PA - 1d Progressing-workshop-V3
PA - 1d Progressing-workshop-V3
Automation Line
Refit
- Progress Updating
https://www.planacademy.com
Plan Academy – Progress Updating in P6 Hands-on Workshop v3 – April 2016
Introduction
This workshop is designed to help you better your Primavera P6 skills.
The best way to get better at using any software package is to simply
work in it often.
This workshop goes hand in hand with Plan Academy’s Progress updating in
Primavera P6 course.
Use your company’s copy of Primavera, or perhaps you have a trial copy with
which to complete this workshop.
Follow each step of the workshop and use the resources and hints listed in the
sidebar as you go. For each step of the workshop, we’ve referenced the course
lesson that will help you to complete the step.
If you run into problems, post a message in our Forums and we’ll get you sorted
out.
Happy planning!
If you are ready to start this Progressing Workshop, go to the next page to get
started.
Objective: Let’s start by importing a project that gets us to a good point for
progressing.
2. Close all projects before you start. Goto File -> Close All.
3. Goto the Projects screen.
4. Goto File -> Import
5. Select Import format as Primavera-PM (XER) and click Next.
6. Select Import type as Project and click Next.
7. Select the Aline-progressing-workshop.xer file from your system and
click Next.
8. Select Import to field and select an EPS node to import the project and
click Next.
9. Select the Default Configuration Layout and click Next to complete the
import.
10. The project file should now be in your database.
11. After importing, open the project.
Objective: Practice creating a project baseline to help monitor the project Resources:
performance.
Maintain & Assign Project
1. On the activity screen Goto -> Project -> Maintain Baselines. Baseline
2. Click Add button on the Maintain Baselines dialogue box.
3. Select Save a copy of the current project as a new baseline option and
click OK.
4. Now a new project baseline will be created as Automation Line Refit-
Workshop4 - B1.
Objective: Practice performing activity status updates. Update the project with Resources:
activity status information for the previous month. How to use progress spotlight
1. Start by rescheduling the project, ensuring the Data Date in the scheduler Progressing a milestone activity
window is set to 2-Jan-2017.
Progressing resource loaded
2. Turn on the Progress Spotlight tool (View -> Progress Spotlight). Drag the
activities
highlighted area on the Gantt Chart to extend to 2-Feb-2017 (Month #1).
3. Update the dates and resource units of the activities in the table below.
For each activity, update the actual data from table on both the Status
and, if application, the Resources tab.
Objective: Practice rescheduling a project and moving the data date after a
status update.
After updating the activity status as of 2-Feb-2017, it’s time to move the Data
Date to reschedule the not-started and in-progress activities in the project.
1. Use this tutorial to understand more about Moving the Data Date in
Primavera P6.
2. Run the project scheduler, Go to Tools->Schedule, change the Data
Date to 2-Feb-2017 and click Schedule.
3. Now check your Gantt Chart to see the results.
Analysis:
1) Which not-started Activities are affected by the late start and finish of
DE-1030?
_______________________________
3. Enter the Layout name as ‘Progress Measurement’ and save it. You can
open this layout at any time to monitor the project’s progress.
Analysis:
Objective: Practice performing activity status updates. Update the project with
activity status information for the previous month.
1. Turn on the Progress Spotlight tool (View -> Progress Spotlight). Drag the
highlighted area on the Gantt Chart to extend to 2-Mar-2017 (Month #2).
2. Now update the activity status for February by updating the activities in
the tables.
DE1020 - -
System
DE1040 48 h
Engineer
SE2000 - -
Activity Actual
Activity Id Activity type Actual start
name finish
Site
SE2010 Task Dependent 27-Feb-17 -
Preparation
Analysis:
This workshop was focused on updating activities with progress in Primavera P6. You should have a good feel for the
updating process now that you’ve completed the workshop.
If you want to check your results, then head-on over to the Progress Updating Course Workshop page. Once there,
follow the link to the Results page.
Take me to the
Workshop Results page!
If you have any questions, please post them in the Forums on our website.
Feedback
We’d love to hear your opinion on this workshop. Did you learn from these exercises? Did we miss something?