Broad Status Report: Thermal Power Projects
Broad Status Report: Thermal Power Projects
Broad Status Report: Thermal Power Projects
GOVERNMENT OF INDIA
विद्युत मंत्रालय
MINISTRY OF POWER
1.B Year Wise Sector Wise Thermal Capacity Addition Achievement against Revised Target during
12th Plan:
S. Project Name LOA Unit Fuel Targeted Org. Ant. Trial Achiev Actual/ Ant.
No. Date No Cap. Comm. Run/ COD ed Date of Cap.
(MW) Sched. at the Cap. Addition
Beginning (MW)
of the year
CENTRAL SECTOR
1 Nabi Nagar STPP Jan-13 U-1 Coal 660 Jan-17 May-19 660 12.07.19(A)
4 Khargone STPP St-I Mar-15 U-1 Coal 660 Mar-19 Aug-19 660 29.09.19(A)
5 Darlipalli STPP St-I Feb-14 U-1 Coal 800 Feb-18 Aug-19 800 30.12.19(A)
6 Tanda TPP St- II Sep-14 U-5 Coal 660 Sep-17 Sep-19 660 28.09.19(A)
7 Neyveli New TPP Jun-11 U-1 Lignite 500 Mar-18 Apr-19 500 20.12.19(A)
STATE SECTOR
1 Dr.Narla Tata Rao Dec-15 U-8 Coal 800 Jun-19 Feb-20 Oct-20
TPS Stage-V
2 Namrup CCGT Feb-09 ST Gas 36.15 Jan-12 Nov-19 Mar-20
3 Wanakbori TPS Extn. Oct-14 U-8 Coal 800 Oct-18 Nov-19 800 12.10.19(A)
6 Suratgarh SCTPP Mar-13 U-7 Coal 660 Jul-16 Nov-19 660 15.03.20 (A)
ADDITIONAL PROJECTS
PRIVATE SECTOR
State Project Name Impl Agency Unit No LOA Date BTG Targeted Actual Cap. Comm. Date COD
Supplier Cap. comm. Envisaged at the Ant. /Act(A)
(MW) (MW) beginning of year
CENTRAL SECTOR
Chhattisgarh Sipat -I NTPC U-3 Apr-04 Others 660 660 06/12 02.06.12(A) 01.08.2012
Haryana Indira Gandhi TPP APCPL U-3 Jul-07 BHEL 500 500 12/12 07.11.12(A) 26.04.2013
Jharkhand Kodarma TPP DVC U-2 Jun-07 BHEL 500 500 12/12 15.02.13(A) 14.06.2014
Maharashtra Mouda TPP NTPC U-1 Nov-08 BHEL 500 500 07/12 19.04.12(A) 13.03.2013
Maharashtra Mouda TPP NTPC U-2 Nov-08 BHEL 500 29.03.13(A) March 14
MP Vindhyachal TPP-IV NTPC U-11 Jan-09 BHEL 500 500 07/12 14.06.12(A) 01.03.2013
MP Vindhyachal TPP-IV NTPC U-12 Jan-09 BHEL 500 22.03.13(A) March 14
TN Vallur TPP Ph-I NTECL U-2 Aug-07 BHEL 500 500 02/13 28.02.13(A) 25.08.2013
Tripura Tripura Gas ONGC Module-1 Jun-08 BHEL 363.3 363.3 11/12 03.01.13 (A) 04.01.2014
UP Rihand TPP-III NTPC U-5 Feb-09 BHEL 500 500 06/12 25.05.12(A) 19.11.2012
Total Central Sector 4023.3 5023.3
STATE SECTOR
Chhattisgarh Korba West Extn.St.III TPP CSEB U-5 BEHL 500 22.03.13(A) 05.09.2013
Chhattisgarh Marwa TPP CSEB U-1 Apr-08 BHEL 500 02/13 Slipped
Delhi Pragati CCGT - III PPCL GT-3 May-08 BHEL 250 250 08/12 27.06.12(A) 28.10.2013
Pipavav CCPP GSECL Block-2 Dec-07 BHEL 351 351 01/13 27.03.13(A) 27.03.2013
Gujarat
Ukai TPP Extn GSECL U-6 Sep-07 BHEL 490 490 12/12 05.03.13(A) 08.06.2013
Ramgarh CCGT RRVUNL GT Aug-09 BHEL 110 110 01/13 20.03.13(A) 06.12.2013
Rajasthan
Ramgarh CCGT RRVUNL ST-1 BHEL 50 02/13 Slipped
MP Satpura TPP Extn. MPPGCL U-10 Mar-08 BHEL 250 250 02/13 22.03.13(A) 18.08.2013
Mettur TPP Ext TNEB U-1 Aug-08 Chinese 600 600 06/12 11.10.12(A) 12.10.2013
TN
North Chennai Extn. TNEB U-2 Aug-08 BHEL 600 600 03/13 09.03.13(A) 08.05.2014
Harduaganj Ext UPRVUNL U-9 Jun-06 BHEL 250 250 05/12 25.05.12(A) 10.10.2013
UP Parichha Extn UPRVUNL U-5 Jun-06 BHEL 250 250 06/12 24.05.12(A) 17.07.2012
Parichha Extn UPRVUNL U-6 250 250 09/12 11.03.13(A) 18.04.2013
Total -State Sector 3951 3911
PRIVATE SECTOR
Simhapuri TPP Ph-1 Madhucon Projects Ltd. U-2 Jan-09 Chinese 150 150 09/12 02.07.12(A) 15.07.2012
AP Thamminapatnam TPP-I Meenakshi Energy Pvt. Ltd. U-1 Chinese 150 150 08/12 09.09.12(A) 07.10.2012
Aug-09
Thamminapatnam TPP-I Meenakshi Energy Pvt. Ltd. U-2 150 11/12 Slipped
Kasaipalli TPP M/s ACB (India) U-2 Nov-08 Chinese 135 135 06/12 21.06.12(A) 21.06.2012
Salora TPP M/s Vandna Vidyut U-1 Nov-08 Chinese 135 12/12 Slipped
Chhattisgarh
Swastik Korba TPS ACB U-1 Others 25 06/12 Slipped
Ratija TPP SCPL U-1 Chinese 50 04.02.13(A) 27.02.2013
Mundra Ultra Mega TPP Tata Power Co. U-2 May-07 Others 800 800 12/12 25.07.12(A) 28.07.2012
Mundra Ultra Mega TPP Tata Power Co. U-3 May-07 Others 800 16.10.12(A) 27.10.2012
Mundra Ultra Mega TPP Tata Power Co. U-4 May-07 Others 800 16.01.13(A) 21.01.2013
Gujarat
Mundra Ultra Mega TPP Tata Power Co. U-5 Jun-07 Others 800 18.03.13(A) 22.03.2013
UNO-SUGEN CCPP Torrent Power Ltd. Mod-1 Others 382.5 20.01.13(A) 04.04.2013
Salaya TPP ESSAR U-2 Nov-07 Chinese 600 600 08/12 13.06.12(A) 15.06.2012
Haryana Jhajjar TPP (Mahatma Gandhi TPP) CLP Power India Pvt. Ltd. U-2 Jan-09 Chinese 660 660 04/12 11.04.12(A) 19.07.2012
Adhunik Power TPP Adhunik Power Co. Ltd. U-1 May-09 BHEL 270 270 09/12 19.11.12(A) 21.01.2013
Jharkhand Adhunik Power TPP Adhunik Power Co. Ltd. U-2 May-09 BHEL 270 29.03.13(A) 19.05.2013
Corporate Power Ltd Ph-I (Maitrishi Usha) M/s Corporate Power Ltd. U-1 Dec-09 BHEL 270 12/12 Slipped
State Project Name Impl Agency Unit No LOA Date BTG Supplier Targeted Actual Cap. Actual At the COD
Cap. (MW) comm. Comm. beginning of
(MW) Date the year
CENTRAL SECTOR
03/08&
Bihar Barh STPP St-II NTPC 4 BHEL 660 660 30/11/13 12/13 15.11.2014
10/08
TN Vallur TPP Ph-I NTPC/ NTECL/ TNEB-JV 3 07/09 BHEL 500 500 28.02.2014 03/14 26.02.2015
TN Tuticorin TPP NLC/ TNEB-JV 1 01/09 BHEL 500 Slipped 03/14
Tripura Tripura CCGT ONGC JV Blk-2 06/08 BHEL 363.3 Slipped 09/13
UP Rihand STPP St-III NTPC 6 02/09 BHEL 500 500 7/10/2013 12/13 March 2014
WB Raghunathpur TPP DVC 1 12/07 CHINA 600 Slipped 03/14
Total Central Sector 3123.3 1660
STATE SECTOR
Chhattisgarh Marwa TPP CSEB 1 04/08 BHEL 500 500 30.03.2014 09/13
Delhi Pragati St-III CCGT PPCL GT-4 05/08 BHEL 250 250 7/5/2013 06/13 27.02.2014
Delhi Pragati St-III CCGT PPCL ST-2 05/08 BHEL 250 250 26.02.2014 09/13 27.03.2014
Gujarat Pipavav JV CCGT GSECL Block-1 12/07 BHEL 351 351 05/02/2013 09/13
MP Shree Singaji TPP(Malwa TPP) MPPGCL 1 12/08 BHEL 600 600 18/11/2013 06/13 February 2014
MP Satpura TPS Extn. MPPGCL 11 03/08 BHEL 250 250 25/12/2013 10/13 16.03.2014
Maha-rashtra Chandrapur TPS Extn. MAHAGENCO 8 07/08 BHEL 500 Slipped 12/13
Rajasthan Kalisindh TPP RRVUNL 1 07/08 SEPCO, CHINA 600 Slipped 12/13
Rajasthan Chhabra TPS Extn. RRVUNL 3 08/08 BHEL 250 250 14/09/13 06/13 19.12.2013
Rajasthan Chhabra TPS Extn. RRVUNL 4 08/08 BHEL 250 Slipped 01/14
Rajasthan Ramgarh CCPP RRVUNL ST 08/09 BHEL 50 Slipped 12/13
TN North Chennai TPS Extn. TNEB 1 08/08 BHEL 600 600 13/09/13 09/13 20.03.2014
Total -State Sector 4451 3051
PRIVATE SECTOR
AP Vizag TPP Hinduja 1 03/10 BHEL 520 03/14
AP Thammina-patnam TPP Meena-kshi Energy 2 08/09 Chinese 150 150 17/04/13 09/13 30.04.2013
Chhattis-garh Tamnar TPP Jindal Power 1 12/08 BHEL 600 600 10.03.2014 03/14 14.03.2014
BOILER: CETHAR
VESSELS LTD
Chhattis-garh Vandana Vidyut TPP Vandana Vidyut TPP 1 05/08 135 Slipped 06/13
TG: CNAIC,
CHINA
Chhattis-garh DB Power TPP DB Power Ltd 1 05/10 BHEL 600 600 23.02.2014 12/13 03.11.2014
BOILER: IJT;
Chhattis-garh Swastik Korba TPP ACB 1 02/10 TURBINE: 25 Slipped 12/13
SIEMENS
Chhattis-garh Akaltara TPP KSK Mahanadi 1 04/09 SEC,CHIINA 600 600 13/08/13 09/13 14.08.2013
MP Sasan UMPP Reliance Power 3 06/08 SEC, CHINA 660 660 30/5/13
05/13
MP Sasan UMPP Reliance Power 2 06/08 SEC, CHINA 660 660 18/12/13 09/13
Maha-rashtra Nasik TPP Ph-I India Bulls 1 11/09 BHEL 270 270 25.02.2014 09/13 29.03.2014
Maha-rashtra Dhariwal Infrastructure (P) Ltd.TPP Dhariwal Infra-structure (P) Ltd. 1 04/10 SEC, CHINA 300 300 3/11/2013 06/13 13.02.2014
Maha-rashtra Dhariwal Infrastructure (P) Ltd.TPP Dhariwal Infra-structure (P) Ltd. 2 04/10 SEC, CHINA 300 Slipped 12/13
Maha-rashtra EMCO Warora TPP GMR EMCO Energy Ltd. 2 09/09 SEC, CHINA 300 300 27/08/2013 06/13 01.09.2013
Maharashtra Tirora TPP Ph-II Adani Power 1 02/08 SCMEC, CHINA 660 660 10/6/2013 06/13 14.06.2013
CENTRAL SECTOR
Assam Bongaigaon TPP NTPC BHEL 3 250 Dec-17 Slipped
Bihar Nabi Nagar TPP JV of NTPC &Rly BHEL 2 250 Apr-17 - 03.04.2017 250.00 10.09.2017
Bihar New Nabi Nagar TPP JV of NTPC & BSPGCL NON BHEL 1 660 Aug-17 Slipped
Chhattisgarh Lara TPP NTPC NON BHEL 1 800 Oct-17 - 23.03.2018 800.00
Karnataka Kudgi STPP Ph-I NTPC NON BHEL 3 800 Aug-17 - 12.03.2018 800.00
MP Gadarwara STPP,St-I NTPC BHEL 1 800 Jan-18 Slipped
Maharashtra Solapur STPP NTPC NON BHEL 1 660 Apr-17 - 07.04.2017 660.00 25.09.2017
UP Meja STPP JV of NTPC & UPRVUNL NON BHEL 1 660 Oct-17 - 31.03.2018 660.00
TOTAL CENTRAL SECTOR 4880 3170.00
STATE SECTOR
AP Rayal seema TPP APGENCO BHEL 6 600 Aug-17 - 12.03.2018 600.00 29.03.2018
Assam Namrup APGCL BHEL ST 36.15 Feb-18 Slipped
MP Shree Singaji TPP, St-II MPPGCL NON BHEL 3 660 Dec-17 Slipped
Rajasthan Suratgarh TPS RRVUNL BHEL 7 660 Nov-17 Slipped
Rajasthan Chhabra SCTPP RRVUNL L&T & MHI 5 660 Apr-17 - 04.04.2017 660.00
Rajasthan Chhabra SCTPP RRVUNL L&T & MHI 6 660 Jan-18 Slipped
Telangana Bhadradri TPP TGENCO BHEL 1 270 Mar-18 Slipped
TOTAL STATE SECTOR 3546.15 1260.00
PRIVATE SECTOR
Chhattisgarh Akaltara (Naiyara) TPP KSK Mahandi Power Company Ltd CHINESE 3 600 Nov-17 - 18.01.2018 600.00 28.02.2018
Chhattisgarh Binjkote TPP SKS Power Generation ( Chhattisgarh) Ltd CHINESE 1 300 May-17 - 25.04.2017 300.00
