Broad Status Report: Thermal Power Projects

Download as pdf or txt
Download as pdf or txt
You are on page 1of 120

भारत सरकार

GOVERNMENT OF INDIA
विद्युत मंत्रालय
MINISTRY OF POWER

BROAD STATUS REPORT


Under Construction
THERMAL POWER PROJECTS

जनििी– फिििी ‘2020


January–February’ 2020

तापीय विद् यु त परियोजना प्रबोधन प्रभाग


Thermal Project Monitoring Division
के न्द्रीय विद् यु त प्रावधकिण
Central Electricity Authority
नई वदल्ली
New Delhi
(विद् युत अवधवनयम, २००३ की धािा ७३ (एफ) के तहत के.वि.प्रा. के दावयत्व की पूणणता के विये संकवित )
(In fulfillment of CEA’s obligation under section 73(f) of Electricity)
Sl. No. Contents Page No
SUMMARY
1.0 12th Plan Capacity Addition Programme 05
1.A Total Capacity Addition (MW) During 12th Plan 05
1.B Year wise Sector wise Thermal capacity Addition Target / Achievement during 12th Plan 05
1C Sector-wise break up of under construction Thermal Power Projects 05
1D Thermal capacity added during the year 2018-19 05
1E Provisional Thermal Capacity Addition Target for 2019-20 06
2.0 Thermal Capacity Addition Target/ Achievement for the year 2012-13 07-08
2.1 Thermal Capacity Addition Target/ Achievement for the year 2013-14 09-10
2.2 Thermal Capacity Addition Target/ Achievement for the Year 2014-15 11-12
2.3 Thermal Capacity Addition Target/ Achievement for the Year 2015-16 13-14
2.4 Thermal Capacity Addition Target/ Achievement for the Year 2016-17 15-15
2.5 Thermal Capacity Addition Target/ Achievement for the Year 2017-18 16-16
2.6 Thermal Capacity Addition Programme (RFD) for the year 2018-19 17-17
2.7 Thermal Capacity Addition Target/ Achievement for the Year 2019-20 18-18
3.0 Target/Achievement of Thermal Cap. Addition During 12th Plan 19-26
4.0 Thermal Projects Slipped from 12th Plan Target with reason for slippage 27-28
5.0 Thermal Power Projects under construction in the country 29-32
CENTRAL SECTOR PROJECTS
1. NATIONAL THERMAL POWER CORPORATION LTD.(NTPC Ltd.) 34-49
Bongaigaon TPS, Distt: Kokrajhar, Assam 34
Barh STPP St-I, Dist: Patna, Bihar 35
Nabinagar TPP, Dist: Aurangabad, Bihar 36
New Nabinagar STPP, Dist.: Aurangabad, Bihar 37
Lara STPP, Dist:Raigarh, Chhattisgarh 38
North Karanpura STPP, Dist.Chatra, Jharkhand 39
Kudgi STPP St-I, Dist: Bijapur, Karnataka 40
Solapur STPP, Dist: Solapur, Maharashtra 41
Gadarwara STPP, St–I, Dist: Narsinghpur, Madhya Pradesh 42
Khargone STPP, Dist.Khargone, Madhya Pradesh 43
Darlipalli STPPSt-I, Dist. Sundergarh, Odisha 44
Telangana TPP (Ph-I), Dist. Karim Nagar Telangana 45
Meja STPP, Dist:Allahabad, Uttar Pradesh 46
Tanda-II STPP, Dist. Ambedkar Nagar, Uttar Pradesh 47
Patratu TPS, Dist. Ramgarh, Jharkhand. (JV of NTPC & Govt. of Jharkhand)] 48
Rourkela PP-II Expension, Odisha 49
2. NEYVELI LIGNITE CORPORATION LIMITED (NLC Ltd.) 50-53
Neyveli New TPP, M/s Neyveli Lignite Corporation Ltd. at Neyveli in Tamil Nadu 50
Ghatampur TPP,JV of NLC & UPRVUNL,Lahurimau village,Ghatampur,Kanpur 51
Barsingsar TPP ext, (Distt. Bikaner ), Rajastan 52
Bithnok TPP, (Distt. Bikaner ), Rajastan 53
3. TEHRI HYDRO DEVELOPMENT CORPORATION LIMITED (THDC Ltd.) 54-54
2x660 Khurja STPP (UP) (THDCIL) 54
4. SATLAJ JAL VIDHUT NIGAM LIMITED (SJVN Ltd) 55-55
Buxar TPP U.P. (SJVNL) 55
STATE & PRIVATE SECTOR PROJECTS
Northern Region
5. Rajasthan 58-59
Chhabra SCTPP, Chhabra RRVUNL, (Distt. Baran ) 58
Suratgarh Super Critical TPP, RRVUNL, Suratgarh 59

TPM_Broad Status Report (January-February’2020) 2


Sl. No. Contents Page No
6. Uttar Pradesh 60-64
Prayagraj TPP, Distt. Bara, Allahabad, M/s Prayagraj Power Generation Co. Ltd. 60
Harduaganj Expn.,-II, UPRVUNL, Distt.; Aligarh 61
Obra-C TPP, UPRVUNL, Obra, Dist. Sonebhadra 62
Jawaharpur STPP, JVUNL( A 100% subsidiary of UPRVUNL), Dist. Etah 63
Panki TPS Ext, Distt. Kanpur, U.P. (UPRVUNL) 64
7. Uttarakhand 65-66
Kashipur Gas Based CCPP, Ph-II, Udhamsingh Nagar (M/s Sravanthi Energy Pvt. Ltd.) 65
BETA CCPP, Module-I, at Kashipur Udhamsingh Nagar 66
(M/s Beta Infratech Pvt. Ltd.)
Western Region
8. Chhattisgarh 67-74
Akaltara(Nariyara) TPP, Distt: jangir-Champa 67
M/s KSK Mahanadi Power Company Ltd
Uchpinda TPP Ph-I, R.K.M Power, Janjgir Champa District, Chhattisgarh 68
Lanco Amarkantak Mega TPS Phase-II (Pathadi ), 69
(Distt. Korba ) M/s LAP Pvt. Ltd.
Salora TPP , Katghora Tal; Distt. Korba, M/s Vandana Vidyut Ltd 70
Deveri TPP Raigarh TPP (Visa) (VISA Raigarh STPP, Ph-I,) (Distt: Jangir Champa) 71
M/s VISA Power Ltd.
Singhitarai TPP ( DumatpalliTPP), Janjgir (Vill), Champa Distt. 72
(M/s Athena Chhattisgarh Power Ltd)
Binjkote TPP, Vill-Binjkote, Distt.: Raigarh, 73
SKS power Gen. (Chhattisgarh.) Ltd
Nawapara TPP (TRN TPP), Distt: Raigarh, M/s TRN Energy Pvt Ltd 74
9. Gujarat 75-75
Wanakbori TPS Extn., GSECL, Dist: Kheda 75
10. Madhya Pradesh 76-79
Shree Singaji TPP, Stage –II, (At Dongalia Distt. Khandwa), MPPGCL 76
Mahan TPP, Dist. Singrauli, Essar Power MP Ltd. 77
Gorgi TPP , Dist. Singrauli, DB Power (MP) Ltd. 78
BLA Power Pvt.Ltd (Niwari) TPP , Dist. Narsinghpur, BLA Power Ltd. 79
11. Maharashtra 80-83
Amravati TPP , Ph-II, (Distt: Amravati) 80
M/s RattanIndia Power Ltd.(Formermerly known as Indiabulls Power Ltd.)
Nasik TPP, Ph-I, Distt: Nasik 81
M/s RattanIndia Nasik Power Ltd.(Formerly known as Indiabulls Realtech Ltd.)
Nasik TPP, Ph-II, Distt: Nasik 82
M/s RattanIndia Nasik Power Ltd.(Formerly known as Indiabulls Realtech Ltd.)
Lanco Vidarbha TPP, Distt: Wardha, 83
M/s Lanco vidarbha Thermal Power Ltd.
Bijora Ghanmukh TPP, Distt: Yavatmal 84
M/s Jinbhuvish Power Generations Pvt. Ltd. (JPGPL)
Shirpur Power Private Ltd. Distt. Dhule, Maharashtra 85
Bhusawal TPP, Distt. Jalgaon, Maharashtra 86
Southern Region
12. Andhra Pradesh 88-92
Rayalaseema TPP St-IV, (M/s. APGENCO), Distt.Cuddapah 88
Sri Damodaram Sanjeevaiah TPP St-II (Krishnapatnam), (APPDCL) Distt.Nellore 89
Dr. Narla Tata Rao TPP, Distt. Vijayawada, AP (APGENCO) 90
Thamminapatnam TPP Ph-II, Thamminapatnam, Distt.: SPSR Nellore, AP 91
(M/s Meenakshi Energy Pvt.Ltd.),
Bhavanapadu TPP Ph-I, Distt.: Srikakulam, (M/s East Coast Energy Pvt. Ltd.) 92

TPM_Broad Status Report (January-February’2020) 3


Sl. No. Contents Page No
13. Telangana 93-95
Kothagudem TPS –VII (TSGENCO) Distt. Kammam 93
Bhadradri TPP (TSGENCO), Distt. Khammam 94
Yadadri TPP (TSGENCO), Distt. Nalgonda, Telangana 95
14. Karnataka 96-96
Yelahanka Combined Cycle Power plant. 96
15. Tamil Nadu 97-103
Ennore SEZ SCTPP, Distt. Thiruvallur, TANGEDCO 97
Uppur SCTPP, Distt. Ramnad, T.N, TANGEDCO 98
North Chennai TPP St-III, Distt. Thiruvallur, TANGEDCO 99
Ennore SCTPP, Distt. Thiruvallur TANGEDCO 100
TuiticorinTPP St-IV, Distt. Tuticorin, Tamil Nadu, 101
M/s SEPC Power Pvt. Ltd.
Tuticorin TPP, Tamil Nadu (Ind. Barath Power Limited) 102
Udangudi STPP, TANGEDCO (Distt. Thoothukudi) Tamil Nadu 103
Eastern Region
16. Bihar 105-106
Barauni Extn TPS, P.O.: Barauni, Dist: Begusarai Bihar -742237 (BSPGCL) 105
Siriya TPP, (JAS INFRA), Village.: Siriya, Dist.: Banka Bihar 106
17. Jhakhand 107-108
Matri Shri UshaTPP, Distt. Latehar, Jharkhand 107
M/s Corporate Power Ltd.
Tori TPP Essar Power (Jharkhand) Ltd. Distt. Angarha Latehar Jharkhand 108
18. Odisha 109-113
Ib Valley TPP, Village: Banaharpalli, Dist: Jharsaguda 109
(OPGC)
Ind Barath TPP, Distt-Jharsuguda 110
M/s Ind-Barath Energy (Utkal) Ltd.
Lanco Babandh TPP, Distt-Dhenkanal 111
(M/s Lanco Babandh Power Ltd.)
Malibrahmani TPP, Distt-Angul, M/s Monnet Ispat 112
KVK Nilachal TPP, Ph-I Kandarei, Distt-Dhenkanal, Odisha 113
M/s KVK Nilanchal Ltd
19. West Bengal 114-114
Hiranmaye Energy Limited, PO-Shibramnagar, Haldia, Dist.- Purba Medinipur- 721635, West 114
Bengal, India Power Corporation (Haldia) Ltd.,
North-Eastern Region
20. Assam 116-117
Lakwa Replacement Power Project, Distt: Shivsagar, Assam APGCL 116
Namrup Replacement Power Project, Distt: Dibrugarh, Assam APGCL 117
21. List of Abbreviations 118

TPM_Broad Status Report (January-February’2020) 4


th
1.0 12 Plan Capacity Addition:

1.A. Capacity Addition Target (MW) during 12th Plan

SECTOR THERMAL HYDRO NUCLEAR TOTAL


CENTRAL 14877.6 6004 5300 26181.6
STATE 13922 1608 - 15530
PRIVATE 43540 3285 - 46825
TOTAL 72339.6 10897 5300 88536.6

1.B Year Wise Sector Wise Thermal Capacity Addition Achievement against Revised Target during
12th Plan:

Thermal capacity addition during 12th Plan (MW) Revised


Year % Achievement
Central State Private Total Target
2012-13 5023.3 3911 11187.5 20121.8 15154.3 132.78%
2013-14 1660 3322 11785 16767 15234.3 110.06%
2014-15 2659.2 4886.1 13285 20830.3 14988.3 138.98%
2015-16 3295.6 6460 12705 22460.6 17346.1 129.49%
2016-17 3230.5 3622.25 4698 11550.75 13440.5 85.94%
Total 13463.6 21151.35 53660.5 91730.45 76163.5 126.81%

1.C Thermal Capacity Addition during FY 2017-18 and FY 2018-19

Thermal capacity addition after 12th Plan (from 01.04.2017 onwards)


2017 - 18 (MW) 2018-19 (MW) 2019-20(MW)
As on 31.01.2020
Sector
Achievement Achievement Achievement
Target (MW) Target (MW) Target (MW)
(MW) (MW) (MW)
Central 4880 3170 2760 1300 6040 3940
State 3546.15 1260 4506.15 2780 4256.15 2780
Private 2940 2280 Nil Nil Nil Nil
Total 11366.15 6710 7266.15 4080 10296.15 6720
Additional Thermal Capacity included in Capacity Addition
Central - 0 - 660 - -
State - 500 - 69.755 - -
Private - 1500 - 972 - 45
Total - 2000 - 1701.755 - 45
Grand
11366.15 8710 7266.15 5781.755 10296.15 6765
Total

1. D. Sector-wise break up of under construction Thermal Power Projects are as follows:


(As on 01.04.2020)
SECTOR CAPACITY (MW)
CENTRAL 19120
STATE 18066.15
PRIVATE 23730
TOTAL 60916.15

TPM_Broad Status Report (January-February’2020) 5


1.E. PROVISIONAL RFD FOR THE YEAR 2019-20

S. Project Name LOA Unit Fuel Targeted Org. Ant. Trial Achiev Actual/ Ant.
No. Date No Cap. Comm. Run/ COD ed Date of Cap.
(MW) Sched. at the Cap. Addition
Beginning (MW)
of the year
CENTRAL SECTOR

1 Nabi Nagar STPP Jan-13 U-1 Coal 660 Jan-17 May-19 660 12.07.19(A)

2 Lara STPP Dec-12 U-2 Coal 800 May-17 Dec-19 Mar-20

3 Gadarwara STPP Mar-13 U-2 Coal 800 Sep-17 Dec-19 Mar-20

4 Khargone STPP St-I Mar-15 U-1 Coal 660 Mar-19 Aug-19 660 29.09.19(A)

Mar-15 U-2 Coal 660 Sep-19 Feb-20 660 24.03.20(A)

5 Darlipalli STPP St-I Feb-14 U-1 Coal 800 Feb-18 Aug-19 800 30.12.19(A)

6 Tanda TPP St- II Sep-14 U-5 Coal 660 Sep-17 Sep-19 660 28.09.19(A)

7 Neyveli New TPP Jun-11 U-1 Lignite 500 Mar-18 Apr-19 500 20.12.19(A)

Jun-11 U-2 Lignite 500 Sep-18 Oct-19 Mar-20

Total Central Sector 6040 3940

STATE SECTOR

1 Dr.Narla Tata Rao Dec-15 U-8 Coal 800 Jun-19 Feb-20 Oct-20
TPS Stage-V
2 Namrup CCGT Feb-09 ST Gas 36.15 Jan-12 Nov-19 Mar-20

3 Wanakbori TPS Extn. Oct-14 U-8 Coal 800 Oct-18 Nov-19 800 12.10.19(A)

4 Yelahanka CCPP Nov-15 GT+S Gas 370 Mar-18 Nov-19 2021-20


T
5 Ib valley TPP Mar-14 U-3 Coal 660 Aug-17 Apr-19 660 01.07.19(A)

Mar-14 U-4 Coal 660 Jul-19 660 17.08.19(A)

6 Suratgarh SCTPP Mar-13 U-7 Coal 660 Jul-16 Nov-19 660 15.03.20 (A)

7 Bhadradri TPP Mar-15 U-1 Coal 270 Mar-17 Jan-20 Feb-20

Total Sector Sector 4256.15 2780

TOTAL THERMAL CAPACITY ADDITION 10296.15 6720

ADDITIONAL PROJECTS

PRIVATE SECTOR

1 BLA Power Pvt. Apr-11 U-2 Coal 45 06.06.2019(A)


Ltd(Niwari) TPP
Total Private Sector 45

Total Additional Capacity 45

TOTAL GRAND THERMAL CAPACITY ADDITION 6765

TPM_Broad Status Report (January-February’2020) 6


2.0 Thermal Capacity Addition Target/ Achievement for the Year 2012-13

State Project Name Impl Agency Unit No LOA Date BTG Targeted Actual Cap. Comm. Date COD
Supplier Cap. comm. Envisaged at the Ant. /Act(A)
(MW) (MW) beginning of year
CENTRAL SECTOR
Chhattisgarh Sipat -I NTPC U-3 Apr-04 Others 660 660 06/12 02.06.12(A) 01.08.2012
Haryana Indira Gandhi TPP APCPL U-3 Jul-07 BHEL 500 500 12/12 07.11.12(A) 26.04.2013
Jharkhand Kodarma TPP DVC U-2 Jun-07 BHEL 500 500 12/12 15.02.13(A) 14.06.2014
Maharashtra Mouda TPP NTPC U-1 Nov-08 BHEL 500 500 07/12 19.04.12(A) 13.03.2013
Maharashtra Mouda TPP NTPC U-2 Nov-08 BHEL 500 29.03.13(A) March 14
MP Vindhyachal TPP-IV NTPC U-11 Jan-09 BHEL 500 500 07/12 14.06.12(A) 01.03.2013
MP Vindhyachal TPP-IV NTPC U-12 Jan-09 BHEL 500 22.03.13(A) March 14
TN Vallur TPP Ph-I NTECL U-2 Aug-07 BHEL 500 500 02/13 28.02.13(A) 25.08.2013
Tripura Tripura Gas ONGC Module-1 Jun-08 BHEL 363.3 363.3 11/12 03.01.13 (A) 04.01.2014
UP Rihand TPP-III NTPC U-5 Feb-09 BHEL 500 500 06/12 25.05.12(A) 19.11.2012
Total Central Sector 4023.3 5023.3
STATE SECTOR
Chhattisgarh Korba West Extn.St.III TPP CSEB U-5 BEHL 500 22.03.13(A) 05.09.2013
Chhattisgarh Marwa TPP CSEB U-1 Apr-08 BHEL 500 02/13 Slipped
Delhi Pragati CCGT - III PPCL GT-3 May-08 BHEL 250 250 08/12 27.06.12(A) 28.10.2013
Pipavav CCPP GSECL Block-2 Dec-07 BHEL 351 351 01/13 27.03.13(A) 27.03.2013
Gujarat
Ukai TPP Extn GSECL U-6 Sep-07 BHEL 490 490 12/12 05.03.13(A) 08.06.2013
Ramgarh CCGT RRVUNL GT Aug-09 BHEL 110 110 01/13 20.03.13(A) 06.12.2013
Rajasthan
Ramgarh CCGT RRVUNL ST-1 BHEL 50 02/13 Slipped
MP Satpura TPP Extn. MPPGCL U-10 Mar-08 BHEL 250 250 02/13 22.03.13(A) 18.08.2013
Mettur TPP Ext TNEB U-1 Aug-08 Chinese 600 600 06/12 11.10.12(A) 12.10.2013
TN
North Chennai Extn. TNEB U-2 Aug-08 BHEL 600 600 03/13 09.03.13(A) 08.05.2014
Harduaganj Ext UPRVUNL U-9 Jun-06 BHEL 250 250 05/12 25.05.12(A) 10.10.2013
UP Parichha Extn UPRVUNL U-5 Jun-06 BHEL 250 250 06/12 24.05.12(A) 17.07.2012
Parichha Extn UPRVUNL U-6 250 250 09/12 11.03.13(A) 18.04.2013
Total -State Sector 3951 3911
PRIVATE SECTOR
Simhapuri TPP Ph-1 Madhucon Projects Ltd. U-2 Jan-09 Chinese 150 150 09/12 02.07.12(A) 15.07.2012
AP Thamminapatnam TPP-I Meenakshi Energy Pvt. Ltd. U-1 Chinese 150 150 08/12 09.09.12(A) 07.10.2012
Aug-09
Thamminapatnam TPP-I Meenakshi Energy Pvt. Ltd. U-2 150 11/12 Slipped
Kasaipalli TPP M/s ACB (India) U-2 Nov-08 Chinese 135 135 06/12 21.06.12(A) 21.06.2012
Salora TPP M/s Vandna Vidyut U-1 Nov-08 Chinese 135 12/12 Slipped
Chhattisgarh
Swastik Korba TPS ACB U-1 Others 25 06/12 Slipped
Ratija TPP SCPL U-1 Chinese 50 04.02.13(A) 27.02.2013
Mundra Ultra Mega TPP Tata Power Co. U-2 May-07 Others 800 800 12/12 25.07.12(A) 28.07.2012
Mundra Ultra Mega TPP Tata Power Co. U-3 May-07 Others 800 16.10.12(A) 27.10.2012
Mundra Ultra Mega TPP Tata Power Co. U-4 May-07 Others 800 16.01.13(A) 21.01.2013
Gujarat
Mundra Ultra Mega TPP Tata Power Co. U-5 Jun-07 Others 800 18.03.13(A) 22.03.2013
UNO-SUGEN CCPP Torrent Power Ltd. Mod-1 Others 382.5 20.01.13(A) 04.04.2013
Salaya TPP ESSAR U-2 Nov-07 Chinese 600 600 08/12 13.06.12(A) 15.06.2012
Haryana Jhajjar TPP (Mahatma Gandhi TPP) CLP Power India Pvt. Ltd. U-2 Jan-09 Chinese 660 660 04/12 11.04.12(A) 19.07.2012
Adhunik Power TPP Adhunik Power Co. Ltd. U-1 May-09 BHEL 270 270 09/12 19.11.12(A) 21.01.2013
Jharkhand Adhunik Power TPP Adhunik Power Co. Ltd. U-2 May-09 BHEL 270 29.03.13(A) 19.05.2013
Corporate Power Ltd Ph-I (Maitrishi Usha) M/s Corporate Power Ltd. U-1 Dec-09 BHEL 270 12/12 Slipped

TPM_Broad Status Report (January-February’2020) 7


State Project Name Impl Agency Unit No LOA Date BTG Targeted Actual Cap. Comm. Date COD
Supplier Cap. comm. Envisaged at the Ant. /Act(A)
(MW) (MW) beginning of year
Bela TTP-I IEPL U-1 Dec-08 BHEL 270 270 09/12 20.03.13(A) 18.07.2013
Butibori TPP Vidarbha Industries Power Ltd U-2 Dec-09 Chinese 300 300 08/12 17.08.12 (A) 04.04.2013
EMCO Warora TPP EMCO Energy Ltd. (GMR) U-1 Sep-09 Chinese 300 300 11/12 07.02.13(A) 19.032013
Tirora TPP Ph-I Adani Power Ltd U-1 Chinese 660 660 08/12 11.09.12(A) 23.09.2012
Maharashtra Tirora TPP Ph-I Adani Power Ltd U-2 Feb-08 660 660 11/12 25.03.13(A) 30.03.2013
Tirora TPP Ph-II Adani Power Ltd U-1 660 02/13 Slipped
GEPL TPP GEPL Pvt. Ltd. U-2 Mar-09 Chinese 60 28.04.12(A)
GEPL TPP GEPL Pvt. Ltd. U-1 Chinese 60 08.09.12(A) 09.05.2012
Amaravathi TPP Ph-I Indiabulls U-1 BHEL 270 25.03.13(A) 03.06.2013
Bina TPP Bina Power Ltd. U-1 Sep-08 BHEL 250 250 09/12 12.08.12(A) 30.08.2012
MP Bina TPP Bina Power Ltd. U-2 Sep-08 BHEL 250 31.03.13(A) 07.04.2013
Mahan Essar Power Ltd. U-1 Chinese 600 24.02.13(A) 29.04.2013
Sterlite TPP Sterlite Energy Ltd. U-4 Sep-08 Chinese 600 600 06/12 25.04.12(A) 26.04.2012
Orissa
Kamalanga TPP U-1 Chinese 350 29.03.13(A) 25.03.2014
Jallipa- Kapurdi TPP U-5 Mar-07 Chinese 135 135 03/13 05.02.13(A) 05.02.2013
U-6 Apr-07 Chinese 135 03.03.13(A) 03.03.2013
Rajasthan Raj west power Ltd (JSW)
U-7 Jun-07 Chinese 135 16.03.13(A) 16.03.2013
U-8 May-07 Chinese 135 28.02.13(A) 28.02.2013
TN Tuticorin TPP Ind Barath U-1 Chinese 150 10.03.13(A) 07.02.2013
Total -Private Sector 7180 11187.5
Total for the year 2012-13 15154.3 20121.8

TPM_Broad Status Report (January-February’2020) 8


2.1 Thermal Capacity Addition Target/ Achievement for the Year 2013-14

State Project Name Impl Agency Unit No LOA Date BTG Supplier Targeted Actual Cap. Actual At the COD
Cap. (MW) comm. Comm. beginning of
(MW) Date the year
CENTRAL SECTOR
03/08&
Bihar Barh STPP St-II NTPC 4 BHEL 660 660 30/11/13 12/13 15.11.2014
10/08
TN Vallur TPP Ph-I NTPC/ NTECL/ TNEB-JV 3 07/09 BHEL 500 500 28.02.2014 03/14 26.02.2015
TN Tuticorin TPP NLC/ TNEB-JV 1 01/09 BHEL 500 Slipped 03/14
Tripura Tripura CCGT ONGC JV Blk-2 06/08 BHEL 363.3 Slipped 09/13
UP Rihand STPP St-III NTPC 6 02/09 BHEL 500 500 7/10/2013 12/13 March 2014
WB Raghunathpur TPP DVC 1 12/07 CHINA 600 Slipped 03/14
Total Central Sector 3123.3 1660
STATE SECTOR
Chhattisgarh Marwa TPP CSEB 1 04/08 BHEL 500 500 30.03.2014 09/13
Delhi Pragati St-III CCGT PPCL GT-4 05/08 BHEL 250 250 7/5/2013 06/13 27.02.2014
Delhi Pragati St-III CCGT PPCL ST-2 05/08 BHEL 250 250 26.02.2014 09/13 27.03.2014
Gujarat Pipavav JV CCGT GSECL Block-1 12/07 BHEL 351 351 05/02/2013 09/13
MP Shree Singaji TPP(Malwa TPP) MPPGCL 1 12/08 BHEL 600 600 18/11/2013 06/13 February 2014
MP Satpura TPS Extn. MPPGCL 11 03/08 BHEL 250 250 25/12/2013 10/13 16.03.2014
Maha-rashtra Chandrapur TPS Extn. MAHAGENCO 8 07/08 BHEL 500 Slipped 12/13
Rajasthan Kalisindh TPP RRVUNL 1 07/08 SEPCO, CHINA 600 Slipped 12/13
Rajasthan Chhabra TPS Extn. RRVUNL 3 08/08 BHEL 250 250 14/09/13 06/13 19.12.2013
Rajasthan Chhabra TPS Extn. RRVUNL 4 08/08 BHEL 250 Slipped 01/14
Rajasthan Ramgarh CCPP RRVUNL ST 08/09 BHEL 50 Slipped 12/13
TN North Chennai TPS Extn. TNEB 1 08/08 BHEL 600 600 13/09/13 09/13 20.03.2014
Total -State Sector 4451 3051
PRIVATE SECTOR
AP Vizag TPP Hinduja 1 03/10 BHEL 520 03/14
AP Thammina-patnam TPP Meena-kshi Energy 2 08/09 Chinese 150 150 17/04/13 09/13 30.04.2013
Chhattis-garh Tamnar TPP Jindal Power 1 12/08 BHEL 600 600 10.03.2014 03/14 14.03.2014
BOILER: CETHAR
VESSELS LTD
Chhattis-garh Vandana Vidyut TPP Vandana Vidyut TPP 1 05/08 135 Slipped 06/13
TG: CNAIC,
CHINA
Chhattis-garh DB Power TPP DB Power Ltd 1 05/10 BHEL 600 600 23.02.2014 12/13 03.11.2014
BOILER: IJT;
Chhattis-garh Swastik Korba TPP ACB 1 02/10 TURBINE: 25 Slipped 12/13
SIEMENS
Chhattis-garh Akaltara TPP KSK Mahanadi 1 04/09 SEC,CHIINA 600 600 13/08/13 09/13 14.08.2013
MP Sasan UMPP Reliance Power 3 06/08 SEC, CHINA 660 660 30/5/13
05/13
MP Sasan UMPP Reliance Power 2 06/08 SEC, CHINA 660 660 18/12/13 09/13
Maha-rashtra Nasik TPP Ph-I India Bulls 1 11/09 BHEL 270 270 25.02.2014 09/13 29.03.2014
Maha-rashtra Dhariwal Infrastructure (P) Ltd.TPP Dhariwal Infra-structure (P) Ltd. 1 04/10 SEC, CHINA 300 300 3/11/2013 06/13 13.02.2014
Maha-rashtra Dhariwal Infrastructure (P) Ltd.TPP Dhariwal Infra-structure (P) Ltd. 2 04/10 SEC, CHINA 300 Slipped 12/13
Maha-rashtra EMCO Warora TPP GMR EMCO Energy Ltd. 2 09/09 SEC, CHINA 300 300 27/08/2013 06/13 01.09.2013
Maharashtra Tirora TPP Ph-II Adani Power 1 02/08 SCMEC, CHINA 660 660 10/6/2013 06/13 14.06.2013

TPM_Broad Status Report (January-February’2020) 9


State Project Name Impl Agency Unit No LOA Date BTG Supplier Targeted Actual Cap. Actual At the COD
Cap. (MW) comm. Comm. beginning of
(MW) Date the year
Orissa Derang TPP Jindal India Thermal Power 1 07/09 BHEL 600 Slipped 12/13
Orissa Kamalang TPP GMR Energy 2 08/08 SEPCO III, CHNA 350 350 28/09/13 09/13 12.11.2013
Punjab Goindwal Sahib TPP GVK Industries 1 02/09 BHEL 270 Slipped 06/13
Punjab Talwandi Sahib TPP Sterlite 1 07/09 SEPCO I, CHINA 660 Slipped 01/14
Total -Private Sector 7660 5150
Total for during the year 2013-14 15234.3 9861
Additional Capacity Commissioned
Tripura State Electricity
Tripura Rokhia GT 9 BHEL 21 31/08/2013
Corporation Ltd.)
Rajasthan Kawai TPP Adani Power Rajasthan Ltd. 1 04/10 Chinese 660 28/05/2013 31.05.2013
Rajasthan Kawai TPP Adani Power Rajasthan Ltd. 2 04/10 Chinese 660 24/12/2013 31.05.2014
Boiler –ISGEC
MP BLA Power (Niwari) TPP BLA Power Pvt.Ltd 1 45 24/03/2012 03.04.2012
Turbine- SIEMENS
TN Tuticorin Indbarath Indbarath Ltd 2 Chinese 150 30/12/2013 15.03.2014
Punjab Rajpura TPP Nabha Power 1 Jul-10 L&T 700 24/01/2014 01.02.2014
Gujarat Dgen CCPP Torrent Power Block-I Jul-10 Siemens Germany 400 12/01/2014
Maharashtra Amaravati TPP Ph-I India bulls Power Ltd 2 Nov-09 BHEL 270 17.02.2014 28.03.2014
AP Simhapuri TPS Ph-II Simhapuri Energy Pvt Ltd 3 Mar-10 Chinese 150 21.02.2014 26.02.2014
Gujarat Dgen CCPP Torrent Power Block-3 Jul-10 Siemens Germany 400 09/03/2014
Orissa Kamalang TPP GMR Energy 3 08/08 SEPCO III, CHNA 350 21/03/14 25.03.2014
Maha-rashtra Tirora TPP Ph-II Adani Power 2 02/08 SCMEC, CHINA 660 23/3/2014 31.03.2014
MP Sasan UMPP Reliance Power 4 06/08 SEC, CHINA 660 25/03/14 12.04.2014
Chhattis-garh Tamnar TPP Jindal Power 2 12/08 BHEL 600 30.03.2014 31.03.2014
Chhattis-garh Chakabura TPP ACBIL 1 Chinese 30 28.03.2014 30.03.2014
West Bengal Durgapur TPS Extn DPL 8 BHEL 250 31.03.2014
Chhattis-garh Avantha Bhandar TPP KWPCL 1 BHEL 600 31.03.2014 01.04.2014
Maharashtra Butibori TPP Vidarbha Industries Power Ltd 1 Chinese 300 19.03.2013 28.03.2014
Total Additional Thermal Capacity in 2013-14 6906
TOTAL THERMAL CAPACITY ADDITION in 2013-14 16767

TPM_Broad Status Report (January-February’2020) 10


2.2 Thermal Capacity Addition Target/ Achievement for the Year 2014-15
State Project Name Impl Agency Equip. Supplier Fuel Unit No LOA date Targeted Actual Cap Actual At the COD
Cap. (MW) .comm. Comm. Date beginning of
(MW) the year
CENTRAL SECTOR
Barh STPP-II NTPC BHEL U-5 SG:03/2008 660 660 04.03.2015 Feb-15 18.02.2016
Coal
Bihar TG:10/2008
Muzaffarpur TPS Exp KBUNL (JV of NTPC & BSEB) BHEL Coal U-3 03/2010 195 195 31.03.2015 Mar-15 18.03.2017
Tuticorin TPP NTPL( JV of NLC & BHEL Coal U-1 500 500 10.03.2015 Oct-14 18.06.2015
TN 28.01.09
TANGEDCO) BHEL Coal U-2 500 Feb-15
Tripura Palatana CCPP OTPC (JV of ILFS, ONGC & BHEL BLK-2 23.06.08 363.3 363.3 16.11.2014 Aug-14
Gas
Tripura Govt)
WB Raghunathpur TPP, Ph-I DVC Chinese Coal U-1 14.12.2007 600 600 24.08.2014 Aug-14 31.03.2016
Total Central Sector 2818.3 2318.3
STATE SECTOR
Damodaram Blr- BHEL U-1 SG:08/2008 800 800 28.08.2014 Jun-14 05.02.2015
AP APPDCL Coal
Sanjeevaiah TPP TG- L&T U-2 TG:09/2008 800 800 17.03.2015 Jan-15 24.08.2015
Chhattisgarh Marwa TPP CSPGCL BHEL Coal U-2 11.04.08 500 Slipped Dec-14
Chandrapur TPS MSPGCL BHEL Coal U-8 25.07.08 500 500 29.03.2015 Oct-14 04.06.2016
Koradi TPS Expn. MSPGCL L&T Coal U-8 23.09.09 660 660 30.03.2015 Oct-14 16.12.2015
Maharashtra
Koradi TPS Expn. MSPGCL L&T Coal U-9 660 Slipped Jan-15
Parli TPS Expn. MSPGCL BHEL Coal U-8 21.01.09 250 Slipped Nov-14
MP Malwa TPP MPPGCL BHEL U-2 12.12.08 600 600 15.10.2014 Sep-14 01.01.2015
Coal
(Shree Singaji)
Rajasthan Kalisindh TPP Chinese Coal U-1 600 600 02.05.2014 Jun-14 01.06.2014
09.07.08
Kalisindh TPP Chinese Coal U-2 600 Slipped Jan-15
RRVUNL
Ramgarh CCPP BHEL Gas ST 18.08.09 50 50 01.05.2014 Jul-14
Chhabra TPP BHEL Coal U-4 20.08.08 250 250 30.06.2014 Jun-14 30.12.2014
UP Anpara-D TPS UPRVUNL BHEL Coal U- 6 27.10.07 500 Slipped Mar-15
Total State Sector 6770 4260
PRIVATE SECTOR
Painampuram TPP Thermal Power Tech Corp.Ltd Chinese Coal U-1 09/2010 660 660 07.02.2015 Dec-14 02.03.2015
AP Vizag TPP Hinduja National Power BHEL U-1 03/2010 520 Slipped Oct-14
Coal
Corp.Ltd
Swastic Korba TPP ACB India Ltd. Blr:ISGEC India U-1 29.03.10 25 25 31.03.2015 Nov-14
Coal
TG:Siemens
Chhattisgarh
Salora TPP Vandana Vidyut Ltd Chinese Coal U-1 11/2008 135 135 10.04.2014 Sep-14 01.05.2014
Bandakhar TPP Maruti Clean coal Chinese Coal U-1 300 Slipped Jan-15
Maharashtra Amravati TPP Ph-I India Bulls Power Ltd BHEL Coal U-3 30.11.09 270 270 29.01.2015 Oct-14 03.02.2015
Maharashtra Nasik TPP Ph-I India Bulls Realtech BHEL Coal U-2 24.11.09 270 Slipped Jul-14
Maharashtra Dhariwal TPP Dhariwal Infrastucture Ltd Chinese Coal U-2 28.04.10 300 300 28.05.2014 Jun-14 02.08.2014
Orissa Derang TPP JIPL BHEL Coal U-1 26.07.09 600 600 10.05.2014 Jun-14 06.06.2014
Punjab Rajpura TPP (Nabha) Nabha Power Ltd L&T Coal U-2 16.07.10 700 700 06.07.2014 Jul-14 01.08.2014
Punjab Talwandi Sabo TPP M/s Sterlite Chinese Coal U-1 18.07.09 660 660 17.06.2014 May-14 01.08.2014
Punjab Talwandi Sabo TPP M/s Sterlite Chinese Coal U-2 18.07.09 660 Slipped Sep-14
WB Haldia TPP M/s Haldia Energy Ltd. Chinese Coal U-1 14.09.11 300 300 14.01.2015 Dec-14 28.01.2015
Total Private Sector 5400 3650
Total during 2014-15 14988.3 10228.3

TPM_Broad Status Report (January-February’2020) 11


Additional Capacity Commissioned during 2014-15
State Project Name Impl Agency Equip. Supplier Fuel Unit No LOA date Actual Cap Actual At the COD
.comm. Comm. Date beginning of
(MW) the year
Central Sector
TN Neyveli TPS Ph-II Exp NLC BHEL Coal U-2 250 24.01.2015 22.04.2015
Tripura Monarchak gas power project NEEPCO BHEL Gas 65.4 30.03.2015
GT
Tripura Agartala CCPP NEEPCO Thermax Gas ST-2 25.5 22.03.2015
Total Central Sector (Addition in 2014-15) 340.9
State Sector
Gujarat Dhuvaran CCPP GSECL Siemens
Gas Uniit 1 376.1 21.05.2014
Germany
Total Sate Sector (Additional in 2014-15) 376.1
Private Sector
Gujarat D gen CCPP Torrent Power Siemens
Gas Block-II 02.07.2010 400 23.04.2014
Germany
MP Sasan UMPP SPL Chinese 4th Unit 27.05.2014
Coal 660 21.05.2014
(Unit-1)
MP Sasan UMPP SPL Chinese Coal Unit-5 660 24.08.2014 26.12.2014
Chhattisgarh Akaltara TPP KSK Chinese Coal Unit-2 600 22.08.2014 26.08.2014
MP Nigrie TPP JPVL L&T Coal Unit-1 660 29.08.2014 03.09.2014
Maharashtra Tirora TPP Ph-II Adani Power Maharashtra Chinese 11.10.2014
Coal Unit-3 05.11.2009 660 25.09.2014
Pvt Ltd
TN Mutiara TPP Coastal Energen Chinese Coal Unit-1 25.02.2009 600 02.12.2014 23.12.2014
Chhattisgarh Tamnar TPP (Raigarh) Jindal Power BHEL Coal Unit-3 600 07.01.2015 15.01.2015
Orissa Derang TPP JIPL BHEL Coal U-2 600 24.01.2015 12.02.2015
WB Haldia TPP M/s Haldia Energy Ltd. Chinese Coal U-2 300 16.02.2015 21.02.2015
MP Nigrie TPP JP Ventures Ltd Non-BHEL Coal U-2 660 17.02.2015 21.02.2015
Chhattisgarh Raikhera TPP GMR Chinese Coal U-1 685 27.02.2015 01.06.2015
Maharashtra Amravati TPP Ph-I India Bulls Power Ltd BHEL Coal U-4 30.11.09 270 04.03.2015 08.03.2015
AP Simhapuri Simhapuri Energy Pvt Ltd Chinese Coal U-4 150 07.03.2015 31.03.2015
Maharashtra Amravati TPP Ph-I India Bulls Power Ltd BHEL Coal U-5 30.11.09 270 12.03.2015 13.03.2015
MP Sasan UMPP SPL Chinese Coal Unit-6 660 19.03.2015 27.03.2015
Chhattisgarh DB Power TPP DB Power Ltd BHEL Coal Unit-2 600 24.03.2015
Chhattisgarh Tamnar TPP (Raigarh) Jindal Power BHEL Coal Unit-4 600 26.03.2015
Gujarat Sikka TPP Extn GSECL BHEL Coal U-3 250 28.03.2015 14.09.2015

Total Private Sector (Additional in 2014-15) 9885


Additional Capacity Commissioned during 2014-15 10602
TOTAL THERMAL CAPACITY ADDITION in 2014-15 20830.3

TPM_Broad Status Report (January-February’2020) 12


2.3 Thermal Capacity Addition Target/ Achievement for the Year 2015-16
State Project Name Impl Agency Unit No BTG Supplier Cap. (MW) Anti. Comm. ( Now Anti. Cap. Add Actual Date COD
beginning of Comm. (MW) of Comm.
the year)
CENTRAL SECTOR
Assam Bongaigaon TPP NTPC U-1 BHEL 250 06/2015 250 22.06.15(A) 01.04.2016
Bihar Muzafferpur NTPC U-4 BHEL 195 02/2016 Slipped
Bihar Nabi Nagar TPP NTPC U-1 BHEL 250 20.03.16(A) 15.01.2017
Jharkhand Bokaro TPS "Ä" Exp. DVC U-1 BHEL 500 22.03.16(A) 23.02.2017
Maharashtra Mouda STPP-II NTPC U-3 BHEL 660 28.03.16(A) 01.02.2017
MP Vindhyachal TPP-V NTPC U-13 BHEL 500 12/2015 500 06.08.15(A) 30.10.2015
Tripura Agratala STG NEEPCO ST-2 Thermax 25.5 05/2015 Slipped
Tripura Monarchak CCPP NEEPCO ST BHEL 35.6 08/2015 35.6 14.01.16(A)
TN Tuticorin TPP NLC U-2 BHEL 500 07/2015 500 09.07.15(A) 29.08.2015
WB Raghunathpur TPP,Ph-I DVC U-2 Chinese 600 01/2016 600 18.01.16(A) 31.03.2016
Total Central Sector 2106.1 3295.6
STATE SECTOR
Chhattisgarh Marwa TPP CSPGCL U-2 BHEL 500 09/2015 Slipped
Gujarat Sikka TPS GSECL U-4 BHEL 250 12/2015 250 25.09.15(A) 28.12.2015
Karnataka Bellary TPS St-III KPCL U-3 BHEL 700 12/2015 700 01.03.16(A) 16.09.2017
Karnataka Yermarus TPP KPCL U-1 BHEL 800 01/2016 800 29.03.16(A) 07.03.2017
Maharashtra Chandrapur TPS MSPGCL U-9 BHEL 500 10/2015 500 21.03.16(A) 24.11.2016
Maharashtra Koradi TPS Expn. MSPGCL U-9 L&T 660 09/2015 660 15.03.16(A) 22.11.2016
Maharashtra Koradi TPS Expn. MSPGCL U-10 L&T 660 02/2016 Slipped
Maharashtra Parli TPS MSPGCL U-8 BHEL 250 01/2016 250 30.03.16(A) 30.11.2016
Rajasthan Kalisindh TPP RVUNL U-2 Chinese 600 05/2015 600 06.06.15(A) 25.07.2015
Telangana Singareni TPP Singareni Collieries Co Ltd U-1 BHEL 600 01/2016 600 13.03.16(A) 25.09.2016
Telangana Kakatiya TPS Extn. T GENCO U-1 BHEL 600 12/2015 600 31.12.15(A) 24.03.2016
UP Anpara-D TPS UPRVUNL U- 6 BHEL 500 06/2015 500 06.06.15(A) 08.05.2016
UP Anpara-D TPS UPRVUNL U- 7 BHEL 500 12/2015 500 06.03.16(A) 18.10.2016
WB Sagardighi TPS-Extn West Bengal U-3 BHEL 500 09/2015 500 14.12.15(A)
WB Sagardighi TPS-Extn West Bengal U-4 BHEL 500 01/2016 Slipped
Total State Sector 8120 6460
PRIVATE SECTOR
AP Painampuram TPP Thermal Power Tech Corporation Ltd U-2 Chinese 660 08/2015 660 03.09.15(A) 15.09.2015
AP Vizag TPP Hinduja National Power Corp. Ltd U-1 BHEL 520 10/2015 520 27.12.15(A) 11.01.2016
AP Lanco Kondapalli Extn. Ph-III ( PS) Lanco Kondapalli Power Co.Ltd Block-I Others 371 07.08.15(A)
AP Lanco Kondapalli Extn. Ph-III (PS) Lanco Kondapalli Power Co.Ltd Block-II Others 371 05.09.15(A)
AP Vemagiri CCPP-II (PS) GMR Rajahmundry Energy Ltd. Block-I Others 384 12.09.15(A)
AP Vemagiri CCPP-II (PS) GMR Rajahmundry Energy Ltd. Block-II Others 384 05.10.15(A)
AP Vizag TPP Hinduja National Power Corp. Ltd U-2 BHEL 520 30.03.16(A) 03.07.2016
Chhattisgarh Bandakhar TPP M/s Maruti Clean (Chhattisgarh) Ltd. U-1 Chinese 300 06/2015 300 19.06.15(A)
Chhattisgarh Uchpinda TPP RKM Powergen Pvt. Ltd U-1 Chinese 360 06/2015 360 28.10.15(A) 27.11.2015
Chhattisgarh Uchpinda TPP RKM Powergen Pvt. Ltd U-2 Chinese 360 28.01.16(A) 12.02.2016
Chhattisgarh BALCO TPP BALCO Pvt Ltd U-1 Chinese 300 06/2015 300 05.06.15(A) 11.07.2015
Chhattisgarh BALCO TPP BALCO Pvt Ltd U-2 Chinese 300 09/2015 300 24.03.16(A) 30.03.2016
Chhattisgarh Raikheda TPP GMR U-2 Doosan (Non-BHEL) 685 12/2015 685 28.03.16(A)
Chhattisgarh Salora Vandana Vidyut U-2 Chinese 135 09/2015 Slipped
Maharashtra Nasik TPP Ph-I Ratan India (Nasik) Power Ltd U-2 BHEL 270 01/2016 Slipped
MP Anuppur TPP Ph-I MB Power(MP) U-1 Chinese 600 06/2015 600 20.04.15(A) 20.05.2015
M.P Seioni TPP Ph-I Jhabua Power Ltd U-1 BHEL 600 22.03.16(A) 03.05.2016

TPM_Broad Status Report (January-February’2020) 13


State Project Name Impl Agency Unit No BTG Supplier Cap. (MW) Anti. Comm. ( Now Anti. Cap. Add Actual Date COD
beginning of Comm. (MW) of Comm.
the year)
MP Anuppur TPP Ph-I MB Power(MP) U-2 Chinese 600 30.03.16(A) 07.04.2016
Orissa Ind Bharat TPP (Orissa) Ind Barath U-1 Chinese 350 10/2015 350 25.02.16(A) 20.07.2016
Punjab Talwandi Sabo TPP Talwandi Sabo Power Ltd U-2 Chinese 660 06/2015 660 30.10.15(A) 25.11.2015
Punjab Talwandi Sabo TPP Talwandi Sabo Power Ltd U-3 Chinese 660 12/2015 660 29.03.16(A) 25.08.2016
Punjab Goindwal Sahib TPP GVK Power U-1 BHEL 270 14.02.16(A) 06.04.2016
Punjab Goindwal Sahib TPP GVK Power U-2 BHEL 270 15.03.16(A) 16.04.2016
TN ITPCL TPP IL&FS TN PC.Ltd U-1 Chinese 600 19.09.2015 29.09.2015
TN Melamaruthur (Mutiara) Coastal Energen U-2 Chinese 600 02.01.16(A) 15.01.2016
UP Lalitpur TPP Lalitpur power Generation Co. Ltd U-1 BHEL 660 660 26.03.16(A) 01.10.2015
UP Lalitpur TPP Lalitpur power Generation Co. Ltd U-2 BHEL 09/2015 660 08.01.16(A) 14.10.2016
UP Prayagraj (Bara ) TPP Prayagraj power Gen. Co. Ltd( U-1 BHEL 660 10/2015 660 25.12.15(A) 29.02.2016
J.P.Power Ventures)
Total Private Sector 7120 12705
Total Grand Thermal Capacity in 2015-16 17346.1 22460.6

TPM_Broad Status Report (January-February’2020) 14


2.4 Thermal Capacity Addition Target/ Achievement for the Year 2016-17
State Project Unit Imp Agency BTG Supplier Capacity Anticipated Actual date Capacity COD
(MW) Commng. Schedule of comm. Achieved
CENTRAL SECTOR
Bihar Nabinagar TPP U-2 NTPC BHEL 250 Slipped
Bihar Kanti TPS St-II U-4 NTPC BHEL 195 24.03.2017 195.0 01.07.2017
Chhattisgarh Lara STPP U-1 NTPC NON BHEL 800 Slipped
Karnataka Kudgi TPP U-1 NTPC NON BHEL 800 25.12.2016 800.0 31.07.2017
Maharashtra Mauda STPP-II U-4 NTPC BHEL 660 18.03.2017 660.0 18.09.2017
Tripura Agartala Gas Based Power Project ST-1 NEEPCO NON BHEL 25.5 23.08.2016 25.5
Total Central Sector 2730.5 1680.5
STATE SECTOR
Assam Namrup CCGT GT APGCL BHEL 70 11.01.2017 62.25
Assam Namrup CCGT ST APGCL BHEL 30 Slipped
Bihar Barauni TPP, U-8 BSEB BHEL 250 Slipped
Chhattisgarh Marwa TPS U-2 CSPGCL BHEL 500 15.07.2016 500.0 31.07.2016
Gujarat Bhavnagar TPP U-1 BECL BHEL 250 16.05.2016 250.0
Gujarat Bhavnagar TPP U-2 BECL BHEL 250 27.03.2017 250.0
Karnataka Yermarus TPP U-2 KPCL BHEL 800 29.03.2017 800.0 06.04.2017
Maharashtra Koradi TPP U-10 MSPGCL NON BHEL 660 28.12.2016 660.0 17.01.2017
Telangana Singreni TPP U-2 SCCL BHEL 600 25.11.2016 600.0 02.12.2016
West Bengal Sagardighi TPS-II U-4 WBPDCL BHEL 500 15.12.2016 500.0
Total State Sector 3910 3622.25
PRIVATE SECTOR
Andhra pradesh Sembcorp Gayatri Pvt.ltd.(NCC TPP) U-1 SGPL NON BHEL 660 12.11.2016 660.0 17.11.2016
Andhra pradesh Sembcorp Gayatri Pvt.ltd.(NCC TPP) U-2 SGPL NON BHEL 660 15.02.2017 660.0 21.02.2017
Chhattisgarh Nawapara TPP U-1 TRN CHINESE 300 14.08.2016 300.0 19.08.2016
Chhattisgarh Nawapara TPP U-2 TRN CHINESE 300 Slipped
Chhattisgarh Ucchpinda TPP U-3 RKM CHINESE 360 Slipped
Chhattisgarh Binjkote TPP U-1 SKS NON BHEL 300 Slipped
Chhattisgarh Athena Singhitarai TPP U-1 Athena Chhattisgarh NON BHEL 600 Slipped
Maharashtra Nashik TPP, Ph-I U-2 Rattan Power BHEL 270 15.02.2017 270.0
Maharashtra Nashik TPP, Ph-I U-3 Rattan Power BHEL 270 Slipped
Orissa Utkal TPP U-2 Ind Barath NON BHEL 350 Slipped
Orissa Lanco Babandh TPP U-1 Lanco Babandh NON BHEL 660 Slipped
Tamilnadu ITPCL TPP U-2 ILFS NON BHEL 600 18.04.2016 600.0 30.04.2016
Uttar pradesh Bara TPP U-2 Jaypee BHEL 660 06.09.2016 660.0 10.09.2016
Uttar pradesh Lalitpur TPP U-3 LPGCL BHEL 660 01.04.2016 660.0 23.12.2016
West Bengal Hiranmaye Energy TPP U-1 Hiranmaye Energy Limited BHEL 150 Slipped
Total Private Sector 6800 3810.0
Total Thermal 13440.5 9112.75
ADDITIONAL PROJECTS COMMISSIONED IN RFD 2016-17
CENTRAL SECTOR
Assam Bongaigaon TPP U-2 NTPC BHEL 22.03.2017 250.0 01.11.2017
Karnataka Kudgi TPP U-2 NTPC NON BHEL 23.03.2017 800.0 31.12.2017
Uttar Pradesh Unchahar TPS ST-IV U-6 NTPC BHEL 31.03.2017 500.0
PRIVATE SECTOR
Chhattisgarh Ratija TPP -II U-2 Spectrum Coal&Power Ltd Non-BHEL 10.11.2016 50.0
Uttrakhand GAMA CCPP Module-1 (GT1&2+ST) M/s GAMA Infraprop Ltd. Others 25.04.2016 225.0
Uttrakhand Kashipur CCPP Blk-I Srawanthi Energy Pvt.Ltd Others 20.11.2016 225.0
Maharashtra Mangaon CCPP Block-I M/s PGPL Others 14.07.2016 388.0
Total Additional Projects Commissioned in 2016-17 2438.0
Total Grand Thermal Capacity in 2016-17 13440.5 11550.75

TPM_Broad Status Report (January-February’2020) 15


2.5 Thermal Capacity Addition Target/ Achievement for the Year 2017-18
State Project Name Impl Agency Equipment Unit No. Targeted Anti. Comm Anti. Actual Date Capacity COD
Supplier Cap. Date at Comm of Comm Achieved
(MW) beginning Date (At (MW)
of year present)

CENTRAL SECTOR
Assam Bongaigaon TPP NTPC BHEL 3 250 Dec-17 Slipped
Bihar Nabi Nagar TPP JV of NTPC &Rly BHEL 2 250 Apr-17 - 03.04.2017 250.00 10.09.2017
Bihar New Nabi Nagar TPP JV of NTPC & BSPGCL NON BHEL 1 660 Aug-17 Slipped
Chhattisgarh Lara TPP NTPC NON BHEL 1 800 Oct-17 - 23.03.2018 800.00
Karnataka Kudgi STPP Ph-I NTPC NON BHEL 3 800 Aug-17 - 12.03.2018 800.00
MP Gadarwara STPP,St-I NTPC BHEL 1 800 Jan-18 Slipped
Maharashtra Solapur STPP NTPC NON BHEL 1 660 Apr-17 - 07.04.2017 660.00 25.09.2017
UP Meja STPP JV of NTPC & UPRVUNL NON BHEL 1 660 Oct-17 - 31.03.2018 660.00
TOTAL CENTRAL SECTOR 4880 3170.00

STATE SECTOR
AP Rayal seema TPP APGENCO BHEL 6 600 Aug-17 - 12.03.2018 600.00 29.03.2018
Assam Namrup APGCL BHEL ST 36.15 Feb-18 Slipped
MP Shree Singaji TPP, St-II MPPGCL NON BHEL 3 660 Dec-17 Slipped
Rajasthan Suratgarh TPS RRVUNL BHEL 7 660 Nov-17 Slipped
Rajasthan Chhabra SCTPP RRVUNL L&T & MHI 5 660 Apr-17 - 04.04.2017 660.00
Rajasthan Chhabra SCTPP RRVUNL L&T & MHI 6 660 Jan-18 Slipped
Telangana Bhadradri TPP TGENCO BHEL 1 270 Mar-18 Slipped
TOTAL STATE SECTOR 3546.15 1260.00
PRIVATE SECTOR
Chhattisgarh Akaltara (Naiyara) TPP KSK Mahandi Power Company Ltd CHINESE 3 600 Nov-17 - 18.01.2018 600.00 28.02.2018
Chhattisgarh Binjkote TPP SKS Power Generation ( Chhattisgarh) Ltd CHINESE 1 300 May-17 - 25.04.2017 300.00
Chhattisgarh Nawapara TPP TRN Energy CHINESE 2 300 May-17 - 18.04.2017 300.00 01.05.2017
Chhattisgarh Lanco Amarkantak TPS-II LAP Pvt. Ltd. CHINESE 3 660 Nov-17 Slipped
Maharashtra Nasik TPP Ph-I RattanIndia Nasik Power Ltd BHEL 3 270 May-17 - 14.04.2017 270.00
UP Bara TPP Prayagraj Power Generation Co.Ltd. BHEL 3 660 Aug-17 - 22.05.2017 660.00 26.05.2017
WB Hiranmaye Energy TPP Hiranmaye Energy Limited BHEL 1 150 Apr-17 - 07.06.2017 150.00 13.08.2017
TOTAL PRIVATE SECTOR 2940 2280.00
ADDITIONAL PROJECTS COMMISSIONED
PRIVATE SECTOR
Maharashtra Nasik TPP Ph-I RattanIndia Nasik Power Ltd BHEL 4 19.05.2017 270.00
Maharashtra Nasik TPP Ph-I RattanIndia Nasik Power Ltd BHEL 5 30.05.2017 270.00
Chhattisgarh Uchpinda TPP RKM Powergen Pvt.Ltd. Chinese 3 12.09.2017 360.00
Maharashtra Shirpur TPP Shirpur Power Pvt. Ltd. BHEL 1 28.09.2017 150.00
WB Hiranmaye Energy TPP Hiranmaye Energy Limited BHEL 2 31.12.2017 150.00 31.12.2017
Bihar Barauni Ext. BSEB BHEL 8 11.01.2018 250.00
Chhattisgarh Binjkote TPP SKS Power Generation ( Chhattisgarh) Ltd CHINESE 2 28.03.2018 300.00
Bihar Barauni Ext. BSEB BHEL 9 31.03.2018 250.00
TOTAL ADDITIONAL PRIVATE SECTOR 2000.00
TOTAL THERMAL CAPACITY in 2017-18 11366.15 8710.00

TPM_Broad Status Report (January-February’2020) 16


2.6 Thermal Capacity Addition Target/ Achievement for the Year 2018-19
State Project Name Impl Agency Equipment Unit No. Targeted Anti. Anti. Actual Date Capacity COD
Supplier Cap. Comm Comm of Capacity Achieved
(MW) Date at Date (At addition (MW)
beginning present)
of year
CENTRAL SECTOR
Assam Bongaigaon TPP NTPC BHEL 3 250 Sept-18 - 250.00 26.03.2019
Bihar Nabi Nagar TPP JV of NTPC &Rly BHEL 3 250 Dec-18 - 250.00 26.02.2019
Bihar New Nabi Nagar TPP JV of NTPC & BSPGCL NON BHEL 1 660 Jan-19 Slipped
MP Gadarwara STPP,St-I NTPC BHEL 1 800 Jan-18 29.03.2019 800.00 02.04.2019
Odisha Darlipali STPP NTPC BHEL 1 800 Slipped
TOTAL CENTRAL SECTOR 2760 1300.00

STATE SECTOR
Assam Namrup CCGT APGCL BHEL ST 36.15 Feb – 19 Slipped
MP Shri Singhaji TPP St-II MPGCL L&T & MHI 3 660 Sept - 18 18.11.2018 660.00 18.11.2018
MP Shri Singhaji TPP St-II MPPGCL L&T & MHI 4 660 Feb – 19 27.03.2019 660.00 27.03.2019
Odisha Ib valley TPP OPGC BHEL 4 660 March - 19 Slipped
Rajasthan Chhabra TPP Extn RRVUNL L&T & MHI 6 660 Dec – 18 29.03.2019 660.00 02.04.2019
Rajasthan Suratgarh SCTPP RRVUNL L&T & MHI 7 660 Dec – 18 Slipped
Karnataka Yelahanka CCPP KPCL BHEL 1 370 Oct – 18 Slipped
Telangana Kothagudem TPS St-VII TGENCO BHEL 800 Dec – 19 26.12.2018 800.00 26.12.2018
TOTAL STATE SECTOR 4506.15 2780.00

ADDITIONAL PROJECTS COMMISSIONED


Central SECTOR
Maharashtra Solapur STPP NTPC Non-Bhel 2 29.03.2019 660.00 30.03.2019
State Sector
Assam Lakwa Replacement Power APGCL 26.04.2018 69.755 26.04.2018
Project
Private Sector
MP Mahan TPP Essar Power Ltd Chinees 2 07.10.2018 600.00 07.10.2018
Chhattisgarh Uchpinda TPP R K M PowerGen Ltd Chinees 4 20.03.2019 360.00 20.03.2019
WB Dishergarh TPS IPCL Non-BHEL 27.03.2019 12.00 25.09.2012*
TOTAL ADDITIONAL PRIVATE SECTOR 1701.755
TOTAL THERMAL CAPACITY in 2018-19 7266.15 5781.755
* Dishergarh TPS Achieved COD on 25.09.2012 but intimation received in March’2019 .

