INCOMPLETE TENDER PACKAGE

(FOR REFERENCE PURPOSE)

KUWAIT OIL COMPANY (K.S.C.)


(Register of Commerce No. 21835)

ANNEXURE 1
- to –

ATTACHMENT NO. 2 TO FORM OF TENDER – BILL OF QUANTITIES


- for –

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION


FOR INDEMNIFICATION

"NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION


(NKETR)”

METHOD OF MEASUREMENT (“MoM”) – ZONE 1 & ZONE 2

TABLE OF CONTENTS

METHOD OF MEASUREMENT (“MoM”)......................................................................... 3

GENERAL NOTES ................................................................................................................. 3


I. PREAMBLES ................................................................................................................................. 3
II. MEASUREMENT........................................................................................................................... 6
III. VERIFICATION OF MEASUREMENT ........................................................................................ 7
IV. COORDINATION .......................................................................................................................... 7
V. REGULATORY REQUIREMENTS .............................................................................................. 7
VI. ABBREVIATIONS ......................................................................................................................... 7

PORTION 1A – PRELIMINARIES ...................................................................................... 8


1A.1 CONTRACTUAL PRELIMINARIES ................................................................... 8
1A.2 HSE STUDIES ........................................................................................................ 8
1A.3 Mobilization of Mobile Site Offices and Temporary Site Offices ....................... 10
1A.4 WORK RELATED PRELIMINARIES, TEMPORARY WORKS AND
ENABLING WORKS .......................................................................................... 10

PORTION 1B - PRELIMINARIES, ENABLING AND GENERAL WORKS ............... 16


1B.1 PRELIMINARIES WORKS ................................................................................. 16
1B.2 ENABLING WORKS ........................................................................................... 19
1B.2a AIR QUALITY CHARACTERIZATION ........................................................... 19
1B.2b SURVEY OF UTILITY SERVICES / MANUAL EXCAVATION FOR SLIT
TRENCHES ......................................................................................................... 20

Page 1 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.2c POST–TOPOGRAPHIC SURVEY ...................................................................... 22


1B.2d BASELINE NATURALLY OCCURRING RADIOACTIVE MATERIALS
(NORM) SURVEY .............................................................................................. 23
1B.2e GROUNDWATER CHARACTERIZATION ...................................................... 25
1B.2f MONITORING WELL AND PIEZOMETER INSTALLATIONS ..................... 26
1B.2g GROUNDWATER, SURFACE WATER & LEACHATE SAMPLING,
ANALYSIS, MONITORING, DATA MANAGEMENT AND PIEZOMETER 36
1B.3 GENERAL WORKS............................................................................................. 37
1B.3a ACCESS ROAD & CRASH BARRIERS ............................................................ 37
1B.3b NORMS, IDENTIFIED ASBESTOS AND HAZARDOUS WASTES
MATERIALS ....................................................................................................... 42

PORTION 2 – SITE WORKS: EXCAVATION & TRANSPORTATION WORKS (RE-


MEASURABLE) ................................................................................................ 44
2.1 COMPLIANCE SOIL SAMPLES MONITORING ............................................ 44
2.2 MATERIALS DESIGNATED FOR REMEDIATION or STOCKPILING ........ 46
2.3 MATERIALS DESIGNATED FOR REMEDIATION or STOCKPILING ........ 48
2.4 UNTREATED CONTAMINATED DRY MATERIALS MIXING WITH OIL
SLUDGE .............................................................................................................. 50
2.5 WASTE MANAGEMENT - CONSTRUCTION DEBRIS MATERIALS:......... 51
2.6 TRANSPORTATION AND PLACEMENT OF TREATED SOIL ..................... 53

PORTION 3A - SITE WORKS: REMEDIATION WORKS - TPH >1% - ≤ 5%........... 56


3.1 SAMPLE ANALYSIS & DATA MANAGEMENT ............................................ 57
3.2 REMEDIATION WORKS ................................................................................... 60

PORTION 3B - SITE WORKS: REMEDIATION WORKS - TPH >5% - ≤ 7% ........... 63


3.1 SAMPLE ANALYSIS & DATA MANAGEMENT ............................................ 64
3.2 REMEDIATION WORKS ................................................................................... 67

PORTION 4 – SITE WORKS: REMEDIATION WORKS – TPH >7% ......................... 70


4.1 SAMPLE ANALYSIS & DATA MANAGEMENT ............................................ 70
4.2 REMEDIATION WORKS FOR CONTAMINATED SOILS ............................. 72

PORTION 5 – SITE WORKS: EXISTING LANDFILL EXPANSION .......................... 75


5.0 EXISTING LANDFILL EXPANSION ................................................................ 75
Page 2 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

6.0 KUWAITIZATION............................................................................................ 80

METHOD OF MEASUREMENT (“MoM”)

To fulfil the scope of Works related to this project, the Contractor shall execute the
scope of Works as specified and reference to Contract documents. This Method of
Measurement (MoM) describes the method in which the respective line items in the
Bill of Quantities (BOQ) are to be measured and priced in accordance with the
Technical Specifications and terms and conditions of the Contract.

Contents of Bill of Quantities (BOQ)

The Bill of Quantities has been divided into the following Portions, which are
tailored to the TS Portion 1A through Portion 5:

• Portion 1A - Preliminaries (Fixed Lump Sum Price)


• Portion 1B - Preliminaries, Enabling and General Works
• Portion 2 - Site Works: Excavation & Transportation Works
• Portion 3A - Site Works: Remediation Works – TPH >1% - ≤ 5%
• Portion 3B - Site Works: Remediation Works – TPH >5% - ≤ 7%
• Portion 4 - Site Works: Remediation Works – TPH >7%
• Portion 5 - Site Works: Existing Landfill Expansion

Each of the above Portions include a variety of subtasks to be completed as detailed


within the Contract and as implied there from.

GENERAL NOTES

I. PREAMBLES

i. The priced BOQ represents the Works to be carried out in accordance with the
Contract. Descriptions contained in the BOQ represents the outline of the scope of
the respective item of work and proper reference is made to other parts of Contract
documents for complete information for pricing. Where appropriate, items are
cross-referenced to the Technical Specifications and other parts of Contract
documents.

ii. The Contractor shall be deemed to have included all necessary costs for Portion 1A
(Preliminaries, HSE studies, Temporary Works and Enabling Works) against the
respective items in the BOQ and shall not include an allowance for any such rates
or sums in any measured item of Portions 1B, 2, 3, 4, 5 and 6 of the BOQ.

Page 3 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

iii. The Contractor shall allow in the Unit Rates for protecting all Works against
damage by whatever method is deemed necessary.

iv. The Unit Rate against each item in the BOQ shall be comprehensive and shall
include all matters and activities necessary for the proper engineering, design,
execution, and completion of the Works irrespective of access conditions, slope,
nature of ground, presence of oil or water or any other conditions. No claims for
additional payment will be allowed for any error or misunderstanding by the
Contractor of the work involved.

v. The Unit Rate for each item shall allow for all unforeseen costs, specific item(s) of
works not specified and/or included in the BOQ and expenses in complying with
all general risks, liabilities and obligations set forth or implied in the Drawings,
Specifications and the Contract including, but not limited to, the costs of the
following:
• Protection of all Works during transportation and construction activities;
• Any downtime (inclement weather, delays due to Contactor’s negligence
and Defects in the Works) shall be accounted for in the Unit Rates;
• Providing Work Plans, Method of Statements, Reports, deliverables and
other necessary required documents as per Contract requirements;
• Disposal of any wastes generated by the Contractor for its own operation
and maintenance of facilities, transportation fleet or equipment through
performance of the Works including all associated fees;
• Providing GIS data’s formats in preparing documentation and reports;
• Providing portable camera to record progress of the Project, key events and
activities from beginning to end including preliminaries, enabling works,
E&T, remediation technologies, landfilling and backfilling. Providing fixed
camera to monitor progress at Treatment Areas/Pads;
• Familiarization / Training of Company staff – during execution treatment
used;
• Cost for Air Conditioner Requirement in Heavy Equipment
• Cost in installing video surveillance system around the remediation/
treatment areas consisting of several video cameras with full view of the
entire areas in accordance but not limited to Clause 4.3 of Technical
Specification Portion 3 & Clause 4.3 of Technical Specification Portion 4
• Cost for capturing video and photography during the contractual period.
Various activities are to be recorded, including: key events, information
videos, monthly remediation progress activities, end-of-year summation
videos in accordance but not limited to Clause 9.6 of Technical
Specification Portion 1(A&B).

Page 4 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Inclusive of costs associated with Contractors proven attempts to obtain, in


accordance with Technical Specification Portion 1(A&B), energy through
renewable energy sources and water conservation and re-use for the
following;

o Contractor and Company’s Field Offices, 20% supplied by renewable


energy and energy savings.
o Recycling and re-use segregation bins for papers, plastics, garbage’s,
glasses.
• Grey or treated water: conservation, recycling and re-use for 30% of treated
water to meet the project objectives and minimize the water usages
throughout the project duration. All Unit Rates for civil/construction
activities shall include allowance in providing UXO escort One (1) UXO
Level II per team at significant activities/areas with a potential UXO
anomalies;
• Providing UXO Construction Support to all civil works construction
activities (i.e. BAC, Survey works, excavation, treatment, stockpiling,
restoration and other civil works mentioned in the Contract);
• Pre-or Post-treatment activities;
• Providing signage boards or other signage safety, hazard, UXO etc. to the
excavation or remediated areas and delineated wooden posts in accordance
but not limited to Clause 16 of Technical Specification Portion 1(A&B);
• Maintenance of applicable Project Works in accordance but not limited to
Clause 11.3 of Technical Specification Portion 1(A&B);
• All required tests, inspections and trainings;
• Securing required permits, licenses or the like from State of Kuwait
Government and/or non-Governmental institutions/authorities as
applicable. All applicable taxes, duties, charges, import/export
duties/charges, government levies, landing charges, transport and the like
not mentioned in the BOQ line items;
• Temporary Works and other incidentals necessary to complete the Works;
and
• Compliance with all HSE requirements including provision of
environmental controls and mitigations; and providing emergency clinics
with trauma certified medics and ambulances.
• All costs associated with any / all interfaces with other Company nominated
Contractor(s) are to be included within Contractors Unit Rates
• Water or dust suppressions to prevent dust emission during execution of
works

Page 5 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

vi. In relation to the Unit Rates herein, no claim shall be entertained for loss of
overhead or profit because of any variation, omission or addition, or because of
Contractor’s method of pricing.

vii. The Unit Rates for all personnel to complete the Works shall be deemed to be
inclusive of all mobilization and demobilization and for all ancillary costs,
including but not limited to, flights, accommodation, subsistence, in-and out
country transport, import/export duties and taxes etc.

viii. The Unit Rates shall be valid for the entire duration of the Contract and any
extensions thereof. No adjustment in the Unit Rates shall be allowed for any
increase or decrease in the estimated quantities.

ix. All Unit Rates are independent and not extra over unless specifically stated to the
contrary, thus only one Unit Rate shall apply to any item of measured work except
where specifically stated otherwise.

x. The Clause(s) of each item in the MoM is assigned at the relevant marginal heading
of the Bill of Quantities for cross reference but will not be limited to the mentioned
specific Clauses.

xi. The MoM and BOQ shall be read in conjunction with all other documents forming
the Contract, all of which shall be taken as mutually explanatory.

xii. The Contractor is referred to the Specification for the description and detail of the
standard of workmanship and material required for the Work.

xiii. Contractor shall be deemed to have understood and accepted the methodology by
which the BOQ has been prepared and is and will be priced accordingly.

II. MEASUREMENT

i. Detail calculation shall be up to two (2) decimal places. The total of all detail
calculations shall be rounded to the nearest units of measurement.
ii. The quantities are estimated in BOQ and may be varied, and actual quantities will
be determined and measured in accordance but not limited to Clause 12.5 of
Contract Specification.
iii. The item / quantities may be used in whole, in part or not at all and the Company
accepts no responsibility for the accuracy of the items and quantities.
iv. The BOQ defines the items, their quantities and the units of measurement under this
Contract. The BOQ are supplemented by measurement rules detailed herein.
v. The MoM shall prevail throughout the Contract notwithstanding any trade, local or
general custom and shall be used in the adjustment of all measured variation, or

Page 6 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

further measurement or re-measurement, if any.


vi. All items or work is measured net as fixed in position.
vii. The use of hyphen between two dimensions in the BOQ shall mean a range of
dimensions exceeding the first dimension stated but not exceeding the second.
viii. Remeasuring of the quantities shall use same principles and method used to estimate
quantities in BOQ.

III. VERIFICATION OF MEASUREMENT

i. All measurements and records for the purpose of payment shall be made jointly by
the Company & Contractor in accordance but not limited to Clauses 12.5 & 12.7 of
Contract Specification.
ii. Measurement Plan shall be provided by Contractor and shall be submitted to
Company for approval.
IV. COORDINATION
The Contractor shall make due allowance in the Unit Rates for executing the Works
in cooperation and coordination with the works being executed by others, and
sequence and program the Works accordingly.

V. REGULATORY REQUIREMENTS
Unless otherwise required by the Contract, all costs of statutory requirements,
including obtaining any required permits, licenses and any other such statutory
requirements shall be inclusive to be included in the Unit Rates and/or Lump Sum.

VI. ABBREVIATIONS

The following standard abbreviations are used throughout the Bill of Quantities:

MoM Method of Measurement


BOQ Bill of Quantities
DXF Drawing Exchange Format
EQuIS Environmental Quality Information System
GIS Geographical Information System
Kg Kilograms
L Litre(s)
LS Lump Sum
m² Square Meter(s)
m³ Cubic Meter(s)

Page 7 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

No. Number(s)
NORM Naturally Occurring Radioactive Materials
RFI Request for Inspection
RMCS Re-Measurement Calculation Sheets
RSO Radiation Safety Officer
RST Radiation Safety Technician
RTC Remediation Target Criteria
T Tonnes
USD US Dollars
UXO Unexploded Ordnance
IVS Instrument Verification Strip
PORTION 1A – PRELIMINARIES

1A.1 CONTRACTUAL PRELIMINARIES

1A.1a Bonds and Guarantees

The Lump sum price for bonds and guarantees shall cover all costs and expenses
incurred in obtaining, providing and maintaining all bonds and guarantees to be
provided by the Contractor in accordance but not limited to Clause 16 of Contract
Specification and Clause 40 of General Conditions of Contract.

1A.1b Insurances

The Lump sum price for insurances shall cover all costs and expenses incurred in
obtaining and maintaining all insurances to be provided by the Contractor in
accordance but not limited to Clause 9 of Contract Specification and Clause 39 of
General Conditions of Contract.

1A.2 HSE STUDIES

1A.2a Project Conceptual HSE Plan and Health Safety and Environmental Reviews
(PHSER 3, 4, 5 & 6)

The lump sum price for Project Conceptual HSE Plan and Health Safety and
Environmental Reviews (PHSER 3, 4, 5 & 6) shall include but not be limited to,
preparation, submission, performance of sessions Project HSE, PHSERs, HSE Plan
and HSE final reports, execution, compliance monitoring and required approval of
Project HSE plan on the basis of Company Conceptual HSE plan and PHSER 3, 4,
5 & 6 deliverables and closing & approval of all pending items, in accordance but

Page 8 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

not limited to Clauses 8.0, 8.1 & 8.3 of Contract Specification and Clauses 13.2 &
13.3 of Technical Specification Portion 1(A&B) and closing of pending items and
approval, whether or not they are specifically mentioned within the item
description.

1A.2b Hazard Identification (HAZID)

The lump sum price for Hazard Identification (HAZID) shall include but not be
limited to, preparation, submission, execution and compliance monitoring and
required approval of HAZID deliverables (i.e. final reports, etc.), in accordance
with Clauses 8.0 & 8.3 of Contract Specification and Clauses 13.2 & 13.3 of
Technical Specifications Portion 1(A&B), whether or not they are specifically
mentioned within the item description.

1A.2c Hazard and Operation (HAZOP)

The lump sum price for Hazard and Operation (HAZOP) shall include but not be
limited to, preparation, submission, execution and compliance monitoring and
required approval of HAZOP deliverables (i.e. final reports, etc.), in accordance
with Clauses 8.0 & 8.3 of Contract Specification and Clauses 13.2 & 13.3 of
Technical Specifications Portion 1(A&B), whether or not they are specifically
mentioned within the item description.

1A.2d Quantitative Risk Assessment (QRA)

The lump sum price for the QRA shall include but not be limited to, preparation,
submission, execution, compliance monitoring and required approval of QRA
deliverables, as contained in Clauses 8.0 & 8.5 of Contract Specification and
Clauses 13.2 & 13.3 of Technical Specifications Portion 1(A&B), whether or not
they are specifically mentioned within the item description.

1A.2e Environmental Social Impact Assessment (ESIA) Studies & Reports inclusive
Environmental Management Plan and Progressive Environmental Monitoring
Reports

The lump sum price Environmental Social Impact Assessment (ESIA) Studies &
Reports inclusive Environmental Management Plan and Progressive
Environmental Monitoring inclusive of Environmental Management Plan and
Progressive Environmental Compliance Monitoring Testing and Reports during
Contract duration shall include but not be limited to, preparation, submission,
execution of comprehensive studies, preparation and submission of ESIA reports,
execution of environmental compliance monitoring and reporting during the
contract duration and obtaining permits, approval of ESIA deliverables, in
accordance but not limited to Clauses 8.0 & 8.4 of Contract Specification and
Clauses 13.2 & 13.5 of Technical Specification Portion 1(A&B), whether or not they

Page 9 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

are specifically mentioned within the item description.

1A.3 GENERAL PRELIMINARIES - For Technical Specification Portion 1(A&B), 2,


3 & 4 Works

1A.3 Mobilization of Mobile Site Offices and Temporary Site Offices

The lump sum price for Mobilization of Mobile Site Offices and Temporary Site
Offices for the period of the Contract, shall include but not limited to all costs
necessary in mobilizing all such temporary facilities to/from the project site
including but not limited to supply, construction, handling, procurement,
importation, clearing, grubbing & levelling of soils and all civil works related to
this item, approval of locations and subsequent re-exportation of materials, waste
handling and disposals and vehicles of whatever type or size required for the
performance of the Work, provision of necessary certification, custom Clearance,
duties, taxes, levies, obtaining necessary permits & licenses required to operate at
Work site for the execution of the Work, whether or not they are specifically
mentioned within the item description. Suitable facilities in accordance but not
limited to Clause 8.10 of Technical Specifications Portion 1(A&B), the price for
Mobile Site Office & Temporary Site Offices and Facilities shall be in accordance
but not limited to Clause 7 and Appendix IV of Contract Specification.

