DDR N°02 - Sydnw1 - Enf57 - 24122019
DDR N°02 - Sydnw1 - Enf57 - 24122019
SONATRACH
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
M. BOUMEZRAG / T.BENAISSA ENF 57 BERKINE 284 days 5 349 101 280 EXPLORATORY
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAILY NPT: CUM NPT: I.SERVICE:
30,000 in @ 59,00 m 0,00 m 24/12/2019 0,00 hr 0,00 days NONE
ACCIDENT / INCIDENT TOPICS:
No Incident // No Accident
BIT DATA LAST BHA MUD CHECKS
BIT No./Re-Run(U) 1/U / NAME: DRILLING BHA TYPE 1: WBM TIME/LOC 00:01/OUT
BIT RUN No. 1 OD TOOL JTS LENGTH TYPE 2: TIME/LOC /
BIT SIZE (in) 36,000 (in) TYPE No (m) DENSITY (sg) 1,06 ECD (sg)
BIT MANUFACTURE NOV 5,000 HW 4 36,98 DEPTH (m) 60,0 SAND ()
BIT TYPE T11 5,000 XO 1 0,65 FL TEMP (°C) 83 SOLIDS (%) 3,00
BIT IADC CODE 115 9,500 DC 2 18,53 FUN VIS (s/qt) 67 OIL (%)
BIT SERIAL No. OP2841396-1-07 36,000 IBS 1 2,75 PV (cp) 5 H2O (%)
BIT JETS (32nd") 9,500 SS 1 3,75 YP (lbf/100ft²) 47 OIL/H2O / /
9,500 BS 1 2,24 GEL (10sec) (lbf/100ft²) LGS (%) 2,30
BIT TFA (in²) 36,000 BIT 1 1,12 GEL (10m) (lbf/100ft²) HGS (%) 0,47
AV DP: DP/CSG: STRING: 0,0 ANNULUS: 24,0 TQ.on BTM: TQ.off BTM:
AV DC: Jets Vel ( m/s): PITS: 372,0 TOTAL 396,0 BELOW JAR: ABV. JAR:
SURVEY DATA
MD INC AZI TVD N/S (-) E/W (-) VS DLS MD INC AZI TVD N/S (-) E/W (-) VS DLS
(m) (°) (°) (m) (m) (m) (m) (°/30m) (m) (°) (°) (m) (m) (m) (m) (°/30m)
PERSONNEL DATA
COMPANY NO HOURS NAMES COMPANY NO HOURS NAMES
ENAFOR 45 0,00 H.TOUATI + M.BOUTOBZA SH/EXP/GEOLOGIST 2 0,00 A. BENYAYA + S.SNASNI
OIL SERV CMT 4 0,00 Y.BOULHDJEL VIGILANCE 25 0,00 VIGILANCE
FORAQUA 2 0,00 GUARDS ALMAFRIQUE 21 0,00 DJAMEL
ES WASTE MANAGEMENT 3 0,00 M.CHIHAMI + ABBAS ABDELKRIM ENSP MUD LOGGING 4 0,00 M.AOUADI + A.BOUKHELONA
EMEC (MUD ENGINEERS) 2 0,00 Y.BASSI +M.LOULLOU WATER TRUCK LAOUINI 1 0,00 LAMARA KHALIFA
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
M. BOUMEZRAG / T.BENAISSA ENF 57 BERKINE 284 days 5 349 101 280 EXPLORATORY
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAILY NPT: CUM NPT: I.SERVICE:
30,000 in @ 59,00 m 0,00 m 24/12/2019 0,00 hr 0,00 days NONE
ACCIDENT / INCIDENT TOPICS:
No Incident // No Accident
PERSONNEL DATA
COMPANY NO HOURS NAMES COMPANY NO HOURS NAMES
SONATRACH (SH/DOF) 2 0,00 M.BOUMEZRAG + Z.LAOUR
OPERATIONS SUMMARY
FROM-TO HRS PHASE CODE SUB DESCRIPTION FROM-TO NPT NPT DETAIL NPT Co Op Co BILL
00:00-01:00 1,00 36" 05 P G CIRCULATE HOLE CLEAN 60,0-60,0 ENF T1
* Pump 10m3 Hi-Vis pill
01:00-04:00 3,00 36" 06 P I PULL-OUT 36'' BHA TO SURFACE -Freely 60,0-0,0 ENF T1
* Soft break & rack back 36'' BHA, L/D 36'' Bit & Bit sub
04:00-06:30 2,50 36" 12 P F CUT 42'' CONDUCTOR 0,0-0,0 ENF T2
* Rig-up 30'' csg running equipment
06:30-11:30 5,00 36" 12 P Q RUN 30'' CASING 0,0-60,0 ENF T1
* Held PJSM
* Tested Float shoe -ok-
* Fill up every joint
11:30-15:00 3,50 36" 12 P A CENTRALIZE & SET 30" CASING ON IPN BEAMS 60,0-60,0 ENF T2
* Weld beams between 42'' conductor pipe and 30" casing.