TPM_Broad Status Report (January-February’2020) 17


2.7 Thermal Capacity Addition Target/ Achievement for the Year 2019-20

State Project Name Impl Agency Equipment Unit No. Targeted Anti. Comm Anti. Actual Date Capacity COD
Supplier Cap. Date at Comm of Capacity Achieved
(MW) beginning Date (At addition (MW)
of year present)
CENTRAL SECTOR
Bihar New Nabi Nagar TPP JV of NTPC & BSPGCL NON BHEL 1 660 May-19 - 12.07.2019 660.00
Chhatisgarh Lara STPP NTPC BHEL 2 800 Dec-19 Slipped
MP Gadarwara STPP,St-I NTPC BHEL 2 800 Dec-19 Slipped
MP Khargone STPP NTPC BHEL 1 660 Aug-19 29.09.2019 660.00
MP Khargone STPP NTPC BHEL 2 660 Feb-20 24.03.2020 660.00
Odisha Darlipali STPP NTPC BHEL 1 800 Aug-19 30.12.2019 800.00
U.P. Tanda TPP Stage - II NTPC L&T & MHI 1 660 Sep-19 28.09.2020 660.00
Tamil Nadu Neyveli New TPP NLC BHEL 1 500 Apr-19 21.12.2019 500.00
Tamil Nadu Neyveli New TPP NLC BHEL 2 500 Oct-19 Slipped
TOTAL CENTRAL SECTOR 6040 3940.00

STATE SECTOR
Andhra Dr.Narla Tata Rao TPS APGENCO BHEL 8 800 Feb – 20 Slipped
Pradesh
Stage-V
Assam Namrup CCGT APGCL BHEL ST 36.15 Nov-19 Slipped
Gujarat Wanakbori TPS Extn. GSECL BHEL 800 Nov-19 12.10.2019 800.00
Karnataka Yelahanka CCPP KPCL BHEL GT+ST 370 Nov - 19 Slipped
Odisha Ib valley TPP OPGC BHEL 3 660 Apr – 19 01.07.2019 660.00
Odisha Ib valley TPP OPGC BHEL 4 660 Jul - 19 17.08.2019 660.00
Rajasthan Suratgarh SCTPP RRVUNL L&T & MHI 7 660 Nov -19 15.03.2020 660.00
Telangana Bhadradri TPP TGENCO BHEL 1 270800 Jan - 20 Slipped 26.12.2018 800.00
TOTAL STATE SECTOR 4256.15 2780.00
ADDITIONAL PROJECTS COMMISSIONED
Private Sector
MP Niwari TPP BLA Power Ltd Chinees 2 06.06.20219 45.00
TOTAL ADDITIONAL PRIVATE SECTOR 45.00

TOTAL THERMAL CAPACITY in 2019-20 10296.15 6765.00

TPM_Broad Status Report (January-February’2020) 18


3.0 Target/ Achievement of Thermal Capacity addition during 12th Plan

State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
CENTRAL SECTOR
Assam Bongaigaon TPP NTPC BHEL U-1 250 250 250 22.06.15
Assam Bongaigaon TPP NTPC BHEL U-2 250 250 250 22.03.17
Assam Bongaigaon TPP NTPC BHEL U-3 250 250
Bihar Barh STPP-II NTPC BHEL U-4 660 660 660 30.11.13
Bihar Barh STPP-II NTPC BHEL U-5 660 660 660 04.03.15
Bihar Muzaffarpur TPP Extn KBUNL (JV of NTPC and BSEB) BHEL U-3 195 195 195 31.03.15
Bihar Muzaffarpur TPP Extn KBUNL (JV of NTPC and BSEB) BHEL U-4 195 195 195 24.03.17
Bihar Nabi Nagar TPP NTPC BHEL U-1 250 250 250 20.03.16
Bihar Nabi Nagar TPP NTPC BHEL U-2 250 250
Bihar Nabi Nagar TPP NTPC BHEL U-3 250 250
Bihar Nabi Nagar TPP NTPC BHEL U-4 250 250
Bihar Barh STPP-I NTPC Others U-1 660 660
Bihar Barh STPP-I NTPC Others U-2 660 660
Bihar Barh STPP-I NTPC Others U-3 660 660
Chhattisgarh Sipat-I NTPC Others U-3 660 660 660 02.06.12
Haryana Indira Gandhi TPP APCPL BHEL U-3 500 500 500 07.11.12
Jharkhand Koderma TPP DVC BHEL U-2 500 500 500 15.02.13
Jharkhand Bokaro TPS "A" Exp. DVC BHEL U-1 500 500 500 22.03.16
Karnataka Kudgi STPP Ph-I NTPC Non-BHEL U-1 # 800 800 25.12.16
Karnataka Kudgi STPP Ph-I NTPC Non-BHEL U-2 # 800 800 23.03.17
Maharashtra Mouda TPP NTPC BHEL U-1 500 500 500 19.04.12
Maharashtra Mouda TPP NTPC BHEL U-2 500 500 500 29.03.13
Maharashtra Mouda STPP Ph-II NTPC BHEL U-3 # 660 660 28.03.16
Maharashtra Mouda STPP Ph-II NTPC BHEL U-4 # 660 660 18.03.17
MP Vindhyachal TPP-V NTPC BHEL U-13 # 500 500 06.08.15
MP Vindhyachal STPS-IV NTPC BHEL U-11 500 500 500 14.06.12
MP Vindhyachal STPS-IV NTPC BHEL U-12 500 500 500 25.03.13
TN Vallur TPP Ph I NTECL BHEL U-2 500 500 500 28.02.13
TN Vallur TPP-II NTECL BHEL U-3 500 500 500 28.02.14

TPM_Broad Status Report (January-February’2020) 19


State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
TN Neyveli TPS-II EXP NLC BHEL U-2 250 250 250 24.01.15
TN Tuticorin TPP NTPL (JV NLC & TANGEDCO) BHEL U-1 500 500 500 10.03.15
TN Tuticorin TPP NTPL (JV NLC & TANGEDCO) BHEL U-2 500 500 500 09.07.15
Tripura Tripura Gas ONGC BHEL Module-1 363.3 363.3 363.3 03.01.13
Tripura Tripura Gas OTPS BHEL Module-2 363.3 363.3 363.3 16.11.14
Tripura Monarchak Gas Power Project NEEPCO BHEL GT 65.4 65.4 65.4 30.03.15
Tripura Monarchak CCPP NEEPCO BHEL ST 35.6 35.6 35.6 14.01.16
Tripura Agartala CCPP NEEPCO Thermax ST-2 # 25.5 25.5 22.03.15
Tripura Agartala CCPP NEEPCO Thermax ST-I # 25.5 25.5 23.08.16
UP Rihand STPS- III NTPC BHEL U-6 500 500 500 07.10.13
UP Rihand STPS- III NTPC BHEL U-5 500 500 500 25.05.12
UP Unchahar - IV NTPC BHEL U-6 # 500 500 31.03.17
WB Raghunathpur TPP Ph-I DVC Chinese U-1 600 600 600 24.08.14
WB Raghunathpur TPP,Ph-I DVC Chinese U-2 600 600 600 18.01.16

Total Central Sector 14877.6 11897.6 3971 15868.6 2980


STATE SECTOR
AP Damodaram Sanjeevaiah TPS APPDL BHEL/MHI U-1 800 800 800 28.08.14
AP Damodaram Sanjeevaiah TPS APPDL BHEL/MHI U-2 800 800 800 17.03.15
AP Rayalaseema St-IV AP Genco BHEL U-6 600 600
Assam Namrup CCGT APGCL BHEL GT 63.85 62.25 62.25 11.01.17
Assam Namrup CCGT APGCL BHEL ST 36.15 36.15
Chhattisgarh Korba West -St -III CSPGCL BHEL U-5 500 500 500 22.03.13
Chhattisgarh Marwa TPP CSPGCL BHEL U-1 500 500 500 30.03.14
Chhattisgarh Marwa TPP CSPGCL BHEL U-2 500 500 500 15.07.16
Delhi Pragati CCGT - III PPCL BHEL GT-3 250 250 250 27.06.12
Delhi Pragati CCGT - III PPCL BHEL GT-4 250 250 250 07.05.13
Delhi Pragati CCGT - III PPCL BHEL ST-2 250 250 250 26.02.14
Gujarat Pipavav CCPP GSECL BHEL Block-2 351 351 351 27.03.13
Gujarat Pipavav CCPP GSECL BHEL Block-1 351 351 351 05.02.14
Gujarat Ukai TPP Extn. GSECL BHEL U-6 500 500 500 05.03.13
Gujarat Dhuvaran CCPP-III GSECL Others Block-1 # 376.1 376.1 21.05.14
Gujarat Sikka TPS Extn GSECL BHEL U-3 250 250 250 28.03.15

TPM_Broad Status Report (January-February’2020) 20


State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
Gujarat Sikka TPS GSECL BHEL U-4 # 250 250 25.09.15
Gujarat Bhavnagar CFBC TPP Bhavnagar Energy BHEL U-1 # 250 250 16.05.16
Gujarat Bhavnagar CFBC TPP Bhavnagar Energy BHEL U-2 # 250 250 27.03.17
Karnataka Bellary TPS St-III KPCL BHEL U-3 # 700 700 01.03.16
Karnataka Yermarus TPP KPCL BHEL U-1 # 800 800 29.03.16
Karnataka Yermarus TPP KPCL BHEL U-2 # 800 800 29.03.17
Maharashtra Chandrapur TPS MSPGCL BHEL U-8 500 500 500 29.03.15
Maharashtra Koradi TPS Extn MSPGCL L&T U-8 660 660 660 30.03.15
Maharashtra Koradi TPS Expn. MSPGCL L&T U-9 # 660 660 15.03.16
Maharashtra Koradi TPS Expn. MSPGCL L&T 10 # 660 660 28.12.16
Maharashtra Chandrapur TPS MSPGCL BHEL U-9 # 500 500 21.03.16
Maharashtra Parli TPS MSPGCL BHEL U-8 250 250 250 30.03.16
MP Malwa TPP ( Shree Singaji TPP) MPGENCO BHEL U-2 600 600 600 15.10.14
MP Malwa TPP ( Shree Singa ji TPP) MPGENCO BHEL U-1 600 600 600 18.11.13
MP Satpura TPS Extn MPPGCL BHEL U-10 250 250 250 22.03.13
MP Satpura TPS Extn MPPGCL BHEL U-11 250 250 250 25.12.13
Rajasthan Ramgarh RRVUNL BHEL GT 110 110 110 20.03.13
Rajasthan Ramgarh CCPP Extn. -III RRVUNL BHEL ST 50 50 50 01.05.14
Rajasthan Chhabra TPS Extn. RRVUNL BHEL U-3 250 250 250 14.09.13
Rajasthan Chhabra TPS Extn. RRVUNL BHEL U-4 250 250 250 30.06.14
Rajasthan Kalisindh TPP RRVUNL Chinese U-1 600 600 600 02.05.14
Rajasthan Kalisindh TPP RVUNL Chinese U-2 # 600 600 06.06.15
TN North Chennai Extn TNEB BHEL U-2 600 600 600 09.03.13
TN North Chennai TPS Extn, U-1 TNEB BHEL U-1 600 600 600 13.09.13
TN Mettur TPS Ext TNEB Chinese U-1 600 600 600 11.10.12
Telangana Singareni TPP Singareni Collieries Co Ltd BHEL U-1 # 600 600 13.03.16
Telangana Singareni TPP Singareni Collieries Co Ltd BHEL U-2 # 600 600 25.11.16
Telangana Kakatiya TPS Extn. T GENCO BHEL U-1 # 600 600 31.12.15
Tripura Rokhia CCPP Govt.of Ttipura GT-9 # 21 21 31.08.13
UP Parichha Extn UPRVUNL BHEL U-5 250 250 250 24.05.12
UP Parichha Extn UPRVUNL BHEL U-6 250 250 250 11.03.13
UP Harduaganj Ext UPRVUNL BHEL U-9 250 250 250 25.05.12

TPM_Broad Status Report (January-February’2020) 21


State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
UP Anpara-D TPS UPRVUNL BHEL U- 6 500 500 500 06.06.15
UP Anpara-D TPS UPRVUNL BHEL U- 7 500 500 500 06.03.16
WB Durgapur TPS Extn U-8 DPL BHEL U-8 # 250 250 31.03.14
WB Sagardighi TPS-Extn West Bengal BHEL U-3 # 500 500 14.12.15
WB Sagardighi TPS-Extn West Bengal BHEL U-4 # 500 500 15.12.16
Total State Sector 13922 13284.25 8917.1 22201.4 0 636.15
PRIVATE SECTOR
AP Simhapuri TPP Ph-I Madhucon Chinese U-2 150 150 150 02.07.12
AP Thamminapatnam TPP-I Meenakshi Chinese U-1 150 150 150 09.09.12
AP Thamminapatnam TPP-I Meenakshi Energy Pvt. Ltd Chinese U-2 150 150 150 17.04.13
AP Thamminapatnam TPP-II Meenakshi Energy Pvt. Ltd Chinese U-3 350 350
AP Thamminapatnam TPP-II Meenakshi Energy Pvt. Ltd Chinese U-4 350 350
AP Simhapuri Energy Pvt Ltd Ph-II Madhucon Projects Ltd. Chinese U-3 # 150 150 21.02.14
AP Simhapuri Ph-II Simhapuri Energy Ltd., Chinese U-4 # 150 150 06.03.15
AP Bhavanapadu TPP Ph-I East Coast Energy Ltd. Chinese U-1 660 660
AP Bhavanapadu TPP Ph-I East Coast Energy Ltd. Chinese U-2 660 660
AP NCC TPP NCC Power Project Ltd. Chinese U-1 660 660 660 12.11.16
AP NCC TPP NCC Power Project Ltd. Chinese U-2 660 660 660 15.02.17
AP Painnampuram TPP Thermal Power Tech Corp.Ltd. Chinese U-1 660 660 660 07.02.15
AP Painampuram TPP Thermal Power Tech Corporation Chinese U-2 660 660 660 03.09.15
Ltd
AP Vizag TPP Hinduja National Power Corp. Ltd BHEL U-1 525 520 520 27.12.15
AP Vizag TPP Hinduja National Power Corp. Ltd BHEL U-2 525 520 520 30.03.16
AP Lanco Kondapalli Extn. Ph-III ( PS) Lanco Kondapalli Power Co.Ltd Others Block-I # 371 371 07.08.15
AP Lanco Kondapalli Extn. Ph-III (PS) Lanco Kondapalli Power Co.Ltd Others Block-II # 371 371 05.09.15
AP Vemagiri CCPP-II (PS) GMR Rajahmundry Energy Ltd. Others Block-I # 384 384 12.09.15
AP Vemagiri CCPP-II (PS) GMR Rajahmundry Energy Ltd. Others Block-II # 384 384 05.10.15
Chattisgarh Kasaipalli TPP ACB Chinese U-2 135 135 135 21.06.12
Chattisgarh Nawapara TPP TRN energy Pvt.Ltd.. Chinese U-1 300 300 300 14.08.16
Chattisgarh Nawapara TPP TRN energy Pvt.Ltd.. Chinese U-2 300 300
Chhattisgarh Ratija TPP Spectrum Coal & Power Ltd Chinese U-1 50 50 50 03.02.13
Chhattisgarh Ratija TPP -II Spectrum Coal & Power Ltd Non-BHEL U-2 # 50 50 10.11.16
Chhattisgarh Akaltara (Nariyara) TPP Wardha PCL (KSK) Chinese U-1 600 600 600 13.08.13

TPM_Broad Status Report (January-February’2020) 22


State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
Chhattisgarh Akaltara (Naiyara) TPP KSK Mahandi Power Co. Ltd Chinese U-2 (4th) 600 600 600 22.08.14
Chhattisgarh Akaltara (Naiyara) TPP KSK Mahandi Power Co. Ltd Chinese U-3 600 600
Chhattisgarh Avantha Bhandar TPP, U-1 Korba West Power Co. Ltd. BHEL U-1 600 600 600 31.03.14
Chhattisgarh Baradarha TPP D.B. Power Ltd BHEL U-1 600 600 600 23.02.14
Chhattisgarh Baradarha TPP D.B. Power Ltd BHEL U-2 600 600 600 24.03.15
Chhattisgarh Chakabura TPP ACB India Non-BHEL U-1# 30 30 28.03.14
Chhattisgarh Tamnar TPP ( Raigarh) O.P.Jindal BHEL U-1 600 600 600 10.03.14
Chhattisgarh Tamnar TPP ( Raigarh) O.P.Jindal BHEL U-2 600 600 600 30.03.14
Chhattisgarh Tamnar (Raigarh) TPP Jindal Power BHEL U-3 # 600 600 07.01.15
Chhattisgarh Tamnar (Raigarh) TPP Jindal Power BHEL U-4 # 600 600 26.03.15
Chhattisgarh Salora TPP M/s Vandana Vidyut Chinese U-1 135 135 135 10.04.14
Chhattisgarh Salora TPP M/s Vandana Vidyut Chinese U-2 135 135
Chhattisgarh Raikheda TPP GMR Chhattisgarh Power Ltd. Doosan (Non-BHEL) U-1 # 685 685 27.02.15
Chhattisgarh Raikheda TPP GMR Doosan (Non-BHEL) U-2 # 685 685 28.03.16
Chhattisgarh Swastic TPP ACB India Others U-1 25 25 25 31.03.15
Chhattisgarh Bandakhar TPP M/s Maruti Clean Chinese U-1 300 300 300 19.06.15
(Chhattisgarh) Ltd.
Chhattisgarh Uchpinda TPP RKM Powergen Pvt. Ltd Chinese U-1 360 360 360 28.10.15
Chhattisgarh Uchpinda TPP RKM Powergen Pvt. Ltd Chinese U-2 360 360 360 28.01.16
Chhattisgarh Uchpinda TPP RKM Powergen Pvt. Ltd Chinese U-3 360 0 360
Chhattisgarh Athena Singhitarai TPP Athena Chinese U-1 600 600
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-1 300 300
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-2 300 300
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-3 300 300
Chhattisgarh Lanco Amarkantak TPP-II LAP Pvt. Ltd. Chinese U-3 660 660
Chhattisgarh Lanco Amarkantak TPP-II LAP Pvt. Ltd. Chinese U-4 660 660
Chhattisgarh BALCO TPP BALCO Pvt Ltd Chinese U-1 300 300 300 05.06.15
Chhattisgarh BALCO TPP BALCO Pvt Ltd Chinese U-2 300 300 300 24.03.16
Gujarat Mundra UMTPP Tata Power Others U-2 800 800 800 25.07.12
Gujarat Mundra UMTPP Tata Power Others U-3 # 800 800 16.10.12
Gujarat Mundra UMTPP Tata Power Others U-4 # 800 800 16.01.13
Gujarat Mundra UMTPP Tata Power Others U-5 # 800 800 18.03.13
Gujarat Salaya TPP EssarPower Chinese U-2 600 600 600 13.06.12

TPM_Broad Status Report (January-February’2020) 23


State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
Gujarat Uno sugen Mega CCPP Torrent Energy Ltd Others Mod.I # 382.5 382.5 20.01.13
Gujarat DGEN Mega CCPP Torrent Energy Ltd Others Module-1 # 400 400 12.01.14
Gujarat DGEN Mega CCPP Torrent Energy Ltd Others Module-3 # 400 400 09.03.14
Gujarat DGEN Mega CCPP Torrent Energy Ltd Others Module-2 # 400 400 23.04.14
Haryana Jajjar TPS ( Mahatama Gandhi TPP) CLP Power Chinese U-2 660 660 660 11.04.12
Jharkhand Adhunik Power TPP Adhunik Power BHEL U-1 270 270 270 19.11.12
Jharkhand Adhunik Power TPP Adhunik Power BHEL U-2 270 270 270 29.03.13
Jharkhand Matrishri Usha TPP Ph-I Corporate Power Ltd. BHEL U-1 270 270
Jharkhand Matrishri Usha TPP Ph-I Corporate Power Ltd. BHEL U-2 270 270
Maharashtra Butibori TPP VIPL Chinese U-1 300 300 300 19.03.13
Maharashtra Butibori TPP VIPL Chinese U-2 # 300 300 17.08.12

Maharashtra Bela TPP-I, IEPL BHEL U-1 270 270 270 20.03.13
Maharashtra EMCO Warora TPP, EMCO GMR Chinese U-1 300 300 300 07.02.13
Maharashtra EMCO Warora TPP, EMCO GMR Chinese U-2 300 300 300 27.08.13
Maharashtra Tirora TPP Ph-I, Adani Power Ltd Chinese U-1 660 660 660 11.09.12
Maharashtra Tirora TPP Ph-I, Adani Power Ltd Chinese U-2 660 660 660 25.03.13
Maharashtra Gupta Energy Power Ltd Gupta Energy Power Ltd Chinese U-2 60 60 60 28.04.12
Maharashtra Gupta Energy Power Ltd Gupta Energy Power Ltd Chinese U-1 60 60 60 08.09.12
Maharashtra Amaravati TPP Ph-I Indiabulls BHEL U-1 270 270 270 25.03.13
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-2 270 270 270 17.02.14
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-3 270 270 270 29.01.15
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-4 270 270 270 04.03.15
Maharashtra Amravati TPP Ph-I India Bulls BHEL U-5 270 270 270 12.03.15
Maharashtra Dhariwal Infracture TPP Dhariwal Infracture (P) Ltd Chinese U-1 300 300 300 03.11.13
Maharashtra Dhariwal Infracture TPP Dhariwal Infracture (P) Ltd Chinese U-2 300 300 300 28.05.14
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-1 270 270 270 25.02.14
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-2 270 270 270 15.02.17
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-3 270 270
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-4 270 270
Maharashtra Nasik TPP Ph-I Ratan India Nasik Power Ltd. BHEL U-5 270 270
Maharashtra Tirora TPP Ph-II Adani Power Ltd Chinese U-1 660 660 660 10.06.13
Maharashtra Tirora TPP Ph-II Adani Power Ltd Chinese U-2 # 660 660 23.03.14

TPM_Broad Status Report (January-February’2020) 24


State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
Maharashtra Tirora TPP Ph-II Adani Power Ltd Chinese U-3 # 660 660 25.09.14
Maharashtra Lanco Vidarbha TPP Lanco Vidarbha Chinese U-1 660 660
Maharashtra Lanco Vidarbha TPP Lanco Vidarbha Chinese U-2 660 660
Maharashtra Mangaon CCPP PGPL Others Block-1# 388 388 14.07.16
MP Nigri TPP Jaiprakash Power Ventures Ltd L&T/MHI U-1 # 660 660 29.08.14
MP Nigri TPP Jaiprakash Power Ventures Ltd L&T/MHI U-2 # 660 660 17.02.15
MP Sasan UMPP Reliance Power Ltd. Chinese U-1 # 660 660 21.05.14
MP Sasan UMPP Reliance Power Ltd. Chinese U-4 # 660 660 25.03.14
MP Sasan UMPP Reliance Power Ltd. Chinese U-5 # 660 660 24.08.14
MP Sasan UMPP Reliance Power Ltd. Chinese U-6 # 660 660 19.03.15
MP Sasan UMPP Reliance Power Ltd. Chinese U-2 660 660 660 18.12.13
MP Sasan UMPP Reliance Power Ltd. Chinese U-3 660 660 660 30.05.13
MP BLA Power (Niwari) TPP BLA Power Ltd Non-BHEL U-1 # 45 45 24.03.12
MP Bina TPP, Bina Power BHEL U-1 250 250 250 12.08.12
MP Bina TPP, Bina Power BHEL U-2 250 250 250 31.03.13
M.P. Mahan TPP Essar Power MP Ltd Chinese U-1 # 600 600 24.02.13
MP Anuppur TPP Ph-I MB Power(MP) Chinese U-1 600 600 600 20.04.15
MP Anuppur TPP Ph-I MB Power(MP) Chinese U-2 600 600 600 30.03.16
MP Seioni TPP Ph-I Jhabua Power Ltd BHEL U-1 600 600 600 22.03.16
MP Gorgi TPP ( D B Power) DB Power Ltd BHEL U-1 660 660
Orissa Sterlite TPP, Sterlite Chinese U-4 600 600 600 25.04.12
Orissa Lanco Babandh TPP Lanco babandh Power Ltd. Chinese U-1 660 660
Orissa Kamalanga TPP GMR Chinese U-1 350 350 350 28.03.13
Orissa Kamalanga TPP GMR Chinese U-2 350 350 350 28.09.13
Orissa Kamalanga TPP GMR Chinese U-3 350 350 350 21.03.14
Orissa Derang TPP JITPL BHEL U-1 600 600 600 10.05.14
Orissa Derang TPP JITPL BHEL U-2 # 600 600 24.01.15
Orissa Ind Bharat TPP (Orissa) Ind Barath Chinese U-1 350 350 350 25.02.16
Orissa Ind Bharat TPP (Orissa) Ind Barath Chinese U-2 350 350
Orissa KVK Neelanchal TPP KVK Neelanchal Chinese U-1 350 350
Punjab Talwandi Sabo TPP M/s Sterlite Chinese U-1 660 660 660 17.06.14
Punjab Talwandi Sabo TPP Talwandi Sabo Power Ltd Chinese U-2 660 660 660 30.10.15

TPM_Broad Status Report (January-February’2020) 25


State Project Name Impl Agency Main Plant Equipment Unit No 12th Plan Cap. Ach. Add. Cap. Total cap. Actual Slipped
Supplier Tar. Cap. From Target Ach (MW) Ach. (MW) Comm.Date
(MW)
Punjab Talwandi Sabo TPP Talwandi Sabo Power Ltd Chinese U-3 660 660 660 29.03.16
Punjab Rajpura TPP ( Nabha) Nabha Power Ltd L&T U-2 700 700 700 06.07.14
Punjab Rajpura TPP ( Nabha) Nabha Power Ltd BTG- L&T U-1 700 700 700 24.01.14
Punjab Goindwal Sahib TPP GVK Power BHEL U-1 270 270 270 14.02.16
Punjab Goindwal Sahib TPP GVK Power BHEL U-2 270 270 270 15.03.16
Rajasthan Jallipa-Kapurdi TPP, Raj West Chinese U-5 135 135 135 05.02.13
Rajasthan Jallipa-Kapurdi TPP Raj West Chinese U-6 135 135 135 03.03.13
Rajasthan Jallipa-Kapurdi TPP Raj West Chinese U-8 # 135 135 28.02.13
Rajasthan Jallipa-Kapurdi TPP Raj West Chinese U-7 # 135 135 16.03.13
Rajasthan Kawai TPP Adani Power Ltd. Chinese U-1 # 660 660 28.05.13
Rajasthan Kawai TPP Adani Power Ltd. Chinese U-2 # 660 660 24.12.13
TN Tutucorin TPP -2(Ind Barath) Ind Barath Chinese U-1 # 150 150 10.03.13
TN Tuticorin TPP(Ind barath) Ind Barath Chinese U-2 # 150 150 30.12.13
TN Tuticorin TPP-II(Ind barath) IBPIL Chinese U-1 660 660
TN Melamaruthur TPP Coastal Energen Chinese U-1 # 600 600 02.12.14
TN Melamaruthur (Mutiara) Coastal Energen Chinese U-2 # 600 600 02.01.16
TN ITPCL TPP IL&FS TN PC.Ltd Chinese U-1 # 600 600 19.09.15
TN ITPCL TPP IL&FS TN PC.Ltd Chinese U-2 # 600 600 18.04.16
Uttrakhand GAMA CCPP M/s GAMA Infraprop Ltd. Others Module-1# 225 225 25.04.16
Uttrakhand Kashipur CCPP Ph-I M/a Sravanthi Energy Pvt.Ltd Others Module-1# 225 225 20.11.16
UP Lalitpur TPP Lalitpur power Generation Co. Ltd BHEL U-2 # 660 660 08.01.16
UP Lalitpur TPP Lalitpur power Generation Co. Ltd BHEL U-1 # 660 660 26.03.16
UP Lalitpur TPP Lalitpur power Generation Co. Ltd BHEL U-3# 660 660 01.04.16
UP Prayagraj (Bara ) TPP Prayagraj power Gen. Co. Ltd BHEL U-1 660 660 660 25.12.15
( J.P.Power Ventures)
UP Prayagraj (Bara ) TPP Prayagraj power Gen. Co. Ltd BHEL U-2 660 660 660 06.09.2016
( J.P.Power Ventures)
UP Prayagraj (Bara ) TPP Prayagraj power Gen. Co. Ltd ( BHEL U-3 660 660
J.P.Power Ventures)
WB Haldia TPP-I Haldia Energy Ltd Chinese U-1 300 300 300 14.01.15
Haldia TPP-I Haldia Energy Ltd Chinese U-2 300 300 300 16.02.15

Total Private Sector 43540 31285 22375.5 53660.5 12245


Total Commissioned during 12th Plan up to 31.03.17 72339.6 56466.85 35263.6 91730.45 15861.15
Note: # indicates the additional units commissioned which are not included in 12th Plan Target
Difference of 11.60 MW is 10 MW in Vizag TPP (PS) and 1.6 MW in Namrup CCGT
TPM_Broad Status Report (January-February’2020) 26
4.0 Thermal power projects Slipped from the 12th Plan Target with reasons for Slippage

State Project Name Impl Agency Main Plant Unit No 12th Plan Reasons for Slippage
Equipment Slipped Cap.
Supplier (MW)
CENTRAL SECTOR
Assam Bongaigaon TPP NTPC BHEL U-3 250 Frequent bandhs, Heavy monsoon and slow civil works. Delay in supply
of material by BHEL. Work came to halt due to violence and mass exodus
of labour from site in 2011-12. Civil works got affected due to poor
performance by civil contractors resulting in to their contract cancellation.
Balance civil and structural works awarded to NBCC on 29.09.14.
Bihar Nabi Nagar TPP NTPC BHEL U-2 250 Delay in acquisition of Land. Slow progress of works by main plant civil
Bihar Nabi Nagar TPP NTPC BHEL U-3 250 agency M/s ERA resulting in delay in handing over civil fronts to erection
Bihar Nabi Nagar TPP NTPC BHEL U-4 250 agencies. Delay in Supply of equipment by BHEL. Agitation by villagers.
Patches of land could not be acquired because of unwillingness of people
to accept compensation. Financial crunch faced by CHP vendor(Techpro).
Bihar Barh STPP-I NTPC Others U-1 660 Delay due to contractual dispute of NTPC with Power machine &
Bihar Barh STPP-I NTPC Others U-2 660 Technopromexport, Russia. *Orig. Sch. was in 2009-10 & 2010-11.
Bihar Barh STPP-I NTPC Others U-3 660 Delay in supply of boiler material and ordering of Bought out
Items(BOIs)by M/s TPE due to financial constrant. M/s. TPE stopped
work from 10/13. M/s TPE contract was terminated on 14.01.2015 by
NTPC. Delay in supply of material and slow progress by M/s. Power
Machine.
Total Central Sector 2980
STATE SECTOR
AP Rayalaseema St-IV AP Genco BHEL U-6 600 Delay in start & completion of civil works and land acquisition. Delay in
BoP works.
Assam Namrup CCGT APGCL BHEL ST 36.15 Delay in start and slow progress of of civil works, Termination of civil
contractor. Poor soil conditions and heavy monsoon. Delay in supply of
material by BHEL & shortage of skilled manpower. Termination of
NBPL order. Delay in award of civil and Electrical, Mechanical &
Instrumentation agency.
Total State Sector 636.15
PRIVATE SECTOR
AP Thamminapatnam TPP-II Meenakshi Energy Chinese U-3 350 Slow progress of Civil works. Due to financial problem, work at site
Pvt. Ltd remained closed for a long time.
AP Thamminapatnam TPP-II Meenakshi Energy Chinese U-4 350
Pvt. Ltd
AP BhavanapaduTPP Ph-I East Coast Energy Chinese U-1 660 Work remained under suspension due to MoE&F order for a long time.
Ltd. After restart works hampered due to two cyclones. Agitation against State
AP BhavanapaduTPP Ph-I East Coast Energy Chinese U-2 660 bifurcation. Slow progress of work at site due to financial problems.
Ltd.
Chattisgarh Nawapara TPP TRN energy Pvt.Ltd.. Chinese U-2 300 Delay in start of civil works. Slow progress in erection works of boiler
and T.G. Manpower shortage.
Chhattisgarh Akaltara (Naiyara) TPP KSK Mahandi Power Chinese U-3 600 Shortage of manpower, Agitation by Villagers. Delay in supply of
Co. Ltd material due to fund contraints.
Chhattisgarh Salora TPP M/s Vandana Vidyut Chinese U-2 135 Delay in commissioning of unit-1. Agitation by vllagers at site. Delay in
TPM_Broad Status Report (January-February’2020) 27
State Project Name Impl Agency Main Plant Unit No 12th Plan Reasons for Slippage
Equipment Slipped Cap.
Supplier (MW)
supply of BTG and CHP material. Non cooperation of BTG supplier in
commissioning activities. Acquistion for railway siding and ash pond.
Chhattisgarh Uchpinda TPP RKM Powergen Pvt. Chinese U-3 360 Work suffered due to agitation by villagers. Slow progress of work at site.
Ltd Delay in readiness of BOPs.Delay in readiness of start up power. Delay
due to financial problem. Balance land acquistion for ash pond and
Railway line siding. Consent to operate for U- 3 &4.
Chhattisgarh Athena Singhitarai TPP Athena Chinese U-1 600 Delay in land acquisition. Slow progress of Boiler & TG erection. Delay
due to financial problems.
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-1 300 Delay in start of civil works. Slow progress of pressure parts erection.
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-2 300 Balance land acquisition for ash dyke. Delay due to financial problems.
Chhattisgarh Binjkote TPP SKS Power Gen Chinese U-3 300
Chhattisgarh Lanco Amarkantak TPP-II LAP Pvt. Ltd. Chinese U-3 660 Delay in acquisition of land for water system. Presently work is going
Chhattisgarh Lanco Amarkantak TPP-II LAP Pvt. Ltd. Chinese U-4 660 slow at site due to financial problems.
Jharkhand Matrishri Usha TPP Ph-I Corporate Power Ltd. BHEL U-1 270 Law and order problem. Delay in supply of BTG equipment. Delay in
Jharkhand Matrishri Usha TPP Ph-I Corporate Power Ltd. BHEL U-2 270 readiness of transmission line due to forest clearance. Work held up due
to financial problems since Nov, 12.
Maharashtra Nasik TPP Ph-I Ratan India Nasik BHEL U-3 270 Non-Acceptanceof BTG material by Project Authorities. Work is going
Power Ltd. slow at site due to financial problems.
Maharashtra Nasik TPP Ph-I Ratan India Nasik BHEL U-4 270
Power Ltd.
Maharashtra Nasik TPP Ph-I Ratan India Nasik BHEL U-5 270
Power Ltd.
Maharashtra Lanco Vidarbha TPP Lanco Vidarbha Chinese U-1 660 Work is going slow at site due to financial problems
Maharashtra Lanco Vidarbha TPP Lanco Vidarbha Chinese U-2 660
MP Gorgi TPP ( D B Power) DB Power Ltd BHEL U-1 660 Order for main plant equipment has been placed. Work is on hold.
Commissioning schedule would be assessed after re-start of work.
Orissa Lanco Babandh TPP Lanco babandh Chinese U-1 660 Delay in land acquisition. Work is going slow at site due to financial
Power Ltd. problem.
Orissa Ind Bharat TPP Ind Barath Chinese U-2 350 Delay due to heavy rains. Delay in readiness of transimission line for start
(Orissa) up power. Commissioning problems such as change of firing guns of
Orissa KVK Neelanchal TPP KVK Neelanchal Chinese U-1 350 boiler and change in bypass valve.
TN Tuticorin TPP-II(Ind barath) IBPIL Chinese U-1 660 Late start and slow progress of civil works and delay in supply of boiler
structural material at site.
UP Prayagraj (Bara ) TPP Prayagraj power Gen. BHEL U-3 660 Delay in BTG supply, Raw water pipe line readiness and transmission line
Co. Ltd( J.P.Power readiness for start up power. Progress of work at site delayed due to
Ventures) financial problems. Delay in Land Acqisition for railway siding and
power evacuation.
Total Private Sector 12245
Total Slippage from 12th Plan Target as on 31.03.17 15861.15

TPM_Broad Status Report (January-February’2020) 28


5.0 THERMAL POWER PROJECTS UNDER CONSTRUCTION IN THE COUNTRY

S. No. State Project Name / Impl. Agency/ Org. Ant.


Ant. Comm. Exp. In
EPC or BTG LOA Date/ Unit No Cap. (MW) Comm. Trial Run / Till Date
Sched. crores.
Sched. COD
CENTRAL SECTOR
1. Bihar Barh STPP-I /NTPC/Others Mar-05 U-1 660 May-17 Oct-20 Nov-20
17010.22 Feb-20
Mar-05 U-2 660 Nov-17 Mar-21 Apr-21
Mar-05 U-3 660 May-18 Sep-21 Oct-21
2. Bihar Nabi Nagar TPP / JV of NTPC & Jan-08 U-4 250 Nov-13 Dec-20 Feb-21 8077.37 Feb-20
Rlys/BHEL
3. Bihar New Nabi Nagar TPP / JV of Jan-13 U-2 660 Jul-17 Dec-20 Jan-21
NTPC & BSPGCL /TG- Alstom 14408.86 Feb-20
Jan-13 U-3 660 Jan-18 Jul-21 Aug-21
& Bharat Forge, SG-BHEL
4. Bihar Buxar TPP Jun-19 U-1 660 Jul-23 Jun-23 Jul-23
882.92 Feb-20
Jun-19 U-2 660 Jan-24 Jan-24 Jan-24
5. Chhatisgarh Lara STPP / NTPC / SG-Dooson Dec-12 U-2 800 May-17 Jul-20 Aug-20 12964.82 Feb-20
TG-BGR Hitachi
6. Jharkhand North Karanpura STPP/ NTPC / Feb-14 U-1 660 Feb-18 May-21 Jun-21
BHEL 10035.08 Feb-20
Feb-14 U-2 660 Aug-18 Nov-21 Dec-21
Feb-14 U-3 660 Feb-19 May-22 Jun-22
7. MP Gadarwara STPP / NTPC / Mar-13 U-2 800 Sep-17 Aug-20 Sep-20 12571.63 Feb-20
BTG-BHEL
8. Odisha Darlipalli STPP / NTPC / SG- Feb-14 U-2 800 Jun-18 Oct-20 Nov-20 10257.95 Feb-20
BHEL TG-JSW & Toshiba
9. Rajasthan Barsingar TPP ext / NLC / Nov-16 U-1 250 May-20 Hold Hold 159.0581 Mar-20
Reliance Infra
10. Rajasthan Bithnok TPP / NLC / Reliance Nov-16 U-1 250 May-20 Hold Hold 174.6634 Mar-20
Infra
11. Telangana Telangana STPP St- I / NTPC / Feb-16 U-1 800 Jan-20 Apr-21 May-21 6457.92 Feb-20
SG- BHEL, TG- Alstom &
Feb-16 U-2 800 Jul-20 Oct-21 Nov-21
Bharatforge
12. TN Neyveli New TPP / NLC / Dec-13 U-2 500 Mar-18 Sep-20 Oct-20 6265.1603 Feb-20
BHEL
13. UP Meja STPP / JV of NTPC & Apr-12 U-2 660 Dec-16 Sep-20 Oct-20 10182 Jan-20
UPRVUNL / SG-BGR, TG-
Toshiba
14. UP Ghatampur TPP / JV of NLC & Aug-16 U-1 660 Apr-20 Feb-21 Apr-21
UPRVUNL / MHPS Boiler Pvt. 8844.35 Feb-20
Aug-16 U-2 660 Oct-20 Aug-21 Oct-21
Ltd.
Aug-16 U-3 660 Oct-20 Jan-22 Mar-22
15. UP Tanda TPP St II / NTPC / SG: Sep-14 U-6 660 Feb-20 Nov-20 Dec-20 7143.97 Feb-20
L&T / TG: Alstom
16. UP Khurja SCTPP Mar-19 U-1 660 Mar-23 Apr-23 Apr-23
918.62 Feb-20
Mar-19 U-2 660 Sep-23 Sep-23 Sep-23

TPM_Broad Status Report (January-February’2020) 29


S. No. State Project Name / Impl. Agency/ Org. Ant.
Ant. Comm. Exp. In
EPC or BTG LOA Date/ Unit No Cap. (MW) Comm. Trial Run / Till Date
Sched. crores.
Sched. COD
17. Jharkand Patratu STPP / JV of NTPC & Mar-18 U-1 800 Mar-22 Mar-22 Mar-22
Jharkhand Bidyut Vitran Nigam 2672.12 Feb-20
Mar-18 U-2 800 Sep-22 Sep-22 Sep-22
Ltd.
Mar-18 U-3 800 Mar-23 Mar-23 Mar-23
18. Odisha Rourkela PP-II Expansion / May-16 U-1 250 Dec-18 Feb-21 Apr-21
NTPC-Sail Power Co Ltd 1554.68 Mar-20
(NSPCL) (JV of NTPC & SAIL) /
BHEL
TOTAL CENTRAL SECTOR 19120
STATE SECTOR
1. A.P Dr.Narla Tata Rao TPS St-V / Oct-20 Nov-20 4639.42 Sept-19
Oct-15 U-1 800 Jun-19
APGENCO / BTG- BHEL
2. A.P Sri Damodaran Sanjeevaiah TPP Nov-20 Dec-20 5928 Feb-20
Nov-15 U-1 800 Mar-19
St-II / APGENCO /BTG- BHEL
3. Assam Namrup CCGT / APGCL / 06.03.2020 Jun-20 581.48 Jun-19
Feb-09 ST 36.15 Jan-12
BHEL
4. Karnataka Yelahanka CCPP BY KPCL Oct-20 Nov-20 1578.8517 Feb-20
Nov-15 GT+ST 370 Mar-18
5. Maharashtra Bhusawal TPS/MAHAGENCO Apr-22 Jun-22
Jan-18 U-6 660 Mar-22
6. Rajasthan Suratgarh SCTPP/ RRVUNL /
May-13 U-8 660 Dec-16 June-20 Dec-20 9303.23 Feb-20
BHEL
7. Telangana Bhadradri TPP / TSGENCO/ Mar-15 U-1 270 Mar-17 20.03.2020 Jun-20
BHEL Mar-15 U-2 270 May-17 Jul-20 Aug-20 Feb-20
6325.52
Mar-15 U-3 270 Jul-17 Dec-20 Jan-21 (13.02.2020)
Mar-15 U-4 270 Sep-17 May-21 Jun-21
8. TN Ennore exp. SCTPP (Lanco) /
May-14
TANGEDCO / BTG-BGR U-1 660 Jan-18 Sep-19 791.4 Dec-17
Dec -19
(Lanco – Terminated)
9. TN Ennore SCTPP / TANGEDCO/ Sep-14 U-1 660 Jan-18 Jul-21 Aug-21
BHEL 3960.73 Dec-19
Sep-14 U-2 660 Mar-18 Oct-21 Nov-21
10. TN North Chennai TPP St-III
Jan-16 U-1 800 Mar-19 Nov-20 Jan-21 5304.14 Feb-20
TANGEDCO/BHEL
11. TN Udangudi STPP Stage I/ U-1 660 Feb-21 Jan-23 Mar-23
Dec-17 979.1192 Feb-20
TANGEDCO, EPC- BHEL U-2 660 Feb-21 Jul-23 Sep-23
12. TN Uppur Super Critical TPP Feb-16 U-1 800 Mar-19 Jan-23 Mar-23
TANGEDCO /BHEL 2665.45 Feb-20
Feb-16 U-2 800 Oct-19 Jul-23 Sep-23
13. UP Harduaganj TPS Exp-II /
Sep-15 U-1 660 Jun-19 Jun-20 Sept-20 3063.61 Nov-19
UPRVUNL/ Toshiba JSW
14. Telangana Yadadri TPS/TSGENCO/BHEL U-1 800 Oct-20 Sep-22 Oct-23
Oct-17 U-2 800 Oct-20 Sep-23 Oct-23 5861.88 Nov-19
U-3 800 Oct-21 May-23 Jun-23

TPM_Broad Status Report (January-February’2020) 30


S. No. State Project Name / Impl. Agency/ Org. Ant.
Ant. Comm. Exp. In
EPC or BTG LOA Date/ Unit No Cap. (MW) Comm. Trial Run / Till Date
Sched. crores.
Sched. COD
U-4 800 Oct-21 May-23 Jun-23
U-5 800 Oct-21 Sep-23 Oct-23
15. UP Jawaharpur STPP/ Dec-16 U-1 660 Sep-20 Aug-21 Oct-21
3968.2 Feb-20
UPRVUNL/ Doosan Dec-16 U-2 660 Jan-21 Dec-21 Jan-22
16. UP Panki TPS Extn./ URVUNL Mar-18 U-1 660 Dec-21 Dec-21 Jan-22 16 Apr-18
17. UP Obra-C STPP/ UPRVUNL/ Dec-16 U-1 660 Sep-20 Apr-21 Jun-21
3018.19 Dec-19
Doosan Dec-16 U-2 660 Dec-20 Jul-21 Nov-21
Total State Sector 18066.15
PRIVATE SECTOR
1. AP Bhavanapadu TPP Ph-I / East Sep-09 U-1 660 Oct-13 Uncertain* Uncertain*
Coast Energy Ltd./ BTG- 3785.6 Jan-16
Sep-09 U-2 660 Mar-14 Uncertain* Uncertain*
Chinese
2. AP Thamminapatnam TPP stage -II Dec-09 U-3 350 May-12 Stressed Stressed
/ Meenakshi Energy Pvt. Ltd. 5414.4 Feb-19
Dec-09 U-4 350 Aug-12 Stressed Stressed
SG-Cether vessels TG-Chinese
3. Bihar Siriya TPP (Jas Infra. TPP) / Mar-11 U-1 660 Aug-14 Uncertain* Uncertain*
JICPL / BTG-Chinese Mar-11 U-2 660 Dec-14 Uncertain* Uncertain*
NA
Mar-11 U-3 660 Apr-15 Uncertain* Uncertain*
Mar-11 U-4 660 Aug-15 Uncertain* Uncertain*
4. Chhattisgarh Akaltara TPP (Naiyara) / KSK Apr-09 U-4 600 Apr-13 Stressed Stressed
Mahandi Power Company Ltd./ Apr-09 U-5 600 Aug-13 Uncertain Uncertain 18730.00 Dec-16
Chinese Apr-09 U-6 600 Dec-13 Uncertain Uncertain
5. Chhattisgarh Binjkote TPP/ SKS Power Mar-11 U-3 300 Mar-14 Uncertain Uncertain
Generation (Chhattisgarh) Ltd.
3828 Jun-15
SG-Cethar Vessels TG-Harbin Mar-11 U-4 300 Jun-14 Uncertain Uncertain
China
6. Chhattisgarh Lanco Amarkantak TPP-II/ Nov-09 U-3 660 Jan-12 Uncertain Uncertain
9537.79 Dec-16
LAP Pvt. Ltd. BTG-DEC Nov-09 U-4 660 Mar-12 Uncertain Uncertain
7. Chhattisgarh Singhitarai TPP / Athena Dec-09 U-1 600 Nov-14 Uncertain Uncertain
Chhattisgarh Power Ltd./ 6408.47 May-17
Dec-09 U-2 600 Feb-15 Uncertain Uncertain
BTG -DECL
8. Chhattisgarh Salora TPP / Vandana Vidyut/
Sep-09 U-2 135 Sep-11 Uncertain* Uncertain* 2386.89 Mar-15
BTG-Cether Vessles
9. Chhattisgarh Deveri (Visa) TPP / Visa Power
Jun-10 U-1 600 Aug-13 Uncertain* Uncertain* 2077.23 Nov-15
Ltd. BTG-BHEL
10. Jharkhand Matrishri Usha TPP Ph-I / Dec-09 U-1 270 Apr-12 Uncertain* Uncertain*
Corporate Power Ltd. /EPC- 3120 Nov-12
Dec-09 U-2 270 May-12 Uncertain* Uncertain*
BHEL
11. Jharkhand Matrishri Usha TPP Ph-II / Mar-11 U-3 270 Oct-12 Uncertain* Uncertain*
Corporate Power Ltd. / EPC- 2207 Sep-12
Mar-11 U-4 270 Jan-13 Uncertain* Uncertain*
BHEL
12. Jharkhand Tori TPP Ph-I / Essar Power Aug-08 U-1 600 Jul-12 Uncertain* Uncertain*
4757.92 Jun-17
Ltd. / BTG-China Aug-08 U-2 600 Sep-12 Uncertain* Uncertain*

TPM_Broad Status Report (January-February’2020) 31


S. No. State Project Name / Impl. Agency/ Org. Ant.
Ant. Comm. Exp. In
EPC or BTG LOA Date/ Unit No Cap. (MW) Comm. Trial Run / Till Date
Sched. crores.
Sched. COD
13. Jharkhand Tori TPP Ph-II / Essar Power
U-3 600 Dec-15 Uncertain* Uncertain* 246.65 Mar-15
Ltd.
14. Maharashtra Amravati TPP Ph-II / Ratan Oct-10 U-1 270 Jul-14 Uncertain* Uncertain*
India Power Pvt. Ltd. / BTG- Oct-10 U-2 270 Sep-14 Uncertain* Uncertain*
BHEL Oct-10 U-3 270 Nov-14 Uncertain* Uncertain* 763.8 Mar-15
Oct-10 U-4 270 Jan-15 Uncertain* Uncertain*
Oct-10 U-5 270 Mar-15 Uncertain* Uncertain*
15. Maharashtra Lanco Vidarbha TPP / LVP Nov-09 U-1 660 Jul-14 Uncertain* Uncertain*
5338 Apr-17
Pvt. Ltd. /EPC-LANCO Nov-09 U-2 660 Nov-14 Uncertain* Uncertain*
16. Maharashtra Nasik TPP Ph-II / Ratan India Nov-09 U-1 270 Apr-13 Uncertain Uncertain
Nasik Power Pvt. Ltd. BTG- Nov-09 U-2 270 Jun-13 Uncertain Uncertain
BHEL Nov-09 U-3 270 Aug-13 Uncertain Uncertain 711.81 Mar-15
Nov-09 U-4 270 Oct-13 Uncertain Uncertain
Nov-09 U-5 270 Dec-13 Uncertain Uncertain
17. Maharashtra Bijora Ghanmukh TPP / Sep-11 U-1 300 Dec-16 Uncertain Uncertain
Jinbhuvish Power Generation 422.27 Mar-15
Sep-11 U-2 300 Mar-17 Uncertain Uncertain
Pvt. Ltd. / BTG-Chinese
18. Maharashtra Shirpur TPP ,Shirpur Power
Nov-11 U-2 150 Apr-15 Uncertain Uncertain 2277.94 Apr-17
Pvt. Ltd.-BHEL
19. MP Gorgi TPP / D.B. Power (MP)
Mar-11 U-1 660 Jun-13 Uncertain Uncertain 475.79 Sep-15
Ltd. BTG-BHEL
20. Odisha Ind Barath TPP (Odisha) / Ind
May-09 U-2 350 Dec-11 Uncertain Uncertain 4254 Apr-17
Barath /BTG-Cethar Vessels
21. Odisha KVK Nilanchal TPP/ Nov-09 U-1 350 Dec-11 Uncertain* Uncertain*
KVK Nilanchal / BTG-Harbin Nov-09 U-2 350 Feb-12 Uncertain* Uncertain* 1708.36 Mar-15
China Nov-09 U-3 350 Feb-12 Uncertain* Uncertain*
22. Odisha Lanco Babandh TPP / LBP Nov-09 U-1 660 Apr-13 Uncertain* Uncertain*
7615 Mar-17
Ltd./ BTG-Chinese Nov-09 U-2 660 Aug-13 Uncertain* Uncertain*
23. Odisha Malibrahmani TPP / MPCL/ Jun-10 U-1 525 Dec-12 Uncertain* Uncertain*
5329.75 Dec-14
BTG-BHEL Jun-10 U-2 525 Feb-13 Uncertain* Uncertain*
24. TN Tuticorin TPP (Ind- Barath) /
IBPIL / BTG- May-10 U-1 660 May-12 Uncertain* Uncertain* 2000 May-15
Chinese
25. TN Tuticorin TPP St-IV / SEPC/
Jan-14 U-1 525 Sep-18 Oct-20 Oct-20 2725.72 Feb-20
EPC-MEIL (BTG-BHEL)
26. WB Hiranmaye Energy Ltd (India
Power corporation (Haldia) TPP
Sep-10 U-3 150 May-16 Uncertain* Uncertain* 3263.05 Oct-17
/ Haldia Energy Ltd/ BTG-
BHEL.
Total Private Sector 23730
Grand Total 60916.15
* Presently work at site is on hold.

