Professional Documents
Culture Documents
Wall Statioons
Wall Statioons
PROJECT REPORT
OCTOBER, 2016
RESEARCH TOPIC:
BRAD COSTELLO
STUDENT NUMBER:
0061046613
SUPERVISOR:
ZAHRA GHARINEIAT
ABSTRACT
The wellbeing of the mine and underground workers directly rely on the accuracy of wall stations that
controls the workings on the mine. Some of the daily responsibilities of a mine surveyor comprise of
staking out construction lines to control the direction and gradient of development drives. When there
is deviation in the direction and gradient of construction lines in relation to the design it can lead to
damage to infrastructure within the mine that causes problems such as re-development or altering
designs which are expensive. This is why it is significant high order check surveys are undertaken to
follow up advancing capital development as a means to verify the quality of existing wall stations and
provide accurate control to further advance into the mine.
The objective of the proposed research is to perform a high order control survey and adjust the
observations of the traverse using a least squares adjustment incompliance with ICSM Class “D”.
Variables of the network will be statistically assessed and important considerations in the check survey
will be identified to educate and render the importance of check surveying.
Slope distance, direction and vertical angles were analysed to assess the quality of the check survey.
It was observed that the greatest standardised residuals were located at the start and end of the
survey. The assumption is that the traverse is closing onto another fixed control point which will lead
to variation. Integrity of the original fixed control points was questioned as the fixed stations were
verified in a check survey three years ago. Over three years wall stations are expected to move due to
the nature of the mine.
The absolute and relative error ellipses were analyse at a 95% confidence interval. It was observed
that there was an azimuth deficiency in the Eastern direction which was caused by the orientation of
the fixed control. The relative ellipses semi-major axis did not exceed the limitation of 50mm with the
greatest semi-major axis being 27mm.
The dissertation is to help mine surveyors understand the process of check surveys and show the
importance of regularly performing high order controls surveys. While rendering the possible issues
that can affect accuracy and quality when completing an underground check survey.
3
University of Southern Queensland
Faculty of Health, Engineering and Sciences
ENG4111/ENG4112 Research Project
LIMITATIONS OF USE
Persons using all or any part of this material do so at their own risk,
and not at the risk of the Council of the University of Southern
Queensland, its Faculty of Health, Engineering & Sciences or the staff
of the University of Southern Queensland.
4
CERTIFICATION OF DISSERTATION
I further certify that the work is original and has not been previously
submitted for assessment in any other course or institution, except
where specifically stated.
BRAD COSTELLO
_____________________
STUDENT NUMBER:
0061046613
5
ACKNOWLEDGEMENTS
Mr Frank Smith played a key role in the dissertation providing CompNet least
squares adjustment program. Not only did Mr Smith generously loan the
program but also provided feedback and direction with his extensive knowledge
in relation to control networks.
Luke Czaban and Callum McNaughton were a great help throughout the year
providing constructive feedback and offering their time on short notice.
6
TABLE OF CONTENTS
2.2 Standards and Practices for Control Surveys (SP1) v2.1; ICSM............................................. 18
2.4 Recent Changes in Underground Traversing Techniques in Western Australia – A.Jarosz &
L.Shepherd......................................................................................................................................... 27
7
3.7 Check Survey Processing ....................................................................................................... 37
4.4 Traversing.............................................................................................................................. 46
8
4.7 Conclusion ............................................................................................................................. 53
5.3.5 Ventilation..................................................................................................................... 57
9
7. Chapter 7 – Recommendations .................................................................................................... 84
8. References .................................................................................................................................... 87
9. Appendices .................................................................................................................................... 90
10
LIST OF FIGURES
Figure 2-1 Wall Station Leica Circular Prism (McCormack, 2002)......................................................... 24
Figure 2-2 Aluminium Sleeve (McCormack, 2002)................................................................................ 25
Figure 2-3 Two Point Resection (Grocock, 2014) .................................................................................. 25
Figure 2-4 Three Point Resection (Grocock, 2014) ............................................................................... 26
Figure 2-5 Replacement of Right Angled Triangles with Narrow Triangles (Shepherd & Jarosz, 2006)
.............................................................................................................................................................. 28
Figure 3-1 Mount Isa, Queensland Map (Mount Isa Mines Rotary Rodeo, 2016) ................................ 32
Figure 3-2 Wall Station Prism placed into Sleeve ................................................................................. 33
Figure 3-3 Check Survey traversing up the Incline................................................................................ 36
Figure 4-1 Survey Network in CompNet ............................................................................................... 42
Figure 4-2 CompNet Adjustment Measures ......................................................................................... 43
Figure 4-3 High Precision & Low Accuracy ............................................................................................ 44
Figure 4-4 High Accuracy & Low Precision ............................................................................................ 45
Figure 5-1 Standardised Residuals – Slope Distances ........................................................................... 59
Figure 5-2 Derived RMS Deviation Slope Distances .............................................................................. 60
