
10300
700
0.014167
145.92
0.0073
5.11
151.03
11000
Required:
Length of DP OH
46
2300
700
8000
Calculate Annulus Open Hole Volume
(VAOH)
0.10853
9.875
11000
30
645
40
1180
11000
0.040087
0.075059
8000
1392
46
28.06
172.64
200.70
26
0.10853
8000
Calculate Annulus Volume (V
Ann)
0.10853
8000
Calculate Annular Strokes (Stk
Ann)
9.875
11000
30
645
40
1180
9.875
11000
11000
30
10300
700
0.014167
0.0073
145.92
5.11
151.03
700
2300
0.040087
0.075059
28.06
172.64
200.70
8000
0.077472
619.78
1392
46
10300 0.014167
820.5 bbl
0.10853 bbl/stk
700 0.0073
Total Strokes
645
40
1180
Total Volume
700
2300
0.040087
0.075059
28.06
172.64
200.70
8000
0.077472
619.78
11000
= 8952 stk
0.014167
= 151.03 + 820.5
700
0.0073
= 971.53 bbl
700
2300
8000
0.040087
0.075059
0.077472
1392
= 9.8 +
1849
61.6
820.5
5711
7560
190
252
971.53
8952
298
619.78
650
11000
645
61.6
5711
7560
190
252
650
11.0
SIDPP
0.052 TVD
650 psi
0.052 11000 ft
= 10.94 ppg
REMEMBER for Kill Mud Weight:
Round UP to one decimal
10.94
10.94
46
650
9.8
MWK = MWH
650
11000
9.8
5.11
28.06
172.64
200.70
1849
650
145.92
151.03
46
= StkDS + StkAnn
9.875
11000
= 1392 + 7560
10300
1392
11000
= VolDS + VolAnn
5.11
820.5
8000
Calculate Total Volume & Strokes
30
145.92
151.03
= 7560 stk
820.5
0.10853
11000
645
Annulus
1180 Volume (bbl)
StkAnn =
Pump Output (bbl/stk)
40
650
650
11000
9.8
11.0
645
1295
650
11
9.8
MWK
FCP = SRP
MWH
11.0
= 645 9.8
= 723.98 psi
27
10.94
645
11.0
1295
723.98
724
9.8
1295
724
1295
724
723.98
9.8
1295
571
724
1295
571
571
1392
724
0.41
100
10
1392
571
0
139
278
418
557
696
835
974
1113
1252
1392
10
10
100
139.2
0
244
488
732
976
1120
1392
571
571
1392
724
0.41
1.
2.
3.
4.
100
100
0.41
41
1295
1254
1213
1172
1131
1090
1049
1008
967
926
885
844
803
762
724
Definition:
It is the Wait and Weight
Method broken up into
two or more pieces.
1295
1195
1095
995
895
795
724
1295
723.98
9.8
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1392
244
57
1295
1238
1181
1124
1067
1010
952
895
838
781
724
1295
0.41
Drillers Method
Wait & Weight Method
Modified Wait and Weight Method
Volumetric Method
28
Sequence of Events
1. Shut well in.
2. Bring pump to speed and start incremental weight
increases. Pump partial kill weight to bit following a
pump-down plan.
3. Pump the contaminant to surface and out the choke.
4. Pump the partial kill weight to surface.
5. Start pumping next incremental mud weight down drill
pipe and up to surface.
6. Repeat until well is killed (2-3 circulations).
psi/pt =
(ICP-FCP)
10(MWkill -MWOrig. )
(ICP-FCP)
10(MWkill -MWOrig. )
psi/pt =
(1300-760)
49.1
10(14-12.9)
Strokes 1945
195
10
10
34
10
10
FCP2ndCirc = 760
20
10
10
29
0
565
1130
1695
1945
Pressure
Second Circulation
Strokes
1300 (ICP)
1200
1100
1000
956 (FCP)
0
992
1945
30
Pressure
956 (ICP)
856
760 (FCP)
VInflux
Cap
2
H
L InfluxDC
D DP
1029.4
2
H
D DC 2
1029.4
Cap DP
Cap DC
20
690
0.029
8.5
1029.4
8.5
H Influx L Influx G I
0.046
6.52
1029.4
0.029
PShoe 6, 282psi
31
Case 1:
Case 2:
Case 3:
Case 4:
Case 5:
32
Determination of
Method of Well Control
97 4 1
2
VOHAnn 2300 8
1029.4
Determination of
Method of Well Control
1029.4
2
2
97 7 1
2
700 8
1029.4
Determination of
Method of Well Control
8.6812 52
VOHAnn 1990
1029.4
Determination of
Method of Well Control
Main Uses
1. Ratio
Meas. Depth
2. Top of bubble at FCP Depth BubbleTopInitially -
Ratio
33
1. Ratio
Ratio
Meas. Depth
2. Top of bubble at FCP Depth of Top bubble initially -
Ratio
12,720
Top of bubble at FCP 12,000 -
2.765
0.047
0.017
Ratio = 2.765
Stk.
(12,000 - 6,000)(0.017)(2.765)
0.113 (bbl/stk)
Strokes = 2,496
34
1. Depth:
2. Bit & Hole:
3. Casing:
4. Drill Pipe:
5. Drill Collars:
6. Pumps:
7. SPR:
8. Mud:
9. L.O.T.
10.
11.
12.
13.
14.
SIDPP:
Water Depth:
Riser:
Choke Line:
Surface Line:
Subsea Problem #2
11,000 RKB, MD, TVD
9
10, J-55, 40.5 lb/ft, 10 ID, 3130 psi
burst, Shoe @ 8,000 RKB, TVD
10,300, 4, 16.60 lb/ft, X-95,
NC 50 IF, 0.014167 bbl/ft
700 ft., 7 2, 0.0073 bbl/ft
Triplex, Pump Output: 0.10835 bbl/stk
434 psi @ 30 spm (3.22 bpm)
*817 psi @ 40 spm (4.36 bpm)
9.8 ppg
12.5 ppg @ 8000 TVD with 750 psi
surface pressure
650 psi
500
22 ID
3.5 ID, 148 psi friction loss at 40 spm
5 bbls
Subsea #2
5
47
14.3
500
500
1872
2191
30
40
9.8
10.75
8000
8000
0.10835
434
817
9.875
11000
148
11000
750
12.5
35
Conventional Method
Conventional Method
965 psi
965 psi
Step 1 - Read pressure while circulating down drill string and up through riser (PRiser).
Step 2 - Close BOP, then circulate down drill string and up through choke line (PChoke)
Subsea #2
750
12.5
5
47
14.3
500
500
9.8
10.75
8000
8000
0.10835
30
40
434
817
9.875
11000
148
11000
36
Removing CL Friction
Step 4 - Circulate through choke line and up riser, then read Casing Pressure
Removing CL Friction
Removing CL Friction
Removing CL Friction
Removing CL Friction
37
RID 2 DPOD 2
VRiser L Riser
1029.4
OHID 2 DCOD 2
1029.4
OHID 2 DPOD 2
VADPOH L DPOH
1029.4
CID 2 DPOD 2
VADPCH L DPCH
1029.4
CLID 2
VCL L CL
1029.4
VADCOH L DC
Given:
Chokeline Length
Riser Length
Length of DCs
Length of HWDP
Depth of casing
MD
Required:
Length of DP CH
Length of DP OH
VDC L DC Cap DC
DPlength OH =
MD (DClength OH) (HWDPlength OH) (DPlength CH)
700
0.10835
8000
8000
Calculate Annulus Volume (V
Ann)
9.875
30
40
434
817
148
= 28.06 + 172.64
10300
0.014167
= 200.7
2300
38
11000
145.92
700
0.0073
700
0.040087
5.11
151.03
28.06
2300
0.075059
172.64
200.70
1394
46.5
7500
0.10835
30
40
0.10835
8000
8000
Calculate Annulus Volume (V
Ann)
434
817
9.875
11000
0.014167
145.92
700
0.0073
5.11
151.03
700
0.040087
2300
0.075059
172.64
200.70
7500
0.077472
581.04
10300
500
0.0119
1394
5.95
151.03
1394
46.5
StkCH =
200.70
StkCL =
1852
5363
62
191
55
787.7
7270
242
StkAnn =
11000
145.92
10300 0.014167
200.7 bbl
= 1852 stk
0.10835 bbl/stk
5.11
700 0.0073
46.5
28.06
434
817
StkOH =
787.7
9.875
11000
Volume
(bbl)
148
Strokes =
Pump Output (bbl/stk)
30
40
11000
148
8000
8000Ann)
Calculate Annular Strokes (Stk
787.7 bbl
= 7270 stk
0.10835 bbl/stk
39
0.10835
30
40
8000
8000
Calculate Total Volume & Strokes
Total Strokes
434
817
Total Volume
= 1394 + 7270
10300
700
2300
7500
0.10835
8000
0.014167
10300
RID DPOD
700 0.0073
1029.4
VRiser = LRiser
22 700
4.5 0.040087
2300 0.075059
1029.4
= 500
= 500
0.45057500
225.25 bbl
=
0.10835 bbl/stk
5.11
151.03
= 2079 stk
172.64
200.70
581.04
0.0119
500
1394
46.5
1852
5363
62
191
55
787.7
7270
242
938.73
8664
289
225.25
2079
5.95
0.4505
817
10.94
650
11
817
172.64
200.70
581.04
1852
5363
62
191
55
7270
242
938.73
8664
289
5.95
10.94
11.0
650
1467
650
11000
9.8
11.0
817
1467
917.04
650
11
918
9.8
10.94
11.0
650
817
1467
917.04
918
850
MWK
MWH
11.0
= 817
9.8
46.5
787.7
650
11000
11000
650
11000
9.8
1394
28.06
650
817
650
9.8
0.0119
9.8
5.11
28.06
0.077472
500
= 225.25 bbl
145.92
0.077472
11000
148
= 8664 stk
145.92
9.875
11000
434
817
0.0073
700 0.040087
= 938.73
bbl
0.075059
500
30
40
0.014167
= VolDS + VolAnn
8000
Calculate Riser Volume (VRiser) and Strokes
(StkRiser)
= StkDS + StkAnn
11000
148
9.875
11000
148
702
FCP = SRP
= 917.04 psi
When ICP has been reached and the Choke Line Friction has been removed,
the remaining pressure is called the Initial Dynamic Casing Pressure.
If our SICP were 850, the Initial Dynamic Casing Pressure would be 702 psi.
40
Formulating
Pump-Down
Plan
11
817
917.04
9.8
(Step Method)
1467
918
Formulating
Pump-Down
Plan
11
817
917.04
9.8
(psi
Increment Method)
918
549
1467
918
549
549
1394
918
0.394
100
10
1394
549
0
139
279
418
558
697
837
976
1115
1255
1394
10
10
100
139.4
0
254
508
762
1016
1270
1394
Formulating
Pump-Down
Plan
11
817
917.04
9.8
(Stroke
Increment Method)
918
549
549
1394
0.394
0.394
39.4
1467
1428
1388
1349
1309
1270
1231
1191
1152
1112
1073
1034
994
955
918
1467
1367
1267
1167
1067
967
918
918
100
100
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1394
254
54.9
1467
1412
1357
1302
1247
1193
1138
1083
1028
973
918
1467
0.394
KOPMD
PL KOP PL FCP PL
TDMD
PL EOB PL FCP PL
TDMD
41
July 1, 2014
Deviated Well
14.5
10.0
0.520
1872
5000
5000
8600
8000
Stk EOBtoFCP
0.13
0.13
8.681
8600
8000
50
500
500
40
320
320
8.5
15000
10000
8600
8000
50
500
500
40
320
320
July 1, 2014
Deviated Well
8.5
15000
10000
800
10000
5000
3600
.017464
.017464
87.32
62.87
672
484
6100
.017464
106.53
819
300
0.00491
1.47
300
6100
0.02914
0.0459
8600
0.0489
500
11
258
800
10000
10.0
1986
800
11.6
11.538
1300
1300
40
8.74
280
289
2221
420.72
709
3236
5457
109
967
7438
149
700
1667
5385
12823
11.6
10.0
44
65
500
580
500
800
11.6
580
580
500
5000
15000
5000
10.0
527
384
July 1, 2014
800
11.6
527
10.0
11.6
546
911
911
680
580
10.0
911
580
500
8600
15000
8000
134
389
231
100
0
100
200
300
400
500
600
672
772
872
972
1072
1156
1256
1356
1456
1556
1656
1756
1856
1956
1986
384
384
500
800
Deviated Well
5000
546
2000
134
1500
680
389
672
57.9
231
484
47.7
100
830
12
1000
500
42
500
1000
1500
2000
1300
1242
1184
1126
1068
1011
953
911
863
816
768
720
680
668
656
644
632
620
608
596
584
580
Day Three
Review homework
General Mud Topics
Shallow Gas & Kicks, Diverting
Top Hole Cleaning & Trends
Hydraulics Workshop
Problem Diagnosis & Pump Plan Revision
Simulator Exercises
Hydraulics
Well Control
Kill Sheet for Simulator
Problem #4
Dont forget Day 8 homework
IWCF Equipment 1 (bonus)
Operational Well Control &
Simulator (bonus)
A. Functions of Mud:
1.
2.
3.
4.
Country
Area
State
Local
Air
Mist
Foam
WBM
Multiple Types
5. OBM
Multiple Bases
We will Focus on WBM and OBM Muds
Mud Weight
Funnel Viscosity (FV)
Apparent Viscosity (AV)
Plastic Viscosity PV
Yield Point (YP)
1. Mud Weight
A. In addition to the Mud Engineer you want the man
in charge of the mud pits to be a key man on the rig
B. Correct Mud Weight Maintenance is one of the key
measurements in Drilling Performance.
C. One of the most important jobs for the pit man is to
keep up with changes in mud weight.
D. Have the pit man check and record the mud weight
every 10 minutes at the flow line and at the suction
tank (coming out of the hole and going in the hole).
6. Gel Strengths
7. Water Loss
8. Solids Analysis
9. Solids
10. Clay Content (MBT)
1. Mud Weight
2. Funnel Viscosity (FV)
Mud Balance
Tru-Wate Balance
2. Funnel Viscosity
2. Funnel Viscosity
C. FV measures: A Viscosity
through a tube with known
diameter and length.
D. Rule-of-thumb: 4 MW(ppg)
AV = 50/2
AV = 25 cp
Fann Viscometer
1.
2.
3.
4.
Mud Weight
Funnel Viscosity (FV)
Apparent Viscosity (AV)
Plastic Viscosity (PV)
0.45
Where:
PV1 and PV2 are the respective plastic viscosities
corresponding to the drilling rates D1 and D2.
Example:
D1
PV1
PV2
= 20 ft/hr
= 32 cp
= 8 cp
1.
2.
3.
4.
5.
0.45
D2 37 ft/hr
Mud Weight
Funnel Viscosity (FV)
Apparent Viscosity (AV)
Plastic Viscosity (PV)
Yield Point (YP)
=
=
PV
YP
ECD
Trip MW
SWAB
SURGE
Hole Cleaning
DH - DDP
ECD 18 20 0.1
8.5-5
YP
MWT MWB
11.7 D H D DP
Where:
MWT =
MWB =
YP =
DH =
DDP =
DH - DDP
Where:
ECD =
MWH =
YP =
DH =
DDP =
YP
MWT MWB
11.7 D H D DP
20
MWT 17.5
11.7 8.5 5
200
100
6
3
Example:
32
25
8
5
Bio-polymers such as XC
polymer are called
Thixotropic or Shear
Thinning.
There is a critical polymer
concentration in the mud
where flow and suspension
properties are optimum.
6 RPM
3 RPM
LSYP
LSYP
LSYP
=
=
=
=
=
24
20
(2R3 - R6)
(2 20 - 24)
16
Shear
Thinning
= 30
YP
= 20
Rate of Shear
(Refer to Mud Chapter page 31.)
Temperature Influence
Drilling and Well
On Rheology
Control Training
Temperature Influence
Drilling and Well
On Rheology
Control Training
Example: 80 F
120 F
600 = 80
600 =
80
300 = 50
300 =
50
48
30
PV
= 30
PV
30
18
YP
= 20
YP
20
12
Temperature Increases
1. A significant decrease in viscosity (Shear Stress)
as the temperature increases from 150 to 300F.
2. The viscosity (shear stress) for a given low shear
rate is not as pressure and temperature
dependent as shear stress at high shear rates.
1.
2.
3.
4.
5.
6.
Mud Weight
Funnel Viscosity (FV)
Apparent Viscosity (AV)
Plastic Viscosity (PV)
Yield Point (VP)
Gel Strengths (Gels)
Low Gels
=
Medium Gels
=
High Gels
=
Progressive Gels =
Initial
1 to 4
5 to 8
9 to 15
5 to 10
Ten Minutes
3 to 6
8 to 12
18 to 50 (or higher)
25 to 100 (or higher)
1. Mud Weight
2. Funnel Viscosity
(FV)
3. Apparent Viscosity
(AV)
4.
5.
6.
7.
7. Water Loss
Test Equipment
Press
#50 Whatman Filter Paper
Parameters
Units
PSI
Time
Temp
Parameters
Units
PSI
Time
Temp
1. Mud Weight
2. Funnel Viscosity
(FV)
3. Apparent Viscosity
(AV)
4. Plastic Viscosity
(PV)
ml
100 psi
30 min
Ambient
ml
500 psi differential
30 min
300 F
8. Solids Analysis
A. Test Equipment
Heating Element
Retort Assembly
Thermostat
Condenser
8. Solids Analysis
8. Solids Analysis
A. Test Equipment
Retort Chamber
Retort Lid
Retort Cup
9. Solids
1. Inert
A. Low Density
B. High Density
3. Fine Solids
Less than 1 micron
4. Coarse Solids
Greater than 1 micron
2. Active
Drill Solids
Inert
Active
Sand
Limestone
Dolomite
Clay
Anhydrite
Salts
Solids Removal
Shaker
Hole Dia.
6.5
8.5
12.25
Ft./hr.
25
25
25
Bbls./hr.
1.03
1.76
3.65
Lbs./hr.
800
1,400
2,900
Desander
Desilter
Centrifuge
Flocculation
Screen Size
40
80
100
150
200
325
Micron Size
381
234
178
105
74
44
50-60
20-30
5-15
<1-5
Fine Solids
Surface Area
6 In2
12 In2
48 In2
384 In2
1,536 In2
6,144 In2
98,304 In2
6% < 1 micron
F = MBT 0.06
10
Where:
VC
VF
MWF
MWC
VW
MWW
Clay Req.
High Density
SG
2.6
H2O
8.33 ppg
Clay
21.66 42 gal/bbl
909.6 ppb
SG
4.2
H2O
8.33 ppg
Barite =
=
=
=
=
=
=
=
Barite Req. =
Vol. Check =
34.99 42 gal/bbl
1469 ppb
35 MWF
VC VF
35 MWC
35 MWF
VC VF
35 MWC
SUMMARY
35 15
VC 1,000
35 8.8
1. VC
2. VW
3. Clay (lb)
763
4. Barite (lb) =
VC = 763 bbl
5. VFCheck
Where:
VC
MWC
VW
MWW
=
=
=
=
SUMMARY
21.66 MWC
VW VC
21.66 MWW
21.66 8.8
VW 763
21.66 8.33
1. VC
763
2. VW
736
3. Clay (lb)
4. Barite (lb) =
VW = 736 bbl
5. VFCheck
11
Where:
VW
MWC
MWW
Clay Req.
21.66 MWC
21.66 8.8
21.66 MWC
Where:
VC
=
=
MWF
MWC
=
Barite Req. =
SUMMARY
1. VC
763
2. VW
736
3. Clay (lb)
24,478
35 - MWF
4. Barite (lb) =
5. VFCheck
35 - MWF
SUMMARY
1470 15 - 8.8
Barite Req. = 763
35 -15
1. VC
763
2. VW
736
3. Clay (lb)
24,478
4. Barite (lb) =
347,699
5. VFCheck
12
Where:
Volume FCheck VW
910
1470
VW
Clay Req.
24,478 347,699
910
1470
Volume FCheck = VW +
+
910
1470
763
2. VW
736
3. Clay (lb)
24,478
4. Barite (lb) =
347,699
5. VFCheck
SUMMARY
1. VC
1,000
13
VF =
VF =
VS
26 MWF
26 MWI
MWF
MWI
26 MWF
VBar (bbl)
2174
2347.9 bbl
26 11.0
26 9.8
VBar (Sx)
VBar (lbs)
1470
189920.6
129.2 bbl
1470
189,921
1900 100-lb sx
100
=
=
=
=
VH2O
VH2O = VF - Bar VS
1470
189,920.6
VH2O 2348
2174 45 bbl
1470
= VF - Bar VS
1470
14
=
=
=
=
VF =
VF =
189,920.6
45 2174
1470
VF = 129.2 45 2174
VBar
VH2O VS
1470
VF = 2348 bbl
The material balance verifies that our numbers are correct.
After weighting up from 9.8 ppg to 11.0 ppg, the volume
will increase from 2174 bbl to 2348 bbl.
SUMMARY
1. Base Fluid Wt. =
2. VF (bbl)
3. VS (bbl)
4. Barite (lb)
5. VFCheck
Calculate the starting volume for a final volume of 1000 bbls. With a
mud weight of 12ppg.
7.33 ppg
VS =
VF
VS =
1000 bbls
Starting volume of base fluid with a 75/25 O/W Ratio = 831 bbls.
Starting volume of water = 831 0.25 = 207.75 bbls
Starting volume of base oil = 831 0.75 = 623.25 bbls
15
OBM
Calculate Barite Required
7.33 ppg
1,000 bbls
=
=
208 bbls
623 bbls
3. VS (bbl)
831 bbls
4. Barite (lb)
5. VFCheck
= 1470 (
) 831
1,000 bbls
3. VS (bbl)
831 bbls
4. Barite (lb)
= 248,032 lbs
5. VFCheck
50 ml Retort Analysis
Oil
= 31.2 ml
Water
= 10.4 ml
Solids
= 8.4 ml
7.33 ppg
1,000 bbls
3. VS (bbl)
831 bbls
4. Barite (lb)
= 248,032 lbs
5. VFCheck
SUMMARY
2. VF (bbl)
7.33 ppg
2. VF (bbl)
SUMMARY
) VS
SUMMARY
=
VH2O
VBASE Oil
%Oil
%H2O
%Solids
1,000 bbls
16
50 ml Retort Analysis
Oil
= 31.2 ml
Water
= 10.4 ml
Solids
= 8.4 ml
% Oil
% H2O
Oil
Water
Solids
.
.
.
.