Chhattisgarh Nawapara TPP TRN Energy CHINESE 2 300 May-17 - 18.04.2017 300.00 01.05.2017
Chhattisgarh Lanco Amarkantak TPS-II LAP Pvt. Ltd. CHINESE 3 660 Nov-17 Slipped
Maharashtra Nasik TPP Ph-I RattanIndia Nasik Power Ltd BHEL 3 270 May-17 - 14.04.2017 270.00
UP Bara TPP Prayagraj Power Generation Co.Ltd. BHEL 3 660 Aug-17 - 22.05.2017 660.00 26.05.2017
WB Hiranmaye Energy TPP Hiranmaye Energy Limited BHEL 1 150 Apr-17 - 07.06.2017 150.00 13.08.2017
TOTAL PRIVATE SECTOR 2940 2280.00
ADDITIONAL PROJECTS COMMISSIONED
PRIVATE SECTOR
Maharashtra Nasik TPP Ph-I RattanIndia Nasik Power Ltd BHEL 4 19.05.2017 270.00
Maharashtra Nasik TPP Ph-I RattanIndia Nasik Power Ltd BHEL 5 30.05.2017 270.00
Chhattisgarh Uchpinda TPP RKM Powergen Pvt.Ltd. Chinese 3 12.09.2017 360.00
Maharashtra Shirpur TPP Shirpur Power Pvt. Ltd. BHEL 1 28.09.2017 150.00
WB Hiranmaye Energy TPP Hiranmaye Energy Limited BHEL 2 31.12.2017 150.00 31.12.2017
Bihar Barauni Ext. BSEB BHEL 8 11.01.2018 250.00
Chhattisgarh Binjkote TPP SKS Power Generation ( Chhattisgarh) Ltd CHINESE 2 28.03.2018 300.00
Bihar Barauni Ext. BSEB BHEL 9 31.03.2018 250.00
TOTAL ADDITIONAL PRIVATE SECTOR 2000.00
TOTAL THERMAL CAPACITY in 2017-18 11366.15 8710.00
STATE SECTOR
Assam Namrup CCGT APGCL BHEL ST 36.15 Feb – 19 Slipped
MP Shri Singhaji TPP St-II MPGCL L&T & MHI 3 660 Sept - 18 18.11.2018 660.00 18.11.2018
MP Shri Singhaji TPP St-II MPPGCL L&T & MHI 4 660 Feb – 19 27.03.2019 660.00 27.03.2019
Odisha Ib valley TPP OPGC BHEL 4 660 March - 19 Slipped
Rajasthan Chhabra TPP Extn RRVUNL L&T & MHI 6 660 Dec – 18 29.03.2019 660.00 02.04.2019
Rajasthan Suratgarh SCTPP RRVUNL L&T & MHI 7 660 Dec – 18 Slipped
Karnataka Yelahanka CCPP KPCL BHEL 1 370 Oct – 18 Slipped
Telangana Kothagudem TPS St-VII TGENCO BHEL 800 Dec – 19 26.12.2018 800.00 26.12.2018
TOTAL STATE SECTOR 4506.15 2780.00
State Project Name Impl Agency Equipment Unit No. Targeted Anti. Comm Anti. Actual Date Capacity COD
Supplier Cap. Date at Comm of Capacity Achieved
(MW) beginning Date (At addition (MW)
of year present)
CENTRAL SECTOR
Bihar New Nabi Nagar TPP JV of NTPC & BSPGCL NON BHEL 1 660 May-19 - 12.07.2019 660.00
Chhatisgarh Lara STPP NTPC BHEL 2 800 Dec-19 Slipped
MP Gadarwara STPP,St-I NTPC BHEL 2 800 Dec-19 Slipped
MP Khargone STPP NTPC BHEL 1 660 Aug-19 29.09.2019 660.00
MP Khargone STPP NTPC BHEL 2 660 Feb-20 24.03.2020 660.00
Odisha Darlipali STPP NTPC BHEL 1 800 Aug-19 30.12.2019 800.00
U.P. Tanda TPP Stage - II NTPC L&T & MHI 1 660 Sep-19 28.09.2020 660.00
Tamil Nadu Neyveli New TPP NLC BHEL 1 500 Apr-19 21.12.2019 500.00
Tamil Nadu Neyveli New TPP NLC BHEL 2 500 Oct-19 Slipped
TOTAL CENTRAL SECTOR 6040 3940.00
STATE SECTOR
Andhra Dr.Narla Tata Rao TPS APGENCO BHEL 8 800 Feb – 20 Slipped
Pradesh
Stage-V
Assam Namrup CCGT APGCL BHEL ST 36.15 Nov-19 Slipped
Gujarat Wanakbori TPS Extn. GSECL BHEL 800 Nov-19 12.10.2019 800.00
Karnataka Yelahanka CCPP KPCL BHEL GT+ST 370 Nov - 19 Slipped
Odisha Ib valley TPP OPGC BHEL 3 660 Apr – 19 01.07.2019 660.00
Odisha Ib valley TPP OPGC BHEL 4 660 Jul - 19 17.08.2019 660.00
Rajasthan Suratgarh SCTPP RRVUNL L&T & MHI 7 660 Nov -19 15.03.2020 660.00
Telangana Bhadradri TPP TGENCO BHEL 1 270800 Jan - 20 Slipped 26.12.2018 800.00
TOTAL STATE SECTOR 4256.15 2780.00
ADDITIONAL PROJECTS COMMISSIONED
Private Sector
MP Niwari TPP BLA Power Ltd Chinees 2 06.06.20219 45.00
TOTAL ADDITIONAL PRIVATE SECTOR 45.00
State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
CENTRAL SECTOR
Assam Bongaigaon TPP NTPC BHEL U-1 250 250 250 22.06.15
Assam Bongaigaon TPP NTPC BHEL U-2 250 250 250 22.03.17
Assam Bongaigaon TPP NTPC BHEL U-3 250 250
Bihar Barh STPP-II NTPC BHEL U-4 660 660 660 30.11.13
Bihar Barh STPP-II NTPC BHEL U-5 660 660 660 04.03.15
Bihar Muzaffarpur TPP Extn KBUNL (JV of NTPC and BSEB) BHEL U-3 195 195 195 31.03.15
Bihar Muzaffarpur TPP Extn KBUNL (JV of NTPC and BSEB) BHEL U-4 195 195 195 24.03.17
Bihar Nabi Nagar TPP NTPC BHEL U-1 250 250 250 20.03.16
Bihar Nabi Nagar TPP NTPC BHEL U-2 250 250
Bihar Nabi Nagar TPP NTPC BHEL U-3 250 250
Bihar Nabi Nagar TPP NTPC BHEL U-4 250 250
Bihar Barh STPP-I NTPC Others U-1 660 660
Bihar Barh STPP-I NTPC Others U-2 660 660
Bihar Barh STPP-I NTPC Others U-3 660 660
Chhattisgarh Sipat-I NTPC Others U-3 660 660 660 02.06.12
Haryana Indira Gandhi TPP APCPL BHEL U-3 500 500 500 07.11.12
Jharkhand Koderma TPP DVC BHEL U-2 500 500 500 15.02.13
Jharkhand Bokaro TPS "A" Exp. DVC BHEL U-1 500 500 500 22.03.16
Karnataka Kudgi STPP Ph-I NTPC Non-BHEL U-1 # 800 800 25.12.16
Karnataka Kudgi STPP Ph-I NTPC Non-BHEL U-2 # 800 800 23.03.17
Maharashtra Mouda TPP NTPC BHEL U-1 500 500 500 19.04.12
Maharashtra Mouda TPP NTPC BHEL U-2 500 500 500 29.03.13
Maharashtra Mouda STPP Ph-II NTPC BHEL U-3 # 660 660 28.03.16
Maharashtra Mouda STPP Ph-II NTPC BHEL U-4 # 660 660 18.03.17
MP Vindhyachal TPP-V NTPC BHEL U-13 # 500 500 06.08.15
MP Vindhyachal STPS-IV NTPC BHEL U-11 500 500 500 14.06.12
MP Vindhyachal STPS-IV NTPC BHEL U-12 500 500 500 25.03.13
TN Vallur TPP Ph I NTECL BHEL U-2 500 500 500 28.02.13
TN Vallur TPP-II NTECL BHEL U-3 500 500 500 28.02.14
Maharashtra Bela TPP-I, IEPL BHEL U-1 270 270 270 20.03.13
Maharashtra EMCO Warora TPP, EMCO GMR Chinese U-1 300 300 300 07.02.13
Maharashtra EMCO Warora TPP, EMCO GMR Chinese U-2 300 300 300 27.08.13
Maharashtra Tirora TPP Ph-I, Adani Power Ltd Chinese U-1 660 660 660 11.09.12
Maharashtra Tirora TPP Ph-I, Adani Power Ltd Chinese U-2 660 660 660 25.03.13
Maharashtra Gupta Energy Power Ltd Gupta Energy Power Ltd Chinese U-2 60 60 60 28.04.12
Maharashtra Gupta Energy Power Ltd Gupta Energy Power Ltd Chinese U-1 60 60 60 08.09.12
Maharashtra Amaravati TPP Ph-I Indiabulls BHEL U-1 270 270 270 25.03.13
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-2 270 270 270 17.02.14
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-3 270 270 270 29.01.15
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-4 270 270 270 04.03.15
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-5 270 270 270 12.03.15
Maharashtra Dhariwal Infracture TPP Dhariwal Infracture (P) Ltd Chinese U-1 300 300 300 03.11.13
Maharashtra Dhariwal Infracture TPP Dhariwal Infracture (P) Ltd Chinese U-2 300 300 300 28.05.14
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-1 270 270 270 25.02.14
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-2 270 270 270 15.02.17
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-3 270 270
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-4 270 270
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-5 270 270
Maharashtra Tirora TPP Ph-II Adani Power Ltd Chinese U-1 660 660 660 10.06.13
Maharashtra Tirora TPP Ph-II Adani Power Ltd Chinese U-2 # 660 660 23.03.14
State Project Name Impl Agency Main Plant Unit No 12th Plan Reasons for Slippage
Equipment Slipped Cap.
Supplier (MW)
CENTRAL SECTOR
Assam Bongaigaon TPP NTPC BHEL U-3 250 Frequent bandhs, Heavy monsoon and slow civil works. Delay in supply
of material by BHEL. Work came to halt due to violence and mass exodus
of labour from site in 2011-12. Civil works got affected due to poor
performance by civil contractors resulting in to their contract cancellation.
Balance civil and structural works awarded to NBCC on 29.09.14.
Bihar Nabi Nagar TPP NTPC BHEL U-2 250 Delay in acquisition of Land. Slow progress of works by main plant civil
Bihar Nabi Nagar TPP NTPC BHEL U-3 250 agency M/s ERA resulting in delay in handing over civil fronts to erection
Bihar Nabi Nagar TPP NTPC BHEL U-4 250 agencies. Delay in Supply of equipment by BHEL. Agitation by villagers.
Patches of land could not be acquired because of unwillingness of people
to accept compensation. Financial crunch faced by CHP vendor(Techpro).
Bihar Barh STPP-I NTPC Others U-1 660 Delay due to contractual dispute of NTPC with Power machine &
Bihar Barh STPP-I NTPC Others U-2 660 Technopromexport, Russia. *Orig. Sch. was in 2009-10 & 2010-11.
Bihar Barh STPP-I NTPC Others U-3 660 Delay in supply of boiler material and ordering of Bought out
Items(BOIs)by M/s TPE due to financial constrant. M/s. TPE stopped
work from 10/13. M/s TPE contract was terminated on 14.01.2015 by
NTPC. Delay in supply of material and slow progress by M/s. Power
Machine.
Total Central Sector 2980
STATE SECTOR
AP Rayalaseema St-IV AP Genco BHEL U-6 600 Delay in start & completion of civil works and land acquisition. Delay in
BoP works.
Assam Namrup CCGT APGCL BHEL ST 36.15 Delay in start and slow progress of of civil works, Termination of civil
contractor. Poor soil conditions and heavy monsoon. Delay in supply of
material by BHEL & shortage of skilled manpower. Termination of
NBPL order. Delay in award of civil and Electrical, Mechanical &
Instrumentation agency.
Total State Sector 636.15
PRIVATE SECTOR
AP Thamminapatnam TPP-II Meenakshi Energy Chinese U-3 350 Slow progress of Civil works. Due to financial problem, work at site
Pvt. Ltd remained closed for a long time.
