S.L Name of Item Uni T Hasan Remarks
S.L Name of Item Uni T Hasan Remarks
Uni
S.L Name of Item Remarks
t
1. NTCL will provide Roof hoist, Mixture Machine, Vibrator machine, Welding machine, Plate Compactor, Mud pump, Rod,
Cement, Sand, Stone Chips, Brick, Brick chips, Water, Chemical, Electrode rod,Bucket, Drum, Ropes, Polythine,Cup brush,
old Mobil, Foam, Labor shade, Electricity and all Shuttering materials.
2. The Sub-Contractor will provide Rod cutting machine, granding machine and other equipment if needed.
3. All machine operator (Roof hoist, Mixture machine, Welding machine, Rod cutting machine) supply by sub-contractor.
4. NTCL will provide Curing man.
5. Spade, Shovel, Rupban Sheet, All Nails, 24 no Gi wire& others materials supply by sub-contractor.
6. 4% will increase for every floor from 1st Floor.
7. Tk.300 (Three Hundred) will be given per day per worker for day.
8. 10% Security money deduction from each running bill which will be paid after 3 months of completion of the project.
9. No intermediate enhancement in rate will be allowed till completion of the project.
10. All incidental expenses are to be borne by the sub-contractor. NTCL will not pay any compensation, donation to the
workers for any fatal incidents or any incidental expenses.
11. The sub-contractor is fully responsible for the safety and security of his employed workers and shell bear all legal
consequences, if any.
12. Work should be as per Drawing for any faulty and defective works done by the sub-contractor shall be rectified by the
sub-contractor at his own cost.
13. Before brick work, bricks must be wet 24 hours in the water house.
14. Rate of any non-schedule items of works (if any) shell be settled by mutual consent of both the parties as per market
rate.
15. Final bill will be made only after satisfactory completion of work.
16. Management reserves the right to cancel the contract at any time or stages of the work/item are satisfactory.
17. If the sub-contractor failure to complete the work, security money will be not paid & that balance work will be done by
the other contractor.
18. Sub-contractor must clean site area every day after finish the work by his own expenses and responsibility as per
instruction of Engineer-in-charge, rubbish/dust will be removed to the specific space area if sub-contractor failure to
clean the site area. NTCL will take responsibility to clean &that expenses will deduct from the sub-contractor’s bill.