= 62.4%
= 20.8%
= 16.8%
or
. %
. %
100
= 75%
or
. %
. %
100
= 25%
% Oil X
bbls Oil X bbls
or
% H2O
bbls H2O
624 bbls X bbls
208 bbls
Desired % Oil
Desired % H2O
80%
20%
208 bbls Base Oil or 0.208 bbls Base Oil / bbl mud
Check Calculations
624 bbls 208 bbls
208 bbls
100
80%
20%
= 80% Oil
) 208 bbls
= 66,470
Bbls Barite 66,470 1,470
45 bbls
17
Dh
MW
FP
= 17 in
= 9.2 ppg
= 2,000 0.465 psi/ft
= 930 psi
HP = 9.2 2,000 0.052
= 957 psi
POB = 27 psi
Cuft/hr R.O.P.
(Dh) 2 0.7854
144
Gas Cuft/hr
P1V1 P2 V2
Cuft/hr R.O.P.
Gas = Cuft/hr
(D H )2 0.7854
144
(17.5)2 0.7854
Cuft/hr 100
144
Gas = 50 Cuft/hr
18
P1V1 P2 V2
1.Control Drill
(controlling the rate
of penetration)
2.Drill Pilot Hole
3.Combination
4. Log before hole opening operations. If GAS is
present isolate with plug before hole-opening
944.7 50
14.7
V2 3213 cuft/hr
V2
V2
3213
= 574 bbl/hr
5.6
Diverting
Should be automatic
Diverting
Diverting
1. Detection is difficult
because of wave
action.
19
2. Lost returns
and broaching
because of low
frac gradients.
3. Unstable
(listing, etc)
with single
hull vessels.
Considerations:
Prevention and Solutions
1. Unlatching from
riser (moving off
location).
2. Drilling without
riser (gas exhausting
at sea bottom).
3. Dynamic kills.
4. Collapse of riser.
Considerations:
Prevention and Solutions
20
Present Situation
Well is stable.
No loss or gain with 11 ppg mud.
Well had kicked (because of
porosity gas volume) and was
dynamically killed with 11 ppg
mud.
Estimated leak off at 700' is 11.0
ppg.
A 9.3 ppg mud was being used at
3,700 ft when well was diverted
and dynamically killed.
Case History
Case History
Top Hole
Choices
1. Run casing at present depth
2. Set cement plug on bottom to isolate gas &
run casing on plug
3. Drill ahead and cut mud weight carefully
4. Plug and abandon.
BREAK
DISCUSS!
Top Hole
Top Hole
Rig move
Moving equipment (trucks) lined up
Rig equipment moved
Serviced / rental equipment moved
21
Top Hole
Water on hand
Casing on hand
Casing jewelry - shoe - duplex collar, et
Cement on hand
BOPE rigged up (diverter lines mostly)
(Case History of Agha Jari)
Communication system ready
Fuel on hand
Top Hole
Top Hole
Top Hole
Good alignment is
needed.
Top Hole
Drill the top hole carefully for a good surface casing job.
Do not overpump.
Use pump wisely.
900
800
YP15
YP20
700
600
500
YP30
YP40
0
500
22
17.5"
6. Consider in special
Range
Angle (degrees)
Near-vertical I
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
II
III
60
30
Inclination (degrees)
Angle (degrees)
Near-vertical I
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
II
III
30-60
High IV
60-90
II
III
IV
60
30
Inclination (degrees)
90
Range
Angle (degrees)
Near-vertical I
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
II
III
IV
60
30
Inclination (degrees)
90
Range
Angle (degrees)
Near-vertical I
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
IV
II
III
IV
Difficulty
Intermediate III
Difficulty
Range
10-30
90
0-10
Low II
IV
Angle (degrees)
Near-vertical I
Difficulty
Range
Difficulty
Difficulty
60
30
Inclination (degrees)
90
23
60
30
Inclination (degrees)
90
Range
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
III
IV
Difficulty
II
60
30
Inclination (degrees)
90
Range
Angle (degrees)
Near-vertical I
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
Range
Angle (degrees)
Near-vertical I
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
II
III
60
30
Inclination (degrees)
III
IV
IV
24
90
Range
Angle (degrees)
Near-vertical I
0-10
Low II
10-30
Intermediate III
30-60
High IV
60-90
90
60
30
Inclination (degrees)
Difficulty
II
Difficulty
Angle (degrees)
Near-vertical I
II
III
IV
Difficulty
60
30
Inclination (degrees)
90
35 to 65
Cuttings beds
develop and are
unstable (prone
to avalanche)
25
Hole Size
Critical RPM to
Remove Cuttings
>12"
150
120
< or = 8"
90
Critical RPM
(minimum pipe
rotation speed) is
dependent on hole
size. FR < RPMcrit
will not move cuttings
into flow stream
AV
CCI (MW)(YP)
(PV)(14000)
2
Example 1:
Example 2:
CCI (MW)(YP) 2
AV
(PV)(14000)
AV
(PV)(14000)
120
CCI 9(20) 2
(12)(14000)
CCI 2.57
CCI (MW)(YP) 2
120
(8)(14000)
CCI 0.1543
CCI 9(4) 2
26
Hydraulics
Hydraulics
Drilling Hydraulics
Drilling Hydraulics
Bit Hydraulics
Clean the Bit And Hole Bottom
Cool the Bit
Evaluate
Communicate
Annular Hydraulics
Lift Cuttings and Cavings
Limit Annular Pressure Drop
Limit Hole Erosion
Recommend
Optimization
Actual
Situation
Pump Pressure
Pump Pressure
400
41
800
SPM2
800
P2 P1
164
41
SPM
400
1
27
Pump Pressure
Pump Pressure
Pipe Size
Pressure Required
41
Length (feet)
67 (63% more)
1000
41
2000
82 (twice as much)
400 gpm 10 lb/gal mud 1000 ft of 5" and 4" drill pipe
400 gpm 10 lb/gal mud 5" XH 19.50 drill pipe
Pump Pressure
10
41
12
49 (20% more)
Drilling Hydraulics
Drilling Hydraulics
2800
Pumps
Standpipe
System
Bit
See Drilling Manual, Optimization Chapter, page 18.
28
Hydraulic Horsepower
IF (lb)
Kelly Hose
Standpipe
Pumps
Maximum
Energy
Bit
0
100
200
400
500
Flow Rate (gpm)
300
600
700
800
900
Hydraulic Horsepower
Maximum HHP
2800
HHP (hp)
Max. HHP
Pumps
Standpipe
System
Bit
100
Annulus
Hole Erosion
Hole Cleaning
Loss of Circulation
200
300
400
500
Flow Rate (gpm)
600
Laminar Flow
Turbulent Flow
Cuttings Transport
ECD
Pump
SPM
Liner Size
29
800
Drilling Hydraulics
Downhole Tools
PDM
Turbine
MWD
700
900
Laminar Flow
Reynolds Number
V D
Where :
Re Re ynolds Number
Density (ppg)
V Annular Velocity (ft / min)
Re
Laminar Flow
Drillpipe
Flow Regime
Hole Wall
Cuttings Transport
Cuttings Concentration
Slip Velocity
Cutting Transport
Velocity
Transport Efficiency
Cutting Concentration
Centrifugal
Effect
Rotating
No
Rotation
ROP
Torque
Effect
Hole Diameter
Velocity
Gradient
Transport Efficiency
Flow Rate
30
ECD - Equivalent
Circulating Density
Hydrostatic Pressure
Pressure Loss
in Annulus
Hydraulic Horsepower
Weight of Cuttings
Jet Impact
Hydraulics
Soft Rock vs. Hard Rock
Soft Rock
1. Bit balling is main
problem if drilling with
Water Base Mud.
2. Requires good crossflow
(Flow rate).
3. Requires good hydraulic
horsepower. Use the
following rule of thumb.
Hard Rock
1. Hole balling below
bit main problem.
2. Need good surface
pressure so that jet
velocity is optimized.
3. Low Flow rate is
okay.
Question!
What is wrong with being in
the window (49% to 65%)?
Hydraulics
Soft Rock vs. Hard Rock
Soft
Rock
1. Hydrostatic
4680 psi
2. Formation Pressure 4650 psi
3. Overbalance Pob
30 psi
4. Observation
No chipHolddown
Hard
Rock
Crushed Formation
The process continues, forming a pocket of crushed, permeable material until the stress level is
sufficiently high to propagate cracks and generate major chips.
4680 psi
4330 psi
350 psi
High Chip-Holddown and
hole balling below bit.
As the high stress is released, the large chips are removed leaving behind a pocket of
crushed formation.
31
Rig Hydraulics
2. Hand Calculations:
Flowrate
Critical velocity
Annular Velocity
Pressure losses in
system
Pressure required @ bit
Pressure required @
surface
Given Data:
Present Depth
Anticipated Depth
Mid-depth (used for hydraulics)
Hole Size
Mud Properties
Optimization checks
Nozzle sizing
Actual Pressure at bit
Jet velocity
Optimization final
check
Down hole tools
consideration
Drill String
Anticipated ROP
Pumps
Step 1.
Hose
Swivel
Kelly
Length ID
Length ID
Length ID
Length ID
Type
(ft)
(in)
(ft)
(in)
(ft)
(in)
(ft)
(in)
40
45
40
40
55
40
45
55
40
45
55
40
13,000 ft.
13,800 ft.
13,400 ft.
8 in.
Wt. 13.5 ppg; Pv-28 cps;
Yv - 12 lb/100ft2
Dp 5", 19.5, XH, S, 12,500';
DC 6" 213/16" 450 ft.
HW 5", 49.3, 3", 450 ft.
15 ft/hr.
(2) 12 P 160 Triplex with 6" liners
Rig Hydraulics
Rig Hydraulics
Rig Hydraulics
ROP Ranges
Range 1 - over 50 ft/hr, 50 gpm/inch
Range 2 - 25 to 50 ft/hr, 40 to 50 gpm/inch
Range 3 - 15 to 25 ft/hr, 38 to 45 gpm/inch
Range 4 - 10 to 15 ft/hr, 35 to 40 gpm/inch
Range 5 - 5 to 10 ft/hr, 30 to 39 gpm/inch
See Drilling Manual, Optimization, page 25.
Step 1.
Rig Hydraulics
Rig Hydraulics
Q = Dh gpm/inch
Q = 8.5 40
Q = 340 gpm
32
Rig Hydraulics
Rig Hydraulics
Rig Hydraulics
= 12.72 (D)1.47
QMin
Rig Hydraulics
QMin
= 296 gpm
This compares with 248 gpm for conventional bits.
= 34.8 gpm/inch
QMin
Rig Hydraulics
Step 2.
VC
83.1
PV PV 2 7.22 (YV) (OD - ID)2 MW
(OD - ID) MW
Rig Hydraulics
Step 2.
83.1
2
2
VC
28 28 7.22 (12) (8.5 - 5) 13.5
(8.5 - 5) 13.5
Va
Vc
MW
Vc = 265 ft/min
Va
YV
PV
= plastic viscosity
ID
OD = hole size
33
= drill pipe OD
Rig Hydraulics
Step 2.
Velocity
Type
Va
DP
Annulus
176
278
Vc
265
314
Rig Hydraulics
Step 2 (continued)
Vc = 265 Ft/Min
Rig Hydraulics
Description
1. Surface Equipment
2. DP (Inside) 12,500
3. HW (Inside) 450
4. DC (Inside) 450
5. DC (Outside)
6. DP & HW (Outside)
7. Summary @ 10 ppg
8. Corrected for MW
9. Correction for PV
MW2
P2 P1
MW1
PV Corrections
Corrected Pressure Loss (psi)
PV
MW
0.14
34
DC
Annulus
Va
If:
Rig Hydraulics
Rig Hydraulics
Flow is
laminar.
Rig Hydraulics
Pressure Loss in System
@ Flow Rate (step one)
(Page 72)
(Page 75)
(Page 77)
(Page 77)
(Page 79)
(Page 81)
See formula,
page 27.
21
12.5 25 = 313
4.5 14 = 63
4.5 20 = 90
4.5 6 = 27
12.95 13 = 168
682
13.5/10 682 = 921
28
13.5
0.14
921
1020
Rig Hydraulics
Step 1: Q
340 gpm
Step 2: Vc
265 Ft/Min
Va
176 Ft/Min
1,020 psi
Step 3: Psys
Rig Hydraulics
Pbit
D
ROP
Q
or Pbit
Where:
=
=
=
=
Rig Hydraulics
1346 D 2
Q
Rig Hydraulics
Step 1:
Step 2:
Q
Vc
Va
Psys
Pbit
ROP
1 3 4 6 8 .5 2
340
Step 3:
Step 4:
15
=
=
=
=
=
340 gpm
265 Ft/Min
176 Ft/Min
1,020 psi
1,108 psi
Rig Hydraulics
Rig Hydraulics
35
Step 1:
340 gpm
Step 2:
Vc
265 Ft/Min
Va
176 Ft/Min
Step 3:
Psys =
1,020 psi
Step 4:
Pbit =
1,108 psi
Step 5:
Pt
2,128 psi
Rig Hydraulics
PBit 100
PSurf
Formulas
(30-50 gpm/in)
Check 1: Q =
Step 3:
Q
Vc
Va
Psys
Step 4:
Step 5:
Step 6:
1108 100
= 52%
2128
(48-65%)
(2.5-5.0) HH/in2
Check 3: HH/in2 =
340 1108
= 3.87
1346 8.52
(2.5-5.0) HH/in2
= 265 Ft/Min
= 176 Ft/Min
= 1,020 psi
QOPT Q NOW
PSystem Desired
PSystem Now
Rig Hydraulics
Q OPT 340
Rig Hydraulics
Rig Hydraulics
Q OPT Q NOW
(30-50 gpm/in)
Check 2: % PBit =
= 340 gpm
340
= 40 gpm/in
8.5
Desired Ranges
(48-65%)
Rig Hydraulics
Step 1:
Step 2:
Desired Ranges
Q
Bit OD
Rig Hydraulics
PSystem Desired
10 ppg
P
Bit Actual MW (ppg)
PSystem Now
950
1020
Q OPT 328
36
Rig Hydraulics
3 nozzle
2 nozzles.
3. Choose 3 nozzles with corrected flow rate based on bit
pressure (corrected for 10 ppg - hydraulic handbook).
12
12
Rig Hydraulics
13
Rig Hydraulics
3
340 510 gpm/821 psi 15
2
15
Rig Hydraulics
Choice 2.
Rig Hydraulics
Q
No.of
Jets
MW
P
bit
Choice 2.
* Any number of Jets 3.535
Q
No.of
Jets
MW
P
bit
13.5
1108
37
12 - 12 - 13
or 12 - 12 - 12
Rig Hydraulics
Rig Hydraulics
J12 J 22 J 32
3
J2
J12 J 22
2
Where:
Rig Hydraulics
Step 1:
Step 2:
Q = 340 gpm
Vc= 265 Ft/Min
Va= 176 Ft/Min
Step 3:
Step 4:
Step 5:
Step 6:
Step 7:
J3
MW
Jet Size 2.501 Q
PBit
Rig Hydraulics
PBit actual =
156.482 gpm 2 MW
(J12 +J 22 +J 32 ) 2
Rig Hydraulics
Step 1:
Step 2:
PBit actual =
PBit actual =
156.482 gpm 2 MW
2
1
2
2
2 2
3
(J +J +J )
= 1,309 psi
38
Rig Hydraulics
Step 3:
Step 4:
Step 5:
Q = 340 gpm
Vc= 265 Ft/Min
Va= 176 Ft/Min
Psys= 1,020 psi
Pbit = 1,108 psi
Pt = 2,128 psi
Step 6:
Step 7:
Step 8:
Optimization okay
Jets = 12 12 12
PBit actual = 1,309 psi
Rig Hydraulics
GPM
Pbit actual
Where :
Pbit actual
MW
10863.1 A 2
in
Pbit Q
(2.5-5 HH/in2 okay)
1346 (bit OD)2
Jet Velocity
418.3 Flow Rate
Vj
Check 4:
(ft/sec)
J12 J22 J32
Check 3: HH/in2
GPM
MW
A 2
in
Rig Hydraulics
Rig Hydraulics
Rig Hydraulics
Check 3.
Check 3.
Q
bit OD
340
40 gpm / in
8.5
%Pbit
Pbit 100
Psurf
%Pbit
1309 100
56%
2329
Rig Hydraulics
(48-65% okay)
Rig Hydraulics
Check 3.
Pbit Q
HSI
1346 (bit OD) 2
HSI
1309 340
4.6 HSI
1346 (8.5) 2
VJ
418.3 340
329 ft / sec
122 122 122
39
Rig Hydraulics
Step 1:
Step 2:
Q = 340 gpm
Vc= 265 ft/min
Va= 176 ft/min
Psys= 1,020 psi
Pbit = 1,108 psi
Pt = 2,128 psi
Optimization okay
Jets = 12 12 12
Pbit actual = 1,309 psi
HH/in2 = 4.6, VJ = 329 ft/sec
Step 3:
Step 4:
Step 5:
Step 6:
Step 7:
Step 8:
Step 9:
=
=
=
=
=
=
=
=
=
0.75
2.5
408
329
ROP2 15
17.19 ft/hr
340
329
17.19-15 14.6%
% Increase =
15
See Drilling Manual, Optimization, pages 32-33.
Case 2
Jet Velocity (JV1) is increased by 20% from 329 to 395
(JV2). Flow Rate (Q1) is held constant at 340 gpm. What is
the change in ROP?
0.75
Case 1
Flow Rate (Q1) is increased by 20% from 340 gpm to 408
gpm (Q2). Jet Velocity (JV1) is held constant @ 329. What
is the change in ROP?
JV
8.5inches
ROP2 ROP1 2 or
340 gpm
JV1
408 gpm (New)
0.75
2.5
329 ft/sec
Q2
JV2
ROP2 ROP1
Rig Hydraulics
2.5
340
395
ROP2 15
23.69 ft/hr
340
329
23.69-15 57.9%
% Increase =
15
Note: Jet Velocity will make you more money than Flow Rate!
40
Rig Hydraulics
Well Data:
1496
727
800
12
704
1164
152
5055
Rig Hydraulics
Rig Hydraulics
Rig Hydraulics
Rig Hydraulics
Rig Hydraulics
41
PBit =
156.482 Q 2 MW
(J12 + J 2 2 + J 32 ) 2
PBit
PBit =
156.482 Q 2 MW
(J12 + J 2 2 + J 32 ) 2
PBit =
156.482 Q 2 MW
(J12 + J 2 2 + J 32 ) 2
PBit
PBit
Step 4.
42
Step 6.
Determine
optimum flow
rate (Q).
Q
JN
MW
PBit
J Avg 3.536
325 13.5
11.1
3 1636
Questions to ask:
1. Was there a change in pressure on both the DP
Pressure Gauge and the Casing Pressure Gauge?
Yes. The problem is with the choke.
If the pressure is decreasing, there is a choke
washout. Close in the well by closing the valve
in front of the remote choke and turn off pump.
Realign the choke manifold to remote choke #2.
Bring the pump back up to SCR holding casing
pressure constant and continue killing the well.
Questions to ask:
1. Was there a change in pressure on both the DP
Pressure Gauge and the Casing Pressure Gauge?
Yes. The problem is with the choke.
If the pressure is increasing, there is a plugged
choke. Turn the pump off. Realign the choke
manifold to remote choke #2. Bring the pump
back up to SCR holding casing pressure constant
and continue killing the well.
43
Questions to ask:
2. Was there a change only on the DP Pressure Gauge?
3. Was there a total pump failure?
Close in the well and realign the standpipe
manifold to pump #2. Bring the pump up holding
casing pressure constant and continue killing the
well.
Questions to ask:
3. Was there a total pump failure?
No. There is a problem in the drill string. It is
probably a washed out or plugged nozzle.
4. Did the pressure increase?
It is probably a plugged nozzle. Determine how
much increase in pressure has occurred. If FCP
has been reached, continue with the new slow
circulating rate.
Questions to ask:
4. Did the pressure increase?
If FCP has not been reached, calculate the new
slow circulating pressure. Revise the pumpdown plan. Bring the pump back up to slow
circulating rate holding casing pressure constant
and continue killing the well.
Questions to ask:
5. Did the pressure decrease?
There is a probably a washed-out nozzle.
Determine how much the pressure has dropped.
If FCP has been reached, the new pressure is
your new FCP. Continue circulating with the
new FCP.
Questions to ask:
5. Did the pressure decrease?
There is a probably a washed-out nozzle.
Determine how much the pressure has dropped.
If FCP has not been reached, calculate the new
slow rate pressure. Calculate the revised FCP.
Revise the pump-down plan.
Bring the pump back up holding casing pressure
constant and follow the revised pump-down plan.
44
2500
0
177
353
530
706
883
1059
1236
1412
1589
1765
Action List
The calculated ICP was 2,500 psi. However, the actual
ICP is 2,200 psi due to washed-out nozzle, the plan must
be revised. Revised SRP = (2,200 1,500) = 700 psi.
1. Revised FCP = (12.2/9.6) 700 = 890 psi.
2500
2377
2254
2131
2008
1885
1763
1640
1517
1394
1271
2200
2069
1938
1807
1676
1545
1414
1283
1152
1021
890
2000
1500
1000
500
45
500
1000
1500
2000
Day Four
Review homework
Mud Solids
Lost Circulation Top Hole Causes &
Preventions, Shallow kicks
Deviation and Stuck Pipe
Simulator Exercises
Solids
Stuck Pipe
Lost Circulation Top Hole
Kill Sheet for Simulator
Problem #5
Mud Solids
Mud Solids
Mud Solids
Shaker System
Distribution paths
Solids
Shaker System
Shaker Screens
Desander
Desilter
Centrifuge
Flocculation
Screen Size
40
80
100
150
200
325
Shaker System
Micron Size
381
234
178
105
74
44
50-60
20-30
5-15
<1-5
Shaker Capacity
Shaker Screens
10
500
30
200
60
25
Shaker System
Shaker System
Shaker Screens
Shaker System
Shaker Screens
Sand Trap
Hydrocyclones
Cone Diameter
Cut Point
Desander
5 12
30-60
Desilter
3 4
12-20
Hydrocyclones
Mud Cleaners
Mud Cleaner
A mud cleaner is a
combination shale shaker
and desilter used to desilt
weighted mud.
Mud Cleaners
Centrifuges
Mud Cleaner
Centrifuges
Centrifuges
Hutchison-Hayes 5500
Good centrifuges:
Have a cut point of
from 3-5 microns.
Recover about 90% of
the barite and discard
the colloidal drilled
solids.
Standard Centrifuge
(16 55 bowl size)
Variable speed drives,
1600 rpm up to 3700 rpm
Max G-Force In excess of 3100 Gs
The conveyor torque is the weak link and with more
barite (high MW), it must be run slower.
See Drilling Manual, Top Hole Chapter, page 26.