1A.4 WORK RELATED PRELIMINARIES, TEMPORARY WORKS AND


ENABLING WORKS
1A.4a WORK RELATED PRELIMINARIES - For Technical Specification Portion 1
(A&B), 2, 3 and 4 Works

1A.4a.1 High Resolution Satellite Imagery – Preliminary Works

The lump sum price to obtain and/or acquire High Resolution Satellite Imagery over
the areas of interest (full aerial coverage) in accordance but not limited to Clauses
8, 8.2, 13.1.2 & 13.6.1 of Technical Specification Portion 1(A&B) shall include, but
not be limited to utilization of all necessary labour, vehicles, software’s, computer,
office equipment, stationaries, office consumables, interpretation, processing,
providing working drawings, permits, authorizations, notifications, calculations,
including submission of any other relevant documents and deliverables, providing
sufficient number of drawings, whether or not they are specifically mentioned
within the item descriptions.

1A.4a.2 UXO Project Final Reports including Project GIS Database (s): For GIS +
Geophysical Survey + Clearance

The lump sum price for UXO Project Final Reports including Project GIS Database
(s): For GIS for Geophysical Survey + Clearance in accordance with Clause 10 of
Technical Specification Portion 1(A&B) shall include, but not be limited to

Page 10 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

utilization of all necessary labour, vehicles, software’s, computer, office equipment,


stationaries, office consumables, interpretation, data processing, providing working
drawings (if applicable), permits, authorizations, notifications, any calculations,
including submission of any other relevant documents and deliverables for
Company approval, whether or not they are specifically mentioned within the item
descriptions.

1A.4b ENABLING WORKS

1A.4b Groundtruthing Survey and Pre-Topographic Survey

1A.4b.a Unit of Measurement


Square Meter (m²)

1A.4b.b Pricing

The rates for undertaking Groundtruthing Survey and Pre-Topographic Survey,


other associated activities and submission of relevant document (i.e. approved
RFI’s, etc.), deliverables in accordance but not limited to Clauses 1.2, 7.4, 8, 8.3 &
8.4 of Technical Specification Portion 1(A&B) and Clause 3.0 of Technical
Specification Portion 2, shall include but not be limited to the following:

• Utilizing of all necessary labour, equipment and material, vehicles, software


(shape files, AutoCAD & DXF), calibration/upgrading of equipment’s, photos,
logging, JSA, monuments/benchmarks, lay outing, pre/post topographic survey
(not mentioned in other BOQ items), Constructional Plant, obtaining Clearance,
Gate Passes, license, taxes & Permits;
• Preparation of pre-& final reports (survey control reports and other related
reports);
• Providing confirmation of boundaries among features and clean ground and
boundary of Oil Lakes, Contaminated Soil Piles (OCP) and/or tarcrete;
• Provide lists of underground and above ground facilities/obstructions identified
during survey;
• Survey of plant facilities with relevance to the treatment areas, disposal areas,
stockpiling areas and storage areas;
• Provision of any relevant associated works that are not listed and/or included in
the BOQ requiring ground-truthing and topographic survey works;
• Providing updated drawings for approval with new boundaries after further
ground-truthing and all costs for complying with all relevant requirements in
accordance with Clause 8 of Technical Specification Portion 1(A&B), whether
or not they are specifically mentioned within the item description;
• Related works to update approved documents, drawings based on changes in
boundary conditions.
• Verification of pre-excavation elevations across the areas designated for

Page 11 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

excavations project activities;


• Pre-Topographic Survey across the areas designated for other project activities
(features, treatment areas, lay-down areas, landfill areas, any location as
required in the Contract);
• Survey works in monitoring wells steel casing elevation and piezometer;

1A.4b.c Measurement

• Measurement shall be based in approved Ground-truthing and Pre-Topographic


survey report completed net areas in square meters (m²) & associated with
approved relevant documents and supported by an approved final RFI’s and
marked up drawings showing acquired data in the site, extent, elevations,
boundaries & limit of features;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified, adjusted and agreed during final
measurement based in all relevant approved documents.

1A.4c UXO BATTLE AREA CLEARANCE

1A.4c UXO Battle Area Clearance

1A.4c.a Unit of Measurement


Square Meter (m²)

1A.4c.b Pricing

The rates for undertaking UXO Battle Area Clearance (including but not limited
to treatment areas/pads and treatment technologies areas/pads, roads, soil features,
temporary facilities, landfill;), and other associated activities and submission of
relevant document deliverables in accordance but not limited to requirement of
Clauses 1.2, 10. 10.4 & 10.5 of Technical Specifications Portion 1(A&B) shall
include but not be limited to the following:

• Utilization of all necessary labour, Constructional Plant, obtaining gate passes,


permits, clearance, taxes & license, providing UXO anomaly avoidance/support
team, providing instruments, calibration/upgrading & standardizations,
storages, Interim & Final certificates, quality control/reviews of data processing
& analysis, recording of all findings & reporting and/or any required documents
to the approved depth by complying for each location/feature;
• UXO anomalies retrieval, transportation & storage includes excavation and
backfill of voids due to excavation of anomalies and other related UXO works
to complete BAC works and issuance of clearances;
Page 12 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Providing UXO Construction support


• Separate construction debris and other waste materials for further storage or
disposal
• Prepare and submit plans methodology, procedures, RFI’s, issuance of
clearance certificates & drawings to carry out the cited activities and all costs
for complying with all relevant requirements contained in Clause 10.4 of
Technical Specification Portion 1(A&B), whether or not they are specifically
mentioned within the item descriptions.

1A.4c.c Measurement

• Measurement shall be based in the approved executed works, net cleared areas
in square meters (m²), a 30cm overlapping whenever is deemed necessary is
included in the Unit Rates, supported by an approved RFI’s, marked up
drawings, interim clearance certificates and/or any approved relevant
documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1A.4d SOIL CHARACTERIZATION

1A.4d Soil Sample Collection, Laboratory Analysis & Data Management for Enabling
works as per Technical Specifications Portion 1 (A&B).

1A.4d.a Unit of Measurement


Number (No.)

1A.4d.b Pricing

The rates for undertaking Soil Sample Collection, Laboratory Analysis & Data
Management for Enabling works as per Technical Specifications Portion 1 and
submission of relevant document deliverables for Company approval in accordance
but not limited to Clauses 8, 8.5, 8.16, 13.1.2, 13.5 & 15 of Technical Specification
Portion 1 and shall include but not be limited to the following:
Page 13 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Utilizing of all necessary labour, constructional plant, equipment, material and


any consumables items required for collecting and delivery of samples,
software, hand tools, packaging, labelling, marking, copying, binding, testing,
calibration, obtaining gate passes & permits, clearance, taxes, providing
scaffolds and barricades;
• Conducting manual and/or hand pitting and mechanical soil sampling
collections at various completion depth inclusive UXO anomaly avoidance;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory);
• Survey works of top of steel casing of monitoring groundwater wells and water
supply wells and piezometers to provide elevations of soil and
groundwater/surface sampling points, test pits points; or compliance points,
stack sampling;
• Rejected samples (i.e. not meeting the requirements in the Technical
Specification) shall not be paid and cost for retest including re-excavation, soil
and/or groundwater sample collection, re-packing, labelling and transportation
are solely Contractor’s responsibilities;
• Providing sufficient protection throughout the Contract period until issuance of
the Certificate of Completion whereupon the permanent monitoring boreholes
will be handed over to the Company;
• Field logs submission according to KOC standards;
• Familiarization and trainings of Company staff for Site Characterization which
includes but not limited to Sampling methodologies, plans, protocol set-up,
collection, logging, procedures, use of field test kits, field operations between
site and GIS map production, and appropriate statistical measures of their
functionality in accordance with Technical Specification Portion 1.
• Submission, screening records documented in detail for soil, location, TPH
values, all reports shall be submitted to substantiate and/or support the main
sampling reports;
• Preparation of pre-& final reports, results, documentations and other related
reports), whether or not they are specifically mentioned within the item
description; and
• Rejecting of data sample result based on validation and/or QA/QC analysis shall
be re-collected and analysed at no cost to the Company.

1A.4d.c Measurement

• Measurement shall be based in number(s) on the approved Soil Sample


Collection, Laboratory Analysis & Data Management for Enabling works and
associated with approved relevant documents and supported by an approved
RFI’s;
• Providing calculation sheets as per approved measurement plan/re-
Page 14 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

measurement calculation sheets (RMCS) referring to the relevant approved


documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified, adjusted and agreed during final
measurement based in all relevant approved documents.
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with
all requirements in accordance but not limited to Clause 11.5 of Technical
Specification Portion 1, whether or not they are specifically mentioned within
the item descriptions

1A.4e TREATMENT AREAS/PADS


(Includes Supply, Construct, Maintenance and Decommissioning)

1A.4e.a Unit of Measurement


Square Meter (m²)

1A.4e.b Pricing

The rate for undertaking Remediation Treatment Area/Pads and Treatment


Technologies Area/Pads, other associated activities and submission of relevant
document deliverables in accordance but not limited to Clause 8.8 of Technical
Specification Portion 1(A&B), Clauses 4.3 & 4.4 of Technical Specification Portion
3 and Clause 4.4 of Technical Specification Portion 4, shall include but not be
limited to the following:

• Utilizing of all necessary labour, equipment, constructional plant, supply of


materials, water, loading, transportation, stockpiling, maintenance & any
consumables items, compaction, testing, obtaining clearance, gate passes &
permits;
• Ground surface preparation includes clearing, levelling, watering, compacting
of treatment areas/pads in accordance with the Contract;
• Segregation, screening, breaking and pulverising oil contaminated materials and
separate construction debris and other waste materials for further storage or
disposal.
• Provide gatch material for construction of remediation pads;
• Provide asphalt material/equipment’s for construction of treatment technologies
pads;
• Inclusive of cost in providing temporary secure perimeter fences, gates and sign
board in accordance with the Contract requirements and clause 8.8 of Technical
Specification Part 1.
• Water or dust suppressions to prevent dust emission during execution of works;
• Provide and submit method statement for construction of treatment areas/pads

Page 15 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

for Company approval prior to commence the cited activities;


• Protection of underlying clean soils, groundwater and surface water and air. The
treatment areas/pad type and thickness shall be sufficient to eliminate leaching
of contaminants to underlying virgin soils;
• Cleaning of work areas as work progress and/or completion of works return
adjacent areas to condition existing before start of work;
• Cleaning and watering adjacent roadways areas of dust, dirt, and debris caused
by the transportation or spillages as directed by the Company's Superintendent;
• Stockpiling/segregation and breaking at approved designated areas of any
materials found in working areas;
• Maintenance includes storm water managements and other associated works;
• Submission of proposal for the location and methodology of treatment
areas/pads construction to Company for review and approval prior to commence
the works;
• Restoring the areas covered by treatment areas/pads to pre-existing conditions
upon completion of the contract;
• All costs for complying with all requirements contained as per above Clauses
in technical Specifications, whether or not they are specifically mentioned
within the item descriptions.

1A.4e.c Measurement

• Measurement shall be based in approved quantities in square meter (m²)


supported by an approved relevant document, drawings, RFI’s, calculations
with all associated acquired data in the site and other relevant approved Contract
documents;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) which is referring to the relevant
approved documents in accordance with the requirements of technical
specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

PORTION 1B - PRELIMINARIES, ENABLING AND GENERAL WORKS

1B.1 PRELIMINARIES WORKS

1B.1a GENERAL PRELIMINARIES - For Technical Specification Portion 1(A&B), 2,


3 and 4 Works

1B.1a.1 Demobilization of Mobile Site Offices and Temporary Site Offices

Page 16 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

The lump sum price for Demobilization of Mobile Site Offices and Temporary Site
Offices for the period of the Contract, shall include but not limited to all costs
necessary in demobilizing all such site offices to/from the project site including but
not limited to removal of constructed facilities (i.e. offices and temporary facilities),
re-handling, re-procurement, re-importation, and subsequent re-exportation of all
Constructional Plants, materials, and vehicles utilized during the performance of
the Work, provision of necessary certification, custom Clearance, duties, taxes,
levies, obtaining necessary permits & licenses required to demobilized at the site,
whether or not they are specifically mentioned within the item descriptions in
accordance but not limited to Clause 9.5 of Technical Specifications Portion
1(A&B). Making the area/land to pre-installation condition and bringing to the
original conditions including cleaning from all construction debris left by site
office, all rubbish materials (i.e. metal, wood, concrete etc.).

1B.1a.2 Maintenance of Mobile Site Offices and Temporary Site Offices


The lump sum price for Maintenance of Mobile Site Offices and Temporary Site
Offices shall include all scheduled and unscheduled maintenance in accordance but
not limited to Clause 7 specifically Appendix IV of Contract Specification and
Clause 11.3 of Technical Specification Portion 1(A&B), including but not limited to,
Cleaning of cabins, workshop, laboratory facilities (if used), stores, security huts,
welfare, messing and sanitary facilities, furniture as required to suit personnel needs
on site office, equipment, fences, gates, parking facilities (including access & sign
boards), water including potable water, fuels, office consumables and equipment,
disposal of sewage, waste water & rubbish to an approved dumping location,
telecommunications, data and electricity supplies including payment of all bills,
fees, rent, charges and the like, office, safety, first aid and medical consumables,
security arrangement including provision of security staff, payment of all fees,
taxes, rates, subscriptions, utilization and consumption charges for services, repair
and utilities, stationary and other office consumables, oils, grease, and all other
requirements in respect of maintaining the facilities throughout the duration of the
Contract, including approvals by Company and certification for use/occupation as
required and all costs in complying with the Contract, Company procedures and
State laws and regulations.

Inclusive of costs associated with Contractors proven attempts to obtain, in


accordance with Technical Specification Portion 1(A&B), energy through renewable
energy sources and water conservation and re-use for the following;
Contractor and Company’s Field Offices, 20% supplied by renewable energy and
energy savings.
Recycling and re-use segregation bins for papers, plastics, garbage’s, glasses.
Grey or treated water: conservation, recycling and re-use for 30% of treated water
to meet the project objectives and minimize the water usages throughout the project
duration.

Page 17 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.1b WORK RELATED PRELIMINARIES - For Technical Specification Portion


1(A&B), 2, 3 and 4 Works

1B.1b.1 Works Reports

The Lump sum price for Works reports shall include but not limited to all the
requirements in accordance but not limited to Clauses 1.2, 8, 9.2, 9.3, 9.4, 13, 14
and 15 of Technical Specification Portion 1 including submission of any other
relevant documents and deliverables for Company approval, whether or not they
are specifically mentioned within the item descriptions.

1B.1b.2 Pre-Field Reporting Requirements as per Technical Specification Portion 1(A&B).

The Lump sum price for Pre-Field Reporting Requirements shall include but not
limited to all the requirements in accordance but not limited to Clauses 8.2, 9, 13 &
14 of Technical Specification Portion 1(A&B), including submission of any other
relevant documents and deliverables for Company approval, whether or not they
are specifically mentioned within the item descriptions.

1B.1b.3 Verification and Compliance Reports

The Lump sum price for Verification and Compliance Reports shall include but not
limited to all the requirements in accordance but not limited to Clauses 9.3, 13 &
14 of Technical Specification Portion 1(A&B), including submission of any other
relevant documents and deliverables for Company approval, whether or not they
are specifically mentioned within the item descriptions.

1B.1b.4 Project Record Books and Dossiers

The Lump sum price for Project Record Books and Dossiers shall include but not
limited to all requirements and documentations in accordance but not limited to
Clauses 9, 13, 14 & 14.7 of Technical Specification Portion 1(A&B) and providing
copies as per Contract requirement, whether or not they are specifically mentioned
within the item descriptions.

1B.1b.5 Project Documentations, Deliverables and Drawings

The lump sum price for the preparation of Project Documentation, Deliverables and
Drawings (includes preparation of shop drawings, issued for construction drawings
and as built drawings as per KOC standard formats) shall include but not limited to

Page 18 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

all documentations which require Company review/pre-approval/approval and as


included in Appendix I to Contract Specification except those that are marked and
specified to be part of the corresponding BOQ line item as stated in the MoM, All
necessary associated costs in accordance but not limited to Annexes A & N, Clauses
17 (Drawings), 8, 9, 10, 13, 14 & 15 of Technical Specification Portion 1(A&B) and
providing copies as per Contract requirement, whether or not they are specifically
mentioned within the item descriptions.

General Pricing Considerations for Other Common Contract Documentations

The lump sum price shall include, but not be limited to utilization of all necessary
labour, material, computer, vehicles, equipment, software, or any other office
equipment & consumables required for the generation of technical documentation
in a professional format and manner, professional fees associated with the
development of the draft report, all printing, reproduction and binding fees
associated with generating all required copies of the reports, all professional fees
and permit fees associated with revising the reports based on review comments
provided by Company, all printing, reproduction and binding fees associated with
generating all required copies of the final reports, calculations (if any).

1B.2 ENABLING WORKS

1B.2a AIR QUALITY CHARACTERIZATION

1B.2a.a Unit of Measurement


Number (No.)