Figure 5-3 Derived RMS Deviation Direction ........................................................................................ 61
Figure 5-4 Derived RMS Deviation Vertical Angle................................................................................. 61
Figure 5-5 Effect of Derived RMS Deviation ......................................................................................... 62
Figure 5-6 Metres Derived RMS Deviations .......................................................................................... 62
Figure 5-7 5-20 Metres Derived RMS Deviations .................................................................................. 63
Figure 5-8 Direction and Vertical Angle Standardised Residuals .......................................................... 64
Figure 5-9 Vertical Angle Offsets .......................................................................................................... 65
Figure 5-10 Error Rectangle .................................................................................................................. 66
Figure 5-11 Absolute Error Ellipses ....................................................................................................... 68
Figure 5-12 2D Absolute Ellipses 95% CI ............................................................................................... 69
Figure 5-13 Adjusted Coordinates ........................................................................................................ 70
Figure 5-14 Orientation of Fixed Stations ............................................................................................. 71
Figure 5-15 Two Point Resection .......................................................................................................... 73
Figure 5-16 Three Point Resection ........................................................................................................ 74
Figure 5-17 Four Point Resection .......................................................................................................... 75
11
LIST OF TABLES
Table 2-1 Classification of Horizontal Control Survey (Inter-governmental Committee on Surveying and
Mapping (SP1) v1.7, 2007) .................................................................................................................... 20
Table 2-2 Horizontal Angle Observation Requirements (Inter-governmental Committee on Surveying
and Mapping (SP1) v1.7, 2007) ............................................................................................................. 22
Table 2-3 Astronomical Azimuth Observation Requirement (Inter-governmental Committee on
Surveying and Mapping (SP1) v1.7, 2007) ............................................................................................ 23
Table 5-1 Two Point Resection Options ................................................................................................ 73
Table 5-2 Two Point Resection Solutions .............................................................................................. 73
Table 5-3 Three Point Resection Options ............................................................................................. 74
Table 5-4 Three Point Resection Solutions ........................................................................................... 75
Table 5-5 Four Point Resection Options ............................................................................................... 76
Table 5-6 Four Point Resection Solutions ............................................................................................. 77
12
ABBREVIATIONS & NOMENCLATURE
B&D – Bearing and distance
CI – Confidence Interval
SF – Scale Factor
TS – Total station
SP1 – Special Publication 1 (Standard for the Australian Survey Control Network)
ENT – Enterprise
PU – Positional Uncertainty
RU – Relative Uncertainty
SU – Survey Uncertainty
13
1. CHAPTER 1: INTRODUCTION
1.1 OVERVIEW
Mount Isa Mines is controlled by Glecore Xstrata Copper which is a section of its North Queensland
Operations. Some of the tasks involve mining, processing and smelting processes in Mount Isa and just
mining and processing at Cloncurry and then Townsville control refining and port operations. The
method of mining used at Mount Isa involves the ore broken down underground and then transported
to the surface. Once the ore has been brought to the surface it is then grounded finely and then goes
to the flotation operation, in this stage the copper- bearing sulphide minerals are separated and
concentrated from the waste. Once the ore has completed these processes, the concentrated ore is
sent to the smelter.
At Mount Isa Copper Operations (MICO) there are two underground mines which are called X41 and
Enterprise (ENT). The survey department at Mount Isa performs surveys in both X41 and Enterprise to
meet the demands of production and development of the mine. In order for the surveying department
to remain confident in their everyday work, checks need to be implemented which is why check
surveys are completed. Check survey traverses are an integral part of underground mine surveying. A
check survey involves using high precision surveying techniques to transfer survey control from an
area of established checked control to one with either no control, or survey control of low order. High
order check surveys will follow up advancing capital development as a means to verify the quality of
existing wall stations and provide accurate control to further advance into the mine.
1.2 BACKGROUND
“In underground mines the mine surveyor will determine and control the location and direction of
tunnels as well as the mapping of all underground tunnels” (Surveyors Board of Queensland, 2016).
Some of the work that an underground metalliferous surveyor can perform includes:
14
- Survey for raisebore set outs
- Survey for diamond drill hole set outs
- Survey for Cavity Monitor Scan (CMS) and Cavity Auto scanning Laser System (CALS)
In order to relay mining instructions to underground mining staff, a survey memorandum is created
detailing the control that survey have provided, how it relates to the design that is to be mined and
any pertinent safety information that the miner should be aware of.
With the constant demand of the mine, the survey department is required to communicate
instructions to mining staff as to what needs to be done. The mine surveyor must be able to ensure
that all the survey work is in the correct position in relation to the mine’s baselines to prevent mishaps
such as; drilling operations drilled in the wrong position and not hitting the target which impacts on
the production of the mine and raise bore drilling machine not hitting their targets. It is essential that
mine surveyors prevent mishaps like these from happening as problems can potentially cost jobs,
money and lives.