Centrifuges
Centrifuges
GPM
250
205
40
Feed
Feed tube
Inlet distributor
Gearbox
Screw conveyor
Liquid
Discharge port
Solids
Conical End
Centrifuges
Centrifuges:
Flowline (out)
0730 9.4
42 150 10
73
0745 9.4
42 150 10
73
0830 9.6
44 125 10
86
2. Desander
3. Desilter
(Fixed
amount of
Equip.)
Solids
separated &
diluted
60
Solids #/bbl
60 1. Shaker
39 100 10
FV
39 100 10
0615 9.2
MW
Solids
Control
Equipment
Solids #/bbl
Water gpm
ROP ft/hr
0600 9.2
0630
Maintaining Correct MW
With Two Variables
FV sec/qt
MW ppg
Time
Centrifuges
9.0 38
47
13
9.0 38
47
13
9.2 40
60
13
9.2 40
60
13
9.4 42
73
13
Maintaining Correct MW
With Two Variables
Total Solids
In
Suction Tank
TS Flowline
Water Added
Variable ROP
Variable
Minus Solids
Separated
Dilution of Solids
Dilution of Solids
24
50
24
50
24
9.5
1662 Bbls
7.6
1330 Bbls
5.7
992 Bbls
.
.
.
.
Dilution of Solids
Case 1
Equipment removing 70% of solids being drilled (30% solids
being retained to dilute).
Rate of Penetration (ROP) = 50 ft/hr or 50
F R A Den DS MWH
808.5 MWH MWW
Where:
F
= Fraction (%) of drill solids retained
ROP = Rate of Penetration (or feet per day) (feet/hour
hr/day)
A
= Area of hole
DenDS = Density of Drill Solids (2.6 8.33)
MWH = Mud Weight in Hole (ppg)
MWW = Mud Weight of water (ppg)
Dilution of Solids
24 = 1,200 ft/day.
24
Dilution of Solids
VH2O
F R A Den DS MWH
808.5 MWH MWW
VH2O
VH2O / VolDS
VH2O / VolDS
VolH2O
ROP 24(day)
DH
1029.4
992
5.7 bbl
12.252
50 24
1029.4
Dilution of Solids
Solids Workshop
Unweighted Example 1
Mud Weight
MBT
Chlorides
TS
Bentonite(B)
Drill Solids(DS)
DS/B Ratio
9.5
20
0
79
20
59 (79-20)
59/20 = 3:1
Solids Workshop
Unweighted Example 2
Unweighted Example 3
Mud Weight
9.5
MBT
20
Chlorides
40,000
Oil
10%
69
TS
20
Bentonite(B)
Drill Solids(DS) 49 (69-20)
49/20 = 2.5:1
DS/B Ratio
Mud Weight
9.5
MBT
20
Chlorides
40,000
TS
57
Bentonite(B)
20
Drill Solids(DS) 37 (57-20)
DS/B Ratio
37/20 = 1.85:1
Solids Workshop
Unweighted Example 4
Mud Weight
Retort Data
Chloride
MBT
Solids Workshop
Solids Workshop
Unweighted Example 4
Mud Weight
Retort Data
Chloride
MBT
[d] 5.2
24. The corrected solids_______%
(on slide rule)
[a] 48 ppb (on slide rule)
25. The solids content_____
Solids Workshop
Unweighted Example 5
Mud Weight
Retort Data
Chloride
MBT
Formation MBT
Unweighted Example 5
Mud Weight
MBT
Formation MBT
29.
30.
Solids Workshop
Solids Workshop
Unweighted Example 5
Solids Workshop
Mud Weight
Retort Data
Chloride
MBT
Formation MBT
12 33
100
12
1
100
8.8 ppg
no oil
100 mg/l
9.0 ppb
12.0 ppb
[d] 27 ppb
32. Actual drill solids______
[b] low
34. The viscosity would probably be ________.
[a] high
35. The water loss would probably be ________.
Solids Workshop
Weighted Example 1
Mud Weight
Retort Data
Chloride
Solids Workshop
15 ppg (weighted)
Oil - 5%, solids - 25%, water - 70%
100,000 Mg/L
Solids Workshop
Solids Workshop
For example,
.
.
ROPM2 = ROPM1
Solids Workshop
.
.
Solids Workshop
F1 = 12 ppb
C1 = 67 lb/bbl
Gel Only
Gel + Polymer
Dispersed Mud
F= MBT
F= MBT
F= MBT
0.13
0.06
0.80
Solids Workshop
Solids Workshop
ROPM2 = 20
.
.
.
.
ROPM2 = 24.6
% increase = 23%
10
Solids Workshop
MW
% ROP INCREASE
ROP FT/HR
11.0
1040
10
10.5
780
14%
11.4
10.0
520
20%
13.7
9.5
260
28%
17.5
9.0
30%
22.8
Depth (ft) 10,000 normal pressure (0.465). Field data (above) indicates a
128% increase ROP by reducing overbalance (lowering MW).
% inc =
Solids Workshop
9.0
6
3
12
22 ppb LSND mud (poly)
solids content 5.0%, 46 lbs/bbl,
low density solids
Solids Workshop
0.8
0.13
0.06
Introduction To
Lost Circulation
Drilling Problems Around The World
Lost Circulation
Stuck Pipe
Well Control
Hole Cleaning & Stability
13.5 ppg
27%
57
6
3.6
12.5 ppb
0
slide rule: 166 lbs/bbl barite,
145 lbs/bbl low density solids
See Workbook, Homework, page 130.
Solids Workshop
Solids Workshop
47.6
11
Introduction To
Lost Circulation
Natural fractures
Already exist in the formation.
Not caused by drilling
operations.
Induced fractures
Caused by drilling operating
practices.
Introduction To
Lost Circulation
Lost Circulation
In Top Hole
Important Considerations:
Area knowledge should take priority.
Analyze, diagnose and focus the cure
on the root cause.
Topics Covered
I. Lost Circulation in Top Hole
II. Lost Circulation in Abnormal
Pressure
III. Lost Circulation in Gas Cap
IV. ECD Drilling
Introduction To
Lost Circulation
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
12
Lost Circulation
In Top Hole
Causes of lost circulation in top hole:
Natural fractures.
Sub-normal formation pressure
gradient.
Mud weight increases caused by
high solids or cuttings accumulation
in the annulus.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
I.
II.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Priority List
Area knowledge should
always take priority.
Use methods that have
proven effective in the
area being drilled.
13
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Priority List
A. Blind Drilling
Fluid is not put in annulus.
Drilling is done with water.
Hole is kept clean with hole
sweeps using viscous mud
based on the drillers trends.
Priority List
A. Blind Drilling
Drilling is done with
minimum hydraulics.
Use 30 gpm per inch
(525 gpm in a 17
hole).
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Priority List
A. Blind Drilling
Circulate hole sweeps when hole conditions
indicate to unload hole (cuttings are swept into
fracture).
This will minimize the associated problem of
stuck pipe.
Priority List
A. Blind Drilling
It can be done
with a limited
water supply by
hauling it in.
It is done safely and successfully all over the
world.
80
D.O.I.
W
DPAW 1 BF
70
70
20
20
40
40
50
50
60
60
70
80
70
80
ASIA
10
10
20
30
30
60
PE
50
40
PACIFIC
OCEAN
30
30
30
40
40
50
50
60
60
70
70
80
10
INDIAN
OCEAN
EQUATOR
10
20
20
80
20
AFRICA
TROPIC OF CAPRICORN
RO
20
IC
SOUTH
AMERICA
10
70
EU
30
EQUATOR
OCEAN
10
80
TROPIC OF CANCER
PACIFIC
10
50
40
30
AN
NL
EE
60
60
40
GR
50
TROPIC OF CANCER
30
30
40
TROP OF CAPRICORN
40
50
50
60
60
70
80
ANTARCTICA80
10
20
AUSTRALIA
30
70
30
40
40
50
50
60
60
70
80
70
80
Lost Circulation
In Top Hole
80
80
EE
NL
AN
NORTH
AMERICA
30
Lost Circulation
In Top Hole
Use buoyancy to
calculate the depth of
interest (D.O.I.).
GR
70
60
50
40
5000
22.12 1 0.862
FG (psi/ft)
D.O.I. = 1,638 ft
D - D.O.I. GM
FG (psi/ft)
14
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Priority List
A. Blind Drilling
B. Mud Cap Drilling
C. LCM Pills
Lost Circulation
In Top Hole
It is important to keep
putting mud in the annulus
while tripping out or in and
while running casing.
Generally, a casing DV
packer is placed just above
the loss zone.
Lost Circulation
In Top Hole
Instead of loading up
the system with LCM,
use a LCM pill.
15
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
16
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Priority List
A. Blind Drilling
B. Mud Cap Drilling
C. LCM Pills
D. Cement Plugs
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Priority List
A. Blind Drilling
B. Mud Cap Drilling
C. LCM Pills
D. Cement Plugs
17
Lost Circulation
In Top Hole
When setting balance
plugs, the cement is
allowed to U-tube
around the drill string.
When setting lost
circulation cement
plugs, the cement is
NOT allowed to U-tube
around the drill string.
Lost Circulation
In Top Hole
E. Gunk Plugs
Must have partial returns at the surface for gunk
to work (fluid level to the surface).
Gunk originally 300 lb gel, and 1 barrel diesel oil.
It has been modified, using combinations of Gel
and cement in diesel oil.
Must be able to squeeze it.
Lost Circulation
In Top Hole
E. Gunk Plugs
Use oil spacers
ahead and behind.
You cannot have any
water come in touch
with this mixture,
because it will set
up.
Lost Circulation
In Top Hole
E. Gunk Plugs
Pump out of
diverting sub at 2
parts of Gunk and
pump underneath
BOP at 1 part of
mud. H20 in mud
makes Gunk thicken.
Lost Circulation
In Top Hole
E. Gunk Plugs
Operators cannot make contractors or service
companies do things that violate their policies or
safety regulations.
Always operate within the contractors or service
companys safety regulations.
Lost Circulation
In Top Hole
Priority List
A. Blind Drilling
B. Mud Cap Drilling
C. LCM Pills
D. Cement Plugs
E. Gunk Plugs
F. Combinations
Lost Circulation
In Top Hole
F. Combinations
Sometimes a loss zone
must be cured before
drilling ahead.
A combination of
techniques may be
required.
Use DP and diverter sub.
18
Lost Circulation
In Top Hole
Priority List
A. Blind Drilling
B. Mud Cap Drilling
C. LCM Pills
D. Cement Plugs
E. Gunk Plugs
F. Combinations
G. Gravel
F. Combinations
Use LCM pill first and
follow it with an oil spacer.
Follow with gunk and
another oil spacer.
Follow with cement.
The LCM and gunk give
resistance so that the
cement plug will have
enough time to thicken.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
I.
G. Gravel
It can be all sizes. Gravel will help plug vugular
limestone.
1. Pull your drill string out.
2. Rig up a conveyor belt up to rig floor.
3. Dump gravel down the hole.
4. Go in the hole very carefully.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Present Situation:
MW is 9.8 ppg
20 BPH losses are
occurring.
19
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
F.L.
2 Variables
Solids Fixed
Suction Tank
MW
MW
R.O.P.
H2O
#/bbl
9.2
100
10.0
Solids
Control
Equip.
#/bbl
Lost Circulation
In Top Hole
F.L.
2 Variables
Solids Fixed
Suction Tank
MW
#/bbl
9.0
46.0
9.2
60.0
MW
R.O.P.
H2O
#/bbl
9.2
100
10.0
60.0
9.4
200
10.0
73.0
Solids
Control
Equip.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
20
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Cas ID
DP OD 2
1029.4
2
L H 2O ft
Lost Circulation
In Top Hole
(bbl)
(bbl/ft)
Lost Circulation
In Top Hole
L Mud
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
D.O.I.-L
H 2O
MWE
21
H2 0
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Example:
Casing annular volume is
0.0489 barrels/foot.
48.9 barrels were added.
Example:
Casing annular volume is
0.0489 barrels/foot.
48.9 barrels were added.
L H 2O ft
MWe
MWe
H2 0
48.9
1,000
0.0489
Lost Circulation
In Top Hole
0.433 Lmud MW 0.052
Lost Circulation
In Top Hole
D.O.I. 0.052
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
(9.8 - 9.0)
Vd 2,000
(9.8 - 8.33)
MWN - MWd
Vd Vf
MWN - MWdF
Vd = 1,088 bbls
1,088 barrels of mud must
be dumped.
1,088 barrels of water must
be added to reduce the MW
to 9.0 ppg.
Where:
Vd
= Volume of mud to dump and volume of dilution
fluid to add, bbl.
Vf
= Final vol. mud, surface pits & hole, bbl (2000)
MWn = MW now in system, ppg (9.8)
MWd = MW desired, ppg. (9.0)
MWdf = MW of dilution fluid, ppg (water 8.33)
22
Lost Circulation
In Top Hole
M Wd
MW
Lost Circulation
In Top Hole
Given:
Vm
MWn
MWd
MWdf
Vdf
=
=
=
=
=
V m ud M W df Vdf
V m ud Vdf
ppg
Lost Circulation
In Top Hole
Vdf
Vm M W n M W d
M W d M W df
Vdf
Vm M W n M W d
M W d M W df
1000 9.8 - 9.0
9.0 8.33
Lost Circulation
In Top Hole
M W
Example 2
The surface tanks have been cleaned and 300 bbls of new
9.0 ppg mud built. How much H20 will be required to
reduce the mud in the hole to 9.0 ppg while circulating?
Vdf
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
V t V m V df
M Wd
M W N xVM M W df xVdf
Vm Vdf
MWd
9.8x1000 8.33x1194
1000 1194
V t = 1000+1194
23
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
I.
II.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Air/Gas Drilling
Foam Drilling
Blind Drilling
24
Lost Circulation
In Top Hole
Prevention
1. Mitigate problem by using alternates such as:
a. Natural gas or
b. Nitrogen
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
B. Artesian Flows
Good area
knowledge.
Good driller.
Heavier mud can be
spotted to balance
the pressure and to
prevent flow on
trips.
In SS operations, lost
circulation could be a
problem below shallow
casing because of low frac
gradients. Therefore, if mud
returns are required through
riser to surface, an analysis
should be done.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Formula:
Category 1:
Category 2:
MWE
25
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lr:
Length of riser (WD + S1 = Riser MD or Lr), ft
Pmh: Hydrostatic pressure, psi
Lsw: Length of seawater, ft
DOI: Depth of interest, ft
MWh: Mud wt. In hole, ppg
MWk: Kill mud wt., ppg
TVDa: True Vertical depth, ft
Lost Circulation
In Top Hole
Example:
Category 1: (Maximum MW with riser in place)
(MWls Lc 0.052 WD 0.445)
MWE
(WD Sl Lc) 0.052
MWE
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Category 2:
MWE
MWE
26
Lost Circulation
In Top Hole
I.
II.
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
27
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
MAASP = 91 psi
MAASP MWF - MWH ) 0.052 TVDS
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
91
28
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
91
312
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Case #3
MW is 12.0 ppg
MWF is 14.5 ppg
TVD is 2,500 feet
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
312
325
29
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
91
312
325
1170
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
Case #5
MW is 17.0 ppg
MWF is 18.8 ppg
TVD is 12,000 feet
Lost Circulation
In Top Hole
Lost Circulation
In Top Hole
312
325
1170
1123
It is important to communicate
what you expect the driller to
do.
He needs to know exactly what
to do and how to carry out those
procedures.
30
1. Contracts
Footage wells need good supervision
We will interface with you and decide
what to do if you deviate more than 5
degrees.
We require a packed-hole assembly.
2. Geology-need good co-operation
from geologists
In a straight hole drilling contract, many of the possible troubles can be
prevented by obtaining satisfactory contract terms on deviation and dog-legs.
7. Equipment malfunctions
downhole
8. Tripping practice (with
low overbalance)
9. Handling bridges in hole
Example:
Cause of Bridge is poor tripping
practices with low overbalance
in normal pressure drilling.
To Analyze:
Step 1: Calculate overbalance
@ top of bridge
P = (GM - GF) Bd
P = (0.468-0.465) 2,000
P = 6 psi
31
Step 3
Since only one stand can be P.O.H. before going
under balance, the pipe would have to be P.O.H.
while circulating the well head through a trip tank.
Step 2
Calculate feet of 5, 19.5, E, XH
that can be P.O.H. when the Pob = 6.0 psi
Len (ft.)
Len (ft.)
POB
G M met. disp
(cas. vol - met. disp)
6 psi
22.12
bbl/ft
0.468 psi/ft
2748
3. Keep weight on
bit (WOB) below
the WOB used to
drill original hole.
2. De-cake bridge
(Mash-Rock
Technique is
good)
32
Requirements for
Differentially Stuck Pipe
1. Permeable Formation
2. Differential Pressure
3. Wall Contact
4. Lack of Pipe Movement
5. Mud Cake
Differentially
Stuck Pipe Causes
Differentially
Stuck Pipe Causes
4. Permeability and
length of zone open
5. Drill string design
(clearance, etc.)
3. Bentonitic Shale
33
4. Mobile Formations
a. Salt
b. Squeezing marls
Mechanically Related
Stuck Pipe
Mechanically Related
Stuck Pipe
Mechanically Related
Stuck Pipe
3. Hole cleaning
Tuckers Wrench
Tuckers Wrench
34
Tuckers Wrench
Mud:
MW = 14 ppg.
BF = 0.786
65.44 14
BF
0.786
65.44
For Buoyancy Factors, see Drilling Manual, DS Design, page 5.
WTAIR = ((7,000
WTAIR = ((L1
W1) + (L2
W2) + (L3
23.89) + (5000
W3))
22.12) + (720
91))
SUMMARY
1. WTAIR = 343,350 lbs
35
SUMMARY
1. WTAIR = 343,350 lbs
BF + HL)
0.786 + 100,000)
WTWI = 369,895 lb
WTAir (lb)
2748 (lb/bbl)
VolTRIP (bbl) =
343,350 (lb)
2748 (lb/bbl)
SUMMARY
1. WTAIR = 343,350 lbs
36
W1
Where :
W1 Top (larger) dp, plain end wt, lb/ft.
W2 Lower (smaller) dp, plain end wt, lb/ft
L1 Length of top dp, ft.
e Stretch, in
P Differential pull, lb.
W1 = 5, 19.5, S, XH,
(22.6/17.93)
735,294 e W2
W
L
L 1 1 - 2
P
W1
W2 = 3, 13.3, S, EU,
(14.69/12.31)
735,294 35 12.31
12.31
L
9,000 1
30,000
17.93
Interpretation:
L = 13,381 Ft
37
SUMMARY
1. WTAIR = 343,350 lbs
= 12,360 Ft
BOWmech = DOI
DPadj wt
BOWmech = 3000
21.29
BF + Block Weight
0.76 + 100,000
BOWmech = 156,337 lb
4. ESP
= 12,360 Ft
5. B.O.W.Mech = 156,337 lb
=
=
=
=
=
WDC
BOW = (Weight
Indicator weight Fish to be left in hole)
BF ]
38
BOWString shot
WTWI L DC WDC L DP WDP BF
B.O.W.StringShot = 344,146 lb
NOTE: This is an approximate
number. The back-off specialist
will finalize B.O. weights where
the best torque and stretch
readings are measured using his
instrumentation.
7. Back-off techniques:
(a) General, (b) Hard Rock, (c) Soft Rock
a. General
SUMMARY
= 12,360 Ft
5. B.O.W.Mech = 156,337 lb
6. B.O.W.String Shot
= 317,297 lb
7. Back-off techniques:
(a) General, (b) Hard Rock, (c) Soft Rock
7. Back-off techniques:
(a) General, (b) Hard Rock, (c) Soft Rock
One wire line run is made with Free point and String
Shot tools in tandem.
39
8. String shot
prima cord
requirements.
A driller working in
West Texas in 1956.
It is a classic
communication and
leaves no doubt that
they had better follow
his instructions.
World Oil, March
1999
40
V C
RD
ND F
Cd
B. Diagram the
problem.
Where :
Nd Maximum number of fishing days
VF Total replacement value of fish in hole $
Hole size:
12
XO SUB 4 IF
Box 6 Reg.
Pin 5.48
Top of Fish:
8, 096
Cmt plug
5x8 Steel DC
6 Reg. BxP
Bottom of Fish
8,364 Ft
Mud
MW (Balanced all around)
Viscosity (FV)(YP)(Gels)
41
Day Five
Tripping
H2S
Kill Sheet for Simulator
Problem #6
Review Homework
Difficult Well Control
Situations (Lubrication,
Stripping, Snubbing)
Video Well Under Control
Tripping Practices and
Considerations
H 2S
Simulator Testing
Lubrication Technique
Lubrication Technique
Step 1.
F 90 91 8190 lbs
Lubrication Technique
Step 2.
Lubrication Technique
Step 3.
Calculate the Pressure (P).
F
P
A
8190 lb
P
33.18 sq inches
A (6.52 )0.7854
A 33.18 sq inches
247
Lubrication Technique
Lubrication Technique
This is a stand-off.
A safety factor (SF)
is needed.
Lubrication Technique
Step 4.
Step 5.
Determine the pressure increment that can be safely
used that will not break down the shoe.
In this example, we will use a 200-psi increment.
Lubrication Technique
15 0.052 psi/ft
0.0744 bbl/ft
Lubrication Technique
Step 6.
Pump lubrication fluid into
well through choke line until
casing pressure increases
by 200 psi.
Lubrication Technique
Step 8.
Calculate the amount of
pressure that can be bled
down.
(6.0 bbl 10.48 psi/bbl = 63 psi)
Step 9.
Wait for the gas to percolate through the
lube fluid, and then bleed down the
pressure.
(700 263 = 437 psi)
Step 7.
Calculate the amount of fluid
pumped into the well.
(60 strokes 0.09967 bbl/stk = 6.0 bbl)
Lubrication Technique
Step 10.
Repeat steps 6-9 until
casing pressure has been
reduced to desired
pressure (147 psi).
Best Fluids
1. Salt H2O
2. Salt Mud
3. FW Mud
Never use Oil Mud!
Lubrication Technique
Mixing Method For Salt Mud
1. Start with fresh H2O.
2. Add starch (gel) and
prehydrate.
3. Add salt (salt bbl).
4. Add barite
Rig #47
VR Plug Blowout
Iran
Rig #47
Drilling and Well
Control Training
Rig #47
Drilling and Well
Control Training
Iran
Iran
Stripping
1. People
Experience
Good
communicator
Organized
Calm
Honest
Stripping Considerations
1. People
2. BOPE
3. Stripping Schedule
No false pride
Safety minded
Energetic
Good delegator
Stripping
Stripping
2. BOPE
Accumulators
Make sure every bottle is Nitrogen pre-charged (key to
volume).
Each bottle needs to have a 1000 lb. Nitrogen precharge.
