Urban Governance and Management

Assignment-10

Week 10

1. A set of activities which are networked in an order and aimed 1 mark


towards achieving the goals is called
a. Process
b. Project Management
c. Project
d. Project cycle
2. Which of the following is correct project life cycle? 2 marks
a. Initialization Process Planning Process, Monitoring and
Controlling process, Execution process, Closing Process
b. Initialization Process, Execution process, Monitoring and
Controlling process, Planning Process, Closing Process
c. Initialization Process, Planning Process, Execution process,
Monitoring and Controlling process, Closing Process
d. Initialization Process, Execution process, Closing Process,
Monitoring and Controlling process, Planning Process
3. Which of the following software can be used for Project 1 mark
management?
a. MS Project
b. Primavera
c. Zoho Project
d. All of the above
4. Project monitoring is sometimes referred to as: 1 mark
a. Process Evaluation
b. Impact Evaluation
c. Evaluation
d. Performance Evaluation

5. At what stage of a development program should monitoring take 1 mark


place?
a. At the beginning of the program
b. At the midpoint of the program
c. At the end of the program
d. Throughout the life of the program
6. What consideration is taken for the Engineering design for the 1 mark
construction?
a. It should be durable and for long life span
b. It should be safe and permanent
c. It should comprise optimum cost
d. All of the above
7. GTS stands for 1 mark
a. Global Trigonometrical Survey
b. Great Trigonometrical Survey
c. Great Time Survey
d. Geological Trigonometrical Survey
8. Which type of projects considered for the trans municipal projects? 1 mark
a. Solid waste management
b. Water supply
c. Sewerage
d. All of the above

9. TOD stands for 1 mark


a. Transportation-oriented development
b. Transit-occupied development
c. Transit-oriented development
d. Transfer-oriented development