AP Thamminapatnam TPP-II Meenakshi Energy Chinese U-4 350
Pvt. Ltd
AP BhavanapaduTPP Ph-I East Coast Energy Chinese U-1 660 Work remained under suspension due to MoE&F order for a long time.
Ltd. After restart works hampered due to two cyclones. Agitation against State
AP BhavanapaduTPP Ph-I East Coast Energy Chinese U-2 660 bifurcation. Slow progress of work at site due to financial problems.
Ltd.
Chattisgarh Nawapara TPP TRN energy Pvt.Ltd.. Chinese U-2 300 Delay in start of civil works. Slow progress in erection works of boiler
and T.G. Manpower shortage.
Chhattisgarh Akaltara (Naiyara) TPP KSK Mahandi Power Chinese U-3 600 Shortage of manpower, Agitation by Villagers. Delay in supply of
Co. Ltd material due to fund contraints.
Chhattisgarh Salora TPP M/s Vandana Vidyut Chinese U-2 135 Delay in commissioning of unit-1. Agitation by vllagers at site. Delay in
TPM_Broad Status Report (January-February’2020) 27
State Project Name Impl Agency Main Plant Unit No 12th Plan Reasons for Slippage
Equipment Slipped Cap.
Supplier (MW)
supply of BTG and CHP material. Non cooperation of BTG supplier in
commissioning activities. Acquistion for railway siding and ash pond.
Chhattisgarh Uchpinda TPP RKM Powergen Pvt. Chinese U-3 360 Work suffered due to agitation by villagers. Slow progress of work at site.
Ltd Delay in readiness of BOPs.Delay in readiness of start up power. Delay
due to financial problem. Balance land acquistion for ash pond and
Railway line siding. Consent to operate for U- 3 &4.
Chhattisgarh Athena Singhitarai TPP Athena Chinese U-1 600 Delay in land acquisition. Slow progress of Boiler & TG erection. Delay
due to financial problems.
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-1 300 Delay in start of civil works. Slow progress of pressure parts erection.
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-2 300 Balance land acquisition for ash dyke. Delay due to financial problems.
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-3 300
Chhattisgarh Lanco Amarkantak TPP-II LAP Pvt. Ltd. Chinese U-3 660 Delay in acquisition of land for water system. Presently work is going
Chhattisgarh Lanco Amarkantak TPP-II LAP Pvt. Ltd. Chinese U-4 660 slow at site due to financial problems.
Jharkhand Matrishri Usha TPP Ph-I Corporate Power Ltd. BHEL U-1 270 Law and order problem. Delay in supply of BTG equipment. Delay in
Jharkhand Matrishri Usha TPP Ph-I Corporate Power Ltd. BHEL U-2 270 readiness of transmission line due to forest clearance. Work held up due
to financial problems since Nov, 12.
Maharashtra Nasik TPP Ph-I Ratan India Nasik BHEL U-3 270 Non-Acceptanceof BTG material by Project Authorities. Work is going
Power Ltd. slow at site due to financial problems.
Maharashtra Nasik TPP Ph-I Ratan India Nasik BHEL U-4 270
Power Ltd.
Maharashtra Nasik TPP Ph-I Ratan India Nasik BHEL U-5 270
Power Ltd.
Maharashtra Lanco Vidarbha TPP Lanco Vidarbha Chinese U-1 660 Work is going slow at site due to financial problems
Maharashtra Lanco Vidarbha TPP Lanco Vidarbha Chinese U-2 660
MP Gorgi TPP ( D B Power) DB Power Ltd BHEL U-1 660 Order for main plant equipment has been placed. Work is on hold.
Commissioning schedule would be assessed after re-start of work.
Orissa Lanco Babandh TPP Lanco babandh Chinese U-1 660 Delay in land acquisition. Work is going slow at site due to financial
Power Ltd. problem.
Orissa Ind Bharat TPP Ind Barath Chinese U-2 350 Delay due to heavy rains. Delay in readiness of transimission line for start
(Orissa) up power. Commissioning problems such as change of firing guns of
Orissa KVK Neelanchal TPP KVK Neelanchal Chinese U-1 350 boiler and change in bypass valve.
TN Tuticorin TPP-II(Ind barath) IBPIL Chinese U-1 660 Late start and slow progress of civil works and delay in supply of boiler
structural material at site.
UP Prayagraj (Bara ) TPP Prayagraj power Gen. BHEL U-3 660 Delay in BTG supply, Raw water pipe line readiness and transmission line
Co. Ltd( J.P.Power readiness for start up power. Progress of work at site delayed due to
Ventures) financial problems. Delay in Land Acqisition for railway siding and
power evacuation.
Total Private Sector 12245
Total Slippage from 12th Plan Target as on 31.03.17 15861.15
CENTRAL SECTOR
Critical Areas Material supply against open door and poo mobilization by SG agency of BHEL.
AHP critical supplies by Indure.
Balance land issues on 38.47 acres of land.
Reasons for Delay Delay in Civil Works, SG Supplies, Frequent bandhs/Local agitation by villagers
Delay in Land acquisition issues.Physical possession of Banace land fro ESP/VFD area fro U-2, 3&4 received in Jan’16/Nov’16.
Physical possession of 70 acres of critical land is still balance due to court cases, wrong payment in awarded land and ownership
dispute in Mai pALnt, MUW corridor, Ash Dyke and township.
TG civil fronts delayed due to corporate in solvency proceedings by NCLT against MS ERA. Contract now terminated.
MK 11.02.2020
Critical Areas Support of State Govt. is required for early possession/ acquisition of balance land for MGR route
Support of Railways required for CRS Sanction for insertion of turnout & completion of associated S&T works at
Kotarlia station
Completion of balance work of Railway siding.
Support required from WRD for Closing of Barrage gate at saradih barrage (Mahanadi river) for water impounding in
make up water channel.
Reasons for Delay Delay in readiness of Railway siding due to land acquisition, ROW issue in 18 nos foundation of MU Water
66kVtransmission line coprridors is hampering process.
Delay in supplies of Ash Handling Material.
MPS 30.03.2020
Reasons for Delay Delay in start of Civil works due to land acquisition issues. Delay in BHEL supplies related to boiler foundation. Delay
in land handover by NTPC to BHEL due to change in main plant area location change in plot plan. Delay in award of
ACC package by BHEL.
Delay in reaward of sub agency for U-2.
MK 11.02.2020
Critical Areas Land acquisition for Railway siding, ash pipe corridor, raw water reservoir. Poor progress of main plant civil works
Readiness of railway siding.
Reasons for Delay Stoppage of work on account of NGT order–work stopped from 17.03.2014 to 01.04.2014. Work stoppage due to agitation
against the project (05.07.2014 to 22.07.2014). Delay in award of SG civil works. Delay in TG erection start. Unrest and
violent agitation in 07/14 with exodus of manpower. Delay in supply of generator stator of Unit #2 &3 by M/s Toshiba.
Supply of material against CHP-Energo, AHP- MBECL, ESP-L&T and FDPS & slow progress.
MK 11.02.2020
Critical Areas Delay in Laying of Make Up Water Pipe line due to No Right of Use Act in Maharashtra. Delay in SG supplies by
BGR-Hitachi and resource augmentation. Resources augmentation by M/s Indure, for CHP & AHP packages.
Major damage in Pressure parts and support structure (9nos hdrs, buckstays, springs, etc) and delay in rectification
and replacement by BGR. Rectification work started in May -17 but work progress is very slow. Expediting Supply
of U#2 Boiler components & BOIs by BGR Energy- Systems Ltd. & Hitachi Power Europe, Supply of Structures &
BOIs/SMIs by M/s. Indure for AHP and CHP Packages. Supply of FDA and inert gas nozzles & detectors by M/s
Sureland for FDPS Package. Due to resistance from farmers, seeking higher compensation than as recommended by
state revenue/agriculture dept., the Completion of MUWPH 132 KV line is getting delayed.
Reasons for Delay Delay in steam generator Engineering & supply by BGR due to non-settlement of QSGM between BGR and
Hitachi. Delay in repair & replacement of damaged pressure parts due to accident.
MK 11.02.2020
Critical Areas Possession of 2.91acres part land for Crossing Station of Railway Siding.
Support of Railways is required for early completion of works of Crossing station.
Slow Progress of AHP agency (M/s Indure) due to inadequate manpower mobilization & repeated defaults in
material supplies. Comfort letters issued by site for supplies of BOIs.
Reasons for Delay Work stopped for 56 daysin 2014 due to agitation by villagers demanding additional compensation for already
acquired land.
In may 2016, work was stopped for two and half day from 18.05.16 due to labour strike and one more day was lost
due to death of labour on 27.05.2016
Work stopped for 56 days in 2017-18 (22.12.2017 to 15.02.2018) due to agitation by PAP’s under the banner of
“Kisan Mazdoor Sangh” with their major demand for permanent employment in NTPC and some demands related
to local development work as part of R&R plan.
MPS 30.03.2020
BOPs:
Chimney: Shell completed and flue can erection of U-2
completed in 07/19.
CHP: M/s. L&T. 8848/9386 MT CHP structure
completed. WT-1 Tippling testing along with coal done
on 27.05.2019.
AHP: AHP structure 3318/3991 MT completed AHP
equip. erection 1219/1633 MT completed. AHP piping
work in u/p. HCSD recirculating pump C2 trail
completed on 24.07.19
Cooling Tower: IDCT-1- RCC Super structure-
completed, IDCT-2- RCC super structure is i/p.
CW system: CW piping U-2 erection 1300/2222mtr
done.
PT plant: Completed.
DM plant: Fully Commissioned
FOHS: LDO tanks-1&2 completed.
Switchyard: 400 kV GIS charged through LILO
system on 06.07.18. 66kV line charged in 05/19.
Critical Areas Power evacuation oline of khargone has not completed yet.
Support of railway is required for expeditious completion of OHE works from Nimarkhedi to plant.
MPS 30.03.2020
TPM_Broad Status Report (January-February’2020) 43
Sl. Capacity Commissioning Schedule
No. PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
11. Darlipalli STPP ST-I, 1600 Unit-1: COD declaredin 01.03.20 .72 hrs
Dist. Sundergarh, trial run completed on 31.12.19, Full load
Odisha (NTPC Ltd.)
on 02.10.19 and synchronized on
U-1 800 12/17 04/18 04.04.19(A) 30.12.19(A)
04.04.2019.
02/18 02.10.19(A) 01.03.20(A)
U-2 800 04/18 08/18 07/20 - Boiler: Boiler erection started in 04/15. HT
06/18 08/20 09/20 completed in 8/17. BLU completed in 10/18. Steam
Investment. approval blowing completed in 02/19.
Orig.Est. cost : Rs 12532.44 Crores. TG: Condenser erection started in 12/15. TG
Latest. Est. Cost : Rs 13740.53 Crores. (Jan 2014) erection started in 05/16.TG box-up done in
11/17.TG oil flushing done in 11/18.TG put on
Exp. During 2013-14 :Rs. 951.00 Crores. barring gear on 12/18.
2014-15 :Rs 1457.00 Crores. ESP: All passes completed.
2015-16 :Rs 1417.00 Crores.
2016-17 :Rs 2384.00 Crores. Unit-2:
2017-18 :Rs 2100.00 Crores. Boiler: Boiler erection started in 07/15. HT done in
2018-19 :Rs 1531.66 Crores. 03/18. BLU in OCt-2019
2019-20 Rs 991.99 Crores. TG: Condenser erection started in 09/16. TG
Rs. 1156.00 Crores (upto 02/20) erection started in 03/17. TG BOX up in 02/19. TG
Cumulative Exp :Rs 10257.63 Crores (up to 2/20) oil flushing completed in Jan 2020.
MOEF clearance ESP: 6 passes are completed.
Type of fuel : Coal
Date of Main Plant Order SG. Awarded in 02/14 on M/s BHEL.
BOPs:
Chimney: raft completed.
TG awarded in 02/14 on M/s Toshiba
CHP: Order placed on Tata projects in Feb’15. Civil
work in Track hopper, Wagon tippler, erection work
in TPs, Crusher house, stacker reclaimer in progress.
Belt laying commenced.
DPR & Coal Trans. : 13 km rail laying (priority
line)competed. Coal is transported by MGR to
Project site
AHP: Order placed on Indure in Oct’14. Structural
work at bottom ash hopper erection, ASPH and
AWPH foundations completed. Supply of material
from Indure is pending.
Ash Dyke: Lagoon1, 2 and OFL is completed. and
work in Lagoon 3 under progress.
PT/DM Plant: Order for water treatment plant
placed on Triveni Engineering in Feb’15. One stream
for DM water generation is ready, one stream
clarifier ready. Completion work is in progress.
CWPs: Order for CW equipment placed on Kirloskar
Brothers Ltd in Oct’14. Equipment supplies done.
Work in progress. RW PH & CWPH completed;
makeup PH work balance.
CT: Order placed on L&T, ECC in Dec’14. Unit 1
all 32 cells mech& civil work completed.32 cells
charged erection under progress & U- 2 Cooling
tower 16 cells comkpleted bala;nce civil work in
progress.
Switchyard: 765kV one bay and 132kV switchyard
charged for startup power.
AHP:
Ash Dyke: Protective bund and reservoir earth work
in progress.
Critical Areas During last CRM held with BHEL on 28/9/17, BHEL confirmed primary structure dispatch commences only from
Dec 17.
Reasons for Delay Change in boiler design w.r.t. new environmental norms, Delay in BHEL supplies.
Slow progress of work by M/s GE power.
MK 11.02.2020
BOPs:
Chimney: Order placed on GDCL in 02/15. Work is in
progress.
