NOVEMBER 2013 51311/SAZ5C

Time : Three hours Maximum : 75 marks

SECTION A — (10 × 2 = 20 marks)


Answer any TEN questions.
All questions carry equal marks.
Each answer should not exceed 30 words.

1. Write any two features of operations Research


Solution.

2. Mention the advantages of Linear Programming.

3. Define Surplus variable.

4. What do you mean by an optimal basic feasible


solution to a linear programming problem?

5. What is mean by duality?

6. Define North west corner rule.

7. What is an assignment problem?

8. Define sequencing problems.

9. Write a rules to determine saddle point.

10. What is pay – off matrix?


11. What is predecessor and successor activities in
network diagram?

12. Define Simulation. Why is simulation used?


SECTION B — (5 × 5 = 25 marks)
Answer any FIVE questions.
All questions carry equal marks.
13. Explain the general mathematical model of linear
programming problem.
14. Use the graphical method to solve the following
LP problem.
minimize z = − x1 + 2x2
Subject to the constraints: − x1 + 3 x2 ≤10
x1 + x2 ≤ 6
x1 − x2 ≤ 2
and x1 ; x2 ≥ 0.
15. Compute all the basic feasible solution to the LP
problem
maximize z = 2 x1 + 3 x2 + 4 x3 + 7 x4
subject to the constraints 2 x1 + 3 x2 − x3 + 4 x4 = 8
x1 − 2 x2 + 6 x3 − 7 x4 = − 3
and x1 , x2 , x3 , x4 ≥ 0.

2 51311/SAZ5C
16. Describe the computational procedure of
optimality test in a transportation problem.

17. We have five jobs, each of which must be processed


on the two machines A and B in the order AB.
Processing times in hours are given in the table
below.
Job 1 2 3 4 5
Machine A 5 1 9 3 10
Machine B 2 6 7 8 4

Determine a sequence for the five jobs that will


minimize the elapsed time T.
18. Player A is paid Rs 8/- if two coins turn both heads
and Rs 10/- if two coins turn both tails. Player B is
paid Rs 3 when the two coins do not match. Give
the choice of being A or B, which one would you
choose and what would be your stratergy?
19. A bakery keeps stock of a popular brand of cake –
previous experience shows the daily demand
pattern for the item with associated probabilities,
as given below.
Daily
Demand : 0 10 20 30 40 50
Probability 0.01 0.20 0.15 0.50 0.12 0.02
Use the following sequence of random numbers to
simulate the demand for next 10 days.
Random number: 25, 39, 65, 76, 12, 05, 73, 89, 19, 49
Also estimate the daily average demand for the cakes
on the basis of simulated data.
3 51311/SAZ5C
SECTION C — (3 × 10 = 30 marks)
Answer any THREE questions.
All questions carry equal marks.

20. A trucking firm has received an order to more


3,000 tonnes of industrial material to a
destination 1,000km away. The firm has available
at the moment a fleet of 150 class – A 15 tonne
trailer trucks and another fleet of 100 class – B 10
tonnes trailer trucks. The operating costs of these
trucks are Rs 3 and Rs 4 pertonnes per km,
respectively. Based on past experience, the firm
has a policy of retaining at least one class – A
truck with every two class – B trucks in reserve. It
is desired to know how many of these two classes
of vehicles should be dispatched to move the
material at minimal operating costs.
Formulate this problem as an LP model.

21. Use the penalty method to solve the following LP


problem.
maximize z = 2 x1 + x2 + 3 x3

subject to constraints : x1 + x2 + 2 x3 ≥ 5

2 x1 + 3x2 + 4 x3 =12

and x1 , x2 , x3 ≥ 0

4 51311/SAZ5C
[P.T.O.]
22. The following table shows all the necessary
information in the availability of supply to each
warehouse, the requirement of each market and
unit transportation cost (in Rs) form each
warehouse to each market.
Market

P Q R S Supply

A 6 3 5 4 22

Warehouse B 5 9 2 7 15

C 5 7 8 6 8

Demand 7 12 17 9 45

The shipping clerk has worked out the following


schedule form experience:
12 units from A to Q
1 units from A to R
8 units from A to S
15 units from B to R
7 units from C to P
and 1 units from C to R
(a) Check and see if the clerk has the optimal
schedule.
(b) Find the optimal, schedule and minimum
total transport cost.
5 51311/SAZ5C
23. Five workers and available to work with the
machines and the respective cost(Rs) associated
with each worker – machine assignment are give
below. A sixth machine is available to replace one
of the existing ones and the associated costs are
also given below.
Machines

M1 M2 M3 M4 M5 M6

W1 12 3 6 – 5 9

W2 4 11 – 5 – 8

Workers W3 8 2 10 9 7 5

W4 – 7 8 6 12 10

W5 5 8 9 4 6 1

(a) Determine whether the new machine canbe


accepted.
(b) Also determine optimal assignment and the
associated saving in cost.

24. A project consists of the activities A, B, C ….H, I,


and x < y means that the activity x must be
completed before y can start, and x, y< w means
that ‘w’ will start only after completion of
activities x and y. With the notation construct the
network diagram for the following constraints.
A < D; A < E; B < F; C < G, D < H; E, F < I
The project has the following time schedules of the
above activities.
6 51311/SAZ5C
Task: A B C D E F G HI

Optimistic (to) time 5 18 26 16 15 6 7 7 3

Pessimistic time(tp) 10 22 40 20 25 12 12 9 5

More likely time,(tm) 8 20 33 18 20 9 10 8 4

Determine the following


(a) Draw the network diagram of activities and
determine the cirtical path.
(b) The probability of an event occurring at the
expected completion date if the original
schedule time of completing the project is
41.5 weeks.

———————

7 51311/SAZ5C