Estimates (Jan 31, 2013)
Estimates (Jan 31, 2013)
CALCULATION SHEET
5CE-B
• ACUSA, Gerald Virgilio • AVILA, Mark Edward
• Beltran, Feby Ann Page 1
TWO STOREY RESIDENCE
Lot. 21 Blk. 1 Brgy. Fairview, Quezon City
Mga hindi pa nagagawa:
Autocadd - Lahat
EXCAVATION
LAND CLEARING :
C1
EXCAVATION :
WF1 /WF2
C. SEPTIC TANK: * with allowance of 100mm on width/length
TOTAL VOL. TO VOL. COVERED
= LENGTH X WIDTH X DEPTH
BE EXCAVATED BY CHB
= 4.90 X 1.50 X 1.65 INTERIOR
= 12.128 m³ WALL
VOL. COVERED
D. CATCH BASIN: * with allowance of 100mm on width/length BY CHB
TOTAL VOL. TO NUMBER OF EXTERIOR
= LENGTH X WIDTH X DEPTH X
BE EXCAVATED PIECES WALL
= 0.70 X 0.70 X 0.50 X 9
= 2.205 m³
VOL. COVERED
E. SEWER LINE: * with allowance of 100mm on width/length BY PIPE
TOTAL VOL. TO
= LENGTH X WIDTH X DEPTH
BE EXCAVATED
= 44.94 X 0.50 X 0.40
= 8.988 m³ TOTAL
EXCAVATION
BACKFILL:
A. ISOLATED FOOTINGS:
TOTAL VOL. NUMBER OF
= LENGTH X WIDTH X DEPTH X
OF CONCRETE PIECES TOTAL ADDITION
= 0.20 X 0.40 X 1.15 X 11
C1
= 1.012 m³ TOTAL VOL. OF
BACKFILL
= 0.35 X 0.20 X 1.15 X 7 100.528
C2
= 0.5635 m³ say
TOTAL VOL. NUMBER OF
= LENGTH X WIDTH X THICKNESS X
OF CONCRETE PIECES TOTAL VOLUME O
= 1.20 X 1.20 X 0.35 X 11
F1
= 5.544 m³
TOTAL VOL
= 1.50 X 1.50 X 0.35 X 7 BASE COU
F2
= 5.5125 m³ 14.450
ADDITIONAL BACKFILL:
TOTAL VOL. OF ADDITIONAL
= AREA X THICKNESS
BACKFILL
24.66 m³ = 109.6 m² X 0.225 m
TOTAL ADDITIONAL BACKFILL = 24.660 m³
SLAB ON GRADE
TOTAL VOL. OF SLAB
= AREA X THICKNESS
ON GRADE
14.821 m³ = 148.205 m² X 0.10 m
SUMMARY
TOTAL VOLUME OF SOIL TO ORDER: 130.687 m³
CEMENT : 103.744 BAGS
SAND : 7.410 m³
GRAVEL : 14.821 m³
CONCRETE
SLABS
NAME THICKNESS AREA VOLUME
SLAB (GRADE) 0.100 148.205 14.821
S1 0.100 72.840 7.284
S2 0.100 41.910 4.191
CS 0.100 4.780 0.478
TOTAL 26.774
TOTAL (W/O COL) 26.557
COLUMN
NAMEHEIGHT LENGTH WIDTH VOLUME QUANTITY T. AREA TOTAL VOLUME
C1 3.2 0.2 0.4 0.256 8 0.64 2.048
6 0.2 0.4 0.48 3 0.24 1.44
C2 6 0.2 0.35 0.42 3 0.21 1.26
3.2 0.2 0.35 0.224 4 0.28 0.896
PC 3.2 0.2 0.4 0.256 10 0.8 2.56
TOTAL 2.17 8.204
BEAM
NAME WIDTH DEPTH TOTAL LENGTH VOLUME
B1 0.200 0.400 21.900 1.752
B2 0.200 0.400 39.000 3.120
B3 0.200 0.400 23.800 1.904
RB 0.200 0.300 99.300 5.958
TOTAL 12.734
MECHANICAL
NAME THICKNESS AREA VOLUME
SEPTIC TANK 0.150 31.260 4.689
CATCH BASIN 0.100 1.800 0.180
TOTAL 4.869
CONCRETE
STAIRS
NAME THICKNESS LENGTH WIDTH VOLUME STEPS TOTAL VOLUME
STR 1 0.187 1.2 0.3 0.067 13 0.875