Keep accumulators on or off, but not in neutral. If it
leaks, fix the leak.
Combination of RAM and Annular
Equalize from an outside source
Refer to Workbook, BOPE, page 14.
Accumulators
Stripping
Stripping
Emergency BOP to
do repair work on
upper BOP.
Stripping
Stripping
Stripping
Pump to equalize
the pressure
1. People
2. BOPE
3. Stripping
Schedule (Bv)
Stripping
3. Stripping Schedule
Stands Bv Pcsg
Comments
Bv
Volumetric
Schedule
Capacity
Stripping
Metal Disp. Len std.
22.6
Bv 0.017
94 ft.
2748
BV = 2.37 bbls
3. Stripping Schedule
Stands Bv Pcsg
150
Comments
Volumetric
Schedule
2.37 150
BV = Cap + Met/Std
2.37 150
100
Started @ 0130
100
2.37 150
101
2.37 150
Snubbing
Snubbing
Snubbing is jacking
the pipe in the hole.
There is more force up
than force down.
Therefore, the pipe
must be jacked into the
hole.
Stripping
Snubbing
Snubbing
Shell
Well Under Control
Tripping Practices
To allow a
KICK
Caused by surge
by not following
a proper fill up
procedure can only
be classified as
NEGLECT!
3. Stuck Pipe
- Key seats
- Cuttings beds
- Differential sticking
- Mechanical
- Well control
1.
2.
3.
4.
While Tripping:
1. Hole not taking the right
amount of fluid.
Compare the actual
amount of fluid in the
Trip Tank with the Trip
Schedule.
4. Shale Stability
Surge or swabbing upsets shale stability.
Shales balloon very easily.
Shales cause hole instability
Shales do not respond well to tripping.
When trips are required through shales, close
supervision is required to prevent surge and
swabbing.
1.
2.
3.
4.
Complacency and
lack of supervision
while tripping are
two reasons why
65%-85% of all
blowouts are trip
related!
I.
II.
III.
IV.
V.
10
Tripping Considerations
Mechanical Considerations
Hole Considerations
Mud Considerations
Slugging Considerations
Trip Schedule and Monitoring
Considerations
Tripping Considerations
I. Mechanical Considerations
1. Bit Condition
A bit is a machine tool.
If it fails, it must be pulled out of the
hole.
Tripping out of the hole requires
preparation.
Tripping Considerations
I. Mechanical Considerations
1. Bit Condition
2. Bottom Hole Assembly (BHA)
Allocate adequate amount of time to
give proper care to the BHA.
Tripping Considerations
Tripping Considerations
I. Mechanical Considerations
1. Bit Condition
2. Bottom Hole Assembly (BHA)
Tripping Considerations
Tripping Considerations
WARNING!
11
Tripping Considerations
I. Mechanical Considerations
1. Bit Condition
2. Bottom Hole Assembly
3. Drill String Washout
4. Rig Mechanical Problems
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
I. Mechanical Considerations
II. Hole Considerations
III.
IV.
V.
12
Pressure Stroke
Relationship
Drag
Torque
Rate of Penetration
Mud
Trip
Well Control
Lost Circulation
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
Foremen are
appraised by %
time on bottom!
Tripping Considerations
Tripping Considerations
13
Sedco 135
Tripping Considerations
Tripping Considerations
I. Mechanical Considerations
II. Hole Considerations
III. Mud Considerations
IV.
V.
Tripping Considerations
3.
4.
Tripping Considerations
Tripping Considerations
Tripping Considerations
MWtrip MWbal
14
yield point
11.7(D h - D DP )
Tripping Considerations
Example 1.
YP = 15; MWbal = 14.6
MWtrip MWbal
Tripping Considerations
Example 2.
YP = 25; MWBal = 14.6
yield point
11.7(D h - D DP )
Yield Point
11.7(D H -D DP )
25
14.6
11.7(8.5-5)
MWTrip MWBal
15
MWtrip 14.6
11.7(8.5
5)
MWTrip
MWtrip 15 ppg
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
15
Tripping Considerations
I.
II.
III.
IV.
V.
Tripping Considerations
Tripping Considerations
Mechanical Considerations
Hole Considerations
Mud Considerations
Slugging Considerations
1. Well Control
4. Cost of Mud
2. Hole Stability
5. Environmental
Concerns
3. Safety
Tripping Considerations
Tripping Considerations
Tripping Considerations
16
Tripping Considerations
Prevention technology
can help drilling, service
rigs to minimize
environmental footprint
at the source.
(Drilling Contractor
November/December
2009)
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
17
Tripping Considerations
Dry Pipe :
Tripping Considerations
DPW
psi GM psi / ft MetalDisp 2748 bbl / ft
ft
(cas. vol. - Metal Disp.) bbl / ft
Tripping Considerations
Tripping Considerations
Tripping Considerations
23.89
bbl / ft
0.78
psi
2748
Tripping Considerations
psi
GM (Met Cap.)
23.89
(0.78 (
0.017))
psi
2748
Wet Pipe :
18
Tripping Considerations
There is 4 times
more pressure loss
pulling wet pipe
than dry pipe
before filling the
hole!
Tripping Considerations
P
(MWS - MWH )0.052
Len slug
Tripping Considerations
Tripping Considerations
P
(MWS - MWH )0.052
Len slug
147
(16 -15)0.052
Lenslug = 2,827 ft
Tripping Considerations
Tripping Considerations
Volslug = 48 bbl
Pump slug mud into the top of the
drill string. Do not pump slug mud
to the bottom of the pipe.
19
Tripping Considerations
Stk Slug
Tripping Considerations
VolSlug bbl
P.O. bbl/stk
P.O.
P.O.
25BBL
221STK
= 0.113 bbl/stk
Tripping Considerations
Stk ClearSlug
Tripping Considerations
VolSL
1029.4
1029.4
Tripping Considerations
2
ID of Line
4 2
VolPump S.L.
VolSL
Tripping Considerations
Stk ClearSlug
200
1.9 3.1
0.113
20
Tripping Considerations
Tripping Considerations
I.
II.
III.
IV.
V.
Tripping Considerations
Tripping Considerations
Mechanical Considerations
Hole Considerations
Mud Considerations
Slugging Considerations
Trip Schedule and Monitoring
Considerations
Tripping Considerations
Tripping Considerations
Definition Of A Trip
A trip starts when you start circulating
bottoms up before the trip. In includes the trip
out, all the things you do when you are out of
the hole. It includes the trip in with the pipe.
The trip ends when you get bottom circulated
up after the trip.
21
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
Swabbing is characterized:
On Trips: Hole must take
the right amount of mud
based on metal
displacement.
After Trips: Trip gas or
water or oil cut drilling
fluids or a combination.
22
Tripping Considerations
Overcoming Swabbing:
Swabbing can be overcome
by two or three ways:
Pull the pipe slower.
Lower the gel strength and
yield point.
As a last resort, raise the
mud weight a point or two.
Tripping Considerations
Tripping Considerations
Tripping Considerations
1. Drilling Mode:
Catch a 5 bbl kick
2. Tripping Mode:
Catch a 1 bbl trip trend
change
Tripping Considerations
Tripping Considerations
Fill Up Line:
Things To Consider In
Building A Trip Tank
Closed Loop:
Circulate across top of
well head.
Returns back into the trip
tank.
Centrifugal Pump:
Keeps hole filled at all times.
Flow Line:
Used at all times. It circulates mud from the hole.
Is part of the closed loop to get mud back into the trip
tank.
23
Tripping Considerations
Vol TT (bbl)
M et.D isp.(bbl)
M et.D isp .
5 9 4 2 3 .8 9
2748
Grade S, 5, XH Pipe
Tripping Considerations
Stands
D.P.
Incr.
Vol.
Acc.
Vol.
Trip
Tank
In
Actual
Incr.
Vol.
0-5
4.09
4.09
8.18
6.09
6.09
+2
4.09
8.18
16.36
6.09
12.18
+2
11-15
4.09
12.27
24.54
5.09
17.27
+1
16-20
4.09
16.36
32.72
4.09
21.36
21-25
4.09
20.45
40.90
3.09
24.45
-1
26-30
4.09
24.54
49.08
2.09
26.54
-2
31-35
4.09
28.63
57.26
2.09
28.63
-2
Stands
D.P.
Incr.
Vol.
Acc.
Vol.
4.09
0-5
4.09
6-10
4.09
11-15
4.09
16-20
4.09
21-25
4.09
26-30
4.09
31-35
4.09
Trip
Tank
In
Actual
Incr.
Vol.
Actual
Acc. Trends
Vol.
Tripping Considerations
Situation:
CM and TP decide to RIH after pulling 35 stands
because of 5-bbl negative trend.
After RIH and circulating, gas off bottom was more than
previous trips and gas was recovered 15 minutes ahead
of calculated lag time.
Decision was made to raise MW to 15.2 ppg (2 points).
The mud YP was adjusted to 18. A short trip was made to
check the trip margin. Well looked OK on short trip and
the trip out of the hole was OK.
Actual
Acc. Trends
Vol.
6-10
Tripping Considerations
0.5 bbl/inch
Tripping Considerations
Vol TT
48 bbls
Vol TT
Tripping Considerations
24
Tripping Considerations
G M 1029.4
DH 2
psi / bblOH =
0.781029.4
8.52
(Openhole)
2. psi/bbl =
0.781029.4
(8.6812 -52 )
Tripping Considerations
Tripping Considerations
3. P(psi)=Vol NT psi/bbl
P(psi) 5 bbl 11.1 psi / bbl
P(psi)= 55.5
G M 1029.4
(DP Csg AV)
(CID2 -POD2 )
psi/bblDP/CSG =
Tripping Considerations
Tripping Considerations
Tripping Considerations
25
POB (psi)
psi / bbl
Tripping Considerations
G M 1029.4
(Openhole)
DH 2
0.676 1029.4
psi / bbl
23.3
5.47 2
psi / bbl
Vol.(bbl)
POB (psi)
psi / bbl
Vol.(bbl)
300 (psi)
12.9 bbls
23.3 psi / bbl
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
Tripping Considerations
26
Tripping Considerations
Tripping Considerations
1. Drillstring:
Grade E
Grade X
a. Inspections
b. Two working strings
GRADE
YIELD
TENSILE
HARDNESS
MIN
MAX
MIN
MAX
HCL-80 80,000
95,000
95,000
95,000
22 Rc
H2S-90
90,000
105,000
95,000
100,000
25 Rc
H2S-95
95,000
110,000
95,000
105,000
25 Rc
Ammonia Hydroxide
(trips). This neutralized
the smell of the H2S.
27
Rotating Head
A rotating head is a
pack-off to divert flow
down flowline.
It allows about 300 psi
of control.
It allows pipe to be
rotated.
Rotating Head
The RH was used to
protect the rig crew on the
rig floor.
The stripping element was
set back on the first stand.
The key to trouble free
operation of a rotating head
is rig alignment.
28
Originally prepared
and donated
by
ConocoPhillips
H2S Orientation
for
Offshore Drilling Supervisors
Produced and Presented by
Murchison Drilling Schools
H2S Orientation
Written
by
David H. Schwartz
H2S Orientation
Characteristics
Detection
Prevention
Emergency Procedures
Safety and First Aid
Training and Planning
H2S Characteristics
Poisonous
Invisible
Heavier than air
Kills sense of smell
Explosive
Destroys steel and rubber
Threshold Limit
Threshold Limit
10 minutes in 8 hours
50 PPM (.005%)
H2S Comparison
KILLERS
1000
600
300
20
10
H2S
HCN
50
CO
Smells like
rotten eggs!
H2S Symptons
< 100 PPM
Suphur Dioxide
Threshold Limit:
5 ppm
Lethal Concentration:
1000 ppm
When ignited,
H2S produces:
Suphur Dioxide
YES
NO
Sulphide Stress
Cracking (SSC)
YES
NO
H2S Characteristics
Toxic
Invisible
Heavier than air
Kills sense of smell
Explosive
Destroys steel and rubber seals
Portable
Type
Fixed Point
Lead acetate
Solid state metal oxide
Electrochemical
Change in Properties
Smells like
rotten eggs!
Change in Properties
H2S + NaOH
NaHS + H20
To Detect H2S
Monitoring units
Chemical tests
Change in pH
Fluid properties
Expensive
Dependent on temperature and pressure
Affect mud properties
Testing difficult
Hydrogen Peroxide
Ammonium Hydroxide
Strong chemicals
Can cause severe irritations to:
Skin
Eye
Nose
CHECK FOR
USE
OIL BASE MUD or
LOW LIME WATER BASE
10
Severity Determination
I.
Potentially dangerous:
NO FREE GAS
Stop drilling
Check for flow
Call supervisor
If the well is flowing, follow your
procedure for taking a kick.
Drill cautiously
Treat mud
Hold bit weight & speed constant
Call loggers & engineer
Monitor
Stop drilling
Treat mud
Close diverter & ventilate floor
Wear breathing gear in suspected areas
Consider raising mud weight
11
Stop drilling
Put on breathing gear
Sound alarm
Reduce H2S concentration
Consider plugging well
Stop drilling.
Sound alarm.
Alert boats.
Go to briefing area.
DONT PANIC!
DONT PANIC
12
13
First Aid
14
KEY
TO
H2 S
SAFETY
15
Contingency Plan
Contingency Plan
General Information
General Information
Safety Procedures
Alarms
First aid
Equipment use
Contingency Plan
Contingency Plan
General Information
Safety Procedures
Operating Procedures
Gas monitoring
Pressure prediction
Kick killing
Operational limits
Contingency Plan
General Information
Safety Procedures
Operating Procedures
Evacuation Plan of Essential Personnel
Contingency Plan
General Information
Safety Procedures
Operating Procedures
Evacuation Plan of Essential Personnel
List of Responsibilities
16
General Information
Safety Procedures
Operating Procedures
Evacuation Plan of Essential Personnel
List of Responsibilities
Personnel Directory
Contingency Plan
Everyone Must
Recognize H2S
General Information
Safety Procedures
Operating Procedures
Evacuation Plan of Essential Personnel
List of Responsibilities
Personnel Directory
Check Lists
Everyone Must
Everyone Must
Recognize H2S
Read monitoring units
Recognize H2S
Read monitoring units
Know First Aid
Everyone Must
Everyone Must
Recognize H2S
Read monitoring units
Know First Aid
Use breathing gear
17
Recognize H2S
Read monitoring units
Know First Aid
Use breathing gear
Have a buddy
Everyone Must
Everyone Must
Recognize H2S
Read monitoring units
Know First Aid
Use breathing gear
Have a buddy
Locate briefing area
Drilling Crews
Mud weight importance
Gas in mud
Emergency procedures
18
Recognize H2S
Read monitoring units
Know First Aid
Use breathing gear
Have a buddy
Locate briefing area
Participate in drills
THE END
This program is for educational
purposes only. Nothing herein is
approval or disapproval of any
product or practice.
19
Day Six
Review Homework
Causes of Abnormal Pressure
Well Control Red Flags and Transition Zone
Indicators
Managed Pressure Drilling
Shales (Diagnosing, Solving & Preventing Shale
Problems)
Wellhead Installation & Subsea Presentation
Casing & Cementing
Simulator Testing
Causes of
Abnormal
Pressure
Causes of
Abnormal
Pressure
Dual Induction
Focused Log can
be used to
determine
transition zones.
See Drilling Manual,
Logging Chapter, page 20.
Causes of
Abnormal
Pressure
Causes of
Abnormal
Pressure
2. Uplifting/ Salt
plugs (Normal
pressure @ deeper
depth, that is
uplifted to
shallower depth
becomes an
abnormal
pressure.)
3. Gas transfer
Natural
Man made i.e. liners,
etc.
Natural
Gas
Transfer
Gas
10,000 Ft.
Fp = 4,650 psi
Natural
Gas
Transfer
Gas
Gas
6,000 Ft.
6,000 Ft.
MWB =
0.052
4650
10,000 Ft.
Gas
10,000 Ft.
Fp = 4,650 psi
MWN New
0.052 D LT
(5350 200)
MWN
0.052 7500
(14.2 8.33)
LH 2 O
LH 2 O
Liner Considerations:
Check:
5366 ft 0.052 8.33 ppg = 2324 psi
(7500 - 5366) 0.052 14.2 ppg = 1575 psi
2324 + 1575 = 3900 psi
3900
= 10 ppg (MWEquivalent for 10 ppg reverse test)
(7500)(0.052)
Primary Indicator
One that the driller sees
immediately without
any lag time (time from
bit to surface).
Secondary Indicator
Requires circulating
bottoms up. Could
have an hour lag time
or so on.
Secondary
1. Increase in R.O.P.
2. Increase in torque.
3. D exponent decrease.
4. Increase in drag, particularly in
sloughing shale.
5. Fill on connections. (Top drive
connections made 10 off bottom.)
8. Pit gains.
A. Geophysical
Methods
B. Drilling
Parameters
C. Drilling Mud
D. Drill Cuttings
E. Well Logging
F. Direct Pressure
Measuring Devices
9. SIPs.
6. Flow increase.
6. Chloride increase.
Scene 1
Blew out for 2 weeks.
Geopressure
Detection
Methods
Scene 2
Scene 3
Took 7 minutes
to burn up.
See Drilling Manual,
Logging Chapter, page 20.
Required Equip.
Rotating
Control Device
(Rotating
Head)
Drill String
Floats
Dedicated
Chokes
Technical Notes:
MPD may allow faster corrective action to deal with
observed pressure variations. The ability to dynamically
control annular pressures facilitates drilling of what
might otherwise be economically unattainable
prospects.
MPD techniques may be used to avoid formation influx.
Any flow incidental to the operation will be safely
contained using an appropriate process (Dual Gradient
Drilling).
Technical Notes:
MPD process employs a collection of tools and
techniques which may mitigate the risks and costs
associated with drilling wells that have narrow
downhole environmental limits, by proactively
managing the annular hydraulic pressure profile.
MPD (CBHP) may include control of back pressure,
fluid density, fluid rheology, annular fluid level,
circulating friction, hole geometry, pressurized mud cap
drilling (PMCD), or combinations thereof.
Objectives
Objectives
UBD:
Improve Rate of Penetration
Extend Bit Life
Limit Lost Circulation
Reduce Formation Damage
Early Production Recovery While Drilling
Enhance Formation Evaluation or Testing While Drilling
Identify Productive Zones (Oil =>Optimize; Water = Shutoff)
Establish TD Based on Inflow Performance
Improve Production Index for More Effective Completion
MPD:
Improve Rate of Penetration
Extend Bit Life
Minimize Differential Sticking
Limit Lost Circulation
Shales
Hole unloading
Shales
Gamma Ray is
our best shale
log.
Shales
Shales
Shales
Shales
Shales
4. Mud making
(cuttings stay in
mud).
Shales
Shales
6. MBT will go up
without adding
commercial bentonite.
7. Bit balling if hydraulics
not good or if too much
weight on bit.
MWE 9
21 psi
= 9.2 ppg
2000 0.052
Shales
8. Water requirements
increase to keep MW
down.
To maintain a 9 ppg
mud (5% solids by
volume) with 70%
efficiency, use the
Efficiency Factor of 5.7.
If 60% efficient,
multiply by solids factor
of 7.6.
17.52
5.7 4, 070 bbl / day
1029.4
Shales
Shales
Shales
Shales
Shales
10
Mud Rings
Later
Shales
Shales
Shales
Shales
Shales
Shales
11
Shales
Shales
Length
POB (CSG V -
DPAW
)
2748
DPW
2748
22.12
6 psi (0.0732 )
2748 = 104 ft
Length
22.12
0.468
2748
GM
Shales
Shales
Shales
Shales
12
Shales
Shales
Note: This same approach also works well for coal drilling.
3,000+
Shales
Anhydrite
Salt
Shale
Limestone
2,000
Drilling and Well
Control Training
2,200
Drilling and Well
Control Training
Anhydrite
Anhydrite
Salt
Salt
Shale
Shale
Limestone
Limestone
13
2,600
Drilling and Well
Control Training
3,000+
Drilling and Well
Control Training
2,400
Drilling and Well
Control Training
Anhydrite
Anhydrite
Salt
Salt
Shale
Shale
Limestone
Limestone
Shales
Anhydrite
Salt
Shale
Limestone
Shales
Shales
Normally
In These Formations
14
Shales
Shales
Shales
Shales
Shales
Shales
15
Shales
Shales
2. Calculate Mud
Weight Equivalent
at casing shoe with
pressure calculated
in 1.0.
PSurf
MWE MWH
TVD
0.052
Shoe
PSurf
MWE MWH
TVD
0.052
Shoe
345
MWE 18.0
6,500 0.052
MWE = 19 ppg
Additive Pressure is very dangerous if you dont put a
pencil to it!
Shales
Shales
Roughneck Formula
P
SPM 2
P2 P1
SPM1
Shales
Sloughing Shale
Sloughs on bottom
Sloughs because of:
pressure in the shale
weak rock matrix
strength caused by
interruption of water
compaction trends.
Has nothing to do with
water loss or over exposure.
Roughneck Formula
Above squeezing marl = 2,000 psi/100spm.
Adjacent squeezing marl = 2,100 psi/98 spm.
What is the P due to squeezing?
2
98
P2 2, 000
1920 psi
100
Therefore: P = (2,100 - 1,920) = 180 psi
This shows a restricted annulus.
Shales
Heaving Shales
Falls in off bottom.
Has been overexposed. You have
given time for the
osmotic hydration
process to take place.
16
Shales
Shales
Capillary forces
Osmotic forces
Interruption of Compaction
Trend
1. Low MBT.
2. Associated with shale
transition zones. (Water
compaction trend
interrupted.)
3. Greater: porosity, water
content, ROP, gas
content, torque, drag.
Shales
Hole Unloading!
Shales
Hole Unloading!
Shales
Shales
17
Shales
Shales
True Yp
Shales
W1 W 2
Ph
PP S I
33.81 Log
W2
14.7
Where
Ppsi
W1
W2
Ph
=
=
=
=
W1 W 2
Ph
PP S I
33.81 Log
W2
14.7
9
14.7
PPSI = 105 psi
Shales
Reduced
Head
1,000
936 psi
866 psi
60 psi
5,000
4,600 psi
4,598 psi
82 psi
10,000
9,360 psi
9,265 psi
95 psi
20,000
18,720 psi
18,615 psi
105 psi
Shales
Shales
Head
Reduction
18
Shales
Volp (bbl)
P = 198 psi
Change in BHP due to HW Pill
Shales
Shales
Shales
Shales
Shales
19
Shales
Shales
Shales
Shales
Shales
Chevron
Subsea
Presentation
Surface
Wellhead
Installation
Rigging Up
Casing
Drilling
20
This formula
will give you
the proper
weight mud to
balance static
forces.
