SECTION 400
Manual mixing shall be permitted only where the width of laying is not adequate for
mechanical operations, as in small-sized jobs. The equipment used for mix-in-place
construction shall be a rotavator or similar approved equipment capable of mixing the
material to the desired degree. If so desired by the engineer, trial runs with the equipment
shall be carried out to establish its suitability for the work.
Moisture content of the loose material shall be checked in accordance with IS : 2720 (Part 2)
and suitably adjusted by sprinkling additional water from a truck mounted or trailer mounted
water tank and suitable for applying water uniformly and at controlled quantities to variable
widths of surface or other means approved by the engineer so that, at the time of
compaction, it is from 1 per cent above to 2 per cent below the optimum moisture content
corresponding to IS: 2720 (Part 8). While adding water, due allowance shall be made for
evaporation losses. After water has been added, the material shall be processed by
mechanical or other approved means like disc harrows, rotavators until the layer is uniformly
wet.
Immediately thereafter, rolling shall start, if the thickness of the compacted layer does not
exceed 100 mm, a smooth wheeled roller of 80 to 100 KN weight may be used. For a
compacted single layer upto 225mm the compaction shall be done with the help of a
vibratory roller of minimum 80 to 100 KN static weight with plain drum or pad foot-drum or
heavy pneumatic tyred roller of minimum 200 to 300 KN weight having a minimum tyre
pressure of 0.7 MN/m2 or equivalent capacity roller capable of achieving the required
compaction. Rolling shall commence at the lower edge and proceed towards the upper edge
longitudinally for portions having unidirectional crossfall and super-elevation and shall
commence at the edges and progress towards the centre for portions having crossfall on
both sides.
400-1
SECTION 400
Each pass of the roller shall uniformly overlap not less than one-third of the track made in
the preceding pass. During rolling, the grade and crossfall (camber) shall be checked and
any high spots or depressions, which becomes apparent, corrected by removing or adding
fresh material. The speed of the roller shall not exceed 5 km per hour. Rolling shall be
continued till the density achieved is at least 98 per cent of the maximum dry for the material
determined as per IS : 2720 (Part 8). The surface of any layer of material on completion of
compaction shall be well closed, free from movement under compaction equipment and
from compaction planes, ridges, cracks or loose material. All loose, segregated or otherwise
defective areas shall be made good to the full thickness of layer and re-compacted.
400.1.5 Surface finish and quality control of work - The surface finish of construction
shall conform to the requirements of clause 900.2. Control on the quality of materials and
works shall be exercised by the engineer in accordance with section 900.
400.1.6. Arrangements for traffic - During the period of construction, arrangement of traffic
shall be maintained in accordance with clause 100.12.
400.1.8. Rate - The contract unit rate for granular sub-base shall be payment in for carrying
out the required operations including full compensation for:
(i) making arrangements for traffic according to clause 100.12 except for initial treatment to
verges, shoulders and construction of diversions;
(ii) furnishing all materials to be incorporated in the work including all royalties, fees, rents
where necessary and all leads and lifts;
(iii) all labour, tools, equipment and incidentals to complete the work to the specifications;
(iv) carrying out the work in part widths of road where directed; and
400-2
SECTION 400
400.2.2. Materials
400.2.2.1. Soil - Except when otherwise specified, the soil used for stabilisation shall be the
local clayey soil having a plasticity index greater than 8.
400.2.2.2 Lime - Lime for the lime-soil stabilisation work shall be commercial dry lime slaked
at site or pre-slaked lime delivered to the site in suitable packing. Unless otherwise
permitted by the engineer, the lime shall have purity of not less than 70 per cent by weight of
quick–lime (CaO) when tested in accordance with IS: 1514. Lime shall be properly stored to
avoid prolonged exposure to the atmosphere and consequent carbonation, which would
reduce its binding properties.
400.2.2.4 Water - The water to be used for the lime stabilisation shall be clean and free
from injurious substances. Potable water shall be preferred.
400.2.3.2. Degree of pulverisation - For lime stabilisation, the soil before addition of
stabiliser, shall be pulverised using agricultural implements like disc harrows and rotavators
to the extent that it passes the requirements set out in Table 400-3 when tested.