TPM_Broad Status Report (January-February’2020) 32


BROAD STATUS
Of

THERMAL POWER PROJECTS

CENTRAL SECTOR

TPM_Broad Status Report (January-February’2020) 33


BROAD STATUS OF UNDER CONSTRUCTION CENTRAL SECTOR THERMAL POWER PROJECTS
(NTPC Limited)
Sl. Cap. Commissioning Schedule
No. Project Details (MW) Original Actual(A) / As now Broad Status
Expected
Syn. Trail Syn. Trail run
Com run/COD Com COD
Central Sector
1. Bongaigaon TPS, 750 Unit-1: COD achieved on 01.04.2016.
Distt: Kokrajhar, Commissioned on 22.06.2015.
Assam NTPC Ltd
Boiler: Boiler Erection started on 27/02/2009.
U-1 250 11/10 - 06/15(A) -
22.06.15(A) 01.04.16(A) Drum lifted on 25/01/2010.Hydro test done on 01/2011. BLU
01/11
done on 29/11/14 & steam blowing completed on 01/04/15.
U-2 250 03/11 - 02/17(A) -
TG: Condenser erection started in 2/10. TG erection started
05/11 22.03.17(A) 01.11.17(A)
in 03/11& boxed up in 04/15.
U-3 250 07/11 - 02.01.19(A) 14.02.19(A)
09/11 10.02.19(A) 26.03..19(A)
Original / Latest cost : Rs. 4375.35 Cr/ Rs. 6749.18 Cr / 8150.00 Cr
Unit-2: COD achieved on 01.11.2017.
Commissioned on 22.03.2017.
Exp. During 2007-08 : Rs. 238.31 Cr
2008-09 : Rs. 160.46 Cr Boiler: Boiler Erection started on 3/10. Drum lifted in
2009-10 : Rs 709.13 Cr 10/10.Hydro test done in 04/12. BLU done on 27.03.16.
2010-11 : Rs 563.00 Cr Steam blowing completed in 11/16.
2011-12 : Rs 1376.10 Cr TG: TG erection started in 01/16. TG Box up completed in
2012-13 : Rs. 749.00 Cr 11/16.TG oil flushing completed in 12/16.
2013-14 Rs. 685.00 Cr
2014-15 : Rs. 657.00 Cr
2015-16 : Rs. 787.00 Cr
Unit-3: COD achieved on 26.03.2019. Trail run
2016-17 : Rs. 591.00 Cr completed on 14.02.2019. Commissioned on
2017-18 : Rs. 506.00 Cr 10.02.2019. Unit synchronized on 02.01.2019.
2018-19 : Rs. 299.52 Cr (1/19)
Cumulative Exp. : Rs. 7299.48 Cr (1/19) Boiler: Boiler Erection started in 4/12. Boiler drum lifted on
25/02/13 & HT done on 21/03/14. BLU done in 07/2017.
Investment Approval : 30/01/2008 Steam Blowing is completed in 09/18.Coal firing done in
Type of fuel : Coal 12/18.
Investment Approval : 30/01/2008 TG: TG deck casting done in 03/16. TG erection started in
10/16. HP, IP module placed. TG boxed up in 03/18.
Date of Main Plant : 05/02/08,M/s BHEL
Order BoP:
Power Evacuation: 1. 400KV BTPS(NTPC)- Chimney: Completed.
Bongaigaon (PG) D/C Line CHP: Order placed on M/s McNally Bharat in Jan’10. Both
2. 220 KV BTPS(NTPC)- Trippers are ready and coal bunking conveyors
Bongaigaon (Assam ) D/C Line commissioned.
Coal Source and Transportation: AHP: Dry ash system readiness by Mar’19.
2/3 of required Coal will be transported from Margarita- Makuma mines of NECL CW: CW pumps commissioned.
(Upper Assam).Rest 1/3 will be supplied by ECL mines in Raniganj area of West Cooling tower: Ready
Bengal. Coal will be transported using Railway wagons by BOBR. DM plant: DM control room building civil work is in
progress.

FGD: Awarded with SG Package to BHEL.


Resolution of Commercial issues between M/s
BHEL and OEM of FGD M/s Ducon is awaited.
Owing to poor performance of main plant civil agencies
(SPML, Punjlloyd) their contracts were terminated on
25.11.13. Balance works of U-2&3 awarded to NBCC on
29/09/14. NBCC finalized its sub agencies on 06/01/15 and
construction works commenced in Feb’15 due to delay in
mobilization by M/s NBCC.
Critical Areas Intermittent suspension of supplies of aggregates by local vendors, demand for aexhorbitnat rates etc. have affected the
progress of work. Frequent work stoppage at site due labor unrest.
Reasons for Delay Inadequate deployment of work force by BHEL and its sub-agencies affected the progress of Unit-1. Law and order issues.
Frequent bandhs leading to stoppage of work.
Work has come to halt in Jul’12, May’14 & Dec’14 due to violence and mass exodus of labor from site. Poor performance
of BOP/Civil contractors. .
MK 11.02.20

TPM_Broad Status Report (January-February’2020) 34


Sl. Cap Commissioning Schedule
No. PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As
now Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
2. Barh STPP St-I, 1980 Unit-1:
Dist: Patna, Bihar Boiler: Boiler erection started in 03/11. Boiler Hydro Test
(NTPC Ltd.) completed on 28.02.13. Boiler light up on 14.08.2019. SBO
U-1 660 03/09 06/17 06/20 - completed on 23.01.2020. Balance of works of insulation of
08/09 07/20 8/20 ducts, errection of temporary piping for steam blowing
05/17* activities in progress.
05/17*
U-2 660 01/10 12/17 10/20 - TG: TG erection started in 08/11. TG Box up completed on
06/10 10/20 12/20 28/12/13.TG Lub oil flushing completed. TG put on barring
11/17* gear in July, 2019.
11/17*
U-3 660 11/10 Unit-2:
04/11 06/18 4/21 - Boiler: Boiler erection started in 07/11. Boiler Hydro Test
05/18* 4/21 08/21 expected by 01/20.
05/18* TG: TG erection started in 09/11.TG Box up completed in
(*Revised as per award of balance works of SG 01/15. TG oil-flushing completion in 07/19.
package dated 30.01.16)
Original/Latest Cost : Rs8692.97 / 15095.67 / 21312.11 Crs. Unit-3:
Boiler: Boiler erection started in 01/12. Boiler Hydro Test
Cum Exp.upto 2009 : Rs 3967.10 Crores expected by 07/20.
2009-10 : Rs 695.39 Crores TG: TG erection started in 03/12.TG box-up expected by
2010-11 : Rs 922.00 Crores 09/20.
2011-12 : Rs 1272.00 Crores
Balance of Plant (BoP):
2012-13 : Rs 1433.00 Crores
Chimney: lining for FGD to be done to existing chimney
2013-14 : Rs 1601.00 Crores
before light up. Yet to mobilize. Basic Engg, ordering in
2014-15 : Rs 811.00 Crores
progress.
2015-16 : Rs 1167.00 Crores
CHP: Erection up to TP-4 completed. Beyond TP-4 erection
2016-17 : Rs 1474.00 Crores
is in progress. Track hopper & WT system stream
2017-18 : Rs.1395.00 Crores
commissioned.
2018-19 : Rs.1366.84 Crores
AHP: Erection of ash water pumps, vacuum pumps, 3 Nos.
2019-20 Rs.1105.04 Crores (02/20)
FAE tower structures completed. Trench work, Ash slurry
Cumulative Exp : Rs 17010.22 Crs (up to (02/20) sump, BA line pedestal work in progress.
Investment Approval : Feb’05 Original / Qtr - 4 2018 (Latest) Ash dyke: All works in Ash Dyke completed.
Sanctioning Authority : NTPC Board Cooling Tower: Erection completed. Water charging done
Type of fuel : Coal once, repair/replacement required.
Date of Main Plant Order SG :03/2005 on M/s Technopromexport, Russia. PT Plant: 2 clarifiers Ready
(BTG) (Terminated on 14.01.2015) # DM Plant: Ready
TG : 03/2005 on M/s Power Machines Russia CW System: Erection nearly completed. 2nos Raw water
pumps & SACW pumps commissioned.2nos CW pumps trial
Zero Date 14/03/2005 taken. 01 PT make up pump trial taken in R/C mode.
Switchyard: Ready
Power Evacuation
FGD: FGD is awarded to BHEL on 18.09.18.
Detailed Engg ordering and ordering in progress.
 Test Pile completed.
 Chimney liner preparatory work in progress. Borosilicate
Lining for FGD to be done in the existing Chimney by
BHEL.
Critical Areas  USA has imposed sanction on Power Machine, Russia on 26.01.2018 whiuch is affecting balance supply erecyion
& commissioning of TG & Aux Package of Unit 2 &3.
 DPSI has expressed inability in supply of balance main equipments as well as mandatory spares of SG pkg ordered
by them on TKZ, Russia due to risk of secondary sanaction.
US Sanctions imposed on Power Machines affecting supplies of SG Package materials (ordered by Doosan to TKZ,
Russia). Expeditious resolution on issues required to move forward.
 Readiness of railway line Hazaribagh-Koderma-Tilaiya-Rajgir-Bakhtiyarpur route (250km) is critical for
transportation of coal for Project. Project would face major coal supply constraints until this line is made operational.
NTPC has funded Rs 664 Crores to Railways for development of following works in envisaged Coal transportation
route. − Construction of Karnauti-Bakhtiyarpur flyover with 3rd line and surface triangle. − Construction of Manpur
Flyover (ROR) − Electrification of Manpur-Tillaiya-Bakhtiyarpur section. Work progress is slow due to land
acquisition issues.
 Apart from above, deposit work of 03 nos Push culvert work (required for Stage-I ash slurry pipeline) and OHE
work inside plant is moving at slow pace. Support of Ministry of Railways is required for timely completion of the
above Railway works.
MPS 30.03.2020

TPM_Broad Status Report (January-February’2020) 35


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail Syn. Trail run
Com run Com COD
COD
Central Sector
3. Nabinagar TPP, Dist: 1000 Unit-1: COD declared on 15.01.2017. Trial run completed
Aurangabad, Bihar on 06.01.17. Commissioned on 20.03.2016.
[BRBCL-Bhartiya Rail Boiler: Boiler erection started in 05/11. Boiler drum lifted on
Bijlee Co. Ltd. (JV of 20/10/12. Boiler HT completed on 11.04.2014. BLU done in
NTPC & Indian Railways)] Mar’15. Chemical cleaning completed on 11.10.15. SBO
U-1 250 08/10* 06/13 03/16(A) 06.01.17(A) completed in 01/16.
10/10* 20.03.16(A) 15.01.17(A) TG: Condenser erection started on 26.2.13. TG erection
12/12** started in 01/14. TG Box-up done in 12/15. TG oil flushing
02/13** completed in 12/15.
U-2 250 02/11* 10/13 03/17(A) 30.08.17(A) Unit-2: COD declared on 10.09.2017; Trial run completed
04/11* 03.04.17(A) 10.09.17(A) on 03.08.17. Commissioned on 03.04.2017.
03/13** Boiler: Boiler erection started in Dec’11. Boiler drum lifting
05/13** completed on 21st Mar’13. Boiler HT completed in 02/15.
U-3 250 08/11* 02/14 31.12.18(A) 10.02.19(A) BLU done in 10/16.
10/11* 23.01.19(A) 26.02.19(A) TG: TG deck casting completed in 04/15. Condenser erection
06/13** started in 05/15. TG erection started in 10/15. TG box-up done
08/13** in 02/17.
U-4 250 02/12* 07/20 - Unit-3: COD Declared on 26.02.2019. Trial run completed
04/12* 06/14 08/20 09/20 on 10.02.19. Commissioned on 23.01.19. Unit Sync on
09/13** 31.12.18
11/13** Boiler: Boiler erection started in 11/11. Boiler drum lifting
(* Org / completed on 10.06.13. Boiler hydro test done on 30.11.16.
** Rev) Trial run completed on 10.02.19.
Original/Latest. Cost : Rs 5352.51 /7998.00 Crores TG: TG erection started in 06/16. TG box-up done in 3/18.
TG Deck floating work started on 28/08/18
Exp. During 2007-08 : Rs 263.19 Crores Unit-4:
2008-09 : Rs 68.37 Crores Boiler: Boiler erection started in 12/12. Boiler drum lifting
2009-10 : Rs 196.17 Crores completed on 16.09.13. Boiler Drainable HT done on
2010-11 : Rs 226.80 Crores 28.04.19.
2011-12 : Rs 487.13 Crores TG: TG columns work in progress. TG erection started in
2012-13 : Rs 1096.68 Crores 01/19.HP&IP turbine erected.
2013-14 : Rs 1300.68 Crores ESP: Pass A&D all columns erected. Frame erection work i/p
2014-15 : Rs 906.04 Crores Balance of Plant:
2015-16 : Rs 927.77 Crores  Chimney: Chimney-1(for U-1&2) ready. Chimney #2 (for
2016-17 : Rs 924.09 Crores U-3&4) shell casting completed. Flue can erection
2017-18 : Rs 705.71 Crores completed for U-3.
2018-19 : Rs 620.79 Crores
 CHP: Coal feeding in progress at both 2A & 2B Side. WT1
2019-20 : Rs 327.92 Crores (02/20)
– Commissioned on 25.12.18. SR-2 Bal foundation civil
Total Expenditure : Rs 8077.37 Crores (02/20) work i/p.
Investment Approval : January’2008.  AHP (Indure): AWPH commissioning u/p. Ash slurry
Sanctioning Authority : BRBCL board accorded investment approval Trench has been completed, Compressor house comm. U-3
Type of fuel : Coal ( Pachra and South Pachra blocks of North Karanpura BAH completed. U-4 BAH welding work
Coalfields) completed.Clinker grinder work is u/p.
Fuel linkage : 5 MTPA (FSA signed on 29.08.13)  CW Pump house: Fore bay raft completed. Pumps (11
Nos) erection completed. CW Pump 5 & 6 trial run taken
Date of Main Plant Order : 23.01.2008 on M/s BHEL(BTG) on 24/08/18
 IDCTs: Order placed in Sep’13. IDCT is FRP type. There
Zero Date : 01/01/2008 are 20 cells in each IDCT. IDCT-1&2 ready. IDCT-3 cells
completed and fan trail taken.. IDCT-4 cells (18/20)
Power Evacuation : ATS work completed and is in charged condition. completed.
 PT plant: Completed in all respect.
 DM plant: DM plant comm. DM lab building civil work is
i/p. CW treatment is i/p. DM Tank -1 & 2 – in service.
 Switchyard:
 FOHS: LDO tanks commissioned. HFO tank work is i/p.

Critical Areas Material supply against open door and poo mobilization by SG agency of BHEL.
AHP critical supplies by Indure.
Balance land issues on 38.47 acres of land.
Reasons for Delay Delay in Civil Works, SG Supplies, Frequent bandhs/Local agitation by villagers
Delay in Land acquisition issues.Physical possession of Banace land fro ESP/VFD area fro U-2, 3&4 received in Jan’16/Nov’16.
Physical possession of 70 acres of critical land is still balance due to court cases, wrong payment in awarded land and ownership
dispute in Mai pALnt, MUW corridor, Ash Dyke and township.
TG civil fronts delayed due to corporate in solvency proceedings by NCLT against MS ERA. Contract now terminated.
MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 36


Sl. No. PROJECT DETAILS Capacity Commissioning Schedule
(MW) Original Actual(A) / Anticiciapted Broad Status
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
4. New Nabinagar STPP, 1980 Unit-1: COD declared on 06.09.19. Trial
Dist.: Aurangabad, Bihar
[NPGCPL- Nabinagar
run completed on 12.07.19. Unit Achieved
Power Generating Co. Full Load on 29.03.2019. Synchronized on
Pvt. Ltd. (JV of NTPC & 14.01.19.
BSPGCL)] Boiler: Boiler erection started on 15th Jun’14 (delay: 05
U-1 660 11/16 05/17 14.01.19(A) 12.07.19(A) months). Hydro test done in 12/16. BLU done in 07/17.
01/17 29.03.19(A) 06.09.19(A) Steam blowing completed on 27.12.17.
TG: Condenser erection started in 09/15. TG erection
U-2 660 05/17 11/17 03/20 - started in 01/16. TG Box-up achieved in 12/16. TG oil
07/17 04/20 06/20 flushing completed in 06/17.TG on barring gear on
14.09.17 .
U-3 660 11/17 05/18 02/21 - ESP: All six passes ATT & electrode erection done.
01/18 04/21 06/21
Orig.Cost/Latest Cost : Rs 13624.02 Cr/15131.67/17304 Crores Unit-2:
Boiler: Boiler erection started on 29.11.14. Hydro test
Exp. During 2008-09 :Rs 0.10 Crores completed. Boiler light up expected in 02/19.
2009-10 :Rs 222.90 Crores TG:TG raft casting completed.TG erection started in
2010-11 :Rs 83.00 Crores 12/16.TG boxed-up in 07/17. TG put on barring gear.TG
2011-12 :Rs 383.92 Crores oil flushing completed in 02/18.
2012-13 :Rs 711.17 Crores ESP: All SIX passes ATT done.
2013-14 :Rs 369.91 Crores
2014-15 :Rs 1534.32 Crores Unit-3:
2015-16 Boiler: Boiler erection started on 29.04.2015.
:Rs 2697.12 Crores
2016-17 TG:TG erection started on 31.07.17. TG box up
:Rs 3070.00 Crores
2017-18 completed in 06/18.condenser erection started in 06/17.
2018-19 :Rs 2265.00 Crores
Rs 1786.00 Crores ESP: 7380/9253 work completed.
2019-20 BOPs:
Rs 1111.27 Crores
Cum. Exp up to Rs 14408.86 Crores (02/20)  Chimney: Chimney-1(Unit-1) & Chimney-2 (Unit-
2&3) shell casting completed. Flue can erection
Investment Approval : 31.01.2013(Jan’13) completed for U-1, 2 & 3.Both chimneys are for All of
Sanctioning Authority : NTPC Board the three units.
Type of fuel/FSA : Coal. Coal linkage from CCL for 7.03Million Ton Per Annum.  CHP: Order has been placed on M/s TRF Ltd in
For commissioning coal 2 Lakh MT MOU has been signed. March’13. Coal Transportation- 2nos NPGC Loco Trial
FSA will be signed after unit commissioning as per guideline. Run from Warf Wall to R&D and R&D yard to Inside
plant completed on 25.05.18
Zero Date : 31.01.2013
Rail laying 6.5 km completed.
Date of Main Plant Order TG –M/s ALSTOM-Bharat Forge on 31.03.2013. WT-1&3 commissioned.WT-2 hydraulic work is in
SG-Awarded to M/s BHEL on 31.01.2013. progress.
Crusher house, Stacker cum reclaimer, Crusher house
Financial Closure loan from REC. Debt, equity ratio is 70:30. NOC from BSPCB work has been completed.
received on 08.04.2011  AHP: U-1 : Fly Ash water pump house work
Main plant order Boiler erection agency: U-1&3 – Powermech and U-2 is completed. BASPH motors no load trail run
Indwell. completed, HCSD pump trail run completed. Bottom
MOEF clearance received in Dec 2010. Mega status received in Apr’09. ash hopper U#2 erection work in progress. HCSD silo
and other work is u/p. Pump house is common for all
Power Purchase Agreement :- ( Bihar/BSEB:-1552.5 MW signed on21.01.10, Jharkhand:- 60 three units.
MW signed on 01.12.10, Sikkim :-10 MW signed on 28.09.10,UP:-209 MW signed on  DM plant: Order placed on M/s Thermax in Jan’14.
07.04.18, Un-Allocated - 148.5MW) All the three streams charged manually. Work for two
Power Evacuation System: Being Executed by PGCIL. 400 kV One line from NPGC to GAYA streams completed for auto mode.
is charged. Second line 400 kV NPGC to Patna - work under progress  CW pump house: All three units trial is completed for
2/2 each unit.. RWPH 2/3PT pump comm. CWPH 2/2
Coal Transportation- 2nos NPGC Loco Trial Run from Warf motors trail done.
Wall to R&D and R&D yard to Inside plant completed on  CTs: Order placed on M/s Fans.
25.05.18 CT # 1A:-commissioned.
Rail laying 6.5 km completed. CT # 1B:- commissioned.
CT # 2A:- Piping work completed. Equip erection is
i/p.
CT # 2B:- Civil work completed. Piping work i/p.
CT # 3A:-16 /16 Deck Slab completed.
CT # 3B:-RCC of basin slab completed.Column
casting is i/p.
 Switchyard: 132kV &.400kV switchyard
charged..Power evacuation line(400kV) nabinagar-
Gaya line charged.ICT1& 2 charged.
 U-2 132 kV cable laying for station transformer is u/p.
FGD: Under bulk tendering process by
NTPC ltd. BOD in June 2018.
Critical Areas Poor worl progress in ASh handing and CHP milestones acquisition of balalnce land fro makeup water, railway siding and ash
dyke.
Reasons for Delay Dela in acquisition of land. Acquisition and physical possession of 42 acre land is till balalnce due to court cases/ownership
dispute etc. in railway siding, MUW Corridor, Outfall drain & Ash dyke.
MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 37


Sl. Capacity Commissioning Schedule
No. PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail Syn. Trail run
Com run Com COD
COD
Central Sector
5. Lara STPP, 1600 Unit-1: COD – 01.10.2019. Unit completed 72 hr.
Dist: Raigarh, full load trial on 02.03.2019, Commissioned on
Chhattisgarh
22.03.18. Synchronized on oil on 09.09.17.
(NTPC Ltd.) U-1 800 09/16 03/17 09.09.17(A) 02.03.19(A)
Boiler: Boiler erection started on 23/12/13. Boiler Hydro test
11/16 22.03.18(A) 01.10.19 (A)
done on 12/15.BLU done in 01/17.SBO completion done in
-
05/17.
U-2 800 03/17 09/17 14.02.20(A) 08/20
TG: Condenser erection started on 29.05.2015 and TG
05/17 07/20
erection started in 08/15.TG box-up done in 02/17. TG oil
flushing completed in 07/17.
Investment Approval : 07.11.2012 ESP: 05 out of 06 passes of ESP erection completed.
Sanctioning Authority : NTPC Board
Orig.Est. cost : Rs 11846.00 Crores Unit-2: Synchronized on 14.02.2020
: Rs 12739.82 Crores Boiler: Boiler erection started in 04/14. Boiler Hydro test
Latest.Est. Cost
done on 26.04.16. BLU completed on 24.12.18. MS, CRH,
Exp.During 2011-12 : Rs 280.0 Crores
HRH hydro test completed. Boiler ready for steam blowing.
2012-13 : Rs 77 3.00 Crores
2013-14 : Rs 535.00 Crores
TG: Condenser erection started in 01/16. TG deck casting
2014-15 : Rs 2147.00 Crores
started on 26.05.16. TG erection started in 02/17. TG Box-up
2015-16 : Rs 2383.00 Crores
completed in 03/19. Chemical cleaning for feed water system
2016-17 : Rs 1900.00 Crores
completed, MDBFP trial run done. TG boxup in Marc h 2019.
2017-18 : Rs.1512.00 Crores
ESP: ESP structural erection completed. ESP hoppers erection
2018-19 : Rs 1988.29 Crores
completed in 3rd pass and hopper erection works are in
2019-20 Rs 1256.53 Crores
progress in 4th pass.
Cum Exp : Rs 12964.82 Crores (up to 2/20)
Type of fuel : Coal BOPs:
Fuel linkage Chimney: U#1& U#2 work completed
CHP: Both streams commissioned from TH to Bunker for
Date of Main Plant SG- M/s Doosan, in Dec’12
U#1. Work for U#2 is in progress. Wagon tippler trial
Order (BTG) TG - M/s BGR Hitachi in Dec’12
operation completed. Stacker reclaimer work
Zero Date 13.12.2012
commissioned.MGR priority line commissioned. Wagon
Power Evacuation There are two nos. of D/c evacuation lines from Lara unloading started.
switchyard, each line is capable of evacuating around AHP: Unit#1 system commissioned and ash discharged up to
1000 MW. One line is going to Champa and the other ash dyke. Erection of Unit#2: Fly ash system, HCSD silo
going to Kotra. Tower erection, stringing of one line (balance 1nos), ASPH (3rd stream) erection is in progress.
near to the plant is completed and for the other line However, due to poor financial condition of agency, balance
stringing is to be done. supplies for Common Systems &Unit#2 are criticallydelayed.
Poor mobilization by agency affecting the progress.
Ash dyke: Ash slurry lines pedestals work started. Excavation
and bund raising works are in progress.
PT Plant: Both streams are commissioned.
DM Plant: Both streams for DM water generation are ready.
CWPs: CW pump house is of open type in this project. U-1:
Stream Commissioned, U-2: pump comm done.
IDCT: Unit-1 & 2 circuit is commissioned.
Switchyard: Charged.

FGD: FGD is awarded to L&T on 31.07.18.


Chimney &absorber, gypsum dewatering, gypsum shed
civil foundation is i/p. Chimney flue can i/p.

Critical Areas  Support of State Govt. is required for early possession/ acquisition of balance land for MGR route
 Support of Railways required for CRS Sanction for insertion of turnout & completion of associated S&T works at
Kotarlia station
 Completion of balance work of Railway siding.
 Support required from WRD for Closing of Barrage gate at saradih barrage (Mahanadi river) for water impounding in
make up water channel.
Reasons for Delay Delay in readiness of Railway siding due to land acquisition, ROW issue in 18 nos foundation of MU Water
66kVtransmission line coprridors is hampering process.
Delay in supplies of Ash Handling Material.

MPS 30.03.2020

TPM_Broad Status Report (January-February’2020) 38


Sl. Capacity Commissioning Schedule
No. PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As
now Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
6. North Karanpura 1980 Unit-1:
STPP, Dist.Chatra, Boiler: Boiler erection started in 04/16. Hydro test (Non
Jharkhand NTPC ltd drainable) completed in 01/19.
Unit-1 660 12/17 04/19 09/20 - TG: TG civil work started in 04/16, TG erection started in
02/18 12/20 03/21 11/17.Condensor erction started in 11/18. TG Box up in 08/19.
02/19*
02/19*
Unit-2 660 06/18 10/19 03/21 -
08/18 06/21 09/21 Unit-2:
08/19* Boiler: Boiler erection started in 07/16.
08/19* TG: TG erection started in 01/18. Box up expected in 08/19
Unit-3 660 12/18 04/20 09/21 -
02/19 11/21 03/22 Unit-3:
02/20* Boiler: Boiler erection started in 06/17.
02/20*
* Revised Schedule. TG: TG civil work started in 06/16.
Original /Latest Cost : Rs 14366.58 / 15164.05Crores BOP:
Exped. during2013-14 : Rs. 1530.00 Crores Chimney: U#1 Flue can Erection completed.U#2 ,Flue can
2014-15 : Rs. 525.00 Crores erection done ,U#3 Chimney Shell: Beam erection in progress
2015-16 : Rs 573.00 Crores CHP: Civil & Structural works under progress
2016-17 : Rs 2208.00 Crores AHP: Civil & Structural works under progress
2017-18 : Rs 2042.00 Crores PT/DM Plant: Civil works on clarifier in progress. Tank
2018-19 : Rs.1699.13 Crores foundations completed.
2019-20 Rs 1288.04 Crores Cooling Towers: Supplies under progress.
Cumulative Exp : Rs. 10035.08 Crores (up to 02/20) Fuel Oil System: Civil work completed, Mech erection of both
Type of fuel : Coal tank in progress.
Investment. approval Feb 2014 Switchyard: Structural Works under progress.
Date of Main Plant EPC placed on BHEL (except external CHP,
Order MUW system and Ash dyke) on 28.02.14. Main FGD: Awarded to BHEL on 31.07.18. Civil work in
plant civil works awarded on BHEL progress.

Amendment to EC issued by MOEF on 31.10.2014 for use of Air Cooled


Condenser system (one ACC for each unit).

Critical Areas Worl of EPC Pkg (BHEL) needs to be expedited.


Forest Clearance in ATS –NK Chandwa line to be expedited.
Support of State Govt of Jharkhand is required for following:
1. Acquisition / transfer/ possession of balance land for Ash Dyke and Reservoir
2. Acquisition of Land by CCL for external CHP.
3. Early completion of Road Widening and strengthening of SH-7 from Hazaribagh to Bijupara. It is being done on
deposit basis by RCD. The road diversion in project area needs to be completed on priority.

Reasons for Delay Delay in start of Civil works due to land acquisition issues. Delay in BHEL supplies related to boiler foundation. Delay
in land handover by NTPC to BHEL due to change in main plant area location change in plot plan. Delay in award of
ACC package by BHEL.
Delay in reaward of sub agency for U-2.

MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 39


Sl. No. Capacity Commissioning Schedule
PROJECT (MW) Broad Status
Original Actual(A) / As now
DETAILS
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
7. Kudgi STPP ST-I, 2400 Unit-1: COD achieved on 31.07.2017. Commissioned
Dist: Bijapur, on 25.12.2016.
Karnataka, NTPC Boiler: Boiler erection started on 04.05.13. Boiler hydro test done in
Ltd. 01/15. BLU done in 12/15. SBO completed on 12.06.16.
U-1 800 09/15 04/16 12/16 - TG: Condenser erection started in 02/14. TG erection started in
12/15 25.12.16(A) 31.07.17(A) Jun’14. TG box-up done on 24.04.2015. TG oil flushing started in
U-2 800 03/16 10/16 03/17 - Jun’15 and completed in 11/15. TG put on barring gear in 12/15.
06/16 22.03.17(A) 31.12.17(A) Full Load achieved on 25.12.2016.

800 09/16 04/17 08/17(A) -


U-3 12/16 12.03.18(A) - Unit-2: COD achieved on 31.12.2017. Commissioned
Orig.Est. cost : Rs 15166.19 lakhs Crores on 22.03.2017.
: Rs 15166.19 lakhs Crores Boiler: Boiler erection commenced on 20.08.13. Boiler hydro test
Latest.Est. Cost done in 08/15. BLU done in 10/16.SBO completion achieved in
01/17.
Exp.During 2011-12 : Rs 192.00 Crores TG: Condenser erection started on 14.11.14.TG erection started in
2012-13 : Rs 1304.00 Crores 03/15. TG box-up done in 01/16. TG oil flushing done in 11/16
2013-14 : Rs 2277.00 Crores
2014-15 : Rs 4047.00. Crores Unit-3: Commissioned on 12.03.2018. Synchronized in
2015-16 : Rs 2800.00 Crores
2016-17 : Rs 2560.00 Crores 08/17.
2017-18 : Rs. 2098..00 Crores (2/18) Boiler: Boiler erection started in 09/13. Boiler Hydro test done in
03/16. BLU done in 04/17. SBO completed in 06/17. Unit
Cum Exp :Rs 1508.00 Crores (up to 2/18) synchronized on oil on 22.08.17. Full load achieved on 12th
Invest. Approval :Dec’2011. March 18.
Sanctioning : NTPC Board TG: Condenser & TG erection started in 09/15. TG box-up done in
Authority 01/17.TG oil Flushing done in 01/17.Turbine rolled.
Type of fuel : Coal
Coal block Bhalumuda Captive coal block BOPs:
Chimney: Chimney-1 (for unit-1) & Chimney-2 (for unit-2&3)
Zero Date 25.01.2012
Shell casting works completed.
Date of Main Plant SG: Feb’12, M/s Doosan Heavy Ind., Korea
Order TG: Feb’12 on M/s Toshiba
CHP: The progress of CHP is slow. Only structural work of transfer
points, conveyor galleries and crusher house etc. are in progress.
Civil works have been started in WT4 & WT5. Erection of
mechanical equipment are yet to be started. Requirement for U#1 &
U#2 services completed and U#3 portion works in progress. M/s.
Energo contract terminated in Oct 17.

AHP: Order placed on McNally Bharat in Aug’13.


Ash Dyke package awarded to M/s Sunil Hitech in 09/15.
Requirement for U#1 & U#2 services completed and U#3 portion
works in progress
CW system: Out of total 7 CW pumps, 2 CW pumps have been
commissioned- to meet requirement of unit- 1. Another 2 pumps
have been installed and their motors are available at site. Pump &
motors for last 3 CWPs are available at site and these are yet to be
installed.
IDCTs: Requirement for U#1 & U#2 services completed and U#3:
IDCT #3 B & IDCT #3A charged.

FGD: Not Awarded

Critical Areas Land acquisition for Railway siding, ash pipe corridor, raw water reservoir. Poor progress of main plant civil works
Readiness of railway siding.
Reasons for Delay Stoppage of work on account of NGT order–work stopped from 17.03.2014 to 01.04.2014. Work stoppage due to agitation
against the project (05.07.2014 to 22.07.2014). Delay in award of SG civil works. Delay in TG erection start. Unrest and
violent agitation in 07/14 with exodus of manpower. Delay in supply of generator stator of Unit #2 &3 by M/s Toshiba.
Supply of material against CHP-Energo, AHP- MBECL, ESP-L&T and FDPS & slow progress.

MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 40


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
8. Solapur STPP, 1320 Unit-1: COD achieved on 25.09.2017.
Dist: Solapur, Commissioned on 07.04.2017.
Maharashtra, NTPC Ltd. Boiler: Boiler erection started on 07th May’13.
U-1 660 03/16 07/16 03/17(A) - Boiler hydro test done in 12/15. BLU done on
05/16 0 07.04.17(A) 25.09.17(A) 21.08.16. SBO completed in 03/17.
U-2 660 09/16 01/17 02/19(A) 21.03.19(A) TG: TG erection started on 04.07.14. TG box-up
11/16 03/19(A) 30.03.19(A) completed in 07/15. TG oil flushing completed in
Investment Approval : March’12 11/15.
Sanctioning Authority : NTPC Board
Orig.Est. cost : Rs 9395.18 Crores
Unit-2: COD Declared on 30.03.2019.
Latest.Est. Cost : Rs 10154.27 Crores Trail run completed on 21.03.2019. Taken
Exp.During 2011-12 : Rs 95.00 Crores into capacity addition on 29.03.2019.
2012-13 : Rs 1142.00 Crores Boiler: Boiler erection started on 29/09/13.Boiler
2013-14 : Rs 983.00 Crores hydro test completed in 09/18. BLU done in
2014-15 : Rs 2128.00 Crores 11/18.Steam blowing completed in 01/19.
2015-16 : Rs 166800 Crores TG: TG erection started on 15th May’15. TG
2016-17 : Rs 1326.00 Crores Boxed-up in 08/16.TG oil flushing completed in
2017-18 : Rs. 925.00 Crores 05/17. TG on barring gear since 05/17.
2018-19 : Rs. 515.07 Crores (2/19)
Cum Exp :Rs 9131.59 Crores (up to (2/19) BOPs:
Type of fuel : Coal Chimney: Chimney shell casting completed. Flue
can have erected for both the units.
Date of Main Plant Order SG : 06.04.12 on M/s BGR Energy Systems Ltd – Hitachi CHP: Priority area completed. Balance works in
(BTG) TG : 23.04.12 on M/s Alstom-Bharat Forge progress.
AHP:Ash dyke Priority area completed. Balance
19.03.2012 work in progress. U-2 erection work i/p.
Zero date DM/PT Plant: completed.
CW System: Work completed.
IDCTs: completed.
Switchyard: 400& 132kV line charged.

FGD: FGD is awarded to GE on 31.07.18.


Geotech investigation is completed. Civil
drag submission i/p.

Critical Areas Delay in Laying of Make Up Water Pipe line due to No Right of Use Act in Maharashtra. Delay in SG supplies by
BGR-Hitachi and resource augmentation. Resources augmentation by M/s Indure, for CHP & AHP packages.
Major damage in Pressure parts and support structure (9nos hdrs, buckstays, springs, etc) and delay in rectification
and replacement by BGR. Rectification work started in May -17 but work progress is very slow. Expediting Supply
of U#2 Boiler components & BOIs by BGR Energy- Systems Ltd. & Hitachi Power Europe, Supply of Structures &
BOIs/SMIs by M/s. Indure for AHP and CHP Packages. Supply of FDA and inert gas nozzles & detectors by M/s
Sureland for FDPS Package. Due to resistance from farmers, seeking higher compensation than as recommended by
state revenue/agriculture dept., the Completion of MUWPH 132 KV line is getting delayed.
Reasons for Delay Delay in steam generator Engineering & supply by BGR due to non-settlement of QSGM between BGR and
Hitachi. Delay in repair & replacement of damaged pressure parts due to accident.

MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 41


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
9. Gadarwara STPP, St–I, 1600 Unit-1: COD - 01.06.19. Trail run
Dist: Narsinghpur completed on 23.11.18. Taken into
M.P NTPC Ltd.
cap addition on 29.03.2019. Full
U-1 800 12/16 07/17 30.08.18(A) 23.11.18(A)
03/17 13.10.18(A) 01.06.19(A) load is achieved on 13.10.18.
U-2 800 06/17 01/18 06/20 - Synchronization on 30.08.18
09/17 07/20 08/20 Boiler: Boiler erection started in 06/14. HT done in
Investment Approval : 22.02.2013 12/16. BLU achieved in 04/17. SBO completed in
July‘17.
Sanctioning Authority : NTPC Board ESP: All six pass erection completed and emitter’s
Orig.Est. cost : Rs 11638.55 Crores erection is in progress. Hopper erection completed.
: Rs 12865.92 Crores TG: Condenser erection started in 12/15. TG erection
Latest.Est. Cost started in 04/16. TG box-up completed in 08/17. TG
Exp.During 2012-13 : Rs 655.00 Crores oil flushing completed in 09/17.
2013-14 : Rs 463.00 Crores
2014-15 : Rs 1614.00 Crores Unit-2:
2015-16 : Rs 2749.00 Crores Boiler: Boiler erection started in 30th Nov’14. Pressure
2016-17 : Rs 1988.00 Crores part erection in progress. HT completed in 11/17. BLU
2017-18 : Rs 1556.00 Crores completed on 31.12.18
2018-19 : Rs 1914.61 Crores ESP: Pass A, B & C erection completed and
2019-20 Rs 918.23 Crores foundation work of D, E & F passes completed.
Cumulative Exp : Rs 12571.63 Crores ( upto 02/20) TG: TG erection started in 06/17. TG Box-up
Type of fuel : Coal completed in 11/18. TG oil flushing completed in
03/19. TG put on barring gear on 31.03.19.
Fuel linkage
Date of Main Plant Order in 03/2013 M/s BHEL, Main plant & offsite civil works BOPs:
(BTG) order placed in 08/13. Chimney: Unit-1 work done. Unit-2 flue can erection
Zero Date 22.03.13 done. Mini shell concreting achieved 275 m.
CHP: .Both stream from WT to Bunker commn. for
U-1, 2/3 nos WT commn. Both stacker/reclaimer
commissioned.
AHP: Silos piling work completed. HCSD pump
foundation completed. U-1 Bottom ash evacuation
with 2nos ash slurry series completed up to ash dyke.
Fly ash evacuation for all 6 passes completed up to
HCSD silo & up to Dyke. U-2 : BH erection under
progress.
PT Plant: All three CW streams commissioned.
DM Plant: Both stream of DM water commissioned.
CWPs: All 5nos CW pumps erection done
IDCTs: CT-1: All 28 nos fan erection done. CT-1
taken into service.
CT-2: Trail completed.
Switch Yard: 132KV tower erection completed and
charged.Both 765KV Jabalpur & Waroraline line
charged.
FGD: FGD is awarded to ISGEC on
18.09.18.Drawing approval in progress.
Absorber & chimney pilling under progress

Critical Areas  Possession of 2.91acres part land for Crossing Station of Railway Siding.
 Support of Railways is required for early completion of works of Crossing station.
 Slow Progress of AHP agency (M/s Indure) due to inadequate manpower mobilization & repeated defaults in
material supplies. Comfort letters issued by site for supplies of BOIs.
Reasons for Delay  Work stopped for 56 daysin 2014 due to agitation by villagers demanding additional compensation for already
acquired land.
 In may 2016, work was stopped for two and half day from 18.05.16 due to labour strike and one more day was lost
due to death of labour on 27.05.2016
 Work stopped for 56 days in 2017-18 (22.12.2017 to 15.02.2018) due to agitation by PAP’s under the banner of
“Kisan Mazdoor Sangh” with their major demand for permanent employment in NTPC and some demands related
to local development work as part of R&R plan.
MPS 30.03.2020

TPM_Broad Status Report (January-February’2020) 42


Sl. No. Capacity Commissioning Schedule
PROJECT (MW) Broad Status
Original Actual(A) / As now
DETAILS
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
10. Khargone STPP, 1320 Unit-1:Unit achieved COD on
Dist.Khargone, 01.02.2020.Unit completed 72 hr. full
M.P. (NTPC Ltd.)
29.09.19(A)
load trial on 29.09.2019. Unit
Unit-1 660 01/19 07/19 27.06.19(A)
03/19 30.08.19(A) 01/02/20(A) commissioned on 30.08.2019.
Unit-2 660 07/19 01/20 31.12.19(A) 24.03 20 (A) Synchrinisation on 27.06.2019.
09/19 19.01.20(A) 04.04.20(A) Boiler: Boiler erection started in 04/16. Boiler Hydro
Original/Latest Cost : Rs 9870.51/11148.86 Crores test done on 24.6.18.BLU completed on 29.12.18.
Steam blowing completed in 05/19.
Exp. During 2014- : Rs. 634.00 Crores TG: TG erection started in 06/17. TG Box-up done on
15 : Rs. 902.00 Crores 29.05.18. TG oil flushing completed on 27.01.19. TG
2015- : Rs. 1124.00 Crores put on barring gear in 01/19.
16 : Rs. 2439.00 Crores
2016-17 : Rs 2513.04 Crores Unit-2: Unit achieved COD on
2017-18 Rs 1477.97 Crores
2018-19 04.04.2020.Unit completed 72 hr. full load
2019-20 : Rs. 1884.117 Crores (upto 02/2020) trial on 24.03.2020, Full Load on 19.01.20
Cumulative Exp : Rs. 9568.44 Crores (up to 02/20) and Synchrinisation on 31.12.2019.

Type of fuel : Coal Boiler: Boiler erection started in 09/16.Pressure part


Zero date 31.03.2015 erection in progress. Boiler Hydro test completed on 30/
Date of Main Plant EPC On L&T on 31.03.2015 09/18. BLU completed on 11/18. SBO completed on
Order 12/19.
TG: TG erection started in 12/17. TG Box-up done on
27.11.18. TG put on BG on 29.10.2019.
ESP: pass E air leak test successfully completed on
16.08.18. pass F air leak test successfully completed on
12.09.18.

BOPs:
Chimney: Shell completed and flue can erection of U-2
completed in 07/19.
CHP: M/s. L&T. 8848/9386 MT CHP structure
completed. WT-1 Tippling testing along with coal done
on 27.05.2019.
AHP: AHP structure 3318/3991 MT completed AHP
equip. erection 1219/1633 MT completed. AHP piping
work in u/p. HCSD recirculating pump C2 trail
completed on 24.07.19
Cooling Tower: IDCT-1- RCC Super structure-
completed, IDCT-2- RCC super structure is i/p.
CW system: CW piping U-2 erection 1300/2222mtr
done.
PT plant: Completed.
DM plant: Fully Commissioned
FOHS: LDO tanks-1&2 completed.
Switchyard: 400 kV GIS charged through LILO
system on 06.07.18. 66kV line charged in 05/19.

FGD: Awarded to L&T on 31.07.2018.


Chimney-1 shell shell completed on 24.12.19.
Chimney-2 shell construction started..
Limestone Building and equipment
foundation Work in Progress
Limestone handling system exacavation
work completed. Gypsum dewatering
building-upto +3.95 work completed.
Absorber RCC work in progress.

Critical Areas Power evacuation oline of khargone has not completed yet.
Support of railway is required for expeditious completion of OHE works from Nimarkhedi to plant.

Reasons for Delay Coal Constraints and less manpower resources

MPS 30.03.2020
TPM_Broad Status Report (January-February’2020) 43
Sl. Capacity Commissioning Schedule
No. PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
11. Darlipalli STPP ST-I, 1600 Unit-1: COD declaredin 01.03.20 .72 hrs
Dist. Sundergarh, trial run completed on 31.12.19, Full load
Odisha (NTPC Ltd.)
on 02.10.19 and synchronized on
U-1 800 12/17 04/18 04.04.19(A) 30.12.19(A)
04.04.2019.
02/18 02.10.19(A) 01.03.20(A)
U-2 800 04/18 08/18 07/20 - Boiler: Boiler erection started in 04/15. HT
06/18 08/20 09/20 completed in 8/17. BLU completed in 10/18. Steam
Investment. approval blowing completed in 02/19.
Orig.Est. cost : Rs 12532.44 Crores. TG: Condenser erection started in 12/15. TG
Latest. Est. Cost : Rs 13740.53 Crores. (Jan 2014) erection started in 05/16.TG box-up done in
11/17.TG oil flushing done in 11/18.TG put on
Exp. During 2013-14 :Rs. 951.00 Crores. barring gear on 12/18.
2014-15 :Rs 1457.00 Crores. ESP: All passes completed.
2015-16 :Rs 1417.00 Crores.
2016-17 :Rs 2384.00 Crores. Unit-2:
2017-18 :Rs 2100.00 Crores. Boiler: Boiler erection started in 07/15. HT done in
2018-19 :Rs 1531.66 Crores. 03/18. BLU in OCt-2019
2019-20 Rs 991.99 Crores. TG: Condenser erection started in 09/16. TG
Rs. 1156.00 Crores (upto 02/20) erection started in 03/17. TG BOX up in 02/19. TG
Cumulative Exp :Rs 10257.63 Crores (up to 2/20) oil flushing completed in Jan 2020.
MOEF clearance ESP: 6 passes are completed.
Type of fuel : Coal
Date of Main Plant Order SG. Awarded in 02/14 on M/s BHEL.
BOPs:
Chimney: raft completed.
TG awarded in 02/14 on M/s Toshiba
CHP: Order placed on Tata projects in Feb’15. Civil
work in Track hopper, Wagon tippler, erection work
in TPs, Crusher house, stacker reclaimer in progress.
Belt laying commenced.
DPR & Coal Trans. : 13 km rail laying (priority
line)competed. Coal is transported by MGR to
Project site
AHP: Order placed on Indure in Oct’14. Structural
work at bottom ash hopper erection, ASPH and
AWPH foundations completed. Supply of material
from Indure is pending.
Ash Dyke: Lagoon1, 2 and OFL is completed. and
work in Lagoon 3 under progress.
PT/DM Plant: Order for water treatment plant
placed on Triveni Engineering in Feb’15. One stream
for DM water generation is ready, one stream
clarifier ready. Completion work is in progress.
CWPs: Order for CW equipment placed on Kirloskar
Brothers Ltd in Oct’14. Equipment supplies done.
Work in progress. RW PH & CWPH completed;
makeup PH work balance.
CT: Order placed on L&T, ECC in Dec’14. Unit 1
all 32 cells mech& civil work completed.32 cells
charged erection under progress & U- 2 Cooling
tower 16 cells comkpleted bala;nce civil work in
progress.
Switchyard: 765kV one bay and 132kV switchyard
charged for startup power.