Wcsg BFcmt
MWB MWCMT -
42 Vcsg
Wcsg BFcmt
MWB MWCMT -
42 Vcsg
Where:
)F
= Force tending to hydraulic casing off bottom
(minus number)
L
= Casing length
WCsg = Casing weight (lb/ft)
BFCmt = Buoyancy Factor of cement
) MW = Balancing mud weight to prevent hydraulicing
VCsg
= Volume of casing (bbl/ft)
MWCmt = Weight of cement (ppg)
MW
= Mud weight (ppg)
87.5 0.775
MWB 14.7 -
42 0.3062
MW
9.4
1791 lb
328 0.052
21
Example:
ROP is important in
picking a competent
shoe.
Example:
22
Drilling Engineer
Engineers Responsibility
Change current program as needed.
Change next well program to adjust for time
sensitive shale.
Casing point
Oil-based mud
Bits
2. Supports casing.
3. Running of casing.
23
Example of tool
made on rig to
measure casing:
24
10. If U-tube pressure to land 1st stage plug is 200 psi low,
how much cement column was lost?
Given Data:
TD:
Hole:
MW:
BF:
FC:
DV:
Shoe:
Csg/OH:
Csg/csg:
Ann. Cap.:
Blocks:
1. Calculate air
weight (WAir) and
weight indicator
weight (WWI).
12,000 ft
12.75 (from caliper)
10 ppg
0.847
11,920 ft
6,000 ft
9, 12,000 ft
0.3814 cu ft/ft
0.3354 cu ft/ft
0.0732 bbl/ft, 0.4110 cu ft/ft
80,000 lbs
TD
WCsg
MW
Blocks
WAir
WWI
=
=
=
=
=
=
W A ir L C sg W C sg
W W I (( W A ir B F ) H L )
25
12,000 ft
47 lb/ft (9)
10 ppg
80,000 lbs
?
?
Pipe Elongation
Air weight causes pipe to stretch and lengthen. Temperature
also causes pipe to lengthen. Buoyancy (piston effect)
causes pipe to shorten.
W A ir 1 2 , 0 0 0 4 7 564,000 lbs
W W I ((5 6 4 , 0 0 0 0 .8 4 7 ) 8 0 , 0 0 0 ) 558,000 lbs
Stretch
12, 000
564, 000
2
8.3 feet
2. Calculate metal
displacement
a) 500 feet
b) total
Vm Len(ft)
Vmt
TD = 12,000 ft;
DH = 12.75 (caliper)
WCsg = 47 lb/ft (9)
a. Vm 500
b. Vmt
WCsg lb/ft
47 lb / ft
= 8.55 bbl
2748 lb / bbl
12000 47
= 205 bbl
2748
2748 lb/bbl
WAir lb
or
2748 lb/bbl
3. Discuss
monitoring metal
displacement
regular float and
differential float
equipment.
3. Discuss
monitoring metal
displacement
regular float and
differential float
equipment.
26
Differential Float
Equipment Blowout
Example
MW = 13.5 ppg
Pob = 200 psi @
Top of Gas Cap
L=
200 psi
= 286 ft
0.7 psi/ft
V = 286 ft
(8.6812 -7 2 )
= 7.3 bbl loss
1029.4
Data:
Twelve 40 ft joints have been run in hole.
Casing = 13, 61 lb/ft;
Casing capacity = 0.1521 bbl/ft;
Annular Capacity = 0.124 bbl/ft;
Mud Weight = 11.5 ppg
Differential Float
Equipment Blowout
27
TD
DH
MW
Shoe
FC
DV
Cap 9
MW
CapCsg
CapAnn
HUnfilledCsg
HPL
=
=
=
=
=
=
=
=
=
=
=
=
CapAnncsgOH =
Csg/csg
=
BF
=
Primary CW =
Yield
=
Mix H2O
=
15.7 ppg
1.35 cu ft/sk
5.0 gal/ sk
Outside
First Stage:
12,000 ft;
12.75 (caliper)
10 ppg
9 @ 12,000
11,920 ft
6,000 ft
0.0732 bbl/ft and
0.4110 cu ft/ft;
0.3814 cu ft/ft
0.3354 cu ft/ft
0.847
First Stage:
Inside 1
SF
100
30
100
CuftT = 3,008 cu ft
28
First Stage:
SacksL = cu ftL / cmt. yeild (lead) cu ft/sk
SacksL = 2768/1.35 = 2050 sacks
Mix H2OL = gal/sk sacks / 42 gal/bbl
or H2O1st = (5.0 2050 + 4.5 200)/42
H2O1st = 266 bbls (total)
Primary CW=
Yield
=
Mix H2O =
14.5 ppg
1.67 cu ft/sk
6.0 gal/ sk
Second Stage: 1
Both are
outside.
Second Stage:
sf
sf
PREV. SHOEd - TOP CMTD CAPCAS 1 +
100
30
10
= 6000 - 4000 0.3814 1 +
+ 4000-1000 0.3354 1 +
100
100
CuftT = 2,098 cu ft
TD
DH
= 12,000 ft
= 12.75
VAnn (bbl/ft) =
(from caliper)
(12.75 9.625 )
1029.4
DCas = 9
Va = 150 ft/min
VAnn
(DH 2 DP 2 )
1029.4
29
VPreFlush (bbl)
(MWH PFwt. )0.052
VAnn (bbl/Ft)
70
P
(10 8.33)0.052 = 89.5 psi
0.0679
P
8. Calculate U-tube
pressure to land 1st
and 2nd stage plugs.
Ignore weight of
spacer fluid.
3008 cu.ft
Mix/Disp. Time
10 bbl/min
MW
Shoe
FC
DV
CW1st
CW2nd
=
=
=
=
=
=
10 ppg
9; 12,000
11,920 ft
6,000 ft
15.7 ppg
14.5 ppg
30
Notes:
You need more pressure than the U-tube pressure.
You want to bump the plug so that you know that you
have the tail end cement in.
Slow pump down near the end so you dont bump the
plug too hard.
Use rig pumps with known outputs.
PS u rf (PU T 1 5 0 0 p si)
Cv
PP B cas vo l C
3 0 0, 0 0 0
Cv
Cv =
(2,6706,0000.0732)
300,000
=
=
=
=
=
10 ppg
9 @ 12,000
11,920
6,000
15.7 ppg
DOI (D DV
P
)
(CW MW)0.052
DOI (6,000 ft
200 psi
)
(15.7 10) 0.052
DOI = 6,675 ft
Is this the Loss Zone Depth?
P
)
(CW MW)0.052
31
1.
2.
3.
4.
5.
6.
3. Mix cement
(1st
stage)
32
14. Observe.
Running Casing
1. Get your Workshop to clean and threadlock the
factory collars for the first three or four joints.
2. Threadlock the field end as you run the casing.
3. Run casing in the correct order.
4. Have the right integrity by torqueing casing properly.
5. Make sure you dont knock the bottom out of the
hole. Keep up with metal displacement.
6. If you think you are on bottom, count the joints left
on location. This is a known number.
Where:
T
n
Vh
Vm
c
=
=
=
=
=
= equivalent dial
reading
VPMT = maximum casing
velocity without
frac, ft/min(turb)
33
n
n
Log Vh / Vm
0.301
Log 70 40
0.301
n = 0.807
1 .6 5
V
D
2
n
2 n
M W
4 0 0 .8 0 7
1 . 6 5 8 . 5 7 2 1 5
0 .8 0 7
( 2 0 .8 0 7 )
c 3 1 .9 7
8000
MWF 16.7 15
2000
MWF
= 6.8
824 D 2H D P2
VPM T
D 2H D P2
824 8 .5 2 7 2
VPM T
8.5 2 7 2
M WF D H D P
6 .8 8 .5 7
VPML
VM
D2H DP2
MW
(Thisisanexampleofaturbulentflow.Therefore,
nonumbersareputintotheformula.)
15
34
JL (ft) 60 (sec/min)
VPM (L) or VPM (ft/min) (T)
MWF MWLot MW
t=
MWF 16.7 15
t = 18.4 sec/joint
Casing Length
2,000 feet
18.4
Dcsgshoe
8000
4000
MWF = 3.4
824 D 2H - D P2
VPM T =
D 2H + D P2
= 70.7
(70.7) > c (31.97); Therefore it is turbulent.
JL (ft) 60 (sec/min)
VPM (L) or VPM (ft/min) (T)
t=
M WF D H - D P
8 2 4 8 .5 2 - 7 2
V P M T =
8 .5 2 + 7 2
LI
MW
3 .4 8 .5 - 7
15
Summary
Casing Length
2,000 feet
4,000 feet
t = 26 sec/joint
35
Dcsgshoe
LI
8000
MWF = 16.7 -15
8000
= 35.4
MWF = 1.7
JL (ft) 60 (sec/min)
VPM (L) or VPM (ft/min) (T)
824 8.5 2 - 7 2
1.7 8.5 - 7
VPM T =
2
2
15
8.5
+
7
40ft 60sec/min
65ft/min
t = 37 sec/joint
8 2 4 D 2H - D P2
VPM T =
D 2H + D P2
M W F D H - D P
MW
Summary
Casing Length
2,000 feet
4,000 feet
8,000 feet
1.
2.
3.
4.
5.
NOTE:
The longer the casing string that is picked-up, the slower
the casing should be run in the hole to stay below FRAC.
36
How long to
circulate has
nothing you do
with how long it
takes the company
man and the tool
pusher to have
breakfast.
Pre-Cementing Meeting
37
Pre-Cementing Meeting
Company Man
Drilling Engineer
Man in charge
Assists Foreman
Has no business
weighing cement
Pre-Cementing Meeting
Toolpusher
Driller
Liaison between
the company man
and all the
contractor people.
drag
hook loads
circulating rates
Pre-Cementing Meeting
Responsible for
supervising crew,
working pipe, and
monitoring such data as:
Pre-Cementing Meeting
Mud Engineer
Pre-Cementing Meeting
Underbalanced Cementing
This is what happens when you dont mix the cement at the
right weight to keep the well overbalanced.
38
Underbalanced Cementing
Application:
When cement
cannot be mixed at
required weight to
balance formation
pressure.
Operational Requirement:
1. Hang casing before
cementing.
2. Line up to take returns,
below where casing is
landed, through choke
line.
3. Make a back pressure
schedule.
Underbalanced Cementing
0.104
G
(bbl/ft)
1.82psi/bbl
Ann.Vol.
0.057
3. BPI (psi) Desired increment psi/bbl
BPI
BPS
431
862
1,293
1,724
2,155
2,586
3,017
3,448
3,879
4,310
4,741
** 4,913
570 bbl
0.116 bbl/stk
= 4,913 stk **
Underbalanced Cementing
Nomenclature:
G
Underbalanced Cementing
2. psi/bbl
Surface Back
Pressure (psi)
91
182
273
364
455
546
637
728
819
910
1,001
*1,038
39
An
Overview Of Land
&
presents
Sub-sea Drilling
Operations
Murchison
Drilling Schools
Leadership Training
For The Man On The Rig
An Overview Of Land
&
Sub-sea Drilling Operations
The objective of
this ppresentation
is to show the
differences
between land rigs,
jack ups, semisubmersibles and
drill ships.
Fixed Rigs
Land Rig
Jack Up Rig
A fixed rig is
located just
above earths
surface.
Above the
surface of the
sea, far above
the drilling
site.
Fixed Rigs
Jack Up Rigs
Towed to the drilling
site.
i
Legs are lowered into
place raising the barge
out of the water.
Floating Rigs
Floating Rigs
Drill Ships
Drill Ships
Drilling
proceeds
through an
opening in
mid-ship,
called the
moon pool.
Have drilling
rigs
i mounted
t d on
them.
Have the hull
profile of a ship.
Semi-submersibles
Floating Rigs
Drill Ships
Drill ships are
used in deeper
water, when a
jack up rig
cannot be
used.
Most
floating rigs
are semisubmersible.
Floating Rigs
Floating Rigs
Semi-submersible
Semi-submersibles
Semis may be
anchored or have
dynamic positioning
systems.
Floating Rigs
Drill ships and
semis have special
equipment to
compensate for
movement caused
by wind, waves,
and tides.
Special Adaptations
If the rig is
anchored and uses
guidelines when
running BOPs and
wellhead
equipment, a
guideline tensioning
system is used to
compensate for the
rigs motion.
The type of
offshore rig
selected for a
drill site
depends on
several factors:
Depth
Weather
Logistics
Drilling Procedures
Bottom-Supported Units
Weather:
If ice m
must
st be contended with,
ith a drill
ship or semi-submersible is required.
In areas where the rig may be exposed
to icebergs or pack ice, a drill ship is
used for its increased mobility.
Logistics:
Drilling Procedures
Bottom-Supported Units
Drilling Procedures
Bottom-Supported Units
Drilling from a
jack up rig is far
more dangerous
than a land drilling
operation,
particularly related
to shallow gas.
Drilling Procedures
Floating Units
Drilling Procedures
Bottom-Supported Units
The whole rig
would
ld go down
d
in the water.
Drilling Procedures
Floating Units
Drilling Procedures
Floating Units
Guidelines
Drilling Procedures
Floating Units
Drilling Procedures
Floating Units
In soft bottom areas, the conductor
pipe is jetted into place.
A temporary guide base is not used.
Guidelines are attached to the
permanent guide structure posts.
Drilling Procedures
Floating Units
Drilling Procedures
Floating Units
When drilling has been
completed, the BOP is
removed.
If the well is to be
placed in production, a
sub-sea production
christmas tree is
installed or the well is
temporarily capped off.
The End
Produced by :
Murchison Drilling Schools, Inc.
2501 Juan Tabo NE
Albuquerque, NM 87112
(505) 293-6271
[email protected]
Day Seven
Review Homework
Good Mud Practices
Logging & Perforating
BOP Equipment &
Accumulator
Considerations
Simulator Testing
MDS Bonus
HW Award
Ideally, this
should be done
when the rig is
being selected.
Spud
Top Hole
Intermediate interval
Production Interval
1.
2.
3.
4.
Air
Mist
Foam
WBM
Multiple Types
5. OBM
Multiple Bases
E. Inhibited WBM
A mud that can suppresses hydration of a
particular type of formation into the mud.
1.
2.
3.
4.
5.
C. Synthetic Oils
Highly refined mineral oil-based fluids and fluids
derived from vegetable and animal sources
SBM Development
The problem with OBM cuttings disposal was
recognized as early as 1985. Cuttings piles discharged to
the seafloor persisted, continuing to pollute for many
years. An alternative to oil-based muds was required.
A. Synthetic Base Oil Synthetic Fluid is a hydrocarbon manufactured from smaller base molecules.
The end product is not normally found in nature.
SBM Development
Any environmentally sound alternative fluid had to
offer the technical performance of OBMs as well. SBMs
were designed to retain the key benefits of OBMs,
including:
Borehole stability, especially in sensitive shale
formations
Lubricity,
Mud stability over a range of temperatures and hole
conditions,
Absence of reaction with formations.
3. HSE Regulations
Health
Short and long term health issues
Closed or open pits
Diesel onshore with open topped pits
Mineral oil onshore with closed pits
2. Company Policy
If there are regulatory differences use the
most conservative regulation.
Safety
Mixing areas
Rig floor
Personnel Protection Equipment (PPE)
1.
2.
3.
4.
Health issues
Elastomer impact
Economics
Specific area requirements
Environmental Impact
Sheen on water surface
Oil on cuttings
Biodegradation rates
1.
2.
3.
4.
5.
6.
7.
8.
Base Oil
Primary Emulsifiers, and Secondary Emulsifiers
Water with a Salt concentration
Lime
Fluid Loss Additives
Wetting Agents
Weight Materials
Viscosity Enhancers
Component Functions
1. Primary and Secondary Emulsifiers
Help form water droplets in continuous oil phase.
Emulsifies any water added to the mud while drilling
Base Oil
Primary and Secondary Emulsifiers
Viscosifier
Lime, (Shear 30min. minimum)
Salt Water (Shear 30 min.)
Wetting Agent
Weight Material (Shear 30 min.)
Fluid Loss Reducers
2. Lime
Lime forms a soap with the emulsifier that helps
stabilizes the water droplets.
Helps control acid gas influxes (CO2 & H2S)
Component Functions
3. Water
Adds weight
Impacts viscosity and rheology of the mud
Helps reduce cost of mud
Electrical Stability
The probe is placed in the mud.
A meter reads between 0 -2000
volts
The reading indicates stability
of the water in oil emulsion and reflects the oil
wetting qualities. The higher the value the more
stable the emulsion
700 900 might be a typical range
4. Salts
Calcium Chloride (CaCl2)or Sodium Chloride (NaCl)
that helps stabilize reactive formations.
The correct concentration minimize changes in the
water concentration in shale sections.
Mud Additives
Mud Additives
14. Corrosion inhibitors reduce steel corrosion Bisulfite, iron oxide zinc products amines
15. Defoamers: Reduce surface tension, reduce air in
muds particularly in salt systems
16. Foaming Agents: Surfactants that let water foam
17. Temperature Stability Products: Particularly WBM
18. Hydrate Suppressants. Alcohol base for riser
environments
Lost Circulation
A. Lost Circulation
Lost Circulation
Stuck Pipe
Well Control
Hole Cleaning & Stability
People & Supervision
Mud & Hydraulics
Tripping & Shale
Lost Circulation
1. Seepage Losses
Water Base
< 25 bbls/hr
1. Unconsolidated Formations
Sand
Pea Gravel
Gravel
Shells
Reefs
2. Moderate Losses
Water Base
25-100 bbls/hr
3. Severe Losses
Water Base
Lost Circulation
Lost Circulation
Lost Circulation
Lost Circulation
Lost Circulation
Lost Circulation
Lost Circulation
F. Types of LCM
1.
2.
3.
4.
Rigid
Deformable
Large to fine sizes
Micron sized
Lost Circulation
G. Seepage
Lost Circulation
Lost Circulation
Shale Inhibition
Shale Stability
Shale Stability
OR
Base Mud
40
20
PV 20
YP 0
Spud Mud
40
28
12
16
10
11
Good Bentonite
S.P. Log
(Spontaneous Potential)
SP Log measures
voltage between open
formation and wellbore
Works similar to a
battery
Measured in millivolts
(1/1000 volt)
Normal range is 15 to
150 millivolts
Permeability log
S.P. Log
(Spontaneous Potential)
12
S.P. Log
(Spontaneous Potential)
S.P. Log
(Spontaneous Potential)
S.P. Log
(Spontaneous Potential)
S.P. Log
(Spontaneous Potential)
Gamma Ray
Gamma Ray
13
Gamma Ray
Gamma Ray
Gamma Ray
Gamma Ray
Caliper
Uses
GR
1. Correlation
Yes
Yes
2. Shale
Yes
Yes
3. Bit Selection
Yes
Yes
4. Lithology
Yes
Maybe
5. Completion
Yes
No
14
SP
6. Post Appraisal
Yes
Yes
7. Abnormal Pressure
Yes
Indirectly
8. Permeability
No
Yes
Caliper
Caliper
Caliper
Resistivity Ohm-Meters
15
Caliper
Caliper
Resistivity Ohm-Meters
Resistivity Ohm-Meters
Resistivity Ohm-Meters
Resistivity Ohm-Meters
Resistivity Ohm-Meters
Well G
Well H
16
Well H
Uses
Neutron Log
Rock
Caliper
Yes
Yes
2. Shale
Yes
Yes
3. Bit Selection
Yes
Yes
4. Lithology
Yes
Yes
5. Completion
Yes
Yes
6. Post Appraisal
Yes
No
7. Abnormal Pressure
Yes
Yes
Density Log
Hydrogen
Gamma
Ray
Receiver
Gamma Ray
Neutron-Density
Log
Drilling and Well
Neutron and
Density
Logs
Drilling and Well
Control Training
Control Training
NOTE:
The Neutron and
Density logs are radioactive source logs and
should be run after
evaluating hole
condition with other
logs, i.e. Induction, etc.
Neutron
kicks left
in shale.
17
Resistivity
1. Correlation
Radioactive
Element
Rule of Thumb
Shale:
Sand:
18
Shale:
Sand:
Uses
Logging Uses of
Neutron-Density
Neutron and Density
1. Correlation
Yes
2. Shale
Yes
3. Bit Selection
Yes (best)
4. Lithology
Yes
5. Completion
Yes
6. Post Appraisal
Yes
7. Abnormal Pressure
Yes
8. Permeability
No
Logging
Logging
Pop Quiz
Anhydrite
Dolomite
Anhydrite
Dolomite
Logging
Dolomite
Limestone
Limestone:
Tracking
Hard drilling
19
Logging
Sandstone
Limestone Scale:
Dolomite
Logging
Sandstone
Sandstone
Tracking
Lmt & SS
Limestone
Sandstone
Logging
Logging
Limestone
Shale
Sandstone
Shale
Sandstone
High Water Content
Shales (very
unstable), (Stuck
Anchor on D.S.T.)
Shale
Shale
2.71 2.98
2.71 1.1
App. Porosity =
2.71-2.65
2.71-1.1
= 3.7%
Density of Limestone
= 2.71 gm/cc
Density of Sandstone
= 2.65
20
2.65 2.98
2.65 1.1
Apparent Porosity
2.65 2.71
2.65 1.1
Density of Sandstone
= 2.65 gm/cc
Density of Anhydrite
= 2.98
Density of Formation Fluid = 1.1
Density of Sandstone
= 2.65 gm/cc
Density of Anhydrite
= 2.71
Density of Formation Fluid = 1.1
Sonic Log
Sonic Log
Talc
Gypsum
Calcium
Fluorite
Apatite
Why do we need
seismic while
drilling?
To help
geologists with
their correlations.
To set casing at
the correct depth.
21
6. Orthoclase
7. Quartz
8. Topaz
9. Corundum
10.Diamond
Basic
Induction
Log
Principles
Resistivity Log
Resistivity
from 2000 Hz Waveforms
Log from
2000+
Waveforms
Drilling and Well
Control Training
Resistivity Log
NMR Logging
NMR Principles
22
NMR Principles
NMR Principles
NMR Principles
NMR Principles
NMR Principles
NMR Principles
23
NMR Principles
Perforating:
Gamma-Ray
Tie-In The
Open Hole Log
Fermions:
3H
13C
13N
15O
21Na
25Mg
27Al
29Si
33S
35Cl
45.4
10.7
4.9
11.0
12.1
2.6
11.1
8.5
3.3
4.2
2H
14N
22Na
32P
36Cl
40K
42K
52Mn
6.5
3.1
4.4
1.9
4.9
2.5
4.3
3.9
Bosons:
Perforating:
Gamma-Ray
Tie-In The
Open Hole Log
Perforating:
Gamma-Ray
Tie-In The
Open Hole Log
Perforating:
Gamma-Ray
Tie-In The
Open Hole Log
First Run
They dont match up yet.