* L/D landing joint
15:00-16:00 1,00 36" 12 P P RIH 4 1/2'' STINGER WITH 5" DP 0,0-59,0 ENF T1
* Spaced out with 5'' pup joint
* Tested stinger seals -ok-
16:00-17:30 1,50 36" 12 P M R/U CIRCULATING HEAD AND OILSERV CMT LINE 59,0-59,0 OILSERV T2
* Held PJSM
* Test cement line @ 2000psi -ok
* Break circulation confirme return
17:30-19:15 1,75 36" 12 P B PERFORM 30'' CSG CMT JOB 59,0-59,0 OILSERV T2
* Pumped 06m3 fresh water + Pumped 23m3 cement slurry d=1.90 sg + Displace
with 0.3 m3 water
* Get cement at surface
* Bleed off - no return
19:15-19:45 0,50 36" 12 P H L/D CMT HEAD & OILSERV CMT LINE 59,0-59,0 OILSERV T2
19:45-21:00 1,25 36" 12 P P UNSET STINGER AND POOH 5'' DP 59,0-0,0 ENF T1
* Circulate to clean out DP
21:00-00:00 3,00 36" 14 P A NIPPLE UP 30" RISER & CONNECT FLOW LINE 0,0-0,0 ENF T2
REMARKS:
************************************************** DRILLING WITH TOP DRIVE *******************************************************
** Planned vs Achieved Operations:
- Drill 36" To CSG -Pt planned in -------- 00.70 days ------- Achieved in 0.50 days ---- Gain : 0.20 days
- Interphase 36" x 26 " planned in ------- 01.88 days ------- Achieved in **** days ---- : *** days
**************************** NPT ************************************************************************************************************
TOTAL NPT (Daily // Cumul) = (00.00 hrs // 00.00 Days)
DOWNHOLE NPT (Daily // Cumul) = (00.00 hrs // 00.00 Days)
ENAFOR NPT : T3 (Daily // Monthly) = (00.00 hrs // 00.00 hrs) - NR (Daily // Monthly) = (00,00 hrs // 00.00 hrs)
SH/FOR NPT (Daily // Cumul) = (00.00 hrs // 00.00 Days)
********************************* ON LOCATION *****************************************************************************************
* SH Materiel Programme
* 03 JTS CSG 30''
* 50 Jts CSG 18”5/8 #87.5 K55 BTC
* 250 JTS 13"3/8 CSG 68# N80 BTC
* OILSERV : 02 CMT Cylo + 02 Mix water tank + Oilserv CMT unit () + Air Compressor + Banana truck + 18''5/8 Circ-head BTC
* Remark : CMT unit Rceived 20/12/19, Tested on 23/12/2019.
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
M. BOUMEZRAG / T.BENAISSA ENF 57 BERKINE 284 days 5 349 101 280 EXPLORATORY
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAILY NPT: CUM NPT: I.SERVICE:
30,000 in @ 59,00 m 0,00 m 24/12/2019 0,00 hr 0,00 days NONE
ACCIDENT / INCIDENT TOPICS:
No Incident // No Accident
********************** WATER SUPPLY***********************************************
* Water well SYDNW-101 inside wellsite / Flow rate = 17m3/hr
* 01 WATER TRUCK LAOUINI ON SITE (15m3) : 03463-281-39
* AMANE Water line on service since 19/12/2019.