Dunlop Pneumatic Tyre Co Ltd (‘Dunlop’) entered into a contract to sell tyres and other accessories to New Garage

Motor
Co Ltd (‘New’) on terms design to ensure that the tyres were not sold below the manufacturers listed price. New agreed to
pay Dunlop “the sum of £5 for each and every tyre … sold in breach of this agreement, as and by way of liquidated
damages and not as a penalty”. New sold tyres in breach of the agreement.

Whether the clause constituted a penalty and, consequently, was unenforceable.

In the circumstances of the case, the sum of £5 was a liquidated damage and not a penalty.

Lord Dunedin in his classic statement of liquidated damages said, at paragraphs 86 to 88:
1. Though the parties to a contract who use the words ‘penalty’ or ‘liquidated damages’ may prima facie be
supposed to mean what they say, yet the expression used is not conclusive. The Court must find out
whether the payment stipulated is in truth a penalty or liquidated damages. This doctrine may be said to
be found passim in nearly every case.
2. The essence of a penalty is a payment of money stipulated as in terrorem of the offending party; the
essence of liquidated damages is a genuine covenanted pre-estimate of damage (Clydebank Engineering
and Shipbuilding Co v Don Jose Ramos Yzquierdo y Castaneda [1905] AC 6.
3. The question whether a sum stipulated is penalty or liquidated damages is a question of construction to be
decided upon the terms and inherent circumstances of each particular contract, judged of as at the time of
the making of the contract, not as at the time of the breach (Public Works Commissioner v Hills [1906]
AC 368 and Webster v Bosanquet [1912] AC 394.
4. To assist this task of construction various tests have been suggested, which if applicable to the case under
consideration may prove helpful, or even conclusive. Such are:
a. It will be held to be penalty if the sum stipulated for is extravagant and unconscionable in amount in
comparison with the greatest loss that could conceivably be proved to have followed from the breach.
(Illustration given by Lord Halsbury in Clydebank Case [1905] AC 6.)
b. It will be held to be a penalty if the breach consists only in not paying a sum of money, and the sum
stipulated is a sum greater than the sum which ought to have been paid (Kemble v Farren 6 Bing 141).
This though one of the most ancient instances is truly a corollary to the last test. Whether it had its
historical origin in the doctrine of the common law that when A promised to pay B a sum of money
on a certain day and did not do so, B could only recover the sum with, in certain cases, interest, but
could never recover further damages for non-timeous payment, or whether it was a survival of the
time when equity reformed unconscionable bargains merely because they were unconscionable, - a
subject which much exercised Jessel MR in Wallis v Smith 21 Ch D 243 - is probably more interesting
than material.
c. There is a presumption (but no more) that it is penalty when 'a single lump sum is made payable by
way of compensation, on the occurrence of one or more or all of several events, some of which may
occasion serious and others but trifling damage' (Lord Watson in Lord Elphinstone v Monkland Iron
and Coal Co 11 App Cas 332).
On the other hand:
d. It is no obstacle to the sum stipulated being a genuine pre-estimate of damage, that the consequences
of the breach are such as to make precise pre-estimation almost an impossibility. On the contrary, that
© Doyles Construction Lawyers 2005

This publication is intended to be a topical report on recent cases in the construction, development and project industries. This publication is not intended to be a
substitute for professional advice, and no liability is accepted. This publication may be reproduced with full acknowledgement.
NSW QLD VIC
Jim Doyle Frank Nardone Vinodhini Krisnan
P: 02 9283 5388 P: 07 3221 2970 P: 03 9620 0322
E: [email protected] E: [email protected] E: [email protected]

www.doylesconstructionlawyers.com
is just the situation when it is probable that pre-estimated damage was the true bargain between the
parties (Clydebank Case, Lord Halsbury [1905] AC at p11; Webster v Bosanquet, Lord Mersey [1912]
AC at p 398.

The use of the words ‘penalty’ or ‘liquidated damages’ does necessary mean that a clause is either a ‘penalty’ or a
‘liquidated damages’ clause. The Court will review the clause in light of the circumstances at the time of entering into the
Contract.

© Doyles Construction Lawyers 2005

This publication is intended to be a topical report on recent cases in the construction, development and project industries. This publication is not intended to be a
substitute for professional advice, and no liability is accepted. This publication may be reproduced with full acknowledgement.
NSW QLD VIC
Jim Doyle Frank Nardone Vinodhini Krisnan
P: 02 9283 5388 P: 07 3221 2970 P: 03 9620 0322
E: [email protected] E: [email protected] E: [email protected]

www.doylesconstructionlawyers.com

You might also like