1B.2a.b Pricing

The rates for undertaking Air Quality, Source Emissions & Dust and
Meteorological Testing as per Technical Specifications Portion 1 and submission
of relevant document deliverables for Company approval in accordance but not
limited to Clauses 8, 8.5, 8.16, 13.1.2, 13.5 & 15 of Technical Specification Portion
1 and shall include but not be limited to the following:

• Utilizing of all necessary labour, constructional plant, equipment, material and


any consumables items required for collecting and delivery of samples,
software, hand tools, packaging, labelling, marking, copying, binding, testing,
calibration, obtaining gate passes & permits, clearance, taxes, providing
scaffolds and barricades;
• Return visit to Site where re-testing or further test is required;
• Rejected test results (i.e. not meeting the requirements in the Technical
Specification) shall not be paid and cost for retest, re-packing, labelling and

Page 19 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

transportation are solely Contractor’s responsibilities;


• Providing sufficient protection throughout the Contract period until issuance of
the Certificate of Completion whereupon the permanent monitoring boreholes
will be handed over to the Company;
• Field logs submission according to KOC standards;
• Familiarization and trainings of Company staff for Air Quality Characterization
which includes but not limited to testing methodologies, plans, protocol set-up,
collection, logging, procedures, use of field test kits, field operations between
site and GIS map production, and appropriate statistical measures of their
functionality in accordance with Technical Specification Portion 1(A&B).
• Submission, screening records documented in detail for air, location, test values,
all reports shall be submitted to substantiate and/or support the main test reports;
• Preparation of pre-& final reports, results, documentations and other related
reports), whether or not they are specifically mentioned within the item
description; and
• Rejecting of data or tests result based on validation and/or QA/QC analysis shall
be re-collected and analysed at no cost to the Company.

1B.2a.c Measurement

• Measurement shall be based in number(s) on the approved Air Quality, Source


Emissions & Dust and Meteorological Testing associated with approved
relevant documents and supported by an approved RFI’s;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified, adjusted and agreed during final
measurement based in all relevant approved documents.
• Rejected test results, i.e. not meeting the requirements as per Contract shall not
be paid and cost for retest including labelling and transportation etc., testing and
analysis, validation and QA/QC are solely Contractor’s responsibilities and all
costs for complying with all requirements in accordance but not limited to
Clause 11.5 of Technical Specification Portion 1(A&B), whether or not they are
specifically mentioned within the item descriptions

1B.2b SURVEY OF UTILITY SERVICES / MANUAL EXCAVATION FOR SLIT


TRENCHES

1B.2b.a Unit of Measurement


Cubic Meter (m³)

Page 20 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.2b.b Pricing

The rates for undertaking Survey of utility services / manual excavation for slit
trenches, Size 1.0m x 1.5m depth and metal detection and other associated activities
& works to be carried out and submission of relevant document deliverables in
accordance but not limited to Clauses 8.3 of Technical Specification Portion 1(A&B)
and Clauses 3.3 & 7.2.3 of Technical Specification Portion 2, shall include but not
be limited to the following:
• Utilization of all necessary labour, equipment and material, constructional plant,
photos, logging, lists of underground utilities identified, marking, backfilling,
signboard, obtaining gate passes, permits, clearance, taxes & license, hand tools,
signboard, barricades, marked up drawing showing length, coordinates, width,
depth, quality control/reviews, recording of all findings & reporting as
specified;
• The slit trenches for verification of these utilities shall be photographed and
logged by the Contractor describing soil strata encountered, logging to British
Standard BS5930:2015;
• All materials from excavation shall be placed/stockpile near the vicinity of
excavation and provide an approved safety measures during pre/post excavation
of slit trenches;
• Ground re-statement from its original surrounding/situations as per Company
representative satisfaction;
• Control over excavation of trenches; depth/width more than specified in the
Contract, Contractor shall inform the Company through correspondence prior
to commence the works;
• Backfilling and/or restoration of excavated areas and making good the
surrounding to its natural conditions;
• Preparation and submission of plans methodology, procedures, proposal to
monitor the width/depth of excavation, RFI’s and drawings/marked up drawings
to carry-out the cited activities and all costs for complying with all relevant
requirements contained in Contract documents, whether or not they are
specifically mentioned within the item descriptions.

1B.2b.c Measurement

• Measurement shall be based in the approved executed quantities in cubic meter


(m³) supported by an approved RFI’s, photos and marked up drawings showing
the coordinates, width, length, location, grids and/or any approved relevant
documents;
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved

Page 21 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

documents in accordance with the requirements of technical specifications;


• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2c POST–TOPOGRAPHIC SURVEY

1B.2c.a Unit of Measurement


Square Meter (m²)

1B.2c.b Pricing

The rates for undertaking Post-Topographic Survey works, other associated


activities and submission of relevant document (i.e. approved RFI’s, etc.),
deliverables in accordance but not limited to Clauses 1.2, 7.4, 8, 8.3 & 8.4 of
Technical Specification Portion 1(A&B) and Clause 3.0 of Technical Specification
Portion 2, shall include but not be limited to the following:

• Utilizing of all necessary labour, equipment and material, vehicles, software


(shape files, AutoCAD & DXF), calibration/upgrading of equipment’s, photos,
logging, JSA, monuments/benchmarks, lay outing, pre/post topographic survey
(not mentioned in other BOQ items), Constructional Plant, obtaining Clearance,
Gate Passes, license, taxes & Permits;
• Preparation of post/ final reports (survey control reports and other related
reports);
• Providing confirmation of boundaries among features and clean ground and
boundary of Oil Lakes, Contaminated Soil Piles (OCP) and/or tarcrete;
• Provide lists of underground and above ground facilities/obstructions identified
during survey;
• Survey of plant facilities with relevance to the treatment areas, disposal areas,
stockpiling areas and storage areas;
• Provision of any relevant associated works that are not listed and/or included in
the BOQ requiring topographic survey works;
• Providing updated drawings for approval with new boundaries after further
post-topographic survey and all costs for complying with all relevant
requirements in accordance with Clause 8 of Technical Specification Portion
1(A&B), whether or not they are specifically mentioned within the item
description;
• Related works to update approved documents, drawings based on changes in
boundary conditions.
• Verification of post excavation elevations across the areas designated for
excavations project activities;
• Post work elevations across the areas designated for other project activities
(features, treatment areas, lay-down areas, landfill areas, any location as
required in the Contract);

Page 22 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Survey works in monitoring wells steel casing elevation and piezometer;

1B.2c.c Measurement

• Measurement shall be based in approved Post-Topographic Survey Report


completed net areas in square meters (m²) with corresponding volume in m3 &
associated with approved relevant documents and supported by an approved
final RFI’s and marked up drawings showing acquired data in the site, extent,
elevations, boundaries & limit of features;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified, adjusted and agreed during final
measurement based in all relevant approved documents.

1B.2d BASELINE NATURALLY OCCURRING RADIOACTIVE MATERIALS


(NORM) SURVEY

1B.2d.1 Conduct baseline Naturally Occurring Radioactive Materials (NORM) Survey in


accordance with Contract Requirements

1B.2d.1a Unit of Measurement


Number (No.)

1B.2d.1b Pricing

The rate for undertaking baseline Naturally Occurring Radioactive Materials


(NORM) Survey in accordance with Contract Requirements, other associated
activities and submission of relevant document deliverables in accordance but not
limited to Clauses 1.2, 7, 8, 8.5.2, 9 & 13 of Technical Specification Portion 1(A&B)
& KOC.HE.024 and shall include but not be limited to the following:
• Utilizing of all necessary labour, equipment, instrument(s), calibration of
instrument(s), vehicles, software(s), risk assessment, procedures, chain of
custody, obtaining gate passes & permits, clearance, taxes, providing scaffolds
and barricades;
• Providing certified Radiation Safety Technician (RST) and Radiation Safety
Officer (RSO) will complete a non-intrusive radiological survey of the areas to
be excavated to identify NORM;
• Preparing Pre-Field Work Reporting Requirements for Company approval;
• Conducting NORMS within the potential excavation areas and/or treatment
areas for the identified pipes, metal and other hazardous or non-hazardous
materials, whether or not they are specifically mentioned within the item
description;
• Resurvey of areas suspected by NORMS based on validation and/or QA/QC

Page 23 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

data (e.g. rejection of data) shall be collected and analysed at no cost to the
Company.

1B.2d.1c Measurement

• Measurement shall be based in number(s) (i.e. 1 Number is equal to 25m x 25m)


on the approved NORM survey reports associated with approved relevant
documents and supported by an approved RFI’s;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.
• Rejected survey reports, i.e. not meeting the requirements as per Contract shall
not be paid and cost for re-survey/reports including re-excavation/drilling,
sample collection, re-packing, labelling and transportation etc., testing and
analysis, validation and QA/QC are solely Contractor’s responsibilities and all
costs for complying with all requirements contained in Clause 11.5 of Technical
Specification Portion 1(A&B), whether or not they are specifically mentioned
within the item descriptions.
• In the event, number of NORMS are not equal to the define dimensions size the
payment shall be calculated on pro-rata basis of the unit rate of respective
Number as above.
• The NORM of work requires a grid of 25 m x 25 m (1 unit), with a survey
density of minimum one reading per grid. Where it existed, liquid phase
material in the feature reduced the area of walkover survey; and interfered with
the regularity of the grid pattern.
• To calculate the area of walkover survey, it is asserted that once a grid is
established, the vector sum of the displacements of all individual survey points
tends to zero, with respect to an offset from a perfect grid pattern. In other
words, a single reading cannot be judged as noncompliant by virtue of its
position; readings can only be considered on the merits of the whole
distribution. Each 25 m x 25 m grid square should contain at least one
radiological survey reading, such that grid-square can be considered covered by
radiological walkover survey.

1B.2d.2 Conduct Asbestos Materials Testing and Survey in accordance with Contract
Requirements

1B.2d.2a Unit of Measurement


Number (No.)

1B.2d.2b Pricing

Page 24 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

The rate for undertaking Asbestos Materials Testing and Survey in accordance with
Contract Requirements, other associated activities and submission of relevant
document deliverables in accordance but not limited to Clauses 1.2, 7, 8, 8.5.2, 9 &
13 of Technical Specification Portion 1(A&B) & KOC.HE.005 and shall include but
not be limited to the following:

• Utilizing of all necessary labour, equipment, instrument(s), calibration of


instrument(s), vehicles, software(s), risk assessment, procedures, chain of
custody, obtaining gate passes & permits, clearance, taxes, providing scaffolds
and barricades;
• Providing Work Plans, Method of Statements, Reports, deliverables and other
necessary required documents as per Contract requirements;
• Preparing Pre-Field Work Reporting Requirements for Company approval;
• Providing all required training and certification for the involved personnel;
• Based on asbestos testing survey, provide procedures for addressing asbestos
material removal in accordance with all the requirement listed under
KOC.HE.005

1B.2d.2c Measurement

• Measurement shall be based in number(s) on the approved asbestos material


testing and survey reports, associated with approved relevant documents and
supported by an approved RFI’s;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.
• Rejected testing, results, survey and reports, i.e. not meeting the requirements
as per Contract shall not be paid and cost for retest including re-
excavation/drilling, sample collection, re-packing, labelling and transportation
etc., testing and analysis, validation and QA/QC are solely Contractor’s
responsibilities and all costs for complying with all requirements contained in
Clause 11.5 of Technical Specification Portion 1(A&B), whether or not they are
specifically mentioned within the item descriptions.

1B.2e GROUNDWATER CHARACTERIZATION

1B.2e Existing Groundwater Monitoring Well Assessment (per Well)


1B.2e.a Unit of Measurement
Number (No.) per well

1B.2e.b Pricing

Page 25 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

The rate for undertaking groundwater characterization for each existing


groundwater monitoring well (per well) to carry out assessment other associated
activities and submission of relevant document deliverables in accordance but not
limited to Clauses 8, 8.5, 8.5.3 & 15 of Technical Specification Portion 1(A&B) shall
include but not be limited to the following:

• Utilizing of all necessary labour, material, equipment, constructional plant,


obtaining gate passes & permits, clearance, taxes, packaging, marking,
software(s), photos, hydraulic equipment & accessories, calibration, water, well
condition/operable, scaffolds, barricades, protections, coordination and all
consumables items used during the measurement of water and free oil product
elevations.
• Conducting hydraulic permeability test to acquire hydrogeological and
hydraulic information about the groundwater formation;
• Maintaining the good seal around and the well surrounding in good conditions
(i.e. sealing the top casing ensuring integrity of backfill around the monitoring
well casing to prevent infiltration of surface water into the annulus of the
borehole) during sampling or testing;
• Log sheets (field), screen parameters of the well and ground monitoring wells.

1B.2e.c Measurement

• Measurement shall be based in number(s) on the approved assessment


monitoring wells inclusive of reports, documents and/or any approved relevant
documents and supported by an approved RFI’s;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with
all requirements contained in Clause 11.5 of Technical Specification Portion
1(A&B), whether or not they are specifically mentioned within the item
descriptions

1B.2f MONITORING WELL AND PIEZOMETER INSTALLATIONS

1B.2f.1 Drilling, Install, Sampling, Well Sealing and Decommissioning of Boreholes (up to
15 m)

Page 26 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.2f.1a Unit of Measurement


Number (No.)

1B.2f.1b Pricing

The rates for undertaking Drilling, Installation, Sampling and Abandonment of


Boreholes (up to 15m) per location, other associated activities and submission of
relevant document deliverables in accordance but not limited to Clauses 8, 8.5, 8.5.3
& 15 of Technical Specification Portion 1(A&B) shall include but not be limited to
the following:

• Utilizing of all necessary labour, equipment and material, Constructional Plant,


obtaining gate passes & permits, clearance, taxes, any consumables items
required for drilling (i.e. hard & soft drilling) of a suitable monitoring well,
scaffolds, barricades and coordination;
• Disposal of any contaminated materials arising during drilling to the treatment
soils;
• Any required in-situ testing;
• Relocation costs associated with the movement of drilling equipment between
monitoring well drilling locations;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Supply of all associated materials and install;
• Sampling, maintain, decommissioning, abandonment, assessment and purging
(if required) of well or borehole;
• Monitoring and handover of well or borehole with a various completion depth
below surface levels;
• Any consumables items required for installation and sample collections,
permeability testing and well development, clean up, backfilling and making
good the surrounding as per Company representative satisfaction and approval;
• Borehole soil sampling and plugged in accordance with Contract requirements;
• Survey of borehole soil sampling or well;
• Abandonment and plugged of monitoring well and piezometer boreholes, if
groundwater is not encountered for both monitoring well boreholes &
piezometer boreholes below ground surfaces, and making good the surrounding
as per Company representative satisfaction and approval;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation, sample collection,
re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;

Page 27 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.2f.1c Measurement

• Measurement shall be based in number(s) as per the approved completion


depth(s) executed and supported by an approved RFI’s and/or any approved
relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2f.2 Design, Drilling, Supply, Survey top of steel casing & PVC, Install, Sampling,
Maintenance of Shallow Monitoring Wells (up to 15 m)

1B.2f.2a Unit of Measurement


Number (No.)

1B.2f.2b Pricing

The rate for undertaking Design, Drilling, Supply, Survey top of steel casing &
PVC, Install, Sampling, Maintenance of Shallow Monitoring Wells (up to 15m),
other associated activities & works to be carried out and submission of relevant
document deliverables in accordance but not limited to Clauses 8, 8.5 & 8.5.3 of
Technical Specification Portion 1(A&B) shall include but not be limited to the
following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


obtaining gate passes & permits, clearance, taxes, any consumables items
required for preparing WMS drilling (i.e. hard & soft drilling) of a suitable
monitoring well, scaffolds, barricades and coordination;
• Designing the monitoring wells to allow for sufficient volumes of water,
drilling, supply of all associated materials and sampling activities for both
monitoring wells and piezometer boreholes;
• Disposal of any contaminated materials arising during drilling;
• Any required in-situ testing to estimate the hydraulic and hydrogeological
conditions of the subsurface material;
• Conduct topographic survey as necessary to maintain the top level of steel

Page 28 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

casing & PVC;


• Maintain the wells in a good condition and operable within the whole duration
of the Contract as necessary;
• Relocation costs associated with the movement of drilling equipment between
monitoring wells drilling locations;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Sampling, maintain, decommissioning, assessment and purging (if required) of
wells;
• Monitoring and handover of wells with a various completion depth below
surface levels;
• Any consumables items required for installation and sample collections,
permeability testing and well development, clean up, backfilling and making
good the surrounding as per Company representative satisfaction and approval;
• Borehole soil sampling and plugged in accordance with Contract requirements;
• Abandonment and plugged of monitoring well and piezometer boreholes, if
groundwater is not encountered by 15m for monitoring well boreholes & 3m for
piezometer boreholes below ground surfaces, and making good the surrounding
as per Company representative satisfaction and approval;
• Return visit to Site where re-sampling or further sampling is required such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation, sample collection,
re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;

1B.2f.2c Measurement

• Measurement shall be based in number(s) as per the approved completion


depth(s) executed and supported by an approved RFI’s and/or any approved
relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2f.3 Design, Drilling, Supply, Survey top of steel casing & PVC, Install, Sampling,
Maintenance of Deep Monitoring Wells (up to 70 m)

Page 29 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.2f.3a Unit of Measurement


Number (No.)
1B.2f.3b Pricing

The rates for undertaking Design, Drilling, Supply, Survey top of steel casing &
PVC, Install, Sampling, Maintenance of Deep Monitoring Wells (up to 70 m), other
associated activities & works to be carried out and submission of relevant document
deliverables in accordance but not limited to Clauses 8, 8.5 & 8.5.3 of Technical
Specification Portion 1(A&B) shall include but not be limited to the following:
• Utilizing of all necessary labour, equipment and material, constructional plant,
obtaining gate passes & permits, clearance, taxes, any consumables items
required for drilling (i.e. hard & soft drilling) of a suitable monitoring well,
scaffolds, barricades and coordination;
• Designing the monitoring wells to allow for sufficient volumes of water,
drilling, supply of all associated materials and sampling activities for both
monitoring wells and piezometer boreholes;
• Disposal of any contaminated materials arising during drilling;
• Any required in-situ testing;
• Conduct topographic survey as necessary to maintain the top level of steel
casing & PVC;
• Maintain the wells in a good condition and operable within the whole duration
of the Contract as necessary;
• Relocation costs associated with the movement of drilling equipment between
monitoring wells drilling locations;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Sampling, maintain, decommissioning, assessment and purging (if required) of
wells;
• Monitoring and handover of wells with a various completion depth below
surface levels;
• Any consumables items required for installation and sample collections,
permeability testing and well development, clean up, backfilling and making
good the surrounding as per Company representative satisfaction and approval;
• Borehole soil sampling and plugged in accordance with Contract requirements;
• Abandonment and plugged of monitoring well and piezometer boreholes, if
groundwater is not encountered by 15m for monitoring well boreholes & 5m for
piezometer boreholes below ground surfaces, and making good the surrounding
as per Company representative satisfaction and approval;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation, sample collection,
re-packing, labelling and transportation etc. are solely Contractor’s

Page 30 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

responsibilities, whether or not they are specifically mentioned within the item
description;

1B.2f.3c Measurement

• Measurement shall be based in number(s) as per the approved completion


depth(s) executed and supported by an approved RFI’s and/or any approved
relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2f.4 Design, Drilling, Supply, Survey top of steel casing, Install, Sampling, Maintenance
of Piezometers (up to 3m below ground)

1B.2f.4a Unit of Measurement


Number (No.)