CHP: Order placed on L&T in 12/15. Equipment
erection and trials i/p. reclaiming conveyors comm.
Direct steam 1 set of conveyors commissioned, balance
erection is i/p.
AHP: Order placed on L&T in 03/16. Civil works
under progress. Mech erection of AWPH, ASPH,
HCSDPH and TACH &HCSD silo completed.
DM Plant: Order placed on Driplex in 08/15.Civil and
Mechanical work completed.
CWPs: Order for CW system equipment placed on
KBL in Jun’15. CW Pumps erected. OAC U-5 portion
work completed. Pumps 1,2 &5 erected & trial taken.
Pumps 3 & 4 erection WIP.
NDCTs: Order placed on L&T in 10/15.U-5 completed.
U-6 Grillage column 1470/1567 lifts done. Shell
116/116 lifts casting done.
Switchyard: Startup power charged.U-5 portion is
ready. CEA clearance received.
Critical Areas Physical possession of balance 11.299 Acres Abadi land. Out of this, 3.15 acres in Ash Dyke area is critical.
41 houses of Khattegaon need to be shifted for completion of Lagoon IIA and 3 houses, school & Temple shifting
to be done foe completion of Lagoon IIB.
Associated Transmission System for Unit-6 by UPPTCL:
- Construction of sub-station at Basti
- Construction of Tanda – Basti 400 KV Line
Reasons for Delay Poor mobilization by civil agency, Delay in Engg. & Supply.
Delay in AHP (L&T MMH)
Delay in Civil Front
MPS 30.03.2020
Shifting of Transmission line from Project Area, Acquisition of Balance land of 35Acre for ash dyke-2 and lease of
Critical Areas 14.09acres of land and acquisition of 0.269 acre land fro railway siding.
Reasons for Delay Delay in award of ACC Pkg, WPT, Mian Power House Str erection Pkg by BHEL
MK 11.02.2020
Critical issues
Reasons for Delay Delayed due to change in design of foundations(depth) of main plant area and finalisation of civil contractors. Initial delay in
supply of Boiler Material and inadequate resource mobilization and new technology(Boiler) being used first time in India.
Critical issues
Reasons for Delay
AK-16/01/2020
Power evacuation Through two No. S/C 220 kV transmission lines viz (i) BTPSE- Gajner (ii)
Uncertain
system BTPSE-Bikaner, to be executed by RVPNL
Water: Water supply agreement signed on 08/10/03 b/w Indira Gandhi Nahar Pariyojna, GoR and
NLC
Land: Land is in procession of NLC and the proposed plant is being constructed with in the existing
2x125MW Barsingsar TPP
MOE&F clearance: EC for mines granted on 21/10/13. EC for thermal granted on 30/07/12
Civil Aviation: NOC obtained on 23/01/2012
Critical Issues
Reasons for delay GoR had informed that due to increased project cost and time over run, Rajasthan Discom will not be in position to buy the power
from BTPSE. NLCIL had replied that delay is due to acquisition of land for linked mine by GoR and informed to review the decision.
Matter is pending with GoR. Project activities are under hold from 02/06/2017.
Uncertain
Type of Fuel : Lignite, Bithnok Lignite Mine 2.25MTA (Original cost is Rs.
513.63 Cr.)
PPA : Signed with GoR on 31/12/2010
Power evacuation Through three No. S/C transmission lines viz (i) BLTPS-
system Kolayat (ii) BLTPS-Nokha(iii)BLTPS-Bikaner to be executed
by RRVPNL.
Water: Water supply agreement signed on 10/06/14 b/w Indira Gandhi Nahar
Pariyojna, GoR and NLC
Land: Private land-1088.20 ha in possession.
Govt Land-Transfer in favour of NLC India is under progress at O/o Commissioner
colonization, Bikaner
Forest land- Transfer in favour of forest dept is under progress at O/o Commissioner
colonization, Bikaner
MOE&F clearance:EC for mines granted on 26/02/16. EC for thermal granted on
30/04/10 and validity extension is under progress.
Civil Aviation: NOC obtained on 09/08/16
Critical Issues
Reasons for delay GoR had informed that due to increased project cost and time over run, Rajasthan Discom will not be in position to
buy the power from BTPSE. NLCIL had replied that delay is due to acquisition of land by GoR and informed to
review the decision. Matter is pending with GoR.
MPS – Jan 2020
Critical Areas
Reasons for Delay
MPS 30.03.2020
MPS 30.03.2020
Commissioning Schedule
Sl.
Actual (A) / As now
No. Capacity Original
PROJECT DETAILS Anticipated. Broad Status
(MW)
Syn. Syn.
COD
Comm Comm COD
Private Sector
1 PRAYAGRAJ TPP 1980 U-1: Full load Achieved on 25.12.15. COD on
M/s Prayagraj Power Generation 29.02.16
Co. Ltd.
(Distt. Bara, Allahabad), U.P. Boiler erection started on 12/07/11. HT done on
Unit-1 660 06/13 10/13 31.10.15(A) 29.02.16 (A) 24/10/13. BLU done on 31/03/15. TG erection started
25.12.15(A) in 01/13 & boxed up on 20/02/14. Oil flushing
completed on 18/03/15.
Unit-2 660 11/13 03/13 07.07.16 (A) 10.09.16 (A) Unit Synchronised on 31.10.15.
06.09.16 (A)
Unit-3 660 04/14 07/14 26.03.17(A) 26.05.2017 (A) U- 2: Full load Achieved on 06.09.16. COD on
22.05.17(A) 10.09.16.
Date of clearance by State Govt. : Nov, 2006.
Boiler: Boiler erection started on 12.09.2011.
Original/Latest Est. Cost : Rs.1162227 Lakhs/ 1387000 lakhs Hydro test conducted on 29.01.15. BLU completed on
Date of Financial Closure : Achieved on 06.07.2010 with SBI 03.03.16. SBO completion expected in 05/16
Exp. Upto 03/2011 :Rs.124478 Lakhs ESP: ESP work completed
Exp. During 2011-12 :Rs.137691 Lakhs TG: Condenser erection started on 10.06.13. TG
Exp. During 2012-13 :Rs.296958 Lakhs erection started on 20.09.13. TG boxed up on 14.05.15.
Exp. During 2013-14 :Rs 308897 Lakhs OF completed on 16.03.16. Unit Sync. on 07.07.16.
Exp. During 2014-15 :Rs. 285952 Lakhs
Exp. During 2015-16 : Rs. 171135 Lakhs U-3: Full load achieved on 22.05.17. COD on
Exp. During 2016-17 : Rs. 130126 Lakhs 26.05.17.
Exp. During 2017-18 :Rs.10097 Lakhs
Cumulative Expd. (4/17) :Rs. 1465334 Lakhs Boiler: Boiler erection started on 05.09.2011.
Hydro test conducted on 29.11.14. BLU on 31.05.16.
Type of fuel : Coal Acid cleaning completed. Temporary piping work for
steam blowing is under progress. SBO completed on
Date of Main Plant Order : 22.01.2009 (BTG) on M/s BHEL 06/02/17. Unit Syn. (on oil) on 26/03/17.
ESP: ESP work completed.
Boiler U-1: Structure from BHEL, Pressure parts from Alstom, U- TG: Condenser erection started on 10.01.14. TG
2&3: From BHEL. erection started on 11.11.14. TG box up completed in
Boiler, TG & Generator make.
TG & Gen U-1&2: From Siemens, U-3: From BHEL Hardwar. 05/02/17. TG Oil flushing done on 14/02/17.
BOPS:
FGD: The order for FGD installation has been
Zero date 23.02.2010. placed on M/S Tata Consultant Engineers (TCE) at
the cost of @ 1000Crs. There is no space constraint
PPA : PPA signed on 21.11.2008. for installation of FGD system in the plant.
Chimney: Awarded to Paharpur. 275 height achieved
Fuel Linkage : Fuel supply agreement between PPGCL & NLC for 6.95 MTPA has
for both chimneys. Flue 1&2 completed. Chimney 2
been executed on 29.08.2013. completed.
Associated Transmission System Power is proposed to be evacuated at 765 KV and 400 KV level for
CHP: Package A awarded to L&T and Package B
which 765KV and 400 KV switchyards are proposed. Responsibility of
awarded to HEW. For Package A, WT4 & WT 3
UPPCL & PPGCL. Work awarded to Isolux.
commissioned. For U-1,2,3 bunker ready. Load trials
carried out. For Package B, 1st stacker reclaimer
commissioned.
AHP: Awarded to Macawber Beekay. System ready
for U-1,2 & 3 completed.
Land: :1468 acres of land for the project is in physical possession. Land for the facilities outside the plant area NDCT: CT-1,2 &3 completed.
is being acquired. For land required for railway sliding about 32.71 Ha out of 35 Ha has been acquired. Lease
PTP: PT plant commissioned
deed executed and the process of taking physical possession of land is completed.
DM Plant: DM plant commissioned
MOEF clearance: Obtained on 08.09.2009 FOS: ALL HFO and LDO storage & Day tanks
completed. FOH pump house ready, LDO system
commissioned.
FPS: Ready for U-1,2 &3
SWYRD: Work in 400 KV switchyard completed and
charged one 765 kV line
Critical Areas/Assistance Delay in Unit 1 & 2 COF will be approx. 12.2 months as compared to the baseline schedule of 21st Dec. 2020. The efforts are being
required made to catch up the baseline schedule with below catch-up activities:
- Acceleration effort for various work activities like
(a) day & night shift work for piling and steel structure fabrication (TG & CCB)
(b) working on Sundays and holidays
(c) Emphasis on maximizing pressure part pre-assembly at ground level
(d) Subcontract with additional vendors for Boiler steel structure supply
(e) Acceleration work for TBN pedestal
AK-24/01/2020
MOE&F clearance:
Critical Areas
Reasons for Delay
Stressed Project
Financial closure Achieved on 04/11/10
Main Plant Order : 04/11/10 on M/s Sravanthi Infratech Private
*Schedule will be decided after availability of gas
Ltd (EPC Basis).
BTG Make GTGs# GE, France(6FA), HRSGs#Greens
Power Equipments(China) Co. Ltd.and STGs
are from HTC China
BOP Package Common BoPs for Ph-I&II, Reputed Indian
Vendors
Type of fuel : Natural Gas (1.2 mmscmd)
PPA : PPa yet to be signed
Source and supply of Fuel :Domestic Gas from D-6, KG Basin (Right now E-
Bidding RLNG)
Power Evacuation system open access: Transmission with PGCIL for
450MW capacity power evacuations through
400 kV/220kV permission granted by NRLDC
on 29/12/10. Readiness of ATS through nearby
Grid sub-station is scheduled by 12/16.
FSA yet to be signed.
All statutory clearances are available.
All the BOPs has already been commissioned.
M/s TCE, Bangalore is the owner’s consultant.
Gas pipeline connectivity completed.
All common utilities are ready.
Critical issues Availability of Gas & PPA
Stressed Project
Exp. During 12-13 : Rs. 222416 lakhs
Exp. During 13-14 : Rs 209517 lakhs Unit-4 (U-5)
Exp. During 14-15 : Rs.164917 lakhs Boiler. :Boiler erection started on 08/12/11. Boiler Drum lifted on
Exp. During 15-16 : Rs. 90320 lakhs 31/08/16. Pressure parts and joints erection is in progress. Duct
Exp. During 16-17 : Rs. 318700 lakhs erection work is in progress. Boiler Hydro Test yet to be happen.
Exp. During 17-18 Pedestal work in progress. Work at site is on hold.
Total Exp.( upto :Rs. 1873000 Lakhs TG: TG Deck casting completed on 06/10/12. Various level floor
12/16) castingwork in progress.
Approval date: NA FGD: FGD plant expected in 12/22.
Zero date: : 21/04/09 Unit-5 (U-1)
Financial closure : Achieved on 30/03/10 Boiler.: Boiler erection started on 06/02/12. Foundation work is
EPC Order : EPC ordered on 21/01/09 on SEPCO (China) completed. Balance work in progress.
Package(BTG) (Boiler-Shanghai Boiler Works, China), TG: TG raft and main coloumns casted and column TG Deck casting is yet
(TG-Dongfang Electric Company, China) to be completed.
Type of fuel Coal FGD: FGD plant expected in 02/23.
PPA PPA: PPA signed with Gujarat Urja Vikas Nigam Ltd for 1010 MW on Presently order was placed for techno-commercial feasibility study
03/06/10. with black and veatch for all six units.
PPA signed with APCPDCL for 400 MW on 31/07/12. Unit-6
PPA signed with CSP Trade Co for 225 MW on 18/10/13 Boiler:Boiler raft casting completed. Boiler erection yet to start.
PPA signed with TANGEDCO for 500 MW on 27/11/13 Foundation work is completed
PPA signed with UPPCL for 1000 MW on 26/02/14 TG:TG raft casting completed and column casting is in progress. Deck
Power Evacuation Power is to be evacuated to PGCIL pooling station through 400kV casting yet to be completed.
system transmission system. Final bulk power transmission agreement signed with
PGCIL on 25/02/10. FGD: FGD plant expected in 04/23.
Land: Complete land for the project is under possession.
FGD draft report received and Detailed
MOE&F: Received on 19/10/09 Feasibility Report under preparation
State Pollution Control Board: Chhattisgarh Environment Conservation Board (CECB) granted BoPs:
“consent for Establishment” for 6x600 MW on 16/02/10.
