1 1 PROJECT STARTING 75 days Wed 9/6/17 Mon 11/20/17
2 1.1 Starting Based on SPK 75 days Wed 9/6/17 Mon 11/20/17
3 1.2 Field Survey 3 days Sun 9/10/17 Tue 9/12/17
4 1.3 Club Med Bali Survey 3 days Sun 9/10/17 Tue 9/12/17
5 1.4 Club Med Study 8 days Wed 9/13/17 Wed 9/20/17
6 1.5 Submit Field Survey & Club Med Study Report 3 days Wed 9/20/17 Sat 9/23/17
7
8 2 CONCEPTUAL PLANNING 12 days Mon 9/25/17 Fri 10/6/17
9 2.1 Room Module Study 5 days Mon 9/25/17 Fri 9/29/17
10 2.2 Conceptual Progress review 1 day Tue 9/26/17 Tue 9/26/17 9/26
11 2.3 Internal Workshop 1 (TIM) 1 day Thu 9/28/17 Thu 9/28/17
12 2.4 Internal Wokshop 2 (TIM) 1 day Fri 9/29/17 Fri 9/29/17
13 2.5 Finalization Conceptual Design Draft 2 days Fri 9/29/17 Sat 9/30/17
17 2.6 Conceptual Design Presentation to ITDC & Club med (ARCH, INT, & LAND) 1 day Wed 10/4/17 Wed 10/4/17
18 2.7 Submit Conceptual Design 100% (ARCH, INT & LAND) 1 day Fri 10/6/17 Fri 10/6/17
19
20 3 SCHEMATIC DESIGN PLANNING 47 days Mon 10/2/17 Fri 11/17/17
21 3.1 Starting 1 day Mon 10/2/17 Mon 10/2/17
22 3.2 Schematic Design Internal Workshop 25% 1 day Fri 10/13/17 Fri 10/13/17
23 3.3 Schematic Design Draft Finalization 25% 1 day Fri 10/13/17 Fri 10/13/17
24 3.4 Submit Draft Schematic Design 25 % 1 day Sat 10/14/17 Sat 10/14/17
25 3.5 Schematic Design Presentation 25% to ITDC & Club Med 1 day Wed 10/18/17 Wed 10/18/17
26 3.6 Submit Final Schematic Design 25% to ITDC 3 days Thu 10/19/17 Sat 10/21/17
27 3.7 Schematic Design Internal Workshop 50% (1) 1 day Wed 10/25/17 Wed 10/25/17
28 3.8 Schematic Internal Workshop 50% (2) 1 day Thu 10/26/17 Thu 10/26/17
29 3.9 Send draft Schematic design 50% 1 day Sat 10/28/17 Sat 10/28/17
30 3.10 Schematic Design Draft Presentation 50% 1 day Wed 11/1/17 Wed 11/1/17
31 3.11 Send Final Schematic Design 50% 3 days Thu 11/2/17 Sat 11/4/17
32 3.12 Schematic Design Internal Workshop 100% (1) 1 day Wed 11/8/17 Wed 11/8/17
33 3.13 Schematic Design Internal workshop 100% (2) 1 day Thu 11/9/17 Thu 11/9/17
34 3.14 Send Draft Schematic Design 100% 3 days Thu 11/9/17 Sat 11/11/17
35 3.15 Schematic Design Final 100% Presentation 1 day Wed 11/15/17 Wed 11/15/17
36 3.16 Send Schematic Design Final 100% 2 days Thu 11/16/17 Fri 11/17/17

Task Project Summary Manual Task Start-only Deadline

Project: CLUBMED(ENG)_rev1 Split Inactive Task Duration-only Finish-only Progress


Date: Fri 9/22/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
Oct 1, '17 Oct 8, '17 Oct 15, '17 Oct 22, '17 Oct 29, '17 Nov 5, '17 Nov 12, '17 Nov 19, '17
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

9/26
9/28
9/29

10/13

Task Project Summary Manual Task Start-only Deadline

Project: CLUBMED(ENG)_rev1 Split Inactive Task Duration-only Finish-only Progress


Date: Fri 9/22/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2

You might also like