1B.2f.4b Pricing

The rate for undertaking Design, Drilling, Supply, Survey top of steel casing/or
PVC, Install, Sampling, Maintenance of Piezometers (up to 3m below ground),
other associated activities and submission of relevant document deliverables in
accordance but not limited to Clauses 8, 8.5 & 8.5.3 of Technical Specification
Portion 1(A&B) shall include but not be limited to the following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


obtaining gate passes & permits, clearance, taxes, any consumables items
required for drilling (i.e. hard & soft drilling) of a suitable monitoring well,
scaffolds, barricades and coordination;
• Designing the piezometers to allow for sufficient volumes of water, drilling,
supply of all associated materials and sampling activities for both piezometer
boreholes;
• Disposal of any contaminated materials arising during drilling;
• Any required in-situ testing to obtain the hydraulic and hydrogeological specific
conditions of the subsurface material;
• Conduct topographic survey as necessary to maintain the top level of steel
casing & PVC;
Page 31 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Maintain the piezometer in a good condition and operable within the whole
duration of the Contract as necessary;
• Relocation costs associated with the movement of drilling equipment between
piezometer drilling locations;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Sampling, maintain, decommissioning, assessment and purging (if required) of
piezometers;
• Monitoring and handover of piezometers with a various completion depth below
surface levels;
• Any consumables items required for installation and sample collections,
permeability testing and piezometer development, clean up, backfilling and
making good the surrounding as per Company representative satisfaction and
approval;
• Borehole soil sampling and plugged in accordance with Contract requirements;
• Abandonment and plugged of piezometer boreholes, if groundwater is not
encountered by 3m for monitoring well boreholes & 5m for piezometer
boreholes below ground surfaces, and making good the surrounding as per
Company representative satisfaction and approval;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation, sample collection,
re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;
1B.2f.4c Measurement

• Measurement shall be based in number(s) on the approved completion depth(s)


executed and supported by an approved RFI’s and/or any approved relevant
documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2f.5 Well Sealing and Decommissioning of Shallow groundwater Monitoring well (up
to 15 m)

1B.2f.5a Unit of Measurement

Page 32 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

Number (No.)

1B.2f.5b Pricing

The rate(s) for undertaking Well Sealing and Decommissioning of Shallow


groundwater Monitoring well (up to 15 m), other associated activities and
submission of relevant document deliverables in accordance but not limited to
Clauses 8, 8.5, 8.5.3 & 8.5.3.3(L) of Technical Specification Portion 1(A&B) shall
include but not be limited to the following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


obtaining gate passes & permits, clearance, taxes, any consumables items
required for abandonment of wells, scaffolds, barricades and coordination;
• Abandonment and plugged of monitoring well and piezometer boreholes, if
groundwater is not encountered and making good the surrounding as per
Company representative satisfaction and approval;
• Disposal of any contaminated materials arising during drilling and/or plugging
of well;
• Any required in-situ testing;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Sampling, maintain, decommissioning, assessment and purging (if required) of
wells;
• Monitoring and handover of wells with a various completion depth below
surface levels;
• Any consumables items required for abandonment, installation and sample
collections, permeability testing and well development, clean up, backfilling
and making good the surrounding as per Company representative satisfaction
and approval;
• Borehole soil sampling and plugged in accordance with Contract requirements;
• Return visit to Site where the abandonment is failure and/or occurring problems
affecting the surrounding or further re-work is required (such as replacement,
lost/destroyed of plugged, protections & barricades) are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;

1B.2f.5c Measurement

• Measurement shall be based in number(s) on the approved reports and


supported by an approved RFI’s and/or any approved relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-

Page 33 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

measurement calculation sheets (RMCS) referring to the relevant approved


documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2f.6 Well Sealing and Decommissioning of Deep groundwater Monitoring well (up to
70 m)

1B.2f.6a Unit of Measurement


Number (No.)

1B.2f.6b Pricing

The rate(s) for undertaking Well Sealing and Decommissioning of Deep


groundwater Monitoring well (up to 70 m), other associated activities & works
required to be carried out and submission of relevant document deliverables in
accordance but not limited to Clauses 8, 8.5, 8.5.3 of Technical Specification
Portion 1(A&B) shall include but not be limited to the following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


obtaining gate passes & permits, clearance, taxes, any consumables items
required for abandonment of wells, scaffolds, barricades and coordination;
• Abandonment and plugged of monitoring well and piezometer boreholes, if
groundwater is not encountered at a certain depth below existing surface ground
level, and making good the surrounding as per Company representative
satisfaction and approval;
• Disposal of any contaminated materials arising during drilling and/or plugging
of well;
• Any required in-situ testing;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Sampling, maintain, decommissioning, assessment and purging (if required) of
wells;
• Monitoring and handover of wells piezometer with a various completion depth
below surface levels;
• Any consumables items required for abandonment, installation and sample
collections, permeability testing and well development, clean up, backfilling
and making good the surrounding as per Company representative satisfaction
and approval;
• Borehole soil sampling and plugged in accordance with Contract requirements;
• Return visit to Site where the abandonment is failure and/or occurring problems
affecting the surrounding or further re-work is required (such as replacement,
lost/destroyed of plugged, protections & barricades) are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item

Page 34 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

description;

1B.2f.6c Measurement

• Measurement shall be based in number(s) as per the approved reports and


supported by an approved RFI’s and/or any approved relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2f.7 Well Sealing and Decommissioning of Piezometers (up to 3m below ground)

1B.2f.7a Unit of Measurement


Number (No.)

1B.2f.7b Pricing

The rate(s) for undertaking Well Sealing and Decommissioning of Piezometers (up
to 3m below ground), other associated activities & necessary works required to be
carried out and submission of relevant document deliverables in accordance but not
limited to Clauses 8, 8.5, 8.5.3 & 8.5.3.3(L) of Technical Specification Portion
1(A&B) shall include but not be limited to the following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


obtaining gate passes & permits, clearance, taxes, any consumables items
required for abandonment of wells, scaffolds, barricades and coordination;
• Abandonment and plugged of monitoring well and piezometer boreholes, if
groundwater is not encountered at a certain depth below ground surface level,
and making good the surrounding as per Company representative satisfaction
and approval;
• Disposal of any contaminated materials arising during drilling and/or plugging
well or piezometer;
• Any required in-situ testing;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Sampling, maintain, decommissioning, assessment and purging (if required) of
wells;
• Monitoring and handover of and piezometer with a various completion depth

Page 35 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

below surface levels;


• Any consumables items required for abandonment, installation and sample
collections, permeability testing and well development, clean up, backfilling
and making good the surrounding as per Company representative satisfaction
and approval;
• Borehole soil sampling and plugged in accordance with Contract requirements;
• Return visit to Site where the abandonment is failure and/or occurring problems
affecting the surrounding or further re-work is required (such as replacement,
lost/destroyed of plugged, protections & barricades) are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;

1B.2f.7c Measurement

• Measurement shall be based in number(s) on the approved reports and


supported by an approved RFI’s and/or any approved relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.2g GROUNDWATER, SURFACE WATER & LEACHATE SAMPLING,


ANALYSIS, MONITORING, DATA MANAGEMENT AND PIEZOMETER

1B.2g Sampling and analysis of Groundwater Monitoring Wells, Water Supply, Surface
Water with a various completion depth below surface levels & Data Management

1B.2g.a Unit of Measurement


Number (No.)

1B.2g.b Pricing

The rate for undertaking Sampling and analysis of Groundwater Monitoring Wells,
Water Supply, surface water with a various completion depth below surface levels
& Data Management, other associated activities & necessary works required to be
carried out and submission of relevant document deliverables in accordance but
not limited to Clauses 8, 8.5, 8.5.3 & 15 of Technical Specification Portion 1(A&B)
shall include but not be limited to the following:

• Utilizing of all necessary labour, pumping equipment and material,


constructional plant, obtaining gate passes & permits, clearance, taxes,
Page 36 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

approved sample container (i.e. plastic or glass jar), dry ice chest, labelling,
marking, any consumables items required for Sampling & analysis, barricades
and coordination;
• Conduct the following analysis and activities: Field logs, water screening per
water records, duplicate samples for QA/QC, Sample Analysis with various
parameters, Analytical Test, Sample identification, EGIS and EQuIS
formattable data, Chain of Custody, Arising, Sampling QA/QC, Trip Blanks,
Field & Equipment Rinse Blanks, Blind Duplicates and Certified Reference
Sample;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation (if required), sample
collection, re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;
• Rejecting of data sample result based on validation and/or QA/QC shall be re-
collected and analysed at no cost to the Company

1B.2g.c Measurement

• Measurement shall be based in number(s) on the approved Sampling and


Analysis Reports as executed and supported by an approved RFI’s and/or any
approved relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with
all requirements contained in Clause 11.5 of Technical Specification Portion
1(A&B), whether or not they are specifically mentioned within the item
descriptions.
1B.3 GENERAL WORKS

1B.3a ACCESS ROAD & CRASH BARRIERS

Page 37 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.3a.1 ACCESS ROAD

1B.3a.1a Construct and Maintain New Access Roads

1B.3a.1a.a Unit of Measurement


Square Meter (m²)

1B.3a.1a.b Pricing

The rates for constructing and maintaining new access roads, other associated
activities & works required to be carried out and submission of relevant document
deliverables in accordance with requirement of Clauses 8.9, 8.11 & 8.12
Technical Specifications Portion 1(A&B) shall include but not be limited to the
following:

• Utilization of all necessary labour, materials (includes procurement,


transportation, any costs to provide required material to complete the works),
Constructional Plant, storage, surface water drainage, regulatory & directional
signs, detour, locating/re-locating & protection existing services in the line of
access roads.;
• Any consumables items, obtaining gate passes & permits, clearance, taxes,
barricades, disposal of any contaminated arisings and any required in-situ
testing;
• Any Transportation and/or loading of materials from its current position to the
designated areas;
• Carry out necessary survey, road protection, cleaning, and traffic management
plan;
• Supply, transport, and backfill with approved suitable backfilling materials
(imported fill) and collecting, stockpiling;
• Relocation costs associated with the movement of equipment between working
areas, quality control/reviews of data processing & analysis and all costs for
complying with all relevant requirements contained in Technical Specifications;
• Supply, spraying (if necessary) and storage of water required for construction
and maintenance;
• Approval of the design drawings & compaction requirements as per KOC
standard;
• Protection of flowline crossing points for vehicular access in accordance with
KOC.SA.015 “Breaking of Flanges & Bolting Replacement/ Rework on
Pipework”, KOC.SA.017 “Procedure for Clamping of Piping and Pipelines” and
other relevant procedures
• Separate construction debris and other waste materials for further storage or
disposal;
• Upgrade, maintain compact as per approved compaction degree and repair (i.e.

Page 38 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

as required) throughout the Contract period to safely utilized the transportation


activities without interruption to KOC operations, to make the road in good
shape for transportation and meet the project objectives, whether or not they are
specifically mentioned within the item descriptions.

1B.3a.1a.c Measurement

• Measurement shall be based in net areas in square meters (m²) on the approved
actual executed works and supported by an approved RFI’s and/or any approved
relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (in RMCS the percentage for item 1B.2.1
Supply & Construct is approximately 70% while Maintenance is approximately
30% of the total costs) referring to the relevant approved documents in
accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.3a.1b Maintain Existing Access Roads


1B.3a.1b.a Unit of Measurement
Square Meter (m²)

1B.3a.1b.b Pricing

The rates for maintaining existing access roads, other associated activities &
works required to be carried out and submission of relevant document deliverables
in accordance with requirement of clauses 4.2.2, 4.3.2, 8.9, 8.11 & 8.12 of
Technical Specifications Portion 1(A&B) shall include but not be limited to the
following:

• Utilization of all necessary labour, materials (includes procurement,


transportation, any costs to provide required material to complete the works),
Constructional Plant, storage, surface water drainage, regulatory & directional
signs, detour, locating/re-locating & protection existing services in the line of
access roads.;
• Any consumables items, obtaining gate passes & permits, clearance, taxes,
barricades, disposal of any contaminated arisings and any required in-situ
testing;
• Any Transportation and/or loading of materials from its current position to the
designated areas;
• Carry out necessary survey, road protection, cleaning, and traffic management

Page 39 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

plan;
• Upgrade, supply, transport, backfill and compact as per approved compaction
degree and with approved suitable backfilling materials (imported fill) and
collecting, stockpiling;
• Relocation costs associated with the movement of equipment between working
areas, quality control/reviews of data processing & analysis and all costs for
complying with all relevant requirements contained in Technical Specifications;
• Supply, spraying (if necessary) and storage of water required for construction
and maintenance;
• Protection of flowline crossing points for vehicular access in accordance with
KOC.SA.015 “Breaking of Flanges & Bolting Replacement/ Rework on
Pipework”, KOC.SA.017 “Procedure for Clamping of Piping and Pipelines” and
other relevant procedures
• Separate construction debris and other waste materials for further storage or
disposal
• Approval of the design compaction as per KOC standard and approval of
submitted documents for the Works;
• Upgrade, maintain compact as per approved compaction degree and repair (i.e.
as required) throughout the Contract period to safely utilized the transportation
activities without interruption to KOC operations, to make the road in good
shape for transportation and meet the project objectives, whether or not they are
specifically mentioned within the item descriptions.

1B.3a.1b.c Measurement

• Measurement shall be based in net areas in square meters (m²) on the approved
actual executed works and supported by an approved RFI’s and/or any approved
relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (in RMCS the percentage for item 1B.2.2
Upgrade, Supply & Construct is 60% while Maintenance is 40% of the total
costs)) referring to the relevant approved documents in accordance with the
requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.3a.2 CRASH BARRIERS

1B.3a.2 Protective Measures: Supply, Fabricate and Install Concrete Crash Barriers /
Crossing Ramps

Page 40 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

1B.3a.2a Unit of Measurement


Number (No.)

1B.3a.2b Pricing

The rates for undertaking Protective Measures: Supply, Fabricate and Install
Concrete Crash Barriers / Crossing Ramps, other associated activities & works
required to be carried out and submission of relevant document deliverables for
Company approval shall be in accordance with the requirement of Clause 8.9 of
Technical Specifications Portion 1(A&B) shall include but not be limited to the
following:

• Utilization of all necessary labour, Constructional plants, obtaining gate passes,


permits, clearance, taxes & license and/or any required documents;
• All associated Cost to prepare purchase order;
• Supply of water, materials requisition, taxes, shipping, delivery (from source to
site, vice versa);
• Warehousing, any necessary documents required by Contract terms and
conditions;
• Supply all materials, fabricate and install crash barriers and construct crossing
ramps where the haul road runs adjacent to sensitive plant, utilities, equipment
and infrastructure and/or Contractor proposed location and approved by
Company. This largely applies to the areas within the oilfield or utilities
crossing;
• The barriers & crossing ramps shall be established in accordance with KOC
standard/drawings;
• All associated civil works (i.e. excavation, layout, reinforcement, concreting,
formworks, painting, supply of water, etc.) to complete the works, submission
of relevant drawings proposal and specification of crash barriers to be used and
submit to Company prior to commence the works;
• Preparation of plans methodology, procedure to carry the cited activities,
relocation costs associated with the movement of equipment between working
areas;
• Protection of flowline crossing points for vehicular access in accordance with
KOC.SA.015 “Breaking of Flanges & Bolting Replacement/ Rework on
Pipework”, KOC.SA.017 “Procedure for Clamping of Piping and Pipelines” and
other relevant procedures
• Quality control/reviews of data processing & analysis and all costs for
complying with all relevant requirements in accordance but not limited to
Clause 8.9 of Technical Specification Portion 1(A&B), whether or not they are
specifically mentioned within the item descriptions.

1B.3a.2c Measurement

Page 41 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Measurement shall be based in net quantities in number (No.) on the approved


actual executed works/length and supported by an approved RFI’s and/or any
approved relevant documents;
• Any measurements and calculations method proposed by the Contractor and
approved by Company representative and any required relevant approved
documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets which is referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

1B.3b NORMS, IDENTIFIED ASBESTOS AND HAZARDOUS WASTES


MATERIALS

1B.3b.1 REMOVAL/CONTAINERIZE AND STORAGE OF NORMS, IDENTIFIED


ASBESTOS AND HAZARDOUS WASTES MATERIALS
(Remove, Segregate; Containerize (as necessary), temporarily store to designated
areas all asbestos, norms and hazardous materials in accordance with the Company
approvals as described in Technical Specification Portion 1 A&B)).

1B.3b.2 PROVISION OF LOADING AND TRANSPORTATION OF NORM and


HAZARDOUS MATERIALS
(Load and Transport and Dispose all NORM, Asbestos and Hazardous containing
materials in accordance with the Company approvals as described in Technical
Specification Part I to the Company designated facilities or areas).