Chimney-: Chimney 3,4 & 2 are in service. Flue Cans Erection completed
State pollution Control Board Clearance: Chhattisgarh Environment Conservation Board
(CECB) has granted ‘Consent for Establishment for 6x600 MW power plant of WPCLCG on for all
16/02/10. CHP: Ready in all respect
Civil Aviation: NOC received on 12/05/09. AHP: Ready
Water: Water Resources Department, Govt., of Chhattisgarh has allocated 100 Raw Water Supply System: Water Resources Department, Govt., of
MCM of water /year from Mahanadi River from proposed anicut at Basantpur. Chhattisgarh has allocated 100 MCM of water /year from Mahanadi
Coal linkage: SECL (Tapering coal linkage to 3x600MW only) Letter of Assurance(LOA) River
for tapering coal linkage to 3x600 MW has been granted by SECL on 11/06/09. FSA has been PT/ DM Plant: Three streams are commissioned and in operation.
executed with SECL on 19/03/14 for 2 units. Tapering FSA for U-3 has been executed with CW System: majority of work has been completed. Only Connection
Eastern Coalfields Ltd on 12/08/14. between CW piping is pending for Unit #5 &6.
As per the letter dated 18/10/16 IDCT: IDCT for U-1(3), 2(4) & U-3(2) are in service and for rest of
Coal blocks of Gujarat and Goa linked to the power project for cancelled by Supreme court. unit’s erection works are in progress.
Tapering linkage granted for 1800 MW was also cancelled by the Ministry of Coal on FOPH: Fuel oil distribution system commissioned
30/06/13. Long term coal linkage is required for the power project, for which policy is under CCR Building is ready for all units.
formulation with GOI. Switchyard: Back charging of 400kV switchyard completed on
27/08/2012. Control building is in service.
Critical issues Coal Linkage to remaining 3 units.
Reasons for Delay Delay due to shortage of manpower and agitations by Villagers. Supply of material due to shortage of funds.
* Unit numbering is given as per order of commissioning. Unit numbering given in brackets is as per original nomenclature.
SK-11.06.19
Stressed Project
Expenditure during 2017-18 TG: Condenser erection started on 11/11/11. TG
Total Expenditure Rs. 953779 lakhs ( up to 12/16) Deck casting completed & TG erection stared on
Zero date: 17/11/09 15/05/13
ESP: All 4 passes are under progress.
Financial closure : Achieved in March,2011
Main Plant Order : Unit-3 &4: Main plant package (BTG) awarded on 17/11/09
to M/s DEC BoPs:
BOP Package Main plant package (BTG) awarded on 17/11/09 on M/s DEC
as vendor and award of contracting agency on 12/11/09 on Chimney: RCC shell completed. Flue can erection
M/s HTC/HEC. work completed for U-3. Flue can assembly work is
u/p. Structure erection 76% completed. Stack elevator
Type of fuel Coal erection, alignment & commissioning completed.
PPA PPA signed with CSP Tradeco for 35% home state share on CHP: Track hopper work completed. Crucher house
04/01/11 erection work is u/p. TP 11,7,8,9 structural erection
Power Evacuation system LTOA approved and BPTA signed on 24/02/10. Pooling completed. Equipment erection is u/p.
station location at Champa to be confirmed by PGCIL to AHP: Ash slurry pump house; All civil work
start survey. completed. Paving& finishing are u/p. fly ash tower
Land: Total land requirement for U-1,2,3,&4 is 1395 acres out of which 791 acres already work completed.
acquired. For the entire balance land, section 4,6 &9 completed. Lease deed is to be Cooling Tower: 10985m3 RCC casting completed.
registered shortly. (Lease deed signed for 90% of total land with CSIDC, Raipur and All 24 nos deck slab completed in CU-3. 8979m3
balance is Under process). RCC casting completed and 24 nos deck slab
MOE&F: MOEF clearance for unit-3 received on 04/09/08 & renewed on 19/02/14 up to completed in CT U-4.
12/2017 and for Unit-4 on 26/05/10 & renewed on 22/06/15 up to 12/2017. Raw Water Supply System: river water intake
Civil Aviation: NOC for 275 m. Twin flue chimney was obtained on 25/08/08 from AAI. pump house slab casting completed. RCC work &
backfilling completed in forebay. Pump house
Water: Sanction of Water requirement of 54 MCM from Hasdeo river for U-3 & U-4
MCC room- slab casting completed.
received from Govt. of Chhattisgarh.
PT/ DM Plant: PT plant-RCC work is completed.
Coal linkage: U-3: LOA issued by SECL on 06/06/09. All milestones achieved.
Pumps erection is u/p. DM pant- DM plant
Letter submitted to SECL. FSA signed for U-3 on 27/08/13 U-4: LOA issued by SECL on
building, erection, alignment and grouting of
03/06/10. All milestones achieved. Letter submitted to SECL. FSA signed on 27/08/13.
vessels are u/p. DM water storage tanks are also
ready.
*Due to insolvency problem, project activities are on hold. The commissioning schedule will be decided after restart of work.
Stressed Project
Vessels Ltd, Turbine Genarator: M/s Harbine Turbine getting of startup power. Delay due to agitation by the
Co.Ltd, China villagers at project site.
Power Evacuation PGCIL granted LTOA & BPTA executed on 24/02/10. Chimney: Flue can erection completed.
system LILO line construction is completed. Elect. Inspectorate CHP: Under progress.
,CEA (WR) has given approval for LILO and 400 kV AHP: Under progress.
switchyard on 04/08/12. CW System: Under progress.
Land: Land : Required 261 Ha , Possession : 260.899 Ha.
MOE&F: obtained on 09/06/09.and State pollution clearance obtained on
09/03/09
Civil Aviation: clearance obtained on 24/04/09
Water: 18 MCM Water allocated by WRD, Govt.of C.G from Hasdeo River
Coal linkage: Allocation of coal is from Fatehpur East Coal Block ( Jointly)
allotted by MOC and tapering coal linkage granted for 2x135 MW on
29/01/10 from SLC, LT meeting of MOC, for 2nd phase of 1x270 MW under
process with MoC. Carpet coal recommended for CEA for startup of 1st unit.
Critical issues Start up / carpet coal MOU is pending with SECL. FSA execution is pending with SECL
Turbine -2 was ready from last 9 months ( as on 09/14), Foe commissioning HEC/HTC Engineers are required. AVR Feed back
Card- pending from long time, LVDT replacement- All the LVDT are not working. Rotor stoppage alarm panel to be supplied,
supply of Technical data sheet of TG instruments and ISCAN-2 for Unit-2 as per letter dated in 09/14
Reasons for Delay Delay in commissioning of U-1.Agitation by villagers at site. Delay in sullpy of BTG and CHP material. Non corporation of BTG
supplier in commissioning activities. Acquisition for railway siding and ash pond.
Uncertain
Exp. During 15-16 ( Up to : Rs. 2373 Lakh completed in all 10 fields.
11/15) Pass B: Column erection work completed.
Pass-C- electrode erection completed in all 10
Cumm. Exp (11/15) : Rs. 207723 lakhs
fields.
Approval date: Pass D: Casing erection completed. electrode
Zero date: 09/08/10 erection
Financial closure Achieved for both the units
Main Plant Order BTG Contract awarded on 28/06/10 to M/s BHEL (Boiler-
BHEL) (TG- BHEL) BoPs:
BOP Package The order for all the BOPs on EPC basis including civil works
have been placed on M/s L&T on 29/09/10. BHEL (Trichy) Chimney: Foundation works completed and
supplied 13031 MT for Boiler & BHEL(Ranipet) 7340MT for shell casting work U/P. Chimney awarded to
ESP up to 11/2014 out of which 5792 MT of Boiler & 3749 MT Bygging India Ltd on 15/01/15
of ESP erected. BHEL (PSWR) supplied 3863 MT of bunker CHP: PCC in wagon tippler & TP-2 area is
structure material, out of which 2261 MT bunker structure U/P.
fabricated. BHEL piping center (Chennai) supplied 1235 MT Coal Mill & Mill Bunker Building: All mill
Type of fuel Coal foundation & bunker pedestal casting
completed. Bunker structure and shell
PPA PPA Signed with CSPTCL & WBSEDCL for 424 MW & 200
fabrication under progress.
MW and WBSEDCL for 200MW.
Raw Water Supply System: Raw Water pipe
As per letter dated 14/01/14
line awarded to TATA Projects Ltd. On
PPA signed with WBSDCo. Ltd on 04/01/11 for 510 MW for 20
14/07/11
years through MOU route with 3part tariff (Cap. Charges+
energy Charges+ transportation charges). CSPTCo.Ltd an CW System: Raw Water pipe line awarded to
authorised representative of GOCG to execute PPA with TATA Projects Ltd. On 14/07/11
Developers on behalf of the GOCG. This PPA is in line with the
implementation agreement executed with GOCG IDCT: CT awarded to Paharpur cooling Towers
Power Evacuation system Awarded the contract for construction of 400kV D/C transmission 25/01/12. IDCT-I &2 excavation work
line on M/s KEC on 24/06/11. From PGCIL S/S at New Kotra. completed.
400/765 Kv Pooling station for power evacuation –bays
construction given to Alstom T7D on 31/12/11. Switchyard: Foundation works completed and
BTPA 24/02/10 shell casting work U/P.
Land: Delay in land acquisition & delay in placement of orders for BoPs. Delay in
supply of boiler drum by BHEL. Work is on hold due to Financial crunch.
MOE&F: MOEF clearance obtained on 23/08/11
Amendment in MOEF clearance issued on 20/05/14 regarding the reduction in project
area of 780 acres to 637 acres.
Fatehpur coal block allocated to the Visa Power.
Civil Aviation: clearance from AAI received on 25/05/10.
Water: Water allocation received from WRD, Chhattisgarh for 35 MCM on 26/09/09
Coal linkage: Fatehpur East Coal Block jointly allotted. Domestic coal linkage applied.
FSA signed with Indonesian coal supplier (PT Kubara Bumi Lestari) for supply of
imported coal.
Critical issues Boiler Drum has not dispatched by the BHEL
Reasons for Delay Order of AHP,Fire protection system, AC & ventilation system,LT/Ht switchgear, cables, air compressor, LT transformers, station, GT &
unit transformer not yet placed. Work is on hold due to financial crunch.
Stressed Project
Exp. 2017-18 : Rs. 11181 lakhs TG erection started in 29/11/13.
Condenser erection started on 01/01/14.
Cum.Exp. up to 05/17 :Rs. 640847 lakhs Work at site is on hold due to
Zero date: 01/06/11 (NIT issued) financial constraints
Financial closure : Achieved (Common loan agreement signed on 30/03/11) BoPs:
Main Plant Order : Awarded on 21/12/09 to M/s DECL.
Chimney: Erection of flue cans and stair
BOP Package M/s Abir infrastructure on 18/08/10
case completed External painting
Type of fuel Coal completed.
PPA Long term and short term PPA signed with PTC. 444 MW signed CHP: Major Erection works completed.
with CSPT and 150 MW signed with Nepal electricity authority. AHP: Major Erection/construction works
For 300 MW- LOI received & for 200 MW participated in Case-I completed.
bidding in RRVPN and 107.5MW praticipated in the case-I bid Raw Water Supply System: RWIS from
invited by MP power mgmt. company ltd. For supply of river Mahanadi to ACPL-contract
107.5MW power on the long term bases. awarded on 16/05/11
Power Evacuation LTOA granted on 01/10/09. Signed BTPA with PGCIL for 683 Barrage construction completed &
system MW 24/02/10. ISTS approval received from PGCIL on finishing work in progress
14/06/11.Approval received form MoP for construction of NoC received from WRD, GoC for laying
400kV D/c dedicted line from ACPL to New Kotra(PGCIL). of pipeline along the canal on 31/10/10.
NOC for tower height clearance received for double and approval received for Nala crossing and
multiple circuit tower from AAI. road crossing. RWIPH construction
Test charging of 400kV transmission line-1 &2 completed. completed.
Land: 927.275 acres of land in possession,25.96 Acres of Govt land
PT/ DM Plant: First stream commissioning
leased to company..
MOE&F: Obtained on 04/06/10.Amendment of EC received on 22/03/16 done in auto mode successfully &
Civil aviation: Clearence received from AAi, Mumbai on 09/04/09 commissioning of other streams are in
Water: 35 MCM per annum allocated from Mahanadi. progress.
Coal linkage: FSA signed with SECL on 27/02/15 for supply of 2497242 CW System: Erection of motor & pumps
Tonnes/annum. completed.
CT: all works completed.
FOHS: No load trail run of motors
completed. Hydro test in progress for
pipes.
Switchyard: commissioning works are
Completed.
Critical issues Delay in BTG erection work. Work at site is on hold due to financial constraints
Reasons for Delay Delay in Land Acquisition. Slow progress of boiler & TG erection. Delay due to financial problems
*Work at site is on hold due to financial constraints. The commissioning schedule will be decided after restart of work.
Uncertain
started in 05/14. TG box up completed on
Original Cost /Latest Cost: : Rs. 505800 lakhs / Rs. 689000 lakhs / Rs. 794000 lakhs 09/08/16.
Ph-I: 3787.2 Cr& Ph-II :
3106.8 Cr /Latest Cost : Ph-I
: 5240Cr & Ph-II: 3200 Cr Unit-2 : COD on 01/04/18. Full load
less 500 Cr on 28/03/18. Syn on 12/17.
