BRIDGE INSTALLATION

TOOLS, TEAM AND METHOD

PT Denpasar Satu Mulia


Jalan Denpasar I/M3, Kuningan, Jakarta 12590


To :

PT. Waskita Karya Tbk, Persero
Oicussie Road Project
Timor Leste

Dear Sirs,

We would like to thank you for opportunity you have given to us.
Herewith we give brief details regarding the team, tools/equipment,
and the method for installation of 2(two) Bridges A25 in Oicussie.

We hope this information will give you greater understanding to
what will we do to install the bridges.

Please do let us know if there are any correction or objection, in
order to get quality assurance and safety during construction.

Thank you

Best Regards










The Team

Director : Kresno Hadi

Team Leader : Oka Muliono

Team Member

1. Suryanto
2. Darji Al Surip
3. Ali Nur Chamid
4. Lukman Hakim
5. Muhlisin
6. Muamar
7. Durjo (Replacement)
8. Aris Priyatin (Replacement)
9. Nasori (Replacement)



















The Equipment

Prepare By Main Contractor
1. Crane 25 Tons including the operator and fuel
2. Generator Set for Electricity
3. Solid Wood 25x25
4. Steel Pipe 2.5 Inch
5. Blender with gas and air tank

Prepare by Erector
1. Impact tool and Moment Torque
2. Hydraulic Jack 50/25 tons
3. Tracker
4. Wire Cable 22 mm with link belt
5. Wrench
6. Hammer
7. Steel Saw
8. Electrical Wire for Impact Tools
9. Safety Standard Equipment for Workers

Time Frame

- 20 Days






















The Method


Bridge Erection Method/Installation Steps :

1. Making Temporary Support using Solid Wood (Coconut
Wood/Pines) with width as same as the Bridge


2. Place Girder on the wood ( on the ground)


3. Install the vertical connection plate on the girder (left and Centre)


4. Place the Bearing on position in abutment


5. Joint the girders


6. Install The Horizontal Connection Plate


7. Place the Left Side Girder on the 2nd Row in abutment and
temporary support (Welding or Tightening)


8. Place the left side Girder on the 1st row in abutment and temporary
support


9. Place All Girders


10. Install the bracings



11. Install the diaphragm



12. All installed