As a general operating procedure, high order “check” surveys will follow up advancing capital
development as a means to verify the quality of existing wall stations and provide accurate control to
further advance into the mine.
Check surveys is a procedure which all mine surveyors should understand the importance and
processes of. As no literature was found that discussed the process of the check survey method the
dissertation aims to outline the need for check surveying and the important considerations of the
practice.
- Perform a high order control survey and adjust the observations of the traverse using a least
squares adjustment.
- The observations in the check survey to the wall stations will be will be in compliance with the
ICSM standards of a Class “D” primary survey control network.
- The least squares adjustment will be broken down to analyse the results of slope distances,
directions and vertical angles and analyse the behaviour and reasoning of the survey data.
- Absolute and relative error ellipses at 95% confidence will be analysed and a summary of the
size, shape and orientation will be outlined.
15
- The wall station resection method will be theoretically analysed to portray the importance of
the number of wall station in a resection and the geometrical relationship of the instrument
to the wall stations.
- The main objective is to help mine surveyors understand the process of check surveys and
show the importance of regularly performing high order controls surveys. While rendering the
possible issues that can affect accuracy and quality when completing an underground check
survey.
1.4 JUSTIFICATION
Mine surveying has been well-defined by the International Society of Mine Surveyors as “the art of
making such field observations and measurements as are necessary to determine the positions, areas
or volumes of natural and man-made features on the earth's surface” (International Society for Mine
Surveying, 2011).
The environment of an underground mine in which the mine surveyor performs everyday tasks is
regulated by accuracy requirements imposed by the country. The wellbeing of the mine and workers
directly rely on the accuracy of survey network wall stations that controls the workings on the mine.
A mine surveyor has daily responsibilities that need to be implemented to exacting limits of error.
Some of the daily responsibilities of a mine surveyor comprise of staking out construction lines to
control the direction and gradient of development drives. When there is deviation in the direction and
gradient of construction lines in relation to the design it can lead to damage to infrastructure within
the mine that causes problems such as re-development or altering designs which are expensive.
Permanent damage to the infrastructure of the mine can be caused by grading and directions having
deviation from what was planned and designed. These deviations can potentially lead to altering the
design of the mine that was originally intended or making amendments to the development which are
both expensive outcomes. Consequently, it’s vital that the quality of the accuracy of primary survey
network is in compliance with the standards of accuracy and the wall stations used to stake out
information are in agreement to the mine’s design.
Correlation between surface and underground mine workings are only confirmed and verified when
there is a breakthrough between levels or a check survey is completed. Where the check survey is
completed to verify the original survey and strengthen the quality of the survey network used to set
out mining operations.
16
1.5 CONCLUSION
The unforgiving environment of an underground mine make the performance of relatively simple tasks
for a mine surveyor difficult. Underground surveying requires a high level of accuracy and care in
everyday tasks. The difference between other branches of surveying and mine surveying is the
mitigation of risks and the significances related to making mistakes prove to be fatal in a mine. As the
wall stations are used every day for resections to determine the instruments position to stake out
information, the primary control network must be verified. Errors in the wall stations means that there
is errors in setting out information for production and development needs which can be fatal.
The check survey is an essential duty for a mine surveyor to maintain the integrity of the primary
survey control of the mine. In conclusion, the objective of this dissertation is to complete a high order
control survey and assess the least squared adjustment. The adjustment will be analysed and variables
will be assessed to portray the effects on the accuracy of the adjustment.
17
2. CHAPTER 2: LITERATURE REVIEW
2.1 INTRODUCTION
The objective of this chapter is to provide information in relation to control networks and
demonstrate relationships with literature. This will be achieved by identifying methods
and data with their limitations and making comments on the relevance to this research
project. The literature review will provide a reliable and traceable base and will show
relationships links with other literature.
V2.1; ICSM
The Mine Surveyor have “in recent times been forced to adapt to a role that sees them
ensuring that the core business drivers of their employers are met, while at the same time
ensuring that all work is performed in compliance with all the relevant Safety and Health
and company Standards and Procedures” (Cawood & Richards, 2007).
SP1 explains and analyses a broad variety of surveying operations and is deliberated as an
inclusive guide to the procedures and practices for spatial science. SP1 was established by
the Intergovernmental Committee on Surveying and Mapping (ICSM) and is continually
referenced by surveyors to follow the correct guidelines and standards. A few topics the
SP1 covers involves: survey and reduction practical guides, suggested marking practices,
18
accuracy standards and expectations and suggested practices for the documentation
process.
The key concept taken out of the SP1 is that the quality of all underground surveys must
comply with Class D of the survey standards. This also agrees with Guidance Note QGN19
- Mine surveying and drafting published in 2011 as it states each control network
underground when feasible should have a close which is in compliance with the standards
of accuracy as stated in ICSM, SP1 Class D. Adjustment by the method of least squares is
demanded by these standards; producing the necessary statistics to carry out the
evaluation also requires the use of this technique (Grocock, 2014). The document is
critically imperative as it states the class needed to be achieved in the traverse and it
provides a basis of professional practice.