Exp. During 2008-09 : Rs 4000 lakhs
Exp. During 2009-10 : Rs. 5225 lakhs Boiler :
Exp. During 2010-11 : Rs. 21435 lakhs Boiler erection started on 08/09/12. Boiler drum
Exp. During 2011-12 : Rs. 55000 lakhs lifted on 30/05/13. Boiler light up has completed
Exp. During 2012-13 : Rs. 126590 lakhs on 27/03/17. EDTA cleaning done on 03/05/17
Exp. During 2013-14 : Rs. 46778 lakhs Steam blowing completed in 11/17.
Exp. During 2014-15 : Rs.112677 lakhs TG :
Exp. During 2015-16 : Rs. 11095 lakhs( up to 06/15) Condenser erection started in 01/15. TG erection
Started in 09/14. TG put on barring gear on
Cumm. Exp Up to 06/15. : Rs 382800 lakhs 30/08/17.
Approval date: SKS signed an MOU with Govt. of Chhattisgarh on
07/01/08.for setting up coal based TPS. Unit-3:
Zero date: : 12/05/11 Work yet to start
Financial closure : completed
Main Plant Order : M/s Cethar Ltd. On 02/03/11. Boiler- Cethar Ltd. trichy, India Unit-4:
and TG - Harbin, China Work yet to start
BOP Package * The dates would be decided after start of
Type of fuel Coal Boiler erection start.
PPA 37.5% of 1200 MW with CSPTRADECO.
550 MW with TPTCL. Participated for 100 MW in Case-I BoPs:
bidding in RVPN. CHP: Ready in all respect.
Power Evacuation system Signed BPTA with PGCILon 24/02/10 for evacuation of AHP: Ready in all respect.
entire power from kotra sub-station. Raw Water Supply System: raw water intake
pump commissioned, raw water reservoir
Land: 568 acres of land acquired completed.
PT/ DM Plant: already commissioned.
MOE&F: obtained on 05/10/10 EC extended till 04/10/17 CW System: Ready.
Civil Aviation: AAI issued NOC on 09/04/2009 FOPH: Ready
Water: 35 MCM from Mahanadi (44 Km pipeline). Switchyard: 440kV trans line charged on
09/05/15. 20/6.6Kv line charged on 20/01/16
Coal linkage: Granted coal linkage for entire 1200 MW by SECL. FSA signed for U-1
&U-2 for 1.3 MTPA on 28/08/13 and 23/09/13 respectively.
Critical issues
Reasons for Delay U-3&4: Work yet to start. Balance land acquisition for ash dyke. Commissioning schedule would be assessed after restart of
work.
Critical issues
Reasons for Delay Delay in start of Civil works. Slow progress in erection works of Boiler and T.G. Manpower shortage.
Critical issues In lieu of cancellation of captive coal block, Coal linkage (5.5 MTPA) or any other coal sourcing is essential to run the plant.
Return of expenditure incurred on Mahan Coal Block.
Reasons for Delay Delays primarily due to financial constraint with the developer.
Uncertain
Expenditure during 2013-14 : Rs. 4712Lakhs
Expenditure during 2014-15 : Rs. 1614 Lakhs
Expenditure during 2015-16 : Rs. 78 Lakhs (upto 09/15)
Total Expenditure : Rs 47579 lakhs
(Upto 09/15)
Approval date: : NA
Zero date: : 03/11
Notice To Proceed (NTP) :03/11
Financial closure Achieved in 03/2011 for unit-1
Main Plant Order BHEL on 03/11 (BTG).
BTG Make BHEL
BOP Order Indure Pvt. Limited.
Type of fuel :Coal
PPA 35% with MPPMC from 2x660 MW
Source and supply of 2.1048 MTPA available for unit-1.
Fuel
Power Evacuation system PGCIL has granted LTA and connectivity.
Power evacuation at vindhyachal pooling
station.
Consultant: Desein
MOEF Clearance: Obtained in Sept.10 for 1st unit.
Land : 735-acre land is acquired.
Water: 25 MCM PA water from Gopad river for 2x660 MW.
All the mandatory clearances are available for two units.
The major part of total land acquired by the company in time but delay
in granting government land which is significant stretches had affected
the contiguity and due to which construction could not commence at
desired time.
PPA has been signed with MP Power Management Company (State
Utility) for 35% capacity from both the 2x660 MW.
Critical issues Acquisition of balance land.
Reasons for Delay Financial Costraints
Critical issues
Uncertain
Expenditure during 2013-14 : Rs.3397 Lakhs
Expenditure during 2014-15 : Rs.2390 Lakhs Boiler
Total Expenditure :Rs 76380 Lakhs(Upto 03/15) Work is on hold.
Approval date: :NA
Unit-4
Zero date: 11/10/10
Boiler
Notice To Proceed (NTP) :11/10/10 Work is on hold.
Financial closure : Achieved on 01/02/11
Main Plant Order : BTG on EPC basis awarded to Unit-5
BHEL on 11/10/10. Boiler
BTG Make BHEL Work is on hold.
Type of fuel Coal
BoPs:
PPA No PPA
Source and supply of Fuel :With MCL & WCL in 11/10(LOA) .
Work is on hold.
Power Evacuation system : Through 400kV/765KV Akola and Wardha
Substations of MSETCL through
400KV/765KV D/C transmission line.
FSA: Letter awaited.
All clearances are available.
Critical issues
Reasons for Delay Due to financial constraints project has been put on hold.
Unit-5
Commissioned on 30/05/17.
Boiler
Boiler erection started on 16/06/11. Boiler drum lifting completed on
06/03/12.BLU achieved on 15/02/17. EDTA completed on 06/03/17. SBO
completed on 24/03/17.
TG
TG erection started on 30/04/16. TG Box Up completed on 13/02/17. TG
oil flushing completed on 17/04/17. TG put on BG on 28/04/17.
BoPs:
Uncertain
Unit-4
Expenditure during 2010-11 : Rs. 10000 Lakhs
Boiler
Expenditure during 2011-12 :Rs. 5339 Lakhs
Work is on hold
Expenditure during 2012-13 :Rs. 9615 Lakhs
Unit-5
Expenditure during 2013-14 :Rs. 5022 Lakhs
Boiler
Expenditure during 2014-15 :Rs. 4400 Lakhs
Work is on hold
Total Expenditure :Rs. 71181Lakhs
(Upto 03/15)
BoPs:
Approval date: : NA
Zero date: : 24/11/09 Work at site has been put on hold since long back.
Notice To Proceed (NTP) : 24/11/09
Financial closure : Achieved on 30/06/10
Main Plant Order : BTG on EPC basis awarded to BHEL on 24/11/09
BTG Make BHEL
BOP on EPC basis Reputed Indian Vendors
Type of fuel Coal
PPA No PPA
Source and supply of Fuel : From SLC (LT) on 17/12/08.
Power Evacuation system : Through 400kV D/C quad Moose transmission line
upto MSETCL sub-station at Bhabaleshwar.
FSA: With MCL, SECL & WCL on 11/06/09.
All clearances are available.
Stressed Project
TG raft completed and Mezzanine Floor work completed. Top deck
Notice To Proceed (NTP) : Achieved on 01/12/10. shuttering work also completed, final inspection work under progress. TG
Financial closure : Achieved on 01/12/10. erection work yet to start.
Main Plant Order : EPC Contract awarded to M/s Lanco Infra Presently work is on hold due to financial constraints.
Tech Ltd.(LITL) through ICB Route in BoPs:
11/09. Boiler & Aux.: Dongfang, China
TG & Aux.: Harbin, China, Chimney: Civil works for chimney are being done by M/s LITL.
BTG Make Boiler & Aux.: Dongfang, China Chimney Raft completed. Chimney shell construction completed upto 30
TG & Aux.: Harbin, China, mtr.upto 07/16.
Type of fuel : Coal CHP: (Elecon Engg.Co. Ltd): Wagon Tippler excavation work
PPA PPA for 680MW(Net)signed with MSEDCL. completed. Raft Completed in WT area and balance work is in progress.
Source and supply of Fuel : SECL Civil works are being done by M/s LITL. In other parts of CHP such as
Stacker reclaimer , Crusher House, TPs and conveyors civil works are in
Power Evacuation system : Grant of connectivity letter received at 765 progress..
kV from Wardha-Seoni line from PGCIL.
AHP: (M/s LITL): Civil works for BA hoppers, Fly ash silo’s, AWPH,
Connectivity agreement is in progress. ASPH and ash dyke are in progress.
All clearances are available. MOEF clearance received on 24/02/11. Raw Water Supply System: Work is in progress.
Design & Engineering completed. PT/ DM Plant (DOshion Veolia water solution): Approx. 80% civil
Order for all BOPs have been placed and progressing as per works completed upto 09/16.
schedule. CW System: Civil works are with M/s LITL and mechanical works are
FSA is in process. with M/s Singrauli Associates Pvt. Ltd.. Civil works in CW pump house,
PPA with MSEDCL for 680MW signed on 25/09/08. CW fore Bay and CW open channel are in progress. 85% CW pipeline
Work was on hold since 01/2013. erection work completed upto 09/16. Balance erection work is under
Work at site restarted since April, 2015. progress.
Work in all the BoPs is also progressing nicely. IDCT: Being done by M/s LITL. For both the IDCT- I: & IDCT- II:
PCC and basin raft concreting completed. Pedestal work is in progress.
FOPH: All civil works are in progress..
Switchyard: 95% switchyard foundations completed so far.
Critical issues Financial crunch.
Reasons for Delay # Work was on hold due to financial crunch. Work has now restarted since 04/15. Work progress is slow due to Financial Costraint.
* Work on hold due to financial crunch. Schedule will be decided after restart of work.
Reasons for Delay The schedule of implementation got revised due to change in capacity from 2x250 MW to 2x300 MW. Formal approval
received on 19/03/14. Signing of FSA with WCL has to be expedited.
Uncertain
Zero date: : completed. Wagon tippler erection in progress.
Notice To Proceed (NTP) : AHP, Cooling tower, Chimney, PT plant, DM plant, CW system
completed.
Financial closure : Achieved on 08/10/12 Fire detection system erection is in progress.
Date of Main Plant Order : BTG Contract awarded to BHEL on 22/11/2011. Station transformer to be charged after back charging 220 Kv
(Boiler &TG from BHEL) Transmission line.
BTG Make Boiler &TG from BHEL
BOP on EPC basis
Type of fuel : Coal
PPA : 195 MW PPA done with private players in steel and
textile sectors. For the rest, new customers like
DISCOMs, Railways needs to be found out.
Source and supply of Fuel : SECL
Power Evacuation system Connectivity approval from MSETCL for 220 kV
line at Amalner substation
All clearances are available.
Design & Engineering completed.
Order for BOPs on EPC basis have been placed M/s Punj Lloyd on 03/08/10.
In all the BOPs work already completed.
Critical issues
Reasons for Delay
AK-31/12/2019
Commissioning Schedule
Sl. Project Details Unit Capa- Original
Actual(A)/ As Broad Status
No. No. city
Expected
(MW)
Syn. COD Syn. COD
Comm Comm
State Sector
1 Rayalaseema TPP St-IV 6 600 07/14 02.07.17(A) 04/18 Unit Synchronized on 02.07.17. Full Load
(M/s. APGENCO) 08/14 29.03.18 (A)
achieved on 29.03.2018.
Distt.Cuddapah,
Andhra Pradesh Boiler: Erection started on 04/02/2013. Boiler Drum
Original /Latest Cost : Rs. 302886 / 388043 Lakh lifted on 30/11/13. 26952 MT/ 29730MT structural
Expenditure during 2009-10 : Rs. 555.00 lakh materials erected till 10/17. Boiler air leak test completed.
Expenditure during 2010-11 : Rs. 25833.00 lakh BLU done on 29/12/16. EDTA cleaning completed on
Expenditure during 2011-12 : Rs. 8155.00 lakh 26.02.17. Mill foundation on both sides completed. Bowl
Expenditure during 2012-13 : Rs. 29331.00 lakh mill deck slabs completed for all mills.
Expenditure during 2013-14 : Rs. 80045.00 lakh TG: TG erection started on 04/03/16. TG box up done in
Expenditure during 2014-15 : Rs. 52429.00 lakh 02/17.
Expenditure during 2015-16 : Rs. 62341.00 lakh Chimney (M/s Gammon): Shell concreting completed.
Expenditure during 2016-17 : Rs. 83576.96 lakh A.R.Brick work completed up to (+) EL 135.30 M height.
Expenditure during 2017-18 : Rs 69776..04 lakh ( 12/17) CHP: Work awarded to M/s Thyssenkrup.
Total Expenditure : Rs 412042 lakh (up to 12/2017) AHP: Vacuum pump house building, Silos, Bottom ash
Zero date : 10/02/2011. hopper, Buffer hopper, ASPH etc. area civil works
completed
Financial closure : Achieved on 19/03/10
RWR: Trimming of slopes of reservoir bund is in
Type of Fuel : Coal progress. In the raw water pump house RCC structure
Main Plant Order Placed on M/s BHEL for BTG on 18/11/10. completed.
BOP Package Purchase order placed on the consortium led by M/s PTP: clarifier works completed.
Tecpro Systems Ltd, including civil works on EPC basis DM Plant: Roof slab work up to 183.10 ml completed.
on 15/12/10. Now it is led by VA Tech. Vessels foundations ready. Vessels material available at
MOEF clearance obtained on 21/10/2010. site. Some vessels are placed in position.
PFC Sanctioned a loan of Rs. 2423 crores. CWS: raft work in CW pump house completed. All walls
M/s Desein Pvt. Ltd is providing engineering consultancy services. raised up to pump floor. PCC works of fore bay in
progress. CW pipe line fabrication is almost complete.