The equipment used for mix-in-place construction shall be a rotavator or similar approved
equipment capable of pulverising and mixing the soil with additive and water to specified
degree to the full thickness of the layer being processed, and of achieving the desired
degree of mixing and uniformity of the stabilised material. If so desired by the engineer, trial
runs with the equipment shall be carried out to establish its suitability for work.
The thickness of any layer to be stabilised shall be not less than 100 mm when compacted.
The maximum thickness shall be 200 mm, provided the plant is accepted by the engineer.
400.2.3.4 Mix-in-place method of construction - Before deploying the equipment, the soil
after it is made free of undesirable vegetation or other deleterious matter shall be spread
uniformly on the prepared subgrade in a quantity sufficient to achieve the desired
compacted thickness of the stabilised layer. Where single-pass equipment is to be
employed, the soil shall be lightly rolled at the discretion of the engineer.
The equipment used shall either be of single-pass or multiple pass type. The mixers shall be
so set that it cuts slightly into the edge of the adjoining lane processed previously so as to
ensure that all the material forming a layer has been properly processed for the full width.
400.2.3.5 Construction with manual means - Where manual mixing is permitted, the soil
from borrow areas shall first be freed of all vegetation and other deleterious matter and
placed on the prepared subgrade. The soil shall then be pulverised by means of crow-bars,
pick axes or other means approved by the engineer.
Water in requisite quantities may be sprinkled on the soil for aiding pulverisation. On the
pulverised soil, the blending material (s) in requisite quantities shall be spread uniformly and
mixed thoroughly by working with spades or other similar implements till the whole mass is
uniform. After adjusting the moisture content to be within the limits mentioned later, the
mixed material shall be levelled up to the required thickness so that it is ready to be rolled.
400.2.3.6 Addition of lime - Lime may be mixed with the prepared material either in slurry
form or dry state at the option on the contractor with the approval of the engineer.
400-4
SECTION 400
Dry lime shall be prevented from blowing by adding water to the lime or other suitable
means selected by the contractor, with the approval of the engineer. The tops of windrowed
material may be flattened or slightly trenched to receive the lime. The distance to which lime
may be spread upon the prepared material ahead of the mixing operation shall be
determined by the engineer.
No traffic other than the mixing equipment shall be allowed to pass over the spread lime until
after completion of mixing.
Mixing or remixing operations, regardless of equipment used, shall continue until the
material is free of any white streaks or pockets of lime and the mixture is uniform.
Non-uniformity of colour reaction, when the treated material is tested with the standard
phenolphthalein alcohol indicator will be considered evidence of inadequate mixing.
Moisture content for compaction - The moisture content at compaction checked vide IS:
2720 (Part 2) shall neither be less than the optimum moisture content corresponding to IS :
2720 (Part 8) nor more than 2 per cent above it enclosed Annexure 300-A.4s.
400.2.3.8 Rolling - Immediately after spreading, grading and levelling of the mixed material,
compaction shall be carried out with approved equipment preceded by a few passed of
lighter rollers if necessary. Rolling shall commence at edges and progress towards the
centre, except at superelevated portions where it shall commence at the inner edge and
progress towards outer edge. During rolling the surface shall be frequently checked for
grade and crossfall (camber) and any irregularities corrected by loosening the material and
removing/adding fresh material. Compaction shall continue until the density achieved is at
least 98 per cent of the maximum dry density for the material determined in accordance with
IS : 2720 (Part 8).
Care shall be taken to see that the compaction of lime stabilised material is completed within
three hours of its mixing or such shorter period as may be found necessary in dry weather.
During rolling it shall be ensured that roller does not bear directly on hardened or partially
hardened treated material previously laid other than what may be necessary for achieving
the specified compaction at the joint. The final surface shall be well closed, free from
movement under compaction planes, ridges, cracks or loose material. All loose or
segregated or otherwise defective areas shall be made good to the full thickness of the layer
and recomputed.
400.2.3.9 Curing - The sub-base course shall be suitably cured for a minimum period of 7
days after which subsequent pavement courses shall be laid to prevent the surface from
drying out and becoming friable. No traffic of any kind shall ply over the completed sub-base
unless permitted by the engineer.