G/F LANDING 0.187 1.2 0.9 0.202 1 0.202
MID LANDING 0.4 1.2 1.96 0.941 1 0.941
L. STRINGER 0.545 1.2 0.1 0.065 2 0.131
U. STRINGER 0.86 1.2 0.1 0.103 2 0.206
TOTAL 2.355
SLAB
CONCRETE
COLUMNS
BEAM
MECHANICAL
CONCRETE ESTIMATES
STAIRS
SUMMARY
MASONRY
CONCRETE HOLLOW BLOCKS (CHB)
MASONRY
SUMMARY
MASONRY
MASONRY
MASONRY
SUMMARY
REINFORCEMENT BARS
SLABS
SLAB NAME WAY SLAB AREA BAR SPACING NO. OF REIN WEIGHT PCS. LENGTH BAR Ø
S1 TWO 19.89 150 64.066 346.320 65 6 12
TWO 15.99 150 51.504 277.056 52 6 12
TWO 22.44 150 72.279 388.944 73 6 12
TWO 14.58 150 46.962 250.416 47 6 12
S2 TWO 6.82 150 21.967 117.216 22 6 12
ONE 5.28 150 13.644 74.592 14 6 12
SLAB NAME AREA BAR SPACING NO. OF REINFORCEMENT PCS. LENGTH BAR Ø WEIGHT
SLAB ON GRADE 148.21 100 177.852 178 6.0 10 658.636
ROOFING
ROOFING
GA # 26 Corr. or Rib type long span
2.5 Corrugations
30 cm end lapping
ROOFING
CEILING EAVES
AREA = Length X Width
60.60 m² = 60.6 X 1.00
No. of PLYWOOD = area / 2.88
21.04 = 60.60 / 2.88
say 22 pcs. 1.2m x 2.4m x 6mm
CE 521L CONSTRUCTION MANAGEMENT LAB. CALCULATION SHEET
5CE-B
• ACUSA, Gerald Virgilio • AVILA, Mark Edward
• Beltran, Feby Ann Page 1
TWO STOREY RESIDENCE
Lot. 21 Blk. 1 Brgy. Fairview, Quezon City
ROOFING
SUMMARY
PAINTING WORKS
ROOF PAINT
AREA OF COVERAGE NO. OF NO. OF TOTAL NO. OF
TOTAL AREA PER GALLON GALLON COATINGS GALLONS
55 15 4 2 8
CEILING PAINT
NO. OF GALLON
AREA OF COVERAGE NO. OF GALLON (TOPCOAT) NO. OF GALLON
TOTAL AREA PER GALLON (PRIMER) (THINNER)
304.87 15 21 21 6
COLUMN PAINT
NO. OF GALLON
AREA OF COVERAGE NO. OF GALLON (TOPCOAT) NO. OF GALLON
TOTAL AREA PER GALLON (PRIMER) (NEUTRALIZER)
111.44 15 8 8 4
EXTERIOR PAINT
NO. OF GALLON
AREA OF COVERAGE NO. OF GALLON (TOPCOAT) NO. OF GALLON
TOTAL AREA PER GALLON (PRIMER) (NEUTRALIZER)
216.35 15 15 15 6
INTERIOR PAINT
NO. OF GALLON
AREA OF COVERAGE NO. OF GALLON (TOPCOAT) NO. OF GALLON
TOTAL AREA PER GALLON (PRIMER) (NEUTRALIZER)
223.56 15 15 15 6
SUMMARY
TRUSS
LENGTH OF MEMBERS:
TC BC KING POST VM DM
HT1 9.170 7.568 2.300 6.895 9.428
HT2 6.760 5.000 2.177 4.090 5.800
HT3 5.390 4.032 1.000 2.062 3.680
HT4 4.880 3.580 0.910 1.890 3.240
HT5 4.670 3.290 0.950 1.526 2.700
HT6 3.920 2.500 0.800 2.000 2.900
HT7 5.050 3.680 0.980 1.941 3.444
HT8 4.180 2.778 0.850 2.260 3.093
TRUSS 17.020 13.500 2.200 11.700 19.300
SUMMARY
SUMMARY
SAGROD 12mm Φ
TOTAL LENGTH 41.30 m
SUMMARY
No. of STEELBARS 12mm Φ X 6.00 m = 7 pcs.