1B.3b.a Unit of Measurement


Tonnes

1B. 3b.b Pricing

The rates for undertaking Provision of removal/containerize and storage of norms,


identified asbestos and hazardous wastes materials, loading and transportation of
norms, asbestos and hazardous materials as directed by company in accordance with
company waste handling procedures (i.e. located/found at Dry Oil Lakes and Wet
Oil Lakes), other associated activities/ other necessary works required to be carried
out and submission of relevant document deliverables in accordance but not limited
to the requirement of Clauses 1.2, 7.5, 7.5.2, 7.5.3 & 13.1.2 of Technical
Specifications Portion 1(A&B) shall include but not be limited to the following:

• Utilization of all necessary labour, Constructional Plant, providing approved


storage/container (if required), photos, lists, weightages of all debris,
stockpiling, excavation, packaging, collection, storage, providing storage,
Page 42 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

marker, signboard, collecting, warning device, transportation, protection during


loading & transportation, calibration and standardizations of the required
equipment (if required), coordination to others, obtaining gate passes, permits,
clearance, taxes & license, storage, marked up drawing, quality control/reviews,
recording of all findings & reporting as specified;
• Perform NORM and asbestos testing at the site as per KOC.HE.024 for metallic
wastes (scrap metal etc.), redundant pipes, foundations, valves, fittings, brackets
and/or any materials that are subject for NORM testing;
• Material with NORM contamination and asbestos will be collected, handled
based on KOC procedure and regulations and temporary stored in designated
areas and later transported by the Contractor’s to final NORM handling area as
per Company directives;
• Removal from excavated materials & excavation areas, certification/inspection,
storage & disposal as inactive waste of munition & non-munition debris;
• Solid Materials shall be handled, cleaned (as necessary), temporarily stored,
loaded and transported in accordance with Company solid waste procedures
(KOC.EV.008 - Waste Management Procedure) including transportation and
off-loading at the approved Company South Kuwait scrap metal facility;
• Providing any special methods, process, platforms and/or equipment in
conducting the cited activities in wet oil lakes;
• Duty of care and chains of custody shall be used for waste disposal and
submission of Chain of custody documentation & other relevant documents;
• Any redundant pipelines (i.e. buried or above ground) more than 5m long shall
be coordinated to Company prior to execute the cited activities;
• Non-munitions debris after inspection and verification as FFE shall be disposed
as inactive waste in accordance with the provisions of the Contract;
• Prepare and submit plans methodology, procedures, proposal to monitor and/or
measured the metallic & construction debris, RFI’s and drawings to carry-out
the cited activities and all costs for complying with all relevant requirements
contained in Contract documents, whether or not they are specifically
mentioned within the item descriptions.

1B. 3b.c Measurement

• Measurement shall be based on the approved executed quantities in tonnes and


supported by an approved RFI’s, weights certifications (i.e. weighbridge
reading and/or similar), lists/weights of materials & photos, marked up
drawings showing the coordinates, location, grids and/or any approved relevant
documents;
• All materials shall be placed into trucks and weighed at the weighbridge prior
to transportation for offloading of materials at the designated KOC facilities.
Duty of care and chains of custody shall be used for waste disposal;
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per

Page 43 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.
• Providing signed waste management manifest.

1B.3b.3 SOIL SAMPLE COLLECTION, ANALYSIS AND DATA MANAGEMENT


for Technical Specification Portion 1(A&B), II, III and IV Works

1B.3b.3a Supply, Operates and maintain Field Screening Instrument for the rapid
measurement of TPH in Soil including insurance, calibration, spare parts, etc.

The lump sum price to Supply, Operates and maintain Field Screening Instrument
for the rapid measurement of TPH in Soil including insurance, calibration, spare
parts and - undertake soil sample collection, analysis and data management; for
Technical Specification Portion 1(A&B), 2, 3 & 4 Works shall include, but not be
limited to, utilization of all necessary labour, equipment, material, computer,
software, insurances, transportation, preparation/submission of testing, reports,
results & procedures, office materials, providing equipment(s) and necessary
materials, calibration & standardization, scanning, procurement, taxes, permits,
analysing, editing, copying, container, labelling, marking, re-test, re-visiting at site
for soil sample collection, analysis, evaluation, processing, duplications, related
reporting & documentation and all associated costs for complying in accordance
with all the requirements in Clauses 8.5 & 15 of Technical Specification Portion
1(A&B).

1B.3b.3b Supply to the Company Field Screening Instrument for the rapid measurement of
TPH in Soil including insurance, calibration, spare parts, etc.

The lump sum price to Supply to the Company Field Screening Instrument for the
rapid measurement of TPH in Soil including insurance, calibration, spare parts,
provision of necessary certification, custom Clearance, duties, taxes, etc. in
accordance with Technical Specification Portion 1(A&B), 2, 3 & 4 Works.

PORTION 2 – SITE WORKS: EXCAVATION & TRANSPORTATION WORKS (RE-


MEASURABLE)

2.1 COMPLIANCE SOIL SAMPLES MONITORING


2.1a Unit of Measurement
Each (ea.)

Page 44 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

2.1b Pricing

The rate for undertaking compliance soil samples monitoring (Post Excavation Soil
Collection & Laboratory for Base of Excavation as per Technical Specification
Portion 1(A&B)), other associated activities/other necessary works required to be
carried out and submission of relevant document deliverables in accordance but not
limited to Clauses 4 & 7.3 of Technical Specification Portion 2, shall include but
not be limited to the following:

• Utilizing of all necessary labour, equipment and material, vehicles, software,


data, chemicals, instrument (i.e. calibration & upgrading), all testing fees,
providing test results in any formats, EQuIS formatted and verified data,
container, labelling, marking, storage, photos, logging, packaging, obtaining
Clearance, Gate Passes, license, taxes & Permits;
• Preparation of pre-& final reports (i.e. test result, analysis & lab results);
• Storage of samples in a controlled manner;
• All reproduction fees associated with duplication of certificates of analysis for
submittal;
• All quality control duplicates, all field and laboratory blanks/spikes, certified
reference materials and all other necessary consumables and documentation to
verify quality;
• Transporting the samples to the approved testing facility/facilities, all
international shipping fees associated with shipment or transport of the samples
to the approved testing facility/facilities including import / export duties &
handling charges;
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with
all requirements contained in Clause 11.5 of Technical Specification Portion
1(A&B), whether or not they are specifically mentioned within the item
descriptions.
• Rejecting of data sample result based on validation and/or QA/QC shall be re-
collected and analysed at no cost to the Company.

2.1c Measurement

• Measurement shall be based in approved compliance soil samples monitoring


in each (ea.) associated with relevant documents, reports/results and supported
by approved RFI’s (if any);
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;

Page 45 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with
all requirements contained in Clause 11.5 of Technical Specification Portion
1(A&B), whether or not they are specifically mentioned within the item
descriptions
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

2.2 MATERIALS DESIGNATED FOR REMEDIATION or STOCKPILING


(Excavate, Segregate, Screened, Break/Pulverized, Load, Transport and Unload at
treatment areas or stockpiling areas a measured quantities (tonnes) of oil
contaminated materials from DOL + WOL) (Layer 2).

2.2a Unit of Measurement


Tonnes

2.2b Pricing

The rate for undertaking materials designated for remediation & treatment or
stockpiling (Excavate Segregate, Screened, Break/Pulverized, Load, Transport and
unload at treatment areas or stockpiling areas a measured quantities of oil
contaminated materials from DOL + WOL), classification & monitoring of soils
for the required TPH level, testing, other associated activities and submission of
relevant document deliverables in accordance but not limited to Clauses 1.2, 5, 7 of
Technical Specification Portion 1(A&B) and Clauses 3.3, 3.4 & 3.5 of Technical
Specification Portion 2, shall include but not be limited to the following:
• Excavation in any Type of soil including Hard Stratum as defined in Clause
3.1.5 of KOC-C-003 subject to assessment, verification and approval as per
Company procedure.
• Utilizing of all necessary labour, equipment and material, constructional plant,
storage, receiving/stockpiling areas, materials & consumables, obtaining
clearance, gate passes & permits;
• Water or dust suppressions to prevent dust emission during execution of works;
• Provision of armored equipment for the performance of the work as directed by
the Company for excavation activities of WOLs, 2nd layer of WOLs, or
locations with no EOD KMOD certificates.
• Handling (including double handling) of excavated materials in forming
temporary stockpiles or spoil heaps to be re-used for transporting;
• De-watering works & associated equipment and disposal (if there is a presence
of water during pre/post excavation or generated by excavation activities) to an
approved designated area;
• Contractor shall provide Barcode System, Loading Notes, tracking system

Page 46 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

(GPS), summary of trips or weight and Log book to monitor the transported
quantity that passed through the weighbridge in accordance but not limited to
Clause 8.14 of TS Portion 1(A&B);
• Contractor shall provide a minimum of three (3) mobile weighbridge facilities
in accordance but not limited to Clause 8.15 of TS Portion 1(A&B) and Clause
3.3.6 of TS Portion 2. Rates to provide weighbridges are inclusive at the rates
of Excavation & Transportation works.
• Provide pre/post topographic survey during excavation activities (if required);
• Excavation, Segregation, Screening and Pulverising & Transportation material
to the designated receiving point (treatment area, stockpiling area, etc.) storage
and/or dumping areas;
• Inclusive of costs in providing in-situ soil densities (kg/m³) (as directed in the
technical specification) to be used in undertaking volumetric analysis and
converting excavated volume (m³) into weight (tonnes) and vice versa as per
defined in situ densities;
• Separate construction debris and other waste materials for further storage or
disposal.
• Cleaning of work areas as work progress and/or completion of works return
adjacent areas to condition existing before start of work;
• Cleaning and watering adjacent roadways areas of dust, dirt, and debris caused
by the transportation or spillages as directed by the Company's Superintendent;
• Provide shoring/sheeting (where required) to protect cave-in or collapse of any
excavation that may be unstable in accordance with KOC standards;
• Maintain the steepness and safe side slopes during excavations;
• Calibration of all meters, gauges and other such measurement equipment/device
by an independent third-party calibration specialist;
• Segregation of contaminated soils, breaking and pulverising of oversized
contaminated soils and/or boulders and weighing;
• Providing survey data, shape files and/or software’s to justify the calculations
and approved drawings (if applicable) and all necessary approved project
documents;
• All cost for complying with all requirements contained as per above clauses in
Technical Specifications, if they are specifically mentioned within the item
descriptions.

2.2c Measurement

• Measurement shall be based in approved quantities in tonnes supported by


weighbridge acquired data and reports considering the gross weight (i.e. full
load, driver and full tank of diesel), net weight (i.e. unloaded/empty, driver and
diesel) of trucks, certification, clearance, log books & loading notes & summary
from off-site/in-site weighbridge facilities and an approved RFI’s (if any),
calculations with all associated acquired data in the site and other relevant
approved Contract documents;

Page 47 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Excavation quantities shall be checked based on the following (if required by


Company);
• Quantity of void formed by the excavation to the lines and levels described in
the Contract, pre/post topographic survey, coordinates, 3D's modelling
software, Surfer, auto Cad (shape files), approved drawing (if applicable) and/or
any relevant approved documents;
• Excavation quantities shall be weighted on the basis of barcode system and
weighbridge for material to be compared with estimated excavation using other
methods for verification and agreement
• Excavation quantities shall be calculated, re-verified and classified based on the
data acquired in the site (i.e. approved pre/post topographic survey, approved
drawing showing the actual/new boundaries of each features, approved
coordinates & approved in situ soil densities for feature for volumetric analysis,
etc.).
• Using weighbridge reading considering acquired data at site;
• Excavated Quantities can be calculated by using software(s) (AutoCAD and
Surfer software, etc.);
• Any MoM and calculation proposed by Contractor and approved by Company;
• Providing calculation sheets, summary of trips (i.e. daily and monthly) as per
approved measurement plan/re-measurement calculation sheets (RMCS)
referring to the relevant approved documents in accordance with the
requirements of technical specifications;
• All interim measurements will be verified, agreed and will be adjusted during
final measurement based in all relevant approved final documents.

2.3 MATERIALS DESIGNATED FOR REMEDIATION or STOCKPILING


(Segregate, Screened, Break/Pulverized, Load, Transport and Unload at treatment
areas or stockpiling areas a measured quantities (tonnes) of oil contaminated
materials from OCPs).

2.3a Unit of Measurement


Tonnes

2.3b Pricing

The rate for undertaking materials designated for remediation or stockpiling.


Segregate, Screened, Break/Pulverized, Load, Transport and Unload at treatment
areas or stockpiling areas a measured quantity of oil contaminated materials from
OCP's, other associated activities and submission of relevant document deliverables
in accordance but not limited to Clauses 7 of Technical Specification Portion
1(A&B) and Clauses 3.3 of Technical Specification Portion 2, shall include but not
be limited to the following:
• Utilizing of all necessary labour, equipment and material, constructional plant,
storage, receiving/stockpiling areas, materials & consumables, obtaining

Page 48 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

clearance, gate passes & permits;


• Water or dust suppressions to prevent dust emission during execution of works;
• Handling (including double handling) of excavated materials in forming
temporary stockpiles or spoil heaps to be re-used for transporting;
• De-watering works & associated equipment and disposal (if there is a presence
of water during pre/post excavation or generated by excavation activities) to an
approved designated area;
• Contractor shall provide Barcode System, Loading Notes, tracking system
(GPS), summary of trips or weight and Log book to monitor the transported
quantity that passed through the weighbridge in accordance but not limited to
Clause 8.14 of TS Portion 1(A&B);
• Contractor shall provide a minimum of three (3) mobile weighbridge facilities
in accordance but not limited to Clause 8.15 of TS Portion 1(A&B) and Clause
3.3.6 of TS Portion 2. Rates to provide weighbridges are inclusive at the rates
of Excavation & Transportation works.
• Provide pre/post topographic survey during excavation/removal activities (if
required); Excavation/removal, Segregation, Screening and Pulverising &
Transportation material to the designated receiving point (treatment area,
stockpiling area, etc.) storage and/or dumping areas;
• Separate construction debris and other waste materials for further storage or
disposal.
• Cleaning of work areas as work progress and/or completion of works return
adjacent areas to condition existing before start of work;
• Cleaning and watering adjacent roadways areas of dust, dirt, and debris caused
by the transportation or spillages as directed by the Company's Superintendent;
• Provide shoring/sheeting (where required) to protect cave-in or collapse of any
excavation that may be unstable in accordance with KOC's standards;
• Calibration of all meters, gauges, and other such measurement
equipment/devise by an independent third-party calibration specialist;
• Segregation of contaminated soils, breaking and pulverising of oversized
contaminated soils and/or boulders and weighing;
• Providing survey data, shape files and/or software’s to justify the calculations
and approved drawings (if applicable) and necessary approved project
documents;
• All costs for complying with all requirements contained as per above Clauses
in technical Specifications, if they are specifically mentioned within the item
descriptions.

2.3c Measurement

• Measurement shall be based in approved quantities in tonnes supported by


weighbridge acquired data and reports considering the gross weight (i.e. full
load, driver and full tank of diesel), net weight (i.e. unloaded/empty, driver and

Page 49 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

diesel) of trucks, certification, clearance, log books & loading notes & summary
from off-site/in-site weighbridge facilities and an approved RFI’s (if any),
calculations with all associated acquired data in the site and other relevant
approved Contract documents;
• Using weighbridge reading considering acquired data at site;
• Any MoM and calculation proposed by Contractor and approved by Company;
• Providing calculation sheets, summary of trips (i.e. daily and monthly) as per
approved measurement plan/re-measurement calculation sheets (RMCS)
referring to the relevant approved documents in accordance with the
requirements of technical specifications;
• All interim measurements will be verified, agreed and will be adjusted during
final measurement based in all relevant approved final documents.

2.4 UNTREATED CONTAMINATED DRY MATERIALS MIXING WITH OIL


SLUDGE

2.4 Mixing untreated Dry Contaminated Materials with sludge oil (inside feature)
2.4a Unit of Measurement
Tonnes

2.4b Pricing

The rate for undertaking Mixing untreated Dry Contaminated Materials with sludge
oil (inside feature), other associated activities/other necessary works required to be
executed and submission of relevant document deliverables in accordance but not
limited to Clause 3.3.3 of Technical Specification Portion 2, shall include but not
be limited to the following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


storage, materials, water, loading, transportation, stockpiling & any
consumables items, mixing trials, obtaining clearance, gate passes & permits;
• Carry out mixing testing to verify optimum mixing ratio in the location of
wet/oil/sludge feature;
• Mechanically mix oil/sludge with the impacted dry oil materials;
• Provide methodologies and selected optimum mixing ratio in carry out mixing
process within mixing areas;
• Provide a 5-mm polyethylene or plastic sheeting at the bottom of clean area for
mixing purposes to avoid cross-contamination with clean material and shall be
located such that runoff from this area does not leave during a rain event.
Temporary berming or other grading controls may be required as part of the
mixing methods;
• Provide and submit method statement for mixing activities for Company
approval prior to commence the cited activities;
Page 50 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Provide and submit estimates of oil/sludge volumes (m3) and quantities (tonnes)
using density of oil sludge derived or estimated and extent of oil sludge areas
(m²) prior to mixing activities;
• Provide and submit proposed optimum mixing ratio for Company approval prior
to commence mixing activities;
• Handling (including double handling) of excavated materials for mixing in
forming temporary stockpiles or spoil heaps to be re-used for transporting,
• Load and Transport the mixed soils to a designated area as per directives by
Company representatives;
• Provide Loading Notes, tracking system (GPS), summary of trips & weight and
Log book to monitor the transported quantity that passed through the
weighbridge,
• Cleaning of work areas as work progress and/or completion of works return
adjacent areas to condition existing before start of work,
• Cleaning adjacent roadways areas of dust, dirt, and debris caused by the
transportation or spillages as directed by the Company's Superintendent,
• Calibration of all tonnes, gauges, and other such measurement
equipment/devise by an independent third-party calibration specialist,
• Operation, maintenance, repair, replacement and depreciation of all equipment
required to facilitate the mixing process,
• Segregation of contaminated soils, breaking of oversized contaminated soils and
transporting to designated mixing areas;
• All costs for complying with all requirements contained as per above Clauses
in technical Specifications, whether or not they are specifically mentioned
within the item descriptions.

2.4c Measurement

• Measurement shall be based in approved quantities in tonnes supported by


weighbridge acquired data and reports considering the gross weight (i.e. full
load, driver and full tank of diesel), net weight (i.e. unloaded/empty, driver and
diesel) of trucks, certification, clearance, log books & loading notes & summary
from off-site/in-site weighbridge facilities and an approved RFI’s (if any),
calculations with all associated acquired data in the site and other relevant
approved Contract documents;
• Providing calculation sheets, summary of trips (i.e. daily and monthly) as per
approved measurement plan/re-measurement calculation sheets (RMCS)
referring to the relevant approved documents in accordance with the
requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

2.5 WASTE MANAGEMENT - CONSTRUCTION DEBRIS MATERIALS:

Page 51 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

(Load, Transport, offload and dispose to KOC designated dumping location in


accordance with KOC waste handling procedure).

2.5 Construction Debris

2.5a Unit of Measurement


Tonnes

2.5b Pricing

The rate for undertaking Waste Management (i.e. located/found at Dry Oil Lakes
& Wet Oil Lakes, OCPs), other associated activities/other necessary works required
to be carried out and submission of relevant document deliverables in accordance
but not limited to the requirement of Clauses 7.5 & 7.6 of Technical Specifications
Portion 1(A&B) shall include but not be limited to the following:

• Utilization of all necessary labour, equipment and material, constructional plant,


providing approved storage/container (if required), photos, lists, weightages of
all debris, stockpiling, protection, marker, signboard, collecting, warning
device, and later on loading and transportation to disposal facility , calibration
and standardizations of the required equipment (if required), coordination with
others, obtaining gate passes, permits, clearance, taxes & license, storage,
marked up drawing, quality control/reviews, recording of all findings &
reporting as specified;
• Removal from excavated materials & excavation areas, certification/inspection,
storage or stockpiling & later to load and disposal as inactive waste of
construction debris, munition & non-munition debris;
• Separate construction debris and other waste materials for further storage or
disposal
• Providing any special methods, process, platforms and/or equipment in
conducting the cited activities in wet oil lakes;
• Duty of care and chains of custody shall be used for waste disposal and
submission of Chain of custody documentation & other relevant documents;
• Non-munitions debris after inspection and verification as FFE shall be disposed
as inactive waste in accordance with the provisions of the Contract;
• Prepare and submit plans methodology, procedures, proposal to monitor and/or
measured the metallic & construction debris, RFI’s and drawings to carry-out
the cited activities and all costs for complying with all relevant requirements
contained in Contract documents, whether or not they are specifically
mentioned within the item descriptions.

2.5c Measurement

• Measurement shall be based in the approved executed quantities in tonnes and


supported by an approved RFI’s, weights certifications (i.e. weighbridge
Page 52 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

reading and/or similar), lists/weight of materials, photos, marked up drawings


showing the coordinates, location, grids and/or any approved relevant
documents;
• Other excavated materials or wastes shall be placed into designated areas and
later loaded into trucks and weighed at the weighbridge prior to transportation
and transported to disposal designated areas. Duty of care and chains of custody
shall be used for waste disposal or other approved method;
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

2.6 TRANSPORTATION AND PLACEMENT OF TREATED SOIL

2.6.1 PLACEMENT WITHIN EXCAVATED AREAS

2.6.1 Load, Transport and unload treated soil from treatment pad to excavated areas
locations up to 0.6 m depth associated works includes spread, placement, tampered
and compact.

2.6.1a Unit of Measurement


Tonnes

2.6.1b Pricing

The rates for undertaking Load and Transport treated soil from treatment pad to
excavated areas locations up to 0.6 m associated works includes spread, placement,
tampered and compact., other associated activities and submission of relevant
document deliverables in accordance but not limited to Clause 1.2 of Technical
Specification Portion 1(A&B), Clauses 3.0, 3.6 & 5 of Technical Specification
Portion 2, Clause 4.6 of Technical Specification Portion 3 and Clause 3.0, 4.6 & 5
of Technical Specification Portion 4, shall include but not be limited to the
following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


hand tools, small equipment(s), obtaining gate passes & permits, clearance,
taxes, water, fences, access roads up grading and maintenance (if required),
loading, transportation, levelling, compacting, barricades, filling at gatch pits,
signboard, any consumables items required in treatment works and coordination
to others;
• Preparing work plans, method statement and other required Contract documents
Page 53 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

and deliverables;
• Mixing and civil works required for handling (including double handling) of
excavated materials in forming temporary stockpiles or spoil heaps to be re-
used for transporting;
• Provide Loading Notes, tracking system (GPS), summary of trips & weight and
Log book to monitor the transported quantity that passed through the
weighbridge;
• Cleaning of work areas as work progress and/or completion of works return
adjacent areas to condition existing before start of work;
• Construction waste & debris removal to an approved stockpile area as directed
by Company;
• Pre-& Post topographic survey for excavated soils;
• Supply of water for compaction in line with KOC standard;
• Provide a compaction method and other control measures to minimize soil
erosion from wind and to support establishment of vegetative growth for Kuwait
natural desert species. Soil erosion measures shall be employed for the final
restorations.
• Cleaning adjacent roadways areas of dust, dirt, and debris caused by the
transportation or spillages as directed by the Company's Superintendent,
• Operation, maintenance, repair, replacement and depreciation of any and all
equipment required to facilitate the transportation and backfilling;
• Providing power supply and accessories, water, telephone, sanitary disposal,
safety, medical, first aid, ambulance, storages, etc.
• Produce transportation and backfilling activities monitoring, operation, quality
control/reviews of data processing & analysis and other required
sample/laboratory, recording & reporting;
• All associated costs to execute loading, transportation, backfilling / restoration
of excavated areas, whether or not they are specifically mentioned within the
item description;

2.6.1c Measurement

• Measurement shall be based in approved quantities in tonnes as executed by


loading, transportation, backfilling / restoration of excavated areas and
supported by an approved RFI’s, weighbridge reading acquired data(s), results,
summary of trips, reports and/or any approved relevant documents;
• Treated quantities shall be weighted in tonnes on the basis of barcode systems
and weight bridge for material used for transportation and placement of treated
soil. Payment shall be calculated on weight basis of the treated material.
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved

Page 54 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

documents in accordance with the requirements of technical specifications;


• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

2.6.2 PLACEMENT WITHIN GATCH PITS

2.6.2 Load, Transport and unload treated soil from treatment areas to gatch pits or other
areas for backfill associated works to the depth between 2m and around 10 m depth
including spread, placement and compact in lift to meet desired surface grade.

2.6.2a Unit of Measurement


Tonnes

2.6.2b Pricing

The rates for undertaking Load and Transport treated soil from treatment areas to
gatch pits or other areas for backfill associated works to the depth between 2m and
around 10 m including spread, placement and compact in lift to meet desired surface
grade., other associated activities and submission of relevant document deliverables
in accordance but not limited to Clause 1.2 of Technical Specification Portion
1(A&B), Clauses 3.5, 3.6 & 5 of Technical Specification Portion 2, Clause 4.6 of
Technical Specification Portion 3 and Clauses 3.0, 4.6 & 5 of Technical
Specification Portion 4, shall include but not be limited to the following:

• Utilizing of all necessary labour, equipment and material, constructional plant,


hand tools, small equipment(s), obtaining gate passes & permits, clearance,
taxes, water, fences, access roads up grading and maintenance (if required),
loading, transportation, levelling, compacting, barricades, filling at gatch pits,
signboard, any consumables items required in treatment works and coordination
to others;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Mixing and civil works required for handling (including double handling) of
excavated materials in forming temporary stockpiles or spoil heaps to be re-
used for transporting;
• Provide Loading Notes, tracking system (GPS), summary of trips & weight and
Log book to monitor the transported quantity that passed through the
weighbridge,
• Cleaning of work areas as work progress and/or completion of works return
adjacent areas to condition existing before start of work;
• Construction waste & debris removal to an approved and/or authorized disposal
areas;
• Pre-& Post topographic survey for excavated soils;

Page 55 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Supply of water for compaction in line with KOC standard;


• Supply and spread topsoil on the surface of the filled soil. The surface grade of
the closed pit shall generally match with the natural grade & drainage pattern of
the area;
• Provide a compaction method and other control measures to minimize soil
erosion from wind and to support establishment of vegetative growth for Kuwait
natural desert species. Soil erosion measures shall be employed for the final
restorations. Consider surface dressing to prevent wind erosion where
necessary;
• Cleaning adjacent roadways areas of dust, dirt, and debris caused by the
transportation or spillages as directed by the Company's Superintendent;
• Operation, maintenance, repair, replacement and depreciation of any and all
equipment required to facilitate the transportation and backfilling;
• Providing power supply and accessories, water, telephone, sanitary disposal,
safety, medical, first aid, ambulance, storages, etc.;
• Produce transportation and backfilling activities monitoring, operation, quality
control/reviews of data processing & analysis and other required
sample/laboratory, recording & reporting;
• All associated costs to execute loading, transportation, backfilling / restoration
of excavated areas, whether or not they are specifically mentioned within the
item description.

2.6.2c Measurement

• Measurement shall be based in approved quantities in tonnes as executed by


loading, transportation, backfilling / restoration of Company other areas and
supported by an approved RFI’s, weighbridge reading acquired data(s), results,
summary or trips, reports and/or any approved relevant documents;
• Treated quantities shall be weighted in tonnes on the basis of barcode systems
and weight bridge for material used for transportation and placement of treated
soil. Payment shall be calculated on weight basis of the treated material.
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications; All
interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

PORTION 3A - SITE WORKS: REMEDIATION WORKS - TPH >1% - ≤ 5%

Page 56 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

3A.1 SAMPLE ANALYSIS & DATA MANAGEMENT

3A.1.1 Samples analysis & data management Treatment progress as per Clause 4.6.5(a) of
Technical Specification Portion 3A and Clause 15.3 of Technical Specifications
Portion 1(A & B)

3A.1.1a Unit of Measurement


Number (No.)

3A.1.1b Pricing

The rate for undertaking collection, sample analysis & data management treatment
progress, other associated activities/other necessary works to be carried out and
submission of relevant document deliverables in accordance but not limited to
Clauses 8, 13 & 15 of Technical Specification Portion 1(A&B) and Clauses 4.0, 4.6.5
of Technical Specification Portion 3, shall include but not be limited to the
following:

• Utilizing of all necessary labour, Constructional Plant/equipment, material,


transportation, obtaining gate passes & permits, clearance, taxes, approved
sample container (i.e. plastic or glass jar), dry ice chest, labelling, marking, any
consumables items required for sample collection & laboratory analysis,
barricades and coordination;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Conduct monthly monitoring consisting of sample collection and laboratory
analysis and reporting to establish degradation for successful remediation is
taking place and monitoring data show trends to meet the Contractors forecast
performance curves.
• Conduct verification samples at the end of treatment period to verify are
compliant with the treatment RTC;
• Conduct the following analysis and activities: Sample screen by gun, Field logs,
duplicate samples for QA/QC, Sample Analysis with various parameters,
Analytical Test, Sample identification, EGIS and EQuIS formattable data,
Chain of Custody, Arising, Sampling QA/QC, Trip Blanks, Field & Equipment
Rinse Blanks, Blind Duplicates and Certified Reference Sample;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation (if required), sample
collection, re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;
Page 57 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Grey or treated water conservation, recycling and re-use for 30 % of water


usages for treatment to meet the project objectives and minimize the water
usages throughout the project duration.

3A.1.1c Measurement

• Measurement shall be based in number(s) on the approved Sampling and


Analysis Data Management documents, results and reports as executed and
supported by an approved RFI’s and/or any approved relevant documents;
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets and/or laboratory data with all as per approved
measurement plan/re-measurement calculation sheets (RMCS) referring to the
relevant approved documents in accordance with the requirements of technical
specifications;
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with
all requirements contained in Clause 11.5 of Technical Specification Portion
1(A&B), whether or not they are specifically mentioned within the item
descriptions
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

3A.1.2 Samples analysis & data management Baselines & Verification as per Clause
4.6.5(b) of Technical Specification Portion 3A and Clause 15.3 of Technical
Specifications Portion 1(A & B)

3A.1.2a Unit of Measurement


Number (No.)

3A.1.2b Pricing
The rate for undertaking collection, sample analysis & data management Baseline
& Verification, other associated activities/other necessary works to be carried out
and submission of relevant document deliverables in accordance but not limited to
Clauses 8, 13 & 15 of Technical Specification Portion 1(A&B) and Clauses 4.0, 4.6.5
of Technical Specification Portion 3, shall include but not be limited to the
following:

• Utilizing of all necessary labour, Constructional Plant/equipment, material,


transportation, obtaining gate passes & permits, clearance, taxes, approved
sample container (i.e. plastic or glass jar), dry ice chest, labelling, marking, any

Page 58 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

consumables items required for sample collection & laboratory analysis,


barricades and coordination;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Conduct monthly monitoring consisting of sample collection and laboratory
analysis and reporting to establish degradation for successful remediation is
taking place and monitoring data show trends to meet the Contractors forecast
performance curves.
• Conduct verification samples at the end of treatment period to verify are
compliant with the treatment RTC;
• Conduct the following analysis and activities: Sample screen by gun, Field logs,
duplicate samples for QA/QC, Sample Analysis with various parameters,
Analytical Test, Sample identification, EGIS and EQuIS formattable data,
Chain of Custody, Arising, Sampling QA/QC, Trip Blanks, Field & Equipment
Rinse Blanks, Blind Duplicates and Certified Reference Sample;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation (if required), sample
collection, re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;
• Grey or treated water conservation, recycling and re-use for 30 % of water
usages for treatment to meet the project objectives and minimize the water
usages throughout the project duration.

3A.1.2c Measurement

• Measurement shall be based in number(s) on the approved Sampling and


Analysis Data Management documents, results and reports as executed and
supported by an approved RFI’s and/or any approved relevant documents;
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets and/or laboratory data with all as per approved
measurement plan/re-measurement calculation sheets (RMCS) referring to the
relevant approved documents in accordance with the requirements of technical
specifications;
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with

Page 59 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

all requirements contained in Clause 11.5 of Technical Specification Portion


1(A&B), whether or not they are specifically mentioned within the item
descriptions
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

3A.2 REMEDIATION WORKS

3A.2 REMEDIATION WORKS FOR CONTAMINATED SOILS


WITH >1% to ≤ 5% TPH LEVEL

3A.2.a Unit of Measurement


Tonnes

3A.2.b Pricing

The rate for undertaking Remediation works for contaminated soils with 1% to ≤
5% TPH level and other associated activities and submission of relevant document
deliverables in accordance but not limited to Clauses 1.2 & 7.0 of Technical
Specification Portion 1(A&B) and All Clauses of Technical Specification Portion 3,
shall include but not be limited to the following:

• All costs related to Optimization Studies and Reports which include: Bench
Scale Test (>1% to ≤5% TPH) with Optimization Study Report for
Bioremediation or Field Trial Test (>1% to ≤5% TPH) with Optimization Study
Report shall include, but not be limited to, utilization of all necessary labour,
equipment, lab analytical instrumentation, analysis, and prototype treatment
equipment, mixing with other TPH ranges testing, pre and/or post treatment,
Construction Plant, material, computer, software, vehicles, preparation of
reports & procedures, the cost for any further revision(s), assessment and
reporting until successful demonstration of meeting the RTC within the project
timeframe, office materials or any other office equipment, procurement, taxes,
permits, analyzing, editing, copying, evaluation, processing, duplications and
all associated costs for complying in accordance but not limited to all
requirements in Clauses 1.2, 8.7 & 13 of Technical Specification Portion
1(A&B), Clause 3.3 of Tech. Specification Portion 3 & clause 3.2 of Technical
Specification Portion 4.

• Utilizing of all necessary labour, equipment and material, constructional plant,


obtaining gate passes & permits, clearance, taxes, segregation (if required),
water, fuel, electrical, providing treatment areas/pads, fences/gates, access
roads, barricades, signboard, any consumables items required in treatment
works and coordination to others;
• Segregation of waste materials that cannot be treated from the treatment stream

Page 60 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

and addressed as per Clause 7.4 of Portion 1(A&B) of the Technical


Specifications (i.e., place in holding area, dispose at extension to existing NK
Landfill, or dispose offsite as directed by Company). Segregated tar ball and
boulders materials, if any, shall be considered as part of the maximum allowable
waste product;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Maintenance includes storm water managements and other associated works;
• Mixing and civil works required for handling (including double handling) of
excavated materials in forming temporary stockpiles or spoil heaps to be re-
used for transporting;
• Provide Loading Notes, tracking system (GPS), summary of trips & weight and
Log book to monitor the transported quantity that passed through the
weighbridge;
• Collect representative samples to measure and determine initial water content
(%) prior to treatment and final water content (%) after treatment in the field
and/or laboratory;
• Provide pre-treatment or post remediation or treatment technique or material for
all input and output parameter; if required or/as directed by the company;
• Provide and handle all mixing with additives for full scale as per pilot study
optimization;
• Cleaning of work areas as work progress and/or completion of works location
or adjacent location to condition existing before start of work;
• Cleaning and watering adjacent roadways areas of dust, dirt, and debris caused
by the transportation or spillages;
• Operation, maintenance, repair, replacement and depreciation of any and all
equipment and treatment system required to facilitate the remediation or
treatment process;
• Pre-& Post water treatment for usage and disposal if necessary and directed by
Company;
• Segregation of contaminated soils, breaking of oversized contaminated soils and
weighing;
• Water extraction from wells or water supply usage from other sources and
treatment if desired, recycling and re-use to use and, sampling, mixing, handling
and monitoring;
• Remediation and Treatment Technologies-Main Works monitoring, sample
collection, and analysis for verification that may be required, and all costs
associated with reporting remediation or treatment progress according to the
requirements outlined in the Contract;
• Providing power supply and accessories, supply water and water storage with
irrigation on planned schedule, water measurements, telephone, sanitary,
chemical disposal, safety, medical, first aid, ambulance, storages, and etc.;
• Produce initial bioremediation or treatment monitoring, operation, quality
control/reviews of data processing & analysis and other required

Page 61 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

sample/laboratory, recording & reporting; and contingent on verification


sample results and approval by Company;
• All costs associated with any and all bioremediation, pre- or post-treatment
required.
• Inclusive of any enhancements or refinements to the remediation methods
required should a treatment method not fulfil the Remediation Treatment
Criteria detailed within the Technical Specification (including but not limited
to additional pre-treatment, secondary or tertiary alike to attain the required
targets).
• Inclusive of costs for water requirement for the supply, storage, transportation,
and treatment if the Company does not provide water sources and usages. If
Company explores water sources and provide some water requirements to the
Contractor, the Contractor shall in return reimburse the net water associated
costs related to pre-treatment of water (if required) shall be provided in
accordance with unit price provided in Form of Tender Attachment 3.
• Inclusive of cost for mixing Soil having a range of >5% to ≤7% TPH to be
mixed with the oil impacted soil to be remediated from ≤ 5% TPH range in
accordance with clause 1.3 (i) of Technical Specification 3
• Payment shall be calculated on pro-rata basis of the unit rate based on each ratio
of respective volume and TPH level/range used in the mixing range (example
% of material from 1% to 5% shall be paid on unit rate specified for this range
and ratio or percent of TPH 5% to 7 % material shall be paid on unit rate for the
same.
• If applicable, Interim Payment for soils having a TPH range of >5% to ≤7%
mixed with the impacted soil to be remediated from ≤ 5% TPH range shall be
calculated on pro-rata basis of the unit rate based on the approved applied
mixing ratio of respective volume and TPH ranges.

Example:
o Approved Applied mixing ratio = 1:3
o Soils having a ≤ 5% TPH range = X Rates ($)
o Soils having a >5% to ≤7% TPH range = Y Rates ($)

Calculation:
• Pro-rata Rates = ((X Rates ($) multiply by 3) + Y Rates ($)) / 4 = $$$$ (This
calculated pro-rata rates to be applied in the mixing activities (if any).
• All associated prices or costs shall include the disposal of residual oil, waste
water, salt, by-product waste etc. generated by the remediation or treatment
process, whether or not they are specifically mentioned within the item
description.

3A.2.c Measurement

• Measurement shall be based in approved quantities in tonnes as executed by

Page 62 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

remediation works for contaminated soils with TPH of >1 % and ≤ 5% level for
remediation and/ or >5 % and ≤7% for remediation or treatment technologies
and > 7 % for treatment technologies and supported by an approved RFI’s,
weighbridge reading acquired data(s), results, reports and/or any approved
relevant documents;
• Measurement shall be total weighted in tonnes deducting the net quantities of
water content. In other words, total weighted (final) soils deduct the added water
weight for the treatment;
• Additive weights due to bulking of contaminated soils during pre- or post-
treatment shall not be counted or weighted for the payments. These weights
shall remove from the post treatment weightages
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• Measurement shall be based on weighted quantity in tonnes from the source
feature and categorized as per TPH level/range.
• Rejected treatment material, not meeting the requirements as per Contract shall
not be paid until retested including loading and unloading, sample collection,
re-packing, labelling and transportation etc. , testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all additional costs for
complying with all requirements contained in Clause 11.5 of Technical
Specification Portion 1(A&B), whether or not they are specifically mentioned
within the item descriptions
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.
• Inclusive of cost for Contractor’s specialists in imparting training to Company
operating/maintenance personnel as follows:
➢ Training in vendor’s/Contractor’s premises in Kuwait for up to ten (10)
personnel for a period of three (3) working days; and on-site training for up
to ten (10) personnel for a duration of 90-120 working days.
➢ Contents and schedules of training program will be subject to Company
approval.
➢ Contractor shall arrange the required training resources (reference materials,
laptop computers, screen projectors etc.). Contractor/vendors shall provide
training documents to each participant. All costs for training shall be borne
by Contractor.
➢ Training certificates shall be issued to the participants.

PORTION 3B - SITE WORKS: REMEDIATION WORKS - TPH >5% - ≤ 7%

Page 63 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

3B.1 SAMPLE ANALYSIS & DATA MANAGEMENT

3B.1.1 Samples analysis & data management Treatment progress as per Clause 4.6.8(a) of
Technical Specification Portion 3B and Clause 15.3 of Technical Specifications
Portion 1(A & B)

3B.1.1a Unit of Measurement


Number (No.)

3B.1.1b Pricing

The rate for undertaking collection, sample analysis & data management Treatment
progress, other associated activities/other necessary works to be carried out and
submission of relevant document deliverables in accordance but not limited to
Clauses 8, 13 & 15 of Technical Specification Portion 1(A&B) and Clauses 4.0, 4.6.5
of Technical Specification Portion 3, shall include but not be limited to the
following:

• Utilizing of all necessary labour, Constructional Plant/equipment, material,


transportation, obtaining gate passes & permits, clearance, taxes, approved
sample container (i.e. plastic or glass jar), dry ice chest, labelling, marking, any
consumables items required for sample collection & laboratory analysis,
barricades and coordination;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Conduct monthly monitoring consisting of sample collection and laboratory
analysis and reporting to establish degradation for successful remediation is
taking place and monitoring data show trends to meet the Contractors forecast
performance curves.
• Conduct verification samples at the end of treatment period to verify are
compliant with the treatment RTC;
• Conduct the following analysis and activities: Sample screen by gun, Field logs,
duplicate samples for QA/QC, Sample Analysis with various parameters,
Analytical Test, Sample identification, EGIS and EQuIS formattable data,
Chain of Custody, Arising, Sampling QA/QC, Trip Blanks, Field & Equipment
Rinse Blanks, Blind Duplicates and Certified Reference Sample;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation (if required), sample
collection, re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;
Page 64 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

• Grey or treated water conservation, recycling and re-use for 30 % of water


usages for treatment to meet the project objectives and minimize the water
usages throughout the project duration.

3B.1.1c Measurement

• Measurement shall be based in number(s) on the approved Sampling and


Analysis Data Management documents, results and reports as executed and
supported by an approved RFI’s and/or any approved relevant documents;
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets and/or laboratory data with all as per approved
measurement plan/re-measurement calculation sheets (RMCS) referring to the
relevant approved documents in accordance with the requirements of technical
specifications;
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with
all requirements contained in Clause 11.5 of Technical Specification Portion
1(A&B), whether or not they are specifically mentioned within the item
descriptions
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

3B.1.2 Samples analysis & data management Baselines & Verification as per Clause
4.6.8(b) of Technical Specification Portion 3B and Clause 15.3 of Technical
Specifications Portion 1(A & B)

3B.1.2a Unit of Measurement


Number (No.)

3B.1.2b Pricing

The rate for undertaking collection, sample analysis & data management Baselines
& Verification, other associated activities/other necessary works to be carried out
and submission of relevant document deliverables in accordance but not limited to
Clauses 8, 13 & 15 of Technical Specification Portion 1(A&B) and Clauses 4.0, 4.6.5
of Technical Specification Portion 3, shall include but not be limited to the
following:

• Utilizing of all necessary labour, Constructional Plant/equipment, material,


transportation, obtaining gate passes & permits, clearance, taxes, approved
sample container (i.e. plastic or glass jar), dry ice chest, labelling, marking, any
Page 65 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

consumables items required for sample collection & laboratory analysis,


barricades and coordination;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Conduct monthly monitoring consisting of sample collection and laboratory
analysis and reporting to establish degradation for successful remediation is
taking place and monitoring data show trends to meet the Contractors forecast
performance curves.
• Conduct verification samples at the end of treatment period to verify are
compliant with the treatment RTC;
• Conduct the following analysis and activities: Sample screen by gun, Field logs,
duplicate samples for QA/QC, Sample Analysis with various parameters,
Analytical Test, Sample identification, EGIS and EQuIS formattable data,
Chain of Custody, Arising, Sampling QA/QC, Trip Blanks, Field & Equipment
Rinse Blanks, Blind Duplicates and Certified Reference Sample;
• Quality control/reviews of data processing & analysis;
• Recording of all finding & reporting as specified;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory,
rejected samples, i.e. not meeting the requirements of Technical Specification
shall not be paid and cost for retest including re-excavation (if required), sample
collection, re-packing, labelling and transportation etc. are solely Contractor’s
responsibilities, whether or not they are specifically mentioned within the item
description;
• Grey or treated water conservation, recycling and re-use for 30 % of water
usages for treatment to meet the project objectives and minimize the water
usages throughout the project duration.

3B.1.2c Measurement

• Measurement shall be based in number(s) on the approved Sampling and


Analysis Data Management documents, results and reports as executed and
supported by an approved RFI’s and/or any approved relevant documents;
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets and/or laboratory data with all as per approved
measurement plan/re-measurement calculation sheets (RMCS) referring to the
relevant approved documents in accordance with the requirements of technical
specifications;
• Rejected samples, i.e. not meeting the requirements as per Contract shall not be
paid and cost for retest including re-excavation/drilling, sample collection, re-
packing, labelling and transportation etc., testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all costs for complying with

Page 66 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

all requirements contained in Clause 11.5 of Technical Specification Portion


1(A&B), whether or not they are specifically mentioned within the item
descriptions
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

3B.2 REMEDIATION WORKS

3B.2 REMEDIATION WORKS FOR CONTAMINATED SOILS


WITH >5% & ≤ 7% TPH LEVEL

3B.2.a Unit of Measurement


Tonnes

3B.2.b Pricing

The rate for undertaking bio/Remediation works for contaminated soils with >5%
& ≤ 7% TPH level and other associated activities and submission of relevant
document deliverables in accordance but not limited to Clauses 1.2 & 7.0 of
Technical Specification Portion 1(A&B) and All Clauses of Technical Specification
Portion 3, shall include but not be limited to the following:

• All costs related to Optimization Studies and Reports which include: Bench
Scale Tests and Field Trial (>5% to ≤7%) with Optimization Study Report using
either Bio and/or Other Technologies shall include, but not be limited to,
utilization of all necessary labour, equipment, lab analytical instrumentation,
analysis, and prototype treatment equipment, mixing with other TPH ranges
testing, pre and/or post treatment test, Construction Plant, material, computer,
software, vehicles, preparation of reports & procedures, the cost for any further
revision(s), assessment and reporting until successful demonstration of meeting
the RTC within the project timeframe, office materials or any other office
equipment, procurement, taxes, permits, analyzing, editing, copying,
evaluation, processing, duplications and all associated costs for complying in
accordance but not limited to all requirements in Clauses 1.2, 8.7 & 13 of
Technical Specification Portion 1(A&B), Clause 3.3 of Tech. Specification
Portion 3 & clause 3.2 of Technical Specification Portion 4.

• Utilizing of all necessary labour, equipment and material, constructional plant,


obtaining gate passes & permits, clearance, taxes, segregation (if required),
water, fuel, electrical, providing treatment areas/pads, fences/gates, access
roads, barricades, signboard, any consumables items required in treatment
works and coordination to others;
• Segregation of waste materials that cannot be treated from the treatment stream
and addressed as per Clause 7.4 of Portion 1(A&B) of the Technical

Page 67 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

Specifications (i.e., place in holding area, dispose at extension to existing NK


Landfill, or dispose offsite as directed by Company). Segregated tar ball and
boulders materials, if any, shall be considered as part of the maximum allowable
waste product;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Maintenance includes storm water managements and other associated works;
• Mixing and civil works required for handling (including double handling) of
excavated materials in forming temporary stockpiles or spoil heaps to be re-
used for transporting;
• Provide Loading Notes, tracking system (GPS), summary of trips & weight and
Log book to monitor the transported quantity that passed through the
weighbridge;
• Collect representative samples to measure and determine initial water content
(%) prior to treatment and final water content (%) after treatment in the field
and/or laboratory;
• Provide pre-treatment or post remediation or treatment technique or material for
all input and output parameter; if required or/as directed by the company;
• Provide and handle all mixing with additives for full scale as per pilot study
optimization;
• Cleaning of work areas as work progress and/or completion of works location
or adjacent location to condition existing before start of work;
• Cleaning and watering adjacent roadways areas of dust, dirt, and debris caused
by the transportation or spillages;
• Operation, maintenance, repair, replacement and depreciation of any and all
equipment and treatment system required to facilitate the remediation or
treatment process;
• Pre-& Post water treatment for usage and disposal if necessary and directed by
Company;
• Segregation of contaminated soils, breaking of oversized contaminated soils and
weighing;
• Water extraction from wells or water supply usage from other sources and
treatment if desired, recycling and re-use to use and, sampling, mixing, handling
and monitoring;
• Remediation and Treatment Technologies-Main Works monitoring, sample
collection, and analysis for verification that may be required, and all costs
associated with reporting remediation or treatment progress according to the
requirements outlined in the Contract;
• Providing power supply and accessories, supply water and water storage with
irrigation on planned schedule, water measurements, telephone, sanitary,
chemical disposal, safety, medical, first aid, ambulance, storages, and etc.;
• Produce initial Remediation or treatment monitoring, operation, quality
control/reviews of data processing & analysis and other required
sample/laboratory, recording & reporting; and contingent on verification

Page 68 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

sample results;
• All costs associated with any and all pre- or post-treatment required.
• Inclusive of any enhancements or refinements to the remediation methods
required should a treatment method not fulfil the Remediation Treatment
Criteria detailed within the Technical Specification (including but not limited
to additional pre-treatment, secondary or tertiary alike to attain the required
targets).
• Inclusive of costs for water requirement for the supply, storage, transportation,
and treatment if the Company does not provide water sources and usages. If
Company explores water sources and provide some water requirements to the
Contractor, the Contractor shall in return reimburse the net water associated
costs related to pre-treatment of water (if required) shall be provided in
accordance with unit price provided in Form of Tender Attachment 3.
• Inclusive of cost for mixing Soil having a range of >5% to ≤7% TPH to be
mixed with the oil impacted soil to be remediated from ≤ 5% TPH range in
accordance with clause 1.3 (i) of Technical Specification 3
• Payment shall be calculated on pro-rata basis of the unit rate based on each ratio
of respective volume and TPH level/range used in the mixing range (example
% of material from 1% to 5% shall be paid on unit rate specified for this range
and ratio or percent of TPH 5% to 7 % material shall be paid on unit rate for the
same.
• If applicable, Interim Payment for soils having a TPH range of >5% to ≤7%
mixed with the impacted soil to be remediated from ≤ 5% TPH range shall be
calculated on pro-rata basis of the unit rate based on the approved applied
mixing ratio of respective volume and TPH ranges.

Example:
o Approved Applied mixing ratio = 1:3
o Soils having a ≤ 5% TPH range = X Rates ($)
o Soils having a >5% to ≤7% TPH range = Y Rates ($)

Calculation:
• Pro-rata Rates = ((X Rates ($) multiply by 3) + Y Rates ($)) / 4 = $$$$ (This
calculated pro-rata rates to be applied in the mixing activities (if any).
• All associated prices or costs shall include the disposal of residual oil, waste
water, salt, by-product waste etc. generated by the remediation or treatment
process, whether or not they are specifically mentioned within the item
description.

3B.2.c Measurement
• Measurement shall be based in approved quantities in tonnes as executed by
remediation works for contaminated soils with TPH of 1 % and ≤ 5% level for
remediation and/ or >5 % and ≤7% for remediation or treatment technologies
and > 7 % for treatment technologies and supported by an approved RFI’s,

Page 69 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

weighbridge reading acquired data(s), results, reports and/or any approved


relevant documents;
• Measurement shall be total weighted in tonnes deducting the net quantities of
water content. In other words, total weighted (final) soils deduct the added water
weight for the treatment;
• Additive weights due to bulking of contaminated soils during pre- or post-
treatment shall not be counted or weighted for the payments. These weights
shall remove from the post treatment weightages
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• Measurement shall be based on weighted quantity in tonnes from the source
feature and categorized as per TPH level/range.
• Rejected treatment material, not meeting the requirements as per Contract shall
not be paid until retested including loading and unloading, sample collection,
re-packing, labelling and transportation etc. , testing and analysis, validation and
QA/QC are solely Contractor’s responsibilities and all additional costs for
complying with all requirements contained in Clause 11.5 of Technical
Specification Portion 1(A&B), whether or not they are specifically mentioned
within the item descriptions.
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents
• Inclusive of cost for Contractor’s specialists in imparting training to Company
operating/maintenance personnel as follows:
➢ Training in vendor’s/Contractor’s premises in Kuwait for up to ten (10)
personnel for a period of three (3) working days; and on-site training for up
to ten (10) personnel for a duration of 90-120 working days.
➢ Contents and schedules of training program will be subject to Company
approval.
➢ Contractor shall arrange the required training resources (reference materials,
laptop computers, screen projectors etc.). Contractor/vendors shall provide
training documents to each participant. All costs for training shall be borne
by Contractor.
➢ Training certificates shall be issued to the participants.

PORTION 4 – SITE WORKS: REMEDIATION WORKS – TPH >7%

4.1 SAMPLE ANALYSIS & DATA MANAGEMENT

4.1.1 Samples analysis & data management Treatment Progress as per Technical
Specification Portion 4 and TS Portion 1(A&B).

Page 70 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

4.1.2 Samples analysis & data management Baselines & Verification as per Technical
Specification Portion 4 and TS Portion 1(A&B).

4.1a Unit of Measurement


Number (No.)

4.1b Pricing

The rates for undertaking Sample analysis & Data Management, other associated
activities & wok required to be carried out and submission of relevant document
deliverables for Company approval in accordance but not limited to Clauses 1.3 &
4.6 of Technical Specification Portion 4 and Clauses 1.2 & 15 of Technical
Specification Portion 1(A&B) shall include but not be limited to the following:

• Utilizing of all necessary labour, constructional plant, equipment, material and


any consumables items required for collecting and delivery of samples,
software, hand tools, packaging, labelling, marking, copying, binding, testing,
calibration, obtaining gate passes & permits, clearance, taxes, providing
scaffolds and barricades;
• Conducting manual and/or hand pitting and mechanical soil sampling
collections at various completion depth inclusive UXO anomaly avoidance;
• Return visit to Site where re-sampling or further sampling is required (such as
replacement of lost/destroyed samples during transport to or at the laboratory);
• Rejected samples (i.e. not meeting the requirements in the Technical
Specification) shall not be paid and cost for retest including re-excavation, soil
and/or groundwater sample collection, re-packing, labelling and transportation
are solely Contractor’s responsibilities;
• Providing sufficient protection throughout the Contract period until issuance of
the Certificate of Completion whereupon the permanent monitoring boreholes
will be handed over to the Company;
• Rejecting of data sample result based on validation and/or QA/QC shall be re-
collected and analysed at no cost to the Company;
• Field logs submission according to KOC standards;
• Submission, screening records documented in detail for soil, location, TPH
values, all reports shall be submitted to substantiate and/or support the main
sampling reports;
• Preparation of pre-& final reports, results, documentations and other related
reports), whether or not they are specifically mentioned within the item
description;

4.1c Measurement

• Measurement shall be based in number(s) on the approved Sample analysis &


Data Management associated with approved relevant documents and supported

Page 71 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

by an approved RFI’s;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

4.2 REMEDIATION WORKS FOR CONTAMINATED SOILS


WITH >7% TPH LEVEL

4.2a Unit of Measurement


Tonnes

4.2b Pricing

The rates for undertaking remediation works for contaminated soils with >7% TPH
level, other associated activities & works required to be carried out and submission
of relevant document deliverables in accordance but not limited to Clauses 1.2 & 7
of Technical Specification Portion 1(A&B), and all Clauses stated in Technical
Specification Portion 4, shall include but not be limited to the following:

• Field Treatment Technologies Studies (>7% TPH) with Optimization Study


Report, shall include, but not be limited to, utilization of all necessary labour,
equipment, lab analytical instrumentation , analysis, and prototype treatment
equipment, , mixing with other TPH ranges testing, pre and/or post treatment,
if required to achieve the RTC,material, computer, software, vehicles,
preparation of reports & procedures, the cost for any further revision(s),
assessment and reporting until successful demonstration of meeting the RTC
within the project timeframe, office materials or any other office equipment,
procurement, taxes, permits, analyzing, editing, copying, evaluation,
processing, duplications and all associated costs for complying in accordance
but not limited to all requirements in Clauses 1.2, 8.7 & 13 of Technical
Specification Portion 1(A&B), Clause 3.3 of Tech. Specification Portion 3 &
Clause 3.2 of Technical Specification Portion 4.

