Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Del Monte Ph, Inc.

vs Napoleon Aragones
G.R. No. 153033
June 23, 2005

Facts: Del Monte Philippines Inc. (DMPI) entered into an agreement with Mega-Engineering
Services in joint venture with WAFF Construction System Corporation (MEGA-WAFF) represented
by Edilberto Garcia (Garcia), wherein Garcia will supply the installation of modular pavement in
DMPI‘s warehouse. In this regard, Garcia as a contractor entered into a supply agreement with
Dynablock Enterprises represented by respondent Aragones, to supply labor, materials, equipment
and the like.

Thereafter, Argones started to do his obligation. The deadline however was not met. After the
installation, Aragones failed to collect the payment from Garcia. Then, Aragones sent a letter to
DMPI saying that instead of paying Garcia, DMPI should directly pay him. But this did not happen.
Hence Aragones filed a complaint for sum of money with damages against Garcia and DMPI
before RTC.

RTC ruled in favor of Aragones, it held that DMPI and Garcia are jointly and severally liable. DMPI
appealed to Court of Appeal (CA). However at CA, the court affirmed RTC‘s decision. Hence,
DMPI filed this petition. It contends that the supply agreement between Garcia and Aragones is a
contract of sale to which DMPI was not privy, hence DMPI cannot be held liable.

Issue: Whether or not Supply Agreement between Aragones and Garcia is a contract of sale

Held: Contrary to DMPI‘s claim that ―save for the shape, there was no consideration of any
special needs or requirements of DMPI taken into account in the design or manufacture of the
concrete paving blocks,‖ the ―Supply Agreement is replete with specifications, terms or conditions
showing that it was one for a piece of work.

As reflected in the highlighted and underscored above-quoted provisions of the ―Supply


Agreement, as well as other evidence on record, the machines Aragones was obliged to fabricate
were those for casting the concrete blocks specified by Garcia. Aragones did not have those kind
of machines in his usual business, hence, the special order.

Under Article 1467 then of the Civil Code, a contract for the delivery at a certain price of an article
which the vendor in the ordinary course of his business manufactures or procures for the general
market, whether the same is on hand at the time or not, is a contract of sale, but if the goods are to
be manufactured specially for the customer and upon his special order, and not for the general
market, it is a contract for a piece of work. The Supply Agreement was decidedly a contract for a
piece of work.

Following Art. 1729 of the Civil Code which provides that those who put their labor upon or furnish
materials for a piece of work undertaken by the contractor have an action against the owner up to
the amount owing from the latter to the contractor at the time the claim is made.

Aragones having specially fabricated three casting machines and furnished some materials for the
production of the concrete blocks specially ordered and specified by MEGA-WAFF which were to
be and indeed they were for the exclusive use of MEGA-WAFF, he has a cause of action upon
DMPI up to the amount it owed MEGA-WAFF at the time Aragones made his claim to DMPI

You might also like