The first chapter that is relevant to this dissertation is Part A – Standards of Accuracy SP1
v2.1. The success of the underground traverse relies on agreeance with the SP1 in regards
to class and order. Part A uses the standard confidence interval as the standard for
statistical analysis which is used to determine the class and order. Class has a purpose of
intended and achieved precision of a survey network. The SP1 defines class as:
As SP1 has verified, class is dependent on: the design of the survey network, the survey
equipment and the reduction methods which are adopted. Class is generally “proven by
the results of a successful, minimally constrained least squares network adjustment
computed on the ellipsoid associated with the datum on which the observations were
acquired” (Inter-governmental Committee on Surveying and Mapping (SP1) v1.7, 2007).
This is generally attained by evaluating the semi-major axis of each standard error ellipse.
19
The semi-major ellipse is to be less than or equal to (<=) the maximum allowable semi-
major axis length using the equation explained in SP1:
r = c ( d + 0.2 )
Where:
r = length of maximum allowable semi-major axis in mm.
The values of c assigned to various CLASSES of survey are shown in Table 2-1 below
from SP1.
It is noted that for a Class D survey which is relevant to any underground survey, the c
value used is 50. By using the equation r = c ( d + 0.2 ) for a class “D” survey for a
comparative distance of 100 metres the length of allowable semi-major axis is determined
as 0.015 metres.
Part B of the SP1 standards are a guide on how to correctly perform surveys to a minimally
acceptable practice required to meet the requirements of a certain class and order. This
chapter of the standards considers calibration of Electronic Distance Meter (EDM). “All
20
ancillary equipment should be regularly calibrated, carry unique identifiers, and (where
relevant) be regularly compared against each other” (Inter-governmental Committee on
Surveying and Mapping (SP1) v1.7, 2007). The “frequency standard should be traceable
to the national standard, and calibrated once per year (Inter-governmental Committee on
Surveying and Mapping (SP1) v1.7, 2007).
21
Table 2-2 Horizontal Angle Observation Requirements (Inter-governmental Committee
on Surveying and Mapping (SP1) v1.7, 2007)
High 1” 1” 1” 1”
Medium 6” 6”
4.Sets
6* *6 2 1 1 1
A. Minimum number of sets
22
“The following table should be used as a guide to achieve results commensurate with the
CLASS of survey required” (Inter-governmental Committee on Surveying and Mapping
(SP1) v1.7, 2007). It is noted that for class C and lower it is expected that the equipment
(theodolite) will be 1” least count.
23
For this research project, the check survey will have to meet the standards of a Class “D”
primary survey network which is identified in SP1. In order for the check survey to be
accepted and a means to verify the quality of original control it is essential that the survey
standards are met.
A metal sleeve is inserted into the drilled hole which is secured by grout. Figure 2.12
illustrates how the aluminium tube should be placed into the side wall. With the grout
setting correctly and securing the metal sleeve the spigot which is attached to the prism,
can tightly slide into the sleeve. “The wall station sleeve is the physical “survey station”
that is found underground” (McCormack, 2002).
24
Figure 2-2 Aluminium Sleeve (McCormack, 2002)
Similar to conventional stations, the location and placement of wall stations directly
impacts the accuracy of the wall station. According to Accuracy of Wall Stations Surveys
by Smith and successively reinforced by McCormack in Wall Stations (Reference Points),
the “accuracy of wall station surveys is dictated in part by the geometric relationship of
the instrument station to the wall stations used for fixation” (Grocock, 2014). Smith
compares the differences in error when performing a two and three wall station resection.
The resection for both two point and three point had an arbitrary baseline of 25 metres
and “six resection stations were established in varying relationships to the wall stations,
each observing a forward station some 80 metres distant from the closer wall station.”
(Grocock, 2014).
25
Figure 2-4 Three Point Resection (Grocock, 2014)
When comparing the two tables it is evident that there is a significant progression in both
semi-minor and semi-major axes of absolute error, this is the both station precision. There
is also an improvement in the forward bearing precision when incorporating three points
into the resection instead of two. With Smith’s paper, an important relationship outlined
is the accuracy of the forward bearing with the amount of prisms used in a resection. This
dissertation will fill the gap of their papers and examine the propagation in errors over a
larger network. By examining a larger network of wall stations the errors can be magnified
and this will portray the importance of performing a check survey. No literature has been
found that examines the check survey method only papers which examine impacts of the
wall station resection.
The geometry of the existing wall station control relative to the station setup position of
the total station is very important when carrying wall station control. The total station
must be set up inside existing wall stations using two faced observations to coordinate
the instrument position. The aim of this method is to generate a positional solution that
is effectively “braced” within the existing control, hence balancing the errors associated
with the total station measurements.