FGD: FGD is awarded to L&T on


18.09.18. site mobilization being done.
Front handed over ,work in progress
fro Unit-1 Absorber, Electrical & CI
building, U-2 chimney etc.
Critical Areas Balance RoW for 132 kV transmission line (Approx. 300 towers) for Make Up Water pump house.
2. Acquisition/possession of balance land for Railway siding and Outfall drain.
Reasons for Delay Delay due ot readiness of AHP(Indure), MGR( IRCON) civil work(Toshiba)
Non availability of land in railway siding and make up water corridor.
Delay in Completion of CW system fro TG Deck floating.
MPS 30.03.2020

TPM_Broad Status Report (January-February’2020) 44


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
12. Telangana TPP (Ph-I), 1600 Unit-1:
Dist. Karim Nagar
Telangana NTPC Ltd. Boiler: Boiler erection started in 12/17.8th Tier
Unit-1 800 10/19 05/20 01/21 - erection in progress. pressure parts erection u/p.
01/20 02/21 03/21 TG: Condenser erection started in 07/18. TG erection
Unit-2 800 05/20 11/20 12/20 - started in 08/18.TG box up completed. Oil flushing
07/20 01/21 06/21 will start in 01/20.
Orig.Est. cost : Rs 10599.00 Crores ESP: erection in 6 passes completed.
Latest.Est. Cost : Rs 11811.00 Crores
Unit-2:
Exp. During 2015-16 : Rs. 6.00 Crores
Boiler: Boiler erection started in 12/17. 4th Tier
2016-17 : Rs 807.00 Crores
erection in progress. Pressure parts erection u/p.
2017-18 : Rs. 1035.00 Crores
2018-19 : Rs. 2522.06 Crores
TG: Condenser erection start expected in 02/19. TG
2019-20 Rs 2055.05 Crores (upto 02/20)
erection start expected in 03/19
ESP: erection in 6 passes in progress.
Cumulative Exp : Rs. 6457.92 Crores (up to 02/20)
Type of fuel Coal
Date of Main Plant: SG on BHEL BOPs:
Order: TG on Alstom-Bharatforge on 05.02.16. Chimney: shell completed up to 45 m.., U-2
Zero date 31.03.2015 chimney shell casting completed on 13.02.19.
MOEF clearance
CHP: TPs and Conveyor foundation in progress.
Track hopper: Wall lift work in progress. WT#1,2 and
3 –Raft completed, Wall RCC works in progress.
Track Hopper: 5/7 hopper casting done. WT-1,2 and 3
– RCC works in progress. Crusher House erectionn
i/p.
CT: CT#1 footing casting in progress.
WTP area-DM Tank & CW clarifier excavation RCC
civil works completed. Trail operation will start after
start up power.

AHP:
Ash Dyke: Protective bund and reservoir earth work
in progress.

CWPH: CW PH & RW PH- Operating floor casting


done. Mechanical erection commenced. Balance CW
duct civil and fabrication/erection works in progress.
DM Plant: WPT area – DM tank erection started &
CW clarifier mechanical works in progress.
Switchyard: GIS equipment erection commenced
on 25.07.19. and is in advance stage.

FGD: Awarded to M/s GE On04.01.18.


Foundation work in u/p. Absorber
foundation completed & tank Erection i/p.
FGD Control room building civil work i/p.
Lime stone crusher building civil work i/p.
GYPsum deatering building & ECr building RCC
work i/p.

Critical Areas During last CRM held with BHEL on 28/9/17, BHEL confirmed primary structure dispatch commences only from
Dec 17.

Reasons for Delay Change in boiler design w.r.t. new environmental norms, Delay in BHEL supplies.
Slow progress of work by M/s GE power.

MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 45


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
13. Meja STPP, 1320 Unit-1: Commissionedon 31.03.18,
Dist:Allahabad, U.P.
[MUNPL- Meja Urja Nigam
Synchronized on 23.08.17.
Pvt. Ltd. (JV of NTPC &
UPRVUNL)] Boiler: Boiler erection started on 11th Jun’13. Boiler hydro
U-1 660 04/16 08/16 23.08.17(A) - test done on 27.05.16. BLU achieved in 03/17. SBO
06/16 31.3.18(A) - completed in 07/17.
TG: TG erection started in 09/14. TG box-up done in
U-2 660 10/16 02/17 07/19 - 09/15. TG oil flushing completion done in 11/16.
12/16 08/19 08/19
Original/Latest Cost : Rs 10821.00 /10821.00/12176.28 Crores Unit-2:
Boiler: Boiler erection started on 20.06.14 (Delay 06
Exp.During 2008-09 :Rs 54.01 Crores months). All mill and bunker foundations completed.
2009-10 :Rs 41.51 Crores SBO completed on 18.01.2020
2010-11 :Rs 61.43 Crores TG: TG Deck casting completed. Condenser erection
2011-12 :Rs 65.42 Crores started in 11/15. TG erection started on 30/01/18.
2012-13 :Rs 862.87 Crores ESP: U #1-All Pass ATT & purge system piping done.
2013-14 :Rs 565.90 Crores Insulation & cladding works for A,B & C pass completed.
2014-15 :Rs 1624.20 Crores 62/96 rectifier transformer filtration done. A,B pass field
2015-16 test charged. U#2- Erection commenced on 19.02.15
:Rs 1803.86 Crores
2016-17
:Rs 715.83 Crores
2017-18
2018-19 :Rs 2005.97 Crores
Rs 848.00 Crores BOPs:
2019-20 Chimney: Chimney shell concreting completed. Flue can
Rs 741 Crores
erection & Mini cell done completed, Outer platform RCC
Cumulative Exp. :Rs 10182 Crores (Up to 01/20)
done. Painting works done. Wind stack fixing -6/39 done,
Type of fuel : Coal Lift erected.
Zero Date 30.04.2012 CHP: Order placed on BHEL-ISG in Apr’12. Structure
erection of TP-1,2,3,4,5,11 &12 completed and CRUSHER
Sanctioning Authority : NTPC Board house in progress. WT-B: Flushing completed of WT-2
WT-A: Oil flushing -Piping work i/p.
Date of Main Plant Order SG: 30.04.12 on M/s BGR Energy Systems, Chennai. AHP: Order placed on Techpro in 07/12. Ash Water P/H.
(BTG) TG: 01.05.12 on M/s Toshiba Corporation, Japan. Pumps foundations completed. Ash Slurry P/H- -RCC &
Bricks works completed. Pumps foundations completed.
MOE&F clearance available on 10.01.11. Environment Clearance for Project extended up to Pump erection started. Ash disposal pipe laying in side
31.03.2019 by MOEF on 30.08.2018 plant- -Pipe Laying started in May’16 inside plant. 25 Km
pipe supplied. Inside pipe laying done
CWPs: Order placed on Flow more in 12/14. Gantry
commissioned. Two no’s pump commissioned. 3rd
Erection in progress.
IDCTs: Order placed on Fans A S in May’12. Aux CT-
2/3 Fans commissioned. Balance One fan ready for
commissioning. CT 1A: All 16 fans commissioned. CT 1B:
6/16 no’s fan commissioned, Balance cabling works in
progress. Civil works completed, fill erection done, motor
& gear box placed on fdns. Painting & drift eliminators
works competed. CT 2B: Civil works completed, Hot
water pipe risers erection in progress. CT 2A: Civil works-
All fan deck slab done & 14/16 fan stack rcc completed.
Railway siding: Order placed on M/s RITES. This work is
split in to 07 no of packages and all packages are awarded.
Further, works are in progress.
Switchyard: Completed. Startup Power charged by
Allahabad line-1 on 12.11.16
FGD: Bid opened and under evaluation.
Balance land for railway siding-Village Lehdi 22.12 acres for laying 1.8 km track & Other 0.75 KM in assorted patches in
Critical Areas different villages. Various Clearances from Indian Railway and DFCIL to be taken by Rites at the earliest: ·Clearance from
Railways for Connection of Meja Siding with IR Tracks at Meja and Unchdih. Approval of Girder Launching Scheme for
ROR & Block for launching from Railways. Approval of General Arrangement Drawing (GAD) of Rail Over Rail Bridge
(ROR) and ViaDuct from Railways. ·Approval of Girder Launching Scheme for ROR & Block for launching from
Railways. Shifting of UPTCL and Power Grid Transmission lines 4 nos each 132/400 KV.
Reasons for Delay Delay in supply of boiler material by M/s BGR due to non-settlement of QSGM between BGR and Hitachi. Slow progress
of main plant civil works. Dealy in AHPM/s Techpro), physical possession of 0.14 acre land for rilway siding. Poor
performance o f amin palnt civil work agency(M/s IVRCL)
MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 46


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
14 Tanda-II STPP, 1320 Unit-5: Unit completed 72 hr. full load trial
Dist. Ambedkar Nagar, on 28.09.2019. Unit commissioned on
U.P. NTPC Ltd.
14.09.2019. Unit Synchronized on oil
U-5 660 07/18 01/19 09.06.19(A) 28.09.19 (A)
09/18 14.09.19(A) - on 09.06.19.
U-6 660 01/19 07/19 08/20 -
03/19 09/20 10/20 Boiler: Boiler erection started in 12/15. Hydro test done
on 20/04/18.BLU completed on 31.12.18.Steam
Original/Latest Cost : Rs 9188.98 /10016.10 Crores
blowing completed in 05/19.Syn on oil in 06/19.
Exp. During 2013-14 : Rs 280.00 Crores
TG: Condenser erection started in 03/17. TG erection
2014-15 : Rs. 298.00 Crores
started in 07/17. TG Boxed up in 03/18.TG Oil flushing
2015-16 : Rs 649.00 Crores
is completed in 09/18. TG put on barring.
2016-17 : Rs 1413.00 Crores
ESP: ESP is having 6 Passes, all passes commissioned.
2017-18 : Rs 1671.12 Crores
2018-19 : Rs 1553.25 Crores
Unit-6:
2019-20 Rs 1192.10 Crores (Upto 02/20)
Boiler: Boiler erection started in 10/16. Hydro test
Cumulative Exp : Rs 7143.97 Crores (up to 2/20) completed on 18/01/19. 39587/45579 MT structur
Type of fuel : Coal erection done.
Investment. approval Sep 2014 TG: TG erection started in 12/18.Condenser erection
Date of Main Plant Order Boiler: L&T, TG: Alstom in Sep’14. MP civil works started in 10/18. TG boxed up in 03/19. TG oil flushing
awarded to M/s GDCL in Feb’15. in 01/2020. LP & integral piping WIP.
ESP: ESP is having 6 Passes; work is in progress for all
passes

BOPs:
Chimney: Order placed on GDCL in 02/15. Work is in
progress.
CHP: Order placed on L&T in 12/15. Equipment
erection and trials i/p. reclaiming conveyors comm.
Direct steam 1 set of conveyors commissioned, balance
erection is i/p.
AHP: Order placed on L&T in 03/16. Civil works
under progress. Mech erection of AWPH, ASPH,
HCSDPH and TACH &HCSD silo completed.
DM Plant: Order placed on Driplex in 08/15.Civil and
Mechanical work completed.
CWPs: Order for CW system equipment placed on
KBL in Jun’15. CW Pumps erected. OAC U-5 portion
work completed. Pumps 1,2 &5 erected & trial taken.
Pumps 3 & 4 erection WIP.
NDCTs: Order placed on L&T in 10/15.U-5 completed.
U-6 Grillage column 1470/1567 lifts done. Shell
116/116 lifts casting done.
Switchyard: Startup power charged.U-5 portion is
ready. CEA clearance received.

FGD: FGD is awarded to GE on 21.09.18.


Geo technical investigation completed. Test
pilingand job pilling in progress.

Critical Areas  Physical possession of balance 11.299 Acres Abadi land. Out of this, 3.15 acres in Ash Dyke area is critical.
 41 houses of Khattegaon need to be shifted for completion of Lagoon IIA and 3 houses, school & Temple shifting
to be done foe completion of Lagoon IIB.
 Associated Transmission System for Unit-6 by UPPTCL:
- Construction of sub-station at Basti
- Construction of Tanda – Basti 400 KV Line
Reasons for Delay Poor mobilization by civil agency, Delay in Engg. & Supply.
Delay in AHP (L&T MMH)
Delay in Civil Front
MPS 30.03.2020

TPM_Broad Status Report (January-February’2020) 47


Sl. Capacity Commissioning Schedule
No. PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
15. PatratuTPS, 2400 Unit-1:
Imp.Agency-PVUNL Boiler: Boiler, MILL Bunker and ESP Foundation
Dist: Jharkhand. (JV of work in progress. Biler erection started on 27.08.19.
NTPC & Govt. of TG: SG foundation completed.
Jharkhand)]
U-1 800 11/21 03/22 - - Unit-2:
01/22 - 03/22 Boiler: Boiler, MILL Bunker and ESP Foundation
work in progress.
U-2 800 05/22
TG:.SG civil work in progress.
06/22 11/22 - -
- 07/22
U-3 800 11/22 03/23 - -
12/22 - 03/23
Original/Latest Cost : Rs 17112.00/ 18668 Crores
BOPs:
Exp.During 2017-18 :Rs 992.11 Crores Chimney: Chimney#1Work started on 20.07.18,
Exp.During 2018-19 :Rs 485.18 Crores Excavation Completed on11.09.08, PCC completed on
Exp.During 2018-19 Rs 1212.8 Crores 20.09.18.6th segment casting completed. Shell casting
Exp.During 2019-20 Rs 850.41 Crores (02/20) started on 27.05.19. Present height is 86m.
Chimney#2 work started on 20.07.18. 370/810MT bar
Cumulative Exp. Rs 2672.12 Crore (02/20) erection done.Raft casting completed on 10.04.19.
Type of fuel : Coal
Zero Date 07.11.17 CHP: civil work started on 27.08.19. Design & engg
drawings is being finalized.
AHP: Design & engg drawings is being finalized.
Date of Main Plant Order BTG and Main Plant Civil &BTG Awarded to BHEL
Work started on 16.10.19
(BTG) on 08.03.18
ACC: Work yet to start
PT Plant: Work yet to start. Design & engg drawings
is being finalized.
DM Plant: Work yet to start Design & engg drawings
being finalized.
CW System: Work yet to start
Switchyard: Transmission line shifting work started on
14.09.18. Tower erection started on 15.04.19. GIS civil
work started on 26.04.19.Two 220 kV diverted line
charged.

FGD: order placed to BHEL on 08.03.18. Civil


foundations are being released.

Shifting of Transmission line from Project Area, Acquisition of Balance land of 35Acre for ash dyke-2 and lease of
Critical Areas 14.09acres of land and acquisition of 0.269 acre land fro railway siding.

Reasons for Delay Delay in award of ACC Pkg, WPT, Mian Power House Str erection Pkg by BHEL

MK 11.02.2020

TPM_Broad Status Report (January-February’2020) 48


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As
now Expected
Syn. Trail run Syn. Trail run
Com COD Com COD
Central Sector
16 Rourkela PP-II 250 Unit-1:
Expension,Odisha Boiler: Boiler erection started on 30.03.17. Boiler drum
lifted on 04.11.17. Hydro Test (drainable) done on 08.09.18.
U-1 250 - 12/18 - 03/20 9016/12000 MT erection done. All joints (1716) done for
09/18 02/20 04/20 non-drainable hydro. All 834 Reheater joints and 734/978
Investment Approval : 14.09.15 critical piping joints done. Both APH-A & B centre section
Orig.Est. cost : Rs 1885.13 Crores & modules and APH-B rotor erected.
Rs 1885.13 Crores ESP: 3482/4000 MT erection done. Electrode erection
Latest.Est. Cost completed in all Passes. Pass-A & B: hoppers and roof
Exp.During : canopy structure erected, ATT done and ash collection
2016-17 : Rs 237.51 Crore system erection in progress along with insulation work Pass-
2017-18 : Rs 515.81 Crore C: hopper lower part welding done. Pass D: shock bar
2018-19 : Rs 448.96 Crores erection done.
2019-20 : Rs 211.72 Crores (09/19) TG: TG civil work started on 02.03.17. Condenser erection
started on 28.12.17. TG erection started on 27.11. 18.
Cumulative Exp : Rs 1554.68 Crores( upto 02/20) BOPs:
Type of fuel : Coal Chimney: Shell casting completed on 30.03.18. Beam
erection Is u/p. Due to change in FGD complaint flue can
Fuel linkage Project taken up with supply of 1.42 MTPA coal liners, the chimney is expected to be ready in Jan-2020.
from Ramnagore Colliery. However on 17.04.18, CHP: ERH-1&2: ERH-1 & ERH-2 erection completed up to
SAIL informed that Ramnagore Colliery shall be roof truss level & top gratings erected. ERH-2 ground portal
delayed and requested NSPCL for making pedestal casting completed. Crusher house: All 28 columns
alternative arrangements for supply of coal. up to 4th segment erected. TP-2: All columns erection done.
Applied on 14.05.18 under Shakti Scheme TP-3: All columns, beam, bracing & intermediate
Date of Main Plant Order BTG and EPC contracted to M/s BHEL including platform erection done. TP-4: Erection of 1st & 2nd segment
(BTG) offsite civil works, order placed on 11.05.16 column completed. TP-5: All columns upto 3rd segment
erected.
AHP: AHP MCC, MCC control room, compressor house
PPA cum AWPH roof slab cast done. Ash slurry sump foundation
Signe don 09.05.16 with RSP, SAIL.Long term casting completed. Fly Ash Silo Utility building all slab cast.
PPAs with validity of 25 years with M/s SAIL, Bottom ash hoppers leakage test done and castable casting
GRIDCO Odisha,WBSEDCL & DNHPDCL completed. 02 HP water, 02 LP water 02 fly ash water, 01
flushing water, 02 seal water pumps 03 heaters and 03
fluidizing air blowers erected. AHP slurry pumps,
compressors & air driers erected.
PT Plant: Clarified water storage tank wall 1st lift casting
done; final lift wall casting completed. Clarifier A & B raft &
wall 1st lift cast.
DM Plant: Main Foundation completed, DM tank erection
done.
CWPs: CWPH building all columns erected. Crane girder
and 4/5 roof truss erected. CW inlet duct and riser pipe
erected. Recirculating pipe erection completed. Annexe
Building tie beam & connecting channel casting completed.
Switch Yard: GIS building cable trench work in progress.
IDCTs: CT cell 1 to 5 bottom slab cast & Cell 3 beam at
curve level done.
Switch Yard: GIS control room & GIS Building slab casting
completed. Station transformer grade slab, cable trench raft
and oil trench side wall cast. UAT foundation completed up
to top lift.
FGD: Tender issued earlier has been annulaed. Fresh
tender issued on 27.08.2019.
Critical Areas Project taken up with supply of 1.42 MTPA coal from their Ramnagore Colliery (SAIL's letter dated 29.08.13).
However, on 17.04.18, SAIL informed that Ramnagore Colliery shall be delayed and requested NSPCL for making
alternative arrangements for supply of coal to Rourkela PP-II Expansion (1x250 MW) Project. Applied on 14.05.18
under SHAKTI scheme and the same has been recommended by CEA to MOP. Coal linkage is critical for the
Project.
Reasons for Delay

TPM_Broad Status Report (January-February’2020) 49


BROAD STATUS OF CENTRAL SECTOR THERMAL POWER PROJECTS
(NLC India Limited)

Sl. No. Commissioning Schedule


Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Syn. COD Syn. Trial-run
Comm Comm COD
Central Sector
1 Neyveli New TPP 1000 Unit completed 72 hr. full
Unit-1:
M/s Neyveli Lignite load trial on 20.12.2019 ,
Corporation Ltd. at Neyveli
in Tamil Nadu
commissioned on 29.09.2019 and
Synchrinisation on 28.03.2019.
U-1 500 07/17 10/17 28.03.2019(A) 20.12.2019(A)
09/17 29.09.2019(A) - Boiler (M/s BHEL) Civil work srtart on
30.06.2014, erection start on 07.03.2016, Hydro
test (drainable) – 22.08.2018. BLU –
U-2 500 01/18 04/18 02/20 03/20 28.12.2018, Synchronisation on 28.03.2019.
03/18 02/20 Lignite firing 18.07.2019 and full load
Original Estd. Cost : Rs. 5907.11 Crores 29.09.2019
Latest Est. Cost : Rs. 7080.41 Crores (Base-Fab 2018) TG & Condenser: Civil work start on
Expenditure during 2011-12 : Rs. 14.4715 Crores 30.06.2014 and erection start on 24.03.2016.
2012-13 : Rs. 13.5319 Crores Condensor erection start on 24.03.2016. TG
2013-14 : Rs. 311.1426 Crores boxup 31.03.2017, TG oil flushing 20.11.2017
2014-15 : Rs. 445.6023 Crores Steam blow off 20.02.2019.
2015-16 : Rs. 1028.6206 Crores
2016-17 : Rs. 1933.3514 Crores For Unit-2:
2017-18 : Rs. 1099.3654 Crores Boiler : Civil work srtart on 31.10.2014,
2018-19 : Rs. 739.9544 Crores erection start on 28.03.2016, Hydro test
2019-20 : Rs. 409.9579 Crores (drainable) – 26.11.2018. BLU – 30.05.2019.
TG & Condenser: Civil work start on
Total Expenditure : Rs. 6265.1603 Crores (up to 02/20) 29.10.2014 and erection start on 24.03.2016.
Condensor erection start on 24.03.2016. TG
Approval date:
boxup 30.06.2017, TG oil flushing 15.09.2018
Zero date: : 09/06/11 Steam blow off 26.09.2019.
Financial closure Debt: Equity 70:30 Loan availed from power finace corpn. and BOPs
HDFC  Chimney: Initial Operation completed and in
Main Plant Order : Main Plant Order (EPC) issued to M/s BHEL on for SG & service.
Auxiliaries on 31/10/13 and TG & Auxiliaries on 23/12/13.  LHP: Complete and in operation.
BOP Package : Awarded to M/s EPIL on 30/04/2014.  AHP: All the equipments in AHS is
Type of fuel : Lignite from NLC mine 1 & 1A commissioned. Som work is pending and
PPA :PPA signed for 25 years with AP- 52.46 MW, Telangana – work in progress.
61.31 MW, Karnataka 70.54 MW, Kerala 32.38 MW, Tamil  RO/DM plant: Awarded to M/s EPIL on
Nadu 653.07 MW, Puducherry 4.24 MW, NLC – 66.00 MW 30/04/14. Initial Operation completed and
and Un allocated power – 60.00 MW. Plant in service.
Power Evacuation system For power evacuation and drawing of start-up power,400kVand  CW System: Awarded to M/s EPIL on
220kV switchyard would be provided. Each of the 500 MW 30/04/14 and further to M/s KBL on
units would be connected to the 400kV switchyard. The power 20/01/15. CWPH: CWP -IA &IB- pumps
generated at the plant would be evacuated through a 400kV Initial Operation completed and Pump in
system. Start-up power would be drawn from the 220kV service.
switchyard. For unit-2: Both CWP 2A & 2B taken into
The generator transformers of 500MW units would step up service.
generator voltages to the switchyard voltage of 400Kv.One and  Cooling Tower: Initial Operation completed
Half Breaker scheme is proposed for 400kV and 220kV and in service.
switchyard. These schemes are reliable and provide flexibility in  FO System: Completed and in service.
operation.  Switchyard: 220kV GIS : 220kV GIS
permanently charged.
 Coal Linkage/FSA: Lignite from the NLC Mine 1 & 1A.
 Land possession: 160 Hectares Owned by NLC 400kV GIS: 400KV GIS permanently
 Water allocation: Existing TS 1 lake and erstwhile Fertilizer lake of NLC Ltd., charged on 13.02.19.
 MOE&F: Clearances obtained on 21/10/2010 and extended up to 20/10/2017, clearance further Civil work – Area Paving and drain work
extended upto 20.10.19. completed.
 CPCB: Clearances obtained and valid up to 31/03/2018.
 SPCB: Approval up to 31.03.2019 has been obtained and further CTO process initiated.  FGD : LOI issued on 31.08.2019.
 Civil Aviation: Obtained from AAI on 25.11.2009 valid for 7 years. Extention obtained upto
25.11.2021

Critical issues
Reasons for Delay Delayed due to change in design of foundations(depth) of main plant area and finalisation of civil contractors. Initial delay in
supply of Boiler Material and inadequate resource mobilization and new technology(Boiler) being used first time in India.

SB: Dec 2019

TPM_Broad Status Report (January-February’2020) 50


Commissioning Schedule
Original Actual (A) / As now
PROJECT Capacity
NO. Anticipated. Broad Status
DETAILS (MW)
Syn. COD Syn. COD
Comm Comm
2 Ghatampur TPP 1980 Unit -1:
JV of NLC & Boiler #1: civil work start on 17.03.2017, hydrotest (drainable)
UPRVUNL completed on 06.01.2020, 28645/44889 MT erection completed
(Lahurimau village, SCR pre assembly under progress, LDO tank1& Tank 2 Water
Ghatampur, fill test completed. Pressure Part joints & elevator structure
Kanpur), U.P. erection
660 03/20 11/20 08/20 11/20 completed
U-1 04/20 09/20 TG: civil work start on 05.05.2017 and errection started on
08.10.2018. Condensor erection started on 08.10.2018. TG Box
660 09/20 05/21 02/21 05/21 up is done on 27.12.2019.
U-2 HP Condenser- Tube expansion completed LP Condenser Tube
10/20 03/21
660 03/21 11/21 08/21 11/21 expansion work under progress
U-3 ESP-1: Structural erection in progress. 4969/7862 MT erection
04/21 09/21
Original/Latest Est. : Rs.17237.80 Cr completed. Collecting electrode & outlet funnel erection in
Cost progress. Control building EL+15 Mtr. brickwork is in progress
Exp. During 2012-13 :Rs.138.38 Cr
2013-14 :Rs.5.80 Cr Unit-2:
2014-15 :Rs.39.78 Cr Boiler #2: Boiler erection is in progress 16575/42485 MT
2015-16 :Rs.(-)5.28 Cr erected. 24363/54835 nos Pressure Parts joints welding works
2016-17 :Rs.735.80 Cr completed.
2017-18 :Rs. 909.50 Cr TG: Deck casting completed.
2018-19 :Rs.3519.04 Cr ESP-2: Structure erection works in progress. 3232/7862 MT
2019-20 :Rs. 2661.44 Cr erected.
Cumulative Exp :Rs. 8844.35 Cr (up to 2/20)
Type of fuel : Coal Unit-3:
Boiler#3 Mechanical Erection under progress. 12057/44889 MT
Date of Financial : Declared on 31.12.2017
erection completed. 2287/54789 pressure parts joints welding
Closure
work completed.
Date of clearance by : 15.10.2016
TG: Column work is in progress
the board of NUPPL
ESP-3: Structure erection works started. 440/7862 MT erected.
Date of Main Plant : Order for Gen. Auxiliaries (1) placed on MHPS Boilers Pvt.
Order/BoPs Ltd. on 02.08.16
BOPs
Order for Gen. Auxiliaries (2) placed on M/s. Alstom Bharat
Chimney: 269/269 mtr height completed. RCC Shell completed.
Forge Power Ltd. on 02.08.16 Platform beam lifting for roof slab EL (+) 267m & EL (+) 257 m
Zero date : 02.08.2016 level, work under progress. 121/684 MT Platform beam erection
PPA : Signed with UP Govt. on 31.12..2010 completed
Fuel Linkage : Pachwara South Coal block in the state of Jharkhand has Coal handling Plant: Wagon Tippler, Track Hopper, Crusher
been allocated to cater the coal requirement of 8 MT per House, Stacker reclaimer, JT 1 to 12 & Emergency Reclaimer
annum. Letter of award (LOA) dt.22.10.2018 was issued to structure erection works are in progress.
M/s. MIPL GCL Infracontract Pvt. Ltd., Ahmedabad. for the Ash handling Plant: Ash Silo and Ash dyke civil works are in
work of Mine Developer and Operator (MDO) progress.
Power Evacuation System CEA in its 36th Standing Committee meeting held on 13.07.2015 CW System: CW Pump House (CWPH) and CW channel RCC
at New Delhi, has agreed for power evacuation system of works in progress.
Ghatampur Thermal Power Station proposed by UPPTCL DM Plant: DM Plant water generation started CPVC piping &
MoEF MoEF issued Environmental clearance to NUPPL on 17.06.2015 valves erection under progress
Switchyard:
Land Land of 828 Hectares has been acquired, balance for railway -132 KV GIS Building: Finishing work in progress.
siding yet to be acquired - 132 KV Fencing work under progress
Civil Aviation Clearance Civil Aviation clearance received on 13.12.2013 - 400 KV GIS Building –3rd tie beam under progress, control
room brick work under progress
Water U.P. govt. has sanctioned for 80 cusec water to be drawn from
- 765 KV GIS Building –2nd Tie beam work in progress. Column
downstream of Bidhnu canal
works in progress.
- ICT & Reactor Foundation Fire wall works under progress.
Backfilling works under progress.
Cooling Towers: NDCT # 1,2,3 Civil works are under progress

FGD: Board approved for cancellation of old tender and


floating of retender is in process

Critical issues
Reasons for Delay
AK-16/01/2020

TPM_Broad Status Report (January-February’2020) 51


Commissioning Schedule

Unit Actual (A) / As


Sl. Original Broad Status
PROJECT DETAILS Capacity Expected
No
(MW)
Syn. COD Syn. COD
Comm Comm
Central Sector
3 Barsingsar TPP ext
(Distt. Bikaner ) U-1 250 05/20 08/20 05/20 08/20  Detailed engineering work and vendor’ approval is
08/20 08/20 in progress
( 250 MW)  R-infra has established their site office at BTPSE.
 The package activities at BTPSE are yet to start.
Estimated cost Rs. 2112.59 Crores  Soil investigation work was completed.
Exp. During 2017-18 Rs. 154.70 Crores
Exp. During 2018-19
Exp. During 2019-20
Rs.
Rs.
3.6724 Crores
1.2086 Crores
Project activities are under
Total Exp Rs. 159.0581 Crores (up to 12/19.) hold from 02/06/2017 due to
Zero Date of Project : 21/11/2016
Financial Closure Under progress
withdrawl of PPA by
Main Plant order Date EPC contract to M/s Reliance Infra.. DISCOMS.
Type of Fuel Lignite
Fuel linkage Halda Lignite Mine 1.90 MTA (original cost is Rs. 522.45 Cr.)
PPA Signed with GoR on 31/12/2010

Power evacuation Through two No. S/C 220 kV transmission lines viz (i) BTPSE- Gajner (ii)

Uncertain
system BTPSE-Bikaner, to be executed by RVPNL
Water: Water supply agreement signed on 08/10/03 b/w Indira Gandhi Nahar Pariyojna, GoR and
NLC
Land: Land is in procession of NLC and the proposed plant is being constructed with in the existing
2x125MW Barsingsar TPP
MOE&F clearance: EC for mines granted on 21/10/13. EC for thermal granted on 30/07/12
Civil Aviation: NOC obtained on 23/01/2012

Critical Issues

Reasons for delay GoR had informed that due to increased project cost and time over run, Rajasthan Discom will not be in position to buy the power
from BTPSE. NLCIL had replied that delay is due to acquisition of land for linked mine by GoR and informed to review the decision.
Matter is pending with GoR. Project activities are under hold from 02/06/2017.

MPS – Jan 2020

TPM_Broad Status Report (January-February’2020) 52


Commissioning Schedule

Sl. PROJECT DETAILS Original Actual (A) / As Expected Broad Status


Capacity
No
(MW) Syn. COD Syn. COD
Comm Comm
Central Sector
4 Bithnok TPP
Distt. Bikaner,  R-infra has established their site office at Bithnok.
Rajasthan  The package activities at Bithnok are yet to start.
U-1 250 05/20 08/20 05/20 08/20
08/20 08/20 Project activities are under
Estimated cost (M/Y) : Rs. 2196.30 Crores
Exp. During 2017-18
hold from 02/06/2017
: Rs. 169.7948 Crores
Exp. During 2018-19 : Rs. 3.6762 Crores

Exp. During 2019-20 : Rs. 1.1924 Crores

Total Exp : Rs. 174.6634 Crores (up to 12/19)


Zero Date of Project : 21/11/2016
Financial Closure : Under progress
Main Plant order Date : EPC contract to M/s Reliance Infra.

Uncertain
Type of Fuel : Lignite, Bithnok Lignite Mine 2.25MTA (Original cost is Rs.
513.63 Cr.)
PPA : Signed with GoR on 31/12/2010

Power evacuation Through three No. S/C transmission lines viz (i) BLTPS-
system Kolayat (ii) BLTPS-Nokha(iii)BLTPS-Bikaner to be executed
by RRVPNL.
Water: Water supply agreement signed on 10/06/14 b/w Indira Gandhi Nahar
Pariyojna, GoR and NLC
Land: Private land-1088.20 ha in possession.
Govt Land-Transfer in favour of NLC India is under progress at O/o Commissioner
colonization, Bikaner
Forest land- Transfer in favour of forest dept is under progress at O/o Commissioner
colonization, Bikaner
MOE&F clearance:EC for mines granted on 26/02/16. EC for thermal granted on
30/04/10 and validity extension is under progress.
Civil Aviation: NOC obtained on 09/08/16

Critical Issues

Reasons for delay GoR had informed that due to increased project cost and time over run, Rajasthan Discom will not be in position to
buy the power from BTPSE. NLCIL had replied that delay is due to acquisition of land by GoR and informed to
review the decision. Matter is pending with GoR.
MPS – Jan 2020

TPM_Broad Status Report (January-February’2020) 53


BROAD STATUS OF CENTRAL SECTOR THERMAL POWER PROJECTS
(THDC India Limited)

Sl. No. Capacity Commissioning Schedule


PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. COD Syn. Trial-run
com. com COD
Central Sector
1. Khurja STPP 1320 Boiler : Steam Generator and Associated
Khurja Packages including site leveling (SG Pkg) for
(UP) (THDCIL)
INR 4087 Cr. (including taxes and duties) has
U-1 660 08/23 been awarded to M/S L&T MHPS Boiler Pvt.
U-2 660 02/24
Ltd. (LMB) on 29.08.2019 and contract
Original/Latest Cost : Rs 1108942 lakhs agreement has been signed on 18.10.19.
Exp.During 2019-20  Topography Survey and Geotechnical
Investigation has been completed by M/s LMB
Cumulative Expenditure Rs. 918.62 Crores  Site Levelling and area grading work are under
(up to 02/20) process.
Type of fuel : Coal  TG Main Power House area has been handed
Zero Date 31.03.2018 over to M/s BHEL on 14.02.20 and entire TG
Lay down area is likely to be handed over
Date of Main Plant Order EPC package to M/s BHEL. shortly.
(BTG) LOA date: 31.03.18.  Work of priority roads and diversion of Aligarh
Drain has been taken up.
MOEF &CC : EC has been accorded to Khurja STPP by MOEF&CC on 30.03.2017.  Supplies for construction power-ring main
Clearance for Chimney : Revised Clearance for construction of 275 m high chimney works have been ordered and Civil works are
for Khurja STPP obtained from Airport Authority of India on 19.04.2018 for a period in progress.
of 05 years i.e.up to Jul-23.  Components of 60 Cum/hr capacity Batching
Makeup Water : 43 Cusec from Upper Ganga Canal at just 11 Km from Project.
Plant of RMC contractor has reached at
(Water Resource Department, GoUP on 12.06.2014)
Coal : For Coal linkage, Ministry of Coal, GoI vide allotment order dtd.17.01.2017 site on 13.02.20.
has allotted Amelia Coal Mine in District Singraulli, Madhya Pradesh. TG : - Turbine Generator and Associated
PPA : Signed on 05.01.2011 with Uttar Pradesh, Uttrakhand, Rajasthan, Himachal Packages (TG Pkg) for INR 1575 Cr. (including
Pradesh and Delhi. taxes & Duties), has been awarded to M/S
BHEL on 03.10.2019 and contract agreement
has been signed on 22.10.19.
 Site mobilization started andTopography
Survey and Geotechnical investigation has
been completed.
  Geo Technical Investigation Report has
been submitted by BHEL. Survey work for
Pillars & Bench Marks construction is
presently going on.
 Award of enabling work agency, material
handling agency, ground improvement
works etc. are in process by M/s
BHEL.
Switch Yard - Switchyard Packages (SY Pkg) for
INR 112.05 Cr. (including taxes & Duties), has
been awarded to M/S GE T&D on
26.02.2020.FGD: Installation of FGD executed
by BHEL

Critical Areas
Reasons for Delay

MPS 30.03.2020

TPM_Broad Status Report (January-February’2020) 54


BROAD STATUS OF CENTRAL SECTOR THERMAL POWER PROJECTS
(SJVN Limited)

Sl. No. Capacity Commissioning Schedule


PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. COD Syn. Trial-run
com. com COD
Central Sector
5. Buxar TPP 1320
Village Chausa, Distt
Buxar, Bihar (SJVNL) Main Plant works (Single EPC) awarded to M/s
U-1 660 07/23 07/23 L&T on 22.06.2019.
U-2 660 01/24 01/24
Original/Latest Cost : Rs 1043900 lakhs I) Excavation in Ash pond and corresponding
Exp.During 2019-20 : filling in CHP area: 6.25 lakh cum out of
40.50 lakh cum completed.
Cumulative Expenditure Rs. 882.92 Crores
(up to 02/20) II) Piling - Boiler-1, Chimney, coal mill and
Type of fuel : Coal Electro Static Precipitator (ESP)-1MTotal -
Zero Date 22.06.2019 620 Nos. (out of 7463) completed and
further work in progress.
Date of Main Plant Order Main Plant works (Single EPC) awarded
(BTG) iii) Borehole in TG area: Work in progress.
to M/s L&T on 22.06.2019.
MOE&F clearance: MOEF &CC Clearanace on 28.02.17. FGD: Installation of FGD executed by BHEL
 NOC issued on 12.04.17from airport authority.
 CCEA accorded investment approval for the project on 08.03.19.
Foundation stone laid by Hon'ble Prime Minister of India on
09.03.19.
 Power Purchase Agreement (PPA) has been signed with
Bihar State Power Holding Company Limited (BSPHCL) for
85% share of power generation on bus bar rate.
 Consent to establish : NOC granted by Bihar State
Pollution Control Board on 03.09.2019.
 Coal : Long-term coal linkage tied up through Central
Coalfields Ltd. (CCL) vide Letter of Assurance (LoA)
dated 10.12.2018
Critical Areas
Reasons for Delay

MPS 30.03.2020

TPM_Broad Status Report (January-February’2020) 55


STATE
&
PRIVATE SECTOR

Thermal Power Plants

TPM_Broad Status Report (January-February’2020) 56


NORTHERN
REGION
Thermal Power Plants

TPM_Broad Status Report (January-February’2020) 57


BROAD STATUS OF THERMAL POWER PROJECTS IN RAJASTHAN
Commissioning Schedule

Sl. PROJECT Original Actual (A) / As Expected Broad Status


No DETAILS Capacity
(MW) Syn. COD Syn. COD
Comm Comm
State Sector
Chhabra SCTPP, 1320
Chhabra Unit-5: COD achieved on 09.08.2018.
RRVUNL Distt. Commissioned on 04.04.2017.
Baran,Rajasthan Synchronisation done on 25.02.2017
1 660 06/16 09/16 02.10.16(A) 09.08.18(A)
U-5 09/16 04.04.17(A)
 Boiler: erection started on 17/02/14. HT done on 03/11/15.
660 05/18 06/18 28.07.18(A) 02.04.19(A) BLU done on 22/08/16. Steam blowing done on 26/08/16.
11.12.18(A) Syn. on Oil done on 02/10/16. Re-lightning done on 06/1/17.
U-6 Re-syn done on coal on 25/02/17. Coal firing done on
Original/Latest cost : Rs. 792000/955027/1091027 lakhs 25/02/17. PG test completed on 21/03/2018.
 TG: Condenser and TG erection started from 24/01/15 and
Exp. During 2013-14 Rs. 76315 lakhs 27/03/15 respectively. TG box up done on 08/03/16. Oil
2014-15 Rs. 85862 lakhs flushing completed on 27/05/16.
2015-16 Rs. 249612 lakhs
2016-17 Rs. 279774 lakhs Unit-6: COD achieved on 02.04.2019.
2017-18 Rs. 112385 lakhs Commissioned on 11.12.2018.
2018-19 Rs. 88991 lakhs
Synchronisation done on 28.07.2018.
Total Exp Rs. 892939 Lakhs (up to 01/19.)
Zero Date of Project : 28/03/2013
 Boiler: Boiler Erection started on 17/08/15. Boiler HT
Financial Closure Pertains to TD
achieved on 15/02/17. BLU achieved on 24/04/18. Steam
Main Plant order Date EPC Order placed on M/s L&T on 28/03/2013. blowing started on 28/04/18. Steam Blowing of critical piping
Type of Fuel Coal competed on 26.05.18. Reliability Run completed on 03.01.19.
Fuel linkage Coal Blocks (Parsa East & Kante Basen) re-allocated by  TG: TG deck casting completed on 25/06/16. TG erection
MoC, GoI on 24/03/15. started on 11/07/16. TG Box up is completed on 26/09/17.
PPA Signed with Rajasthan Discom on 18/05/10 Second state lube oil flushing started on 27/09/17. seal oil
system second stage flushing completed on 05/10/17. Third
Power evacuation Extension work of ANTA Line upto Chhabra STPP has stage oil circulation completed on 25/12/2017. JOP trial and
system been taken up by RVPN TG rotor lift check done on 26/12/2017. TG Barring Gear
Water: 300 MCFT from Lhasi and 1270 MCFT from Parwan irrigation projects operation achieved on 16/01/2018. Synchronization on oil
has been ensured by GOR. achieved on 28/07/2018.
Land: Land is available for both the units.
MOE&F clearance ESP: Unit#5 ESP commissioned and Unit#6 ESP ready.
Unit-5: 23/05/2012 Insulation completed. Commissioning completed.
Unit-6: 02/02/2015
BoPs:
 Chimney: Ready in all respect.
 CHP: CHP ready in all respect except railway siding. Coal
Feeding through Unit#6 reclaim path started from 03.12.18.
No load trial of Raclaimer completed.
 AHP: Ready except the Fly Ash Silo. Readiness of Silo will
match the commissioning schedule.
 NDCT: Both NDCT commissioned.
 DM Plant: Commissioned.
 CW System: Ready
 FO system: Commissioned
 Switchyard: Anta line charged on 22/04/16 and switch yard
charged on 23/05/16.

Critical Issues 1. Rail Link


2. Raw Water

Reasons for delay

TPM_Broad Status Report (January-February’2020) 58


Commissioning Schedule
Original Actual (A) / As now Expected
PROJECT Capacity
Sl. Broad Status
DETAILS (MW) Syn. Trial Syn. Trial Run
Comm Run Comm /COD
/COD
State Sector
2. Suratgarh Super 1320 Unit-7: Unit completed 72 hr. full load trial on
Critical TPP, 15.03.2020. Commissioned on 30.03.2019.
RRVUNL, Suratgarh 06/16 18.12.18(A) 15.03.2020(A) Synchronisation done on 18.12.2018.
(Distt Sri Ganga 660 09/16 04/20
07/16 30.03.19(A)
Nagar Boiler: Erection started on 26/03/14. Hydro test
U-7 completed on 31/12/15. BLU completed on 24/02/17.
09/16 06/20
660 12/16 07/20 Steam Blowing completed on 25/08/18. Unit
10/16 06/20
U-8 synchronized on 18.12.18 at 1140 hrs with 205MW max
Original/Latest cost Rs. 792000/ 916135 lakh load. full load achieved at 16:08 hrs on 30.03.19. Trial
Exp. during 2012-13 Rs. 1736 lakhs run completed on 15.03.2020.
Exp. during 2013-14 Rs. 55029 lakhs TG: TG civil work started on 07/12/13. Condenser
Exp. during 2014-15 Rs. 191874 lakhs erection started on 29/04/15. TG erection started on
Exp. during 2015-16 Rs. 252788 lakhs 16/11/15. TG box up done on 21/01/17. TG put on
Exp. during 2016-17 Rs 165353 lakhs barring gear on 10/11/17.
ESP: Erection completed. Insulation and cladding work
Exp. during 2017-18 Rs 39264.22 lakhs
also completed
Exp. during 2018-19 Rs 55420.54 lakhs
Exp. during 2019-20 Rs 48616.54 lakhs (up to 12/19) Unit-8
Total Expenditure Rs 929511.62 Lakhs (up to 12/19) Boiler: Erection started on 25/06/14 HT completed on
Type of fuel Coal 15/03/16. Boiler light up completed on 28/09/17. Boiler
Zero date 28/03/13 Hyd. Test (Non-Drainable) performed on 27/07/18.
Main Plant Order Order placed on 23/05/13 on M/s BHEL on Steam Blowing completed on 07.06.2019.
EPC basis. TG: Condenser Erection started on 28/06/15 and TG
Blr-ALSTOM, TG-SIEMENS erection started on 05/11/15. Turbine boxed up on
Fuel linkage Approval accorded by MOC on 03/02/12 from 09.11.17. Turbine oil Flushing completed on 18/08/2018.
Parsa East & Kanta Basan coal bocks of Barring Gear engaged on 05/02/2019.LP turbine blade
RVUNL rectification works at BHEL unit under progress
Power purchase agreement: PPA made between RVUN and Jaipur, Ajmer, SP: Erection completed. Insulation work also completed.
Jodhpur Vidyut Vitran Nigam Ltd. on BoP’s:
18/05/10. Chimney: Both the chimney is ready.Balance electrical
Power evacuation system: Through 4 x 400 kV transmission line of work is in progress
RVPN. CHP: Trial run of BCN-2B, 3A, 4A and 1A locally
done. Erection on BCN-1C, 21ABC, 22AB, 3AB, 4AB,
Land Possession of 672.873 ha of land for water 25, 27AB, 31AB, 31D, 14A,B RBF-1, RBF-2 under
system, construction of main power plant, progress Stacker cum Reclaimer & Reclaimer of Unit 7
residential colony on approach road taken. commissioned. Stacker cum Reclaimer & Reclaimer and
Water 60 cusec of water from Indira Gandhi Canal is Electrical work of SCR &SR unit #8 is u/p.
allocated on 02/09/09. AHP: - Equipment Erection at the top of main Silo#3&4
MOEF Clearance obtained vide letter No. J- is under progress Erection work of PD pump is
13012/14/2009 – IA. II (T) on 23/05/12 completed and conveying piping is under progress
Civil Aviation NOC obtained from AAI on 26/4/10 Bottom ash hopper of U-7 has completed with refractory
work and equipment erection work. Erection and
commissioning work of ADL pipe line (L1 & L2) up to
Ash dyke is completed.
NDCT: U-7: Commissioned 100%. NDCT U#8: Internal
Coloumns completed. Erection is under progress in first
half.U#8 300000/411972 fills erected
CW System: Ready
DM Plant: Commissioning through PLC under progress
PT Plant: Commissioning through PLC under progress
FO system: Shell erection/fabrication completed. HFO
unloading discharge pipe line work on ash handling pipe
rack is under progress. Erection completed
Switchyard: Back charging done from existing plant
400 KV switchyard on 21/1/2017. Progress of SSCTPS-
BABAI Line-Erection-676/676, stringing-197.245/245
km. 400 KV, DC, SSCTPS- BIKANER transmission line
is ready. SSCTPS- BIKANER transmission line charged
on 28/07/18.
FGD Plant: - NIT floated on 13.05.2019.
Critical Areas AHP, Marshalling Yard Extension, Regular CHP
Reasons for delay BHEL manpower; delay in supply and non-sequential supply by BHEL. Non-readiness of regular AHP & CHP by
BHEL.

TPM_Broad Status Report (January-February’2020) 59


BROAD STATUS OF THERMAL POWER PROJECTS IN UTTAR PRADESH

Commissioning Schedule
Sl.
Actual (A) / As now
No. Capacity Original
PROJECT DETAILS Anticipated. Broad Status
(MW)
Syn. Syn.
COD
Comm Comm COD
Private Sector
1 PRAYAGRAJ TPP 1980 U-1: Full load Achieved on 25.12.15. COD on
M/s Prayagraj Power Generation 29.02.16
Co. Ltd.
(Distt. Bara, Allahabad), U.P.  Boiler erection started on 12/07/11. HT done on
Unit-1 660 06/13 10/13 31.10.15(A) 29.02.16 (A) 24/10/13. BLU done on 31/03/15. TG erection started
25.12.15(A) in 01/13 & boxed up on 20/02/14. Oil flushing
completed on 18/03/15.
Unit-2 660 11/13 03/13 07.07.16 (A) 10.09.16 (A) Unit Synchronised on 31.10.15.
06.09.16 (A)
Unit-3 660 04/14 07/14 26.03.17(A) 26.05.2017 (A) U- 2: Full load Achieved on 06.09.16. COD on
22.05.17(A) 10.09.16.
Date of clearance by State Govt. : Nov, 2006.
 Boiler: Boiler erection started on 12.09.2011.
Original/Latest Est. Cost : Rs.1162227 Lakhs/ 1387000 lakhs Hydro test conducted on 29.01.15. BLU completed on
Date of Financial Closure : Achieved on 06.07.2010 with SBI 03.03.16. SBO completion expected in 05/16
Exp. Upto 03/2011 :Rs.124478 Lakhs  ESP: ESP work completed
Exp. During 2011-12 :Rs.137691 Lakhs  TG: Condenser erection started on 10.06.13. TG
Exp. During 2012-13 :Rs.296958 Lakhs erection started on 20.09.13. TG boxed up on 14.05.15.
Exp. During 2013-14 :Rs 308897 Lakhs OF completed on 16.03.16. Unit Sync. on 07.07.16.
Exp. During 2014-15 :Rs. 285952 Lakhs 
Exp. During 2015-16 : Rs. 171135 Lakhs U-3: Full load achieved on 22.05.17. COD on
Exp. During 2016-17 : Rs. 130126 Lakhs 26.05.17.
Exp. During 2017-18 :Rs.10097 Lakhs
Cumulative Expd. (4/17) :Rs. 1465334 Lakhs  Boiler: Boiler erection started on 05.09.2011.
Hydro test conducted on 29.11.14. BLU on 31.05.16.
Type of fuel : Coal Acid cleaning completed. Temporary piping work for
steam blowing is under progress. SBO completed on
Date of Main Plant Order : 22.01.2009 (BTG) on M/s BHEL 06/02/17. Unit Syn. (on oil) on 26/03/17.
 ESP: ESP work completed.
Boiler U-1: Structure from BHEL, Pressure parts from Alstom, U-  TG: Condenser erection started on 10.01.14. TG
2&3: From BHEL. erection started on 11.11.14. TG box up completed in
Boiler, TG & Generator make.
TG & Gen U-1&2: From Siemens, U-3: From BHEL Hardwar. 05/02/17. TG Oil flushing done on 14/02/17.

BOPS:
 FGD: The order for FGD installation has been
Zero date 23.02.2010. placed on M/S Tata Consultant Engineers (TCE) at
the cost of @ 1000Crs. There is no space constraint
PPA : PPA signed on 21.11.2008. for installation of FGD system in the plant.
 Chimney: Awarded to Paharpur. 275 height achieved
Fuel Linkage : Fuel supply agreement between PPGCL & NLC for 6.95 MTPA has
for both chimneys. Flue 1&2 completed. Chimney 2
been executed on 29.08.2013. completed.
Associated Transmission System Power is proposed to be evacuated at 765 KV and 400 KV level for
 CHP: Package A awarded to L&T and Package B
which 765KV and 400 KV switchyards are proposed. Responsibility of
awarded to HEW. For Package A, WT4 & WT 3
UPPCL & PPGCL. Work awarded to Isolux.
commissioned. For U-1,2,3 bunker ready. Load trials
carried out. For Package B, 1st stacker reclaimer
commissioned.
 AHP: Awarded to Macawber Beekay. System ready
for U-1,2 & 3 completed.
Land: :1468 acres of land for the project is in physical possession. Land for the facilities outside the plant area  NDCT: CT-1,2 &3 completed.
is being acquired. For land required for railway sliding about 32.71 Ha out of 35 Ha has been acquired. Lease
 PTP: PT plant commissioned
deed executed and the process of taking physical possession of land is completed.
 DM Plant: DM plant commissioned
MOEF clearance: Obtained on 08.09.2009  FOS: ALL HFO and LDO storage & Day tanks
completed. FOH pump house ready, LDO system
commissioned.
 FPS: Ready for U-1,2 &3
 SWYRD: Work in 400 KV switchyard completed and
charged one 765 kV line

TPM_Broad Status Report (January-February’2020) 60


Commissioning Schedule
Sl. Actual (A) / As now
Original
Broad Status
No. Capacity Anticipated.
PROJECT DETAILS
(MW)
Syn. COD Syn. Trial-run
Comm Comm COD
2 Harduaganj Expn. -II Unit-I
UPRVUNL Boiler: SH circuit hydro test completed. Main Boiler, Mill Bay & APH
Distt.: Aligarh, U.P erection completed and Platform Str. Work in progress. 7 Mills major
Unit-1 660 09/19 01/20 05/20 07/20 erection completed. APH& SCR –A, B erection is under progress.
11/19 06/20 ID Fan-A, PA Fan-A erection work is under progress. FD Fan-A Lub oil
Original//Latest Cost : Rs.482649 lakhs. Revised cost of Project due flushing in progress
inclusion of FGD SCR is Rs. 550098 lakhs. TG & Aux: LP condenser flash box work & neck joint welding in
Exp. During 2015-16 : Rs. 30581 Lakhs progress. HP condenser neck joint welding completed & Gland steam
Exp. During 2016-17 : Rs 11513 Lakhs work in progress HP, IP Turbine trial box-up in progress, CRV & MSV
Exp. During 2017-18 : Rs 45810 Lakhs
erection completed.3. TG Building: Ground & Mezzanine & Operating
Exp. During 2018-19 : Rs 122383 Lakhs
Exp. During 2019-20 : Rs 96074 Lakhs
floor all equipment foundations completed. HP Turbine, IP Turbine, LP-A
Cumulative Expd. :Rs 306361 Lakh
& B final box-up completed.
(11/19) ESP: Pass A, B, C & F ATT completed. Erection for Pass D, E is under
Date of Financial Closure : Achieved on 14.03.2012 (80% PFC Loan & 20% progress.
government equity)
Type of fuel : Coal BOP areas : Civil works under progress :
Date of Main Plant : M/s Toshiba JSW Systems Private Limited as a  Chimney: Shell construction completed. Corbel work, AR Brick
Order/BoPs single EPC basis on 08.09.2015 lining work completed. External Platform & Hopper work in
Boiler: Doosan, India ; TG & Generator: Toshiba JSW progress.
Power Systems
 Raw Water system: Raw water Reservoir-A & B completed, RWI
Zero date : 08.09.2015
NTP (Notice to proceed) : 08.09.2015 Pump House, and RWPH major Civil work is. completed
date  PT Plant: Clarifiers -1, 2, Sludge Thickener erection completed.
PPA : Signed on 16.01.13 Major equipment erected. Balance Piping erection is in progress
Fuel Linkage : From Saharpur-Jamarpani, Jharkhand coal Block  CHP: JT-8, Conveyor Gallery connecting LHS Bunker to JT-08&
allocated on 25.03.15.
JT-07 erection completed. Stacker Reclaimer-1B, JT-6, JT-7, BC-
Power Evacuation System 400kV Switchyard
4A/4B, BC-6A/6B, BC-5A/5B, YBC-1B, WT-A,B & Crusher House
MOEF clearance Change order from MOEF issued. The Govt.of UP has erection is in progress• Track Hopper, WT, ERH, JNTs, Conveyors,
approved the Installation & Construction of FDR & Crusher House and stacker reclaimer civil works under progress.
SCR Syatems in December 2016 which will comply
 AHP: Ash Slurry Piping Fabrication & Laying work in progress.
the MoEF circular dated 7/12/2015
Land Not required being an Expansion Project Ash water pumps erected, Fly Ash piping works in progress at ESP.
BAH erection in progress.
Civil Aviation Clearance Civil Aviation Clearance granted on 11.07.12 from  IDCT: 24/24 no fan deck casting completed & major civil work
Airports Authority of India
completed. Mechanical pipe erection under progress. Equipment &
Water Water Allocated on 03.12.11 from Upper Ganga Canal
Fills erection in advance stage of completion
 CWPH:. Major Civil work completed, front handed over to
Note: - mechanical.
The above dates are based on 58.7 months’ completion schedule.  DM plant: Regeneration equipment& piping erection completed.
- All the other BoP packages have also been awarded to various contracting DMWST-A & B water fill test completed, Now in operation. Stream-
agencies for execution. A & B. Commissioning completed in manual mode
 Switchyard: Erection of Switchyard Structure, EHV Equipment’s
completed.220KV &400KV Switchyard charging completed.
Transmission Tower-1 erection completed, Transmission Tower-2
erection in progress. CCR Building: Electrical SWGR Panels testing
completed. HT Switch gear charging completed
 FGD Plant: FGD awarded to M/S Doosan. Absorber & GGH Area
Civil Works completed. Lime stone & Gypsum processing building
civil works in progress Absorber Tower Make up water tank& steel
structure erection in progress. Material receiving in progress.
Critical Areas/
Assistance Required
Late receipt of the MOEF&CC revised order by UPRVUNL with inclusion of FGD & SCR System in the project i.e. in
Reasons for Delay
December’2016.
AK-24/01/2020

TPM_Broad Status Report (January-February’2020) 61


Commissioning Schedule
Sl.
Original Actual (A) / As
No. Capacity
PROJECT DETAILS
(MW)
now Anticipated. Broad Status
Syn. COD Syn. Trial-run
Comm Comm COD
3 Obra-C 2X660 MW TPP, 1320 Unit-1:
UPRVUNL Boiler: • Erection Work of Furnace Front, Upper Vertical
(Obra, Dist. Sonebhadra), LHS Wall Panel for boiler in progress. RCC work in ER-
U.P. 01,ER-02,ER-04, Drive house-1 & 2, Pent house-3 in
U-1 660 08/20 12/20 02/21 06/21 progress
09/20 04/21 TG: Erection Work of Main Steel Structure for TBN
U-2 Building #1 & CCB Building are in progress
660 12/20 04/21 07/21 11/21
ESP: Preassembly work of casing Panel with columns,
12/20 07/21 Beams & Bracing of ESP#1 is in progress.
Original/Latest Cost : Rs.1041600 lakhs(Including IDC) Unit-2:
Expenditure Boiler: Steel Structure tier #1-#5,TBN Building #1 & CCB
2016-17 42377 Lakhs Building in progress RCC Work for ID Fan Unit #2 &
2017-18 28623 Lakhs Duct Support in progress
Cumulative Expenditure (up TG: Erection Work of Main Steel Structure for TBN
: Rs. 301819 Lakhs
to 12/19) Building #1 & CCB Building.
ESP: Pre-assembly works of casing panel with columns,
Date of Financial Closure : 13.11.2013 beams & bracing under progress
70% debt loaned from REC and 30% equity to be borne
by State Govt. BOP :
Type of fuel : Coal  Chimney: RCC Work for chimney shell in progress
Fuel Linkage : From Saharpur Jamrpani, Jharkhand Coal Block  Raw Water system: RCC work for RWPH forbay electrical
allocated to UPRVUNL with the project specified in the room under progress
end use plants for the Block/ MoU with MMTC for
imported Coal  CHP: Excavation, PCC & RCC Work for Stacker/Re-
Date of Main Plant : Order for main Plant Equipment (BTG) awarded to Claimer, Track Hopper, Wagon tripler & Emergency
Order/BoPs M/s. Doosan Power Systems India Pvt. Ltd. On reclaimer hopper complex, RCC Work for JT#5 & JT#4
22.12.2016 Column. CHP fabrication works for conveyor 10A/B,
SG package by M/s DPSI& STG package by M/s 8A/B,7A/B,5A/B & stringers in progress.
Alstom Bharat Forge Power Ltd.  AHP: RCC work for Ash slurry pump house i/p
Zero date : 22.12.2016
 IDCT:
Land : Not required being an expansion Project
PPA : Signed with UPPCL on 16.01.2013  CWPH: • PCC & RCC work of CW treatment shelter, CW
Power Evacuation System By UPPTCL at 765KV Chlorination in progress
Water allocation Allocation of 54 cusec water by Govt. of UP from  PT Plant: RCC for HRSCC Tank-A, Cascade Ariator,
Rihand Reservoir Excavation of CW Chlorination Building in progress
MOE&F clearance 21.06.2016  DM plant:
Civil Aviation clearance 22.07.2009 and revalidated on 12.07.2016
 Switchyard: RCC Work for 400kV GIS ground slab &
brick work for wall & 765kV AIS Building column,
Switchyard Fdn. & Pedestal in progress.
 FGD: PCC & RCC Work for FGD MCC building in
progress. PO placed for FGD Duct Bearing, GGH, insulation
accessories
Critical Areas/Assistance
Required
AK-11/02/2020

TPM_Broad Status Report (January-February’2020) 62


Commissioning Schedule
Sl. No. Original Actual (A) / As now
Capacity
PROJECT DETAILS Anticipated. Broad Status
(MW)
Syn. COD Syn. Trial-run
Comm Comm COD
4 Jawaharpur STPP (2X660 1320 Unit-1:
MW ) Boiler: Erection of steel structure Tier 2,3 & 4 for Boiler # 1,
JVUNL (100% subsidiary Foundation work for Mill & Duct Supporting Structure are in progress.
of UPRVUNL) Air Duct & Gas Duct pre-assembly work for Boiler in progress. Burner
Village: Malawan, Lifting work Boiler Front 1st Row Foundation & Pedestal work for ID
Dist. Etah), U.P Fan & FD Fan in progress
TG: RCC column and Condenser Wall for TG pedestal in progress. TG
U-1 660 08/20 12/20 08/21 12/21 top slab staging, shuttering and embedded item R/F fixing work for
09/20 09/21 Grid (04~08) in progress. Condenser pre- Assembly for HP & LP
condenser in progress
U-2 660 12/20 04/21 02/22 06/22 ESP: Erection of ESP structure- A& B Pass& Hopper Bin Fabrication
01/21 02/22 welding in progress
Original/Latest Cost : Rs.10566.27 cr Unit-2:
Cumulative Expenditure : Rs. 3968 cr (02/20) Bolier: Erection of Boiler steel structure Tier 1, Tier 2 and Tier 3
(up to 12/19)
Type of fuel Coal TG: Foundation and Pedestal work for STG Building, CEP/CW pit, TG
80% debt loan from M/s PFC/REC and 20% state Raft
Date of Financial Closure equity. Out of 80% loan 50% from PFC & 50% ESP: Pedestal and backfilling work in progress
from REC agreement signed
Order for main Plant Equipment (BTG) awarded to BOP
Date of Main Plant
M/s. Doosan Power Systems India Pvt. Ltd. On  Chimney:RCC Shell work for chimney in progress.
Order/BoPs  Raw Water system: Foundation (RCC) work for Raw water
22.12.2016
Zero date 22.12.2016 reservoir-A, HDPE lining & motor and sand bedding in progress
Coal allocated from Saharpur Jamarpani Coal Block, Excavation work for raw water Reservoir-B in progress
Coal Linkage/FSA
Jharkhand (25.03.2015)  DM Plant: Column work for DM Plant building and backfilling work
Signed on 31. 12.2016 with UPPCL for electrical Building in progress
PPA
 CHP: Foundation for underground Tunnel (JT-1 to PH-1), Slab
Power Evacuation System 765 KV, 400 KV, 220 KV
scaffolding, Form, Rebar work, Water proofing, backfilling for
The land required is 865 acres for the proposed
Land Emergency ReClaimer hopper, Excavation and foundation work for
plant at Malawan is in possession of JVUNL
Received on date 26.10.2016 coal stock yard. Excavation and foundation work for Drive house.
MOE&F clearance
Foundation work for Conveyor 5A/5B, 2A/2B, YBC -1A, YBC-1B, YBC-
Water 09.11.2009, 53 Cusec from U.P. irrigation
1C and BC-4A/4B. Steel Structure erection for JT-10 and JT-05
Civil Aviation clearance 12.06.2015 for Chimney Conveyor 5A/5B (JT-06 ~ JT-08) structure fabrication and erection in
progress
 AHP: Embankment, rock toe and sand chimney, Bottom Excavation
work for ash dyke-A, Embankment, Rock toe & Crushed rock work for
ash dyke-B in progress
 NDCT: - Foundation for Basin Floor (1st and 2nd layer) and pedestal
work for NDCT –B in progress Foundation work for Basin Floor (2nd
layer), Grillage footing, Partition Wall, Hot & Cold water duct and
Precast for NDCT –A
 CWPH: CW pump station & CW Forebay intake wall shuttering & re-
bar work and volute 2nd stage re-bar and form work alignment in
progress.
 PT Plant: Grade slab PCC work for PT plant shelter in progress
 Switchyard: Finishing work (Celling and Epoxy painting for Floor)
for 220KV GIS Building.220 KV Hall HVAC duct support erection,
Super structure work for 400kV GIS building, 765kV GIS building
Brick work, Plastering and cable trench 765 KV GIS HVAC Duct
assembly and erection work Foundation & pedestal (Raft & Column),
Back filling & Trench work for 220 kV, 400 kV & 765kV in progress

Critical Areas/Assistance Delay in Unit 1 & 2 COF will be approx. 12.2 months as compared to the baseline schedule of 21st Dec. 2020. The efforts are being
required made to catch up the baseline schedule with below catch-up activities:
- Acceleration effort for various work activities like
(a) day & night shift work for piling and steel structure fabrication (TG & CCB)
(b) working on Sundays and holidays
(c) Emphasis on maximizing pressure part pre-assembly at ground level
(d) Subcontract with additional vendors for Boiler steel structure supply
(e) Acceleration work for TBN pedestal
AK-24/01/2020

TPM_Broad Status Report (January-February’2020) 63


Sl. No. Capacity Commissioning Schedule
PROJECT DETAILS (MW) Broad Status
Original Actual(A) / As now
Expected
Syn. COD Syn. Trial-run
com. com COD
State Sector
5. Panki TPS Ext, 660 09/21 01/22 09/21 01/22 Unit-1:
Distt. Kanpur, U.P. 12/21 12/21
(UPRVUNL) Boiler:
U-1 660
Original/Latest Cost : Rs / lakhs TG:
Exp.During 2018-19 : Rs 1600 lakhs
Exp.During 2019-20 : BOPs:

Cumulative Exp.upto Rs 1600 Lakhs Chimney:


April,2018 CHP:
AHP:
Type of fuel : Coal
CWPs:
Zero Date 31.03.2018 IDCTs:
.
Date of Main Plant Order EPC package to M/s BHEL. FGD:
(BTG) LOA date: 31.03.18.

MOE&F clearance:

Critical Areas
Reasons for Delay

TPM_Broad Status Report (January-February’2020) 64


BROAD STATUS OF THERMAL POWER PROJECTS IN UTTARAKHAND

Unit Commissioning Schedule


Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ COD Synch/ Trial-run
Comm Comm COD
Private Sector
1. Kashipur Gas Based GT-1 75 11/11 11/11 * OPEN CYCLE
CCPP, Ph-II 11/11 GT-I&II
(M/s Sravanthi Energy GT-2 75 11/11 11/11 * * All civil works are completed in 08/11. Both the gas turbines (6FA, GE
Private Limited), 11/11 France) & generator erection already completed. Cranking of GT
Udhamsingh Nagar ST 75 12/11 12/11 * completed. Both the GTs are on turning Gear. Waiting for gas
12/11 COMBINED CYCLE
(2GT +1ST=225MW) HRSG-I&II:
Original / Latest Cost Rs.89800 Lakhs / Rs. 130000 Lakhs Erection of HRSG equipment supply completed. Erection of both the
Expenditure during 2010-11 Rs.70500Lakhs HRSG nearing completion. HT of both the HRSGs expected just after
Expenditure during 2011-12 Rs. 11500 Lakhs erection is completed.
Expenditure during 2012-13 Rs. 7100 Lakhs
Expenditure during 2013-14 Rs. 1200 Lakhs ST:
Expenditure during 2014-15 Rs. 800 Lakhs (up to 06/14) ST& STG supply received at site. STG erection completed. ACC erection
Total Expenditure : Rs.91100 Lakhs (Upto 06/14) is nearing completion. STG oil flushing completed. STG yet to be put on
BG.
Approval date: : NA
Zero date: : 04/11/10 BoPs:
Notice To Proceed (NTP) : 04/11/10  All the BoPs are ready.

Stressed Project
Financial closure Achieved on 04/11/10
Main Plant Order : 04/11/10 on M/s Sravanthi Infratech Private
*Schedule will be decided after availability of gas
Ltd (EPC Basis).
BTG Make GTGs# GE, France(6FA), HRSGs#Greens
Power Equipments(China) Co. Ltd.and STGs
are from HTC China
BOP Package Common BoPs for Ph-I&II, Reputed Indian
Vendors
Type of fuel : Natural Gas (1.2 mmscmd)
PPA : PPa yet to be signed
Source and supply of Fuel :Domestic Gas from D-6, KG Basin (Right now E-
Bidding RLNG)
Power Evacuation system open access: Transmission with PGCIL for
450MW capacity power evacuations through
400 kV/220kV permission granted by NRLDC
on 29/12/10. Readiness of ATS through nearby
Grid sub-station is scheduled by 12/16.
 FSA yet to be signed.
 All statutory clearances are available.
 All the BOPs has already been commissioned.
 M/s TCE, Bangalore is the owner’s consultant.
 Gas pipeline connectivity completed.
 All common utilities are ready.
Critical issues Availability of Gas & PPA

Reasons for Delay Non-availability of Domestic Gas.

TPM_Broad Status Report (January-February’2020) 65


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
OriginalActual(A)/ As
No. (MW)
Expected
Synch/ COD Sync/. Trial-run
Comm Comm COD
Private Sector
2. BETA CCPP, GT-1 75 12/11 12/11 * OPEN CYCLE
Module-I, at 12/11 GT & GTG
Kashipur GT-2 75 12/11 12/11 * Both the gas turbines (6FA, GE France) & generators supply reached
(M/s BETA 12/11 * at site. Erection of both the GTs and GTGs has completed. Oil
INFRATECH ST 75 03/12 03/12 * flushing of both the GTs completed. Erection of GT exhaust duct
PRIVATE LTD.), 03/12 completed. By pass stack erection completed. Erection of diverter
Udhamsingh Nagar and damper completed. GT is ready to put on turning gear.
Commissioning in open cycle is possible within one month from
(2GT +1ST=225MW) availability of gas
Original /Latest Cost : Rs. 93600 Lakhs / Rs. 125400 Lakhs
COMBINED CYCLE
Expenditure during 2010-11 : Rs. 4649 Lakhs
HRSG-I &II
Expenditure during 2011-12 : Rs. 74994 Lakhs
Both the HRSGs order have placed on M/s Thermax (India)
Expenditure during 2012-13 : Rs. 20008 Lakhs
23/10/10. HRSG erection completed. HT of both HRSGs completed.
Expenditure during 2013-14 : Rs. 16000 Lakhs
HRSG is ready for ABO.
Expenditure during 2014-15 : Rs. 2913 Lakhs (upto 06/14)
Total Expenditure : Rs. 118564 Lakhs (Upto 06/14) ST:
Approval date: : NA ACC erection started on 01/05/12. ACC erection is under progress.
Zero date: : 04/12/10 ST order has placed on M/s G.E. on 04/12/10 and completed. TG
Notice To Proceed (NTP) : 04/12/10 erection started 26/04/12. TG Box Up completed. ST synchronization
Financial closure : Achieved is expected within two and half month from availability of gas.
Main Plant Order : 20/09/10, 04/12/10 And 23/10/10 on M/s Combined cycle commissioning is expected within 3month from
BETA Infraprop (P) Ltd (EPC Basis) through availability of gas.
ICB route.
BoPs:
BTG Make GTGs# GE, France(6FA), HRSGs# Thermax
(India).and STGs are from HTC China
 All the BoPs are either already completed or nearing
BOP Package : Reputed Indian Vendors
completion.
Type of fuel : Natural Gas
PPA Yet to be signed
Source and supply of Fuel Domestic Gas from D-6, KG Basin (Right now *Schedule will be decided after availability of gas
E-Bidding RLNG)
Power Evacuation system Connectivity of the plant with 220/132kV
Mahua Khera Ganj substation has been
approved. LILO of 220kV circuit from
400kV Kashipur to 220 kV Mahua Khera
Ganj is nearing completion. Long Term
Access (LTA) from 220kV/132kV Mahua
Khera Ganj sub-station has been approved by
PGCIL.

 FSA yet to be signed


 All statutory clearances are available.
 All the BOPs are either already completed or nearing completion.
 Both the gas conditioning skids are yet to be made ready.
 Gas in gas pipeline charged upto GAIL skid inside the project.
 Switchyard with control room is ready.
Critical issues Availability of Gas and PPA
Reasons for Delay Non-availability of Gas.

TPM_Broad Status Report (January-February’2020) 66


BROAD STATUS OF THERMAL POWER PROJECTS IN CHHATTISGARH
Unit Commissioning Schedule
Sl. Project Details Cap. Original Actual(A)/ As Broad Status
No. (MW) Expected
Synch/ Trial Sync/. Trial Run
Comm Run Comm /COD
/COD
Private Sector
1 Akaltara(Nariyara) Unit-1 (U-3) : COD achieved on 14/08/13.
TPP, U-1 600 02/12 04/12 18/05/13 (A) 14/08/13(A)
(Distt: Jangir-Champa) (U-3) 04/12 13/08/13 (A) Commissioned on 13/08/13. Synchronised on
M/s KSK Mahanadi 18/05/13.
Power Company Ltd. U-2 600 06/12 08/12 08/08/14(A) 26/08/14(A)
(Formerly Wardha (U-4) 08/12 22/08/14 (A) FGD: FGD plant expected in 6/22.
Power Company Ltd)
U-3 600 10/12 12/12 12/17(A) 21/01/18(A)
(U-2) 12/12 18/01/18(A)
Unit-2 (U-4) : COD achieved on 26/08/14.
(6x600MW=3600MW) U-4 600 02/13 04/13 08/21 08/21 Commissioned on 22/08/14. Synchronized on
(U-5) 04/13 08/21 08/08/14.
U-5 600 06/13 08/13 11/21 11/21
(U-1) 08/13 11/21 FGD: FGD plant expected in 08/22.
U-6 600 10/13 12/13 02/22 02/22
12/13 02/22
Unit-3 (U-2) : COD achieved on 21/01/2018.
Orgiginal Cost / Latest : Rs.1619000 Lakh / Rs. 2708000 lakhs Commissioned on 18/01/18. Synchronised in
Cost 12/17.
Exp. During 10-11 : Rs. 45529.8 Lakh
Exp. During 11-12 : Rs. 821600 Lakh FGD: FGD plant expected in 10/22.

Stressed Project
Exp. During 12-13 : Rs. 222416 lakhs
Exp. During 13-14 : Rs 209517 lakhs Unit-4 (U-5)
Exp. During 14-15 : Rs.164917 lakhs  Boiler. :Boiler erection started on 08/12/11. Boiler Drum lifted on
Exp. During 15-16 : Rs. 90320 lakhs 31/08/16. Pressure parts and joints erection is in progress. Duct
Exp. During 16-17 : Rs. 318700 lakhs erection work is in progress. Boiler Hydro Test yet to be happen.
Exp. During 17-18 Pedestal work in progress. Work at site is on hold.
Total Exp.( upto :Rs. 1873000 Lakhs TG: TG Deck casting completed on 06/10/12. Various level floor
12/16) castingwork in progress.
Approval date: NA FGD: FGD plant expected in 12/22.
Zero date: : 21/04/09 Unit-5 (U-1)
Financial closure : Achieved on 30/03/10 Boiler.: Boiler erection started on 06/02/12. Foundation work is
EPC Order : EPC ordered on 21/01/09 on SEPCO (China) completed. Balance work in progress.
Package(BTG) (Boiler-Shanghai Boiler Works, China), TG: TG raft and main coloumns casted and column TG Deck casting is yet
(TG-Dongfang Electric Company, China) to be completed.
Type of fuel Coal FGD: FGD plant expected in 02/23.
PPA PPA: PPA signed with Gujarat Urja Vikas Nigam Ltd for 1010 MW on Presently order was placed for techno-commercial feasibility study
03/06/10. with black and veatch for all six units.
PPA signed with APCPDCL for 400 MW on 31/07/12. Unit-6
PPA signed with CSP Trade Co for 225 MW on 18/10/13 Boiler:Boiler raft casting completed. Boiler erection yet to start.
PPA signed with TANGEDCO for 500 MW on 27/11/13 Foundation work is completed
PPA signed with UPPCL for 1000 MW on 26/02/14 TG:TG raft casting completed and column casting is in progress. Deck
Power Evacuation Power is to be evacuated to PGCIL pooling station through 400kV casting yet to be completed.
system transmission system. Final bulk power transmission agreement signed with
PGCIL on 25/02/10. FGD: FGD plant expected in 04/23.
 Land: Complete land for the project is under possession.
FGD draft report received and Detailed
 MOE&F: Received on 19/10/09 Feasibility Report under preparation
State Pollution Control Board: Chhattisgarh Environment Conservation Board (CECB) granted BoPs:
“consent for Establishment” for 6x600 MW on 16/02/10.
Chimney-: Chimney 3,4 & 2 are in service. Flue Cans Erection completed
State pollution Control Board Clearance: Chhattisgarh Environment Conservation Board
(CECB) has granted ‘Consent for Establishment for 6x600 MW power plant of WPCLCG on for all
16/02/10. CHP: Ready in all respect
 Civil Aviation: NOC received on 12/05/09.  AHP: Ready
 Water: Water Resources Department, Govt., of Chhattisgarh has allocated 100  Raw Water Supply System: Water Resources Department, Govt., of
MCM of water /year from Mahanadi River from proposed anicut at Basantpur. Chhattisgarh has allocated 100 MCM of water /year from Mahanadi
 Coal linkage: SECL (Tapering coal linkage to 3x600MW only) Letter of Assurance(LOA) River
for tapering coal linkage to 3x600 MW has been granted by SECL on 11/06/09. FSA has been  PT/ DM Plant: Three streams are commissioned and in operation.
executed with SECL on 19/03/14 for 2 units. Tapering FSA for U-3 has been executed with  CW System: majority of work has been completed. Only Connection
Eastern Coalfields Ltd on 12/08/14. between CW piping is pending for Unit #5 &6.
 As per the letter dated 18/10/16  IDCT: IDCT for U-1(3), 2(4) & U-3(2) are in service and for rest of
Coal blocks of Gujarat and Goa linked to the power project for cancelled by Supreme court. unit’s erection works are in progress.
Tapering linkage granted for 1800 MW was also cancelled by the Ministry of Coal on  FOPH: Fuel oil distribution system commissioned
30/06/13. Long term coal linkage is required for the power project, for which policy is under  CCR Building is ready for all units.
formulation with GOI.  Switchyard: Back charging of 400kV switchyard completed on
27/08/2012. Control building is in service.
Critical issues Coal Linkage to remaining 3 units.
Reasons for Delay Delay due to shortage of manpower and agitations by Villagers. Supply of material due to shortage of funds.
* Unit numbering is given as per order of commissioning. Unit numbering given in brackets is as per original nomenclature.
SK-11.06.19

TPM_Broad Status Report (January-February’2020) 67


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch/ COD Sync/. COD
Comm Comm
2 Uchpinda TPP U-1 360 03/12 - 28.02.15 (A) 26.11.15(A) Unit-1 : COD achieved on 26.11.2015.
Unit-1(Ph-I)[] 05/12 28.10.15(A)
Unit-2,3&4(Ph-II) Commissioneed on 28.10.2015.
U-2 360 09/12 - 07.01.16 (A) 12.02.16(A)
R.K.M Power, Janjgir
11/12 28.01.16(A)
Synchronized on 28.02.15.
Champa District,
U-3 360 12/12 - 31.08.17(A) 14.11.17(A)
Chhattisgarh
02/13 12.09.17(A)
(4x360MW=1440MW) U-4 360 05/13 - 06.03.19(A) 20.03.19(A) Unit-2 : COD achieved on 12.02.2016.
07/13 06.03.19(A)
Commissioneed on 28.01.2016. Synchronized
Org.Est. cost / latest cost ( h-I- : Rs. 665361 Lacs /1037733 lakhs/ 1178451 on 07.01.2016.
148750 lacs/ 263835 lacs
Ph-II – 516611 lacs / 914616 lacs )
Exp. During 07-08 : Rs. 1270 Lacs
Exp. During 08-09 :Rs. 12311 Lacs Unit-3 : COD achieved on 14.11.2017.
Exp. During 09-10 : Rs. 37363 Lacs Commissioneed on 12.09.2017.
Exp. During 10-11 : Rs. 67641 lacs
Exp. During 11-12 : Rs. 153338 lacs Synchronization on 31.08.2017.
Exp. During 12-13 : Rs. 277291 lacs
Exp. During 13-14 : Rs. 255521 lacs
Exp. During 14-15 : Rs. 119057 lacs
Exp. During 15-16 : Rs 99890 lacs Unit-4 : After getting CTO on 25.02.2019,
Exp. During 16-17 : Rs 106584 lacs COD achieved on 20.03.2019.
Exp. During 17-18 : Rs 12476 lacs
Cumm Exp. (Up to 10/17 ) : Rs.1141842 lacs
Commissioneed on 06.03.2019.
Zero date: : 01/06/09 Synchronization on 06.03.2019.
Financial closure : 07/06/10 (Ph-II)
02/01/09 (Ph-I) BoPs:
Main Plant Order 06/09. on M/s MIPP International.  Chimney: Chimney-1 Shell construction work
Boiler: China Western completed (270m). Flue erection and insulation for U-
TG: Harbin 1&2 completed.
Chimney-2: Shell construction work completed (270m).
BOP Package GM technical services, Ph-1 & 2 18/01/2011 erection and insulation for U-3&4 completed
.  CHP: Phase 1 & 2 completed in all respect.
Type of fuel Coal  AHP: BAHS for U-1,2,3&4 completed.
PPA : Signed with CSEB for 37.5% on 29/09/06 and PTC for sale of 300  PT/ DM Plant: Three streams are commissioned and in
MW on 08/05/09. PPA for sale of 350 MW signed with UPPCL on operation. Forth stream commissioning to be done
15/03/16.  CW System: CW pump house-1 civil work completed
Power Evacuation system BPTA signed with PGCL on 25/02/10. BG for Rs. 40.95 cr given CW pump house-2 civil work completed and CW
to PGCL.Detail route survey completed Route alignments pumps erection is completed. CW piping for unit-
completed. TSA agreement signed on 06/08/12 1,2,3&4 is completed
 Land: Total 900 acres’ land acquired. Govt. land: 104 acres & private land 645.51 acres. 94.17  Cooling Tower: Aready Commissioned.
acres Govt. land allocated for green belt development.  FOPH: HFO & LDO storage tanks erected and
 MOE&F: Obtained on 26/08/08. insulation completed
 Civil Aviation: AAI issued NOC on 05/09/2008.  Switchyard: Completed in all respects.
 Water: 44.83 MCM per annum.
 Coal linkage: FSA signed with SECL for Phase-I on 03/09/13 and phase-II on 23/09/13. FGD: Vendor identification under
process.
Critical issues Consent to Operate-Due to non availability of CTO, Developer is not able to commission the Unit 4. Tapering coal linkage has been cancelled by SECL. BG
to be issued to release FDR amounts paid customs. PPA issue- CSPTCL has expressed inability to offtake power as per PPA. Working Capital required for
starting operation of U-1 is 153 cr & for U-2,3,and 4 is 571 cr.Readiness of Railway siding(work delayed due to land acquition because of new land
acquition policy and funds)
Reasons for Work suffered due to agitation by villagers. Slow progress of work at site. Delay in readiness of BoPs. Delay in readiness of startup power. Delay due to
Delay financial problems. Balance land acquisition for Ash pond and railway line. Consent to operate for U-2,3&4.

TPM_Broad Status Report (January-February’2020) 68


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch/ COD Sync/. Trial-run
Comm Comm COD
3 Lanco Amarkantak Mega TPS 3 660 01/12 - * * Unit-3
( Pathadi ) 01/12  Boiler: erection started on 09/10. HT completed on
(Distt. Korba ) 22/07/16. BLU delayed due to non-availability of
M/s LAP Pvt. Ltd. 4 660 03/12 - * * start-up power.
Phase-II 03/12
(2x660MW=1320MW)  TG: Condenser erection started on 1/05/11 and
completed & partially tube leak test completed. TG
Original /Latest Cost Rs.688600 Lakhs/ Rs770000 Lakhs/Rs. 1081524 lakhs erection started on 11/10/11. TG Box up completed
on 26/11/16.
Expenditure during 2007-08 Rs. 189 lakhs
Expenditure during 2008-09 Rs. 209 lakhs  ESP: Pass B ATT completed. Pass C ATT is also
Expenditure during 2009-10 Rs. 9841 lakhs completed.
Expenditure during 2010-11 Rs.206364 lakhs
Expenditure during 2011-12 Rs 262658 lakhs
Expenditure during 2012-13 Rs. 125739 Lakhs Work is held up at the site due to fund constraints
Expenditure during 2013-14 Rs. 12500 Lakhs since 07/17.
Expenditure during 2014-15 Rs. 61445 Lakhs 
Expenditure during 2015-16 Rs 165255 Lakhs Unit-4
Expenditure during 2016-17 Rs 109579 Lakhs  Boiler: Boiler erection started on 1/12/10

Stressed Project
Expenditure during 2017-18  TG: Condenser erection started on 11/11/11. TG
Total Expenditure Rs. 953779 lakhs ( up to 12/16) Deck casting completed & TG erection stared on
Zero date: 17/11/09 15/05/13
 ESP: All 4 passes are under progress.
Financial closure : Achieved in March,2011
Main Plant Order : Unit-3 &4: Main plant package (BTG) awarded on 17/11/09
to M/s DEC BoPs:
BOP Package Main plant package (BTG) awarded on 17/11/09 on M/s DEC
as vendor and award of contracting agency on 12/11/09 on  Chimney: RCC shell completed. Flue can erection
M/s HTC/HEC. work completed for U-3. Flue can assembly work is
u/p. Structure erection 76% completed. Stack elevator
Type of fuel Coal erection, alignment & commissioning completed.
PPA PPA signed with CSP Tradeco for 35% home state share on  CHP: Track hopper work completed. Crucher house
04/01/11 erection work is u/p. TP 11,7,8,9 structural erection
Power Evacuation system LTOA approved and BPTA signed on 24/02/10. Pooling completed. Equipment erection is u/p.
station location at Champa to be confirmed by PGCIL to  AHP: Ash slurry pump house; All civil work
start survey. completed. Paving& finishing are u/p. fly ash tower
 Land: Total land requirement for U-1,2,3,&4 is 1395 acres out of which 791 acres already work completed.
acquired. For the entire balance land, section 4,6 &9 completed. Lease deed is to be  Cooling Tower: 10985m3 RCC casting completed.
registered shortly. (Lease deed signed for 90% of total land with CSIDC, Raipur and All 24 nos deck slab completed in CU-3. 8979m3
balance is Under process). RCC casting completed and 24 nos deck slab
 MOE&F: MOEF clearance for unit-3 received on 04/09/08 & renewed on 19/02/14 up to completed in CT U-4.
12/2017 and for Unit-4 on 26/05/10 & renewed on 22/06/15 up to 12/2017.  Raw Water Supply System: river water intake
 Civil Aviation: NOC for 275 m. Twin flue chimney was obtained on 25/08/08 from AAI. pump house slab casting completed. RCC work &
backfilling completed in forebay. Pump house
 Water: Sanction of Water requirement of 54 MCM from Hasdeo river for U-3 & U-4
MCC room- slab casting completed.
received from Govt. of Chhattisgarh.
 PT/ DM Plant: PT plant-RCC work is completed.
 Coal linkage: U-3: LOA issued by SECL on 06/06/09. All milestones achieved.
Pumps erection is u/p. DM pant- DM plant
Letter submitted to SECL. FSA signed for U-3 on 27/08/13 U-4: LOA issued by SECL on
building, erection, alignment and grouting of
03/06/10. All milestones achieved. Letter submitted to SECL. FSA signed on 27/08/13.
vessels are u/p. DM water storage tanks are also
ready.

 FOPH: LDO & HFO tank erection & NDT wok


completed. Erection of all pumps completed. Piping
work is u/p.
 Switchyard: Switchyard building, switchyard
tower, gentry erection SCADA commissioning &
testing of all equipment is completed

Critical issues Additional land acquisition is in progress.


Reasons for Delay Delay in acquisition of land for water system. Post award change in specification like high density system in AHP and wagon trippler
in CHP due to statutory compliance and other constrains like.
Frequent stoppage of construction work by local people and land loser.
Presently work is held up at site due to financial constraints

*Due to insolvency problem, project activities are on hold. The commissioning schedule will be decided after restart of work.

TPM_Broad Status Report (January-February’2020) 69


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
Original Actual(A)/ As
No. (MW)
Expected
Synch/ COD Sync/. COD
Comm Comm
4 Salora TPP U-1 135 06/11 - 04/09/13(A) 01/05/14(A) Unit-1
(Katghora Tal; Distt. 06/11 10/04/ 14(A) COD achieved on 01/05/14. Commissioned on
Korba) U-2 135 09/11 - Uncertain Uncertain 10/04/14. Unit synchronized on 04/09/13.
M/s Vandana Vidyut Ltd 09/11
 Boiler:
(2x135=270MW) Erection of Boiler-1 started in 11/10. Boiler Drum
lifted on 23/02/11. HT completed on 28/01/12. BLU
Original / Latest Cost :Rs 1458.44 Cr./ Rs. 1458.44 Crs. completed on 06/03/13. SBO completed. TG: TG
Exp. During 2009-10 :Rs 14441 lakhs erection started in 11/11and TG box-up completed in
Exp. During 2010-11 : Rs . 43617 lakhs 07/12.
Exp. During 2011-12 : Rs . 88942 lakhs
Exp. During 2012-13 : Rs . 38000 lakhs  Unit-2
Exp. During 2013-14 : Rs . 38657 lakhs  Boiler:
Exp. During 2014-15 : Rs.15032 lakhs Boiler erection started in 11/10 and drum lifted in
04/11. HT completed in 10/12. BLU completed in
Cumm. Exp. ( up to 03/15) : Rs.238689 lakhs 09/14 and steam blowing completed in 10/14.
BOP Package LOA has been issued on 21/11/08 on M/s Cethar Vessels Delay due to supply of boiler material & CHP
Ltd , Thiruchirapalli on BTG basis , Boiler : Cethar material by M/s Cethar Vessels Ltd.and delay in

Stressed Project
Vessels Ltd, Turbine Genarator: M/s Harbine Turbine getting of startup power. Delay due to agitation by the
Co.Ltd, China villagers at project site.

Type of fuel Coal  TG: erection started in 11/11and TG boxed-up 09/14


PPA 50 MW to TNEB through NVVN ( Short term basis) for and put on barring gear in 10/14.
one year. PPA was signed with CSPTCLL on 05/01/11
BoPs:

Power Evacuation PGCIL granted LTOA & BPTA executed on 24/02/10.  Chimney: Flue can erection completed.
system LILO line construction is completed. Elect. Inspectorate  CHP: Under progress.
,CEA (WR) has given approval for LILO and 400 kV  AHP: Under progress.
switchyard on 04/08/12.  CW System: Under progress.
 Land: Land : Required 261 Ha , Possession : 260.899 Ha.
 MOE&F: obtained on 09/06/09.and State pollution clearance obtained on
09/03/09
 Civil Aviation: clearance obtained on 24/04/09
 Water: 18 MCM Water allocated by WRD, Govt.of C.G from Hasdeo River
 Coal linkage: Allocation of coal is from Fatehpur East Coal Block ( Jointly)
allotted by MOC and tapering coal linkage granted for 2x135 MW on
29/01/10 from SLC, LT meeting of MOC, for 2nd phase of 1x270 MW under
process with MoC. Carpet coal recommended for CEA for startup of 1st unit.

Critical issues Start up / carpet coal MOU is pending with SECL. FSA execution is pending with SECL
Turbine -2 was ready from last 9 months ( as on 09/14), Foe commissioning HEC/HTC Engineers are required. AVR Feed back
Card- pending from long time, LVDT replacement- All the LVDT are not working. Rotor stoppage alarm panel to be supplied,
supply of Technical data sheet of TG instruments and ISCAN-2 for Unit-2 as per letter dated in 09/14
Reasons for Delay Delay in commissioning of U-1.Agitation by villagers at site. Delay in sullpy of BTG and CHP material. Non corporation of BTG
supplier in commissioning activities. Acquisition for railway siding and ash pond.

TPM_Broad Status Report (January-February’2020) 70


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch Comm Syn. Comm
COD
5 Deveri TPP Raigarh TPP U-1 600 06/13 08/13 Uncertain Uncertain Unit-1
(Visa)  Boiler:
(VISA Raigarh STPP, Ph-I,) U-2 660 Uncertain Uncertain Boiler erection started on 30/09/11. 8th tier
(Distt: Jangir Champa) erection completed. Ceiling girder A, B, C, D,
M/s VISA Power Ltd. E& F erection completed. Work held up due to
financial Problems.
(1x600+1x660=1260MW)
Org. Est. cost for both the units :Rs. 619000 Lakh  TG:
Unit-1 cost : Rs. 261870 lakhs TG deck raft completed and shuttering work
Unit-1 Latest cost ; Rs. 393000 lakhs final deck casting U/P. EOT crane erected and
Exp. During 10-11 : Rs. 51763 lakhs commissioned.
Exp. During 11-12 : Rs. 53457 Lakh  ESP: Pass A casing erection work completed.
Exp. During 12-13 : Rs. 15481 Lakh Suspensions for electrodes erection completed.
Exp. During 13-14 : Rs. 47890 Lakh Erection of collecting electrodes up to 10th
Exp. During 14-15 : Rs. 36759 Lakh field completed. Hopper top part erection

Uncertain
Exp. During 15-16 ( Up to : Rs. 2373 Lakh completed in all 10 fields.
11/15) Pass B: Column erection work completed.
Pass-C- electrode erection completed in all 10
Cumm. Exp (11/15) : Rs. 207723 lakhs
fields.
Approval date: Pass D: Casing erection completed. electrode
Zero date: 09/08/10 erection
Financial closure Achieved for both the units
Main Plant Order BTG Contract awarded on 28/06/10 to M/s BHEL (Boiler-
BHEL) (TG- BHEL) BoPs:
BOP Package The order for all the BOPs on EPC basis including civil works
have been placed on M/s L&T on 29/09/10. BHEL (Trichy)  Chimney: Foundation works completed and
supplied 13031 MT for Boiler & BHEL(Ranipet) 7340MT for shell casting work U/P. Chimney awarded to
ESP up to 11/2014 out of which 5792 MT of Boiler & 3749 MT Bygging India Ltd on 15/01/15
of ESP erected. BHEL (PSWR) supplied 3863 MT of bunker  CHP: PCC in wagon tippler & TP-2 area is
structure material, out of which 2261 MT bunker structure U/P.
fabricated. BHEL piping center (Chennai) supplied 1235 MT Coal Mill & Mill Bunker Building: All mill
Type of fuel Coal foundation & bunker pedestal casting
completed. Bunker structure and shell
PPA PPA Signed with CSPTCL & WBSEDCL for 424 MW & 200
fabrication under progress.
MW and WBSEDCL for 200MW.
 Raw Water Supply System: Raw Water pipe
As per letter dated 14/01/14
line awarded to TATA Projects Ltd. On
PPA signed with WBSDCo. Ltd on 04/01/11 for 510 MW for 20
14/07/11
years through MOU route with 3part tariff (Cap. Charges+
energy Charges+ transportation charges). CSPTCo.Ltd an  CW System: Raw Water pipe line awarded to
authorised representative of GOCG to execute PPA with TATA Projects Ltd. On 14/07/11
Developers on behalf of the GOCG. This PPA is in line with the
implementation agreement executed with GOCG  IDCT: CT awarded to Paharpur cooling Towers
Power Evacuation system Awarded the contract for construction of 400kV D/C transmission 25/01/12. IDCT-I &2 excavation work
line on M/s KEC on 24/06/11. From PGCIL S/S at New Kotra. completed.
400/765 Kv Pooling station for power evacuation –bays
construction given to Alstom T7D on 31/12/11.  Switchyard: Foundation works completed and
BTPA 24/02/10 shell casting work U/P.
 Land: Delay in land acquisition & delay in placement of orders for BoPs. Delay in
supply of boiler drum by BHEL. Work is on hold due to Financial crunch.
 MOE&F: MOEF clearance obtained on 23/08/11
Amendment in MOEF clearance issued on 20/05/14 regarding the reduction in project
area of 780 acres to 637 acres.
Fatehpur coal block allocated to the Visa Power.
 Civil Aviation: clearance from AAI received on 25/05/10.
 Water: Water allocation received from WRD, Chhattisgarh for 35 MCM on 26/09/09
 Coal linkage: Fatehpur East Coal Block jointly allotted. Domestic coal linkage applied.
FSA signed with Indonesian coal supplier (PT Kubara Bumi Lestari) for supply of
imported coal.
Critical issues Boiler Drum has not dispatched by the BHEL
Reasons for Delay Order of AHP,Fire protection system, AC & ventilation system,LT/Ht switchgear, cables, air compressor, LT transformers, station, GT &
unit transformer not yet placed. Work is on hold due to financial crunch.

TPM_Broad Status Report (January-February’2020) 71


Unit Commissioning Schedule
SI. Project Details Capacity Broad Status
Original Actual(A)/ As
(MW)
Expected
Synch/ COD Sync/. COD
Comm Comm
6 Singhitarai TPP U-1 600 10/14 - * * Unit-1:
( DumatpalliTPP) 11/14 Boiler
Janjgir (Vill) U-2 600 01/15 - * * Boiler erection started in 29/07/12.
Champa Distt. 02/15 Drum lifted on 07/04/13.
(M/s Athena Non-Drainable HT done on 08/10/15.
Chhattisgarh Power Work at site is on hold due to
Ltd) financial constraints.
(2x600=1200MW) TG
Original Cost/Latest : Rs. 620000 lakhs/ Rs. 811900 lakhs (844379 l lakh further TG erection started on 04/07/13.
cost revised) Condenser erection started on 16/05/13.
Exp up to 03/2008 :Rs. 371 lakhs Work at site is on hold due to
Exp 2008-09 :Rs. 3509 lakhs financial constraints
Exp 2009-10 :Rs. 6690 lakhs .
Exp. 2010-11 :Rs. 56343 lakhs Unit-2:
Exp. 2011-12 :Rs. 50204 lakhs Boiler
Exp. 2012-13 :Rs: 92116 lakhs Boiler erection started on 24/12/12
Exp. 2013-14 :Rs: 129337 lakhs Drum lifted on 30/10/13.
Exp. 2014-15 :Rs: 154090 lakhs Work at site is on hold due to
Exp. 2015-16 :Rs: 62395 lakhs financial constraints
Exp. 2016-17 : Rs. 74611 lakhs TG

Stressed Project
Exp. 2017-18 : Rs. 11181 lakhs TG erection started in 29/11/13.
Condenser erection started on 01/01/14.
Cum.Exp. up to 05/17 :Rs. 640847 lakhs Work at site is on hold due to
Zero date: 01/06/11 (NIT issued) financial constraints
Financial closure : Achieved (Common loan agreement signed on 30/03/11) BoPs:
Main Plant Order : Awarded on 21/12/09 to M/s DECL.
 Chimney: Erection of flue cans and stair
BOP Package M/s Abir infrastructure on 18/08/10
case completed External painting
Type of fuel Coal completed.
PPA Long term and short term PPA signed with PTC. 444 MW signed  CHP: Major Erection works completed.
with CSPT and 150 MW signed with Nepal electricity authority.  AHP: Major Erection/construction works
For 300 MW- LOI received & for 200 MW participated in Case-I completed.
bidding in RRVPN and 107.5MW praticipated in the case-I bid  Raw Water Supply System: RWIS from
invited by MP power mgmt. company ltd. For supply of river Mahanadi to ACPL-contract
107.5MW power on the long term bases. awarded on 16/05/11
Power Evacuation LTOA granted on 01/10/09. Signed BTPA with PGCIL for 683 Barrage construction completed &
system MW 24/02/10. ISTS approval received from PGCIL on finishing work in progress
14/06/11.Approval received form MoP for construction of NoC received from WRD, GoC for laying
400kV D/c dedicted line from ACPL to New Kotra(PGCIL). of pipeline along the canal on 31/10/10.
NOC for tower height clearance received for double and approval received for Nala crossing and
multiple circuit tower from AAI. road crossing. RWIPH construction
Test charging of 400kV transmission line-1 &2 completed. completed.
 Land: 927.275 acres of land in possession,25.96 Acres of Govt land
 PT/ DM Plant: First stream commissioning
leased to company..
 MOE&F: Obtained on 04/06/10.Amendment of EC received on 22/03/16 done in auto mode successfully &
 Civil aviation: Clearence received from AAi, Mumbai on 09/04/09 commissioning of other streams are in
 Water: 35 MCM per annum allocated from Mahanadi. progress.
 Coal linkage: FSA signed with SECL on 27/02/15 for supply of 2497242  CW System: Erection of motor & pumps
Tonnes/annum. completed.
 CT: all works completed.
 FOHS: No load trail run of motors
completed. Hydro test in progress for
pipes.
 Switchyard: commissioning works are
Completed.

Critical issues Delay in BTG erection work. Work at site is on hold due to financial constraints

Reasons for Delay Delay in Land Acquisition. Slow progress of boiler & TG erection. Delay due to financial problems

*Work at site is on hold due to financial constraints. The commissioning schedule will be decided after restart of work.

TPM_Broad Status Report (January-February’2020) 72


Unit Commissioning Schedule
Sl. Project Details Capacity Original Actual(A)/ As Broad Status
No. (MW) Expected
Synch/ COD Sync/. COD
Comm Comm
7 Binjkote TPP U-1 300 08/13 - 26/01/17(A) 06/10/17(A) Unit-1: COD on 06/10/17. Full load on
SKS Power Gen. (Chhattis.) 09/13 25/04/17(A)
Ltd. Vill-Binjkote, Distt.:
25/04/17. Syn on 26/1/17.
Raigarh, Chhattisgarh Boiler:
U-2 300 11/13 - 12/17(A) 01/04/18(A)
Boiler erection started on 12/06/12. Boiler drum
12/13 28/03/18(A)
(4x300=1200MW) lifted on 02/05/13. HT conducted on 27/06/14.
U-3 300 02/14 - * *
BLU completed on 09/07/16
03/14
TG :
U-4 300 05/14 - * * Condenser erection started 04/14. TG erection
06/14

Uncertain
started in 05/14. TG box up completed on
Original Cost /Latest Cost: : Rs. 505800 lakhs / Rs. 689000 lakhs / Rs. 794000 lakhs 09/08/16.
Ph-I: 3787.2 Cr& Ph-II :
3106.8 Cr /Latest Cost : Ph-I
: 5240Cr & Ph-II: 3200 Cr Unit-2 : COD on 01/04/18. Full load
less 500 Cr on 28/03/18. Syn on 12/17.
Exp. During 2008-09 : Rs 4000 lakhs
Exp. During 2009-10 : Rs. 5225 lakhs Boiler :
Exp. During 2010-11 : Rs. 21435 lakhs Boiler erection started on 08/09/12. Boiler drum
Exp. During 2011-12 : Rs. 55000 lakhs lifted on 30/05/13. Boiler light up has completed
Exp. During 2012-13 : Rs. 126590 lakhs on 27/03/17. EDTA cleaning done on 03/05/17
Exp. During 2013-14 : Rs. 46778 lakhs Steam blowing completed in 11/17.
Exp. During 2014-15 : Rs.112677 lakhs TG :
Exp. During 2015-16 : Rs. 11095 lakhs( up to 06/15) Condenser erection started in 01/15. TG erection
Started in 09/14. TG put on barring gear on
Cumm. Exp Up to 06/15. : Rs 382800 lakhs 30/08/17.
Approval date: SKS signed an MOU with Govt. of Chhattisgarh on
07/01/08.for setting up coal based TPS. Unit-3:
Zero date: : 12/05/11 Work yet to start
Financial closure : completed
Main Plant Order : M/s Cethar Ltd. On 02/03/11. Boiler- Cethar Ltd. trichy, India Unit-4:
and TG - Harbin, China Work yet to start
BOP Package * The dates would be decided after start of
Type of fuel Coal Boiler erection start.
PPA 37.5% of 1200 MW with CSPTRADECO.
550 MW with TPTCL. Participated for 100 MW in Case-I BoPs:
bidding in RVPN.  CHP: Ready in all respect.
Power Evacuation system Signed BPTA with PGCILon 24/02/10 for evacuation of  AHP: Ready in all respect.
entire power from kotra sub-station.  Raw Water Supply System: raw water intake
pump commissioned, raw water reservoir
 Land: 568 acres of land acquired completed.
 PT/ DM Plant: already commissioned.
 MOE&F: obtained on 05/10/10 EC extended till 04/10/17  CW System: Ready.
 Civil Aviation: AAI issued NOC on 09/04/2009  FOPH: Ready
 Water: 35 MCM from Mahanadi (44 Km pipeline).  Switchyard: 440kV trans line charged on
09/05/15. 20/6.6Kv line charged on 20/01/16
 Coal linkage: Granted coal linkage for entire 1200 MW by SECL. FSA signed for U-1
&U-2 for 1.3 MTPA on 28/08/13 and 23/09/13 respectively.

Critical issues
Reasons for Delay U-3&4: Work yet to start. Balance land acquisition for ash dyke. Commissioning schedule would be assessed after restart of
work.

