SATIP-B-069-01 Rev 8 Emergency EyewashShower System Final
SATIP-B-069-01 Rev 8 Emergency EyewashShower System Final
8 30-Jun-14
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Emergency Eyewash/Shower System SATIP-B-069-01 31-Dec-14 PLUMBING
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Emergency Eyewash/Shower SAIC SAIC Saudi Aramco to be notified on initial delivery of Units
2.1
Receiving Inspection B-4001 B-4001 H W for each building or area
Emergency Eyewash/Shower
SAIC SAIC Saudi Aramco to be notified on initial delivery of
2.2 Accessories
B-4001 B-4001 H W accessories by type or manufacture.
Receiving Inspection
3.0 INSTALLATION
Emergency Eyewash/Shower SAIC SAIC Saudi Aramco to be notified on start of this activity for
3.2
Inspection B-4002 B-4002 H W every building or area
Emergency Eyewash/Shower
SAIC SAIC Saudi Aramco to be notified on start of this activity for
3.3 Accessories
B-4002 B-4002 H W every building or area
Inspection
See See
3.6 Valves See SATIP-L-108-01 Valves
Remarks Remarks
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
REMARKS
NO. & ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
Emergency Eyewash/Shower
SATR SATR
4.1 Functional Testing and Final Visual
B-4001 B-4001 H H
Inspection
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection