-PROPOSED SOFT AND HARD LANDSCAPING WORK FOR PARK
(STAGE 1), SIGNAGE & SHOW HOUSES AND SOFT LANDSCAPING
WORKS FOR CLUBHOUSE.

METHOD OF STATEMENT:
RC WALL BETWEEN FEATURE WALL & RAMP
Rev 01

Prepared by; Verified by; Approved by;

……………………………………. …………………………………….
(Muzaime Bin Razali) ……………………………………. ( )
Position: Landscape Architect ( ) Position :
Company: Spaes Design Studio S/B Position: Company:
Date : 26/02/2019 Company:
Date:
Date:

Rev 01
ATTACHMENT 2

METHOD OF STATEMENT FOR RECTIFICATION OF RC WALL BETWEEN WALL


& RAMP

1.0 PURPOSE

This method statement is to simplify the works sequences for rectification RC


wall between wall and ramp.

The method statement also is intended to assist site personnel in the


performance of the above activity. The method also serves to inform the client
that the contractor has studied the requirement and is capable of undertaking
scope of works.

2.0 MATERIAL

All material or raw materials to be used shall be complied with specification or


consultant approval. Materials used are as follows: -
a) Concrete
b) Plywood (for protection)
c) Well barrow
d) Form work
e) Starter bar
f) And all other tools that related

3.0 INSTALLATION & PROCEDURES


Step 1: Clean it up.
Make sure all the area clean before starting the construction work

Step 2: To dismantle existing handrailing and do protection work.


To properly dismantle existing handrailing at the ramp area and protect by
using plywood to the existing grass crete block and walkway.

Step 3: Hacking out existing wall ramp.


To hack the existing wall and 100mm width walkway (until the groove line).

Step 4: To clean away unused material.


To removed and clean away unused material (concrete waste) after hacking
work before proceeding with construction of RC wall.

Step 5: Installation of starter bar.


To install anchor starter bar at the bottom of the wall.

Step 6: Installation of form work.


To install form work before proceeding with concreting work.

Rev 01
ATTACHMENT 2

Step 7: Concreting work.


To start concreting work (site mix) by pouring from the top.

Step 8: Tidy it up.


To open back all the formwork, tidy up all the affected area, open back all
the protection, install back the handrailing and making good the area.

Step 9: Handover the area


To call for the inspection and handover the area.

Note: All procedures stated is subjected to revise, amend and / or other


alternatives and future discussion with parties involved.

We’ll follow the construction drawing for the installation on rebar.

4.0 MANPOWER

Proposed minimum 1 gang of workers consists of 1 foreman, 2 skilled, 2 semi-


skilled. Gangs of workers will be increased or will be revised based on
subcontractor manpower from time to time upon request and subject to volume
of works available.
Overall there will be minimum one chief foreman to overall in-charge the project.

5.0 QUALITY CONTROL OF WORKS

In order to ensure the works are complying with the specification requirement,
all progress stages shall be monitored closely by consultant. Final inspection
shall be arranged ones the works completed.

6.0 SAFETY

We shall comply with local authority safety regulations and requirements. For
personal protection equipment such as: -
~ PPE – Helmet
~ Safety Shoe
~ Safety Belt – if required

Rev 01