GOVERNMENT OF ANDHRA PRADESH

ABSTRACT

I & C.A.D (PW) Department – T.G.P. – Construction of O.T. Sluice at Km 125.200


of S.S.G. Canal to feed an ayacut of 400 acres – Administrative Approval –
Sanction – Accorded – Orders – Issued.
--------------------------------------------------------------------------------------------------------------------
IRRIGATION & C.A.D (PW-MAJOR IRRIGATION-V) DEPARTMENT

G.O.Ms.No. 136 Dated: 19-11-2009.


Read the following:-

1. From the ENC, TGP, Sriklahasti, Lr.No.ENC/TGS/TS/T4/10564/O.T.Sluices,


dated. 5.9.2008.
2. From the ENC, TGP, Sriklahasti,Lr.No.ENC/TGS/TS/T4/10564/O.T.Sluices,
dated.19.01.2009.
3. From the ENC, TGP, Sriklahasti, Lr.No.ENC/TGS/TS/T4/ 10564/ O.T.
Sluices, dated. 14.9.2009.

& & &

In the references read above, the Engineer-in-Chief , Telugu Ganga


Project, Srikalahasti submitted proposal seeking administrative approval for
construction of O.T. Sluice at Km 125.200 of S.S.G. Canal to feed an ayacut of
400 acres at an estimated cost of Rs. 24.40 Lakhs ( Rupees Twenty Four Lakhs
and Forty Thousand Only).

2. The Engineer-in-Chief, Telugu Ganga Project, Srikalahasti has further


reported that a preliminary survey was carried out and construction of an Off-
take Sluice at Km 125.200 of SSG Canal is proposed. To excavate supply
channel for a length of 650M and then water let into existing channel and then
it will flow in the existing channel for a length of 650M and joins the check Dam
constructed across Chinneru at Naganandapuram village of Varadaiahpalem
Mandal, Chittoor District.

3. The Engineer-in-Chief, Telugu Ganga Project, Srikalahasti has further


reported that due to establishment of S.E.Z in the command area of Branch
Canal No.9, 9A and Mambattu, I.P. to an extent of 14,638 acres under
package-11 got reduced and the present proposals of creating 392 acres
ayacut will compensate to some extent for the ayacut lost due to formation of
S.E.Z., and 45 Mcft of water only proposed to feed an extent of 400 acres
through the proposed O.T. Sluice at Km 125.200 of S.S.G Canal.

4. Hence, the Engineer-in-Chief, TGP, Srikalahasti has requested the


Government to accord administrative Approval for Construction of O.T. Sluice
at Km 125.200 of S.S.G. Canal Rs. 24.40 Lakhs.

5. Government after careful examination hereby accord administrative


approval for construction of O.T. Sluice at Km 125.200 of S.S.G. Canal to feed
an ayacut of 400 acres at an estimated cost of Rs. 24.40 Lakhs ( Rupees Twenty
Four Lakhs and Forty Thousand Only).

6. The expenditure sanctioned above shall be debited to the head of


account “4701 COL on Major and Medium Irrigation (01) Major Irrigation01
(commercial), – MH 123 TGP, S.H.(27) canals and distributaries, 530 Major Works
– 531 other expenditure”.

p.t.o.,
// 2 //

7. This order issues with the concurrence of Finance (W&P) Department


vide their U.O.No.3943/F7 (A2)/2009-1, dated. 29.10.2009.

(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)

RAJIV RANJAN MISHRA


SECRETARY TO GOVERNMENT

To
The Engineer-in-Chief, TGP, Srikalahasti

Copy to:-
The Accountant general, A.P. Hyderabad.
The Director of works & Accounts, Hyderabad.
The Finance (W&P) Department
The P.S. to the Minister (M&MI)
The P.S. to the Secretary (RRM)
SF/SC

// FORWARDED BY ORDER //