If the Contractor conducts the trial outside of Kuwait, it shall pay for the travel
expenses and accommodations for up to four Company personnel to observe the
trial test over one (1) week period in line with Company policies. These costs
shall be included in the price for treatment optimization study.

• Provide and utilize of all necessary labour, equipment and material,


constructional plant, obtaining gate passes & permits, clearance, taxes,
segregation (if required), water, providing treatment areas/pads, fences, access
roads, barricades, signboard, any consumables items required in treatment

Page 72 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

works and coordination to others;


• Segregate waste materials that cannot be treated from the treatment stream and
addressed as per Clause 7.4 of Portion 1(A&B) of the Technical Specifications
(i.e., place in holding area, dispose at extension to the existing NK Landfill, or
dispose offsite as directed by Company). Segregated tar ball materials, if any,
shall be considered as part of the maximum allowable waste product;
• Prepare work plans, method statement and other required Contract documents
and deliverables;
• Mixing and civil works required for handling (including double handling) of
excavated materials in forming temporary stockpiles or spoil heaps to be re-
used for transporting;
• Provide Loading Notes, tracking system (GPS), summary of trips & weight and
Log book to monitor the transported quantity that passed through the
weighbridge;
• Provide water supply sources, recovery, handling, testing, treatment (if
necessary), transportation from and to, and storage from Contractor sources
locations.
• Provide necessary water recovery system, treatment system if required, storage,
and system operation, maintenance, testing and monitoring, transportation and
methods of irrigation, etc.;
• Cleaning of work areas as work progress and/or completion of works return
adjacent areas to condition existing before start of work;
• Cleaning and watering adjacent roadways areas of dust, dirt, and debris caused
by the transportation or spillages as directed by the Company's Superintendent;
• Operation, maintenance, repair, replacement and depreciation of any and all
equipment and treatment system and material required to facilitate the treatment
process;
• Segregation of contaminated soils, breaking of oversized contaminated soils and
weighing,
• Explore and select water supply, manage water storage and treatment, disposal
of reject water, sampling, mixing, handling and monitoring;
• Pre-& Post water supply and/or treatment for usage and recycling and disposal
(if necessary and directed) by Company;
• All Main Works monitoring, sample collection, and analysis that may be
required and all costs associated with reporting treatment progress according to
the requirements outlined in the Contract;
• Providing power supply and accessories, water, telephone, sanitary disposal,
safety, medical, first aid, ambulance, storages, etc.;
• Produce initial Remediation or treatment monitoring, operation, quality
control/reviews of data processing & analysis and other required
sample/laboratory, recording & reporting; and contingent on verification
sample results ;
• Provide the necessary personnel to design, install, commission, operate,
monitor, and maintain the system at the design treatment rate and without

Page 73 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

significant downtime in order to meet the project work;


• Treatment plant system shall be installed, commissioned, operated, and
monitored and decommissioned in accordance with applicable International
Standards and/or Company standards/procedures, the requirements of the
Contract Documents, and the Contractor prepared PEP and other application
documents;
• All costs associated with any and all pre- or post-treatment required.
• All costs associated with treatment any recovered oil and disposal of this
material as per Company’s and KEPA protocols.
• Inclusive of any enhancements or refinements to the remediation methods
required should a treatment method not fulfil the Remediation Treatment
Criteria detailed within the Technical Specification (including but not limited
to additional pre-treatment, secondary or tertiary alike to attain the required
targets).
• Inclusive of costs associated with Contractors proven attempts to obtain
renewable energy sources and water conservation in accordance with Technical
Specification Portion 1(A&B). For treatment plant having a soil greater than 7%
TPH HEM - 10% renewable energy using waste oil product or alternative fuel
for operating equipment or alternative proposed source may utilized.
• All associated costs shall include to execute the disposal of residual oil, waste
water, salt, by-product waste etc. generated by the treatment process, whether
or not they are specifically mentioned within the item description.
• Inclusive of costs for water requirement for the supply, storage, transportation,
and treatment if the Company does not provide water sources and usages. If
Company explores water sources and provide some water requirements to the
Contractor, the Contractor shall in return reimburse the net water associated
costs related to pre-treatment of water (if required) shall be provided in
accordance with unit price provided in Form of Tender Attachment 3.
• All associated costs in providing training for the operation of treatment
equipment plant with full operating system and maintenance. Contractor shall
provide training for each proposed type of equipment in accordance but not
limited to Clause 5 of Technical Specification Portion 4.
• Inclusive of cost for Contractor’s specialists in imparting training to Company
operating/maintenance personnel as follows:
➢ Training in vendor’s/Contractor’s premises in Kuwait for up to ten (10)
personnel for a period of three (3) working days; and on-site training for up
to ten (10) personnel for a duration of 90-120 working days.
➢ Contents and schedules of training program will be subject to Company
approval.
➢ Contractor shall arrange the required training resources (reference materials,
laptop computers, screen projectors etc.). Contractor/vendors shall provide
training documents to each participant. All costs for training shall be borne
by Contractor.
➢ Training certificates shall be issued to the participants.

Page 74 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

4.2c Measurement

• Measurement shall be based in approved quantities in tonnes as executed by


treatment technologies works for contaminated soils with TPH levels 5 % to ≤
7% and TPH levels > 7% and supported by an approved RFI’s, weighbridge
reading acquired data(s), results, reports and/or any approved relevant
documents;
• Measurement shall be total weighted in tonnes deducting the net quantities of
water content. In other words, total weighted (final) soils deduct the added water
weight for the treatment (e.g. final water content minus initial water content
established prior to commencement and end of the treatment technology);
• Any MoM and calculations proposed by the Contractor and approved by
Company representative and any required relevant approved documents as per
the Contract;
• Additive weights due to bulking of contaminated soils during pre- or post-
treatment shall not be counted or weighted for the payments. These weights
shall remove from the post treatment weightages
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• Rejected treatment technology material, not meeting the requirements as per
Contract shall not be paid until retested including loading and unloading, sample
collection, re-packing, labelling and transportation etc. , testing and analysis,
validation and QA/QC are solely Contractor’s responsibilities and all additional
costs for complying with all requirements contained in of Technical
Specification Portion 3, whether or not they are specifically mentioned within
the item descriptions
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

PORTION 5 – SITE WORKS: EXISTING LANDFILL EXPANSION

5.0 EXISTING LANDFILL EXPANSION

5.1 DESIGN OF EXPANSION LANDFILL AS PER 600,000 m³ CAPACITY SHALL


INCLUDES BUT NOT LIMITED TO: Site Sitting and Surveys, Site Geotechnical
and Hydrogeological Studies, Final Design Engineering and Drawings and
Constructability & QA/QC Plans

The lump sum price to undertake Design works of expansion Landfill for a capacity
of 600,000m³ in accordance but not limited to Clauses 8.6 & 13 of Technical
Specification Portion 1(A&B) & All Clauses of Technical Specification Portion 5
including submission of any other relevant documents and deliverables for
Company approval, whether or not they are specifically mentioned within the item
Page 75 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

descriptions.

5.2 CONSTRUCTION OF EXTENSION LANDFILL AS PER COMPANY


APPROVED DESIGN CAPACITY; BUT NOT LIMITED TO: Supply, Construct
and Install of Pits & Bund Walls, HDPE Liner & Gatch, Leachate Systems, Pumps
& Drainages Systems, Landfill Fence & Related Works, Electrical Works &
Mechanical Works, Environmental Works & Portable Instruments and Fire Safety
& Windsocks

5.2a Unit of Measurement


Cubic Meter (m³)

5.2b Pricing

The rates for undertaking Construction of Extension Landfill in accordance with TS


Portion 5. including supply, construction and other associated activities to complete
the works and submission of relevant document deliverables in accordance but not
limited to Clauses 1.2, 1.3, 4.2 & 9.0 of Technical Specification Portion 1(A&B) and
all Clauses stated in Technical Specification Portion 5, shall include but not be
limited to the following:

• Provide all necessary labour and material, Constructional Plant, supply of all
required materials, equipment, power, water and water managements, safety
measures, environmental monitoring networks, site survey, temporary facilities,
tie-in to existing landfill, as-built drawings, protection during transportation,
access road maintenance, signboards, obtaining gate passes & permits,
clearance, taxes, lay-outing, excavation, compaction, trimming, marking, any
consumables items required for landfill expansion and coordination to others;
• Construct an efficient expansion of the existing landfill facility if required and
directed by Company confirmed by trial test and/or pilot study test in
accordance with Kuwait and applicable International Standards to meet
minimum requirements for containment and disposal of untreatable material
and non-treatable or segregated material as directed by the Company;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Review existing UXO clearance and survey records and undertake additional
UXO survey and clearance of Battle area clearance for the existing landfill
extension area, if directed by Company and if necessary and as described in
Clause 10 of Portion 1(A&B) of the Technical Specification;
• Operation, maintenance, and monitoring (OM&M) of the expanded landfill
until defect liability;
• Supply Materials and Testing Equipment for the environmental (OM&M)
during the contract duration;
• Quality control (QC)/reviews of data processing & analysis;
• As built layer of design, equipment and instrument to be installed, layer of
Page 76 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

capping to be listed and all associated works to complete;


• Recording of all finding & reporting as specified, whether or not they are
specifically mentioned within the item description;

5.2c Measurement

• Measurement shall be based on approved work executed progress of landfill


equivalent in cubic meter (m³) as per approved Progress Measurement System
(PMS) and supported by an approved RFI’s and/or any approved relevant
documents;
• Any MoM and calculations proposed by the Contractor to justify the quantities
in the landfill and approved by Company representative and any required
relevant approved documents as per the Contract;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;

5.3 (INFILLING) FOR LANDFILL EXTENSION CAPACITY IN ACCORDANCE


WITH THE REQUIREMENT OF TECHNICAL SPECIFICATION PORTION
1(A&B) & 2

5.3a Unit of Measurement


Tonnes

5.3b Pricing
The rates for undertaking Operation, transportation, disposal and filling at Landfill
in accordance with TS Portion 5 including operation and disposal off untreatable
contaminated soils as compacted, other associated activities to complete the works
and submission of relevant document deliverables in accordance but not limited to
Clauses 1.2, 4.2, 7.4, 9 & 13.6.6 of Technical Specification Portion 1(A&B), Clauses
3.3, 3.4, 3.6, 3.7, 3.8 & 7.3 of Technical Specification Portion 2 and Clauses 1.2 &
All clauses of Technical Specification Portion 5, shall include but not be limited to
the following:

• Provide all necessary labour and material, Constructional Plant, supply of all
required materials, equipment, power, water and water managements, safety
measures, environmental monitoring networks, site survey, temporary facilities,
tie-in to existing landfill, as-built drawings, protection during transportation,
access road maintenance, signboards, obtaining gate passes & permits,
clearance, taxes, lay-outing, excavation, compaction, trimming, marking, any
consumables items required for landfill expansion and coordination to others;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Loading, Transportation and Disposal of untreatable contaminated soils at
expanded landfill Provide QA/QC plan and procedures during the construction
Page 77 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

of the expansion landfill facility.


• Compaction, moisture conditioning (during pre- & post excavation and
disposal), spreading and testing (if applicable) of untreatable contaminated
materials to the expanded landfill.
• Re-compaction for each lift which does not meet the compaction requirement
at no additional cost.
• Conduct pre-post topographic survey during disposal activities to monitor the
filling quantity and submit to Company for review and approval on a planned
schedule or as directed by the Company;
• Quality control (QC)/reviews of data processing & analysis;
• As built layer of design, equipment and instrument to be installed, layer of
capping to be listed and all associated works to complete;
• Recording of all finding & reporting as specified, whether or not they are
specifically mentioned within the item description;

5.3c Measurement

• Measurement shall be based in approved quantities disposed in the landfill in


tonnes, compacted within the range of 85-90% of the maximum density of the
modified proctor test and supported by an approved RFI’s and/or any approved
relevant documents;
• Any MoM and calculations (i.e. pre-during and post topographic survey,
contouring, 3D formats, by trips, by weighbridge reading and or others method
in calculating the quantities) as proposed by the Contractor to justify the
quantities in the landfill and approved by Company representative and any
required relevant approved documents as per the Contract;
• The lowest quantities shall be prevailing after comparing the quantities
calculated as per any proposed and agreed methodology;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents.

5.4 SUPPLY AND INSTALL CAPPING AND COMMISSIONING FOR LANDFILL


EXTENSION CAPACITY AS PER APPROVED DESIGN BUT NOT LIMITED
TO: Supply, Construct and Install of HDPE Liner Cover, Soil Covers, Gatch,
Gravel layer Cover, Geotextile protective layer, Gas vent pipes / Biological
Chambers and Environmental System and Environmental Compliance Reporting.

5.4a Unit of Measurement


Cubic Meter (m³)

Page 78 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

5.4b Pricing

The rates for undertaking Supply and Install Capping and commissioning for
landfill extension in accordance with Technical Specification Portion 5, other
associated activities to complete the works and submission of relevant document
deliverables in accordance but not limited to Clauses 1.2, & 9.5 of Technical
Specification Portion 1(A&B) and all Clauses of Technical Specification Portion 5,
shall include but not be limited to the following:
• Construction, handling, procurement, importation, clearing, grubbing &
levelling of soils and all works related to this item, approval of locations and
subsequent re-exportation of materials, waste handling and disposals and
vehicles of whatever type or size required for the performance of the Work,
provision of necessary certification, custom Clearance, duties, taxes, levies,
obtaining necessary permits & licenses required to operate at Work site for the
execution of the Work, submission of any other relevant documents and
deliverables for Company approval whether or not they are specifically
mentioned within the item description.
• Provide all necessary labour and material, Constructional Plant, supply of all
required materials, equipment, power, water and water managements, safety
measures, environmental monitoring networks, site survey, temporary facilities,
tie-in to existing landfill, as-built drawings, protection during transportation,
access road maintenance, signboards, obtaining gate passes & permits,
clearance, taxes, lay-outing, excavation, compaction, trimming, marking, any
consumables items required for landfill expansion and coordination to others;
• Preparing work plans, method statement and other required Contract documents
and deliverables;
• Loading, Transportation and Disposal of untreatable contaminated soils at
expanded landfill Provide QA/QC plan and procedures during the construction
of the expansion landfill facility.
• Compaction, moisture conditioning (during pre- & post excavation and
disposal), spreading and testing (if applicable) of untreatable contaminated
materials to the expanded landfill.
• Conduct pre-post topographic survey during disposal activities;
• Quality control (QC)/reviews of data processing & analysis;
• As built layer of design, equipment and instrument to be installed, layer of
capping to be listed and all associated works to complete;
• Supply spare parts as per Contract requirements
• Recording of all finding & reporting as specified, whether or not they are
specifically mentioned within the item description;

5.4c Measurement

• Measurement shall be based on approved work executed progress of landfill


equivalent in cubic meter (m³) as per approved Progress Measurement System

Page 79 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

(PMS) and supported by an approved RFI’s and/or any approved relevant


documents;
• Measurement shall be based on equivalent approved quantities compacted
disposed in the landfill in cubic meter (m³) and supported by an approved RFI’s
and/or any approved relevant documents;
• Any MoM and calculations (i.e. pre-post topographic survey, contouring, 3D
formats, by trips, by weighbridge reading and or others method in calculating
the quantities) as proposed by the Contractor to justify the quantities in the
landfill and approved by Company representative and any required relevant
approved documents as per the Contract;
• The lowest quantities shall be prevailing after comparing the quantities
calculated as per any proposed and agreed methodology;
• Providing calculation sheets as per approved measurement plan/re-
measurement calculation sheets (RMCS) referring to the relevant approved
documents in accordance with the requirements of technical specifications;
• All interim measurements will be verified and agreed during final measurement
based in all relevant approved documents;
• Provide training service to Company’s personnel on environmental
management as to be developed for the expansion, and operation and
maintenance of equipment and material as described in this Technical
Specification Portion 5;
• Inclusive of costs associated with Contractors proven attempts to obtain, in
accordance with Technical Specification Portion 1(A&B), energy through
renewable energy sources and water conservation an operational energy
consumption for leachate pumps and lighting, 15% supplied by renewable
energy.

6.0 KUWAITIZATION

The Lump sum price for undertaking Kuwaitization shall include all necessary costs
to comply with requirement as specified in Clauses 6, 12.3.13, Annexure I & II of
Contract Specification but not limited to salaries of Kuwaiti Nationals and
overheads of any nature (such as Taxes, Insurances, benefits & like).
These costs will be paid on an incurred prorated basis (monthly).

Signed : ________________________________

Name : _________________________________

Designation : _________________________________

For and on behalf of : _________________________________

Page 80 of 81
INCOMPLETE TENDER PACKAGE
(FOR REFERENCE PURPOSE)
METHOD OF MEASUREMENT
-For-

ENVIRONMENT REHABILITATION PROGRAM UNDER UN LEGISLATION FOR INDEMNIFICATION

NORTH KUWAIT EXCAVATION TRANSPORTATION AND REMEDIATION (NKETR)

Date : _________________________________

Page 81 of 81