CE 521L CONSTRUCTION MANAGEMENT LAB. CALCULATION SHEET
5CE-B
• ACUSA, Gerald Virgilio • AVILA, Mark Edward
• Beltran, Feby Ann Page 3
TWO STOREY RESIDENCE
Lot. 21 Blk. 1 Brgy. Fairview, Quezon City
REBARS
CE 521L CONSTRUCTION MANAGEMENT LAB. CALCULATION SHEET
5CE-B
• ACUSA, Gerald Virgilio • AVILA, Mark Edward
• Beltran, Feby Ann Page 1
TWO STOREY RESIDENCE
Lot. 21 Blk. 1 Brgy. Fairview, Quezon City
SCHEDULE OF DOORS :
D1 Solid Wooden Panel Door with 2" x 4" door jamb
1.6m length
2.1m height
D2 Solid Wooden Panel Door with 2" x 4" door jamb
0.8m length
2.1m height
D3 Solid Wooden Panel Door with 2" x 4" door jamb
0.7m length
2.1m height
D4 Glass Aluminum Sliding Door with 2" x 4" door jamb
1.6m length
2.1m height
SCHEDULE OF WINDOWS :
W1 Glass Aluminum Sliding Window
2.4m length
1.8m height
W2 Glass Aluminum Sliding Window
1.6m length
1.8m height
W3 Glass Aluminum Sliding Window
0.6m length
0.6m height
W4 Glass Aluminum Sliding Window
1.5m length
0.6m height
W5 Glass Aluminum Sliding Window
2.4m length
1.2m height
P1 Glass Fixed Panel
2.4m length
2.4m height
FORMWORKS
NAME SETS LENGTH WIDTH DEPTH PERIMETER AREA # PLYWOOD BOARD (TABLE 5-1)
RB 2 5.8 0.200 0.300 0.900 10.440 4 100.240
2 4.2 0.200 0.300 0.900 7.560 3 75.180
3 3.7 0.200 0.300 0.900 9.990 4 100.240
3 3.6 0.200 0.300 0.900 9.720 4 100.240
2 3.8 0.200 0.300 0.900 6.840 3 75.180
1 5.2 0.200 0.300 0.900 4.680 2 50.120
1 4.1 0.200 0.300 0.900 3.690 2 50.120
1 1.4 0.200 0.300 0.900 1.260 1 25.060
1 3.2 0.200 0.300 0.900 2.880 1 25.060
1 6.8 0.200 0.300 0.900 6.120 3 75.180
1 1.9 0.200 0.300 0.900 1.710 1 25.060
1 4.7 0.200 0.300 0.900 4.230 2 50.120
1 1.8 0.200 0.300 0.900 1.620 1 25.060
1 2.3 0.200 0.300 0.900 2.070 1 25.060
1 1.5 0.200 0.300 0.900 1.350 1 25.060
1 2.1 0.200 0.300 0.900 1.890 1 25.060
using 1/4" x 4' x 8' plywood form and 2" x 2" lumber TOTAL 76 1904.560
STAIRS