400-5
SECTION 400
400.2.4 Surface finish and quality control of work - The surface finish of construction
shall conform to the requirements of clause 900.2. Control on the quality of materials and
works shall be exercised by the engineer in accordance with section 900.
400.2.5 Strength - When lime is used for improving the subgrade, the soil-lime mix shall be
tested for its CBR value, When lime stabilised soil is used in a sub-base, it shall be tested for
unconfined compressive strength (ucs) at 7 days. In case of variation from the design
CBR/UCS, in-situ value being lower, the pavement design shall be reviewed based on the
actual CBR/UCS values. The extra pavement thickness needed on account of lower
CBR/UCS value shall be constructed by the contractor at his own cost, if so specified in the
contract.
400.2.8 Rates - The contract unit rate for lime stabilised soil sub-base shall be payment in
full for carrying out the required operations including full compensation for all components
listed in clause 400.1.8 (I) to (v).
400.3.2 Materials
400.3.2.1 Material to be stabilised - The material used for cement treatment shall be soil
including sand and gravel, laterite, kankar, brick aggregate, crushed rock or slag or any
combination of these. For use in a sub-base course, the material shall have a grading
shown in Table 400-4; it shall have a uniformity coefficient not less than 5, capable of
producing a well closed surface finish. For use in a base course, the material shall be
sufficiently well graded to ensure a well-closed surface finish and have a grading within the
range given in Table 400-4, if the material passing 425 micron sieve is plastic, it shall have a
liquid limit nor greater than 45 per cent and a plasticity index not greater than 20 per cent
determined in accordance with IS : 2720 (Part 5). The physical requirements for the
material to be treated with cement for use in a base course shall be same as for Grading I
Granular Sub-base, clause 400.1.2.2.
400-6
SECTION 400
(i) Plasticity modulus, expressed as the product of PI of soil and percent fraction passing
425 micron sieve, should not exceed 250 and
(ii) Uniformity coefficient of soil should be greater than 5 and preferably greater than 10.
(iv) Soils with soluble sulphate or carbonate concentration greater than 0.2 percent.
400.3.2.3 Cement:
Cement for cement stabilisation shall comply with the requirements of IS : 269, 455 OR
1489.
400.3.2.2 The amount of cement will depend on the type of soil, design requirements, and
overall economic considerations. Because of difficulties of uniform mixing, however, cement
content of even 2 percent may be necessary in the case of hand mixing. In every case,
cement concentration must be expressed as per cent weight of the dry soil.
Lime: If needed for pre-treatment of highly clayey soils, clause 400.2.2.2 shall apply.
400-7
SECTION 400
400.3.2.4. Water - The water to be used for cement stabilisation shall be clean and free
from injurious substances. Potable water shall be preferred.
400.3.3.2. Degree of pulverisation - For stabilisation, the soil before addition of stabilizer,
shall be pulverised, where necessary, to the extent that it passes the requirements as set out
in Table 400-5 when tested.
400.3.3.3 Clauses 400.2.3.3. to 400.2.3.5 shall apply as regards spreading and mixing the
stabiliser except that cement or lime plus cement as the case may be, shall be used as the
stabilising material.
400.3.3.4 Moisture content for compaction - The moisture content at compaction checked
vide IS: 2720 (Part 2) shall not less than the optimum moisture content corresponding to IS :
2720 (Part 8) nor more than 2 per cent above it.
400.3.3.5 Rolling - clause 400.2.3.8 shall apply except that care shall be taken to see that
the compaction of cement stabilised material is completed within two hours of its mixing or
such shorter period as may be found necessary in dry weather.
400.3.3.6 Curing - The sub-base/base course shall be suitably cured for 7 days.
Subsequent pavement course shall be laid soon after to prevent the surface from drying out
and becoming friable. No traffic of any kind shall ply over the completed sub-base unless
permitted by the engineer.
400.3.4 Surface finish and quality control of works - The surface finish of construction
shall conform to the requirements of clause 900.2.
400-8
SECTION 400
400.3.5 Strength - Control on the quality of materials and works shall be exercised by the
engineer in accordance with section 900.
