2.0 Alexis GPS Construction Schedule - 0B
2.0 Alexis GPS Construction Schedule - 0B
Project Milestone
Project Start Date (tentative)
Construction Site Mobilization
Shutdown Window for GPP5 Aug 2019 (41D) (SD:10D; Mech day: 19D; Start up: 10D)
Shutdown Window for GPP5/6 Aug 2019 (30D) (SD:10D; Mech day: 8D; Start up: 10D)
Mechanical Completion (Overall)
IA (Completion) GPP5 IA
C&S AFC Isometric GPP5/6 IA
Engineering
33Kv Cable, Pipe fittings flanges
Procurement
Instrument valve
Construction Activities
COMMON
Temporary Facility
RF-CEFP CVL Equipment fireproofing replacement
RF-CPFP CVL Piperack fireproofing replacement
RP-C33C CVL C&S New Structure for 33kV Cable Shop fabrication & Site Erection
Remaining trenching interlock, make good and punch list, marker
RP-E33C ELE Replacement of 33kV incomer Cables
Trenching work, Cabling, backfilling up to termination and testing
GPP5
Preshutdown Activity Site Check Checkpoint Gate : Material, Progress, Manpower, Equipment readiness for S/D
Piping Site Measurement, Preparation Prefabrication
Instrument Site Measurement, Preparation, Prefabrication
Field Instrument Calibration and PRD Pretesting
Scaffolding
Exising Equipment/Control station Functionality Check and Tagging
For replacement work where Pre-S/D is allowed
Shutdown Activity
RF-PDSP PIP Dislocated Steam Piping Replacement
RF-PCUI PIP Sectional Replacement for piping CUI
RF-PWEL PIP Replacement of sockelet and weldolet
RF-PPRD PIP Replacement of PRD
RP-INCV INC Replacement of Control Valves
RP-IPCV INC Replacement of Self regulated Control Valve
RP-IFIT INC Replacement of Field Transmitter
RP-ISDV INC Replacement of Shutdown valve
Site Check, Procurement & Mobilization
RF-ICVA INC Replacement of Control Valve Positioner & Accessories
Site Check, Procurement & Mobilization
RF-ISVA INC Replacement of Shutdown Valve SOV & Accessories
RP-ELCS ELE Replacement of LCS
RP-EHVM ELE Replacement of HV motor
RF-EHVM ELE Refurbishment of HV motors Site Check, Procurement & Mobilization
RF-EMCC ELE Retrofit of VCB/VCU/ACB/MCC at Substation
Site Check, Procurement & Mobilization
RF-EUPS ELE Replacement of UPS
GPP5/6
Preshutdown Activity Site Check Checkpoint Gate : Material, Progress, Manpower, Equipment readiness for S/D
Piping Site Measurement, Preparation Prefabrication
Instrument Site Measurement, Preparation, Prefabrication
Field Instrument Calibration and PRD Pretesting
Scaffolding
Exising Equipment/Control station Functionality Check and Tagging
For replacement work where Pre-S/D is allowed
Shutdown Activity
RF-PDSP PIP Dislocated Steam Piping Replacement
RF-PCUI PIP Sectional Replacement for piping CUI
RF-PWEL PIP Replacement of sockelet and weldolet
RF-PPRD PIP Replacement of PRD
RP-INCV INC Replacement of Control Valves
RP-IPCV INC Replacement of Self regulated Control Valve
RP-IFIT INC Replacement of Field Transmitter
RP-ISDV INC Replacement of Shutdown valve
Site Check, Procurement & Mobilization
RF-ICVA INC Replacement of Control Valve Positioner & Accessories Site Check, Procurement & Mobilization
RF-ISVA INC Replacement of Shutdown Valve SOV & Accessories
V
RP-ELCS ELE Replacement of LCS
RP-EHVM ELE Replacement of HV motor
RF-EHVM ELE Refurbishment of HV motors Site Check, Procurement & Mobilization
RF-EMCC ELE Retrofit of VCB/VCU/ACB/MCC at Substation Site Check, Procurement & Mobilization
RF-EUPS ELE Replacement of UPS
Site Check, Procurement & Mobilization
ELE Inspection and & major service for 132kV and 33kV GIS
NOTE:
1 The schedule is preliminary for VENDOR and SUBCON's planning purpose PLANNED CONSTRUCTION SCHEDULE FOR EPCC OF PLANT
2 VENDOR and SUBCON shall propose its schedule and required time to plan its manpower/tools/equipment and procurement REJUVENATION WORKS AT GPS
3 In case any work can be performed during PRE SHUTDOWN, VENDOR and SUBCON shall follow TOYO's instruction to
perform such work to reduce the PROJECT Schedule Risk.
0 17-Jul-18 Preliminary LKE OEL OEL
REV. DATE DESCRIPTION PREP CHK APPR