NAME THICK LENGTH WIDTH No. of STEPS AREA # PLYWOOD BOARD (TABLE 5-1)
SEPTIC TANK
SCAFFOLDINGS
BEAMS
FOR RB
TOTAL LENGTH 99.3 m
VERTICAL SUPPORT 595.8 bd.ft. use 2"x3"
HORIZONTAL SUPPORT 466.71 bd.ft. use 2"x2"
COLUMNS / POSTS
SLAB
SUMMARY
TILE WORKS
SCHEDULE OF TILES
WALL TILES : AREA PER TILE
20 cm x 40cm glazed tiles kitchen 0.08 m²
20 cm x 40cm glazed tiles T&B 0.08 m²
FLOOR TILES:
30cm x 30cm glazed tiles kitchen 0.09 m²
20cm x 20cm unglazed tiles T&B 0.04 m²
40cm x 40cm glazed tiles remaining floors 0.16 m²
G/F WALL
(HEIGHT x LENGTH) - AREA OF WINDOW/D = NET AREA
T &B 1 : 2.1 m x 10 m - 0.36 m² = 20.640 m²
T &B 2 : 2.1 m x 7.05 m - 0.36 m² = 14.445 m²
KITCHEN : 2.1 m x 9.40 m - 2.88 m² = 16.860 m²
REMAINING FLOOR: 0m x 0m - 0 = 0 m²
WALL AREA / TILE AREA = NUMBER OF TILES
T &B 1 : 20.64 / 0.08 = 258 pcs. 20 cm x 40cm glazed
T &B 2 : 14.445 / 0.08 = 180.56 pcs. 20 cm x 40cm glazed
KITCHEN : 16.860 / 0.08 = 210.75 pcs. 20 cm x 40cm glazed
REMAINING FLOOR: 0 / 0 = 0 pcs. no need for tiles
G/F FLOOR
FLOOR AREA / TILE AREA = NUMBER OF TILES
T &B 1 : 6.80 m² / 0.04 = 170 pcs. 20cm x 20cm unglazed
T &B 2 : 0.90 m² / 0.04 = 22.50 pcs. 20cm x 20cm unglazed
KITCHEN : 16.34 m² / 0.09 = 181.56 pcs. 30cm x 30cm glazed
REMAINING FLOOR: 80.00 m² / 0.16 = 500.00 pcs. 40cm x 40cm glazed
G/F TOTAL AREAS
WALL AREA + FLOOR AREA = TOTAL AREA
T &B 1 : 20.640 + 6.800 m² = 27.440 m²
T &B 2 : 14.445 + 0.900 m² = 15.345 m²
KITCHEN : 16.860 + 16.340 m² = 33.200 m²
REMAINING FLOOR: 0 + 80.000 m² = 80.000 m²
G/F TILE ADHESIVES
TOTAL AREA X 0.086 = TOTAL BAGS OF CEMENT MORTAR
T &B 1 : 27.440 X 0.086 = 2.36 bags
T &B 2 : 15.345 X 0.086 = 1.32 bags
KITCHEN : 33.200 X 0.086 = 2.86 bags
REMAINING FLOOR: 80.000 X 0.086 = 6.88 bags
TOTAL AREA X 0.50 = TOTAL BAGS OF CEMENT MORTAR
T &B 1 : 27.440 X 0.50 = 13.72 kg.
T &B 2 : 15.345 X 0.50 = 7.67 kg.
KITCHEN : 33.200 X 0.50 = 16.60 kg.
