Concrete Production: Sika Viscocrete Technology For Precast Concrete
Concrete Production: Sika Viscocrete Technology For Precast Concrete
Maia, Portugal
Sika at Work
Project
Between January and March 2004 the CIVIBRAL precast factory was
producing concrete “delta” beams and “I” beams as well as stair panels for a
major project in Portugal.
Requirements
Max. diameter of aggregate: 15 mm
W/C ratio < 0.5
High early strength: 29 Mpa after 16 hours
Sika Solution
For the 4000m3 of concrete for this special project
Sika® ViscoCrete®20 HE has been used.
All the requirements of the concrete and the finished elements were fulfilled
using the Sika® ViscoCrete® Technology.
Sika Services AG
Corporate Construction
CH8048 Zürich
Switzerland
Phone +41 44 436 40 40
Fax +41 44 436 46 86
www.sika.com
Sika® ViscoCrete® Technology
for Precast Concrete Case Studies
Essex County "Sportsplex" Parking Structure, Viaduct de Herve and Battice,
Newark, New Jersey, USA Belgium
Project Project
A new Parking Structure at the "Bears" Baseball Stadium with a total of A railway bridge with a total length of 459 m between the cities of Herve and
around 9'200 m2 was built in March/April 2004 in Newark. To keep to the Battice in Belgium. The beams between the Ycolumns will be precast and
short construction and erection time, precast concrete elements have been then installed on site. The biggest beam has a weight of 240 tons and is
used as follows: 30 m long. The project started in 2003 and will be finished in 2005. The total
1900 m of Double Tee Girders 130 m of Lifewalls concrete volume for the beams will be approx. 18'000m3.
100 m of Beams 210 m of Shearwalls
95 m of Columns 23 m of Stair Panels
530 m of Spandrel Panels Requirements
Strength development without heating of the concrete beams:
Requirements to >40 N/mm2 after 16 hours
Air stability in all precast concrete elements The required concrete performance should be reached with only one ad
High early strength for all precast concrete elements mixture
Project Participants
Owner: Essex County Department of Public Works, Verona, HJ, USA
Architect: Clarke Caton Hintz, Trenton, NJ
Engineer: Fay, Spofford & Thorndike, LLC, West Caldwell, NJ
Construction Manager/General Contractor:
Prismatic Development Corporation, Little Falls, NJ
Precast Subcontractor: Nitterhouse Concrete Products, Inc., Chambersburg, PA
Requirements Requirements
Cost reduction in: W/C ratio: 0.40
Man hours increased production High early strength > 38 N/mm2 in 14 hours
Cement consumption high early strength (16 hours) Good consistency of the concrete mix
Environment noise, vibration, cement reduction
Sika Solution
Sika Solution All the required properties are easily achieved with the Sika® ViscoCrete®
With a well defined mix design of the concrete using Technology.
Sika® ViscoCrete®20 HE Technology all of the required properties for For the daily production of approx. 180 m3 Sika® ViscoCrete®20 HE
the concrete of the precast elements are more than fulfilled. admixture is used.
Sika® ViscoCrete® Technology
for Precast Concrete Case Studies
Essex County "Sportsplex" Parking Structure, Viaduct de Herve and Battice,
Newark, New Jersey, USA Belgium
Project Project
A new Parking Structure at the "Bears" Baseball Stadium with a total of A railway bridge with a total length of 459 m between the cities of Herve and
around 9'200 m2 was built in March/April 2004 in Newark. To keep to the Battice in Belgium. The beams between the Ycolumns will be precast and
short construction and erection time, precast concrete elements have been then installed on site. The biggest beam has a weight of 240 tons and is
used as follows: 30 m long. The project started in 2003 and will be finished in 2005. The total
1900 m of Double Tee Girders 130 m of Lifewalls concrete volume for the beams will be approx. 18'000m3.
100 m of Beams 210 m of Shearwalls
95 m of Columns 23 m of Stair Panels
530 m of Spandrel Panels Requirements
Strength development without heating of the concrete beams:
Requirements to >40 N/mm2 after 16 hours
Air stability in all precast concrete elements The required concrete performance should be reached with only one ad
High early strength for all precast concrete elements mixture
Project Participants
Owner: Essex County Department of Public Works, Verona, HJ, USA
Architect: Clarke Caton Hintz, Trenton, NJ
Engineer: Fay, Spofford & Thorndike, LLC, West Caldwell, NJ
Construction Manager/General Contractor:
Prismatic Development Corporation, Little Falls, NJ
Precast Subcontractor: Nitterhouse Concrete Products, Inc., Chambersburg, PA
Requirements Requirements
Cost reduction in: W/C ratio: 0.40
Man hours increased production High early strength > 38 N/mm2 in 14 hours
Cement consumption high early strength (16 hours) Good consistency of the concrete mix
Environment noise, vibration, cement reduction
Sika Solution
Sika Solution All the required properties are easily achieved with the Sika® ViscoCrete®
With a well defined mix design of the concrete using Technology.
Sika® ViscoCrete®20 HE Technology all of the required properties for For the daily production of approx. 180 m3 Sika® ViscoCrete®20 HE
the concrete of the precast elements are more than fulfilled. admixture is used.
CIVIBRAL Precast Factory, No 6 / 2004 Corporate Construction
Maia, Portugal
Sika at Work
Project
Between January and March 2004 the CIVIBRAL precast factory was
producing concrete “delta” beams and “I” beams as well as stair panels for a
major project in Portugal.
Requirements
Max. diameter of aggregate: 15 mm
W/C ratio < 0.5
High early strength: 29 Mpa after 16 hours
Sika Solution
For the 4000m3 of concrete for this special project
Sika® ViscoCrete®20 HE has been used.
All the requirements of the concrete and the finished elements were fulfilled
using the Sika® ViscoCrete® Technology.
Sika Services AG
Corporate Construction
CH8048 Zürich
Switzerland
Phone +41 44 436 40 40
Fax +41 44 436 46 86
www.sika.com