Pops Issue No. 2 Presence of Threat Groups (LCM) : (C-1) (C-2) (C-3) (C-4) (C-5)
Pops Issue No. 2 Presence of Threat Groups (LCM) : (C-1) (C-2) (C-3) (C-4) (C-5)
Pops Issue No. 2 Presence of Threat Groups (LCM) : (C-1) (C-2) (C-3) (C-4) (C-5)
Eliminate the risk Reduce possibilities Negative insurgency -Tap other external forces for Internal AFP/PNP
of insurgency of insurgency Security Operations
Strengthen Municipal Task Force Implement Retooled LCE/MTF-ELCAC January 2020 December 2022 RCSP implemented
– ELCAC Community Support Program to 6 identified
(RCSP) conflict afflicted
areas
Conduct needs assessment/ MPDC January 2020 June 2020 BDP approved and
Brgy. Development Planning adopted
Implementation of E-CLIP Provision of Assistance to LCE January 2020 December 2022 Immediate
rebel returnees assistance provided
to FRs
PPSAs Implementing Schedule of Expected Funding Possible Amount
Office Implementation Outputs Requirement Funding
PS MOOE CO Total
Source
Starting Completion
Date Date