TILE WORKS
2/F WALL
(HEIGHT x LENGTH) - AREA OF WINDOW/DOO = NET AREA
T &B 1 : 2.1 m x 11.95 m - 1.26 m² = 23.835 m²
T &B 2 : 2.1 m x 7.10 m - 0.36 m² = 14.550 m²
REMAINING FLOOR: 0m x 0m - 0 = 0 m²
2/F FLOOR
FLOOR AREA / TILE AREA = NUMBER OF TILES
T &B 1 : 9.845 m² / 0.04 = 246.13 pcs. 20cm x 20cm unglazed
T &B 2 : 4.800 m² / 0.04 = 120.00 pcs. 20cm x 20cm unglazed
REMAINING FLOOR: 92.45 m² / 0.16 = 577.81 pcs. 40cm x 40cm glazed
SUMMARY
WALL TILES : 20 cm x 40cm glazed tiles kitchen 211 pcs.
20 cm x 40cm glazed tiles T&B 919 pcs.
FLOOR TILES:30cm x 30cm glazed tiles kitchen 182 pcs.
20cm x 20cm unglazed tiles T&B 559 pcs.
40cm x 40cm glazed tiles remaining floors 1078 pcs.
CEMENT 26 bags
WHITE CEMENT 150.733 kg say 160
CEILING JOIST
AMOUNT OF CEILING JOIST = AREA OF CEILING X 6.379
G/F CEILING
126.88 bd. Ft. 2" x 2" = 19.89 m² X 6.379
102.00 bd. Ft. 2" x 2" = 15.99 m² X 6.379
143.14 bd. Ft. 2" x 2" = 22.44 m² X 6.379
93.01 bd. Ft. 2" x 2" = 14.58 m² X 6.379
43.50 bd. Ft. 2" x 2" = 6.82 m² X 6.379
33.68 bd. Ft. 2" x 2" = 5.28 m² X 6.379
97.28 bd. Ft. 2" x 2" = 15.25 m² X 6.379
92.88 bd. Ft. 2" x 2" = 14.56 m² X 6.379
12.76 bd. Ft. 2" x 2" = 2.00 m² X 6.379
15.44 bd. Ft. 2" x 2" = 2.42 m² X 6.379
2.30 bd. Ft. 2" x 2" = 0.36 m² X 6.379
2/F CEILING
77.76 bd. Ft. 2" x 2" = 12.19 m² X 6.379
85.10 bd. Ft. 2" x 2" = 13.34 m² X 6.379
81.08 bd. Ft. 2" x 2" = 12.71 m² X 6.379
110.23 bd. Ft. 2" x 2" = 17.28 m² X 6.379
33.94 bd. Ft. 2" x 2" = 5.32 m² X 6.379
87.26 bd. Ft. 2" x 2" = 13.68 m² X 6.379
196.60 bd. Ft. 2" x 2" = 30.82 m² X 6.379
123.75 bd. Ft. 2" x 2" = 19.40 m² X 6.379
CEILING BOARD
AMOUNT OF CEILING BOARD = AREA OF CEILING / 2.88
G/F CEILING
6.91 bd. Ft. 2" x 2" = 19.89 m² / 2.88 7 pc/s. 1.20m x 2.4m x 6mm
5.55 bd. Ft. 2" x 2" = 15.99 m² / 2.88 6 pc/s. 1.20m x 2.4m x 6mm
7.79 bd. Ft. 2" x 2" = 22.44 m² / 2.88 8 pc/s. 1.20m x 2.4m x 6mm
5.06 bd. Ft. 2" x 2" = 14.58 m² / 2.88 6 pc/s. 1.20m x 2.4m x 6mm
2.37 bd. Ft. 2" x 2" = 6.82 m² / 2.88 3 pc/s. 1.20m x 2.4m x 6mm
1.83 bd. Ft. 2" x 2" = 5.28 m² / 2.88 2 pc/s. 1.20m x 2.4m x 6mm
5.30 bd. Ft. 2" x 2" = 15.25 m² / 2.88 6 pc/s. 1.20m x 2.4m x 6mm
5.06 bd. Ft. 2" x 2" = 14.56 m² / 2.88 6 pc/s. 1.20m x 2.4m x 6mm
0.69 bd. Ft. 2" x 2" = 2.00 m² / 2.88 1 pc/s. 1.20m x 2.4m x 6mm
0.84 bd. Ft. 2" x 2" = 2.42 m² / 2.88 1 pc/s. 1.20m x 2.4m x 6mm