NDCT (M/s Gammon): Shell erection 32 lifts completed
&33rd in progress.
FO System: M/s Xicon is executing these works Civil
work almost completed. Tanks fabrication & erection in
progress. Fuel oil transfer pump tank HFO and LDO day
tank slab completed & handed over for erection work.
Switchyard: Foundations of all equipment were
completed and handed over for erection of equipment’s.
Critical issues
Reasons for Delay
SB-Jan 2020
Extension granted to 2021
Civil Aviation: NOC obtained on 28/02/11from AAI for 281 m height of chimney.
PROJECT UNDER NCLT
Water:100 Cusec/day sea water from Kandaleru Creek accorded by Principal
Secretary (FAC), Infrastructure & Investment (Ports-I), AP on 18/02/10.
Fuel Linkage: Letter of Assurance (LOA) dated 11th June 2009 obtained from
Mahanadi Coalfields Ltd (MCL) for the supply of 2.023 MMTPA Grade “F” Coal.
Fuel Supply Agreement dated 31 August, 2013 executed with Mahanadi Coalfields
Ltd(MCL) for the supply of 1.0115MMTPA Grade “F” coal for Unit 3 (350 MW).
Imported Coal Supply Agreement: Coal Supply and Transportation Agreement dated
25 November, 2013 executed, with GDF Suez Energy Management Trading SCRL,
34, boulevard Simon Bolivar, 1000 Brussels, Belgium. Coal Quantity : 2.50MMT per
annum
BPTA: BPTA signed with PGCIL for 300 MW on 24/02/2010 and for additional
BPTA signed for 1000 MW on 02/01/12
Mega Status: Achieved in 02/12
Critical issues
Reasons for Delay Slow progress of Civil works. Due to financial problem, work at site remained closed for a long time. Change of stakeholders and
subsequent change in the completion of various milestone.
Stressed Project
Approval date:
CHP: Awarded to M/s BSBK. Piling completed.
Zero date: : 15/09/2010
Dewall works in track hopper area completed.
Financial closure : Achieved on 08/09/2010. Lead Financier - PFC AHP: Order placement is in progress.
Main Plant Order: Order placed on 03/09/2009 on DEC China (BTG) WTP: Engineering is in progress.
BOP Package : EPC of BOP & Main plant Civil works contract DM Plant: Engineering is in progress.
awarded to consortium of M/s NEC and M/s Abir CW System: Engineering is in progress.
Infrastructure Pvt Ltd on 30/01/10. NDCT: Order placed on M/s Paharpur Cooling Towers.
Type of fuel FPS: Engineering is in progress.
PPA :Long term PPA signed with PTC India Ltd on FOS: Order placed on Delta P.D. Pumps on 14/05/12.
25/06/10 as an amendment of 06/05/09 Tank fabrication work completed.
Power Evacuation system Switchyard: Engineering is in progress.
Land: Total land of (2050 + 36.94 Colony) Acres is acquired. ATS: Award of contract to be done by ECEPL.
MoE&F: Clearance obtained on 09/04/2009 & revalidated on 20/08/14.
Water: Permission for drawl of 168 cusec sea water from Govt. of AP is obtained on
10/06/2008. Presently work held up at site
SPCB: clearance obtained from APPCB on 15/06/2009 revalidated on 30/12/14.
Civil Aviation: AAI clearance obtained vide lr. Dt. 04/03/08 & revalidated up to 3 rd due to financial issues.
March 2020.
Coal Linkage / FSA: LOA received from MCL for 4.273 MTPA on 11/06/2009. FSA
to be signed. FSA signed with Global Fuels pvt Ltd Singapore for balance quantity of PPA details are as follows: Having PPA for 100 MW
coal on 23/04/09 with Kerala. Having LOI for 300 MW but in dispute
BPTA: BPTA signed with PGCIL on 21/09/12. due to formation of Telangana. For 500 MW PPA with
Andhra Pradesh, developer is L1.
Reasons for Delay Law & Order problem, Financial problem of the company, acquisition of balance land for sea water intake & railway siding.
Commissioning Schedule
Sl. No. Project Details Unit Capa-city Broad Status
No. (MW) Original Actual(A)/ As
Expected
Syn. COD Syn. COD
Comm Comm
State Sector
1 Kothagudem TPS –VII (TSGENCO) 12 800 09/17 12/17 30.06.18 26.12.18
Distt. Kammam, Telagana 11/17 05.10.18 (A)
(A)
Unit Synchronised on 30.06.18. Full load
achieved on 05.10.18. COD on 26/12/18.
Original Estd. Cost/Latest Cost : Rs. 554844 lakhs / Rs. 554844 lakhs
Expenditure during 2014-15 : Rs. 199.60 lakhs Boiler: Civil work started on 12/06/15 and erection
Expenditure during 2015-16 : Rs. 54654.50 lakhs commenced on 24/01/2016 and is in progress 98.4%
Expenditure during 2016-17 : Rs. 170310.10 lakhs completed. HT (Drainable) completed on 22.09.17.
Expenditure during 2017-18 : Rs. 107615.42 lakhs BLU completed on 31.01.18. TG Deck: TG civil
Expenditure during 2018-19 : Rs. 130783.19 lakhs (12/18) work started in 23/08/15. TG erection started on
Total Expenditure(Up to 12/18) : Rs. 466995.13 lakhs 28.02.17. TG Boxed up in 06/18.
Approval date:
Zero date: 01/01/2015 BOPs
CHP: Civil work awarded to M/s. SNC on 12/02/16.
Financial closure Tied up with REC on 17/01/2014 94% completed. Wagon tippler side arm charger
Main Plant Order (BTG on M/s BHEL)- LOI issued on 27/12/14. works completed. Stacker cum reclaimer awarded to
BOP Package M/s TRF on 12/08/15 commissioning of SCR-I
Type of fuel Coal, FSA: M/s Singareni Collieries Co. Ltd, Kothagudem. completed. Conveyor system awarded to M/s.
BEVCON on 22/08/15: Material received and
PPA PPA signed on 22/01/2013 and power evacuation system
erection work under progress. Crusher, vibrating
400 Kv by TSTRANSCO.
screens/peddle feeder awarded to M/s Elecon on
Power Evacuation system 400kV by TSTRANSCO 23.02.16- Material received Erection works in
LOI was issued to BHEL on 27/12/2014 (i.e Main plant equipment Boiler, Turbine & Generator- progress.
BTG) AHP: Civil work Awarded M/s SNC on 12.02.16.
MOEF clearance obtained on 16/07/15. 93% completed. Supply & Erection work awarded to
SPCB clearance obtained on 12.11.15 M/s OSM : 95% material supplied.
SPCB: Applied for consent for establishment and approval awaited. Cooling Tower: Awarded to M/s. Paharpur cooling
REC has sanctioned a loan vide letter dated 17/01/14. towers ltd. on 04/03/16, work started on 12/07/16 and
Water allocation available vide G.O.MS No.47, dated 24/12/14. 99.8% completed.
AAI clearance obtained vide letter no. AAI/SR/NOC/RHQ dt.15/10/12. Chimney: Awarded to M/s. BIL on 16/05/15.Chimney
is completed.
PT Plant: Civil work Awarded to M/s. Punj Lloyd Ltd
(PLL) and 95% completed. Supply & erection
awarded to M/s Clear water: 98% material supplied &
80% work completed.
DM Plant: 98.5% completed.
CW System: 98% civil works completed.
Fuel Oil Handling System: 97% civil works
completed.
FGD: LOI issued to M/s BHEL
for providing wet lime based
FGD with completion period of
30 months. Works yet to start.
Critical issues
Reasons for Delay
Reasons for Delay Work held up due to order from National Green Tribunal (NGT) and non-availability of MoE&F clearance.
SB –Jan 2020
Critical issues
Reasons for Delay Work held up due to order from National Green Tribunal (NGT) and non-availability of MoE&F clearance
SB-DEc2019
Critical issues
SB-21.01.2020
Critical issues 1) Inter-connection & Transmission facilities are by TANGEDCO which is yet to be awarded. The COD is
linked to the availability of Start up Power.
(2) Approval/NOC from Department of Forests, GoTN for pipeleine and conveyor crossing.
(3) Fixation of revised date of availability of start up Power and accordingly the SCOD at TNERC.
(4) Approval of Coal Supply, Transport and Handling Agreements by TANGEDCO and TNERC.
Reasons for Delay Requirement of startup power was delay from 30.04.2018 to 09.04.2020 (Expected)
SB-03.02.2020
Stressed Project
Financial closure : Achieved on 24/02/2011 Drawings under finalization.
Main Plant Order : 28/05/2010 (BTG) on M/s Shandong ACC: Order placed on HAC China.
Runch Power Plant Engg and Technology Drawings under finalization. ACC
Limited. foundation works in progress.
Type of fuel : COAL M/s Consolidated Construction
PPA : Participating in the Bids Consortium Limited have been
Power Evacuation system : BPTA signed with PGCIL on 24/02/2010. awarded main plant civil & structural
LTOA signed with PGCIL on 12/06/2013. work on 14/12/10. Civil work started
Land: Total land of 880 acre acquired WTP: Order placed on Sokeo Power.
Water: Agreement between IBPML and South Ganga was signed on Engineering works in progress.
03/04/10. DM Plant: Technical discussions are
MOEF: clearance obtained on 12/07/2010. in progress.
SPCB: Consent obtained on 17/10/2013. CW system: Order placed on Sokeo
Civil Aviation: clearance obtained on 24/08/10 Power. Technical specification
PPA: To be executed through case –I bidding. verification is in progress.
BPTA: signed with PGCIL on 24/02/2010 FO system: Engineering is under
progress.
FPS: Foundation works completed.
Erection works to start from 01/16.
Switchyard: Engineering in progress.
Critical issues
Reasons for Delay
SB-21.01.2020
Uncertain
Financial closure :
Presently no work is in progress at
Main Plant Order M/s Dongfang Electric Corporation Ltd., China
BOP Package
site.
Type of fuel Coal
PPA
Power Evacuation system
MOE&F Clearance: MOE&F Clearance received vide letter NO. J-13012/89/2008-IA. II(T)
dated 29.06.2011
SPCB Clearance: NOC for consent to establishment obtained from BSPCB.
Civil Aviation Clearance: Aviation Clearance has been obtained from Airport Authority of
India.
Critical issues
Reasons for Delay
Uncertain/
28/03/2011 for Phase-II.
Main Plant Order Letter of Acceptance for Main Plant Order (EPC) issued to M/s Phase-II
BHEL on 09/2009. Unit-3:
Boiler: Erection started on 06/11. Boiler
BOP Package Order for BOP’s placed on
M/s Energo Engg. Projects. Ltd. for CHP on 06.05.10.
drum lifted on 12/11
M/s DCIPS. for AHP on 08.10.10. ESP
M/s Simplex Infrastructure Ltd. for Chimney on 03.05.10 TG: TG erection started in 10/12.
M/s Paharpur Cooling tower for CT on 04.05.10.
Stressed Project
Type of fuel
PPA
Power Evacuation system
Coal
PPA executed with Lanco Trading Co. in April 2010
LILO at Barauni of Begusarai-Biharsarif 220KV D/C
done. Power evacuation system expected to be ready
by Dec-2015.
Unit-4:
Boiler: Erection started on 07/11. Boiler
drum lifted on 04/12
ESP:
TG: TG deck is ready.
BoPs:
Chimney: Completed in all respect
CHP- 98% structure erection completed
AHP- FA silo completed. Erection of
Bottom Ash Hopper completed.
Station transformer & Unit Transformers
and associated systems is in ready.
Generator Transformer is placed on
foundation.
ATS balance work is to be taken up after
stage – II Forests clearance is obtained.
PT plant, DM plant, CW system, Fire
protection system Fuel oil system &
Switch yard completed.
Critical issues 1.Associated Transmission System for a short distance is to be taken up after Stage-II forest clearance is
obtained.
Reasons for Delay Work held up due to payment issue with BHEL since 11/12. Commissioning Schedule will be
assessed after restart of work.
Uncertain
Unit-3 –Work not yet started.
Expenditure during 2012-13 : Rs. 32446 Lakh Rs. 3172 Lakh
Expenditure during 2013-14 : Rs. 96502 Lakh Rs. 4760 Lakh
Expenditure during 2014-15 : Rs. 37649 Lakh Rs. 63 Lakh BoPs:
Expenditure during 2015-16 Rs. 66430 Lakh Rs. ---
Expenditure during 2016-17 Rs. 23265 Lakh Rs. --- Chimney: Order placed on M/s Essar
Total Expenditure Ph-I: Rs.4718.59 Cr. (till 12/16) Projects India Ltd.. Windshield work
Ph_II: Rs.246.65 Cr(till 3/15) completed. Flue can fabrication 60%
Approval date:
completed.
Zero date:
CHP: Order placed on M/s Elecon engg
Financial closure Achieved & Mcnally Bharat Engg.Co
Main Plant Order Ph-I: AHP: Basic engineering completed.
18/08/2008 - Main plant Civil & Structural work on Essar Projects (I)
CT: Order placed on M/s SPIG Cooling
Ltd.
BTG on M/s Harbin Power (HPE) Engineering, China in 11/ 2008 Tower India Pvt. Ltd.
Ph-II: PT & DM Plant: 40% material received.
Main plant Civil works on EPI Ltd on 26/02/2010 BTG on HPE FPS: Order placed on M/s Brijbasi Hi-
BOP Package Order for BOP’s placed on tech Udyog Ltd on 15.11.10.