24
Sandstone Scale
Perforating:
Gamma-Ray
Tie-In The
Open Hole Log
Perforating:
Gamma-Ray
Tie-In The
Open Hole Log
Perforating
Perforation
can penetrate
into the
formation
30-40 inches.
Report number
and position
(depth) of bad
shots.
25
Perforating
Perforating
Perforating
Perforating
26
BOP Equipment
BOP Equipment
BOP Equipment
BOP Equipment
BOP Equipment
BOP Equipment
BOP Equipment
The Wedgelock is a
hydraulic mechanism
which allows the BOP
to be locked in the
closed position
remotely.
This locks the Ram in
position even if
hydraulic closing
pressure is lost.
27
BOP Equipment
Multiple Position
Locking (MPL)
System for remote
automatic locking of
the BOP.
A mechanical lock is
automatically set each
time the ram is closed.
BOP Equipment
BOP Equipment
BOP Equipment
BOP Equipment
BOP Equipment
Natural rubber is
compounded for drilling
with water based drilling
fluids.
Natural rubber-packing
unit will usually provide
the longest service life
when properly applied.
Operating temperature
range -30F to 225F.
28
BOP Equipment
Control line
arrangement for
automatic control of
valve on diverter line.
When diverter closes
the valve
automatically opens
due to being hooked
up to the same
hydraulic fluid source.
BOP Equipment
BOP Equipment
BOP Equipment
Kelly Valve
A kelly valve is a small
one-piece valve that can
easily be handled by one
person. It has a pressure
rating of 10,000 to 15,000
psi. It has metal to metal
seals and will withstand
pressure from below or
above.
BOP Equipment
BOP Equipment
29
BOP Equipment
PW H1 MW 0.052
PW 10 12.5 0.052 6.5 psi
BOP Equipment
BOP Equipment
BOP Equipment
BOP Equipment
Considerations
1. Pressure
This is one of the biggest
considerations.
You must design, install,
maintain, test and use the BOP
system and system components to
ensure well control. The workingpressure rating must exceed
maximum anticipated surface
pressure....
30
Considerations
Considerations
2. Size
3. Arrangement
The BOP stack must include at least four remotecontrolled, hydraulically operated BOPs consisting
of one annular BOP, two BOPs equipped with pipe
rams, and one BOP equipped with blind or
blind/shear rams. The blind/shear ram must be
capable of shearing the drill pipe that is in the hole.
See Workbook, BSEE Rules, pages 15-16, 250.441 (a), 250.442 (b).
Considerations
Considerations
3. Arrangement
3. Arrangement
a) Stack
a) Stack
A foreman needs to
make sure all BOP
equipment is working
properly.
Considerations
Considerations
3. Arrangement
b) Choke Line/ Kill line
Requires 25 - 36 of spacing
between sheer ram and hang
off ram.
Hang Off For
Routine Kicks
31
Considerations
Considerations
3. Arrangement
b) Choke Line/ Kill line
4. Trim (H2S)
Use BOP system components, wellhead, pressurecontrol equipment, and related equipment exposed to
H2S-bearing fluids in conformance with NACE
Standard MR017503 (as specified in 250.198).
Elastomer seals. You must use H2S-resistant
materials for all seals which may be exposed to
fluids containing H2S.
Considerations
Considerations
When you pressure test the BOP system, you must conduct a lowpressure and a high-pressure test for each BOP component. You
must conduct the low-pressure test before the high-pressure test.
Each individual pressure test must hold pressure long enough to
demonstrate that the tested component(s) holds the required
pressure. Required test pressures are as follows:
(b) High-pressure test for ram-type BOPs, the choke manifold, and
other BOP components. The high-pressure test must equal the rated
working pressure of the equipment or be 500 psi greater than your
calculated maximum anticipated surface pressure (MASP) for the
applicable section of hole. Before you may test BOP equipment to the
MASP plus 500 psi, the District Manager must have approved those
test pressures in your APD.
(c) High pressure test for annular-type BOPs. The high pressure test
must equal 70 percent of the rated working pressure of the equipment
or to a pressure approved in your APD.
Considerations
Considerations
(d) Duration of pressure test. Each test must hold the required pressure
for 5 minutes. However, for surface BOP systems and surface
equipment of a subsea BOP system, a 3-minute test duration is
acceptable if you record your test pressures on the outermost half of a
4-hour chart, on a 1-hour chart, or on a digital recorder. If the
equipment does not hold the required pressure during a test, you must
correct the problem and retest the affected component(s).
32
Considerations
6. Accumulators (API STD 53 12.3.1)
P1V1 =P2 V2 or V2
P1V1
P2
V2
V2
P1V1 (1000)(10)
8.33 gal
P2
1200
P1V1 (1000)(10)
3.33 gal
P2
3000
33
13
10,000
GK Hydril Annular
13
10,000
U CIW Ram
(1) 13
10,000
(1) 4
10,000
F CIW CL Valve
(1) 4
10,000
F CIW KL Valve
Bottle Sizegal
10 5 gallons
1200 3000
Close
Open
(1)
(2)
(1)
(2)
29.35
11.60
11.60
0.00
0.00
0.00
0.00
0.59
Hydril Annular
Ram
Blind Ram
CL/KL Valves
Subtotal
Total
Accumulator
Operating
Pressure
psi
750
1,000
1,000
1,500
0.125
0.33
0.5
0.582
psi
Accumulator
Size
Factor
8
3
2
1.72
VT
Usable Fluid
Volume*
(fraction of
bottle size)
VUFraction
Minimum
Recommended
Precharge
Pressure
1500
2,000
3,000
5,000
52.55
0.59
53.14 + 50% = 79.7 gallons of hydraulic fluid
VUHF
5
0.5
VBottle 10
# Bottles
VReq
VUsable
80
16.0
5
# Bottles 16
V Re q
80
160 gallons
VUFraction 0.5
See Well Control Manual, pages 132-138.
34
V2
PMin
P1V1 (3000)(3.33)
BOP Rating
15,000
1415.1 psi
Closin g Ratio
10.6
VReq
VUsable
80
21.4
3.73
# Bottles 22
Bottle Sizegal
1000
1000
10 3.73 gallons
1415.09 3000
PN
PN
(29.35)(3000)(1900)
294 (3000-1900)
PN 517psi
See Drilling Manual, Abnormal Pressure chapter, page 2.
See Workbook, BOPE, page 15.
517 psi
PAcc
PN
PI
Accumulator Pressure
Pressure Nitrogen Pre-Charge
Initial Accumulator Pressure
PF
VT
VA
VU
35
What To Do If Average
Pre-Charge Is Low
Riser
Tensioner
Riser Tensioners
1. Purpose
To provide sufficient tension to
keep the riser straight
3. Recoil System
Controls speed of changes in the
system
36
BOP Equipment
Subsea Considerations
=
=
=
=
=
=
=
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
37
BOP Equipment
Subsea Considerations
Riser Running
Equipment
Riser joint
Riser spider
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
Surface
Operating fluid passes through 4 way valve
Vented fluid returns to accumulator
Subsea
38
BOP Equipment
Subsea Considerations
In a subsea
operation the
wellhead is
usually welded
to the surface
casing and is
run with the
permanent
guide base.
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
Test Plug
Wear Bushing
Casing
Hangar
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
39
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
Control Systems
BOP Equipment
Subsea Considerations
Hydraulic BOP
Control Systems
1. Original Type
2. Valves controlled by
Hydraulic Pressure
3. Uses pilot pressure
signal
4. Vents operating fluid
to the sea
1. Primary
a. Hydraulic
b. MUX
2. Secondary
a. Acoustic
b. ROV Intervention
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
MUX system
1. Electric Hydraulic
System
2. Electric signal from
control valve to SPM valve
3. Two way communication
4. SPM valve gets order and
operates
40
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
ROV Intervention
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
ROV Intervention
1. Emergency system
2. Does not use Pod
3. Uses sea water as
operating fluid
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
Sequence #1
P1V1 P2 V2 or V2 =
V2
P1V1
P2
496 bbl
41
Sequence #2
Sequence #3
Sequence #4
Sequence #5
Sequence #6
BOP Equipment
Subsea Considerations
Before resuming
operations, check
below the closed ram
for pressure before
opening.
42
BOP Equipment
Subsea Considerations
Subsea Accumulators
A semi-submersible is in 2,000 feet of water with a
subsea BOP stack and a 5,000 psi accumulator with
a 1,500 psi pre-charge is being used. It needs 800
gallons of usable hydraulic fluid; and 700 gallons
will be stored on surface and the remaining 100
gallons will be stored on the subsea BOP stack, what
is the total volume needed on the surface
accumulator system?
What is the total volume needed on the subsea BOP
accumulator system?
5000 6
VT
VUHF 11.65
0.5825
VBottle
20
VReq
VUFraction
VT
VReq
V3
5000 890 14.7 8.14 18.48 gal Nitrogen (1.52 gal HF)
1700 890 14.7
-
BOP Equipment
Subsea Considerations
V
10.31
UHF
0.5165
VBottle
20
VUFraction
PHSW
PAtm
GSW
D
700
1201.7 gal or 61 bottles
0.5825
V2
P1V1 (1500)(20)
VUFraction
100
193.61 gal or 10 20-gallon bottles
0.5165
43
BOP Equipment
Subsea Considerations
Gas Hydrates
Gas Hydrates
The Reverse Riser Method (Tourly method)
cannot be used to check Choke Line Friction
with hydrate inhibitors (like Glycol) in choke and
kill lines.
Use the Choke Line Friction that was recorded
during the drill out and, if necessary, correct for
new mud weight.
BOP Equipment
Subsea Considerations
BOP Equipment
Subsea Considerations
MWN
MWO
12.0
164 psi
11.0
44
Todays Headlines
Instructions on
Presents
Blowout-Prevention
Equipment
Well-Control
Murchison
Drilling Schools
for
Operations
Rotary Helpers and
Derrickmen
Formation
fluids
entering
the hole
push mud
out.
30
40 50 60
20
LO
ADJUST
PADDLE
100
RETURN
MUD
FLOW
LO
HI
FLOW FLOW
HI
ADJUST
SMOOTHING
MUD
FLOW
ON
PADDLE
MOVEMENT
90
70
80
10
LO
MED
HI
FLOW-METER
PROPORTIONATE
READING
Laser Sensors
Loss
Gain
Loss
Gain
GAS DETECTOR
Check for broken lines and dirty
detector heads.
MAINTENANCE OF
VACUUM DEGASSERS
Check vacuum pump for proper oil
level and belt tightness.
Move float-control arm and valve to
ensure free travel.
Check for leaks in suction by looking
for air in discharged mud.
MAINTENANCE OF PUMP
DEGASSERS
Check pump inlet for buildup of mud solids
and lost circulation materials.
Inspect inlet screen for plugging.
Check all belts for tightness.
Inspect electrical connections.
TRIP TANKS
A trip tank can
automatically fill the hole,
or..
MAINTENANCE OF
TRIP TANKS
Check tank valves for easy
operation.
Check drillers readout panel for
accuracy.
10
ANNULAR BOP
WEEKLY MAINTENANCE OF ANNULAR BOP
SHOULD INCLUDE:
Picking up the jet sub and positioning it in the
lower part of the BOP and jetting out solids which
could include drill solids, barite and even cement.
Activating the Annular and making sure it will
open fully. Solids collected under the operator will
sometimes prevent the Annular from being fully
opened.
11
ANNULAR PREVENTERS
BASIC MAINTENANCE FOR
ANNULAR PREVENTER
Check all hydraulic lines for leaks.
Leaks should be repaired immediately.
12
ANNULAR PREVENTERS
BASIC MAINTENANCE
FOR DIVERTERS
Make sure there are no leaks
in the hydraulic control lines.
13
RAM BOPS
BASIC MAINTENANCE FOR
RAM BOPS:
Check daily for leaks in
hydraulic lines!
14
15
ACCUMULATOR SYSTEM
Accumulator maintenance
includes:
Checking daily for leaks in
hydraulic lines.
16
CHOKE MANIFOLD
All valves should be opened
and closed fully, and lubricated
if necessary.
CHOKE MANIFOLD
Be sure that it is securely
fastened down.
17
MUD-GAS SEPARATORS
Check mud and gas lines for
leaks.
If float is used, arm should be
lubricated.
DART
VALVE
type of
Inside
BOP.
18
INSIDE BOPS
19
20
Todays Headlines
The End
21
Day Eight
Review homework
Lost Circulation From Propagation Losses
ECD Drilling Technique
Underground Blowouts & Barite Plugs
Optimization & Bit Practices
Differential Sticking and Freeing Techniques
Kick-Off Plug
WellCAP Surface Review
Simulator Training (Volumetric & Lubrication)
Freeing Technique
Kick-Off Plug
All Day Eight Bonus
Homework is due today.
I. Introduction
II. Induced Fractures
III. Solving A Lost Circulation
Problem Due To Propagation
Losses (Not Just In Abnormal
Pressure)
Rock Integrity
Pore pressure
6,000
8,000
10,000
12,000
14,000
Lots of room
4,000
Depth (ft)
2,000
Narrow rangenot
much room for error.
16,000
10
11
12
13
14
15
16
17
18
MW (ppg)
Reaction time is less on a shallow well!
1. Vugular
2. Seepage (Matrix)
3. Fracture propagation losses (90% of time)
Matting Fibers
Sealing Cellophane Flakes
Bridging Walnut Hulls
Choosing Treatment
Layering
Creating
Immobile Mass
Example of Squeezing
Permeable Zone
Fracture
Propagation
Fracture
Propagation
Fracture Propagation
Given Data for Hydrostatic Packer, Equalization Point, and Hesitation Squeeze:
Example
TVD
Cas. Shoe
Hole Size
DS for Squeeze
MW
ECD
FCS
Pore Press.
Hydrostatic Packer
After
pulling out
of pill, prior
to squeezing
=
=
=
=
=
=
=
=
=
=
Overdisplacement can be
prevented by following the
treatment with sufficient light
fluid so that the total head when
the pumps are shut down is less
than the FCS. The drill string will
have a positive surface pressure
while squeezing . This column of
light fill (i.e. balancing water) is
referred to as a hydrostatic
packer because it acts to prevent
downward or upward fluid
movement.
MW MWE TVD
MW 8.33
14 13.8 12,500
LH O
441 ft
14 8.33
L H2O
or
%VolAnn
Cap Ann
Cap Ann Cap DP
%VolAnn
0.0473
73.6%
0.0473 0.017
Hydrostatic Packers
14 0.052
Mud = 8779 psi
P
TVD 0.052
8970
MWE
12,500 0.052
MWE 13.8 ppg
MWE
Hydrostatic Packers
23.5
0.017
PCsg 16 14 0.052
80
0.017
P 14 8.33 0.052
P 146 psi
PDP 146 81
PDP 65 psi
8.4
0.017
ECD Drilling
Definition of ECD:
The equivalent circulating density
is the effective mud weight on the
formation due to the total effect of
the mud weight plus the friction loss
in the annular space between the
pipe and the hole while circulating.
The pressure prorates up the annulus
and at the flow line the pressure is
zero.
10
ECD Drilling
ECD Calculations
MW
PV
YP
Q
POB
=
=
=
=
=
ECD Calculations
16 ppg
45 cp
25 lb/100 ft2, (too high)
330 gpm
200 psi
AV (DP Ann)
AV (DP Ann)
ECD Calculations
Q 24.51
(D H 2 - D DC 2 )
L YP
L PV V
PAnn
330 24.51
(8.52 - 6.52 )
Where:
PAnn
L
D
V
PV
YP
ECD Drilling
ECD Drilling
ECD Calculations
AV (DC Ann)
330 24.51
(8.52 - 52 )
ECD Drilling
AV (DC Ann)
Q 24.51
(D H 2 - D DP 2 )
AV (DP Ann)
Q 24.51
(D H 2 - D DP 2 )
ECD Drilling
=
=
=
=
=
=
ECD Drilling
ECD Calculations
ECD Calculations
PAnn
L YP
L PV V
PAnn
L YP
L PV V
PAnn
PAnn
700 25
700 45 270
11
ECD Drilling
ECD Drilling
ECD Calculations
ECD Calculations
ECD MWH
TVD 0.052
528
ECD 16
0.052
12,
700
ECD Drilling
ECD Drilling
0.1 YP
ECD MWH
0.1 25
ECD 16
8.5 5
0.1 YP
ECD MWH
ECD Drilling
ECD Drilling
YP
ECD MWH
11.7(DH DDP )
25
ECD 16
11.7(8.5 5)
12
ECD Drilling
PRed
MWN MWH
PRed
MWN MWH
MWN:
New mud weight (ppg)
MWH:
Mud weight in the hole (ppg)
PRed:
Reduction in overbalance pressure (psi)
DepthKick: Depth of kick (feet) *
* MWRed must be based on kick zone depths.
150 psi
MWN 16
12,
000
0.052
ECD Drilling
YP 0.1
ECD N MWN
(DH DDP )
ECD Drilling
YP 0.1
ECD N MWN
(D
H D DP )
16 0.1
ECD N 15.8
16.3 ppg
(8.5
5)
After cutting MW
& Lowering YP
ECD Drilling
Before cutting MW
& Lowering YP
ECD Drilling
ECD Drilling
P G TVD
P: Change in pressure
G: Change in gradient (ECD ECDN)
TVD: True vertical depth
13
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
MWTOH
MW
=
=
MWN
MWB
DepthKick
=
=
DepthShoe
ECD Drilling
MWTOH MWN
ECD Drilling
Overbalance Check:
The overbalance check is to make sure that the
numbers add up to the same pressure at the kick
zone.
(12,000 8,000)
14
ECD Drilling
ECD Drilling
Overbalance Check:
Overbalance Check:
ECD Drilling
ECD Drilling
Choice 1:
DShoe MW 0.052
8,000 16.0 0.052 = 6,656 psi
Choice 2:
6,656
- 6,573
83
DShoe MW 0.052
8,000 15.8 0.052 = 6,573 psi
ECD Drilling
ECD Drilling
15
ECD Drilling
ECD Drilling
Two Choices
May be simpler, but it may not be as good as
spotting heavy mud.
The 15.8 hydrostatic is going to protect it better.
In either case, there is 200 psi overbalance at the
kick zone, which is required to make the trip safely.
ECD Drilling
YP =
40 lbs/100 ft2
MW =
9 ppg
DH =
6
DDP =
3.
TVD =
7,000
Horizontal Section = 2,000
ECD Drilling
ECD Drilling
ECD Drilling
L YP
225 D
psi / ft sec t. length
ECD (ppg)
TVD 0.052
PAnn
16
ECD Drilling
L YP
225 D
(1) 40
P psi / ft
0.071
225 (6 3.5)
PAnn
ECD (ppg)
ECD (ppg)
ECD Drilling
H. Length
MW in Hole
P (psi/ft.)
ECD (ppg)
9 ppg
0.071
0.00
9.0
500
9 ppg
0.071
0.09
9.1
1,000
9 ppg
0.071
0.19
9.2
1,500
9 ppg
0.071
0.29
9.3
2,000
9 ppg
0.071
0.39
9.4
2,500
3,000
9 ppg
9 ppg
0.071
0.071
0.49
0. 59
9.5
9.6
1.
PAnn
ECD Drilling
L YP
225 D
2.
ECD (ppg)
ECDHS
3.
psi/ft sect. length
ECD HS MW ECD
TVD 0.052
ECD Drilling
MD: 7,500 feet
TVD:7,000 feet
DDP: 3 inches
DH: 6 inches
17
0.071 2, 000
0.39
7, 000 0.052
ECD Drilling
ECD HS MW ECD
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
MDMax:
PAvail:
Pfriction:
18
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
ECD Drilling
19
Underground Blowouts
Underground Blowouts
Causes of UGBO
Underground Blowouts
Causes of UGBO
Underground Blowouts
Prevention
1. Plan kick-off
professionally.
2. Establish good safety
barriers in the old hole
section before side
tracking.
3. Re-establishing communication
with an old wellbore (related to
sidetrack operations).
Prevention
Drill hole carefully, with
getting a good cement job on
casing as a high priority.
Plan cement job carefully,
using all drilling and logging
data.
Implement the cement plan,
with emphasis on mixing
cement at correct design
weight.
Avoid surge that exceeds FCS
(LOT) when running casing.
Underground Blowouts
Underground Blowouts
Causes of UGBO
4. Production leaks.
Holes in casing and/or tubing could charge up
exposed hole and cause and UGBO.
Poor cement jobs on casing string(s) could
also contribute to UGBO.
20
Underground Blowouts
Underground Blowouts
200
sx.
300
sx.
0.935
5.10
5.30
18.9
20.0
1.039
3.70
6.43
15.6
21.0
1.090
3.20
6.95
14.4
22.0
1.142
2.75
7.50
13.3
Underground Blowouts
400
sx.
18.0
Underground Blowouts
Barite settling
Water
Barite
Thinner
(Sometimes a
polymer is used.)
Slurry
Slurry
Water Sacks
100
Density Gradient gal/sx. Barite sx.
bbl/slurry
Lb/gal. psi/ft.
Underground Blowouts
Optimization
21
Optimization
Optimization
I. Direct
II. Indirect
Optimization
Optimization
Variables Used In
Optimization
1. Mud
2. Hydraulics
3. Bits
Drilling Optimization
Procedure
Optimizing Approach
22
Optimizing Approach
Controllable
Mud
Hydraulics
Bit Type
Weight-RPM
Rig
Alterable Variables
Mud
Type
Solids Content
Viscosity
Fluid Loss
Density
Uncontrollable
Formations to be Drilled
Depth
Schemes For
Hydraulic Programs
Major Variables
Affecting Drilling Cost
1. Mud System:
Type Solids
Solids Volume
Properties For
Hole Stability
Drilling Variables
Unalterable Variables
Characteristic hole
Weather
problems
Location
Water availability
Rig Conditions
Formation to be
Rig flexibility
drilled
Corrosive borehole gases
Crew
efficiency
Bottom-hole temperature
Depth
Round-trip time
Rock properties
Hydraulics
Pump Pressure
Jet Velocity
Circulating Rate
Annular Velocity
Bits
Bit type
Weight-on-bit
Rotary speed
Major Variables
Affecting Drilling Cost
23
Post Appraisal
Bits
1.
2.
3.
4.
5.
6. Bit Grading
Bit Design
Bit Design
24
Bit Classification
Bit Classification
Formation Type
Bit Name
IADC
Recommended WOB
RPM
Type
GTX-G1
HC404
115
M233
200-80
350-60
STB
PDC
Soft-to-Medium
MSS
131
60-130
STB
HC604
M223
350-60
PDC
Medium
MS-X
216
50-110
STB
HC605
M323
350-50
PDC
Medium Hard
MXL-55
637
90-150
IRC
HC407
M333
350-60
PDC
Hard
HS
HC309
311
M443
40-80
350-50
STB
PDC
Extremely Hard
MX-89
837
80-40
IRC
HC6127X
M423
350-50
PDC
Bit Types
Bit Classification
Bit Types
PDC Bits
60% of all footage is
now being drilled with
PDC bits.