Importantly, this research will examine the check survey method for underground
surveying which has yet to be reviewed. By reviewing the accuracy of the original wall
stations to the “checked” wall stations this dissertation will show the importance and
need for the check survey method.
26
2.4 RECENT CHANGES IN UNDERGROUND TRAVERSING
L.SHEPHERD
This paper covers a variety of aspects regarded to underground traversing and creating a
control network which is pertinent to the data collection and analysis that will be
conducted in the dissertation. Importantly, Jarosz and Shepherd’s research is concerned
with comparable themes as this research project therefore it should contribute a lot of
valuable material.
The first section of this study refers to the two different types of underground traversing.
The first method is classical surveying which means points are located in the roof and wall
station traversing with points in the drive walls. This dissertation is more interested in the
analysis of the wall station traversing method. The paragraph describing wall station
traversing briefly describes the purpose and general methodology which is better
described in Smith’s literature.
This paper has common similarities and relationships with Smith’s research with both
papers analysing the changes in axes of the error ellipse of the forward azimuth. The paper
has a baseline which is 0-1 and determines the points of 2, 3, 4 and 5. The instrument
locations is calculated by observations to adjacent targets with known positions. Then,
the subsequent wall station is calculated by distance and angle observations. This method
is then repetitive to calculate the wall station’s position. The first analysis was achieved
for a configuration where the instrument was positioned 3 metres from the second wall
station which was normal to the direction of the traverse. As expected, the parameters of
the error ellipses semi-minor, semi-major and azimuth of major axis increased at the
consecutive station which is a similar result proven by Smith.
Secondly, this paper by Jarosz and Shepherd acknowledges that the shape of the triangle
used for the resection does effect the accuracy of the bearing transfer. The figure below
illustrates the shape of the resected triangle.
27
Figure 2-5 Replacement of Right Angled Triangles with Narrow Triangles (Shepherd &
Jarosz, 2006)
Jarosz and Shepherd’s review of wall stations method provides a good argument about
the resected triangle shape. Proving that the parameters of the error ellipse increases
when the triangle is narrowed. Meaning the geometry of the points in the survey has a
paramount influence on the transferred direction and position accuracy. “Wall station
traversing where acute geometry of resection angles cannot be maintained requires
forced centring and additional observations between temporary instrument stations”
(Shepherd & Jarosz, 2006).
Again, Jaroz and Shepherd’s paper is concerned about the geometry of resection in wall
station surveying. Even though the importance of the geometrical relationship between
the wall stations and instrument is essential to maintain accuracy, this dissertation
focuses on how errors in wall stations can propagate through wall station traversing. By
analysing the check survey method it will show the importance of verifying the quality of
the wall stations. When poor geometry and the number of points used in a resection are
not adequate the errors in forwarding control and setting out information for the mine
will not be correct. By resecting off wall stations that have not been verified mine
surveyors can be magnifying errors throughout the mine. The greater the wall stations are
from check survey control the greater the error will be propagated and can potentially
cause fatal errors in production and development staking out.
All adjustment methods are based on the assumption that all systematic errors and all
mistakes have been removed from the observations. Thus they are designed to adjust
Random Errors only that is those errors that remain after the correct equipment, methods
and techniques have been used. An adjustment seeks to render a series of observed
28
quantities consistent within themselves. Thus the same results, whether they are co-
ordinates, heights, etc. are obtained no matter which adjusted observations are used.
Least squares adjustment is a processing methodology for the adjustment of surveys and
an analysis. “This is particularly relevant to wall station control since poor geometry and
other factors mean relatively small (less than 5mm) errors to control stations may cause
major forward azimuth errors” (Grocock, 2014). The method incorporates all observations
which increases the redundancy of the network and develops the quality creating
positional precision in both horizontal and vertical axes which is in relation to the baseline.
Smith has elaborated on the meanings of positional and local uncertainties and shown the
formulas for calculating positional and local uncertainty values. “Positional Uncertainty
can be calculated using the Leenhouts formula and the semi major and semi minor axes
of error ellipses which are given as a result of a least squares adjustment program based
on the network input data provided.” (Roberts, Ozdemir, & McElroy, 2009). The formula
below is Leenhouts formula to calculate uncertainty circle’s radius with a 95% confidence
level using error ellipses:
C = b/a
2 3
K=q +q C+q C +q C
0 1 2 3
Radius = aK
Where:
a = semi-major axis of the standard error ellipse
b = semi-minor axis of the standard error ellipse.
q = 1.960790
0
q = 0.004071
1
q = 0.114276
2
q = 0.371625
3
“Once the error ellipse in terms of the national geodetic datum is available, the radius of
the 95% circle of uncertainty (Positional Uncertainty) can be easily calculated as shown in
the formula” (Leenhouts, 1985).