M/s Mc Nally Bharat Engg. Co. Ltd. And Elecon Engg. For CHP on Switchyard: Order placed on M/s Alstom
22.09.10 & 31.08.10. T&D on 22/12/10
M/s Mc Nally Bharat Engg. Co. Ltd. for AHP on 15.09.11.
M/s Essar Projects India Ltd. for Chimney on 18.08.10 Presently no work is in
M/s SPIG Cooling tower India Pvt. Ltd for CT on 19.11.10. progress due to financial
Type of fuel COAL
PPA 1.450MW+300MW with BSEB
constraints
2.PPA signed with JSEB for 12% of the total power generated at
variable cost under MoU route
3. Draft PPA submitted to JUVNL for 13% of the total power
generated at JSERC rates under MoU route.
Power Evacuation system BPTA signed with PGCIL and bay agreement executed. PGCIL
is setting up 400KV substation near the project.
Land 1210 acres of land required for both the Phases 1&II of (2x600 +1x600 MW) is available.
BOPs are common for both units.
MOEF clearance already available for U-I of Phase-I. Clearance for U-2 of Phase-I and U-3
Phase-II received vide MOEF letter dated 14.11.2013.
Civil Aviation Clearance: NOC for height of chimney is valid tilltill 21.07.2020
SPCB: Clearance obtained from JSPCB is valid till 31.03.2016
Coal: Due non availability of MOEF clearance for the Chakla & Ashok Karkatta coal block
allotted to this project it is proposed to import coal from Indonesia & Australia for the time
being.
Water Source of water is from Damodar and Amanat rivers which are 20 &30 KMs from
the site.
Critical issues Mega Power Project status is yet being issued from MoP due to which 97% imported main plant equipment are lying at
site/ Port.
Tapering coal linkage.
Reasons for Delay Reasons for Delay:- Delay in MoE&F Clearance` (14.11.2013 for U2 & U3), Change of design in water cooled condenser to
air cooled condenser due to water availability issue, Law & order issue, delay in grant of Mega power project status,
cancellation of coal block and non-availability of tapering / long term coal linkage etc.
LAND: Required land is in possession of OPGC except the 40 acre of land for MGR BoPs: All BOPs are completed and operational except
work. MGR, because 40 acres land for MGR possession is
MOEF: EC was granted on 04.02.2010, amended on 22.01.2014 and validity extended on pending.
16.1.2015.
Coal linkage: Coal will be sourced from Manoharpur & Dip side Manoharpur allocated to
OCPL, A JV subsidiary company of OPGC. FGD Plant: Consultant finalized,
WATER: Agreement signed with water resource department on 26.08.2013
SPCB: Consent to establish was granted from OSPCB on 04.02.2010 and revalidation was
Techno – commercial bid evaluation in
done on 27.11.15 progress.
CIVIL Aviation: Clearance obtained from AAI on 15.03.2010
Critical issues
Reasons for Delay There is an incident occurred where LP Turbine blade failed at 3000 RPM before synchronization (on coal) so there is
anticipation that COD Unit 4 might shift from Feb 19 to mar 19.
SB-28.08.2019
Critical issues 1.Non readiness of CHP & AHP and ATS for Unit-2
2. Completion of bottom ash hopper
Reasons for Delay 1. Very slow progress of civil work
2. Supply of main Plant material
3. Readiness of power evacuation system
4. Completion of firing guns/burners due to technical problem in design.
5. Mainly financial constraints due to non-disbursement of funds by financer.
Stressed Project
various levels. Burner erection was in progress.
Zero date: : 17.11.2009 Preparatory work for Pressure part erection yet to
Financial closure : Achieved on 08.09.2010 complete.
Main Plant Order Main plant order placed on Lanco Infaratec Ltd. On ESP: 41% of structural erection completed. Hopper
17/11/2009, Boiler: DEC China, TG: HEC China. erection is in progress. Pass A-2/9 Collecting electrode
erection completed. Pass C- hopper assembly erection
BOP Package BOPs to LTTL and casing wall assembly work completed.
Type of fuel Coal TG: EOT crane commissioned. Columns upto deck
PPA Revised PPA signed with GRIDCO, Odisha for 25% bottom completed, MDBFP#2 foundation completed.
power sale on 4.01.11. LBPL signed PPA with UPPCL CEP & CW Pit #2 raft completed. MDBFP#2
for 454MW on 08.08.13 & with RVPNL for 374MW on foundation completed.
01.11.13. BoPs:
Chimney: 252/270m shell construction completed.
Power Evacuation system BPTA signed with PGCIL for 1600 MW on
Flue can fabrication was in progress.
24.02.10(Revised to 800MW as per CERC order). 25KM CT: FRP Cooling tower awarded to Paharpur.
of transmission line is planned for power evacuation from IDCT#1 305/454 raft footing work completed.
LBPL project to PGCIL Angul pooling station. The power 275/481 nos column completed. Excavation upto
shall be evacuated at 400KV level through 1 D/C quad 70% completed for IDCT#2 and raft footing work
Moose transmission conductor. Section 68 and Section was in progress.
164 approval received from MoP. CHP: Track hopper raft and both side walls
Land: 889 acres out of 933 acres’ land acquired. (95%) completed. Crusher house foundation work
completed. Stacker reclaimer footing raft completed..
st
MoE&F: Clearances obtained on 17.02.10 and is valid upto 31 Mar 2017 JTs foundation work completed. Crusher house civil
Forest: II-Stage clearance received on 31.12.13 from MoEF work completed.
Water: Principle approval received for 40 cusecs water for U-1 &U-2 on 07.02.09. AHP: RCC of BAH#1 completed. Raft footing
Renewal received on 18th Jan’16 completed and wall final lift is in progress for ASPH.
Coal linkage: Coal linkage for U-1 received on 29.12.08 for 2.83MTPA. FSA has Ash silo raft#1 completed. 8/26 nos. footing
been executed with MCL on 26.04.16. completed for Ash compressor house building
PT/DM plant: Foundation work completed. DM
SPCB: NOC obtained on 20.05.09 from Odisha SPCB and it is valid till 19.05.19
building structure erection completed and equipment
Civil Aviation: NOC obtained on 03.09.08 and valid till 02.09.2020 erection in progress. Clarifloculator ring wall in
progress. DM tank-1 erection completed.
FO system: 2LDO + 2HFO fuel oil tanks erection
completed. LDO-2 water fill test completed.
Switch yard: Erection of 23 nos. towers & 18 nos.
of beam completed. S/Y equipment received at site.
Control room building brick work completed and
preparation for slab casting has started.
Stressed Project
Financial closure : Achieved on 23.08.2010
are installed, foundation of PA and FD fans
Main Plant Order Main plant order placed on M/s BHEL completed. Drum lifted 21.07.12. HT & BLU may
BOP Package be assessed after start of work.
Type of fuel Coal ESP: Erection of pass B, C & D done and pass A yet
PPA PPA signed with GRIDCO for 117MW for 400 MW to be done.
with West Bengal through PTC. TG: Condenser erection started on 7.02.13 and TG
Power Evacuation system 400KV double circuit transmission line up to proposed erection started in 08/2015, TG box up may be
PGCIL pooling station, which is 31km away from assessed after restart of work.
power plant. BoPs:
Land: 770 acre acquired out of 995 acre required.
Chimney: Chimney shell casting completed flue can
MOEF: Clearance of MOEF has been obtained erection for U-I completed, for U-II two top
Water: Water allocation done segments erected.
Coal linkage: Mandakini captive coal mines. CHP: Fabrication and erection of CHP structure are
SPCB: Clearance obtained from Orissa SPCB. in progress along with equipment erection could be
Civil Aviation: Clearance obtained from AAI completed after restart of work.
AHP: Civil work for ash slurry sump, pump house,
ash water pump house and silos completed. Pipe
erection was in progress.
IDCT: Orders placed to M/s Indure 0n 22.02.2010.
Construction of cooling tower for both the units are
completed in all respect, mechanical and electrical
erection work not completed.
DM Plant: Civil & structural work is completed
mechanical and electrical erection not completed.
PT Plant: Civil work completed, mechanical and
electrical erection to be done.
CW System: Pump house completed. Pumps and
associated pipe lines erection are to be erected.
FO System: Pump house, tank erection, pipe rack
work is yet to be completed.
Fire Protection: Fire water pump house civil
construction is completed and mechanical &
electrical erection yet to be done.
Switchyard: Construction completed.
Commissioning and testing work not completed.
Critical issues
Reasons for Delay Paucity of fund.
Uncertain
Chimney: 90 mtr. Chimney shell completed.
Expenditure during 2013-14 :Rs 5847.00 lakhs
Expenditure during 2014-15 :Rs 6000.00 lakhs
Total Expenditure :Rs 1708.36 Cr (up to 03/15)
Approval date:
Zero date: : 09.11.2009
Financial closure : Achieved for Ph-I(1X350MW) in 07/08 and Ph-II
(2X3501MW) in 08/10
Main Plant Order BTG-Harbin, China, 09.11.09
Note: No work is under progress
BOP Package presently.
Type of fuel Coal
PPA PPA signed for (1000MW)
Power Evacuation system Bulk Power Transmission Agreement (BTPA) with
PGCIL
Land: Required land acquired.
Water: Allocated by GoO vide letter irr-ii-wrc-73/08/15032 dt. 15..04.20008 for 48 cusecs
from Mahanadi.
Critical issues
Reasons for Delay 1.Law and order problem
2. Work held-up due to stay by honorable HC of Odisha. From 18.05.12 to 05/2015
Uncertain
Expenditure during 2017-18 : Rs 4809 lakh ESP: 2153/2158 MT structural erection completed.
Hopper erection is in progress.
Total Expenditure Rs 326305 lakhs (up to 10/17) TG: Deck casting completed.TG erection started on
Approval date: 05/05/16. TG box up done 15.10.17, TG Oil Flushing
Zero date: 28-11-2013 done on 18.10.17.
Financial closure Achieved on 22.12.2011 with REC Unit-3
Boiler: Boiler erection started on 15.05.15.
Main Plant Order Placed to BHEL 29.09.2010 1320/3274MT structural erection completed. Drum lifted
BOP Package Order for BOP’s placed on on 14.01.16. Piling of 2/4 mill completed. Excavation for
M/s Shristi Infrastructural Development Corp. Ltd & Scorpio ID/FD/PA has completed.
Engg Pvt. Ltd. for CHP on 20.12.13. ESP: Foundation completed. 567/2158 MT structural
M/s Shristi Infrastructural Development Corp. Ltd & Energo erection completed.
Engg. Project. Ltd. For AHP on 10.01.14. TG: TG deck raft casting completed. Water has logged in
M/s Simplex Infrastructural Ltd. for Chimney on 09.05.12 this area. Presently no work is going on in this site.
M/s Paharpur Cooling tower for CT on 24.03.14. BoPs:
Type of fuel Coal Chimney: Civil work for chimney completed. Flue can
PPA : For 300MW with WBSEDCL erection for U#1, 2 &3 completed. Platform erection
Power Evacuation system 220KV Transmission line of length from plant to new haldia completed
sub-station of WBSETCL. CT: IDCT-1&2 has completed in all respect. CT#3: Pile
Land: Complete land acquired 213.71 acre, 198 from Haldia Development authority and rest work was in progress. Presently no work is going on in
from private. this site
MoE&F: Clearances extended on 30.08.15 upto 12.04.2017 vide letter No. J-13213/16/2014-IA. CW System: CWPH building completed. All Four CW
I(T) pump commissioned. Laying of CW pipe completed for
Water: 15 MGD water is available from Haldia Development authority. all the three units. Forebay and cold water channels
SPCB: NOC received from GoWB. completed.
Coal linkage: Long term coal supply agreement No: SNRL/IPC(H)L/FSA 2015-16 between M/s CHP: Structural erectionand floor casting of srusher
Swaymbhu natural resources private limited and M/s India Power Corporation (Haldia) Ltd. house is completed.Stacker cum reclaimer has installed.
Civil Aviation: NOC vide letter No.AAI/20012/82/2010-ARI(NOC) date 23.10.2010 for Erection of galleries from coal stack yard to TP-1&2 is
construction of chimney extended upto 22.06.2022. completed. Gallery from TP-2 to bunkers of U-1 is
completed. Conveyor belt laid upto U-1 bunkers for one
stream.MCC room completed.
AHP: Civil work of Ash Silo, Dewatering Bin, Ash
slurry pump house, ash water pump house and control
room building are completed. Construction of Slurry sump
is completed. Erection of Ash water pumps and transport
air compressors completed. MCC room is completed.
Control room is ready.
PT Plant: Raw water reservoir completed. RGF
commissioned and system is operational.
DM plant: DM plant is RO type. Erection of 2nos DM
tank and 3nos.CST completed. DM plant commissioned.
FO system: 2 LDO tanks and necessary pumping system
ready.
Switch yard: Structural erection of 220KV equipment in
switchyard is completedin all respect.
FGD: detailing of feasibility report is under process.
*Unit-3 work is totally on hold.
Critical issues
Reasons for Delay Construction activity was stalled from beginning of 2011 to Sept 2014 due to following reasons:
1. Fresh clearance from Pollution Control Board for 3x150MW (Earlier it was acquired for 3x135MW)
2. MOEF moratorium for no construction activity in Haldia & Asansol industrial area in West Bengal
Engine:Wartisila Finland OY
Generator: ABB Finland OY
Gas Compresor: Kirlosker Pneumatic
Company Ltd.
मासिक प्रसिवेदन
( - ) ‘2020)
(January–February’ 2020)