25
Bit Types
Bit Types
Bit Selection
Bit Selection
Bit Selection
Bit Selection
Bit Selection
Formation Evaluation:
Determine what kind of
formations will be drilled.
Is this a shale formation? Look
at offset logs.
Look at hardness within
formation.
The Gamma Ray and Neutron
Density Logs help identify the
rock.
Look at offset bit records
26
Bit Selection
Bit Selection
Bit Type
API Series
Medium
Hard
>50% Shale
<%50 Shale
Hard Sand
& Limestone
<30% Shale
Dolomite/
hard limestone and
chert
Mill Tooth
Series
Series
Series
1
2
3
Inserts
Series
Series
Series
Series
6
7
8
Bit Selection
Bit Selection
Well H
4&5
& PDC
Bit Selection
Well H
Bit Selection
27
G
C
S
L
yrits
h
A
d
S
lean
im
d
alyS
eston
h
iteD
olm
O
h
alt
S
1. Drill-Off Test
2. Pump-Off Force
Pump-Off Force is the hydraulic force under
the bit that that attempts to pump the bit off
the bottom. It reduces the effective weight on
the bit.
Pump-Off Force is very important with certain
types of bits (diamond bits, PDC bits)
2. Pump-Off Force
2. Pump-Off Force
Procedures:
a. Take off-bottom pressure
reading
b. With bit about 4 inches
off bottom, slack off
slowly
c. Measure change in
pressure (P) and
corresponding weight.
Procedures:
d. Plot on plain graph
paper.
e. At point of deflection
(slope change) record P
and weight on bit.
28
2. Pump-Off Force
2. Pump-Off Force
Procedures:
f. Calculate pump-off area:
Procedures:
Calculate true weight on bit for any given weight
indicator weight, i.e..,
AE
W.O.B.
P
2. Pump-Off Force
$ / Ft.
T time
Trip Time Rotating Time Total hourly Rig cos t * Bit Cost
T2
Footage Drilled
T2
B2
R1
t
C1
T1
B2 R1 (t)
F
C1 1 - R1
T1
29
PBit (Q)
1346 (OD) 2
Advantages
1. Less Hole Surge
2. Less shale problems
3. Less WC problems
4. Take advantage of ECD drilling.
5. Reduced hole problems related to limber hook-ups.
6. Better hole temperature stability because of more
on bottom time.
NOTE:
The stabilization
required for
effective diamond
bit drilling will
give a more
effective hole
diameter.
30
Disadvantages
1. Mud solids problem created by finer cuttings.
2. Cuttings are smaller, making paleo slides more
difficult.
3. More rotating wear on casing because of higher
RPM (if downhole motors cannot be used).
4. More wear on drilling assembly.
Disadvantages
5. Requires a better drill string because diamond
bits are very RPM responsive. Better drill string
supervision is required.
6. Many rigs would require an independent rotary
drive to give adequate horsepower for efficient
diamond bit drilling rotating.
Bit under-gauged
3. Prior To Drilling
a. Circulate hole clean and take three off bottom
pressure and pump stroke readings.
b. Wash to bottom without rotating and apply about
5,000 lbs. to insure bit is on bottom.
c. After cleaning bottom, pick up two or three feet
and rotate to bottom and gradually apply weight.
Build nest.
d. Make sure hydraulics comply with manufacturers
recommendations.
31
3. Prior To Drilling:
Bit Grading
Bit Grading
Bit Grading
Bit Grading
Bit Grading
32
Bit Grading
Stuck Pipe
Stuck Pipe
Stuck Pipe
4. Permeability and
length of zone open
5. Drill string design
(clearance, etc.)
Stuck Pipe
Stuck Pipe
33
Stuck Pipe
FDif
Where:
FDif
Stuck Pipe
Stuck Pipe
Where:
DCOD = Drill Collar Outside Diameter, in.
Stuck Pipe
Stuck Pipe
Stuck Pipe
Example:
Lower equivalent mud weight 9 points,
(from13.5 to 12.6 ppg). TVD 9,934 Ft.
34
Stuck Pipe
Step 1:
Step 2:
POB (psi)
POB (psi)
Vol UTF =
+
465
465
Vol UTF =
+
100.7 bbl
(13.5-8.5) 0.052 20 (13.50.052) 58.82
Where:
VolUTF:
VolAnn:
POB :
G:
G M:
CapDP:
Where:
POB :
MWH:
MWE:
TVD:
Stuck Pipe
VolFB POB
FPE = TVDG M
VolFBM
11.3465
Where:
FPE:
Estimated Formation Pressure (psi)
TVD: True Vertical Depth (ft)
GM:
Gradient of Mud
POB : Pressure Overbalance (psi)
VolFB: Volume that flowed back when pipe came free
VolFPM: Maximum barrels of seawater or oil to be flowed back
Stuck Pipe
Step 1:
Stuck Pipe
Example:
MD:
MW:
DP:
DC:
Dh:
MWF:
Stuck Pipe
Step 3:
Where:
PBBB :
VolUTF:
VolAnn:
G:
Stuck Pipe
Where:
G :
Difference in Fluid Gradients (psi/ft)
MW: Mud Weight (ppg)
MWF: Mud Weight of fluid being spotted
35
Stuck Pipe
Step 2:
L DPO
Step 3:
PSur
500 psi
=
G
0.338 psi/ft
VODC =
Stuck Pipe
Step 4:
DCID
L DC
1029.4
2.81252
VDCI =
844 ft = 6.486 bbl
1029.4
VDCI =
Where:
VDCI:
DCID :
LDC:
VODC = 24.60
Where:
VDPI:
CapDP :
LDP:
CapHW:
LHW:
VTotal:
VDPI =
Stuck Pipe
- 6.5
1029.4
DC
DCVi =
DPVi =
Stuck Pipe
Step 6:
Pumping of oil into Drill Pipe. Check Point #1a.
Summary Oil
Required
VODC = 24.60
VDCI = 6.5
VDPI = 25.1
VTotal = 56.24
Stuck Pipe
Step 6:
Strokes to pump oil from tank. Check Point #1b.
VTotal
W (ft) L (ft) 0.0148 (factor)
56.24 bbl
Tank Inches =
Check
20 6 0.0148 (bbl/in)
VTotal
P.O. bbl/stk
56.24 bbl
Stk =
477 stk
0.118
a. Tank Inches =
VDCI = 6.5
1a
1b
1c
2a
2b
- DCOD
1029.4
Summary Oil
Required
DCVo = 24.60
Step 5:
VDPI = Cap DP L DP + Cap HW L HW
Summary Oil
Required
8.5
Where:
VODC:
Dh :
DCOD:
LDC:
VODC =
Where:
LDPO:
PSur :
G:
Stuck Pipe
Stk =
Points
= 31.5
=
=
=
=
Where:
Stk:
Strokes to pump oil from tank
VTotal: Total Volume
P.O.: Pump Output (bbl/stk)
36
Check Points
1a = 31.5
1b = 477
1c =
2a =
2b =
Stuck Pipe
Step 6:
Pumping of oil into Drill Pipe. Check Point #1c.
PDP =
PDP
VTotal
G
Cap DP
56.24
=
0.338
0.017
Step 7:
Pumping of oil to bit. Check Point #2.
a. Pump Strokes
Check Points
1a = 31.5
1b = 477
1c = 1118
2a =
2b =
V
L - Total Cap DP VDCI
DP Cap
DP
Stk
P.O. bbl/Stk
56.24
12,225' 0.017 6.49 bbl
0.017
Stk
0.118 bbl/stk
Total Volume
Drill Pipe Pressure with oil in Drill Pipe.
Capacity of Drill Pipe (bbl/ft)
Stuck Pipe
Step 7:
Pumping of oil to bit. Check Point #2.
1. Read DP pressure.
2. Start circ. WH through
trip tank. Monitor trip
tank and DP pressure.
3. Torque DS (RH Torque).
4. Slack off weight.
Stuck Pipe
a. Strokes
Check Points
1a = 31.5 in
1b = 477 stk
1c = 1118 psi
2a = 1340 stk
2b = 1275 psi
3a = 209 stk
3b = 500 psi
VODC bbl
P.O. bbl/stk
24.60
Stk=
= 209 strokes
0.118
Stk =
Check Points
1a = 31.5
1b = 477
1c = 1118
2a = 1340
2b = 1275
Stuck Pipe
Stuck Pipe
Step 9: Interpretation
a. What if pressure is 500 psi?
Write down what you see!
Step 8:
Pumping of oil in place. Check Point #3.
Action List With
Oil In Place
Check Points
1a = 31.5
1b = 477
1c = 1118
2a = 1340
2b =
Step 8:
Pumping of oil in place. Check Point #3.
(V - V
PSurf = L DC + Total DCI G
Cap DP
56.24 - 6.5
PSurf = 844 ft +
0.338 psi/ft
0.017
Stuck Pipe
Check Points
1a = 31.5 in
1b = 477 stk
1c = 1118 psi
2a = 1340 stk
2b = 1275 psi
3a = 209 stk
3b = 500 psi
1. Pressure is as planned
2. Hole volume (OH) is as planned
3. Good sign, probably will get free
4. Watch for volume loss in trip tank
and a DP pressure increase this
would make it an excellent sign.
37
Stuck Pipe
Step 9: Interpretation
b. What if pressure is 600 psi?
Step 9: Interpretation
c. What if pressure is 400 psi?
1. Pressure is 100 psi lower than planned.
2. Shorter mud column (lower U-tube
pressure)
3. Longer oil column.
4. Restricted annulus (stretched oil
column out).
5. Bad sign.
6. Alert Back-off man.
7. Organize fishing.
1029.4
Where:
VReq: Volume of oil required to cover the collars
Stuck Pipe
0.338
Stuck Pipe
Kick-off Plug
Considerations
Weighted-mud uses
1. Sensitive overbalance
2. Slim hole (6 hole or less)
H=
Kick-off Plug
Considerations
2. Use mixing-sub on
bottom of setting string
to minimize
contamination. DO
NOT USE OPENENDED PIPE.
Kick-off Plug
Considerations
38
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Kick-off Plug
Considerations
D B P C M TB D
CT
DBP
=
N
=
CMTBD =
C
=
T
=
Kick-off Plug
Considerations
Kick-off Plug
Considerations
39
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Example:
Given Data:
DP = 5, XH, S
0.017 bbl/ft
Dh = 12.75
(caliper)
Bottom of plug
Top of plug
Cement plug
Mud
POB
Cement Weight
Cement yield
Mix H2O
-12,700
-12,400
-300
-14 ppg
-200 psi
-16 ppg
-- 1.35 cu ft/sk
-5.0 gal/sk
Technical Calculations
(12.75)2 0.7854
144
266
CReq = 266 cu ft or
= 47.5 bbls
5.6
266 cu.ft.
1.35 cu.ft./sk
Mix H 2 0 =
Dh 2 0.7854
144
C Req = 300
Technical Calculations
Sacks =
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Kick-off Plug
Considerations
40
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Technical Calculations
Kick-off Plug
Considerations
Technical Calculations
N
)
C+T
47.5 bbl
)
(0.017+0.1336) bbl/ft.
DBP = 12,385 ft
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Technical Calculations
Technical Calculations
Balancing Water
Balancing Water
POB Useable
Lead H 2 0 Len. =
(MW - H 2 0W ) 0.052
Lead H 2 0 Len. =
(Dh 2 - Dp 2 )
1029.4
(12.752 -52 )
Vol. Lead H 2 0 = 339 ft.
1029.4
100 psi
(14-8.33) 0.052
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Technical Calculations
Description
of Operation
Balancing Water
1. Pump
Lead H2O
Surface Pressure
U-Tube
Considerations
U-Tube
45.3
(14 8.33)0.052
0.017
786
Dynamic
1,586
Comments
Circ.Press.
= 800
41
Length G DP Pressure
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Description
of Operation
1. Pump
Lead H2O
2. Mix
cement
U-Tube
Considerations
Surface Pressure
U-Tube
Dynamic
45.3
(14 8.33)0.052
0.017
786
47.5
(16 14)0.052
0.017
500
1,586
1,300
Comments
Circ.Press.
= 800
What if? 100
psi high
MWcmt=15.3
Kick-off Plug
Considerations
Kick-off Plug
Considerations
Vcmt bbls
LCmt ft =
DPCap bbls/ft
47.5
LCmt ft =
= 2,794 ft
0.0170
PU psi
CW CWP
LCmt ft 0.052
100 psi
CW 16
2,794
Ft
0.052
Kick-off Plug
Considerations
Kick-off Plug
Considerations
2. Mix Cement.
Circ.Press. = 800
U-Tube
= 500
Dynamic = 1,300
Description of
Operation
Surface Pressure
U-Tube
1. Pump
Lead H2O
45.3
(14 8.33)0.052
0.017
786
2. Mix
cement
47.5
(16 14)0.052
0.017
500
5. 8
0.2948
0.017
600
3. Pump TI
Spacer
42
U-Tube
Considerations
Dynamic
1,586
1,300
1,400
Comments
Circ.Press.
= 800
What if? 100
psi high
MWcmt=15.3
Kick-off Plug
Considerations
3. Pump TI Spacer
Circ.Press
= 800
U-Tube
= 600
Dynamic
= 1,400
Description of
Operation
Kick-off Plug
Considerations
2. Mix
cement
47.5
(16 14)0.052
0.017
500
5. 8
0.2948
0.017
600
1,400
600
1,400
Description of
Operation
(12,700-5,800).017 =
117.3
Comments
Circ.Press.
= 800
What if? 100
psi high
MWcmt=15.3
Kick-off Plug
Considerations
Surface Pressure
U-Tube
Considerations
U-Tube
Dynamic
786
1,586
2. Mix
cement
47.5
(16 14)0.052
0.017
500
1,300
3. Pump TI
Spacer
5 .8
0.2948
0.017
* NOTE:
When DP side of U-Tube
reverses, open the by-pass
line. Slow mud displacement
to the point of keeping up
with cement U-Tubing to
balance point. When mud
comes out of by-pass line, the
plug is balanced.
1,300
45.3
(14 8.33)0.052
0.017
5. Pump to
Balance Point.
Kick-off Plug
Considerations
1,586
1. Pump
Lead H2O
4. Pump to
bottom of DS
(not out)
Dynamic
786
4. Pump to bottom of DS
(not out)
Circ.Press.= 800
U-Tube = 600
Dynamic = 1,400
U-Tube
45.3
(14 8.33)0.052
0.017
4. Pump to
bottom of DS
(not out)
45.3
47.5
5.8
5,800 ft
0.017 0.017 0.017
Surface Pressure
U-Tube
Considerations
1. Pump
Lead H2O
3. Pump TI
Spacer
Kick-off Plug
Considerations
600
1,400
(12,700-5800).017 =
117.3
600
1,400
UTubing
Comments
Circ.Press.
= 800
What if? 100
psi high
MWcmt=15.3
Plug
balanced
Kick-off Plug
Considerations
5. Pump to Balance Point
U-Tube = 0
Dynamic = U-Tubing
Plug balanced
43
Kick-off Plug
Considerations
GIVEN:
DP:
5, 19.5, XH, Grade S, 0.0170 bbl/ft
DC:
6 213/16 720, 0.00768 bbl/ft
Shoe: 9, 47 lb/ft, 9000
L.O.T.: 17.4 ppg
Casing Burst: 8,150 psi
Pump Output: 0.112 bbl/stk
Slow Rate Pressure (SRP): 600 psi @ 25 spm
SIDPP: 650 psi
SICP: 1100 psi
Papplied
(TVDShoe ) 0.052
1125
MWE LOT 15
17.4
9000 0.052
0.052TVD
PHydro = MW0.052TVD
Papplied
MWEquiv MWhole
(TVD of interest) 0.052
1100
MWEquiv 14
9000 0.052
650
MWK (ppg) = 14 +
0.05212,720
MWK (ppg) = 15
44
300
15
10,000 0.052
MWNew 15.6
300
MWe 15
2,000 0.052
17.9
300
MWe 15
6,000 0.052
16.0
300
MWe 15
10,000 0.052
15.6
FCP = SRP
MWK
MWO
15
FCP = 600
14
FCP = 643
See Workbook, Well Control, page 41, Formula 8.
Note: Final
Circulating pressure is
nothing more than the
slow rate pressure
corrected for kill mud
weight.
VOL DS =(0.01712,000)+(0.00768720)
45
STK DS =
Time DS =
STK DS =
209.5
0.112
Time DS =
1871
25
TimeDS = 75 minutes
Size kick
Percolation
Reaching ICP
Stroke Fluctuation
Method of closing in well
(b) False
YES!
It will increase.
46
a) Increase
b) Decrease
SPM 2
P2 =P1
SPM1
35
P2 800 1089
30
Qty
Size
Rating
Type
13
10,000
GK Hydril
29.35, 20.96
Close/Open
13
10,000
U CIW Ram
5.80, 5.45
10,000
F CIW CL Valve
0.59, 0.59
47
Close
Open
29.35
11.60
0.59
20.96
10.90
0.59
41.54
32.45
(1)
(2)
(1)
Hydril
Ram
CL Valve
Subtotal
2.0
23. The sizing factor of ________,
based on a
3000-psi accumulator with a 1000-psi nitrogen
precharge and a 1200-psi minimum discharge,
is used to calculate minimum recommended
accumulator volume (nitrogen + fluid).
(a) 1.5
(b) 2.0
(c)2.5
(d)3.0
Total
(a) 11 bottles
(b) 12 bottles
(c) 22 bottles
(d) 23 bottles
Short bit runs require trips and both trips and heavy
water dilutions will alter the flow line temperature.
(a) True
(b) False
48
(a)
(b)
(c)
(d)
G M MW 0.052
G M 15.0 0.052 0.78
Slug plan
Trip plan
Monitor plan
Supervision
SPR:
SRP:
SIDPP:
SICP:
MW:
MWK:
DS Stks:
30 spm
600 psi
650 psi
750 psi
14.0 ppg
15.0 ppg
1871
Strokes
DPPress
1250
187
1189
374
1129
561
1068
748
1007
936
947
1123
886
1310
825
1497
764
1684
704
1871
643
(a) True
(b) False
(a)
(b)
(c)
(d)
(a) True
(b) False
49
8 inch diameter
10 inch diameter
12 inch diameter
14 inch diameter
BSEE Rules:
Surface is 10 inches.
Subsea is 12 inches.
(a) True
(b) False
(a) true
(b) false
____Can
be locked in a closed position.
B.
____Can
be closed around any size tool joint.
A.
____Can
support the weight of the drill string.
B.
____Uses
a closing pressure of 1,500 psi.
C.
YES!
50
(a) flange
(b) bonnet seal and ram packer
(c) body of BOP
YES!
I. INTRODUCTION
A. Give two reasons why blowout preventers for
floating drilling rigs are installed on the ocean
floor.
I. INTRODUCTION
B. What do both land based and subsea BOPs have
in common?
1.
2.
3.
4.
I. INTRODUCTION
D. Drilling-vessel heave can cause:
I. INTRODUCTION
C. What is the primary difference between surface
and subsea BOPs?
1.
2.
3.
4.
1.
2.
3.
4.
51
I. INTRODUCTION
E. Which device helps the driller control the
weight-on-bit from a constantly moving vessel?
1.
2.
3.
4.
I. INTRODUCTION
F. In ultra-deep water with heavier muds, the
hydrostatic difference between the mud and
seawater must be considered when testing BOPs
to nominal pressure.
Lower riser.
Telescopic joint.
Motion compensator.
Diverter.
1. True
2. False
1. True. For example, with a 15.0 ppg and seawater
that is 8.7 ppg, at a water depth of 10,000 feet, there is
3,276 psi difference that must be accounted for.
I. INTRODUCTION
G. While hanging off is recommended to prevent
trapped gas in the BOP and to protect the
element in the annular, on dynamically
positioned (DP) vessels there is a third
consideration. What is it?
_____________________________________
In the event of station keeping problems, already being
hung off places you in the best position possible for an
emergency disconnect. Therefore, many operations require
hanging off in all well control situations.
Conductor pipe.
Guide base
Surface casing
All of the above.
Wellhead.
Casing.
Stack.
Riser.
52
5M
13
CH
R
A
1. True.
2. False.
IV.C
blowout preventer
1. Annular
____________________
can be closed around any
size drill pipe or casing.
53
IV.C
IV.C
Wellhead is the
2. The __________
foundation for the BOP
stack or production
tree.
IV.C
IV.C
4. The _____________
Flex Joint
allows for the lateral
(side to side) movement
of the marine riser.
5. The ______________
Control Pods
are the mating portion
of the subsea hydraulic
remote-control
mechanism.
IV.C
IV.C
Hydraulic Connector
6. The _________________
fastens the marine riser to
the BOP stack by remote
control.
7. The _______________
Pipe Rams
are sometimes used to
support the drill string in
a subsea operation.
54
IV.C
IV.C
Riser Pipe
8. The _______________
conducts drill pipe down
to, and drill fluid up
from the well.
IV.C
IV.C
Guide Base
11. The Temporary
__________________
is the first piece of
guidance equipment to
touch bottom.
10. _______________means
Tensioner lines
by which a constant pull
is maintained on the riser
pipe despite vessel
movement.
1. True
2. False
55
If an annular is run as
part of the riser
package, it is run
between the hydraulic
connector and the ball
(or flex) joint.
1.
2.
3.
4.
5.
Hydraulic connector.
Flexible joint.
Hoses of pipe for kill and choke lines.
Annular preventer.
Pipe ram.
16 inch O.D.
17 inch I.D.
18 inch O.D.
20 inch I.D.
Weld on clamps.
Threaded box and pin with torque lock.
Back flange with hinged locks.
Mandrel and box with mechanical lock.
4. All of these.
C. In deep water, _______________
provides a
practical means of increasing riser pipe
buoyancy.
1.
2.
3.
4.
56
VII. TELESCOPIC
JOINT, SUBSEA
DIVERTER
SYSTEM
1. outer
B. The ____________
barrel of a telescopic joint
remains fixed to the riser pipe and contains the
resilient packing elements for the pressure seal.
1.
2.
3.
4.
1. 66,000 lbs
3. 24,000 lbs
outer
inner
middle
all of these
2. 40,000 lbs
4. 15,000 lbs
VIII. RISER
TENSIONERS,
GUIDELINE
SYSTEMS
57
1. Hydraulic pressure
2. Air pressure
3. Counter weight
4. All of these
1. tensioner
2. guideline
3. both of these
1.
2.
3.
4.
3. Shuttle valve
C. A_________________
automatically switches
access to a function from one pod to another
should one of the pods fail
1. Accumulator valve
3. Shuttle valve
Electrically (Electrohydraulic)
2. __________________________
58
2. Redundancy valve
4. All of these
P1V1 P2 V2 or V2 =
V2
P1V1
P2
59
Day Nine
Review Homework
Gas Cap Drilling
Gas Cap Lost Circulation
Squeeze Cementing
Workover & Completions
MDS Final Test
Lost Circulation
Propagation Losses
& Hydrocarbon
Workshop
Gas Cap
Drilling
I.
Many exploration
wells are positioned
on the top of anticline
reservoirs so that
maximum geological
information is
achieved from the
drilling process.
This includes:
Mud and wire line
logging.
DST Responsibility
Stationary Rig
DST
Floating Rig
Drill String
Packer
See Drilling Manual, Drill Stem Testing Chapter, page 3.
Drill String
Packer
A-B
B
C
C-D
D
E-F
F
G
H
H-I
Going in hole
Packer seated, tester valve opened
Mud pressure relieved, formation pressure buildup starts.
Initial closed-in pressure build up curve.
Auxiliary valve opened.
Flowing pressure curve.
Closed-in pressure valve closed.
By-pass opened.
Packer unseated
Coming out of hole
Abnormal:
Well 311
M.I.S.,
Iran
Drilling and Well
Control Training
Adequate
pressure
overbalance
must be
planned.
FP POB
TVD 0.052
MW
MW
FP POB
TVD 0.052
MW
5, 400 200
8, 000 0.052
MW = 13.5
At 9,000 Depth
Depth
(feet)
FP (psi)
At 9,500 Depth
8,000
5,400
8,500
5,450
9,000
5,600
9,500
5,832
Sometimes a formation
pressure is given on a
world geological map for a
water aquifer or water
table.
PHydro
(psi)
POB
(psi)
PF (psi)
MWF
(ppg)
200
At 9,500 Depth
POB (PHydro FP )
Depth
(feet)
FP (psi)
PHydro
(psi)
POB
(psi)
8,000
5,400
5,616
200
8,500
5,450
5,967
517
9,000
5,600
6,318
718
9,500
5,832
6,669
837
PF (psi)
MWF
(ppg)
PF (k(s FP ) FP )
MWF
PF
0.052 TVD
Where:
PF
=
MWF =
k
=
s
=
FP
=
TVD =
At 8,000 Depth
At 8,000 Depth
PF (k(s FP ) FP )
MWF
PF
0.052 TVD
MWF
5842
0.052 8000
MWF = 14 ppg
Depth
(feet)
FP (psi)
PHydro
(psi)
POB
(psi)
PF (psi)
MWF
(ppg)
8,000
5,400
5,616
200
5,842
14.0
8,500
5,450
5,967
517
5,968
13.5
9,000
5,600
6,318
718
6,178
13.2
9,500
5,832
6,669
837
6,455
13.1
More importantly,
when fractures are
cemented as the well is
being drilled, any new
lost circulation that is
encountered will
always be below the
bit.
ABC
Exploration Corporation
One of the
cardinal rules
of drilling is to:
Always keep
the problem
below the bit!
Production
Reservoir
Engineering
Exploitation
Geology
Reservoir
Engineering
Exploitation
Geology
Drilling
ABC
Exploration Corporation
Production
Drilling
10
B. Rotating Head
Considerations for using a
rotating head start when
the braden-head is
installed.
It is essential to have the
braden-head and all other
spools level and properly
aligned.
B. Rotating Head
With any misalignment,
the rotating heads cannot
be used properly.
The stripping element in a
rotating head will not last
if there is any
misalignment.
11
B. Rotating Head
The stripping element is
used while drilling.
When tripping, the
stripping element is set
back on the first stand
that is pulled out of the
hole.
B. Rotating Head
Spacing below rotary beams
is an important consideration
on some rigs.
The rig must have a proper
sub-structure and spacing to
build the wellhead and the
stack with the rotating head
on top.
12
13
E. Choke Manifold.
A header is
provided with the
separator to take
the flow from
adjustable chokes
and other chokes
or from the bypass
line on the choke
manifold.
E. Choke Manifold.
When the BOP is
closed, all mud
and fluids are
diverted through
the choke line to
the choke
manifold.
Choke Manifold
E. Choke Manifold.
The fluids are
diverted from
the choke
manifold to
either the mud
gas separator or
to a burning pit.
E. Choke Manifold.
The choke
manifold has both
manual and
hydraulic valves.
The choke
manifold is used to
hold proper back
pressure.
E. Choke Manifold.
One of the most important considerations
for the choke manifold is that the pressure
rating of all the
valves needs to
be uniform
throughout the
entire manifold.
E. Choke Manifold.
If working around
sour gas reservoirs,
choke manifolds
must be properly
stress relieved to
withstand that
environment.
14
15
16
G. Trip Tank.
A trip tank is
necessary because
keeping pump
strokes with a
triplex pump is not
accurate, because of
the supercharger.
G. Trip Tank.
A trip tank should be
used to pull out and to
go in the hole when
tripping to keep up
with metal
displacement.
17
18
J. Cementing Manifold
and Lines.
This clears the cement
that possibly U-tubed
behind the drill string.
Cement Head
19
20
Len (ft)
G M MW 0.052
Where:
Len:
POB:
GM:
MW:
21
Length (ft)
Pressure Overbalance (psi)
Mud gradient (psi/ft)
Mud weight (ppg)
Len (ft)
Len (ft)
POB
GM
bbl
)
ft
VOL ANN
bbl
)
ft
(CasID 2 - DPOD 2 )
1029.4
(8.6812 52 )
1029.4
Where:
Vol:
Volume (bbl)
Len:
Length (ft)
VOLANN: Annulus Volume (bbl/ft)
CasID:
Casing Inside Diameter (inches)
DPOD: Drill pipe Outside Diameter (inches)
200
0.7
22
23
24
VCmt
VCmt
VCmt
LDp
CapDp
LDc
CapDc
Dp
Dp
25
Sacks (Sk)
Mix H 2 O
V cuft
Cement Yield Cuft / Sk
2. Sacks
2. Sacks
Sacks
V cu ft
Cmt. Yield cu ft / sk
Mix H 2 O
Mix H 2 O
716
Sacks
265
2.7
265 7
42
Mix H 2 O 44 bbls
26
27
Keep circulating
fluid across the
wellhead to keep
the fluid level
from dropping.
28
400
0
2
300
Min.
psi 200
100
0
14.5
Cumulative Volume
29
29
400
psi
0
2
300
Min.
200
100
0
14.5
29
Cumulative Volume
Vol.Bd
Csg shoe depth
Cap bbl / ft
DOI
20
8, 000 '
0.072
DOI 8, 278 ft
30
I.
II.
III.
IV.
Bradenhead
RTTS
Cement Retainer
Bridge Plug
a. Neat cement
b. Low WL cement
c. Lost Circulation cement
A. Walking Squeeze
B. Hesitation Squeeze
C. Combination
31
G 0.052
psi / bbl
G
DPCap
G: Gradient change
CW: Cement weight
MW: Mud weight
BPT SF (D Re t G)
0.052
3.0588
0.0170
Vol.Pumped
CSG UT
(C W - MW)0.052
DPCAP
100 psi
100
Vol
32.69 or 33 bbl
psi/bbl
3.0588
32
CSG UT
Vol.Pumped
(CW - MW)0.052
DPCAP
33
CSG UT
(14.5 -13.5)0.052 100 psi
0.017
200
33
300
66
400
99
500
132
600
33
34
1.
2.
3.
4.
5.
35
Temperature survey
Wireline bridge plugs
Wireline with rag
RTTS and retrievable bridge plug
36
37
Case History #1
Development well.
A 12 hole section was
being drilled below a 13
casing string.
The 13 casing string was
set through a shallow
dogleg.
MW was 11 ppg.
Case History #1
The losses were found in a hole in casing
at 1,037 feet.
A balanced plug was set across the
damaged casing.
The drill pipe was pulled above the plug
and the damaged casing was Bradenhead
squeezed with neat cement.
Case History #1
Archie (foreman):
I got her squeezed. Whats
the program now?
Case History #1
Drilling Supt.: The
program says to test the
squeeze with 11-ppg mud
weight equivalent. If it
holds, clean the bridge
plug, and finish drilling to
casing point. Then, pull out
and run 9 casing as
programmed.
Case History #1
This program sounded simple,
but the problem was that
Archie did not know how to
calculate a mud weight
equivalent.
I was on a well six months
ago that was similar to this.
We tested it to about 700 psi.
That ought to be about right.
Case History #1
They never reached 700
psi, because this is a 21-ppg
mud weight equivalent.
The damaged 13 casing
was set in a 9-ppg
environment.
38
Case History #1
Unfortunately, the
isolating bridge plug had
been set in worn casing.
When pressuring up, the
damaged casing broke.
Case History #1
Everything that was done
from that point on to
correct the problem was
done in open hole.
They hung a sign on it:
OPENED BY MISTAKE
and plugged and abandoned
the well.
Case History #1
Archie took the full brunt of
the mistake.
He was the low man on the
totem pole.
OPENED
By
MISTAKE
Case History #1
The Drilling Superintendent
should have been the one to
shoulder the responsibility.
He failed to communicate
clearly to Archie what he
needed to do.
Case History #1
How should the superintendent have given the order?
He should have done
the calculations
himself and given
Archie a number that
Archie could use.
Case History #1
The superintendent should have said:
Circulate 11.0 ppg mud into the casing above
the bridge plug and observe the well for losses.
Eleven pound mud would not have broken the
casing and they could have completed the well.
39
Case History #1
There are two ways to test a well.
Case History #1
The following formulas are used to calculate the
pressure to test (PT) and the mud weight equivalent
(MWE).
Case History #1
Hole in casing occurred while drilling with 11.0
ppg mud at 11, 200 ft.
The hole in casing was located @ 1037 ft (in
dogleg section).
The damaged casing was Bradenhead squeezed
with cement using water after setting the bridge
plug to isolate the 11.0 environment.
PT
)
0.052 D.O.I.
Case History #1
Two Ways To Test
1. Pressure (144 psi is difficult to read)
2. MW equivalent
PT = 144 psi
Case History #1
Two Ways To Test
1. Pressure (144 psi is difficult to read)
2. MW equivalent
Circulate 11.0 ppg mud above the bridge
plug and observe the well for losses.
Case History #2
Well was located
in Eloi Bay.
15 minute
helicopter ride.
3 hours by car
and boat.
PT
144
MWE MWH
MWE 8.33
11 ppg
0.052 D.O.I.
0.052 1037
40
Case History #2
They were using 18.5
ppg oil-based mud.
Depth was 21,400 feet,
below a 7 inch liner in
the 9 inch casing.
Case History #2
Casing had been set in a
16.0 ppg environment.
Hole in casing was
located at 9,250 ft.
Case History #2
A bridge plug was set
below damaged casing
to isolate the 18.5 ppg
environment.
After changing the mud
above the bridge to 16.0
ppg mud, the hole was
squeezed successfully
using a retrievable
packer.
Case History #2
The foreman (engineer
and consultant) called the
office:
It looks like we got her
squeezed. Whats the
program?
Case History #2
The Drilling Superintendent
told the engineer:
Case History #2
This is what the consultant did.
He put 1,500
PT
MWE MWH
pounds on top of
0.052
D.O.I.
This calculates to
MWE 16
weight equivalent.
MWE 19.1 ppg
41
Case History #2
The 19.1 ppg mud weight equivalent
broke the well down.
The consultant should have put 1200
pounds of pressure on the well.
Case History #2
The mud weight equivalent
for 1,203 psi is 18.5 ppg.
This is what the consultant
was asked to squeeze with.
PT
MWE MWH
0.052
D.O.I.
1203
MWE 16
18.5 ppg
0.052 9250
Case History #2
The problem was that the
engineer/consultant did not
know how to calculate mud
weight equivalent.
How should the
Superintendent in the office
have communicated with the
engineer on the well?
Case History #2
Im having a rough day at the office.
I ran the numbers and I got 1,200 pounds
of pressure for the 18.5 mud weight
equivalent.
Check my numbers for me and then test
the squeeze.
If it holds, then clean out the bridge plug,
condition the hole and tie back the liner to
overlap the hole in the casing.
When communicating
about squeezes and
testing, make sure that
there is no
misunderstanding.
Poor communication is
very costly in both time
and money.
Poor communication is
extremely dangerous.
Case History #2
If the Superintendent had communicated
this way, the Foreman could have checked
out the numbers and verified them.
If he didnt know how to calculate the
mud weight equivalent, he could have
used the 1,200 psi given by the Drilling
Superintendent.
42
1.
2.
3.
4.
5.
Squeeze Considerations
Squeeze Considerations
Squeeze Considerations
1.
2.
3.
4.
5.
3. RTTS Squeeze
a. Run RTTS. Set. Open bypass.
Spot H2O and check injection.
b. Open bypass. Mix and spot
cement in squeeze string using
back pressure. Close bypass and
squeeze.
c. Squeeze (clear tool) and test
after W.O.C.
Note: To prevent possible bypass leaks
(to top of packer) hold more pressure
on inside (csg.) than on squeeze string.
Squeeze Considerations
More pressure on
casing annulus than is
being used to squeeze
with on the drill pipe.
Liner Considerations
Liner Considerations
Temperature Design
43
Liner Considerations
Liner Considerations
4. Operating practices
Run liners carefully and keep up with metal
displacement.
Liner Considerations
Liner Considerations
L H2O
L H2O
LH2O = 7758 ft
Liner Considerations
Check:
7758 ft 0.052 8.33 ppg
(17,000 - 7758) 0.052 16 ppg
11, 050 19.23
MWE
12.5 ppg
17, 000
Squeeze Considerations
= 3,360 psi
= 7,690 psi
11,050 psi
44
L H2O
Squeeze Considerations
MW - 8.33
Check :
7758 ft 0.052 8.33 ppg 3360 psi
Note: LH set tools (champ) can be run with the liner and
squeezing done after primary cement job. Also pressure
can be held on liner lap while cement is setting.
1.
2.
3.
4.
5.
Squeeze Considerations
Squeeze Considerations
Hydraulic Fracturing
Hydraulic Fracturing
Hydraulic Fracturing
45
Hydraulic Fracturing
Hydraulic Fracturing
Squeeze Misconceptions:
1. Pancake Squeeze
Wont work because fractures are vertical,
not horizontal.
G as
360
O il
Hydraulic Fracturing
Squeeze Misconceptions:
1. Pancake Squeeze
Squeeze Misconceptions:
2. Policy Block Squeeze
If it aint broke dont fix it.
Block Squeeze as Policy is bad.
Hydraulic Fracturing
Hydraulic Fracturing
Squeeze Misconceptions
4. You should always Put it away, Since you
have it mixed.
What will this do to the pay zone?
Hydraulic Fracturing
Cmt grains 60
6 60
360
Md (perm.) 360 2
129,600 Md
46
47
Production Squeezing
Through Perforations
Production Squeezing
Through Perforations
Production Squeezing
Through Perforations
Step 1:
Example:
Perforations:
7665 - 7680
Packer:
7625
Tubing:
2.375, 0.00387 bbl/ft
Form. Frac. Press.: 4982
Max Allow. Press.: (4982-300) psi/sf = 4682 psi
Initial Surf. Press. (ISP): 350 psi
Squeeze fluid:
Water (8.33 ppg)
Cement Weight:
15.6 ppg
Cement Yield:
1.18 cu ft/sk Type H
LCMT
LCMT
Max ISP
D FW
0.052
CW FW
4682 350
7625 8.33
0.052
15.6 8.33
= 2,722 ft
Production Squeezing
Through Perforations
Production Squeezing
Through Perforations
Step 2:
Step 3:
Sacks =
psi / bbl
Sacks =
psi / bbl
Sacks = 50
CW - FW 0.052
Cap.Tubular bbl / ft
psi/bbl = 97.69
48
0.00387
Production Squeezing
Through Perforations
Step 4:
Where:
LCMT = Maximum column of cement to prevent break down, feet
Max = Maximum allowable hydrostatic pressure minus SF
(usually 300 psi)
ISP
= Initial desired squeeze pressure @ surface
D
= Depth to bottom of tubular, feet
FW = Flush (or squeeze fluid) Weight, ppg
CW = Cement slurry weight, ppg
Sacks = Number of sacks to equal Cmt column
psi/bbl = Pressure for each barrel of fluid in tubular (or casing)
VolD = Squeeze or displacement volume, barrels
FSP = Final squeeze pressure for any displacement (or squeeze)
volume, psi
Squeeze Schedule = Can be table or expressed graphically
Step 5:
Graphical Approach
To Squeezing
Hesitation,
Dehydrate
perf. node
Production Squeezing
Through Perforations
Graphical Approach
To Squeezing
1379
PSurf
x x
x
350
x
Hesitated
Hesitated,
Disp.
complete
Production Squeezing
Through Perforations
Step 7.
Note: Channel may
squeeze off before the
calculated squeeze
volume is completed. In
that case, reverse out
balance of cement.
Production
Squeezing
49
Production
Squeezing
Production
Squeezing
Well #6
Well #6
Cement
Evaluation Log
Production
Squeezing
Production
Squeezing
Well #7
Well #7
Cement
Evaluation Log
Cement
Evaluation Log
Primary Cement
Job
Lower Bonding
Index
Matches Poorer
Cement Strength
(Lighter Color)
Colored Striations
Indicate Varying
Pipe Wall Thickness
Channels of Poor
Quality Cement
50
Types of Completions
Barefoot Completion
Producing formation is not
cased.
Production of hydrocarbons
is up the production casing.
Most common in low
pressure oil reservoirs
51
Types of Completions
Cased Completion
Types of Completions
Types of Completions
Types of Completions
Types of Completions
Types of Completions
52
Types of Completions
53
Well Re-entry
Well Re-entry
Well Re-entry
Bullheading
Advantages
Easy to do, can be done
with the tree on and
without picking it up.
Provides full control of
well, with the tree, at all
times until it is dead.
Pump down tubing with
higher rated working
pressure
54
Disadvantages
May break down the
formation and cause loss
of returns.
Sometimes difficult to
force formation fluid
back into the perforations
Can bypass gas in the
tubing
Reverse Circulating
Pump kill weight fluid
down one string or the
casing / tubing annulus and
up the producing tubing
string. Circulate out the
fluid that is in the
production tubing string.
Reverse Circulating
Disadvantages
Advantages
Do not have to force fluid Must have a fluid path
from surface to near
into the production
bottom of production
perforations.
tubing.
Lower maximum casing
If annulus is used, lower
pressure
burst strength of casing
Recover fluid in the
must be considered.
tubing string
Conventional Well
Control
Lubrication
Disadvantages
Advantages
Very time consuming
Can reduce tubing
pressure without breaking Works best with gas,
down the formation.
other fluids take too long
to migrate up to top
Can use any kill weight
above kill fluid.
fluid
Can be used on annulus
when there is no
circulation path
55
Given Data:
PF
= 5,200 psi
PTubing = 1,800 psi
PCasing = 850 psi
Depth = 10,000 ft
Formulas:
1. FWK
FWK
FWK:
PF:
TVD:
POB:
FWTa
TVD 0.052
Formulas:
PF - SITP psi
2. FWTa
PF POB psi
Where
TVD 0.052
Where
FWTA:
PF:
SITP:
TVD:
4. SRP = (ICP-SITP)
SRP = (2400 psi - 1800 psi)
5. FCP SRP
FCP 600
MWK
FWTa
ICP - FCP
psi increments
10
10.4
960 psi
6.5
2400 - 960
psi increments
144
10
56
Stroke increment
Tubing Strokes
10
1000 strokes
100 stk / increment
10
Trapped Pressure
Functions of Fluid
Provide hydrostatic pressure to control
formation pressure
Transport any cuttings or solids out of hole
Lubricate and cool down hole tools
Completion Fluids
57
Completion Fluids
Salt
S.G.
Usual
Wt., ppg
NaCl
2.17
9.8
CaCl2
2.15
11.7
KCl
1.98
9.5
NaBr
3.2
12.7
CaBr2 3.35
14.2
ZnBr2 3.2
19.2
Fluid
C, multiplier, ppg/F
Fresh Water
NaCl Brine
CaCl2 Brine
NaBr Brine
CaCl2/CaBr2
CaCl2/CaBr2/ZnBr2
CaBr2/ZnBr2
Comments
Common salt
With SO4 precipitates CaSO4 (Gypsum),
hazardous, high viscosity with NaOH
0.00353
0.0025
0.00235
0.0024
0.0024 - 0.0030
0.0030
0.0030 - 0.0055
Completion Fluids
Non-Soluble Materials:
(use with polymer for sufficient yield strength,
for weighting or fluid-loss control)
CaCO3 (limestone), S.G. 2.71, 95% acid
soluble (10% = of pore size for bridging)
FeCO3 (siderite), S.G. 3.65, 85% acid soluble
Completion Fluids
WH - WD
WH - WL
Decimal % Heavier 1- % Lighter
Decimal % Lighter
Where:
WD = Desired, ppg
WH = Weight of Heavier, ppg
WL = Weight of Lighter, ppg
Completion Fluids
Decimal % Lighter
WH - WD
WH - WL
Decimal % Lighter
58
59
Oil
Packer Fluids
Water
High pH Lime Water
Hydrates Formation
Hydrates Formation
60
Hydrates Prevention
Christmas Tree
The collection of
valves, Cross or
Tee, Gauges, and
chokes that control
the flow from the
well at the surface.
Subsurface Equipment
Subsurface Equipment
Retrievable Packer
Single or multiple production strings
Set on the tubing
Can be recovered when tubing is pulled
Subsurface Equipment
Surface Equipment
Subsurface Equipment
Bridge Plug
Retrievable Packer
Used for injection, shallow completion, or pumping well
Set on the tubing
Can be recovered when tubing is pulled
61
Subsurface Equipment
Cement Retainer
Tubing Retrievable
Controlled from surface with hydraulic
pressure on control line
Fail safe closed, if hydraulic pressure is
lost a spring in the valve will close it
Full opening valve
Subsurface Equipment
Subsurface Equipment
Sliding Sleeve
Subsurface Equipment
Subsurface Equipment
Tubing Nipple
Subsurface Equipment
62
63
a.
b.
c.
d.
It is less corrosive.
It is easier to mix.
It is more readily available.
It inhibits the swelling of clay.
Testing
64
Day Ten
Critiques
IWCF Testing
Individual Reviews
After your well control test has been turned in, and
graded, you will have an individual evaluation and be
presented with an MDS Certificate.
Successful well control candidates will receive a well
control certificate.
Individual photo will be taken with Bill.
Bring Memory Stick for class and individual photo.