Cement treated soil sub-base/ base shall be tested for the unconfined compressive strength
(UCS) value at 7 days, actually obtained in situ. In case of variation from the design UCS, in
situ value being on lower side, prior to proceeding with laying of base/surface course on it,
the pavement design shall be reviewed for actual UCS value.
The extra pavement thickness needed on account of lower UCS shall be constructed by the
contractor at his own cost.
400.3.6 Arrangements for traffic - During the period of construction, arrangement of traffic
shall be maintained in accordance with clause 100.12.
400.3.8 Rates - The contract Unit rate for cement treated soil sub-base/base with
pretreatment with lime if required shall be payment in full for carrying out the required
operations including full compensation for all components listed in clause 400.1.8. (I) to (v).
400.4.1.2 It is, however, not desirable to lay water bound macadam on an existing thin
black topped surface without providing adequate drainage facility for water that would get
accumulated at the interface of existing bituminous surface and water bound macadam.
400.4.2 Materials
400.4.2.1.Coarse aggregates - Coarse aggregates shall be either crushed or broken stone,
crushed slag, overburnt (Jhama) brick aggregates or any other naturally occurring
aggregates such as kankar and laterite of suitable quality. Materials other than crushed or
broken stone and crushed slag shall be used in sub-base courses only. If crushed gravel/
shingle is used, not less than 90 per cent by weight of the gravel/shingle pieces retained on
4.75 mm sieve shall have at least two fractured faces. The aggregates shall conform to the
physical requirements set forth in Table 400-6. The type and size range of the aggregate
shall be specified in the contract or shall be as specified by the engineer. If the water
absorption value of the coarse aggregate is greater than 2 per cent, the soundness test shall
400-9
SECTION 400
be carried out on the material delivered to site as per IS : 2386 (Part 5)- copy enclosed as
Annexure.
400.4.2.2. Crushed or broken stone - The crushed or broken stone shall be hard, durable
and free from excess flat, elongated, soft and distinguished particles, dirt and other
deleterious material.
Table 400-6, Physical requirements of coarse aggregates for water bound macadam for
sub– base courses
Test Test Method Requirements
1 * Los Angeles Abrasion IS:2386 40 percent (Maxi.)
value
Or IS:2386 (Part-4) or 30 percent (Maxi.)
*Aggregate impact value IS;5640**
2 Combined Flakiness and IS:2386 (Part - 1) 30 percent (Maxi.)
Elongation indices (Total)***
* Aggregate may satisfy requirements of either of the two sets.
** Aggregates like brick metal, kankar, laterite etc. which get softened in presence of
water shall be tested for Impact value under wet condition in accordance with IS :
5640.
*** The requirement of flakiness index and elongation index shall be enforced only in the
case of crushed broken stone and crushed slag.
400.4.2.3. Crushed slag - Crushed slag shall be made from air-cooled blast furnace slag. It
shall be of angular shape, reasonably uniform in quality and density and generally free from
thin, elongated and soft pieces, dirt or other deleterious materials. The weight of crushed
slag shall not be less than 11.2 KN per m3 and the percentage of glossy material shall not
be more than 20. It should also comply with the following requirements:
400.4.2.4. Overburnt brick aggregates - Brick aggregates shall be made from overburnt
bricks or brick bats and be free from dust and other objectionable and deleterious materials.
63 mm 25-60
45 mm 0-15
22.4 mm 0-5
2 63 to 45 mm 90 mm 100
63 mm 90-100
53 mm 25-75
45 mm 0-15
22.4 mm 0-5
3 53 to 22.4 mm 63 mm 100
53 mm 95-100
45 mm 65-90
22.4 mm 0-10
11.2 mm 0-5
Note: The compacted thickness for a layer with Grading 1 shall be 100 mm while for
layer with other gradings i.e., 2 & 3, it shall be 75 mm.
400.4.2.6. Screenings - Screenings to fill voids in the coarse aggregate shall generally
consist of the came material as the coarse aggregate. However, where permitted,
predominantly non-plastic material such as moorum or gravel (other than rounded river
borne material) may be used for this purpose provided liquid limit and plasticity index of
such material are below 20 and 6 respectively and fraction passing 75 micron sieve does
not exceed 10 per cent.