TPM_Broad Status Report (January-February’2020) 73


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
Original Actual(A)/ As
No. (MW)
Expected
Synch/ COD Sync/. COD
Comm Comm
7 Nawapara TPP (TRN TPP), U-1 300 11/13 - 31/05/16(A) 19/08/16(A) Unit-1 : COD on 19/08/16.
(Distt: Raigarh) 12/13 14/08/16(A)
M/s TRN Energy Pvt Ltd.,
Commissioned on 14/08/16.
Chhattisgarh U-2 300 03/14 - 20/12/16(A)
18/04/17(A)
01/05/17(A) Synchronized on 31/05/16.
04/14 Boiler
(2x300=600MW) Boiler erection started on 01/10/12.
Org.Est. cost / Latest Cost :Rs. 284400 Lakhs/ 372597 lakhs Boiler Drum lifted on 30/03/13.
Exp. During 11-12 : Rs. 27800 lakhs Boiler HT completed on 28/03/14
BLU completed on 25/12/15
Exp during 12-13 : Rs. 40523 Lakhs Steam blowing completed on 07/01/16.
Exp during 13-14 : Rs. 121353 Lakhs Synchronized on 31/05/16
Exp during 14-15 :Rs. 78824 Lakhs Unit
Exp during 15-16 : Rs 35400 Lakhs TG
Exp during 16-17 Rs. 42755 Lakhs Condenser erection started on 04/14.
TG erection started in 01/06/14.
Cumm. Exp ( 11/16) : Rs 346655 lakhs
TG Boxed up on 08/ 12/15.
Approval date: TG put on barring gear in 12/15 insulation &
Zero date: 27/06/11 cladding work completed. Condenser charged.
Financial closure Achieved on 18/12/09 
Main Plant Order : BTG Contract awarded on 27/01/11 to M/s China Western Unit-2:COD on 01/05/17.
Power Co.Ltd. Commissioned on 18/04/17.
BOP Package The order for main plant civil & structural work and all the
Synchronized on 20/12/16.
BOPs on EPC basis have already been placed on M/s BGR
Energy Systems Ltd. on 09/06/11. The EPC contract covers all
Boiler
the onshore supplies, civil works, erection and commissioning
Boiler erection started in 06/03/13
of the project.
Boiler Drum lifted on 21/09/13
Boiler HT completed on 28/08/15
BLU completed on 23/10/16.
Type of fuel Coal SBO completed.
PPA Entered with Chhattisgarh State Power Trading Company Ltd. TG
for 35% power in accordance with MOU with Govt. of Condenser erection started on 08/07/15. TG
Chhattisgarh. In case-1 bidding with UPPCL, TRN was in 2nd erection started on 01/07/15. TG Boxed up on
position.(L2) for 390 MW. PPA is with PTC on take or pay 20/11/16. TG oil flushing on 22/11/16. TG
basis. As per Letter dated 13/01/14 put on Barring Gear on 24/11/16. Completed.
Signed back to back PPA with PTC for supply of 390 MW to BoPs:
UPPCL on 25/07/13 and 5% of net power i.e 30 MW to be
signed with CSPTCo. Ltd.  Chimney: All work completed.
As per Letter dated 28/04/16  CHP: All work completed.
Already signed PPA for sale of 5% of net power with
 AHP: All work completed.
C.S.P.T.Co on 26/05/15. Further, signed with UPPCL for sale
of 390 MW .
 Raw Water Supply System: Ready
Power Evacuation system BPTA has signed with PGCIL for Raigarh Pooling Station
 CW System: For both units completed.
(Tamnar) on 11/04/11 for 400 MW.
 IDCT-I: commissioned
 Land: Land is in possession.
 IDCT-II: Work in progress
 MOE&F: clearance has been received on 18/03/11
 PT & DM Plant: commissioned.
 Civil Aviation: Clearance received on 24/02/12
 FOHS: LDO & HFO system operational.
 Water: 19 MCM has been allocated by W.R. Dept., Chhattisgarh.
 Switchyard: Switchyard charged.
 Coal linkage: FSA signed on 23/11/2013

Critical issues
Reasons for Delay Delay in start of Civil works. Slow progress in erection works of Boiler and T.G. Manpower shortage.

TPM_Broad Status Report (January-February’2020) 74


BROAD STATUS OF THERMAL POWER PROJECTS IN GUJARAT
Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
Original Actual(A)/ As
No. (MW)
Expected
Synch COD Synch Trial Run
Comm Comm COD
State Sector
1. Wanakbori TPS 8 800 07/18 10/18 03.03.19(A) 12.10.19(A) Unit-8: COD on 13.10.2019, Completed trial
Extn. GSECL, 10/18 14/06/19(A) 13.10.19(A)
Dist: Kheda
run on 12.10.2019, Full load on
Gujarat 14.06.2019. Unit Synchronized on
03.03.2019.
(1x800=800MW)
Original /Latest Cost : Rs.353651 Lakh / Rs 353651 Lakh Boiler: Boiler erection started on 25/02/16. Drainable Hydro test
Expenditure during 2014-15 : Rs.12701 Lakh completed on 12/01/2018. Boiler light up on 30/07/2018. Steam
Expenditure during 2015-16 : Rs.48760 Lakh Blow Off completed on 31.01. 2019. 60% cladding sheet fixing
Expenditure during 2016-17 : Rs.150651 Lakh completed & balance cladding sheet fixing work u/p
Expenditure during 2017-18 : Rs.117495.59 Lakh
Expenditure during 2018-19 : Rs 73178.36 Lakh TG: TG civil works started on 21/12/15. Condenser erection
Total Expenditure : Rs. 429689.61 Lakhs (Upto 11/19) started on 22/12/16 (outside assembly). TG Deck casting
completed on 01/08/17. TG erection started on 31/08/17. TG Box
Approval date: ;NA Up is done on 28/12/18. Main Turbine trial on barring gear carried
Zero date: : 21/10/14 out on 29.12.2018. Main Turbine rolled on 02.03.2019.
Notice To Proceed (NTP) :
Financial closure Completed BoPs:
Main Plant Order : 21/10/14. on M/s BHEL, EPC basis  Chimney: Completed in all respect.
Boiler: Alstom Power INC  CHP: In this package order for Civil works is with Bridge
TG: Siemens AG Germany & Roof (I) Pvt Ltd. The mechanical work is with M/s
BOP Package : BHEL, EPC GMW. Wagon tippler: Tunnel bottom raft 95/152,Both side
wall 94/152 and slab 82/152 completed. Casting of pent
Type of fuel : Coal
house slab competed. WT RCC Slab at RL 59.068 is
PPA :PPA signed on 01/01/2011 with GUVNL. casted.WT RCC wall to RL61.468mt is casted and slab
Source and supply of : Gare Plama Coal Block, Chhattisgarh beam and slab shuttering is U/P.
Fuel  AHP: Order has been placed on M/s Macawber Beekay for
Power Evacuation Mechanical and M/s GMW for structural work. The order
system for civil works is with M/s Bridge & Roof (I) Pvt. Ltd. and
 All mandatory clearances are available. is in progress. All pumps erected. AHP MCC 1, 2 civil
 Power evacuation system readiness is expected 6 months before work completed. Piping work completed. And in service.
COD.  Raw Water Supply System: Order placed to M/s
 Topographical & Soil investigation work is completed. Chembond Solenis Water Technologies Ltd for Erection &
 LOI for RCC Chimney placed on M/s Bygging India Ltd.on Commissioning. Completed and in service
11/06/15.  Fire Protection System: Fire water pump, jockey pump,
 BHEL issued order for civil work to M/s BJCL for Boiler to Chimney hydrant spray pump and placed at site decouple trial taken.
area. Foam system erected, trial pending. Firefighting pedestal
 MOE&F Clearnce obtained 02.12.2013 90% is completed, except Crusher House to WT and Silo
 Civil Avaition clearance on 03.02.2009  PT/ DM Plant: Order for DM plant has been placed on
Water allocation: 10.82MGD allocated from Mahi River. M/s. Aqua Design India Pvt. Ltd for Erection &
Commissioning. Stream 1 and Stream 2 mechanical work
completed. Automation work under progress. PTP order is
with M/s Pennar Enviro Ltd; DM building civil works
(inside) completed and rest under progress. (initially treated
water has to be arranged from existing plant) Filter
backwash sump completed. Clarifier hydro test is
completed.Chemical House in service. Instrumentation
work in progress for DM Plant
 CW System: The order has been placed on M/s Chembond
Solenis Water Technology.Commissioned and in servic.
 NDCT: The order placed on M/s NBCC. NDCT work
completed and in service.
 Switchyard: Order placed on M/s Teknow Overseas
Private Ltd. AIS/GIS in service Switchyard Tie line -I and
ST charged through BUS-I.

FGD – LOA issued to Dattang Technologies &


Engg. India Pvt. Ltd. for erection, testing and
commissioning of FGD system on 16.03.2019. Soil
Investigation at site completed and Report awaited.
Critical issues Readiness of regular CHP, fly Ash disposal system and Ash dyke.
Reasons for Delay Due to soil strata a lot of piling (4300numbers) has been done in BTG area. Non-readiness of NDCT (100%) and fly ash disposal.
Delay in readiness of TG Deck
AK-31/12/2019

TPM_Broad Status Report (January-February’2020) 75


BROAD STATUS OF THERMAL POWER PROJECTS IN MADHYA PRADESH
Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ Trial Synch/ Trial Run
Comm Run Comm /COD
/COD
State Sector
1. Shree Singaji TPP, 3 660 03/18 07/18 27.04.18(A) 18.11.18(A) Unit-3: COD on 18/11/18. Commissioned on
Stage –II 05/18 14.08.18(A)
(At Dongalia Distt. 14/08/18. Synchronisation on 27/04/18.
Khandwa), Boiler: Boiler erection started on 18/06/15. Pressure parts
MPPGCL 4 660 07/18 11/18 27.12.18(A) 27.03.19(A) erection completed. Boiler HT completed on 31/03/17. BLU
(2x660=1320MW) 09/18 26.02.19(A) achieved on 24/01/18. Synchronisation done on 27/04/18. Full
Original /Latest Cost : Rs.650000 lakhs / Rs.773800 lakhs load achieved on 14/08/2018.
Expenditure during 2013-14 : Rs 117 lakhs TG: TG deck casting completed on 30/04/16. Condenser
Expenditure during 2014-15 : Rs 46488 lakhs erection started on 11/07/16.TG erection started on 24/11/16. TG
Expenditure during 2015-16 : Rs 56475 lakhs box up completed on 30/11/17. TG put on BG in 12/17.
Expenditure during 2016-17 : Rs 159878 lakhs
Expenditure during 2017-18 : Rs 206337 lakhs Unit-4: COD on 27/03/2019. Commissioned on
Expenditure during 2018-19 : Rs 127344 lakhs
Expenditure during 2019-20 : Rs 18446 lakhs (Upto 06/2019) 26/02/2019. Full Load on 26/02/19.
Total Expenditure : Rs. 615085 lakhs Synchronisation on 27/12/18.
(Upto 04/19) Boiler: Boiler erection started on 27/10/15. Boiler HT (D)
Approval date: : NA completed on 27/07/17. Boiler light up achieved on 24/10/2018.
Zero date: :31/12/14. Steam Blowing started on 27/10/18 and completed on 25/11/18.
Notice To Proceed (NTP) :31/12/14 Test Synhronisation has been done on 27/12/18.
TG: TG deck casting completed. Condenser erection started on
Financial closure : Achieved in 03/15
02/02/17. TG erection started on 30/05/17. TG boxed up on
Main Plant Order : EPC on M/s L&T on 31/12/14 30/03/18. Over Speed Test of Turbine has been done on
BTG Make : L&T/MHI 27/12/18. Safety Valve setting done successfully on 11.01.19.
BOP on EPC basis :M/s L&T on 31/12/14 Availability of start up power is done on 29/08/17.
Type of fuel Coal
PPA :With MPTradco (now known as MPPMC) on
04/01/2011. BOPs:
Source and supply of : Gondbahera-Ujjaini coal block having 5.32 MT reserve
Fuel to MPPGCL on 07/06/13.  Chimney: Ready for both Units
Power Evacuation system  CHP: Equipments commissioning and trial run is in
 Land: Available. progress.
 Mega Power Status: : Obtained on 05/07/12.  AHP: Wet Ash System is ready. Dry fly Ash System, Ash
 MoEF: Received on 27/08/14. water Recovery System, h2 Genreration Plant and Ash
 Project Consultant: M/s Lahmeyer International (I) Ltd, Gurgaon dyke Lagoon-1 work under progress.
 Design and Engineering works under progress.  Raw Water Supply System: Functional.
 Consent to Operate U-3 granted by MPPCB, Bhopal on 14/04/2018  PT/ DM Plant: Functional
 CW System: Civil work completion is in final stage and
laying of CW pipeline completed. Unit # 3 CW system
already charged.
 NDCT: Unit#3 Functional, Unit#4 50% Functional and
50% Ready.
 FOPH: Ready.
 Switchyard: Switchyard charged. Unit # 3 on load & Unit
# 4 Synchronized with grid on 27/12/18.

FGD: Present Project Consultant to be


continued. Site selection made. Tender is
invited on ICB basis & Published on 20th
Jun'18. Pre bid conference held on 24th Sept.
2018. Due to closing of old E-Procurement
Portal, a fresh tender is floated and under
scrutiny currently. Date of Award expected by
09/2019.
Critical issues First stage Forestry clearance of Gonbahera Coal Block by MoE&F. Major balance works under EPC scope such as Dry fly Ash System,
Ash water Recovery System, h2 Genreration Plant and Ash dyke Lagoon-1
Reasons for Delay
SK-12/07/2019

TPM_Broad Status Report (January-February’2020) 76


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
1. Mahan TPP 1 600 07/11 09/11 24/12/12 (A) 29/04/13 (A) Unit-1 : COD achieved on 29/04/13.
(Dist. Singrauli) 09/11 25/02/13 (A)
Essar Power MP Ltd. Commissioned on 25/02/13.
(2x600=1200MW) Synchronized on 24/12/12.
2 600 10/11 12/11 07/17 (A) 07/10/18 (A)
12/11 26/09/18 (A)
Boiler: Boiler erection started in 09/09. Boiler drum lifted
Original/Latest Cost : Rs. 773800 Lakhs/ Rs. 773800 Lakhs on 21/06/10. HT done in 08/11. BLU done in 31/3/12.
Expenditure during 2006-07 : Rs 155 Lakhs SBO completion on 21/08/12.
Expenditure during 2007-08 : Rs 36609 Lakhs TG: TG erection started in 11/10. TG box up completed
Expenditure during 2008-09 : Rs 38189 Lakhs on 24/09/12. TG oil flushing completed in 11/12. TG on
Expenditure during 2009-10 : Rs 114755 Lakhs barring gear on 07/12/12.
Expenditure during 2010-11 : Rs 335735 Lakhs
Expenditure during 2011-12 : Rs 12807 Lakhs
Expenditure during 2012-13 : Rs 92434 Lakhs Unit-2 : COD achieved on 07/10/18.
Expenditure during 2013-14 : Rs 8953 Lakhs Commissioned on 26/09/18.
Expenditure during 2014-15 : Rs 110285 Lakhs
Expenditure during 2015-16 : Rs 55987 Lakhs
Synchronized in 07/17.
Expenditure during 2016-17 :Rs 18654 Lakhs
Expenditure during 2017-18 :Rs - Lakhs Boiler: Boiler erection started in 06/10. Boiler drum lifted
in 01/11. HT done in 02/12. BLU achieved on 14/05/17.
Total Expenditure : Rs 815610 Lakhs (Upto 03/17) SBO completed in 06/17. Full load achieved on 26/09/18.
Approval date: :NA TG: Condenser erection started in 03/11. TG erection
Zero date: :24/08/07 started in 03/11. TG Box up completed in 07/17. TG oil
Notice To Proceed (NTP) :24/08/07 flushing completed in 07/17. Syn. achieved in 07/17. Coal
Financial closure : 21/01/2009 firing is completed in 08/17.
BoPs:
Main Plant Order :BTG order placed on M/s Harbin Power Co. Ltd,
China on 24/08/07.
BTG Make :Chinese As the unit-1 of the project has already been
BOP Package : Reputed Indian Vendors commissioned and BoPs are common for both the
Type of fuel :Coal units.
PPA : Long Term PPA with ESIL for 200 MW and 55.5
 Chimney: Already completed
MW with Govt. of MP (on variable charge basis).
For tie up of balance capacity of 855 MW,  CHP: Second stream of the CHP is already ready
company is participating in various competitive  AHP: U-2 AHP is ready
bids/merchant power.  Raw Water Supply System: Ready
Source and supply of : Mahan Coal Block allotted jointly to ESSAR  PT/ DM Plant: PT plant ready. DM Plant also
Fuel and Hindalco had been cancelled on 24/09/14. commissioned.
Essar has signed CMPDA with GOI on 2/3/2015  CW System: Ready
for Tokisud Coal Mine located in the State of  CT: : Commissioned.
Jharkhand post e-auction. Vesting order is  FOPH: Completed.
awaited. As per present mining plan, peak  Switchyard: Completed in all respects.
capacity of production of the mine is 2.32
MTPA.
Power Evacuation system :1st unit commissioned by LILO (Temp
arrangement). Long term open access granted by
PGCIL through Mahan-Sipat line.
 MOEF clearance: 20/04/07
 Water: 0.058 MAF/year from Rihand Reservoir.
 SPCB: Obtained on 03/03/09.
 Civil Aviation Clearance: Obtained on 02/02/2007.
 Land: Physical possession of 185.81 Ha. Govt. Land is available.167.32
Ha. Pvt. Land in Viil. Bandhora, 150.31 in Nagwa Vill. 79.08 Ha in
Kharahi. For 4th viilage Karsualal(100.17 Ha.) compensation distribution
is in progress.

Critical issues In lieu of cancellation of captive coal block, Coal linkage (5.5 MTPA) or any other coal sourcing is essential to run the plant.
Return of expenditure incurred on Mahan Coal Block.
Reasons for Delay Delays primarily due to financial constraint with the developer.

TPM_Broad Status Report (January-February’2020) 77


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
Original
Actual(A)/ As
No. (MW)
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
2. Gorgi TPP 1 660 05/13 07/13 Uncertain Unit-1
(Dist. Singrauli) 06/13 The site enabling activities like area grading etc has already
DB Power (MP) completed. Construction of administrative building and hostel facility
Ltd. also completed. Excavation work in water reservoir area and chimney
(1x660=660MW) also started. Erection yet to be started. Work is on hold at site due to
Original/ Latest Cost : Rs.394100 Lakhs / Rs.394100 Lakhs Financial crunch being faced by the developer.
:
Expenditure during 2008-09 : Rs. 349 Lakhs
Expenditure during 2009-10 : Rs. 2303 Lakhs BoPs:
Expenditure during 2010-11 : Rs. 13487 Lakhs
Expenditure during 2011-12 : Rs. 21157 Lakhs  In BoPs work yet to start.
Expenditure during 2012-13 : Rs. 4036 Lakhs

Uncertain
Expenditure during 2013-14 : Rs. 4712Lakhs
Expenditure during 2014-15 : Rs. 1614 Lakhs
Expenditure during 2015-16 : Rs. 78 Lakhs (upto 09/15)
Total Expenditure : Rs 47579 lakhs
(Upto 09/15)
Approval date: : NA
Zero date: : 03/11
Notice To Proceed (NTP) :03/11
Financial closure Achieved in 03/2011 for unit-1
Main Plant Order BHEL on 03/11 (BTG).
BTG Make BHEL
BOP Order Indure Pvt. Limited.
Type of fuel :Coal
PPA 35% with MPPMC from 2x660 MW
Source and supply of 2.1048 MTPA available for unit-1.
Fuel
Power Evacuation system PGCIL has granted LTA and connectivity.
Power evacuation at vindhyachal pooling
station.
 Consultant: Desein
 MOEF Clearance: Obtained in Sept.10 for 1st unit.
 Land : 735-acre land is acquired.
 Water: 25 MCM PA water from Gopad river for 2x660 MW.
 All the mandatory clearances are available for two units.
 The major part of total land acquired by the company in time but delay
in granting government land which is significant stretches had affected
the contiguity and due to which construction could not commence at
desired time.
 PPA has been signed with MP Power Management Company (State
Utility) for 35% capacity from both the 2x660 MW.
Critical issues Acquisition of balance land.
Reasons for Delay Financial Costraints

TPM_Broad Status Report (January-February’2020) 78


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
Original Actual(A)/ As
No. (MW)
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
3. BLA Power 2 45 13.03.17(A) 20.03.17(A) Unit-2 : COD on 20.03.17. Full load on
(Niwari) TPP (Dist. 16.03.17(A)
Narsinghpur) 16.03.17. Unit Synchronized on
BLA Power Ltd. 13.03.17.
(2x45=90 MW)
Original / Actual Cost : Rs.27903 Lakhs / Rs.40483 Lakhs
Expenditure during 2010-11 : Rs. 2598 Lakhs
Expenditure during 2011-12 : Rs. 10954 Lakhs Boiler:
Expenditure during 2012-13 : Rs. 5194 Lakhs Boiler erection started on 13.01.2012.
Expenditure during 2013-14 : Rs. 4468 Lakhs Boiler Hydrotest was carried on 17.08.2015
Expenditure during 2014-15 : Rs. 4549 Lakhs
Expenditure during 2015-16 : Rs. 5910 Lakhs
Boiler drum lifted on 11.06.12.
Expenditure during 2016-17 : Rs. 5688 Lakhs Steam blowing started on 15.01.2017
Expenditure during 2017-18 : Rs. 1122 Lakhs Steam blowing completed on 21.01.2017
Total Expenditure : Rs. 40483 Lakhs
Approval date: : NA TG:
Zero date: : 04/11
TG Erection started on 11.12.2015.
Notice To Proceed (NTP) : 04/11
TG Box up on 26.03.2016.
Financial closure Achieved.
Main Plant Order CFBC Boiler (Design by Foster Wheeler, Mfgd by
ISGEC) in 02/11.Turbine and Generator (Siemens)
in 04/11. BoPs:
BTG Make CFBC Boiler (Design by Foster Wheeler, Mfgd by
ISGEC) and Turbine by Siemens, Generator by  Chimney- 120-meter-high chimney is common for both
Toyo Denky Power Systems units.
BOP Order GT by Alstom, SAT by Schneider, Switchgear by
 CHP is common for both units consisting of conveyors,
ABB, Cooling Tower by Hamon Cottrell, DCS by
Valmet (Metso) Automation crushers, screen, transfer chute etc.
Type of fuel Coal / Petcoke / Partial by Bio Mass  AHP consists of dry ash dense phase conveying system
PPA 30% with MPPMCL and 5% with MP Government on and common bed ash and fly ash silos.
variable cost.  CWPH Raw water pumphouse is common for both
Source and supply of FSA signed with BLA Industries Pvt. Ltd. on
units and situated at the bank of Narmada River, 13 km
Fuel 25/04/11 for 350000 tons per annum for U1 & U2
from coal mine which is affected by Judgment. away from the plant
Fuel from e-auction. Shakti B2R2 LoI issued for  DM Plant, ETP- Demineralized and effluent treatment
PPA backed capacity. plants are common for both units. Storage capacity of
Power Evacuation 132 KV DCDS Line from 132 KV Switch yard DM water is 600 KL (Three DM water storage tank
system (BLA Power) to 132 KV Sub-Station (MPPTCL)
Gadarwara each of capacity 200 KL)
 MOEF Clearance: Obtained on 21/04/2009.  Cooling Tower- is common for both units and consists
 Land: 129.15 Acres of land is acquired for 3x45 MW. of five (5) cooling tower fans. Two fans are required for
 Water: 2.5 MCM PA water from Narmada river for 2x45 MW. each unit and one fan is standby.
 Switchyard and transmission line are common for both
units. Power from both units are transmitted to 132 KV
Sub-Station (MPPTCL) by 132 KV DCDS lines
 FGD – Both Boilers (U1 & U2) are Circulating
Fluidised Bed Combustion Boiler having facility for in-
situ capture of SOx by direct injection of lime/limestone
in furnace which ensures compliance.

Critical issues

Reasons for Delay

TPM_Broad Status Report (January-February’2020) 79


BROAD STATUS OF THERMAL POWER PROJECTS IN MAHARASHTRA

Unit Commissioning Schedule


Sl. Project Details Capacity Broad Status
Original Actual(A)/ As
No. (MW)
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
1. Amravati TPP , Ph-II, 1 270 05/14 08/14 @ @ @: Work is on hold (since April,2012)
(Distt: Amravati) 07/14
M/s Rattan India 2 270 07/14 10/14 @ @ Unit-1
Power 09/14 Boiler
Ltd.(Formermerly 3 270 09/14 12/14 @ @ 1. Boiler erection started on 24/11/11.
known as Indiabulls 11/14 2. Work is on hold.
Power Ltd.) 4 270 11/14 02/15 @ @
(5x270=1350 MW) 01/15 Unit-2
5 270 03/15 04/15 @ @ Boiler
Original/Latest Cost : Rs.664600 Lakh/: Rs.664600 Lakh 1. Boiler erection started in 01/12.
Expenditure during 2011-12 : Rs. 49727 Lakhs 2. Work is on hold
Expenditure during 2012-13 : Rs.20866 Lakhs
Unit-3

Uncertain
Expenditure during 2013-14 : Rs.3397 Lakhs
Expenditure during 2014-15 : Rs.2390 Lakhs Boiler
Total Expenditure :Rs 76380 Lakhs(Upto 03/15) Work is on hold.
Approval date: :NA
Unit-4
Zero date: 11/10/10
Boiler
Notice To Proceed (NTP) :11/10/10 Work is on hold.
Financial closure : Achieved on 01/02/11
Main Plant Order : BTG on EPC basis awarded to Unit-5
BHEL on 11/10/10. Boiler
BTG Make BHEL Work is on hold.
Type of fuel Coal
BoPs:
PPA No PPA
Source and supply of Fuel :With MCL & WCL in 11/10(LOA) .
 Work is on hold.
Power Evacuation system : Through 400kV/765KV Akola and Wardha
Substations of MSETCL through
400KV/765KV D/C transmission line.
 FSA: Letter awaited.
 All clearances are available.

Critical issues
Reasons for Delay Due to financial constraints project has been put on hold.

TPM_Broad Status Report (January-February’2020) 80


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
Nasik TPP, Ph-I 1 270 12/11 03/12 24/02/14(A) 29/03/14 (A) Unit-1 : COD on 29/03/14. Commissioned on
(Distt: Nasik) 02/12 25/02/14(A)
M/s Sinnar Thermal 2 270 02/12 05/12 21/03/16 (A) - 25/02/14. Synch. on 24/02/14.
Power Ltd. 04/12 15/02/17(A) Boiler:
(Formerly known as 3 270 04/12 07/12 04/17(A) - Boiler erection started on 03/11/10. Boiler drum lifting completed on
Indiabulls Realtech 06/12 14/04/17(A) 31/03/11. Boiler HT (D) completed on 28/03/12. BLU completed on
Ltd.) 4 270 06/12 09/12 05/17(A) - 22/10/12. SBO completion achieved on 15/04/13. Unit normalization
(5x270=1350 MW) 08/12 19/05/17(A) completed in 04/13.
5 270 08/12 11/12 05/17(A) - TG:
10/12 30/05/17(A) TG civil works started on 01/06/10. TG erection started on 25/09/11. TG
Box Up completed on 30/01/13. TG oil flushing completed on 15/04/13.
Original /Latest Cost : Rs.678900 lakhs / Rs.784898 lakhs TG on BG achieved on 31/05/13. Boiler lighted up for steam dumping on
22/12/13. Steam dumping started on 22/12/13. Rolling completed on
Expenditure during 03/10 :Rs. 30620 Lakhs
28/12/13. Oil synch. achieved on 05/02/14. Coal bunkering started on
Expenditure during 2010-11 :Rs. 100000Lakhs
10/02/14.
Expenditure during 2011-12 :Rs. 180309 Lakhs
Expenditure during 2012-13 :Rs. 144526 Lakhs
Expenditure during 2013-14 :Rs 107396 Lakhs Unit-2 : Commissioned on 15/02/17. Synch. on
Expenditure during 2014-15 :Rs 98461 Lakhs 21/03/16.
Expenditure during 2015-16 :Rs --
Total Expenditure :Rs. 661312 Lakhs (Upto 03/15) Boiler:
Approval date: : NA Boiler erection started on 08/12/10. Boiler drum lifting completed on
Zero date: : 24/11/09 27/07/11. Boiler HT (D) completed on 03/07/12. BLU achieved on
27/11/13. EDTA completed in 02/14. SBO started on 28/02/14 and
Notice To Proceed (NTP) :211/09
completed on 14/03/14.
Financial closure : Achieved on 30/06/10 TG
Main Plant Order : BTG on EPC basis awarded to BHEL on 24/11/09. TG erection started on 25/12/11. TG Box Up completed on 08/10/13. TG
oil flushing completed on 31/12/13. TG put on BG on 10/03/14. Rolling
BTG Make BHEL completed on 31/03/14. Readiness of Railway siding by 03/16. GIS
BOP on EPC basis Reputed Indian Vendors clearance received in 01/16. Clearance given to BHEL to start the work on
Type of fuel : Coal 10/01/16. BHEL re-started work at site on 30/01/16.
PPA No PPA
Source and supply of Fuel : From SLC (LT) on 17/12/08. Unit-3 : Commissioned on 14/04/17. Synch. on
Power Evacuation system : Through 400kV D/C quad Moose transmission line upto 04/17.
MSETCL sub-station at Bhubaneshwar. Boiler
 FSA: With MCL, SECL & WCL on 11/06/09. All clearances are available. Boiler erection started on 12/01/11. Boiler drum lifting completed on
 Design & Engineering completed. 12/12/11. Boiler HT completed on 30/10/13. BLU achieved on
03/10/16.SBO completed on 06/12/16.
 The BOPs are common for all the five units. All the BoPs are either already
completed or nearing completion. TG
TG erection started on 19/01/12. TG boxed up in 10/16. TG put on BG on
27/01/17.TG rolling done on 04/03/17

Unit-4 : Commissioned on 19/05/17. Synch. on


05/17.
Boiler
Boiler erection started on 16/05/11. Boiler drum lifting completed on
23/12/11. Boiler HT is completed in 11/16. BLU achieved on 30/12/16.
SBO completed on 13/02/17..
TG
TG erection started in 05/12. TG box up completed on 24/01/17. TG oil
flushing completed on 12/03/17. TG put on BG on 29/03/17.

Unit-5
Commissioned on 30/05/17.
Boiler
Boiler erection started on 16/06/11. Boiler drum lifting completed on
06/03/12.BLU achieved on 15/02/17. EDTA completed on 06/03/17. SBO
completed on 24/03/17.
TG
TG erection started on 30/04/16. TG Box Up completed on 13/02/17. TG
oil flushing completed on 17/04/17. TG put on BG on 28/04/17.

BoPs:

 The order was placed on reputed Indian vendors. BoPs were


common for all the five units and completed except Railway
siding.
Critical issues PPA, Completion of Railway Siding.
Reasons for Delay  Railway siding for coal transportation.
 Finalization of PPA.
 Rectification of defect in GIS switchyard by Siemens-Germany.
 Fault in HT panel
 Financial Constraints

TPM_Broad Status Report (January-February’2020) 81


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
Nasik TPP , Ph-II 1 270 01/13 04/13 @ @ @: Work is on hold (May, 2012). Schedule will be decided after restart of
(Distt: Nasik) 04/13 work at site.
M/s Sinnar 2 270 03/13 06/13 @ @
Thermal Power 06/13 Unit-1
Ltd. (Formerly 3 270 05/13 08/13 @ @ Boiler
known as 08/13 Boiler erection started in 09/11. Work is on hold.
Indiabulls Realtech 4 270 07/13 10/13 @ @ Unit-2
Ltd.) 10/13 Boiler
(5x270=1350 MW) 5 270 09/13 12/13 @ @ Boiler erection started in 11/11. Work is on hold.
12/13 Unit-3
Original /Latest Cost : Rs.678900 lakhs / Rs.678900 lakhs Boiler
Work is on hold
Expenditure during 03/10 : Rs.36805 Lakhs

Uncertain
Unit-4
Expenditure during 2010-11 : Rs. 10000 Lakhs
Boiler
Expenditure during 2011-12 :Rs. 5339 Lakhs
Work is on hold
Expenditure during 2012-13 :Rs. 9615 Lakhs
Unit-5
Expenditure during 2013-14 :Rs. 5022 Lakhs
Boiler
Expenditure during 2014-15 :Rs. 4400 Lakhs
Work is on hold
Total Expenditure :Rs. 71181Lakhs
(Upto 03/15)
BoPs:
Approval date: : NA
Zero date: : 24/11/09  Work at site has been put on hold since long back.
Notice To Proceed (NTP) : 24/11/09
Financial closure : Achieved on 30/06/10
Main Plant Order : BTG on EPC basis awarded to BHEL on 24/11/09
BTG Make BHEL
BOP on EPC basis Reputed Indian Vendors
Type of fuel Coal
PPA No PPA
Source and supply of Fuel : From SLC (LT) on 17/12/08.
Power Evacuation system : Through 400kV D/C quad Moose transmission line
upto MSETCL sub-station at Bhabaleshwar.
 FSA: With MCL, SECL & WCL on 11/06/09.
 All clearances are available.

Critical issues Work at site is on hold.


Reasons for Delay Work at site has been put on hold since long back.

TPM_Broad Status Report (January-February’2020) 82


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
Lanco Vidarbha TPP 1 660 03/14 08/14 * * Unit-1
(Distt: Wardha) 07/14 Boiler
M/s Lanco Vidarbha Boiler erection started on 01/08/11. Main structure erection upto 6 th tier
Thermal Power Ltd. 2 660 07/14 12/14 * * completed in 10/15. All the (5) Ceiling Girder (CG) erection work
(2x660=1320 MW) 11/14 completed. Pressure parts erection work started in 04/16.
Original/Latest Cost : Rs.693600 lakhs/ Rs.1043300 lakhs
Expenditure during 03/11 : Rs 97600 lakh TG
Expenditure during 2011-12 : Rs 181100 lakh TG Deck casting completed. TG handed over to mechanical department for
Expenditure during 2012-13 : Rs 67200 lakh erection. TG erection started in 05/16. EOT Crane (2 nos.) already
Expenditure during 2013-14 : Rs 15200 lakh commissioned.
Expenditure during 2014-15 : Rs - lakh
Expenditure during 2015-16 : Rs 98900 lakh Unit-2
Expenditure during 2016-17 : Rs 73800 lakh Boiler
Expenditure during 2017-18 : Rs - lakh Boiler erection started in 10/11. Main structure erection upto 6th tier
completed. All the (5) Ceiling Girder (CG) erection work completed.
Total Expenditure : Rs 533800 lakhs (Upto 04/17) Pressure parts erection work started in 08/16. HT is yet to be done.
Approval date: : NA
Zero date: : Achieved on 01/12/10. TG

Stressed Project
TG raft completed and Mezzanine Floor work completed. Top deck
Notice To Proceed (NTP) : Achieved on 01/12/10. shuttering work also completed, final inspection work under progress. TG
Financial closure : Achieved on 01/12/10. erection work yet to start.
Main Plant Order : EPC Contract awarded to M/s Lanco Infra Presently work is on hold due to financial constraints.
Tech Ltd.(LITL) through ICB Route in BoPs:
11/09. Boiler & Aux.: Dongfang, China
TG & Aux.: Harbin, China,  Chimney: Civil works for chimney are being done by M/s LITL.
BTG Make Boiler & Aux.: Dongfang, China Chimney Raft completed. Chimney shell construction completed upto 30
TG & Aux.: Harbin, China, mtr.upto 07/16.
Type of fuel : Coal  CHP: (Elecon Engg.Co. Ltd): Wagon Tippler excavation work
PPA PPA for 680MW(Net)signed with MSEDCL. completed. Raft Completed in WT area and balance work is in progress.
Source and supply of Fuel : SECL Civil works are being done by M/s LITL. In other parts of CHP such as
Stacker reclaimer , Crusher House, TPs and conveyors civil works are in
Power Evacuation system : Grant of connectivity letter received at 765 progress..
kV from Wardha-Seoni line from PGCIL.
 AHP: (M/s LITL): Civil works for BA hoppers, Fly ash silo’s, AWPH,
Connectivity agreement is in progress. ASPH and ash dyke are in progress.
 All clearances are available. MOEF clearance received on 24/02/11.  Raw Water Supply System: Work is in progress.
 Design & Engineering completed.  PT/ DM Plant (DOshion Veolia water solution): Approx. 80% civil
 Order for all BOPs have been placed and progressing as per works completed upto 09/16.
schedule.  CW System: Civil works are with M/s LITL and mechanical works are
 FSA is in process. with M/s Singrauli Associates Pvt. Ltd.. Civil works in CW pump house,
 PPA with MSEDCL for 680MW signed on 25/09/08. CW fore Bay and CW open channel are in progress. 85% CW pipeline
 Work was on hold since 01/2013. erection work completed upto 09/16. Balance erection work is under
 Work at site restarted since April, 2015. progress.
 Work in all the BoPs is also progressing nicely.  IDCT: Being done by M/s LITL. For both the IDCT- I: & IDCT- II:
PCC and basin raft concreting completed. Pedestal work is in progress.
 FOPH: All civil works are in progress..
 Switchyard: 95% switchyard foundations completed so far.
Critical issues Financial crunch.
Reasons for Delay # Work was on hold due to financial crunch. Work has now restarted since 04/15. Work progress is slow due to Financial Costraint.
* Work on hold due to financial crunch. Schedule will be decided after restart of work.

TPM_Broad Status Report (January-February’2020) 83


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
Bijora Ghanmukh 1 300 10/16 01/17 Uncertain Unit-1
TPP, 12/16 Boiler
(Distt: Yavatmal) Boiler Civil works started in 09/15. Work at site put on hold due to
M/s Jinbhuvish 2 300 01/17 03/17 Uncertain
03/17 financial crunch.
Power Generations
Pvt. Ltd. (JPGPL)
(2x300=600 MW) Unit-2
Original/ Latest Cost : Rs.318900 lakhs / Rs.345000 lakhs Boiler
Expenditure during 03/14 : Rs 37475 lakh Work at site put on hold due to financial crunch.
Expenditure during 2014-15 : Rs 4752 lakh TG
Expenditure during 2015-16 : Rs - lakh Work at site put on hold due to financial crunch.
Total Expenditure : Rs 42227 lakh (Upto 03/15) @: Work at site put on hold. Revised commissioning schedule
Approval date: : will be decided after re-start of work.
Zero date: :
Notice To Proceed (NTP) : BOPs
Financial closure : Achieved (REC &PFC) Work yet to start
Date of Main Plant Order : BTG on EPC basis Contract awarded to M/s
(Boiler &TG from CWPC, CWPC (China Western Power Corporation)
China) (through ICB Route) on 28/09/11.
BTG Make
BOP on EPC basis
Type of fuel : Coal
PPA : Signed with PTC India Ltd.
Source and supply of Fuel : WCL(1.851MMT)
Power Evacuation system : Final connectivity on LILO from PGCIL
Wardha-Parli D/C transmission line.
 FSA: Coal Linkage LOA received from WCL, however FSA is yet
to be signed
 Consent to Establish : Obtained from MPCB.
 All statutory clearances are available. MOEF clearance received on
30/07/12.
 Design & Engineering in progress.
 Order for all BOPs on EPC basis has already been placed on M/s
AEMPL on 26/05/14. The process of subletting packagewise
contract to reputed vendors was in progress.
 Site leveling and grading was in progress.
 Capacity revision from 2x250 MW to 2x300 MW accepted and
issued letter on 19/03/14.
 FSA is in process. All the milestones required under the terms of
LOA have been completed.
 PPA: MOA signed on 27/02/12 with PTC India Ltd. for sale of 430
MW (75%) on Long Term Basis and remaining 25% on merchant
power basis.
 Various site enabling works were in progress.

Critical issues Financial Issue

Reasons for Delay The schedule of implementation got revised due to change in capacity from 2x250 MW to 2x300 MW. Formal approval
received on 19/03/14. Signing of FSA with WCL has to be expedited.

TPM_Broad Status Report (January-February’2020) 84


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch/ COD Synch/ COD
Comm Comm
Private Sector
Shirpur Power 1 150 12/14 02/15 09/17(A) - Unit-1: Commissioning achieved on 28/09/17.
Private Ltd. Distt. 28/09/17(A)
Dhule,
2 150 02/15 04/15 Unit-1 & 2:
Maharashtra
* * Steam blowing of the units completed. Main plant structural work
completed.
(2x150=300 MW)
Original / Latest Cost : Rs.241300 lakhs / Rs. 241300 lakhs
Expenditure during 2011-12 : Rs 3368 lakh Project is 96.7% complete.
Expenditure during 2012-13 : Rs 15821 lakh
Expenditure during 2013-14 : Rs 74610 lakh
Expenditure during 2014-15 : Rs 72102 lakh
Expenditure during 2015-16 : Rs 34176 lakh
Expenditure during 2016-17 : Rs 27686 lakh BoPs:
Total Expenditure :Rs 238385 lakhs Almost all BoPs are completed.
(Upto 11/17)
Approval date: :NA  CHP: coal feeding from emergency reclaim hopper to bunker

Uncertain
Zero date: : completed. Wagon tippler erection in progress.
Notice To Proceed (NTP) :  AHP, Cooling tower, Chimney, PT plant, DM plant, CW system
completed.
Financial closure : Achieved on 08/10/12  Fire detection system erection is in progress.
Date of Main Plant Order : BTG Contract awarded to BHEL on 22/11/2011.  Station transformer to be charged after back charging 220 Kv
(Boiler &TG from BHEL) Transmission line.
BTG Make Boiler &TG from BHEL
BOP on EPC basis
Type of fuel : Coal
PPA : 195 MW PPA done with private players in steel and
textile sectors. For the rest, new customers like
DISCOMs, Railways needs to be found out.
Source and supply of Fuel : SECL
Power Evacuation system  Connectivity approval from MSETCL for 220 kV
line at Amalner substation
 All clearances are available.
 Design & Engineering completed.
 Order for BOPs on EPC basis have been placed M/s Punj Lloyd on 03/08/10.
In all the BOPs work already completed.

Critical issues PPA, Coal Linkage


Reasons for Delay
*Work is on hold. Schedule will be decided after restart of work.

TPM_Broad Status Report (January-February’2020) 85


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
Actual(A)/ As
No. (MW) Original
Expected
Sync Synch Trial-run
Comm COD Comm COD
Private Sector
Bhusawal Unit-6:
Thermal Power
Project, Distt.
03/22 03/22
Jalgaon, 6 660 06/22 06/22 Boiler: M/s BHEL started excavation of Boiler foundation
Maharashtra on 15.05.2019.

(1x660 MW) Boiler: Foundation work completed Column erection


Original / Latest Cost : Rs.509700 lakhs started on 22.11.2019. 700 MT erected. Excavation, PCC
Expenditure during 2018-19 : Rs lakh completed R/f in progress for FD, PA, ID fan
TG: Excavation 23963/28672 cum PCC 278/1020 cum
Total Expenditure :Rs lakhs
RCC 2251/3690 cum Fabrication of 1094 MT completed
(Upto 12/18)
ESP: Excavation 12778/13609cum PCC 725 RCC
Zero date: : 31/12/2018 (Revised)
2838/3372 cum R/f 55/299 MT. E,F,D & C Pass pedestal
Notice To Proceed : 31/12/2018 foundation completed.
(NTP)
Financial closure :
Date of Main Plant : LOA has been issued to M/s BHEL on single point
Order responsibility EPC contract basis on 17.01.2018. BoPs:
Amendment to LOA issued to M/s BHEL dated 31/12/18
for additional work of FGD, SCR and other scope of work. AHP: Ash slurry PH excavation 1200 cum completed
BTG Make M/s BHEL Chimney: Excavation started on 25.07.2019. Excavation &
BOP on EPC basis PCC completed RCC 1658/3300 cum completed. Slip form
Type of fuel Coal fabrication works in progress
CHP: Wagon Tippler excavation 68795/80000 cum
PPA 24.12.2010 as addendum to existing PPA. PPA approved by
completed. TP - 4,5 excavation, PCC completed R/f in
MERC vide order No 103 of 2010. MERC in a suo moto
progress
proceeding in respect of case No 42 of 2017 issued a final
NDCT: Excavation 16820 cum completed
order on dated 27.03.2018 regarding upcoming Generation
projects of MSPGCL. MERC issued directives, as ‘MSPGCL
shall approach the commission afresh accordingly. In the
mean time, it shall not take any effective steps in pursuance of
FGD: Letter issued to BHEL on 20.11.2018 for
Generation Projects approved in the PEA or the other
Technical clearance to proceed further.
Projects now proposed in these proceedings, which are at the
planning stage or in respect of which contracts, which had
not been awarded at the time of last MYT order. Any capital
expenditure incurred on these Projects shall be at MSPGCL's
own risk and cost. MERC has approved further go-ahead for
the project vide order dated 01.08.2018 in case no. 154 of
2018
Source and supply of MSPGCL vide letter dated 12.07.2017 & 18.04.2018 has
Fuel requested Ministry of Coal, Govt of India to transfer the
coal linkage of Mahagenco's retired /decommissioned
units(i.e. Parli U-3, Koradi U-5, Bhusawal 112) constituting
3.18 MMTPA of coal quantity for this project. Reply from
MoC is awaited.
Power Evacuation Revised application for LTOA submitted with CE (STU),
system MSETCL & matter being followed up
Water already tied up with WRD
AAI Clearance AAI issued NOC having the validity till 23 Feb 2022
MoE&F Environment EC was granted till 26 Nov 2019. Application for extension
clearanc of EC for three years i.e upto 26.11.2022 submitted
Land Land in own possession of MPGCL for the project. For
railway siding. Till date out of 8.02 heatcares, 5.21 hectares
in possession of MPGCL, balance not yet acquired.

Critical issues
Reasons for Delay
AK-31/12/2019

TPM_Broad Status Report (January-February’2020) 86


Southern
Region
Thermal Power Plants

TPM_Broad Status Report (January-February’2020) 87


BROAD STATUS OF THERMAL POWER PROJECTS IN ANDHRA PRADESH

Commissioning Schedule
Sl. Project Details Unit Capa- Original
Actual(A)/ As Broad Status
No. No. city
Expected
(MW)
Syn. COD Syn. COD
Comm Comm
State Sector
1 Rayalaseema TPP St-IV 6 600 07/14 02.07.17(A) 04/18 Unit Synchronized on 02.07.17. Full Load
(M/s. APGENCO) 08/14 29.03.18 (A)
achieved on 29.03.2018.
Distt.Cuddapah,
Andhra Pradesh  Boiler: Erection started on 04/02/2013. Boiler Drum
Original /Latest Cost : Rs. 302886 / 388043 Lakh lifted on 30/11/13. 26952 MT/ 29730MT structural
Expenditure during 2009-10 : Rs. 555.00 lakh materials erected till 10/17. Boiler air leak test completed.
Expenditure during 2010-11 : Rs. 25833.00 lakh BLU done on 29/12/16. EDTA cleaning completed on
Expenditure during 2011-12 : Rs. 8155.00 lakh 26.02.17. Mill foundation on both sides completed. Bowl
Expenditure during 2012-13 : Rs. 29331.00 lakh mill deck slabs completed for all mills.
Expenditure during 2013-14 : Rs. 80045.00 lakh  TG: TG erection started on 04/03/16. TG box up done in
Expenditure during 2014-15 : Rs. 52429.00 lakh 02/17.
Expenditure during 2015-16 : Rs. 62341.00 lakh  Chimney (M/s Gammon): Shell concreting completed.
Expenditure during 2016-17 : Rs. 83576.96 lakh A.R.Brick work completed up to (+) EL 135.30 M height.
Expenditure during 2017-18 : Rs 69776..04 lakh ( 12/17)  CHP: Work awarded to M/s Thyssenkrup.
Total Expenditure : Rs 412042 lakh (up to 12/2017)  AHP: Vacuum pump house building, Silos, Bottom ash
Zero date : 10/02/2011. hopper, Buffer hopper, ASPH etc. area civil works
completed
Financial closure : Achieved on 19/03/10
 RWR: Trimming of slopes of reservoir bund is in
Type of Fuel : Coal progress. In the raw water pump house RCC structure
Main Plant Order Placed on M/s BHEL for BTG on 18/11/10. completed.
BOP Package Purchase order placed on the consortium led by M/s  PTP: clarifier works completed.
Tecpro Systems Ltd, including civil works on EPC basis  DM Plant: Roof slab work up to 183.10 ml completed.
on 15/12/10. Now it is led by VA Tech. Vessels foundations ready. Vessels material available at
 MOEF clearance obtained on 21/10/2010. site. Some vessels are placed in position.
 PFC Sanctioned a loan of Rs. 2423 crores.  CWS: raft work in CW pump house completed. All walls
 M/s Desein Pvt. Ltd is providing engineering consultancy services. raised up to pump floor. PCC works of fore bay in
progress. CW pipe line fabrication is almost complete.
 NDCT (M/s Gammon): Shell erection 32 lifts completed
&33rd in progress.
 FO System: M/s Xicon is executing these works Civil
work almost completed. Tanks fabrication & erection in
progress. Fuel oil transfer pump tank HFO and LDO day
tank slab completed & handed over for erection work.
 Switchyard: Foundations of all equipment were
completed and handed over for erection of equipment’s.

Critical issues 1. Readiness of cooling tower, CHP & AHP.


Reasons for Delay 1. Boiler erection start was delayed by 13 months due to initial land acquisition and civil works problems.
Mill, ID, FD & PA fan foundation work delayed.
2. Slow progress of Civil works and BOP works by the consortium led by VA Tech, Techpro and Gammon.
3. Delay in award of CHP& AHP by the consortium leader VA Tech.

TPM_Broad Status Report (January-February’2020) 88


Commissioning Schedule
Sl. No. Project Details Unit Capa- Broad Status
No. city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
State Sector
2 Sri Damodaram Sanjeevaiah 1 800 03/19 06/19 03/20 06/20  Boiler: Civil work start on 10.11.2016.
TPP St-II (Krishnapatnam) 04/19 05/20 Erection started in 26.06.2017. Hydro
(APPDCL) Distt.Nellore, Test (Drainable) in 01.07.2019. Boiler
Andhra Pradesh
structure erection 84 % complete. Boiler
Original / Latest Estd. Rs. 6034 Crs./ 6841.70 Crores (Adminstraive light up on 31.12.2019.
Cost Approval dt 30.08.2019)  TG : TG errection start 20.09.2018. HP
Expenditure during Rs. 199.20 Crs. & IP Turbine boxed up and ESVs and
2015-16 IVCVs erected. LP Turbine -1&2 – Inner
casting boxed up. LPT-1 – Outer casing
Total Expenditure Rs. 5777 Crs. Including IDC (31.12.2019) fabrication in progress. Condenser
Approval date: 14.12.2017 for revised cost erection works started in 01.8.2018. Only
CW Rear interconnection piping between
Zero date: 15.12.2015 condenser is in progress. Generator and
Financial closure Completed Excitor work in progress.
Main Plant Order BTG order placed on BHEL on 02.11.15.  ESP : ESP, ID / FD / PA fans and Duct
Type of fuel/FSA Coal. Available supports Civil works completed. ESP
Power Evacuation system Already in place Control building- RCC framework,
PPA Available with 2 DISCOMS of A.P brickwork & plastering completed.
Transformer foundations 6/6nos
Land Possession: Available. completed, Fire wall in progress. FF floor
Water allocation: Available. finish and Windows fixing completed.
MOE&F clearance: Available Screed concrete works in progress.
State Pollution Control Board Clearance: Available
Civil Aviation clearance: Available  BoPs.
 CHP: Structural Steel fabrication
5855/6000 T completed. Structural
Steel erection 4280/6000 T completed.
Structural steel erection for Conveyors
and JNTs in progress.

 AHP: Compressors TAC & IAC, after


coolers, Intercoolers, Driers &
Receivers placed. Clarifier: Erected
Sludge pumps near clariflocculator.
Silos: Erected Ash Conditioner below
FA Silo, Ash mixer, Ash slurry disposal
piping, valves u/p (12.5 / 26 Km
completed).

 NDCT : 100% Racker columns


completed. 99% Pond& partition wall
completed (561/565RM) & 100% Basin
floor completed. PU coating is in
progress.
 Chimney shell with internal brick
lining, hopper slab, Cage ladder up to
top including platform handrail,
Baffle wall RCC framework
completed. External painting works
completed.
All othe BOP works are in progress.

 FGD : Order not yet placed.