29
Harvey’s paper has elaborated on the methods to calculate a least squares solution for a
survey network. Least squares adjusts random errors, however, doesn’t correct
systematic errors. Literature by Harvey (1993) and Roberts, Ozdemir, & McElroy (2009)
may both thoroughly investigate least squares however do not consider potential
systematic errors that can occur. In this dissertation the gaps from previous literature will
be filled by emphasising the importance to calibrate instruments and check that prism
constants are correct to ensure a reliable adjustment.
The instrument used will be in current calibration (less than 12 months since the previous
EDM calibration) and will be in a clean state, free of dirt and grime. The prisms used will
be specifically only used for control surveying and not used for normal operating
surveying to ensure the prism constants are correct. The total station’s atmospheric
corrections will be set to zero and a Kestrel that has been calibrated against the Beaureau
of Meteorologys instruments for temperature and pressure information will be used to
obtain accurate pressure and temperature readings.
2.6 CONCLUSION
This chapter has described and substantiated the theories put forward by previous
literature. The literature found in regards to wall station surveying focused on the
resection method. Investigating the effect of the number of wall stations in the resection
and the geometry of the resection. The literature concludes that major forward bearing
azimuth issues can occur when poor resections are used as the norm. A theoretically
analysis will be completed in this dissertation to depict the importance of redundancy in
resections.
The papers do not analyse the effects of error propagation over a larger extent. As no
literature was sourced that related to underground check surveys this research project
will assess the check survey method and render the importance of the method in
underground surveying.
The standards for control networks have been examined to outline the requirements that
need to be met for the check survey.
30
3. CHAPTER 3: METHODOLOGY
3.1 INTRODUCTION
This chapter of the research project will outline and identify the planning and processes
undertaken for methodology of the research project. By doing so, this chapter will
provide a better comprehension of how the results were created and qualify an analysis
to be directed on the results achieved in the underground control survey.
Mount Isa Mines is controlled by Glecore Xstrata Copper which is a section of its North
Queensland Operations. Some of the tasks involve mining, processing and smelting
processes in Mount Isa and just mining and processing at Cloncurry and then Townsville
control refining and port operations.
31
Figure 3-1 Mount Isa, Queensland Map (Mount Isa Mines Rotary Rodeo, 2016)
At Mount Isa Copper Operations (MICO) there are two underground mines which are
called X41 and Enterprise (ENT). The survey department at Mount Isa performs surveys in
both X41 and Enterprise to meet the demands of production and development of the
mine. In order for the surveying department to remain confident in their everyday work,
checks need to be implemented which is why check surveys are completed.
3.3 IMPORTANCE
32
the digital Leica file onto Surpac where a string file is created and a report written that
details what control was used, any forward stations that were surveyed in and any points
that were recorded during the survey. This system generally works well however relies on
wall stations to be advanced correctly. With wall stations being used daily in resections it
is expected that these wall stations are in the correct position. To verify the position of
wall stations the underground check survey method will be completed.
Wall stations need to be surveyed using a technique that ensures the best possible
coordinated solution for the station setup is determined, and errors associated with the
survey traverse are minimised as the survey is carried. As headings can extend a significant
distance from the origin of the survey, any small deviation in the bearing or weakness in
the calculated station position that is used to carry control will have a significant influence
on the accuracy of the location of the mining at the end of the heading.
33
wall stations is common and it is essential that this is checked prior to carrying control
further into the development.
The following techniques will be followed to allow the wall station control to remain
reliable and accurate whilst mining headings.
- All wall stations are to be sleeved and grouted. A standard wall station sleeve is
approximately 0.080m in length and has an internal tube diameter of 0.008m.
- All survey control stations must be carried “outwards” of the existing control. This
means to carry control outwards from its origin rather than from “inwards”
overlapping the area previously traversed when the control was extended. Error
propagation is statistically more significant when control is traversed back on
itself before being extended outwards.
- The geometry of the existing wall station control relative to the station setup
position of the total station is very important when carrying wall station control.
The total station must be set up inside a minimum of three existing wall stations
using two faced observations to coordinate the instrument position. The aim of
this method is to generate a positional solution that is effectively “braced” within
the existing control, hence balancing the errors associated with the total station
measurements. If the quality of the free station solution is not deemed
acceptable, more wall stations need to be surveyed and analysis of the network
solution investigated.
With a quality network solution established, forward wall stations can be carried with
confidence. Forward stations are surveyed in two faces and should be staggered along
both sides of the drive (subject to ground/wall conditions). Some examples of where wall
stations should not be installed include:
- On walls that are directly exposed to the firing of the next face
34
3.5 FIXED STATIONS
As a general operating procedure, high order “check” surveys will follow up advancing
capital development as a means to verify the quality of existing wall stations and provide
accurate control to further advance into the mine. All surveyors will be responsible for the
check surveys in their areas and these should be organised during a day when mining
operations using large machinery are not being conducted in the survey area. As a rule,
the working control should not advance more than ten “line of sight” setups from the
existing high order survey network. The method of conducting check surveys differs from
that of working control as all of the information recorded and documented, from the raw
GSI file data to the final traverse report need to explain how the instrument was set up
and the traverse was conducted during the survey.