Screenings shall conform to the grading set forth in Table 400-8. The consolidated details of
quantity of screenings required for various grades of stone aggregates are given in Table
400 – 9. The table also gives the quantities of materials (loose) required for 10 m2 for sub-
base base compacted thickness of 100/75 mm. The use of screenings shall be omitted in
the case of soft aggregates such as brick metal, kankar, laterites, etc. as they are likely to
get crushed to a certain extent under rollers.
Table 400 – 8, Grading for screenings
Grading Size of IS Sieve Per cent by weight
classification screenings designation passing the IS sieve
A 13.2 mm 13.2 mm 100
11.2 mm 95-100
5.6 mm 15-35
180 mcn 0-10
B 11.2 mm 11.2 mm 100
5.6 mm 90-100
180 mcn 15-35
Table 400 – 9, Approximate quantities of coarse aggregates and screenings required for 100
/ 75 mm compacted thickness of water bound macadam (wbm) sub-base /
base course for 10 m2 area
Classific Size Compact Loose Screenings
ation Range thickness Qty. Stone screening Crushable type such as mooram
or gravel
400-11
SECTION 400
The quantity of binding material where it is to be used, will depend on the type of
screenings. Generally, the quantity required for 75 mm compacted thickness of water bound
macadam will be 0.06 – 0.09 m3 / 10m2 and 0.08 – 0.10 m3/ 10 m2 for 100 mm compacted
thickness.
The above mentioned quantities should be taken as a guide only, for estimation of quantities
for construction etc.
Application of binding materials may not be necessary when the screenings used are of
crushable type such as moorum or gravel.
As far as possible, laying water bound macadam course over an existing thick bituminous
layer may be avoided since it will cause problems of internal drainage of the pavement at
the interface of two courses. It is desirable to completely pick out the existing thin
bituminous wearing course where water bound macadam is proposed to be laid over it.
However, where the intensity of rain is low and the interface drainage facility is efficient,
water bound macadam can be laid over the existing thin bituminous surface by cutting 50
mm x 50 mm furrows at an angle of 45 degrees to the centre line of the pavement at one
metre intervals in the existing road. The directions and depth of furrows shall be such that
400-12
SECTION 400
they provide adequate bondage and also serve to drain water to the existing granular base
course beneath the existing thin bituminous surface.
400.4 3.2 Inverted choke - If water bound macadam is to be laid directly over the subgrade,
without any other intervening pavement course, a 25 mm course of screenings (Grading B)
or coarse sand shall be spread on the prepared subgrade before application of the
aggregates is taken up. In case of a fine sand or silty or clayey subgrade, it is advisable to
lay 100 mm insulating layer of screening or coarse sand on top of fine grained soil, the
gradation of which will depend upon whether it is intended to act as a drainage layer as well.
As a preferred alternative to inverted to act as a drainage layer as well. As a preferred
alternative to inverted choke, appropriate geosynthetics performing functions of separation
and drainage may be used over the prepared subgrade as directed by the engineer. section
700 shall be applicable for use of geosynthetics.
The spreading shall be done from stockpiles along the side of the roadway or directly from
vehicles. No segregation of large or fine aggregates shall be allowed and the coarse
aggregate as spread shall be of uniform gradation with no pockets of fine material.
The surface of the aggregates spread shall be carefully checked with templates and all high
or low spots remedied by removing or adding aggregates as may be required. The surface
shall be checked frequently with a straight edge while spreading and rolling so as to ensure
a finished surface as per approved drawings.
The coarse aggregates shall not normally be spread more than 3 days in advance of the
subsequent construction operations.
400.4.3.4 Rolling - Immediately following the spreading of the coarse aggregate, rolling
shall be started with three wheeled power rollers of 80 to 100 KN capacity or tandem or
vibratory rollers of 80 to 100 KN static weight. The type of roller to be used shall be
approved by the engineer based on trial run.
Except on superelevated portions where the rolling shall proceed from inner edge to the
outer, rolling shall begin from the edges gradually progressing towards the centre. First the
edge/ edges shall be compacted with roller running forward and backward. The roller shall
400-13
SECTION 400
then move inward parallel to the centre line of the road, in successive passes uniformly
lapping preceding tracks by at least one half width.