0.13 bd. Ft. 2" x 2" = 0.36 m² / 2.88
2/F CEILING
4.23 bd. Ft. 2" x 2" = 12.19 m² / 2.88 5 pc/s. 1.20m x 2.4m x 6mm
4.63 bd. Ft. 2" x 2" = 13.34 m² / 2.88 5 pc/s. 1.20m x 2.4m x 6mm
4.41 bd. Ft. 2" x 2" = 12.71 m² / 2.88 5 pc/s. 1.20m x 2.4m x 6mm
6.00 bd. Ft. 2" x 2" = 17.28 m² / 2.88 6 pc/s. 1.20m x 2.4m x 6mm
1.85 bd. Ft. 2" x 2" = 5.32 m² / 2.88 2 pc/s. 1.20m x 2.4m x 6mm
4.75 bd. Ft. 2" x 2" = 13.68 m² / 2.88 5 pc/s. 1.20m x 2.4m x 6mm
10.70 bd. Ft. 2" x 2" = 30.82 m² / 2.88 11 pc/s. 1.20m x 2.4m x 6mm
6.74 bd. Ft. 2" x 2" = 19.40 m² / 2.88 7 pc/s. 1.20m x 2.4m x 6mm
SUMMARY
2" X 2" LUMBER 1558.58 bd. Ft.
1.20m x 2.4m x 6mm PLYWOOD 92 pcs.
NAILS
AREA OF CEILING
NAILS
TOTAL = 16.94 kg
TO BE ORDER = 17 kg 2d finishing nail
NAILS : SCAFFOLDINGS
RB
99.3 X 0.73 X 1 = 72.489 kg 20d CWN
TOTAL = 209.07 kg
TO BE ORDER = 210 kg 20d CWN
SUMMARY
14 kg 8d finishing nail
17 kg 2d finishing nail
2 kg 6d casing brad
210 kg. 20d CWN
CE 521L CONSTRUCTION MANAGEMENT LAB. CALCULATION SHEET
5CE-B
• ACUSA, Gerald Virgilio • AVILA, Mark Edward
• Beltran, Feby Ann Page 1
TWO STOREY RESIDENCE
Lot. 21 Blk. 1 Brgy. Fairview, Quezon City
PLUMBING/SANITARY
SUMMARY
ELECTRICAL
SUMMARY
SCHEDULE OF WORKS
SCHEDULE OF WORKS
BILL OF QUANTITIES
JOB: TWO STOREY RESIDENCE Lot. 21 Blk. 1 Brgy. Fairview, Quezon City DATE: 21-Feb-13
ESTIMATORS:ACUSA,Gerald Virgilio; AVILA, Mark Edward ; BELTRAN, Feby Ann
BILL OF QUANTITIES
JOB: TWO STOREY RESIDENCE Lot. 21 Blk. 1 Brgy. Fairview, Quezon City DATE: 21-Feb-13
ESTIMATORS:ACUSA,Gerald Virgilio; AVILA, Mark Edward ; BELTRAN, Feby Ann
BILL OF QUANTITIES
JOB: TWO STOREY RESIDENCE Lot. 21 Blk. 1 Brgy. Fairview, Quezon City DATE: 21-Feb-13
ESTIMATORS:ACUSA,Gerald Virgilio; AVILA, Mark Edward ; BELTRAN, Feby Ann
RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
CIVIL WORKS (m²/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
LAND CLEARING : 160 20 m²/hr. 8 300 m² 1.88 2 1 250 500 500
EXCAVATION : 12.00 1.50 m³/day 8 106.366 m³ 8.86 2 5 350 700 3500
BACKFILL&COMPACTION: 39.04 4.88 m³/day 8 130.687 m³ 3.35 1 3 350 350 1050
COMPACTED BASECOURSE: 400 50 m²/day 8 148.205 m² 0.37 1 1 350 350 350
CE 521L TOTAL : 5400
CONSTR
UCTION RATE Initial No. of hrs. No. of No. of
MANAG Amount Duration Labor Fee Labor Cost Total Cost
EMENT CONCRETE WORKS (m³/day/team) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