For the check survey, the network is constrained by twelve fixed stations. A fixed station
must be a wall station that has been verified by the check survey method previously. The
(X, Y, Z) coordinates of the fixed wall station are known and are noted as check survey
points in the mine’s database. If the check survey was fixing on wall stations that have not
been checked it would defeat the purpose of the check survey method.
As a general operating procedure, high order “check” surveys will follow up advancing
capital development as a means to verify the quality of existing wall stations and provide
accurate control to further advance into the mine. As a rule, the working control should
not advance more than ten “line of sight” setups from the existing high order survey
network.
35
Figure 3-3 Check Survey traversing up the Incline
The ‘Sets of Angles’ program on the Leica total station was used to conduct the survey
traverse. The first instrument setup of a new section of traverse was a free station two
setups back from the end of the existing network. The first set up was coordinated to
verify that the existing control was correct and that the wall stations have not moved since
they were last surveyed. The atmospheric corrections applied to EDM measurements
must be set to 0ppm for the survey (corrections are applied during post processing).
Six sets of observations were taken to survey all visible survey stations, and any existing
setups that are occupied during the survey. The connecting observations between the
instrument station setups are critically important to maintaining the high order of the
survey.
Check survey station naming conventions– the naming conventions for stations surveyed
is to be as follows:
- Station setups are labelled as the date followed by A, B, C…. etc (for example
110716A for the first station setup done on July 11, 2016). This is to uniquely
36
identify each free station setup as it is merged into the master check survey
document and makes sorting of wall / back stations from free set up stations
easier.
Post processing in CompNet – After setting up CompNet with the configuration with the
correct path, the Instrument ID number, a new project is created for the processing of the
check survey observations.
- Import the GSI file data, using individual observations and entering the
instrument PPM and Constant corrections as calculated in the EDM calibration.
Investigate and fix any errors that CompNet reports and then continue with
adjustment.
- CompNet will automatically process the project if sufficient fixed stations are
referenced to allow a solution to be calculated.
- All duplicate point numbers must be addressed.
- Re-import the GSI file and rerun the adjustment. Check the F-Test and Variance
Number and whether the project passes or fails adjustment.
- When the project is optimized as best as can be determined, move the weighted
coordinates to the fixed file.
Prior to commencing the field work at Mount Isa underground mine, survey equipment
should be checked to ensure that it is functioning as it is designed to, and that it is in good
operating condition. This may contain but not be restricted to the following equipment.
37
be conducted prior to the check survey. Section 5 of the Leica MS50 User Manual explains
the method used to complete the “Check and Adjust” on the Leica Instrument. Prior to
conducting the calibration, the log file should be switched on and a minimum of three sets
of observations is carried out to identify the c, a, l, t, i and ATR Collimation errors. If any
of the numbers have changed by greater than 15 seconds from the instruments last check
and adjust, this should be brought to the attention.
An EDM Calibration should be completed within a year of completing the check survey to
ensure the accuracy of the instrument. In Appendix B, a reference to the latest EDM
Calibration is made.
The total station should be in a clean state, free of dirt and grime, be in calibration and be
set to run atmospheric corrections of zero parts per million. A Leica user manual states:
“Distance measurement is influenced directly by the atmospheric conditions of the air in
which the measurements are taken. In order to take these influences into consideration
distance measurements are corrected using atmospheric correction parameters” (Leica
Heerbrugg, 2009).
The atmospheric corrections applied to EDM measurements must be set to 0ppm for the
survey (corrections are applied during post processing). The instrument was checked to
be sure the correct adjustments for the work site were correct especially EDM calibration,
Scale Factor, PPM settings.
The wall station prisms used for the check survey were checked to ensure the prism
constants were the same as the instruments specifications. The prism itself must be
locked securely inside the prism holder. This was tested by gently pressing the prism to
see if it moves inside the prism holder. The spigot was also examined to check to make
sure it was straight. When sliding prisms into the sidewall it is essential to check and verify
that the spigot of the wall station prism is hard up against the sidewall rock. A drill was
38
used on a number of occasions to clean the interior of the metal sleeve so the spigot is
hard up against the wall.
When working in an underground mine there is variation in temperatures and pressures
compared to above ground surveys. Due to the impact the instrument settings can have
on observations raw measurements were taken underground and all corrections were
changed in the processing stage. By recording pressure and temperature readings at every
set up errors were eliminated.
3.8.3 TRIPOD
Before use, tripods were checked to ensure that all hinges, joints and locking mechanisms
were functioning as designed. The tripod was checked for stability once set up by applying
a downwards pressure to the tribrach plate.