Rolling shall be discontinued when the aggregates are partially compacted with sufficient
void space in them to permit application of screenings. However, where screenings are not
to be applied, as in the case of crushed aggregates like brick metal, laterite and kankar,
compaction shall be continued until the aggregates are thoroughly keyed. During rolling,
slight sprinkling of water may be done, if necessary. Rolling shall not be done when the
subgrade is soft or yielding or when it causes a wave-like motion in the subgrade or sub-
base course.
The rolled surface shall be checked transversely and longitudinally, with templates and any
irregularities corrected by loosening the surface, adding or removing necessary amount of
aggregates and re-rolling until the entire surface conforms to desired crossfall (camber) and
grade. In no case shall the use of screenings be permitted to make up depressions.
Material which gets crushed excessively during compaction or becomes segregated shall be
removed and replaced with suitable aggregates.
It shall be ensured that shoulders are built up simultaneously along with water bound
macadam courses as per clause 400.7.4.1.
400.4.3.5 Application of screenings - After the coarse aggregate has been rolled to clause
400.4.3.4, screenings to completely fill the interstices shall be applied gradually over the
surface. These shall not be damp or wet at the time of application. Dry rolling shall be done
be damp or wet at the time of application. Dry rolling shall be done while the screenings are
being spread so that vibrations of the roller cause them to settle into the voids of the coarse
aggregates.
The screenings shall not be dumped in piles but be spread uniformly in successive thin
layers either by the spreading motions of hand shovels or by mechanical spreaders, or
directly from tipper with suitable grit spreading arrangement. Tipper operating for spreading
the screenings shall be so driven as not to disturb the coarse aggregate.
The screenings shall be applied at a slow and uniform rate (in three or more applications) so
as to ensure filling of all voids. This shall be accompanied by dry rolling and becoming with
mechanical brooms, hand-brooms or both. In no case shall the screenings be applied so
fast and thick as to form cakes or ridges on the surface in such a manner as would prevent
filling of voids or prevent the direct bearing of the roller on the coarse aggregate. These
operations shall continue until no more screenings can be forced into the voids of the coarse
aggregate.
The spreading, rolling, and brooming of screenings shall be carried out in only such lengths
of the road which could be completed within one day’s operation.
400-14
SECTION 400
400.4.3.6 Sprinkling of water and grouting - After the screenings have been applied, the
surface shall be copiously sprinkled with water, swept and rolled. Hand brooms shall be
used to sweep the wet screenings into voids and to distribute them evenly. The sprinkling,
sweeping and rolling operation shall be continued, with additional screenings applied as
necessary until the coarse aggregate has been thoroughly keyed, well-bonded and firmly set
in its full depth and a grout has been formed of screenings. Care shall be taken to see that
the base or subgrade does not get damaged due to the addition of excessive quantities of
water during construction.
In case of lime treated soil sub-base, construction of water bound macadam on top of it can
cause excessive water to flow down to the lime treated sub-base before it has picked up
enough strength (is still “green”) and thus cause damage to the sub-base layer. The laying
of water bound macadam layer in such cases shall be done after the sub-base attains
adequate strength, as directed by the engineer.
400.4.3.8 Setting and drying - After the final compaction of water bound macadam course,
the pavement shall be allowed to dry overnight. Next morning hungry spots shall be filled
with screenings or binding material as directed, lightly sprinkled with water if necessary and
rolled. No traffic shall be allowed on the road until the macadam has set. The engineer shall
have the discretion to stop hauling traffic from using the completed water bound macadam
course, if in his opinion it would cause excessive damage to the surface.
The compacted water bound macadam course should be allowed to completely dry and set
before the next pavement course is laid over it.
400.4.4.2. Control on the quality of materials and works shall be exercised by the engineer
in accordance with section 900.
400-15
SECTION 400
400.4.4.3. The water bound macadam work shall not be carried out when the atmospheric
temperature is less than 0 deg. C. in the shade.
400.4. Arrangement for traffic - During the period of construction, the arrangement of
traffic shall be done as per clause 100.12.
400.4.7 Rate - The contract unit rate for water bound macadam sub-base/base course shall
be payable in full compensation for all components listed in clause 400.1.8 (I) to (v)
including arrangement of water used in the work as approved by the engineer.