Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

* THE ENERGY SECTOR *

Date: February 25, 2013
Presented by: Thema Molubi
PRESENTATION OVERVIEW  

1. POWER SUPPLY PLAN 

2. TRANSMISSION GRID DEVELOPMENT PLAN
POWER SUPPLY PLAN 
POWER SUPPLY PLAN OVERVIEW 
1. Electricity Demand Forecast 

2. Power Supply Plan (2013 – 2020)

3. Demand – Supply Balance

4. Long Term Generation Projects 
Botswana  Electricity Demand Forecast 
Energy Demand Forecast
 7,000 Peak Demand (MW)
1000
 6,000
900
 5,000 800
Energy (GWh)

700
 4,000
600
 3,000 500
400
 2,000
300
 1,000 200
 ‐ 100
2012 2013 2014 2015 2016 2017 2018 2019 2020 0
2012 2013 2014 2015 2016 2017 2018 2019 2020
Energy Demand (Revised) GWh Energy Demand (DF Low) GWh
Peak Demand  MW
Energy Demand (DF Likely) GWh

YEAR UNIT 2012 2013 2014 2015 2016 2017 2018 2019 2020

Peak Demand  MW 578 644 681 711 744 773 854 877 902
Energy Demand  3,676 3,890 4,038 4,177 4,320 4,468 5,547 5,660 5,801
GWh
(Revised)
Energy Demand 3,679 3,878 3,995 4,096 4,181 4,292 4,579 4,651 4,868
GWh
(D/Forecast Low)
Energy Demand 3,864 4,298 4,499 4,666 4,852 5,003 5,547 5,660 5,801
GWh
(D/Forecast Likely)
Power Supply Plan (2013 – 2020) 
Sources 2013 2014 2015 2016 2017 2018 2019 2020
MW MW MW MW MW MW MW MW
Morupule  B

264 528 528 528 528 528 528 528


Morupule B 5&6
0 0 0 132 264 264 264 264

Morupule  A
0 60 60 116 116 116 116 116

APR Rental 
70 0 0 0 0 0 0 0

ORAPA  90MW

90 90 90 90 90 90 90 90

SAPP Imports
100
+ 100 100 0 0 0 0 0
200
Capacity Balance (Best Case Scenario)
2012 ‐ 2020 Capacity Balance
1200

1000
Capacity (MW)
800

600

400

200

0
2012 2013 2014 2015 2016 2017 2018 2019 2020
Orapa 90MW 90 90 90 90 90 90 90 90 90
Emergency (70MW) 70 70 0 0 0 0 0 0 0
Eskom (Imports) 350 100 100 100 0 0 0 0 0
Moruple B (5&6) 0 0 0 0 132 264 264 264 264
Morupule B 0 528 528 528 528 528 528 528 528
Morupule A 0 0 60 60 116 116 116 116 116
Peak Demand 580 644 681 711 744 773 854 877 902

Total Supply
510 788 778 778 866 998 998 998 998
Peak Demand
580 644 681 711 744 773 854 877 902 

Capacity Balance ‐70 144 97 67 122 225 144 121 96


Assumptions
 Morupule A: On Care & Maintenance. Return to service 2015/16; 60MW 
secured by Winter of 2014. 

 Morupule B: In full commercial operation by August 2013;

 70MW Rented Diesel: Contract up to December 2013; 

 Eskom Imports: 100MW (2013 – 2015);

 Eskom Imports: 200MW (1st January  to 31st July 2013); and

 New Generation Capacity: Morupule B Units 5&6 secured 2016/17.
Supply ‐ Demand Outlook (2012 ‐ 2020)
1200

1000

800
MW

600

400

200

0
2012 2013 2014 2015 2016 2017 2018 2019 2020
Orapa Facility 90 90 90 90 90 90 90 90 90
APR 70 70 70 0 0 0 0 0 0 0
SNEL 0 0 0 0 0 0 0 0 0
Eskom 150 100 100 100 0 0 0 0 0
Morupule B2 0 0 0 0 264 264 264 264 264
Morupule B 0 132 528 528 528 528 528 528 528
Morupule A 20 0 0 100 100 100 100 100 100
Demand 578 598 655 713 729 745 766 797 829
Long Term Generation Projects 
Capacity Timing Remarks
Sources (MW)
Morupule B 5&6
300 2017 Bankable Feasibility Study in place

Call for Expression of Interest being prepared 
IPP Green Field Green field coal fired project at planning stage
300 2019 Project linked to coal exports, long term coal 
monetization strategy – Coal Road Map
Request for information to be released.
Solar Thermal 

100 TBA Bankable Feasibility Study Stage. (Report Dec 2012)


100MW CSTP; Central Tower with 4hrs TES at Jwaneng

Coal Bed Methane Timing of Commercial Availability of CBM in sufficient 


90 + ?? quality and quantity to operate a gas fired power station 
remains unknown.

1.3MW Pilot project commissioned in August 2012 
75MW TBA (Phakalane).
TRANSMISSION GRID DEVELOPMENT PLAN
GRID PLAN OVERVIEW 
1. Tx Grid Development Constraints

2. Tx Grid Development Plan

2. Tx Grid Capital Outlay (2013 – 2018)
Transmission Grid Constrains
Main Challenges to be addressed 

1. Lack of Grid Access in the 
Northwest Region

2.  Demand Growth Outstripping 
Grid Capacity in the South

3.  Inadequate Transmission 
Impact of Challenges 
capacity to support new 
1. Suppression of Economic 
generation investments (IPPs 
development (mining)
and Public Sector) 
2. Suppression of Coal Beneficiation 
3. Unreliable Power Supply in the 
South 
Transmission Grid Expansion Plan
ZIZABONA

SOUTHERN 
SYSTEM
ZIZABONA PROJECT

To Maun
SOUTHERN SYSTEM REINFORCEMENT & EXPANSION PLAN
From Morupule

ISANG
Jwaneng
Substation

Mochudi
Free Zone
Innovation Hub
Airport Road
Thamaga
Phakalane
Rakola Segoditshane
Spitzkop
Broadhurst
Mogoditshane

Molepolole
Government Enclave

Gaborone Central Gaborone East


Tlokweng

Kanye

Mmakgodumo
Gaborone South
Kgale View
KEY SOUTH
Proposed Existing AFRICA
Substation
132kV Line
Lobatse Woodhall Ramotswa
220kV Line Dwaalboom
400kV Line 
Securing Power Supply Objectives (Access and Reliability) 
No Objective Deliverable

1 Expand Transmission Grid  Executed Transmission Projects as listed Below


Capacity as per Master Plan

PROJECT TIMING ESTIMATE Benefit


COST
(BWP)
North West Grid Extension  2013 ‐ 2017 3.5 billion New Customers 
(400/220/132kV) (Mining)
ZIZABONA 2013 ‐ 2016 100 million Regional Access

Rakola 220/132kV S/S & Lines 2013 ‐ 2015 476 million Secure Power Supply

Ramotswa 132/11kV S/S 2014 ‐ 2015 70 million Secure Power Supply


Mochudi 132/33kV S/S 2014 ‐ 2015 100million Secure Power Supply
Tlokweng 132/11kV S/S 2014 ‐ 2015 48 million Secure Power Supply
Govt. Enclave 132/11kV S/S 2017 ‐2018 70 million Secure Power Supply
TOTAL COST  BWP 4.364 Billion
THANK YOU 
KE A LEBOGA 

You might also like