Critical issues
Reasons for Delay
SB- Jan- 2020

TPM_Broad Status Report (January-February’2020) 89


Commissioning Schedule
Sl. Project Details Unit Capacity Broad Status
No. No. (MW) Original Actual(A)/ As
Expected
Syn. COD Syn. COD
Comm Comm
State Sector
3 Dr. Narla Tata Rao 8 800 03/19 07/19 03/20 07/20 Boiler erection started on 22.05.2017. Drainable Hydraulic
TPP Stage-V 06/19 06/20 Test completed on 05.03.2019
APGENCO Pass I erection and Pass II erection works under progress.
Distt. Vijayawada,
TG deck casting completed. TG and condenser erection
Andhra Pradesh
Original / Latest Cost Rs. 5515 Crs.
started.
ESP erection started on 15.03.2017.
Total Expenditure Rs. 4935.59Crs (12/2020)
incurred till date BOPs.
Approval date: CHP: JT erfection works under progress. WAGON TIPPLER
Zero date: 15/12/2015 - Wall raised upto RL 24.30 & Floor slab completed. Walls
Financial closure Completed above FS 109/109m 1st lift completed. Re bar tying &
Main Plant Order BTG order placed on BHEL on 28.10.15. shuttering for wall in progress. pedestal completed.
BOP Package Tendering for BOP packages completed and order placed Track Hopper: 1 to 8 walls, MB-2 wall side 10.9/12.4
on M/s. BGR energy Systems Ltd on 06/07/2016. (36 completed. MBI wall through slip from under progress.
months for completion of BoP)
Type of fuel /FSA Coal / Available AHP: Ash water pump house steel for roof beams is in
PPA Available with 4 DISCOMS before bifurcation of A.P. To progress. Ash slurry pump house columns final lift
be revised with 2 DISCOMS of A.P completed.
Power Evacuation Under progress Seal water sump walls final lift concrete completed. AHP &
system MRS compressor house columns first lift above plinth beam
Land Possession: Available under progress. Vacuum pump house concreting of all roof
Water allocation: Available beams is completed. Hydrobins 1,2&3 columns 3rd lift above
MOE & F clearance: Available plinth beam completed. Silo 1: columns IInd lift completed,
State Pollution Control Board Clearance: Available
Civil Aviation clearance: Available
silo 2 columns 3rd lift completed. Silo utility building roof
slab completed. Ash water sump walls under progress. Ash
slurry sump works under progress. Bottom Ash Hopper-
Mechnical erection of hopper completed.
ID Fan- Fan A : Alignment of coupled fan shaft with
motor is under progress Fan B : lube oil flushing is under
progress.
Mills- Mill A and Mill –B Mounting of sale plates and
grouting work Completed, Mill-B and Mill-C Mountnig of
Sale plates (elevation and Master level) and grouting work
under progress
Cooling Towers: 80 % of NDCT works completed and
NDCT is ready for synchronization activity. Pre-cast elements
erection -2573/3807 Nos completed and in progress. other
internal works like Hot water ducts walkway at elevation 15.0
OM pipe support pedestals, Fills erection etc, are in progress.
Chimney: Chimney works completed for boiler light up. AR
brick liniling completed cage ladder elevator and Lab in
chimney are yet to be completed. 90 % of Chimney works
completed.
PT Plant /DM Plant: Raw water, PTP & DM water
Mechanical erection works are completed. DM plant one
stream (stream-A) Commisioned. Stream-B resin filling
completed and entire stream is Kept ready for
Commisiong, DM water generation started on 12.09.2019
CW System: 530/563 mtrs CW pipeline RCC base raft
completed ACW pipe line. 328/409 mtrs erection completed
in CWPH. Erection ofgates and Screens for CW pumps is
under progress. 83% of CW and ACW pipe line erection
completed
Switch Yard: 400 KV extension Switchyard charged on
28.02.2019 and charging of Station Transformer charging
completed by 12.06.2019

Critical issues
Reasons for Delay
SB-Jan 2020

TPM_Broad Status Report (January-February’2020) 90


Commissioning Schedule
Sl. Project Details Unit Capa- Broad Status
No. No. city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
Private Sector
4 Thamminapatnam TPP Ph-II 3 350 01/12 06/12 10.02.18 (A) 09/19  Unit-3: . Synchronized - 10.2.18. Full load - 15.4.18.
(M/s Meenakshi Energy Pvt.Ltd.), 05/12 15.04.18 (A)
Thamminapatnam 4 350 03/12 09/12 6/19 10/19  Boiler: erection started on 16/11/11. Drum lifted in 16/05/14.
10/19
Distt.: SPSR Nellore, 08/12 Non-drainable HT completed on 06.08.17. BLU
Andhra Pradesh Completed on 30.11.17. Steam Blowing completed on
Original /Latest Est. Cost :Rs 312000 Lakhs ( 600 MW) / 500500 Lakhs ( 20/12/17. Unit synchronized on 10.2.18. Full load
700 MW) achiebed on 15.4.18.
Expenditure during 2008-09 :Rs -NIL-  TG: Condenser erection started in 15/03/15 & TG erection
Expenditure during 2009-10 :Rs 1157.00 Lakhs started in 04/07/15. LP & HP turbine final box up completed
Expenditure during 2010-11 :Rs 42362.00 Lakhs on 14.02.17. TG oil flushing completed on 27.11.17 and
Expenditure during 2011-12 :Rs 53379.46 Lakhs TG on barring gear. Final Boxed –up on 27.07.17
Expenditure during 2012-13 :Rs 21802.67 Lakhs
Expenditure during 2013-14 :Rs 47833.82 Lakhs Unit-4:
Expenditure during 2014-15 :Rs 81656.43 Lakhs
 Boiler: erection started in 22/09/14. Drum lifted on 31.07.15
Expenditure during 2015-16 :Rs. 98832.77 Lakhs
.HT (Non drainable) completed in 5/18. SBO completed in
Expenditure during 2016-17 :Rs. 86250.65 Lakhs
01/19. Full load expected in 10/19.
Expenditure during 2017-18 :Rs. 74715.67 Lakhs
 TG: Condenser erection stated on 13/07/15. TG erection
Expenditure during 2018-19 :Rs 33450.49 Lakhs (2/19)
started on 29/10/15. TG box up done in 3/18. TG oil
Total Expenditure(up to 2/19) : Rs. 541440.96 Lakhs
flushing done in 06/18. Unit 4 reached 52 MW.
Approval date:
 Chimney: Ready for service.
Zero date:  CHP: Awarded to EDAC Engineering Ltd., Chennai on
Financial closure : 01/10/2010 18/06/10. Priority Stream-I trial run completed  Stream-II
Loan agreement signed with REC, IBDI & other Banks, commissioning work in progress  Stacker & Reclaimer – I&
REC as lead lender II – in operation mode. Sheeting is in progress.
Main Plant Order: 10/12/2009  AHP: Awarded to EDAC Engineering Ltd., Chennai on
Boiler –Cethar Vessels Ltd, Trichy, Tamil Nadu, India 18/06/10. Unit#3 completed  Unit#4 Completed.
TG – China National Automotive International  IDCT: Awarded to EDAC Engineering Ltd., Chennai on
Corporation, China (Harbin) 18/06/10. CT#3 Completed  CT#4 completed.
BOP Package  PTP: PT plant erection completed and commissioned.
Type of fuel  DM Plant: DM plant in operation mode.
PPA : PPA signed with M/s PTC on 25/02/2010 for 600 MW.  CW System: Unit#3 CW and ACW commissioning
Power Evacuation system : 400 KV MEPL – Manubolu (PGCIL) 27 km line is completed.  Unit#4 CW and ACW commissioning
completed by M/s Sujana Towers Hyderabad and completed.
charged. Agreement for Long Term Open Access for  FO System: LDO system completed and oil stored in tanks.
nd
1000 MQ with PGCIL on 2 January 2012.  SW Yard: Switchyard charging completed on 31.05.17.
 Land: 563.90 Acres of land acquired for entire 1000 MW. Switchyard Automation System (SAS) panels, Control Relay
 MOE&F: Clearance obtained on 03/06/2009 & 19/10/09. Further extended up to Panel (CRP) panel charging completed.
18/10/19 on 25/10/13.
 SPCB: Consent for Establishment received vide letter dated May 2011 for 1000MW.


Extension granted to 2021
Civil Aviation: NOC obtained on 28/02/11from AAI for 281 m height of chimney.
PROJECT UNDER NCLT
 Water:100 Cusec/day sea water from Kandaleru Creek accorded by Principal
Secretary (FAC), Infrastructure & Investment (Ports-I), AP on 18/02/10.
 Fuel Linkage: Letter of Assurance (LOA) dated 11th June 2009 obtained from
Mahanadi Coalfields Ltd (MCL) for the supply of 2.023 MMTPA Grade “F” Coal.
Fuel Supply Agreement dated 31 August, 2013 executed with Mahanadi Coalfields
Ltd(MCL) for the supply of 1.0115MMTPA Grade “F” coal for Unit 3 (350 MW).
Imported Coal Supply Agreement: Coal Supply and Transportation Agreement dated
25 November, 2013 executed, with GDF Suez Energy Management Trading SCRL,
34, boulevard Simon Bolivar, 1000 Brussels, Belgium. Coal Quantity : 2.50MMT per
annum
 BPTA: BPTA signed with PGCIL for 300 MW on 24/02/2010 and for additional
BPTA signed for 1000 MW on 02/01/12
 Mega Status: Achieved in 02/12

Critical issues
Reasons for Delay Slow progress of Civil works. Due to financial problem, work at site remained closed for a long time. Change of stakeholders and
subsequent change in the completion of various milestone.

TPM_Broad Status Report (January-February’2020) 91


Commissioning Schedule
Sl. No. Project Details Unit Capa- Broad Status
No. city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
Private Sector
5 Bhavanapadu TPP Ph-I 1 660 08/13 12/13 Uncertain Unit-1
(M/s East Coast Energy Pvt. Ltd.) Distt.: 10/13  Boiler: Boiler erection is started on 27/03/2014. 5th tier
Srikakulam, 2 660 01/14 05/14 Uncertain erection completed. Girders are to be placed which are
Andhra Pradesh 03/14 available at site.
Original /Latest Est. Cost :Rs 657194.00 lakh (Equity:debt::25:75) / 934315.00  ESP: Structures, hoppers erection is in progress.
lakh (09/07/14)  TG: Deck casting completed on 28/05/15. Power house
erection (2nd tier) is in progress. EOT crane to be erected
Expenditure during 2007-08 :Rs 1674.00 lakh
 Unit-2
Expenditure during 2008-09 ;Rs 7018.00 lakh
 Boiler: Boiler erection started in 02/15. 2nd tier erection
Expenditure during 2009-10 :Rs 27800.00 lakh
Expenditure during 2010-11 :Rs 72100.00 lakh completed.
Expenditure during 2011-12 :Rs 22900.00 lakh  ESP: Piling completed.
Expenditure during 2012-13 :Rs 29208.00 lakh  TG: Raft casted on 29/05/15. TG columns scaffolding
Expenditure during 2013-14 :Rs 76300.00 lakh work is in progress. Condenser erection yet to start.
Expenditure during 2014-15 :Rs 82210.00 lakh BoP’s
Expenditure during 2015-16 : Rs. 53006.00 lakh  Chimney: Order placed on M/s. R S Pabla in Oct, 10.
Total Expenditure (till 01/16) :Rs 3785. 60 Crores Shell casting completed. Flue can erection is in
progress.

Stressed Project
Approval date:
 CHP: Awarded to M/s BSBK. Piling completed.
Zero date: : 15/09/2010
Dewall works in track hopper area completed.
Financial closure : Achieved on 08/09/2010. Lead Financier - PFC  AHP: Order placement is in progress.
Main Plant Order: Order placed on 03/09/2009 on DEC China (BTG)  WTP: Engineering is in progress.
BOP Package : EPC of BOP & Main plant Civil works contract  DM Plant: Engineering is in progress.
awarded to consortium of M/s NEC and M/s Abir  CW System: Engineering is in progress.
Infrastructure Pvt Ltd on 30/01/10.  NDCT: Order placed on M/s Paharpur Cooling Towers.
Type of fuel  FPS: Engineering is in progress.
PPA :Long term PPA signed with PTC India Ltd on  FOS: Order placed on Delta P.D. Pumps on 14/05/12.
25/06/10 as an amendment of 06/05/09 Tank fabrication work completed.
Power Evacuation system Switchyard: Engineering is in progress.
 Land: Total land of (2050 + 36.94 Colony) Acres is acquired. ATS: Award of contract to be done by ECEPL.
 MoE&F: Clearance obtained on 09/04/2009 & revalidated on 20/08/14.
 Water: Permission for drawl of 168 cusec sea water from Govt. of AP is obtained on
10/06/2008.  Presently work held up at site
 SPCB: clearance obtained from APPCB on 15/06/2009 revalidated on 30/12/14.
 Civil Aviation: AAI clearance obtained vide lr. Dt. 04/03/08 & revalidated up to 3 rd due to financial issues.
March 2020.
 Coal Linkage / FSA: LOA received from MCL for 4.273 MTPA on 11/06/2009. FSA
to be signed. FSA signed with Global Fuels pvt Ltd Singapore for balance quantity of PPA details are as follows: Having PPA for 100 MW
coal on 23/04/09 with Kerala. Having LOI for 300 MW but in dispute
 BPTA: BPTA signed with PGCIL on 21/09/12. due to formation of Telangana. For 500 MW PPA with
Andhra Pradesh, developer is L1.

Critical issues Signing of FSA. SLC to decide.


Readiness of ATS from Plant to power grid pooling station at Palasa (42 km) by M/s East Coast.
Allotment of land for railway siding, sea water intake pipelines and pump house by Govt. of A.P.

Reasons for Delay Law & Order problem, Financial problem of the company, acquisition of balance land for sea water intake & railway siding.

TPM_Broad Status Report (January-February’2020) 92


BROAD STATUS OF THERMAL POWER PROJECTS IN TELANGANA

Commissioning Schedule
Sl. No. Project Details Unit Capa-city Broad Status
No. (MW) Original Actual(A)/ As
Expected
Syn. COD Syn. COD
Comm Comm
State Sector
1 Kothagudem TPS –VII (TSGENCO) 12 800 09/17 12/17 30.06.18 26.12.18
Distt. Kammam, Telagana 11/17 05.10.18 (A)
(A)
Unit Synchronised on 30.06.18. Full load
achieved on 05.10.18. COD on 26/12/18.
Original Estd. Cost/Latest Cost : Rs. 554844 lakhs / Rs. 554844 lakhs
Expenditure during 2014-15 : Rs. 199.60 lakhs  Boiler: Civil work started on 12/06/15 and erection
Expenditure during 2015-16 : Rs. 54654.50 lakhs commenced on 24/01/2016 and is in progress 98.4%
Expenditure during 2016-17 : Rs. 170310.10 lakhs completed. HT (Drainable) completed on 22.09.17.
Expenditure during 2017-18 : Rs. 107615.42 lakhs BLU completed on 31.01.18. TG Deck: TG civil
Expenditure during 2018-19 : Rs. 130783.19 lakhs (12/18) work started in 23/08/15. TG erection started on
Total Expenditure(Up to 12/18) : Rs. 466995.13 lakhs 28.02.17. TG Boxed up in 06/18.
Approval date:
Zero date: 01/01/2015 BOPs
 CHP: Civil work awarded to M/s. SNC on 12/02/16.
Financial closure Tied up with REC on 17/01/2014 94% completed. Wagon tippler side arm charger
Main Plant Order (BTG on M/s BHEL)- LOI issued on 27/12/14. works completed. Stacker cum reclaimer awarded to
BOP Package M/s TRF on 12/08/15 commissioning of SCR-I
Type of fuel Coal, FSA: M/s Singareni Collieries Co. Ltd, Kothagudem. completed. Conveyor system awarded to M/s.
BEVCON on 22/08/15: Material received and
PPA PPA signed on 22/01/2013 and power evacuation system
erection work under progress. Crusher, vibrating
400 Kv by TSTRANSCO.
screens/peddle feeder awarded to M/s Elecon on
Power Evacuation system 400kV by TSTRANSCO 23.02.16- Material received Erection works in
 LOI was issued to BHEL on 27/12/2014 (i.e Main plant equipment Boiler, Turbine & Generator- progress.
BTG)  AHP: Civil work Awarded M/s SNC on 12.02.16.
 MOEF clearance obtained on 16/07/15. 93% completed. Supply & Erection work awarded to
 SPCB clearance obtained on 12.11.15 M/s OSM : 95% material supplied.
 SPCB: Applied for consent for establishment and approval awaited.  Cooling Tower: Awarded to M/s. Paharpur cooling
 REC has sanctioned a loan vide letter dated 17/01/14. towers ltd. on 04/03/16, work started on 12/07/16 and
 Water allocation available vide G.O.MS No.47, dated 24/12/14. 99.8% completed.
 AAI clearance obtained vide letter no. AAI/SR/NOC/RHQ dt.15/10/12.  Chimney: Awarded to M/s. BIL on 16/05/15.Chimney
is completed.
 PT Plant: Civil work Awarded to M/s. Punj Lloyd Ltd
(PLL) and 95% completed. Supply & erection
awarded to M/s Clear water: 98% material supplied &
80% work completed.
 DM Plant: 98.5% completed.
 CW System: 98% civil works completed.
 Fuel Oil Handling System: 97% civil works
completed.
FGD: LOI issued to M/s BHEL
for providing wet lime based
FGD with completion period of
30 months. Works yet to start.
Critical issues
Reasons for Delay

TPM_Broad Status Report (January-February’2020) 93


Commissioning Schedule
Sl. No. Project Details Capa- Broad Status
city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
State Sector
2 Bhadradri TPP (TSGENCO) 1080 Unit 1: Synchronisation 19.09.2019
Distt. Khammam, Boiler: Boiler erection started on 15.09.17. Boiler
Telangana
U-1 270 02/17 03/17 19.09.19(A) 01/20 drum lifted on 06.01.18.Boiler hydro test completed
03/17 01/20 on 17.08.18. BLU 25.03.2019. SBO – 23.07.2019
U-2 270 04/17 05/17 12/19 03/20 TG: TG civil work staretd on 06.11.15. Condenser
05/17 02/20
erection started on 01.06.18.TG erection started on
U-3 270 06/17 07/17 06/20 06/20
07/17 06/20 01.09.18. TG box up 13.02.2019, TG Oil flushing
U-4 270 08/17 09/17 12/20 12/20 01.04.2019
09/17 12/20 Unit 2:
Original Estd. Cost /Latest Cost Rs. 7290.60 Crs./ Rs.8536.98 Crs (including Boiler: Boiler erction started on 12.01.18. Boilerr
FGD system)
drum lifted on 28.03.18. Boiler hydro test
Expenditure during 2015-16 Rs. 1000 Crs. completed on 04.11.18. BLU on 19.10.2019.
Expenditure during 2016-17 Rs. TG: TG civil work staretd on 06.11.15. Condenser
Expenditure during 2017-18 Rs.
erection started on 29.11.18. TG erection started on
Expenditure during 2018-19 Rs.
Total Expenditure Rs. 66325.52 Crs. ( Current year-up to 3/2020) 10.01.19. TG Box up 03.07.2019. TG oil flushing
Approval date: 25.09.2019
Zero date: : 21.03.2015 Unit 3:
Financial closure Power Finance Corporation Ltd sanctioned loan Boiler: Boiler erction started on 11.01.18. Boiler
for an amount of Rs.5832.34 Cr. vide Letter drum lifted on 28.03.18. Boiler hydro test
dated- 03.06.2015
completed on 26.11.18. BLU on 30.12.2019.
TG: TG civil work staretd on 04.12.15.Condensor
Main Plant Order EPC order placed on BHEL on 21.03.15.
erection start on 11.06.2019. TG erection start on
BOP Package 20.06.2019.
Type of fuel MoC sanactioned 4.2 MTPA on 15.02.2018 Lt Unit 4:
No 23014/1/2018-CLD. Boiler: Boiler erction started on 08.03.18. Boiler
PPA TS Discoms on 07.09.2019. drum lifted on 21.08.18.
TG: TG civil work staretd on 04.12.15. TG erection
Power Evacuation system Commissioned in February 2019. started on 17.12.19. Condenser erection started on
24.12.19.
1. State Government Permission: As directed by Govt. of Telangana State vide
letter from Chief Minister Office, i.e. Lr No. 177/PrlSCM/2014, Dt-1.12.2014
2. Water Allocation: State Govt. has allotted for drawl of 1.4 TMC of water per BoPs:
year@ 45 cusec from Godavari river vide G.O.Ms.No. 03, dt-07.01.2015  CHP: conveyer package- 37% , completed. Stacker
3. Civil Aviation Clearance for Chimney: NOC issued by AAI vide Ref.No.
AAI/SR/NOC/RHQ dt:11.12.2015 Reclaimer- 24 % completed. Wagon Tripler civivl
4. Environmental Clearance from MoE&F& CC, Gol.: EC obtained on Dt: work in progress.
15.03.2017.  AHP: 26 % completed.
5. State PCB Pollution Clearance for water & Air (Consent for Establishment):
Obtained on 30.03.2017.  Cooling Tower: 92% completed.
6. Land Possession : 1179.394 Acres  Chimney: 82% completed.
 DM Plant – 80% completed
 PT Plant – 85 % completed.
 CW treatment plant: Works not started.
 Switchyard – 86 % competed.

FGD: Agency not finalized yet.

Critical issues Readiness of DM plant is subjected to availability of Raw water at Reservoir.


Rediness of FO System subjected to availability of fiuel, oil.

Reasons for Delay Work held up due to order from National Green Tribunal (NGT) and non-availability of MoE&F clearance.

SB –Jan 2020

TPM_Broad Status Report (January-February’2020) 94


Commissioning Schedule
Sl. No. Project Details Capa-city Broad Status
(MW) Original Actual(A)/ As
Expected
Syn. COD Syn. COD
Comm Comm
State Sector
3 Yadadri TPP (TSGENCO) 4000 Civil Works in progress. U #1 & 2 Boiler
Distt. Nalgonda,
Telangana erection expected to start by 12/19& Jan 20
U-1 800 07/20 10/20 07/20 10/20 Engineering activites are under progress
09/20 09/20
.Inhousing material and sub contracting in
U-2 800 07/20 10/20 07/20 10/20
09/20 09/20 progress.
U-3 800 03/21 6/21 03/21 6/21
05/21 05/21
U-4 800 03/21 6/21 03/21 6/21 FGD: Included in the revised LOA placed on
05/21 05/21 M/s. BHEL. Scheduled completion of Unit
U-5 800 07/21 10/21 07/21 10/21 with the new norms is as follows: U-1 & 2 –
09/21 09/21
Original Estd. Cost /Latest Cost Rs. 29965.48 Crs.
08/.20
Expenditure during 2015-16 Rs. 486 Crs U-3,4 – 04/21 and U-5 – 08/21
Expenditure during 2016-17 Rs. Main plant Package All Unit Power house
Expenditure during 2017-18 Rs.
Structural fabrication works are in Progress
Total Expenditure Rs. 5861.88 Crs. ( 11/19) ESP / Boiler foundation are in progress
Approval date:
Zero date: 17.10.2017
Financial closure M/s. REC (Rs.16070.5 Cr vide letter dated 11.8.15)
and
M/s PFC (Rs.4009 Cr vide letter dated 19.7.15)
Main Plant Order LOI has been issued to M/s BHEL on 17.10.2017.
Three Purchase Orders were issued to M/s. BHEL on
Single EPC basis vide dt: 29-03-2018 towards
Supply, Erection & Commissioning and Civilworks
Type of fuel Coal. MOU with M/s SCCL for supply of 14
million MTPA of G9 grade domestic coal.
PPA Govt of Telangana issued Permission to avial 4000
MW power though TSDISCOMs vide its
21.08.2017. PPA is yet to be enetered.
Power Evacuation system 400 KV Jangaon, Maheshwram, Choutupppal and
Dindi
1. Water Allocation: State Govt. has allotted for drawl of 208 CUSECS ( 6.60) TMC of
water per year from Krishna river vide G.O.Ms.No. 13, dt-30.01.2015.
2. Power Purchase Agreement:- Govt. of Telangana issued Permission vide letter Dt:
21.08.2017 to avail entire 4000 MW Power from YTPS through TSDISCOMS Power
purchase Agreement is yet to be entered.
3. Forest Clearence: Stage II clearance was accorded by Central Govt. MOEF &CC for
diversion of forest land of 1892.35 Ha vide Lr. No. F.No. 8.07/2015-FC dtd 7.7.15.
Subsequent Govt order was issued by Govt. of Telanagan vide G.O.Ms. No.38, dtd
30.7.15
4. Environmental Clearance from MoE&F& CC: TOR granted vide Lr. No. J-
L13012/18/2015-IA.I(T) GolMOEF &CC Dt: 16.02.2016.
5. Land possession : 5459.39 Gts
6. Coal Linkage/ Fuel SCCL/ 14MMTPA OF G9 grade coal
7. Power Evacuation : 400KV Janagaon, Maheswaram, Choutuppal and Dindi

Critical issues
Reasons for Delay Work held up due to order from National Green Tribunal (NGT) and non-availability of MoE&F clearance
SB-DEc2019

TPM_Broad Status Report (January-February’2020) 95


BROAD STATUS OF THERMAL POWER PROJECTS IN KARANATAKA

Unit Commissioning Schedule


Sl. Project Details Capacity Original Actual(A)/ As Broad Status
No. (MW)
Expected
Syn. COD Syn. COD
Comm Comm
State Sector
1. Yelahanka Combined Cycle 1 370 Unit 1:
Power plant. GT 10/17 03/18 13/20  Main Plant: GT erection started on
Karnataka 3.04.2017. GT and Generator erected, GTG
ST 02/18 03/20 Aux. erection is in progress (92%). GT Aux.
Original Cost / Latest :Rs 1571.18 Crs / Rs. 1571.18 Crs erection is in progress (70%). STG HIP
Cost module, Generator erected. LP turbine
erection under progress. ST Aux. erection is
Exp. during 2016-17 : Rs 215.668 Crs in progress 60%). HRSG: Leak test
Exp. during 2017-18 : Rs 932.1737 Crs completed, box up completed and insulation
Exp. during 2018-19 : Rs 114.38 Crs ( 2/19) work in progress (87%).
Total Expenditure : Rs 1575.9895 Crs (up to 12/19) STG building structural erection 94%
Approval date: completed. GTG building completed.
BFP/GBC – EOT Crane girder and EOT
Zero date: : 09.11.2015 erection works completed.
Financial closure : 12.01.2017  BOPs:
Main Plant Order : M/s BHEL  Chimney: 23/23 Chimney shells erected up
HRSG Civil Work M/s BHEL to 58.5-meter height (Full Height) completed
Type of fuel Gas (96%).
 CT: Civil work is in progress. 95%
PPA : PPA agreement is under review. completed. Shell internals erection is in
Power Evacuation system Power evacuation work is entrusted to progress (85 %)
M/s.KPTCL and work start up power charged on  CW system: CWP cold and hot tunnel
25.01.2019 hydraulic test completed, colling tower,
forebay inlet screen erected.
 Land: 102.33 acres of land possessed by KPCL.  PTP: Civil works in progress.
 DM Plant: Commissioning of Equipments is
 MOE&F: NOC obtained on 01/09/2015. in progress.
 SPCBC: NOC obtained on 02/12/2015.  Switch Yard: 220 Kv switchyard GTG
Transformer and UAT through Line-I & LT
 Gas allocation/FSA: KPCL & GAIL entered Gas Transport & Supply /HT switch Yard Charginged.
agreement on 24.06.2017. M/s. GAIL have early Supply line and ready  FPS: MVWS, HVWS piping erection,
for Suppling the gas Generation. Regular line work is also completed. testing (85%) completed. Balance work
under progress.
 Civil Aviation: NOC obtained from Airports Authority of India on  Air Conditioning & Ventilation: Erection of
05/05/2015. Chiller units, condenser pumps, chilled
 Water: 15 MLD from Jakkur tertiary treated water plant. water pumps ,piping and fans is in progress
(70%) Hydraulic
 Control & Instrumentation: Control panel
erected and cable laying work in progress
(90%)
 LT Switch gears: panel erection work
completed and cable laying work in progress
(90%)
 Cables(Power/Control): Cable tray erection
works is in progress.Ballance work is in
progress (90%)
 Generator Transformers: GT/ST transformer
testing completed .
 Unit Transformers: UATs erected and
testing of UAT-I completed. Testing of
UAT-2 is in progress (85 %)

Critical issues ----


Reasons for Delay Delay in Civil Works
SB-21.1.2020

TPM_Broad Status Report (January-February’2020) 96


BROAD STATUS OF THERMAL POWER PROJECTS IN TAMIL NADU
Commissioning Schedule
Sl. No. Project Details Unit Cap-acity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Syn. COD Syn. COD
Comm Comm
State Sector
1 Ennore SEZ SCTPP 1 660 07/19 03/21 06/21 08/21
TANGEDCO (Distt. Thiruvallur) 07/20 07/21 Unit-I
Tamil Nadu 2 660 09/19 05/21 09/21 11/21 Boiler: Boiler civil works start on 27.03.2017
09/20 10/21 and erection started on 15.09.17. HT expected
Original Cost/ Latest Cost : Rs. 9800 Crores (Includes cost of FGD, ECHS and by 15 Jan/20. Pressure part & APH erection in
IDC) progress. 23423 / 29640 MT erected. Drainable
Total Expenditure (up to 12/19) : Rs 3960.728 Cr.
hydro test Completed.
TG Civil works started in 17.05.2017. raft casted
Approval date: : 12/12/2005 ESP 1: All inlet funnel erection completed. Pass
A air leak test completed. Outer roof & pent
Zero date: : 27/09/2014 house erection under progress 7243 / 9400
erected. Bottom hopper work & top inner roof
Financial closure Six months from the date of Award. work under progress.
Main Plant Order : Order placed on M/s. BHEL (EPC- Rs. 7688 Crores) on Unit-II
27/09/14. Amended order for Rs 126 Crores For Supply
Boiler: Boiler erection started on 08.06.18. HT
and erection works of environment norms and hence total
EPC cost now revised fromRs. 7688 Crores to Rs. 7814 expected by 01/20. 15639 / 29640 MT erected.
Crores. TG Civil works started in 17.05.2017.Raft &
BOP Package Column: 28/28 TG lifts completed, presently
Type of fuel : Long term Coal Linnkage application submitted on Bottom reinforcement and insert fixing under
Coal Linkage /FSA 26.02.2010 to Ministry of Coal/GoI/New Delhi for supply progress.
domestic coal. Coal allocation is yet to be received. ESP 2: Cooleting electrode loading under
However, MoU has lready been signed beween MMTC & progress in Pass-B. 5847 / 9400 MT erected
TANGEDCO on 25.06.2012 for the supply of 100%
imported coal. During the standing linkage committee BOP:
(SLC) meeting held on 24.6.2019 it has been decided that Chimney: Shell completed (270m). Platform
the discussion on Bridge linkage will be taken up in the
next SLC meeting.
girder erection under progress.
AHP / CHP : Stacker Reclaimer: 1A/1C: 18/18
PPA Schedule dates Actual/ Anticipated N.A. State sector modules completed; 1B/1D: 14/18 modules
project. Entire100% power will be utilised by Tamil nadu completed. Transfer Tower: RC piling for TT 1-
Power Evacuation system Power will be evacuated from the proposed thermal 12 completed, pile cap/pedestal works under
power station through double circuit 400 KV transmission progress. TT-8,10 & 11 superstructure erection
lines i.e, through 2 Nos. Of 400 KV line to 765 KV under progress. External Coal Handling System:
Pooling Station and 2 Nos. 400 KV lines to ETPS Test pile- 57/66 completed; 32/66 load test
Expansion STPP. completed and repTest pile- 36/66 completed;
28/66 load test completed
 Land: Aquistion of land does not arise since own land of TANGEDCO ( Out of
Aux Boiler: : Civil foundation works completed
1100 acres available at Ash dyke of NCTPS, only 500 acres utilised for project
except 2 Nos FD foundations. Erection started on
development).
 MOE&F: NOC obtained on 07/01/2014. 07th Aug 2019.
 SPCBC: NOC obtained on 11/03/2014. Clarified Water Tank: Wall three sides
 Civil Aviation: NOC obtained from Airports Authority of India completed. TANGEDCO not permitting fourth
 Water : 4 MGD water from CMWSSB. side casting with the supplied puddle flange.
 Fuel / Coal : SLC on 24.06.2019 it was decided that the Bridge Linkage will be Work on hold since Feb-19.
taken in next meeting. Cooling : NDCT-1: All 24 segments casting
 Due to Court case/ High Court order work held up at site from 10/15 completed on 31st July’19. 6/48 pedestal
completed; Basin slab works. NDCT -2: Ring
onwards. M/s TANGEDCO filed Special Leave Petition (SLP) in the
raft Ist segment concreting commenced on 16th
Supreme Court of India, hearing/arguments completed on 08/02/16. July’19, 9//24 raft casted shortly after
However, judgment in favour of TANGEDCO came on 18/10/16 only and moblizaton by vendor
work at site commenced with effect from 02/11/16. Switchyard GIS building, Control Room
building and 400 KV Towers pile and pile cap
works completed. Further civil works in progress.
Critical issues
Reasons for Delay  Due to Litigation Work temporarily suspended on 07.09.2015 and hence delay in execution of work and
work resumed on 19.10.2016 by BHEL at site after receipt of judgement from Supreme Court /New Delhi
in favour of TANGEDCO. 408 days and 185 days (on account of delay in handling over of land and
remobilization)
SB-17.01.2020

TPM_Broad Status Report (January-February’2020) 97


Sl. No. Project Details Unit Capa- Commissioning Schedule
No. city Broad Status
(MW) Original Actual(A)/ As
Expected
Syn. COD Syn. COD
Comm Comm
State Sector
2 Uppur SCTPP TANGEDCO at 1 800 02/19 04/19 02/20 09/20 BOILER : Unit-I Structural fabrication in progress -
Distt. Ramnad, Tamil Nadu 03/19 04/20 4296 tonnes.
2 800 06/19 11/19 08/20 02/21 Unit-II Structural fabrication in progress – 1800
07/19 10/20 tonnes.
Original Cost /Latest Cost : Rs. 12778 Crores. (BTG cost –Rs. 5580 Crores.) ESP : Erection of columns in ESP in progress.
BTG : TG Materials – 112734 tonnes ; Structural and
Expenditure during 2016-17 :Rs. 16.74 Crores reinforcement materials – 32553 tonnes received at
Expenditure during 2017-18 :Rs. 226.62 Crores site.
Expenditure during 2018-19 :Rs. 1594.15 Crores No. of
Expenditure during 2019-20 : Rs 755.81 Crores Total piles Balance
Sl.
Total Expenditure :Rs. 2592.69 Crors (up to 12/19) Location No of completed t to be
No
piles as on 30.9 completed
Approval date: 2019
Zero date: Revised from 20.05.2016 to 03.08.2017 Unit-I
1. 3123 3066 57
Financial closure Financial tie-up is proposed with M/s PFC.
2. Unit-II 3180 3113 67
Main Plant Order : Order placed on M/s. BHEL (BTG- Rs. 5580 Crores)
on 27/02/16. Balance of Plant by M/s Reliance Infrastructure Ltd.,
 Soil Investigation bore holes 30 Nos
BOP Package : Awarded to M/s. Reliance Infra Strucure Ltd, Mumbai completed. Balance 27 Nos in litigation land.
on 21.2.2018.
 Jungle clearance for about 240 acres completed.
Type of fuel : COAL MoU entered with MMTC for supply of  Construction of stores building (600 sq.m X 2
imported coal of 5.02 MTPA on 25.05.2015. Nos) in progress.
 Land Litigation - Judgement delivered by
PPA State owned project. Honourable High Court, Chennai on
Power Evacuation system 765 KVA 03.07.2019 not favourable to TANGEDCO.
Appeal being made by GOTN, Listed on
 Land: Out of 995.16 acres of land, Government Poromboke Land for 227.36 acres 14.01.2020.
and private patta lands of 767.80 acres. Around 192.36 acres of Govt. land in Sea water Intake & Outfall system by M/s. L & T
BTG area has been handed over by TANGEDCO to M/s BHEL on 21.07.2016 for  Laying of MS pipes in progress.
project preparatory works. The District Collector/ Ramnad has accorded enter  Gantry rail fixing works under progress for
upon permission to the patta land not covered under litigation for an extent of extension of 10 Tons capacity EOT crane to
407.74 acres to TANGEDCO on 03.08.2017. Out of this, around 63 acres of patta enhance productivity.
land in BTG area has been handed over by TANGEDCO to M/s BHEL on  Forest clearance: GO issued vide
03.08.2017. 552 Acres of land handed over to M/s RIL, BOP contractor on G.O(MS)No.49 dt 27-05-2019 for diversion of
17.03.18. Balance land pending for enter upon due to litigation is around 354 0.40 hectares of forest land for USTPP CW
acres. intake and pipe line structures and work
 MOE&F: Ministry of Environment and Forest has accorded clearance for the commenced on 30-05-2019. Work re-
above Project on 18.05.2016. commenced in offshore area on 28-08-2019 and
is in progress. District Collector has given
 SPCBC: CRZ committee of MOEF recommended the Project on 28.1.16 and
clearance to commence the earth filling for
MOM published in web site on 8.2.16.
earth bund in offshore area from 30.08.19
 Civil Aviation: NOC obtained from Airports Authority of India on 22.11.2012
onwards. But, due to High Court stay filling
valid up to 21.11.2019. Clearance further extended upto 21.11.2024
and earth bund formation works could not be
 Water: Tamil Nadu Maritime Board has issued NOC for construction of Jetty for
taken up.
drawal and discharge of cooling water, vide 27.4.2015.
 Laying of MS pipes in progress.
 Gantry rail fixing works under progress for
extension of 10 Tons capacity EOT crane to
enhance productivity.
 Forest clearance: GO issued vide
G.O(MS)No.49 dt 27-05-2019 for diversion of
0.40 hectares of forest land for USTPP CW
intake and pipe line structures and work
commenced on 30-05-2019. Work re-
commenced in offshore area on 28-08-2019 and
is in progress. District Collector has given
clearance to commence the earth filling for
earth bund in offshore area from 30.08.19
onwards. But, due to High Court stay filling
and earth bund formation works could not be
taken up.

Critical issues

 SB-21.01.2020

TPM_Broad Status Report (January-February’2020) 98


Commissioning Schedule
Sl. No. Project Details Unit Capa- Broad Status
No. city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. Trial Run
Comm Comm COD
State Sector
3 North Chennai TPP St-III by 1 800 02/19 07/19 03/20 06/20  Boiler: Civil works start on 09.02.2017 and Erection
TANGEDCO (Distt. 03/19 05/20 works started on 30.08.2017. Pressure part erection started
Thiruvallur), Tamil Nadu on 26.10.2018 and so far 10176 MT (89.85%) erected.
Original Estd. Cost : Rs. 6376.00 Crores (Including IDC) Pressure parts joints welding works 40530 Nos. (77.06%)
Expenditure during 2009-10 : Rs 0.02206 Crores completed. Drainable Boiler Hydro test was carried out on
Expenditure during 2010-11 : Nil. 31.12.2019. Balance pressure parts erection is in progress.
Expenditure during 2011-12 : Nil.  TG: TG civil work start on 24.04.2017 and erection start
Expenditure during 2012-13 : Rs 0. 2058 Crores on 25.02.2019 Condensor erection start 14.11.2018.
Expenditure during 2013-14 : Rs 0.3955 Crores Erection is in progress LP heater erected. Completed.
Expenditure during 2014-15 : Rs 0.1294 Crores TURBINE: HP turbine erected, ESV 2 no’s erected. ESV
Expenditure during 2015-16 : Rs 0.2529 Crores connection to MS line alignment fit up completed and
Expenditure during 2016-17 : Rs 198.0875 Crores being made ready for steam blowing. IP turbine trial box
Expenditure during 2017-18 : Rs 929.7544 Crores up completed. LP turbine radial & axial blade clearance
Expenditure during 2018-19 : Rs 2243.52 Crores sitting and Diffuser clearance setting are in progress. MD
Expenditure during 2019-20 : Rs. 1707.88 Crores (12/19) BFP erection is in progress. TD BFP 1 -Sole plate and
Total Expenditure (up to 2/20) : Rs 5304.14 Crores (2/20) anchore plate matching under progress. Pipe erection are
in progress.
Zero date: : 29/01/2016 (BTG Package) , 28.10.2016 BOP
 ESP: Civil works completed in ESP area and ESP grade
Main Plant Order : 29/01/16 (EPC) on M/s. BHEL- Rs.2759 slab completed in all passes except spare. Almost all six
Crores. passes completed. Finishing works is in progress. Balance
Boiler: Alstom, TG & generator: Siemens & internal erection and Monorail works are in progress.
BHEL BOPs
BOP Package 28.10.2016 (EPC) on M/s BGRESL- Rs.2600  CHP: ECHS: External Towers (5Nos)- All civil
Crores. foundation works completed. Structural erection is in
Type of fuel : COAL progress for ET 3 to 5. For conveyors 1C/1D, 4A/4B,
5A/5B & 6A/6B-structural erection under progress. For
PPA : Entire power is to be utilized by TANGEDCO. other conveyors civil works are in progress. Bulldozer
Power Evacuation : The power generated from this plant is shed- Tie beam work is in progress. Staircase work and
proposed to be evacuated through a 765 KV DC finishing works are in progress. Coal setting basin: Raft
feeder to the proposed North Chennai Pooling completed on 8.2.2019 and wall upto 2nd lift completed.
Station and 765KV DC link line feeder to the Pump room work is in progress. ICHS-Iternal Tower-
proposed Ennore Replacement Power Plant 9Nos.: Structrural erection completed for IT -1 to 3, 6 to 9
which will be established by TANTRANSCO and structrural works is in progress for IT -4 &5. Internal
Conveyor 1A/1B,2A/2B,3A/B,4A/B- Civil work
 MOE&F Clearances obtained on 20/01/2016. completed.Mechanical erection work under progress. For
other ICHS conveyors-Civil works are in progress.
 SPCB clearance obtained on 13.04.2017  AHP: Fly ash silo-1 & 2: Shell construction completed
upto 38.55m level. Bottom Ash silo: Shell completed on
 Civil Aviation: clearance obtained on 15/05/2013, valid for 7 years 22.04.2019. Pedestal final lift works under progress.
Cooling Tower: NDCT -Pond wall -100% completed.
 Water allocation: Water requirement for the project will be met from NDCT Shell Concrete work and pray cast beam erection is
existing fore bay of NCTPS stage-II. The make-up water for cooling in progress (124 lifts completd)
tower, boiler make-up & other sweet water requirements are to be met  Chimney: Chimney completed only staircase erection
from proposed desalination plant for this project. Construction water work is in progress.
 SWITCHYARD : 765KV GIS Building: Civil works
from M/s.CMWSSB available to the contractor from 07.01.2017.
major portions-95% completd. 230KV GIS Building:
Building works completed. Bay erections completed in
 FSA: MOU has been entered with M/s. MMTC for supply of imported 230KV. Charging of GIS control room Battery bank is in
Coal of 2.51 MTPA on 25.05.2015. MoP has recomanded to ministry of progress. 765KV GIS side wall brick work under
progress. transformer is ready for Charging cableing is
coal for long term coal linkage for 1.971 MT Indiginious Coal with completed and termination work is in Progress Startup
3800 GCV and 85% PLF as no coal block allotted for this project. power will be ready be end of Dec .2019
 Considering the revised emission norms, In
principle approval was given to M/s.BHEL for
making in boiler modification to achieve the
NOx reduction from 510 mg/Nm3 to 300 mg/
Nm3 on 18.08.2016 and commercial acceptance
was given on 31.03.2017.
 FGD is not included in the scope of both BTG
and BOP package. Opininon of consultant
sought for regarding the type of technology to be
adopted for FGD and allied issues like water
availability, disposal of gypsum etc.
Critical issues
Reasons for Delay M/s Bridge and Roof (for Boiler and Bunker erection) – Structureal works kept on hold due to internal issue
from 18.02.2019 and the work recommended on 22.04.2019 (two months).
SB-21.1.2020
TPM_Broad Status Report (January-February’2020) 99
Sl. No. Commissioning Schedule
Project Details Unit Capa- Broad Status
No. city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
State Sector
4 Ennore SCTPP 1 660 10/17 01/18 05/23 -  Boiler (M/s Lanco): Civil work commenced
TANGEDCO (Distt. 01/18 06/23 on 16/02/15. Boiler erection started on
Thiruvallur), Tamil Nadu 01/02/16
Original /Latest Cost :Rs 4956.00 / 5421.38 Crores  TG & Condenser: Civil work commenced
(03/2016) on 18/06/15. Condenser erection started on
Expenditure during 2014-15 :Rs. 23970 Crores 20/07/16 & TG erection started on 11/08/16.
Expenditure during 2015-16 :Rs. 2.8891 Crores BOPs
Expenditure during 2016-17 :Rs. 86.5609 Crores  Chimney: Awarded to LITL, Gurgaon.
Expenditure during 2017-18 : Rs.462.250 Crores
Chimney raft casting commenced on
Total Expenditure (up to 12/2017) :Rs. 791.40 Crores Lakh
Approval date:
22/07/2015. Shell concreting work started on
Zero date: : 14/07/2014 29/02/16, Shell casting completed in 3/2/16.
Financial closure  CHP: Awarded to M/s. FL SMIDTH (P)
Ltd. Chennai on 23/04/15. 70:30 Imported:
Main Plant Order : 30/05/2014 (EPC) on M/s LANCO and
lanco in turn awarded the BTG to Dong Domestic Coal. The soil investigation work
Fang electric corporation, China on commenced on 01/08/2015. NOC/ROW
18/02/15. EPC cost Rs.3921.55crs. (revised) (Statutory clearance) approval has been
BOP Package obtained from PWD for routing ECHS from
Type of fuel : COAL (70:30 Imported: Domestic Coal) North Chennai to project site through
PPA PPA does not arise as the entire power is to be Ennore Creek. The CE / PWD
utilized by TANGEDCO. recommended the proposal for the waiver of
Power Evacuation system Regarding Power Evacuation system is under track rent to Government on 18/11/2015 and
TANRANSCO scope. Go TN has not considered the case. LITL
 Letter of Acceptance for Main Plant Order (EPC) issued to M/s LANCO on 05/14 (27/02/14 remitted the Lease rent & refundable caution
asper lr dt 22/12/16). LANCO in turn placed order on Dong Fang Electric Corporation.,
China on 18/02/15. deposit to PWD on 26/11/15.
 MOE&F Clearances obtained on 18/09/2014.  CW System: Awarded to Kirloskar
 SPCB clearance obtained on 18/02/13. Brothers Ltd and Sea water intake & outfall
 Civil Aviation: clearance obtained on 16/05/2008 system-off shore to M/s Coastal Marine
 Water allocation: Sea water is available near the project. Cooling water consumption to be
drawn from Sea is 1,33,896 m3/day.
construction and Engineering Ltd, Mumbai
on 07/09/15. Intake pump house earth
Corporate Insolvency & Bankruptcy Process (CIRP) initiated against excavation under progress. The earth work
LITL(the EPC Contractor) by IDBI Bank from 07.08.2017 and interim excavation in cooling water intake pump
resolution professional appointed on 10.08.2017 and hence the project has house was commenced on 07/09/2015 and in
been stalled rom 07.08.2017. The CIRP process extended up to 04.05.2018. progress. LITL committed to complete the
permanent marking along the route by
31/12/15. Obtaining approval from various
departments is a time consuming process
hence M/s LITL was requested to arrange
statutory clearance from Railways,
Highways, Chennai Corporation, TNHB
etc., as early as possible.
 NDCT: Awarded to M/s Hamon Thermal
Europe S.A on 05/05/15. All the 768 piles
casting completed on 08/02/16. The earth
work excavation for pile cap commenced on
15/10/2015 and pile chipping commenced
on 16/12/15. Basin piling work under
progress.
 FO System: Award to M/s General
Mechanical Works Pvt. Ltd – Vadodara on
12/10/15.
 Switchyard: Switchyard and related
electrical systems are yet to be awarded.
Critical issues Corporate Insolvency & Bankruptcy Process (CIRP) initiated against LITL(the EPC Contractor) by IDBI Bank from
07.08.2017 and interim resolution professional appointed on 10.08.2017 and hence the project has been stalled rom
07.08.2017.
Reasons for Delay
SB-

TPM_Broad Status Report (January-February’2020) 100


Commissioning Schedule
Sl. No. Project Details Unit Capa- Broad Status
No. city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
Private Sector
5 TuiticorinTPP St-IV / M/s SEPC 1 525 07/18 10/18 06/20 10/20  Boiler: EPC contractor is M/s MEIL, in turn they
Power Pvt. Ltd. 09/18 07/20 awarded the BTG package to M/s BHEL on
(Distt. Tuticorin), in Tamil Nadu 30/10/15 and main plant civil work to M/s L&T
Original /Latest Cost : Rs. 3514.00 / Rs. 3514.00 Crores Geo Structures Ltd.
Expenditure up to 2015-16 :: Rs. 480.79 Crores  Boiler civil work started on 15/12/15 & erection
Expenditure during 2016-17 : Rs. 248.70 Crores started on 15/12/16. Boiler Drum lifted on
Expenditure during 2017-18 : Rs. 822.94 Crores 13.8.17. Bolier hydro Test(non drainable)
Expenditure during 2018-19 : Rs. 508.91 Crores completed on 28.12.2019. Boiler light up may
Expenditure during 2019-20 : Rs. 518.84 Crores (upto 31.12.2019)
bne May 2020.
Total Expenditure (up to 11/ 2019) :Rs. 2580.18 Crores
 TG civil work started on 01/06/016. TG
Zero date : 30/10/2015
erecction started on 8.9.17. TG Boxup expected
Main Plant Order : 18/01/2014 (EPC) on M/s MEIL & in turn BHEL Dec 2019.
for BTG.
BOPs:
Type of fuel : COAL Imported coal to be tied up in 6 months.
 CHP, AHP, CT, Chimney, PT and DM Plant,
PPA :PPA signed with TANGEDCO and approved by
TNERC CW system, Fuel oil system and all other
Power Evacuation system  For power evacuation 2x400 Kv line has been systems related to power evacuation, switchyard
approved by TANGEDCO and is to be including C&I, Fire protection system, air-
implemented by TANGEDCO/ conditioning & ventilation etc. are all awarded to
TANTRANSCO. M/s MEIL on 18/01/14. It is all the part of EPC
 Main Plant Package Awarded on EPC basis to M/s MEGHA Engg. and package.
Infrastructures Ltd. (“MEIL”) on 18/01/14. M/s MEIL in turn awarded the BTG  CHP: Awarded to M/s Lepton for Engineering
package to M/s BHEL on 30/10/2015. consultant & Monitoring agency for ICHS. Civil
 CPCB & MOE&F Clearances obtained and valid up to 10/11/18 and 03/11/17 foundation work is nearing completion.
respectively. MOE & F clearance extended up to 3.11.2020 Mechanical structural fabrication & erection
 Civil Aviation: Clearances obtained and valid up to 17.12.2021 under progress. Mechanical erection is under
progress.
 Land Possession: Land Lease Agreement & Concession Agreement signed with
VOC port Trust.  AHP: Awarded to M/s Macwalber Beckay Civil
 Water Allocation: Sea Water Desalination Plant is envisaged for meeting water
foundation work is in progress. Mechanical
requirement of the power pPlant Permission to draw Sea Water from Sheltered structural fabrication erection under progress.
Basin obntained from Port.  Cooling Tower: M/s MEIL awarded the IDCT
works to M/s Paharpur, civil works are nearing
completion.
 Chimney: M/s MEIL awarded the chimney
works to M/s Paharpur. Foundation works
completed. Shell concreting completed up to 275
mtrs. Inside brick wall work under progress.
 PT Plant: Civil works completed, Equipements
erection under progress.
 DM Plant: Civil works are nearing completion.
Equipements erection under progress.
 Fire Perotection System: Work under progress.
 Fuel Oil System : Civil works underway.
 CW System: CW packages awarded to M/s
Flowserve. Civil works are nearing completion.
 Switchyard: Civil work are nearing completion.
 LT / HT / Cables (Power) / Control) : Civil
works of LT / HT are nearing completion.
Ordering under progress.

Critical issues 1) Inter-connection & Transmission facilities are by TANGEDCO which is yet to be awarded. The COD is
linked to the availability of Start up Power.
(2) Approval/NOC from Department of Forests, GoTN for pipeleine and conveyor crossing.
(3) Fixation of revised date of availability of start up Power and accordingly the SCOD at TNERC.
(4) Approval of Coal Supply, Transport and Handling Agreements by TANGEDCO and TNERC.
Reasons for Delay Requirement of startup power was delay from 30.04.2018 to 09.04.2020 (Expected)
SB-03.02.2020

TPM_Broad Status Report (January-February’2020) 101


Commissioning Schedule
Sl. No. Project Details Unit Capa- Broad Status
No. city Original Actual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
Private Sector
6 Tuticorin TPP in Tamil Nadu 1 660 03/12 05/12 - -  Boiler: All civil work completed &
05/12
(Ind. Barath Power Limited) Boiler erection started.
Original /Latest Cost : Rs.359500 Lakh / Rs.359500 Lakh  ESP: All civil foundation work
completed. Erection started.
Expenditure during 2010-11 : Rs. 17000 Lakh  TG: All civil foundation work
Expenditure during 2011-12 : Rs 2000 Lakh completed. Condenser & TG erection
Expenditure during 2012-13 : Rs 31000 Lakh works yet to start.
Expenditure during 2013-14 : Rs. 9000 Lakh
Expenditure during 2014-15 : Rs. 91000 Lakh BOPs
Expenditure during 2015-16 : Rs. 500 Lakh  Chimney: Awarded to simplex
Total Expenditure(Up to : Rs. 2000.00 Crores Infrastructure. Foundation raft
05/2015) concreting is in progress.
Approval date: : 10/09/2007  CHP: Order placed on Sokeo Power.
Zero date: : 25/03/2010 / April 2012  AHP: Order placed on Sokeo Power.

Stressed Project
Financial closure : Achieved on 24/02/2011 Drawings under finalization.
Main Plant Order : 28/05/2010 (BTG) on M/s Shandong  ACC: Order placed on HAC China.
Runch Power Plant Engg and Technology Drawings under finalization. ACC
Limited. foundation works in progress.
Type of fuel : COAL  M/s Consolidated Construction
PPA : Participating in the Bids Consortium Limited have been
Power Evacuation system : BPTA signed with PGCIL on 24/02/2010. awarded main plant civil & structural
LTOA signed with PGCIL on 12/06/2013. work on 14/12/10. Civil work started
 Land: Total land of 880 acre acquired  WTP: Order placed on Sokeo Power.
 Water: Agreement between IBPML and South Ganga was signed on Engineering works in progress.
03/04/10.  DM Plant: Technical discussions are
 MOEF: clearance obtained on 12/07/2010. in progress.
 SPCB: Consent obtained on 17/10/2013.  CW system: Order placed on Sokeo
 Civil Aviation: clearance obtained on 24/08/10 Power. Technical specification
 PPA: To be executed through case –I bidding. verification is in progress.
 BPTA: signed with PGCIL on 24/02/2010  FO system: Engineering is under
progress.
 FPS: Foundation works completed.
Erection works to start from 01/16.
 Switchyard: Engineering in progress.

Critical issues Work held up due to no PPA in the market.

