A.R.I.

A.R.I. Flow Control Accessories Ltd. Kfar-Charuv 12932 Israel Tel. 972-4-6761988 Fax. 972-4-6763402 www.arivalves.com 0302ENM-D020-10

D-020 COMBINATION AIR VALVE FOR WASTEWATER


Installation Periodic Maintenance
1) The wastewater air valve should be installed (Every 6 months and according to liquid quality)
vertically on the upper portion of the pipe line. 1) Shut the isolating valve underneath the air 1 4
2) An isolating valve should be installed valve.
underneath the air valve. 2) Open the drainage tap (3). 2
3) Do not turn separately the plastic head (1) of 3) Attach quick release connection to the drainage
the air valve. To change the direction of drainage outlet (4) on top of the valve.
connecting, one must turn the whole valve or the 4) Flush clean water via the drainage opening (4)
upper cover, by loosening the screws (2) and in the air valve until seeing clean water running
turning the head at a 900 angle (turning the plastic from the ball valve (3)
head may damage the valve performance due to Pressure rating for back-flush: 3 bar. 3
air escape). 5) Shut off the drainage tap (3)
6) Reopen the isolating valve.
Warning! Do not remove or disassemble
the air valve from pipeline before Comprehensive Periodic Maintenance
performing the following steps: 1) Shut the isolating valve underneath the air
1) Turn off riser shut off valve. valve.
2) Open up pressure release valve located on the 2) Open the drainage tap (3) and drain the air
base of the D-020. valve.
3) Remove valve from line only after ensuring that 3) Open the 4 screws on top cover of air valve (2).
internal pressure in the valve has been released. 4) Pull out the mechanism. Wash the mechanism
and the inside of the air valve.
5) Reassemble back the mechanism and tighten
the screws (1/2”) (2). Pay attention to correct
placing of seal’s O-Ring.
6) Close the drainage tap (3).
7) Reopen the isolating valve.