Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7

Flare Knock-Out Drum

1. Objective

o Separate bulk liquid from gas

o Limit liquid droplet size entrained with gas to the flare

o Provide adequate residence time for liquid

2. Sizing basis

o Based on API 521

o Separation of liquid droplet size of 300-600 microns


considering the design case for the flare

o 20-30 minutes of liquid hold-up time based on a relief case


that results in maximum liquid

o No internals to facilitate separation


o Many orientations / options possible, horizontal KODs
most preferred

Flare KO Drum elevation

3. Flare Knock-Out Drum Elevation

o KO drum elevation decides pipe rack elevation based on


1:500 slope of main flare header
Flare KO Drum elevation

o KO drum elevation determined by pump NPSH


requirement

o To reduce pipe rack elevation options are

o Reduce KOD elevation (option 1)

Use vertical can pump

Locate pump within pit

Locate KO drum within pit

o Use intermediate KO drums (option 2)

>Flare KO Drum elevation arrangement (Option 1)

Flare KO Drum elevation arrangement (Option 2)

4. Flare KOD Liquid Removal


Remove liquid from flare KOD after relief to avoid overfill during future
relief event

1. Options
o Draining to evaporation pond or closed drain drums

o Liquid removal by flare KOD pumps

o Heater to be installed in KOD where freezing, pour point


issues exist

o Rate of liquid removal to consider frequency and amount of


liquid release

o High level in flare KOD to be considered for plant


shutdown

2. Sizing of Flare KOD

Flare KO Drum

o LLLL shall be sufficiently high to avoid any sludge


deposition impacting LT nozzle (150 mm in above figure
not correct, consider 300 mm minimum for services which
are not clean).

o LLLL shall be minimum 700-300 in case flare drum


electrical heaters need to be installed.

o LLLL Level at which pump trips.

o LLL Level at which both pumps stops


o HLL Level at which first pump starts

o HHLL Level at which second pump starts

o HHHLL Level at which entire plant goes into pressurized


trip.

5. Flare KOD sizing depends on two aspects


Liquid Hold up requirement during a major liquid or two phase
release.

Sufficient distance shall be available between inlet device bottom


and HHHLL. It is possible to have manually initiated
depressurization even after HHHLLL. Any possible liquid shall be
accommodated above HHHLL.

Distance between HLL and HHHLL shall be designed to


accommodate maximum liquid release scenario(?). Some
standards this distance is between HHLL and HHHLL.

Residence time required for drop of liquid particles of 300-600


micron size.

Liquid particles separate

o When the residence time of the vapor or gas is equal to or


greater then the time required to travel the available vertical
height at the dropout velocity of the liquid particles and

o When the gas velocity is sufficiently low to permit the


liquid dropout to fall. This vertical height is usually taken
as the distance from the maximum liquid level.

You might also like