LAB. 0.20 8 18.288 m³ 11.43 2 6
FOOTING (helpers): 1.60 m³/hr. 325 650 3900
FOOTING (mason) : 2 6 400 800 4800
SOG (helpers) : *5teams 1.60 0.20 m³/hr. 8 14.821 m³ 9.26 5 2 325 1625 3250
SOG (mason) : *5teams 5 2 400 2000 4000
SUSPENDED SLABS (helpers):
*3teams 1.60 0.20 m³/hr. 8 11.841 m³ 7.40 3 3 325 975 2925
SUSPENDED SLABS (mason):
*3teams 3 3 400 1200 3600
COLUMNS (G/F) (helper): 1.60 0.20 m³/hr. 8 2.944 m³ 1.84 1 3 325 325 975
COLUMNS (G/F) (mason): 1 3 400 400 1200
COLUMNS (2/F) (helper):
*2teams 1.6 0.20 m³/hr. 8 5.26 m³ 3.29 2 2 325 650 1300
COLUMNS (2/F) (mason):
*2teams 2 2 400 800 1600
BEAMS (2/F) (helper): *2teams
1.6 0.20 m³/hr. 8 6.776 m³ 4.24 2 3 325 650 1950
BEAMS (2/F) (mason):
*2teams 2 3 400 800 2400
ROOF BEAMS (helper):
*2teams 1.6 0.20 m³/hr. 8 5.958 m³ 3.72 2 2 325 650 1300
ROOF BEAMS (mason):
*2teams 2 2 400 800 1600
TOTAL : 34800
CE 521L CONSTRUCTION MANAGEMENT LAB. CALCULATION SHEET
5CE-B
ACUSA, Gerald Virgilio • AVILA, Mark Edward • Beltran, Feby Ann
Page 1
LABOR COST
RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
MASONRY WORKS (m²/day/-) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
CHB G/F (helpers) : *2teams 10.00 1.25 m²/day 8 187.73 m² 18.77 2 10 325 650 6500
CHB G/F (mason) : *2teams 2 10 400 800 8000
CHB 2/F (helpers) : *2teams 10.00 1.25 m²/day 8 188.94 m² 18.89 2 10 325 650 6500
CHB 2/F (mason) : *2teams 2 10 400 800 8000
CE 521L PLASTERING (G/F): 4.8 0.6 m²/day 8 158.87 m² 33.10 3 12 400 1200 14400
CONSTR PLASTERING (2/F): 4.8 0.6 m²/day 8 188.94 m² 39.36 4 10 400 1600 16000
UCTION
MANAG TOTAL : 59400
EMENT
LAB. RATE Initial No. of hrs. No. of No. of
Amount Duration Labor Fee Labor Cost Total Cost
PAINTING WORKS (m²/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
EXTERIOR: 27.84 3.48 m³/day 8 216.35 m² 7.77 1 8 350 350 2800
INTERIOR: 27.84 3.48 m³/day 8 639.87 m² 22.98 3 8 350 1050 8400
ROOF: 27.84 3.48 m³/day 8 55 m² 1.98 1 2 350 350 700
TOTAL : 11900
DOORS & WINDOWS RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
INSTALLATION (pc/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
WINDOWS: 8 1 pc./hr. 8 20 pcs. 2.50 1 3 350 350 1050
WOODEN DOORS: 8 1 pc/hr. 8 13 pcs. 1.63 1 2 350 350 700
SLIDING DOORS: 6.64 0.83 pc/hr. 8 1 pcs. 0.15 1 1 350 350 350
TOTAL : 2100
CE 521L CONSTRUCTION MANAGEMENT LAB. CALCULATION SHEET
5CE-B