Reasons for Delay

TPM_Broad Status Report (January-February’2020) 102


Sl. Commissioning Schedule
Project Details Unit Cap- Broad Status
No. acity OriginalActual(A)/ As
(MW) Expected
Syn. COD Syn. COD
Comm Comm
State Sector
7 Udangudi STPP 1 660 12/20 03/21 12/20 03/21 Preliminary works Engineering activities, Geo
TANGEDCO (Distt. Thoothukudi) 02/21 02/21 Technical works, Approach road works,
Tamil Nadu 2 660 12/20 03/21 02/21 05/21 Topographical survey , Jungle clearences and
02/21 04/21
Temporary weigh Bridge Construction are
Original Cost/ Latest Cost : Rs. 13076.70 Crores (Includes cost of Pollution completed.
Control Equipments & IDC) *Site levelling and Grading work under progress.
{ a. Plant RS. 7894.169 Crores & *Boiler foundation earthwork excavation started
b. Coal Jetty Rs. 1902.87 Crores} and base concreting under progress.
Expenditure during 2010-11 Upto 31.03.2014 by UPCL : 102.84 Crores *Chimney earthwork excavation under progress.
Expenditure during 2012-13 : 0.64375 Crores Captive Coal Jetty for Udangudi Power Project
Expenditure during 2013-14 : 0.39802 Crores *Topographical Survey,Land investigation,
Expenditure during 2014-15 : 14.06281 Crores Bathymetry Survey, Marine investigation and
Expenditure during 2015-16 : 0.54035 Crores Construction enabling activities completed.
Expenditure during 2016-17 : 0.14855 Crores *Approach Pile and Pile cap construction
Expenditure during 2017-18 : 0.29594 Crores activities are under progress in the off shore for
about 1 Km from shore are completed.
Expenditure during 2018-19 : 336.4342 Crores
*Approach Pile and Pile cap construction activities
Expenditure during 2019-20 : 439.4635 Crores are started in the off shore from 4 Km
Total Expenditure (up to 10/19) : 881.82712 Crores from shore as a next reach.
Approval date: :
*Casting of PSC Girders and Accropode Pre
Zero date: : 07.12.2017
casting are under progress.
Financial closure . Financial tie up with REC *Pre casting of deck slab are under progress.
Main Plant Order & BOP : EPC Contract was awarded to M/s. BHEL of Rs. *Brake water construction and Construction of
7359.00 Crores on 07.12.2017. compound wall work under progress
Captive Coal Jetty EPC Contract was awarded to M/s ITD Cementation Unit-2 has a phase difference of 2 months
India Ltd for Coal Jettey to the Power Project for an
amount of Rs. 1902.87 Crores (Post GST)
Appointment of Consultants (For Plant) - Project
Type of fuel : COAL. MMTC clearance obtained on 19.11.2012 Management Consultancy LOA was issued to
(Import coal) M/s.TATA Consulting Engineers Ltd., on
19.02.2019 for engaging Project Management
PPA N.A. State sector project. Entire power will be utilised Consultancy services in the post award of EPC
by Tamil nadu contracts till completion of entire project and
consultancy services for preparation of tender
Power Evacuation system 400 KV specification, analysis of bid, award and post
 Land: Out of 1040 acres of land, Government Poromboke Land is of 760 acres award PMC services until completion of the FGD
and private patta lands of 280 acres. Around 760 acres of Govt. land and 135 & SCR.
acres of private land had been handed over by TANGEDCO to M/s. BHEL on
15.12.2017 for project preparatory works. Almost all 280 acres of private land For Captive Coal Jetty - TANGEDCO Board has
are inpossession of TANGEDCO except 11 acres which are under court case. approved the proposed of consultancy services
66 acres of land has been handed over to M/s. ITD cementation India Ltd. EPC through IIT Madras on nomination basis and the
contractor for Captive Coal Jetty. same was approved by GOTN on 07.02.2019.
 MOE&F: Ministry of Environment and forest has accorded clearence for the
above project on 14.10.13 and valid up to 13.10.2020. CRZ clearence awarded
for coal jetty on 06.06.2011 and valid up to 05.06.2021.
 SPCB Clearance: TNPCB has given the consent for extension up to
31.03.2020.
 Civil Aviation Clearance: Obtained on 19.07.2016 valid till 18.07.2023.
 Water: Intake of 21000 m3/hr and outfall discharge of 13500 m3/hr as perCRZ
clearance dt.6.6.2011

Critical issues
Reasons for Delay

SB-21.01.2020

TPM_Broad Status Report (January-February’2020) 103


Eastern
Region
Thermal Power Plants

TPM_Broad Status Report (January-February’2020) 104


BROAD STATUS OF THERMAL POWER PROJECTS IN BIHAR
Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
State Sector
1. Barauni Extn TPS 8 250 02/14 14.11.17(A) 05/18 Unit-8 :Commissioned on 11.01.2018.
P.O.: Barauni, 05/14 11.01.18(A)
Synchronisation on 14.11.2018.
Dist: Begusarai Bihar
31.03.18(A) Boiler: Boiler erection started on 10.12.12. Drum lifted on
(BSPGCL)
9 250 04/14 31.03.18(A) 06/18 05/09/13. Erection of pressure part, ID/FD/PA Fans, APH,
07/14 piping completed. HT done on 21/08/14. Non drainable Hydro
(2x250 = 500 MW)
Test completed. Boiler Light Up with LDO on 18.06.2017, SBO
completed on 04.09.17. Synchronized on 14.11.17ESP:
Original /Latest Cost :Rs 3666.06 Cr. / Rs. 5308.07 Cr Mechanical erection completed and one stream is ready
Expenditure during 2008-09 Rs 25.00 lakhs for use. Another stream of ESP is in progress. Insulation
Expenditure during 2009-10 :Rs 00.00 lakhs & cladding is under progress
Expenditure during 2010-11 :Rs 12500.00 lakhs  TG: Erection of Condenser & TG started on 26/08/14 and
Expenditure during 2011-12 :Rs 25958.00 lakhs 25/08/14 respectively. TG Boxed up on 31/12/15 .TG oil
Expenditure during 2012-13 :Rs 67706.00 lakhs flushing completed in 12/16.
Expenditure during 2013-14 Rs 145630.00 lakhs
Expenditure during 2014-15 :Rs 77058.00 lakhs Unit-9: Synchronisation & Commissioned on
Expenditure during 2015-16 Rs 87030.00 lakhs 31.03.2019.
Expenditure during 2016-17 Rs 64041.00 lakhs
 Boiler: Erection started on 02-12-12, Drum lifted on 15.09.13.
Total Expenditure :Rs 479951 Lakhs (up to 03/17)
Approval date: HT(D) done on 21.09.14. Boiler stage-1 hydro test of unit 9 was
Zero date: : 11.03.2011 successfully completed on 21.09.2014. Non Drainable Hydro
Test completed on10.08.17. BLU done on 29.08.2017,
Financial closure : Achieved in 2015 with PFC
 ESP: Mechanical erection completed. Other works are in
Main Plant Order The order for EPC was awarded to M/s BHEL on
progress.
nomination basis on 11.03.2011
BOP Package Order for BOP’s placed on  TG: Condenser & TG erection started on 26/08/14. TG Boxup
 M/s Mc Nally Bharat Engg. Co. Ltd. for CHP on completed 30.06.2016.
15.05.12. BoPs:
 M/s Mc Nally Bharat Engg. Co. Ltd. for AHP on  Chimney: Completed in all respect including aviation light.
15.05.12.  CT: Erection of water distribution system, drift eliminators and
 M/s Gannon Dunkerley & Co. Ltd. for Chimney on equipment completed for IDCT of unit#8 and unit#9.
19.04.12  CW System: EOT crane erected. Erection of pumps and motors
 M/s Paharpur Cooling tower for CT on 10.08.13. completed. Trail run is also under progress.
 CHP: The work of WT is on hold. WT civil work 60%
Type of fuel Coal completed. Geo-Teck survey completed in wagon tipler, M/s
PPA Dt 31.12.2010 BHEL started the isolation of affected structure by cutting
through M/s HILTI.Cutting work completed.Revisied layout
Power Evacuation system LILO at Barauni of Begusarai-Biharsarif 220KV D/C drawing is under approval of railway authority.
done. Power evacuation system expected to be ready  AHP: Order for civil work placed on M/s McNally Bharat.
by Dec-2015. Vacuum pump house equipment erection completed. ASPH
 Land: Land acquired. except land required for ash dyke and intake water system building is ready and Ash slurry pumps erection completed.
 Water Allocation: Approval for 60 cusec water from River Ganga has been obtained Erection of ash silo under progress. Land for ash dyke acquired
from Irrigation Department, Govt. of Bihar. Approval for 45 cusec water from River and possession of the same is u/p.Erection of ash pipe rack
Ganga has also been received from Central Water Commission. work is in progress. Contingency arrangement made for ash
disposal in HFCL Pond (Ash Dyke) completed.
 MOE&F Clearance: MoE&F clearance obtained on 08.05.14.
 PT Plant: Ready in service. Intake water system ready with
 Civil Aviation Clearance: Aviation clearance obtained from AAI on03-08-09. temporary arrangement at Ganga.
 DM plant: Ready in service.
 FOS: HFO & LDO tanks erection completed. Insulation is
pending.
 Switchyard: 220 kv switchyard charged on 03.03.2016. Station
transformer of unit 8 & 9 erection, testing completed and got
charged. 132Kv switchyard ICT -1&2 testing work u/p.GT of
U8 erection completed and for U9 erection is u/p.
 FGD: Revised estimate for tender towards appointment of
Project Management Consultant for “Feasibility study,
selection of implementing agency and supervision of
installation , commissioning, testing & inspection till
completion of project for installation of FGD ,SCR etc at
2X250MW extension project of Barauni TPS, Begusarai as
per revised emission norms declared by MoEF&CC is
under consideration
Critical issues 1. Construction of Ash dyke, Railway siding, Readiness of CHP, Intake Water System.
2. Heavy water percolation in WT pit so work is on hold.
Reasons for Delay 1. Acquisition of land for laying water pipeline from river Ganga to power plant and Ash Dyke area.
2. Drainage facility for seepage water from Wagon Tippler area.
3. Readiness of Raw Water System and DM plant.

TPM_Broad Status Report (January-February’2020) 105


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
2. Siriya TPP U-1 660 08/14 Uncertain Unit-1:
(JAS INFRA) Boiler: Civil foundation of boiler, ESP & Chimney
Village.: Siriya, U-2 660 12/14 Uncertain completed. Civil foundation of PHB & Mill-Bunker
Dist.: Banka Bihar U-3 660 04/15 Uncertain building under progress. 2730 MT Structural Steel
in PHB erected. Fabrication of 9000MT Structural
(4x 660 = 2640 MW) U-4 660 08/15 Uncertain
steel completed.
Original Estd. Cost :Rs 11,120.00 Cr.
Latest Est. Cost : Not Avialable Unit-2:
Expenditure during 2013-14 Boiler: Boiler foundation work was started.
Expenditure during 2014-15 Not Avialable
Expenditure during 2015-16 Unit-3: Civil works yet to start.
Total Expenditure : Not Avialable
Approval date: Unit-4: Civil works yet to start
Zero date: : 30.03.2011

Uncertain
Financial closure :
Presently no work is in progress at
Main Plant Order M/s Dongfang Electric Corporation Ltd., China
BOP Package
site.
Type of fuel Coal
PPA
Power Evacuation system
 MOE&F Clearance: MOE&F Clearance received vide letter NO. J-13012/89/2008-IA. II(T)
dated 29.06.2011
 SPCB Clearance: NOC for consent to establishment obtained from BSPCB.
 Civil Aviation Clearance: Aviation Clearance has been obtained from Airport Authority of
India.

Critical issues
Reasons for Delay

TPM_Broad Status Report (January-February’2020) 106


BROAD STATUS OF THERMAL POWER PROJECTS IN JHARKHAND
Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
1. Matri Shri UshaTPP U-1 270 03/12 05/12 Uncertain Phase-I
M/s Corporate Power Ltd. 04/12
Unit-1:
Distt. Latehar
Jharkhand U-2 270 04/12 06/12 Uncertain  Boiler: Erection started on 05/10/10.
05/12 Boiler drum lifted on 31/03/11. HT done
(4 x 270 = 1080 MW) on 28/12/11. Erection of 3/6 bunker
U-3 270 09/12 10/12 Uncertain
10/12 completed.
 ESP: ESP is ready
U-4 270 12/12 01/13 Uncertain  TG: condenser erection started on
01/13 25/05/11, Turbine erection started 15/6/11.
TG boxed up in 10/12.
Original Cost /Latest Cost Ph.-I: Rs. 2900.00 Cr, Ph.-II: Rs.3182.00 Cr
Expenditure during 2008-09 Unit-2:
Expenditure during 2009-10 Ph-I - .312000 Lakh Rs ( upto 11/12)
Expenditure during 2010-11 Ph-II – 220700 Lakh Rs. ( upto 9/12)  Boiler: Erection started on 19/12/10. Boiler
Expenditure during 2011-12 drum lifted on 19/07/11. HT completed on
Expenditure during 2012-13 10/12.
 ESP: ESP is ready
Total Expenditure Ph-I - Rs. 3120 Crores
Ph-II - Rs. 2207 Crores  TG: condenser erection started on
Approval date: 24/08/11, Tube insertion is under progress
Zero date: 09/2009 for Phase-I Turbine erection started 13/10/11. HPT &
12/2009 for Phase-II IPT placed on the deck.
Financial closure 05/12/2009 for Phase-I with REC

Uncertain/
28/03/2011 for Phase-II.
Main Plant Order Letter of Acceptance for Main Plant Order (EPC) issued to M/s Phase-II
BHEL on 09/2009. Unit-3:
 Boiler: Erection started on 06/11. Boiler
BOP Package Order for BOP’s placed on
 M/s Energo Engg. Projects. Ltd. for CHP on 06.05.10.
drum lifted on 12/11
 M/s DCIPS. for AHP on 08.10.10.  ESP
 M/s Simplex Infrastructure Ltd. for Chimney on 03.05.10  TG: TG erection started in 10/12.
 M/s Paharpur Cooling tower for CT on 04.05.10.

Stressed Project
Type of fuel
PPA
Power Evacuation system
Coal
PPA executed with Lanco Trading Co. in April 2010
LILO at Barauni of Begusarai-Biharsarif 220KV D/C
done. Power evacuation system expected to be ready
by Dec-2015.
 Unit-4:


Boiler: Erection started on 07/11. Boiler
drum lifted on 04/12
ESP:
 TG: TG deck is ready.

BoPs:
 Chimney: Completed in all respect
 CHP- 98% structure erection completed
 AHP- FA silo completed. Erection of
Bottom Ash Hopper completed.
 Station transformer & Unit Transformers
and associated systems is in ready.
Generator Transformer is placed on
foundation.
 ATS balance work is to be taken up after
stage – II Forests clearance is obtained.
 PT plant, DM plant, CW system, Fire
protection system Fuel oil system &
Switch yard completed.
Critical issues 1.Associated Transmission System for a short distance is to be taken up after Stage-II forest clearance is
obtained.
Reasons for Delay Work held up due to payment issue with BHEL since 11/12. Commissioning Schedule will be
assessed after restart of work.

TPM_Broad Status Report (January-February’2020) 107


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
2 Tori TPP Essar Power Ph-I Phase-I
1 600 05/12 07/12 Uncertain Unit-1:
(Jharkhand) Ltd. Distt.
Angarha Latehar 07/12  Boiler: Boiler erection started in 04/12.
 ESP: Foundation work completed.
Jharkhand
08/12 Uncertain  TG Civil work started in 15.12.11; hall
2 600 09/12 10/12 foundation completed. TG building
(3x660=1980 MW) structural fabrication completed.
Ph-II
3 10/15 Uncertain
12/15 Unit-2
600 12/15
 Boiler: Erection started in 15/12/13
Original /Latest Cost : Rs.570000 Lakh Rs. 250000 Lakh  ESP: Foundation work completed.
Phase-I Phase-II  TG: TG civil work started on 15/12/13.
Expenditure during 2009-10 : Rs 10641 Lakh Rs. Nil
Expenditure during 2010-11 : Rs. 42437 Lakh Rs. 2825 Lakh
Expenditure during 2011-12 : Rs.162489 Lakh Rs. 13845 Lakh Phase-II

Uncertain
Unit-3 –Work not yet started.
Expenditure during 2012-13 : Rs. 32446 Lakh Rs. 3172 Lakh
Expenditure during 2013-14 : Rs. 96502 Lakh Rs. 4760 Lakh
Expenditure during 2014-15 : Rs. 37649 Lakh Rs. 63 Lakh BoPs:
Expenditure during 2015-16 Rs. 66430 Lakh Rs. ---
Expenditure during 2016-17 Rs. 23265 Lakh Rs. ---  Chimney: Order placed on M/s Essar
Total Expenditure Ph-I: Rs.4718.59 Cr. (till 12/16) Projects India Ltd.. Windshield work
Ph_II: Rs.246.65 Cr(till 3/15) completed. Flue can fabrication 60%
Approval date:
completed.
Zero date:
 CHP: Order placed on M/s Elecon engg
Financial closure Achieved & Mcnally Bharat Engg.Co
Main Plant Order Ph-I:  AHP: Basic engineering completed.
18/08/2008 - Main plant Civil & Structural work on Essar Projects (I)
 CT: Order placed on M/s SPIG Cooling
Ltd.
BTG on M/s Harbin Power (HPE) Engineering, China in 11/ 2008 Tower India Pvt. Ltd.
Ph-II:  PT & DM Plant: 40% material received.
Main plant Civil works on EPI Ltd on 26/02/2010 BTG on HPE  FPS: Order placed on M/s Brijbasi Hi-
BOP Package Order for BOP’s placed on tech Udyog Ltd on 15.11.10.
 M/s Mc Nally Bharat Engg. Co. Ltd. And Elecon Engg. For CHP on  Switchyard: Order placed on M/s Alstom
22.09.10 & 31.08.10. T&D on 22/12/10
 M/s Mc Nally Bharat Engg. Co. Ltd. for AHP on 15.09.11.
 M/s Essar Projects India Ltd. for Chimney on 18.08.10 Presently no work is in
 M/s SPIG Cooling tower India Pvt. Ltd for CT on 19.11.10. progress due to financial
Type of fuel COAL
PPA 1.450MW+300MW with BSEB
constraints
2.PPA signed with JSEB for 12% of the total power generated at
variable cost under MoU route
3. Draft PPA submitted to JUVNL for 13% of the total power
generated at JSERC rates under MoU route.
Power Evacuation system BPTA signed with PGCIL and bay agreement executed. PGCIL
is setting up 400KV substation near the project.
 Land 1210 acres of land required for both the Phases 1&II of (2x600 +1x600 MW) is available.
 BOPs are common for both units.
 MOEF clearance already available for U-I of Phase-I. Clearance for U-2 of Phase-I and U-3
Phase-II received vide MOEF letter dated 14.11.2013.
 Civil Aviation Clearance: NOC for height of chimney is valid tilltill 21.07.2020
 SPCB: Clearance obtained from JSPCB is valid till 31.03.2016
 Coal: Due non availability of MOEF clearance for the Chakla & Ashok Karkatta coal block
allotted to this project it is proposed to import coal from Indonesia & Australia for the time
being.
 Water Source of water is from Damodar and Amanat rivers which are 20 &30 KMs from
the site.
Critical issues Mega Power Project status is yet being issued from MoP due to which 97% imported main plant equipment are lying at
site/ Port.
Tapering coal linkage.
Reasons for Delay Reasons for Delay:- Delay in MoE&F Clearance` (14.11.2013 for U2 & U3), Change of design in water cooled condenser to
air cooled condenser due to water availability issue, Law & order issue, delay in grant of Mega power project status,
cancellation of coal block and non-availability of tapering / long term coal linkage etc.

TPM_Broad Status Report (January-February’2020) 108


BROAD STATUS OF THERMAL POWER PROJECTS IN ODISHA
Unit Commissioning Schedule
Sl. No. Project Details1 Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Syn COD Syn. Trial Run
Comm Comm COD
State Sector
1. Ib Thermal Power Station 3 660 08/17 09/17 30.03.2019(A) 01.07.19(A) Unit-3:COD achieved on 03.07.2019. Trial
Village : Banaharpalli, Dist: 08/17 20.04.2019(A) 03.07.19(A)
Run 29.06.2019 to 01.07.2019. Commissioned
Jharsaguda
(OPGC) 4 660 12/17 01/18 23.01.2019(A) 17.08.2019 on 20.04.2019. Synchronisation done on
12/17 11.05.2019 (A) 21.08.2019 30.03.2019.
(2x660 = 1320 MW)
Original / Latest Cost :Rs 1196500 Lakhs  Boiler: All major work completed. Synchronization
Expenditure during 2013-14 : Rs 68690 lakhs achieved 30.03.2019
Expenditure during 2014-15 : Rs. 56887 lakhs Boiler civil works start on 26.11.2014 and errection start at
Expenditure during 2015-16 : Rs. 108659 lakhs 20.01.2015, Hydro Test - Drainable on 26.12.2017 and
Expenditure during 2016-17 : Rs. 208889 lakhs Non-drainable – 13.08.2018, Boiler Light Up on
Expenditure during 2017-18 : Rs. 63758 lakhs 18.11.2018, SBO – 23.02.2019. Coal firing on 31.03.2019
Expenditure during 2018-19 : Rs.  .ESP 3: Mechanical Erection completed, Commissioning
Expenditure during 2019-20 : Rs. completed.
Total Expenditure (up to : Rs 506883 lakhs  TG Unit-3: Unit synchronization on 30.03.2019 and coal
06/17) firing on 31.03.2019.
Approval date:
Zero date: : 26.03.2014  Unit-4:COD declared on 21.08.2019 but
schedule 00 hrs of 22.08.2019; Trial Run
Financial closure : Achieved on 23.11.2012 (PFC and REC) 14.08.2019 to 17.08.2019. Commissioned on
Main Plant Order : NTP issued in 03/2014 11.05.2019. Synchronisation done on
23.01.2019
BOP Package BTG order placed on M/s BHEL
 Boiler: All major work completed. Synchronization
Type of fuel Coal achieved on 23.01.2019
Boiler civil works start on 26.12.2014 and errection start at
PPA : PPA: 50% of the power generated shall be sold to 29.05.2015, Hydro Test - Drainable on 01.12.2017 and
GRIDCO through a long term PPA based on CERC Non-drainable – 17.07.2018, Boiler Light Up on
norms and balance 50% will be sold through mix of long 11.08.2018, SBO – 08.12.2018. Coal firing on 13.02.2019
term PPA (Case-1 bids) and short / medium term sales.  ESP4: All field charged, commissioning completed.
 TG Unit-4: Oil synchronization achieved.
Power Evacuation system Power evacuation through 2xD/C 400KV transmission
lines, one going to OPTCL’s 400kV substation at Lapang
and other to PGCIL’s 400KV pooling station. Signed on Auxiliary Equipment: All major drives commissioning
11.09.2013 completed.

 LAND: Required land is in possession of OPGC except the 40 acre of land for MGR BoPs: All BOPs are completed and operational except
work. MGR, because 40 acres land for MGR possession is
 MOEF: EC was granted on 04.02.2010, amended on 22.01.2014 and validity extended on pending.
16.1.2015.
 Coal linkage: Coal will be sourced from Manoharpur & Dip side Manoharpur allocated to
OCPL, A JV subsidiary company of OPGC. FGD Plant: Consultant finalized,
 WATER: Agreement signed with water resource department on 26.08.2013
 SPCB: Consent to establish was granted from OSPCB on 04.02.2010 and revalidation was
Techno – commercial bid evaluation in
done on 27.11.15 progress.
 CIVIL Aviation: Clearance obtained from AAI on 15.03.2010

Critical issues
Reasons for Delay There is an incident occurred where LP Turbine blade failed at 3000 RPM before synchronization (on coal) so there is
anticipation that COD Unit 4 might shift from Feb 19 to mar 19.

SB-28.08.2019

TPM_Broad Status Report (January-February’2020) 109


Unit Commissioning Schedule
Sl. Project Details Capacity Broad Status
No. (MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
2. Ind Barath TPP 1 350 07/11 10/11 18.06.15(A) 20.07.16(A) Unit-1:
09/11 25.02.16(A)
M/s Ind-Barath Energy Full load achieved on 25.02.16. COD declared
(Utkal) Ltd. on 20.07.2016.
(Distt-Jharsuguda) 2 350 10/11 12/11 Stressed
12/11
 Boiler: Boiler erection started in 01/11, Erection
(2x350 700 MW) of feeders & tripper, all bunkers & Liners
Original / Latest Cost :Rs 3150.00 Cr. / 4001.00 Cr erection and mills completed. SBO completed
Expenditure during 2010-11 Rs 100000 lakhs on 15.12.14. Drum lifted on 30.5.11, HT
Expenditure during 2011-12 :Rs 85000 lakhs
Expenditure during 2012-13 :Rs 110000 lakhs completed on 24.05.12. BLU completed on
Expenditure during 2013-14 :Rs 47000 lakhs 9.01.15.
Expenditure during 2014-15 :Rs 54800 lakhs  ESP: work completed
Expenditure during 2015-16 :Rs 26200 lakhs
Expenditure during 2016-17 :Rs 2300 lakhs  TG: TG erection commenced in 5/12. TG boxed
Expenditure during 2017-18 Rs 100 lakhs up on 23.05.14, Oil flushing completed on
Total Expenditure :Rs 4254.00 Cr (up to 04/17) 10.10.14. Unit synchronized on 18.06.15
Approval date: 29.03.2010
Zero date: : 16.05.2009 Unit-2:

Stressed Project  Boiler: Boiler erection started in 05/11, Drum


Financial closure : FC achieved on 14.05.2008 with M/s Axis Bank Ltd.
Main Plant Order : Cethar Vessel(16.05.2009) Chinese lifted on 26.12.11. HT(D) completed on
BOP Package Awarded to punj Lloyd on 07.01.2010 20.05.14.
Type of fuel Coal and Fuel Linkage MCL  ESP: Erection completed insulation & cladding
PPA PPA signed with GRIDCO on 14.9.09 & TNEB on of ESP and hot gas ducts is in progress.
8.8.13.  TG: TG erection started in 09/12.Erection of
Power Evacuation system Bulk Power Transmission Agreement (BPTA) with TG & condenser completed.TG boxed up to be
PGCIL in 24.02.2010
 Land: Required land acquired re-inspected and final Box up is in progress.
 MOEF: Clearance of MOEF has been obtained on 30.11.2009
 Water: Approval to draw water from Mahanadi river obtained on 23.02.2008 BoPs:
 SPCB: Clearance obtained from Orissa SPCB on 13.08.2010
 Civil Aviation: Clearance obtained from AAI on 14.07.09
 Chimney: Completed for both the units.
 CHP: structural erection completed and
electrical work in progress, Track hopper
completed, Bunker, coal feeder and mills
erection completed. Tripper erection completed
 AHP: U-2 BAH expected in 12/17 and F/A
system work is in progress.
 CT: completed for U-1 and that for U-2 is in
progress.
 PT Plant: completed
 DM plant: Ready to use., already functional for
U-1.
 CW system: Already functioning for U-1.
 FO System: for U-1 & U-2 completed.
 Switchyard: completed in all respect and is
being used for evacuation of power for U-I.

Critical issues 1.Non readiness of CHP & AHP and ATS for Unit-2
2. Completion of bottom ash hopper
Reasons for Delay 1. Very slow progress of civil work
2. Supply of main Plant material
3. Readiness of power evacuation system
4. Completion of firing guns/burners due to technical problem in design.
5. Mainly financial constraints due to non-disbursement of funds by financer.

TPM_Broad Status Report (January-February’2020) 110


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
3. Lanco Babandh TPP 1 660 02/13 05/13 Stressed Unit-1
(Distt-Dhenkanal) 04/13 Boiler: Boiler erection started in 05/11. Main
(M/s Lanco Babandh Power structural erection completed. Boiler Pressure parts
Ltd.) 2 660 06/13 09/13 Stressed erection, Enclosure wall erection are in progress.
(2x660 = 1320 MW) 08/13 Burner erection completed.
 ESP: 58% structural erection completed. All hoppers
Original / Latest Cost :Rs 6930.00 Cr. / Rs. 10430.00 Cr erected. Pass-A collecting electrode erection
completed and Pass B electrode erection was in
progress. Pass-A outlet and Inlet funnel erection
Expenditure during 2010-11 Rs 135000 lakhs completed.
Expenditure during 2011-12 :Rs 214100 lakhs  TG: Deck casting completed. Both EOT cranes
Expenditure during 2012-13 :Rs 78400 lakhs commissioned.TG erection started in 11/15. HPT, IPT
Expenditure during 2013-14 :Rs 54700 lakhs & LPT are not received at site. HPH & LPH erection
Expenditure during 2014-15 :Rs 62200 lakhs completed. Foundations of MDBFP#1 & CEP#1
Expenditure during 2015-16 :Rs 128000 lakhs completed.
Expenditure during 2016-17 :Rs 89100 lakhs Unit-2
Total Expenditure :Rs 7615.00 Cr(up to 03/17)  Boiler: Erection started in 9/11. All ceiling girders
erected. Handrails and Platforms work completed at
Approval date:

Stressed Project
various levels. Burner erection was in progress.
Zero date: : 17.11.2009 Preparatory work for Pressure part erection yet to
Financial closure : Achieved on 08.09.2010 complete.
Main Plant Order Main plant order placed on Lanco Infaratec Ltd. On  ESP: 41% of structural erection completed. Hopper
17/11/2009, Boiler: DEC China, TG: HEC China. erection is in progress. Pass A-2/9 Collecting electrode
erection completed. Pass C- hopper assembly erection
BOP Package BOPs to LTTL and casing wall assembly work completed.
Type of fuel Coal  TG: EOT crane commissioned. Columns upto deck
PPA Revised PPA signed with GRIDCO, Odisha for 25% bottom completed, MDBFP#2 foundation completed.
power sale on 4.01.11. LBPL signed PPA with UPPCL CEP & CW Pit #2 raft completed. MDBFP#2
for 454MW on 08.08.13 & with RVPNL for 374MW on foundation completed.
01.11.13. BoPs:
 Chimney: 252/270m shell construction completed.
Power Evacuation system BPTA signed with PGCIL for 1600 MW on
Flue can fabrication was in progress.
24.02.10(Revised to 800MW as per CERC order). 25KM  CT: FRP Cooling tower awarded to Paharpur.
of transmission line is planned for power evacuation from IDCT#1 305/454 raft footing work completed.
LBPL project to PGCIL Angul pooling station. The power 275/481 nos column completed. Excavation upto
shall be evacuated at 400KV level through 1 D/C quad 70% completed for IDCT#2 and raft footing work
Moose transmission conductor. Section 68 and Section was in progress.
164 approval received from MoP.  CHP: Track hopper raft and both side walls
 Land: 889 acres out of 933 acres’ land acquired. (95%) completed. Crusher house foundation work
completed. Stacker reclaimer footing raft completed..
 st
MoE&F: Clearances obtained on 17.02.10 and is valid upto 31 Mar 2017 JTs foundation work completed. Crusher house civil
 Forest: II-Stage clearance received on 31.12.13 from MoEF work completed.
 Water: Principle approval received for 40 cusecs water for U-1 &U-2 on 07.02.09.  AHP: RCC of BAH#1 completed. Raft footing
Renewal received on 18th Jan’16 completed and wall final lift is in progress for ASPH.
 Coal linkage: Coal linkage for U-1 received on 29.12.08 for 2.83MTPA. FSA has Ash silo raft#1 completed. 8/26 nos. footing
been executed with MCL on 26.04.16. completed for Ash compressor house building
 PT/DM plant: Foundation work completed. DM
 SPCB: NOC obtained on 20.05.09 from Odisha SPCB and it is valid till 19.05.19
building structure erection completed and equipment
 Civil Aviation: NOC obtained on 03.09.08 and valid till 02.09.2020 erection in progress. Clarifloculator ring wall in
progress. DM tank-1 erection completed.
 FO system: 2LDO + 2HFO fuel oil tanks erection
completed. LDO-2 water fill test completed.
 Switch yard: Erection of 23 nos. towers & 18 nos.
of beam completed. S/Y equipment received at site.
Control room building brick work completed and
preparation for slab casting has started.

Presently work at site almost held up due to


financial constraint
Critical issues 1. Work was held up due to financial constraints, now the work restarted.
2.Acquisition of Ash pond and corridor land.
3. Transfer of Govt. land to the project.4.LBPL has requested MoC/MoP to grant normal Linkage in lieu of
cancellation of Rampia Coal Mine for Unit#2
Reasons for Delay Work almost held up due to financial constraint presently.

TPM_Broad Status Report (January-February’2020) 111


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
4. Malibrahmani TPP Unit-1:
M/s Monnet Ispat (Distt-Angul) 1 525 10/12 01/13 Uncertain* ----
(2x525 = 1050 MW) 12/12  Boiler: Erection started on 18.08.11. Erection of
pressure part is in progress, welding of HP joints is
in progress. Feeder floor casted, 4 mills installed and
2 525 12/12 03/13 Uncertain* ---- 4 mills are yet to be installed.
02/13  Drum lifted on 21.03.12., HT completed on 3.4.13
Original /Latest Cost :Rs 5093.00 Cr./ Rs. 6330.00 Cr Boiler light up expected after restart of work.
Expenditure during 2010-11 Rs 63300 lakhs  ESP: All 4 passes completed and air test done.
Expenditure during 2011-12 :Rs 78292 lakhs Control room completed, panel erection and cabling
Expenditure during 2012-13 :Rs 143681 lakhs done.
 TG: Condenser erection started on 01.08.12, Turbine
Expenditure during 2013-14 :Rs 126817 lakhs
erection started on 28.01.13. Generator stator
Expenditure during 2014-15 :Rs 120885 lakhs erected, TG box up yet to be done.
Total Expenditure :Rs 5329.75 Cr (up to 12/2014)
Approval date: Unit-2:
Zero date: : 12.06.2009
 Boiler: Erection started on 10.10.11, 4 out of 8 mills

Stressed Project
Financial closure : Achieved on 23.08.2010
are installed, foundation of PA and FD fans
Main Plant Order Main plant order placed on M/s BHEL completed. Drum lifted 21.07.12. HT & BLU may
BOP Package be assessed after start of work.
Type of fuel Coal  ESP: Erection of pass B, C & D done and pass A yet
PPA PPA signed with GRIDCO for 117MW for 400 MW to be done.
with West Bengal through PTC.  TG: Condenser erection started on 7.02.13 and TG
Power Evacuation system 400KV double circuit transmission line up to proposed erection started in 08/2015, TG box up may be
PGCIL pooling station, which is 31km away from assessed after restart of work.
power plant. BoPs:
 Land: 770 acre acquired out of 995 acre required.
 Chimney: Chimney shell casting completed flue can
 MOEF: Clearance of MOEF has been obtained erection for U-I completed, for U-II two top
 Water: Water allocation done segments erected.
 Coal linkage: Mandakini captive coal mines.  CHP: Fabrication and erection of CHP structure are
 SPCB: Clearance obtained from Orissa SPCB. in progress along with equipment erection could be
 Civil Aviation: Clearance obtained from AAI completed after restart of work.
 AHP: Civil work for ash slurry sump, pump house,
ash water pump house and silos completed. Pipe
erection was in progress.
 IDCT: Orders placed to M/s Indure 0n 22.02.2010.
Construction of cooling tower for both the units are
completed in all respect, mechanical and electrical
erection work not completed.
 DM Plant: Civil & structural work is completed
mechanical and electrical erection not completed.
 PT Plant: Civil work completed, mechanical and
electrical erection to be done.
 CW System: Pump house completed. Pumps and
associated pipe lines erection are to be erected.
 FO System: Pump house, tank erection, pipe rack
work is yet to be completed.
 Fire Protection: Fire water pump house civil
construction is completed and mechanical &
electrical erection yet to be done.
 Switchyard: Construction completed.
Commissioning and testing work not completed.

*Work held up due to financial constraints

Critical issues
Reasons for Delay Paucity of fund.

TPM_Broad Status Report (January-February’2020) 112


Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
5. KVK Nilachal TPP, Ph-I 1 350 10/11 01/13 Uncertain …..
Kandarei, Odisha 12/11 Unit-1:
(Distt-Dhenkanal)  Boiler: Boiler erection started on 20.06.11,
2 350 01/12 03/13 Uncertain ----- structural erection started. Drum lifting may be
M/s KVK Nilanchal Ltd.
02/12 completed after restart of work.
(3x350 = 1050 MW)
 ESP: Foundation work completed, structural
3 350 01/12 03/13 Uncertain erection completed upto hopper level.
02/12 -----  TG: Deck casting partially completed, Foundation
Original / Latest Cost :Rs 4990.00 Cr./ Rs. 6000.00 Cr of all three MDBFPs completed.
Expenditure during 2008-09 Rs 11974.41 lakhs
Expenditure during 2009-10 :Rs 20861.15 lakhs
Expenditure during 2010-11 :Rs 35187.00 lakhs BoPs:
Expenditure during 2011-12 :Rs 75226.00lakhs
Expenditure during 2012-13 :Rs 15740.00lakhs 

Uncertain
Chimney: 90 mtr. Chimney shell completed.
Expenditure during 2013-14 :Rs 5847.00 lakhs
Expenditure during 2014-15 :Rs 6000.00 lakhs
Total Expenditure :Rs 1708.36 Cr (up to 03/15)
Approval date:
Zero date: : 09.11.2009
Financial closure : Achieved for Ph-I(1X350MW) in 07/08 and Ph-II
(2X3501MW) in 08/10
Main Plant Order BTG-Harbin, China, 09.11.09
Note: No work is under progress
BOP Package presently.
Type of fuel Coal
PPA PPA signed for (1000MW)
Power Evacuation system Bulk Power Transmission Agreement (BTPA) with
PGCIL
 Land: Required land acquired.

 MOEF: Clearance obtained vide letter no.J-13011/51/20008-IA.II(T) DT.18/02/2009

 Water: Allocated by GoO vide letter irr-ii-wrc-73/08/15032 dt. 15..04.20008 for 48 cusecs
from Mahanadi.

 SPCB: Clearance obtained for SPCB Orissa vide letter no..26748/Ind-II-NOC-5065


dt.19.12.2008

 Civil Aviation: Received AAI vide letter No. AAI/20012/131/2007-AR(NOC)

Critical issues
Reasons for Delay 1.Law and order problem
2. Work held-up due to stay by honorable HC of Odisha. From 18.05.12 to 05/2015

TPM_Broad Status Report (January-February’2020) 113


BROAD STATUS OF THERMAL POWER PROJECTS IN WEST BENGAL
Unit Commissioning Schedule
Sl. No. Project Details Capacity Broad Status
(MW) Original Actual(A)/ As
Expected
Synch COD Syn. COD
Comm Comm
Private Sector
1. Hiranmaye Energy TPP (3x150MW) 1 150 10/15 11/15 19/03/17 (A) 13/08/17(A) Unit-1
Hiranmaye Energy Limited 11/15 07/06/17 (A) COD achieved on 13/08/17. Full load achieved on
07/06/2017. Unit Synchronized on 19/03/17.
PO-Shibramnagar, Haldia, Dist.- 2 150 01/16 02/16 31/12/17 (A) 31/12/17(A) Boiler: Boiler erection started on 25.03.14. Drum lifted
Purba Medinipur-721635, West 2/16 31/12/17(A) on 04.12.14. HT completed on 16/09/2015. BLU
Bengal completed on 21.08.16. SBO completed 10.12.16. Unit
3 150 05/16 05/16 * * synchronized on 19-03-17.
(3 x 150 = 450 MW)
05/16 TG: TG erection started on 16.08.15 Box up completed
on 20/05/16. TG oil flushing completed on 14.10.16. Unit
Original /Latest Cost :Rs 2656.00 Cr./ Rs. 3307.00 Cr synchronized on 19-03-17.
Latest Est. Cost : Unit-2
Expenditure up to 2010-11 : Rs 107 lakh COD achieved on 31/12/17. Full load achieved on
Expenditure during 2013-14 : Rs 111527 lakh 31/12/17. Unit Synchronized on 31/12/17.
Expenditure during 2014-15 : Rs 46764 lakh Boiler: Boiler erection started on 25.06.14, Drum lifted
Expenditure during 2015-16 : Rs 86968 lakh in 23.02.15. 2218/2526 MT structural erection completed.
Expenditure during 2016-17 : Rs 76130 lakh HT(D) done on 16.09.16. BLU done on 10.07.17.

Uncertain
Expenditure during 2017-18 : Rs 4809 lakh ESP: 2153/2158 MT structural erection completed.
Hopper erection is in progress.
Total Expenditure Rs 326305 lakhs (up to 10/17) TG: Deck casting completed.TG erection started on
Approval date: 05/05/16. TG box up done 15.10.17, TG Oil Flushing
Zero date: 28-11-2013 done on 18.10.17.
Financial closure Achieved on 22.12.2011 with REC Unit-3
Boiler: Boiler erection started on 15.05.15.
Main Plant Order Placed to BHEL 29.09.2010 1320/3274MT structural erection completed. Drum lifted
BOP Package Order for BOP’s placed on on 14.01.16. Piling of 2/4 mill completed. Excavation for
 M/s Shristi Infrastructural Development Corp. Ltd & Scorpio ID/FD/PA has completed.
Engg Pvt. Ltd. for CHP on 20.12.13. ESP: Foundation completed. 567/2158 MT structural
 M/s Shristi Infrastructural Development Corp. Ltd & Energo erection completed.
Engg. Project. Ltd. For AHP on 10.01.14. TG: TG deck raft casting completed. Water has logged in
 M/s Simplex Infrastructural Ltd. for Chimney on 09.05.12 this area. Presently no work is going on in this site.
 M/s Paharpur Cooling tower for CT on 24.03.14. BoPs:
Type of fuel Coal Chimney: Civil work for chimney completed. Flue can
PPA : For 300MW with WBSEDCL erection for U#1, 2 &3 completed. Platform erection
Power Evacuation system 220KV Transmission line of length from plant to new haldia completed
sub-station of WBSETCL. CT: IDCT-1&2 has completed in all respect. CT#3: Pile
 Land: Complete land acquired 213.71 acre, 198 from Haldia Development authority and rest work was in progress. Presently no work is going on in
from private. this site
 MoE&F: Clearances extended on 30.08.15 upto 12.04.2017 vide letter No. J-13213/16/2014-IA. CW System: CWPH building completed. All Four CW
I(T) pump commissioned. Laying of CW pipe completed for
 Water: 15 MGD water is available from Haldia Development authority. all the three units. Forebay and cold water channels
 SPCB: NOC received from GoWB. completed.
 Coal linkage: Long term coal supply agreement No: SNRL/IPC(H)L/FSA 2015-16 between M/s CHP: Structural erectionand floor casting of srusher
Swaymbhu natural resources private limited and M/s India Power Corporation (Haldia) Ltd. house is completed.Stacker cum reclaimer has installed.
 Civil Aviation: NOC vide letter No.AAI/20012/82/2010-ARI(NOC) date 23.10.2010 for Erection of galleries from coal stack yard to TP-1&2 is
construction of chimney extended upto 22.06.2022. completed. Gallery from TP-2 to bunkers of U-1 is
completed. Conveyor belt laid upto U-1 bunkers for one
stream.MCC room completed.
 AHP: Civil work of Ash Silo, Dewatering Bin, Ash
slurry pump house, ash water pump house and control
room building are completed. Construction of Slurry sump
is completed. Erection of Ash water pumps and transport
air compressors completed. MCC room is completed.
Control room is ready.
PT Plant: Raw water reservoir completed. RGF
commissioned and system is operational.
DM plant: DM plant is RO type. Erection of 2nos DM
tank and 3nos.CST completed. DM plant commissioned.
FO system: 2 LDO tanks and necessary pumping system
ready.
Switch yard: Structural erection of 220KV equipment in
switchyard is completedin all respect.
 FGD: detailing of feasibility report is under process.
*Unit-3 work is totally on hold.
Critical issues
Reasons for Delay Construction activity was stalled from beginning of 2011 to Sept 2014 due to following reasons:
1. Fresh clearance from Pollution Control Board for 3x150MW (Earlier it was acquired for 3x135MW)
2. MOEF moratorium for no construction activity in Haldia & Asansol industrial area in West Bengal

TPM_Broad Status Report (January-February’2020) 114


North – Eastern
Region

TPM_Broad Status Report (January-February’2020) 115


BROAD STATUS OF THERMAL POWER PROJECTS IN ASSAM
Commissioning Schedule
Sl.
Actual(A) / As now
No. Cap Original
Expected Broad Status
PROJECT DETAILS (MW)
Syn. Syn.
COD COD
comm comm
I COMMISSIONED PROJECTS
State Sector
1. Lakwa Replacement Power Civil works for all the Gas Engines were
Project Dist.: Charaideo started on 26.05.2016 and completed on
69.755
(Assam) APGCL 16.10.2017.
Gas Engine-1 9.965 10.02.18 10.02.18
Gas Engine-2 9.965 06.02.18 06.02.18 Mechanical work for all the Gas Engines
were started on 19.12.2016 and completed on
Gas Engine-3 9.965 08.02.18 08.02.18 10.02.2018.
Gas Engine-4 9.965 09.02.18 09.02.18
26.04.18 26.04.18(A)
Gas Engine-5 9.965 11.02.18 11.02.18 Electrical work for all the Gas Engines were
Gas Engine-6 9.965 13.02.18 13.02.18 started on 19.07.2017 and completed on
13.12.2017
Gas Engine-7 9.965 14.02.18 14.02.18 .
Date of sanction of the project 22.5.2014 Gas Engine-1 &GTG:
Project sanctioning Authority Govt of Assam Cranking for Gas Engine-1 and FSNL test
Date of Investment Approval 20.02.2015 conducted on 05.02.18 and synchronized on
10.02.18.
Org. Est. cost Rs 26750 Lakhs
Latest cost Rs 26750 Lakhs Gas Engine-2 &GTG:
Exp. During 2015-16 Rs 2461 Lakhs Cranking for Gas Engine-2 and FSNL test
Exp. During 2016-17 Rs 10571 Lakhs conducted on 05.02.18 and synchronized on
Exp. During 2017-18 Rs 10109 Lakhs 06.02.18.
Exp. During 2018-19 (06/18) Rs 3609 Lakhs
Gas Engine-3 &GTG:
Cranking for Gas Engine-3 and FSNL test
Cumulative exp. up to(06/18) Rs 26750 Lakhs
conducted on 06.02.18 and synchronized on
Date of Main Plant Order (LOI) Consortium of Wartsila India Pvt. Ltd. and 08.02.18.
Wartsila Finland OY ( EPC ) on
11.12.2015. Gas Engine-4 &GTG:
Zero date of the project 09.03.2016. Cranking for Gas Engine-4 and FSNL test
conducted on 05.02.18 and synchronized on
 Land: 2.099 Acres of land was available with the project. 09.02.18.
 Environment clearance (Central): Obtained vide letter no J 13012/21/2012-IA.II (T)
dated 14.10.2013 from MOEF, GOI Gas Engine-5 &GTG:
 Water Linkage : 21.6 KL per day is required for the project which is met from Cranking for Gas Engine-5 and FSNL test
existing Raw water system sourced from Disang River. conducted on 06.02.18 and synchronized on
 Fuel: Natural Gas (No fresh Gas allocation is required and used the Ph-I allocation, 11.02.18.
i.e. 0.4 MMSCMD)
 Power Evacuation: 132KV Mariani Feeder, 132 KV Nazira Feeder, 132 KV Gas Engine-6 &GTG:
Dibrugarh feeder, 132 KV Namrup-I & 132 KV Namrup-II Feeder. Cranking for Gas Engine-6 and FSNL test
 NOC AAI (For Height only): 12.06.2014, conducted on 06.02.18 and synchronized on
 Funded by Asian Development Bank (ADB). 13.02.18.

Gas Engine-7 & GTG:


Cranking for Gas Engine-7 and FSNL test
conducted on 05.02.18 and synchronized on
14.02.18.

Engine:Wartisila Finland OY
Generator: ABB Finland OY
Gas Compresor: Kirlosker Pneumatic
Company Ltd.

Reason for Delay: NIL

Critical Issue: NIL

TPM_Broad Status Report (January-February’2020) 116


Sl. Cap Commissioning Schedule
No. PROJECT DETAILS (MW) Original Actual(A) / As now Broad Status
Expected
Syn. COD Syn. COD
comm comm
I PROJECT UNDER CONSTRUCTION
State Sector
1. Namrup Replacement GT&GTG:
Power Project 98.40
Distt:Dibrugarh GT synchronized on 03.01.17 and
(Assam) APGCL Commissioned on 11.01.17 (open cycle).
GT 62.25 08/11 01/12 03.01.17(A) GT was put on barring gear on 01.03.2016
09/11 11.01.17(A) and cranking was completed on 05.08.16.
ST 36.15 11/11 01/12 02/20 2019-20 FSNL achieved on 3.1.17.
01/12 03/20 ST:
Date of sanction of the project 17.03.2007 TG Hall roof collapsed on 09.07.2018.
Roof structure restoration work started.
Project sanctioning Authority Govt of Assam Damaged spares of ST have been
Date of Investment Approval 17.03.2007 identified and being replaced. Now ST
synchronization is likely to be achieved by
Org. Est. cost Rs 41100 Lakhs 10/19.
Latest cost Rs 69373 Lakhs TG erection started in October’16. Oil
Exp. During 2007-08 Rs 23 Lakhs Flushing was STG in progress. ST
Exp. During 2008-09 Rs 1816 Lakhs synchronization and commissioning is
Exp. During 2009-10 Rs 1799 Lakhs expected in 10/19 (Combined cycle). COD is
Exp. During 2010-11 Rs 2159 Lakhs expected in 03/19.
Exp. During 2011-12 Rs 12363 Lakhs HRSG: HRSG work started in 01/12 and
Exp. During 2012-13 Rs 10640 Lakhs insulation work nearing completion.
Exp. During 2013-14 Rs 2105 Lakhs LP/IP/HP Hydro test completed. BFP no
Exp. During 2014-15 Rs 2005 Lakhs load test completed. Chemical cleaning was
Exp. During 2015-16 Rs 12870 Lakhs
in progress at the time of accident
Exp. During 2016-17 Rs 2950 Lakhs
Exp. During 2017-18 Rs 2450 Lakhs  Work for erection, commissioning, PG Test
Exp. During 2018-19 (06/18) Rs 4727 Lakhs and all BOPs (ordering and execution) has
Cumulative exp. up to(06/18) Rs 58148 Lakhs been allotted to M/s NBPPL (Joint venture
Date of Main Plant Order (LOA) : 31.12.2008 ( EPC ) on M/s BHEL of NTPC & BHEL) on nomination basis
Zero date of the project : 09.02.2009 with approval of APGCL.
 Land: 30 Acres of land required for the project.  Earlier BHEL requested for provisional time
 Fuel: Natural Gas. extension up to Dec., 2013. APGCL
 Fuel Source: Gas supply agreement made with Oil India Limited for approved formal extension up to Aug., 12
0.66 MMSCMD of natural gas. Gas Transportation agreement with and provisional extension up to 2013.
Assam Gas Company Ltd. through existing Gas supply line to NTPS.  Main plant civil works was awarded to M/s.
 Power Evacuation: LILO to connect with the existing Namrup –
Ramky and work was started in 4/10.
Tinsukia 220 kV D/C line.  BHEL/NBPPL terminated the civil
contractor M/s. Ramky on 05/09/13 &
BHEL terminated M/s. NBPPL on 22.11.13
for their poor performance.
 Tender for new civil contractor for balance
civil work floated by BHEL on 18.12.13.
Civil contract awarded on 13.03.14 to M/s
Power Mech Projects & work was started on
05.05.14.
Critical Issue - Readiness of firefighting system.
- TG hall roof and TG restoration.
Reason for Delay: - Delay in start of civil work by 7 months and delay in civil work by another 7 months.
- Termination of civil & BoP contracts due to poor performance and re-awarded to new contractors by BHEL, failure
of SFC and Power module cards.
- Gas Turbine & Generator bearing and Load Gear Box damaged due to power failure and DC motor failure.
- Collapsing of TG hall roof (09.07.2018).

TPM_Broad Status Report (January-February’2020) 117


LIST OF ABBREVIATIONS
Sl. No Abbreviation Description
1 AHP Ash Handling Plant
2 BAH Bottom Ash Hopper
3 BFP Boiler Feed Pump
4 BG Barring Gear
5 BLU Boiler Lightup
6 BOP Balance of Plant
7 BTG Boiler Turbine Generator
8 C&I Control & Instrumentation
9 CF Coal Fire
10 CHP Coal Handling Plant
11 COD Commercial Operation Date
12 CRH Cold Re Heat
13 CW System Cooling Water System
14 DM Plant De Mineralisation Plant
15 EDTA Ethyle Diamine Tetraacetic Acid
16 EPC Erection Procurement & Commissioning
17 ESP Electro Static Precipitator
18 FC Financial Closure
19 FD Fan Forced Draft Fan
20 FGD Flue Gas De-sulphurisation
21 FL Full Load
22 FO System Fuel Oil System
23 FSA Fuel Supply Agreement
24 GCB Generator Circuit Breaker
25 GT Generator Transformer
26 HCSD High Concentrated Slurry Disposal
27 HPT High Pressure Turbine
28 HRH Hot Re Heat
29 HT Hydraulic Test
30 ID Fan Induced Draft Fan
31 IDCT Induced Draft Cooling Tower
32 IPT Intermediate Pressure Turbine
33 LOA Letter of Award
34 LPT Low Pressure Turbine
35 MDBFP Motor Driven Boiler Feed Pump
36 MGR Merry Go Round
37 MOE&F Ministtry of Environment & Forests
38 MSL Main Steam Line
39 NDCT Natural Draft Cooling Tower
40 NTP Notice To Proceed
41 PA Fan Primary Air Fan
42 PHB Power House Building
43 PPA Power Purchase Agreement
44 PTP Pre Treatment Plant
45 ROW Right Of Way
46 SBO Steam Blowing Operation
47 SCR Selective Catalytic Reduction
48 SG Steam Generator
49 ST Station Transformer
50 SVF Safety Valve Floating
51 Synch. Synchronisation
52 TDBFP Turbine Driven Boiler Feed Pump
53 TG Turbine Generator
54 WT Wagon Tippler
55 WT Plant Water Treatment Plant

TPM_Broad Status Report (January-February’2020) 118


BROAD STATUS REPORT
(Monthly)
Under Construction
THERMAL POWER PROJECTS

मासिक प्रसिवेदन
( - ) ‘2020)
(January–February’ 2020)

Central Electricity Authority


Thermal Project Monitoring Division
9th Floor(S), Sewa Bhawan,
R.K. Puram,
New Delhi – 110 066
Phone: 011-26732996, 2610 5075 (Fax)
E mail: [email protected]

Last Page