10 KG Weighing Balance (XL-WH-WB-001) ... IOQ
10 KG Weighing Balance (XL-WH-WB-001) ... IOQ
TABLE OF CONTENT
SL. NO. SUBJECT PAGE NO.
1. Preapproval 2
2. Objective 3
3. Scope 3
4. Responsibility 3
5. Acceptance Criteria 4
6. Installation Verification 4
7. Operational Verification 8
8. Deficiency and Corrective Action Taken 11
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 2 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
9. Requalification Criteria 11
10. Combined Installation/Operation Qualification Report 12
11. List Of Annexure 13
12. Reference 13
13. Post approval 14
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 3 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 4 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
The signature by below mentioned persons indicates that the documentation and information
contained herein complies with applicable regulatory, corporate, divisional/departmental
requirements, and current Good Manufacturing Practices.
Reviewed by : Engineering
Name Designation Sign/Date
Reviewed by : Store
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 8 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
2.0 OBJECTIVE:
The objective of this document is to provide a written guideline for the execution of the
Combined Installation/Operation Qualification (IOQ) of Weighing Balance for static attribute to
verify that:
The Instrument / equipment have been installed in accordance with the design and user
requirements and meet the set acceptance criteria and cGMP requirements as stipulated in
this document.
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 11 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Each installed components complies with the engineering design and equipment data
sheets / specification.
All supporting utilities are properly connected & equipment operations are verified for its
intended use.
3.0 SCOPE:
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 12 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
The Scope of this protocol is limited to the Combined Installation/Operation Qualification (IOQ)
of Weighing Balance (Equipment ID: XL/WH/WB/01) is safely installed in Store department
(Powder Dispensing Room) at XL Laboratories Pvt. Ltd., Neemrana.
4.0 RESPONSIBILITY:
Responsibilities of different department / personnel involved in different activities related to the
Combined Installation/Operation Qualification of the Weighing Balance are defined below:
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 13 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Functions Responsible
Functions Responsible
5.6 All the functionality of equipment components, safety features, Utility requirements to be
checked and verified.
EQUIPMENT DESCRIPTION
Equipment Name : Weighing Balance
Equipment ID : XL/WH/WB/01
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 17 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
For Installation Checklist of the equipment and utilities use the word yes to show
its presence and use No to indicate the absence.
For identification of the components of the equipment and utilities use the word
Comply otherwise use Does not comply to indicate non-compliance along with
mode of verification.
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 18 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Give the detailed information in the summary and conclusion part of the Installation
Qualification report.
Whichever column is blank or not used NA shall be used.
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 19 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Checked By Verified By
Sr. No. Statement Yes / No
(Sign/Date) (Sign/Date)
Verify that weighing balance is securely
01 anchored and shock proof.
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 20 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
________________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
Verified By (Sign/Date)
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 22 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 23 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
2 Model CTT-10K1
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 25 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
7 Accuracy 1g
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 26 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Minimum: 20 g
8 Working Range
Maximum: 10 kg
________________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
Verified By (Sign/Date)
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 27 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 28 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
________________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 29 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Verified By (Sign/Date)
6.5 Identification of Safety Features:
Safety
Checked By Verified By
Sr. No. Features Function
(Sign/Date) (Sign/Date)
Description
1. Earthing To avoid electrical shocks
________________________________________________________________________________________________________________________________________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 30 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
________________________________________________________________________________________________________________________________________________________________________________________________________
Verified By (Sign/Date)
6.6 Identification of Standard Operating Procedure:
The following Standard Operating Procedures were identified as important for effective
Operation & performance of Weighing Balance.
Identified By Verified By
Sr. No. SOP Title
(Sign/Date) (Sign/Date)
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 31 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
________________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
Verified By (Sign/Date)
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 32 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Give the detailed information in the summary and conclusion part of the Operational
qualification report.
7.2 Operational Qualification Test:
Comply / Checked
Sr. No. Functions/ Parameter Acceptance Criteria Date
Not Comply By (Sign)
Main Power supply to
On switching Main
1. machine
Switch to On position
should on
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 34 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
________________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 35 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Verified By (Sign/Date)
Checked By Verified By
UTILITY Observation
(Sign/Date) (Sign/Date)
Electricity: Single phase, 220V-240V
________________________________________________________________________________________________________________________________________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 36 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
________________________________________________________________________________________________________________________________________________________________________________________________________
Verified By (Sign/Date)
\
________________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
Verified By (Sign/Date)
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 40 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 41 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
________________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 45 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
_______________________________________________________________________________________________________________________________________________________________________________________________________
________________________________________________________________________________________________________________________________________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 48 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Verified By (Sign/Date)
8.0 DEFICIENCY AND CORRECTIVE ACTION TAKEN
Following deficiency was identified and corrective actions taken in consultation with the
Engineering Department.
Description of deficiency:
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 49 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
Corrective Action(s) Taken:
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 50 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
There are any major changes which affect the operation of the equipment.
After major breakdown maintenance is carried out.
As per Requalification Frequency.
Transfer/Shifting of Equipment.
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 51 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Summary:
_____________________________________________________________________________
_____________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 52 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 53 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
Conclusion:
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 54 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 55 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
12.0 REFERENCE:
1. EudraLex Volume 4 (Annex 15: Qualification and Validation)
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 60 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
2. SOP/QA/028
3. SOP/QA/056
This report for Weighing Balance Combined Installation/Operation Qualification has been
Prepared, reviewed and Approved by the following persons.
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 61 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
The reviewers & approvers signature indicates that this document has been reviewed, approved
and it accurately and completely reflects the tasks and deliverables necessary for installation &
operation Qualification of the equipment / Instrument / System, and the documentation and
information contained herein complies with applicable regulatory, corporate, divisional /
departmental requirements and current Good Manufacturing Practices.
Reviewed by : Engineering
Name Designation Sign/Date
XL LABORATORIES PVT. LTD.
A-141, EPIP, RIICO Industrial Area, Neemrana, Rajasthan, India
TITLE: Combined Installation/Operation Qualification Protocol of Weighing
Page 62 of 64
Balance (Equipment ID: XL/WH/WB/01)
Document No. : XL/IOQ/WB/001 Effective Date: Review Date:
Reviewed by : Store
Name Designation Sign/Date