ACUSA, Gerald Virgilio • AVILA, Mark Edward • Beltran, Feby Ann
Page 1
LABOR COST
FORMWORKS RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
FABRICATION (m²/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
BEAMS : 14.88 1.86 m²/hr 8 97.9 m² 6.58 2 4 400 800 3200
SLABS : 14.88 1.86 m²/hr 8 118.41 m² 7.96 2 4 400 800 3200
COLUMNS : 14.88 1.86 m²/hr 8 78.4 m² 5.27 2 3 400 800 2400
TOTAL : 8800
CE 521L
CONSTR FORMWORKS RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
UCTION
MANAG INSTALLATION (m²/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
EMENT BEAMS : 5.20 0.65 m²/hr 8 97.9 m² 18.83 4 5 400 1600 8000
LAB. SLABS : 9.60 1.20 m²/hr 8 118.41 m² 12.33 3 5 400 1200 6000
COLUMNS : 6.80 0.85 m²/hr 8 78.4 m² 11.53 4 3 400 1600 4800
TOTAL : 18800
FORMWORKS RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
STRIPPING (m²/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
BEAMS : 78.08 9.76 m²/hr 8 97.9 m² 1.25 1 2 400 400 800
SLABS : 74.40 9.30 m²/hr 8 118.41 m² 1.59 1 2 400 400 800
COLUMNS : 94.08 11.76 m²/hr 8 78.4 m² 0.83 1 1 400 400 400
TOTAL : 2000
REBAR WORKS RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
FABRICATION (m²/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
SOG : 224.00 28.00 kg/hr 8 658.956 kg 2.94 3 1 350 1050 1050
SUSPENDED SLABS : 224.00 28.00 kg/hr 8 1882.902 kg 8.41 3 3 350 1050 3150
FOOTING: 224.00 28.00 kg/hr 8 1059.354 kg 4.73 4 2 350 1400 2800
COLUMNS (G/F) : 224.00 28.00 kg/hr 8 1403.04 kg 6.26 2 4 350 700 2800
COLUMNS (2/F) : 224.00 28.00 kg/hr 8 227.52 kg 1.02 1 2 350 350 700
BEAMS: 224.00 28.00 kg/hr 8 1699.29 kg 7.59 3 3 350 1050 3150
ROOF BEAM: 224.00 28.00 kg/hr 8 971.7 kg 4.34 2 3 350 700 2100
TOTAL : 15750
REBAR WORKS RATE Initial No. of hrs. Amount No. of No. of Duration Labor Fee Labor Cost Total Cost
INSTALLATION (m²/day/man) Rate of work Days Laborer/s (days/s) (Php) (Php) (Php)
SOG : 160.00 20.00 kg/hr 8 658.956 kg 4.12 3 2 350 1050 2100
SUSPENDED SLABS : 160.00 20.00 kg/hr 8 1882.902 kg 11.77 5 3 350 1750 5250
FOOTING: 160.00 20.00 kg/hr 8 1059.354 kg 6.62 3 3 350 1050 3150
COLUMNS (G/F) : 160.00 20.00 kg/hr 8 1403.04 kg 8.77 2 5 350 700 3500
COLUMNS (2/F) : 160.00 20.00 kg/hr 8 227.52 kg 1.42 1 2 350 350 700
BEAMS: 160.00 20.00 kg/hr 8 1699.29 kg 10.62 3 4 350 1050 4200
ROOF BEAM: 160.00 20.00 kg/hr 8 971.7 kg 6.07 3 3 350 1050 3150
TOTAL : 22050