METHOD STATEMENT

FOR DEVICE INSTALLATION OF DUCT SMOKE DETECTOR


I. PURPOSE
1. The purpose of this Method Statement is to detail the procedures for the installation of
Duct Smoke Detector.

II. SCOPE
1. The work under this Section includes providing all labors, materials, tools and equipment
necessary for furnishing and installing Duct Smoke Detector as shown in the drawings
and standard details.

III. REFERENCES
1. Latest approved “For Construction Drawing” and/or approved shop drawing mounting
details.

IV. PROCEDURE
1. Determine an appropriate mounting position for the Duct Smoke Detector as per
Approved Shop Drawing Details.
2. Insert gaskets to the intake sampling tube and exhaust tube to avoid any air leak then
insert the sampling and exhaust tube to the drilled hole in the duct as per Approved
Shop Drawing Details. Make sure that the sampling tube holes must be facing into the
air flow.
3. Secure the Duct Smoke Detector enclosure to the duct using mounting screws then
insert the filters to the sampling and exhaust tubes.
4. Attach a flexible metallic conduit with FMC connector to the duct smoke detector base
using locknut and bushing. Terminate the field wiring to the terminals based on the
wiring configuration of the device.
5. Attach the Duct Smoke Detector cover to the base of the device. Secure he cover by
tightening the mounting screws.

V. EQUIPMENT /TOOLS
1. Philips and Flat screw driver 4. Precision tools
2. Long Nose Plier 5. Side Cutter Pliers
3. Electric Drill

VI. MANPOWER (Minimum Required)


1. Foreman 1
2. Electrician 1
3. Helper 1