Professional Documents
Culture Documents
Steel and Cement Rates October 2010TRB - RT1083
Steel and Cement Rates October 2010TRB - RT1083
ABSTRACT
R&B – Common SSR for all Engineering Departments – Fixation of
Cement and Steel Rates for the month of October 2010 (1st month of 2nd
quarter) – Orders – Issued.
------------------------------------------------
TRANSPORT, ROADS AND BUILDINGS(R.I) DEPARTMENT
G.O.Rt.No. 1083 Dated:27.11.2010.
Read the following:
1. G.O.Ms.No. 94, T.R & B, (R.I) Dept., Dated: 16.04.2008.
2. G.O.Rt.No. 1015, T.R & B (R.I) Dept., Dated: 03.11.2010.
3. From ENC(I.W) I&CAD Lr.No.ENC/IW/P&M/ EE.III/
DEE10/AE/13305/ Cement & Steel, Dt. 25.09.2010.
***
ORDER:
In the G.O. 1st read above, orders were issued to adopt price
adjustment for steel and cement every month. Accordingly in the G.O.
2nd read above, orders were issued fixing the rates of Cement and Steel
for the month of September 2010.
5. This order issues with the concurrence of Fin. Dept. vide their U.O.No.
32538/901/A2/Expr.PWD/10, Dated: 25.11.2010.
S.P.SINGH,
PRINCIPAL SECRETARY TO GOVERNMENT
To:
The Engineer-in-Chief (IW),I & CAD Dept. Hyd.
The Engineer-in-Chief (R&B), Admn. & NH, Hyd.
The Director of Works Accounts, A.P., Hyd.
//FORWARDED BY ORDER//
SECTION OFFICER