3.8.4 KESTREL
Kestrel that has been calibrated against the Bureau of Meteorology’s instruments for
temperature and pressure information. Calibration must be completed within a year of
check survey. In the below figure it portrays the calibrations differences. In Appendix C, it
shows the latest calibration of the Kestrel.
3.8.4.2 TEMPERATURE
Fluctuations in the temperature within in underground mine is expected. When
performing the check survey Kestrel readings were taken at the start, middle and end of
39
each station set up. An average temperature was determined for each different set up to
eliminate atmospheric errors.
Data will be collected at MICO underground mine to verify the control stations in X41
around 15 level. The site map of the information needed for the check survey is attached
as Appendix D.
Field work will be completed using Leica “Sets of Angles” on a Leica MS50 1” total station.
The underground traverse will be in compliance with the requirements of ICSM SP1 v1.7
(Class D).
A 3D linear misclose assessment will be carried out which will examine consideration of
any rotational issues. This adjustment will be completed with CompNet v2.9 which has
the advantage of comparing parameters against the requirements of Class D of ICSM SP1.
A Kestrel 4000 Pocket Weather Tracker was used to collect atmospheric temperatures
and pressures at each station set up to accurately edit the raw data collected.
3.10 CONCLUSION
In conclusion, the above sections outline in detail the methodology for the check survey
within this project. In a larger mine, it is important to plan and understand the processes
of the check survey prior to the field work. Problems are encountered that alter original
plans while underground. Problems encountered must be overcome or minimise to
optimise the check survey procedure. The methodology was followed closely in the field
work to ensure eliminate any potential errors. By not following the correct procedures in
the field it can lead to major problems in the processing phase. In an underground mine,
mine surveyors should remain cautious due to the factors of heat stress that can
potentially influence the decision making process of the surveyor.
The chapter provides a description of the procedures taken to ensure that the survey was
completed correctly and in compliance with class “D” standards.
40
4. CHAPTER 4 – RESULTS
4.1 INTRODUCTION
This chapter discusses the results produced from the least squares adjustment. Least
squares is a common processing procedure for analysis and adjustment of survey data.
The check survey has combined fixed stations at the start of the survey which aim to brace
the survey network.
The software incorporated the sets of angles traversing data to generate least squares
solutions of the rigorous network adjustment. The adjustment software CompNet was
used to create output files which provide statistical information of the check survey. For
the least squares adjustment to pass the adjustment it is evaluated statistically to assess
the adjustments quality.
The field work for the check survey was completed over three full days to collect the
desired data for adjustment. The check survey traverse consisted of:
- 62 wall stations
- 12 fixed stations (outlined in red at the start of the survey)
- 39 set ups (to the end and back to the start)
- 900 metres to the end and 900 metres back to start.
o The check survey traverse is a closed traverse but it is not closing back
onto itself it is closing back onto a different fixed control station.
41
Figure 4-1 Survey Network in CompNet
The objective of a least squares survey adjustment is eliminate mistakes from the
collected data and compute the best fit of the adjustment. After performing the least
42
squares adjustment the solution of the survey stations need to be evaluated and assessed.
CompNet software has the ability to summarise the adjustment and provide the user with
the most important information.
In comparison with the new checked survey wall stations and the original wall stations
there was little deviation. The difference in the X, Y, Z coordinates were observed and all
axis had small difference. The greatest difference was in the Z axis which was a
difference of 30mm. The area of the mine that was checked had limited mining activity
over the years which is assumed to have limited movement in the wall stations. Mount
Isa mine surveyor’s ensure to incorporate an adequate positional fix for their resection
when forwarding new control which will be discussed further.
43
- Precision
- Accuracy
- Uncertainty
4.3.1 PRECISION
Precision is the degree of closeness and consistency of a set of observations in surveying
terms. When analysing the observations the variance and standard deviation expresses
the precision if the statistical information is reliable and unbiased.
When the variance of the observations is small it means the measurements are clustered
and confined to the mean which produces a tall and thin normal curve. However, when
the variance of the observations is large it means the set of observations has low precision
and are spread about the mean which produces a flat and low normal curve.
If several measurements are taken repeatedly to represent the same quantity, precision
is used to refer to the degree of closeness or conformity of those measurements to each
other” (Inter-governmental Committee on Surveying and Mapping (SP1) v2.1, 2014). In
44
the figure above, the observations represent high precision and low accuracy. High
precision makes a narrow normal distribution curve as seen in the above figure.
4.3.2 ACCURACY
Accuracy is the amount of closeness of a measurement to the true value. The true value
is theoretically never known. The accuracy not only contains the influence of random
errors, but also any bias due to systematic errors which have not been corrected.
In the figure above, it portrays high accuracy and low precision which gives a flattened
normal distribution curve.
4.3.3 UNCERTAINTY
Uncertainty is the extent within which it is projected the error of an observation will lie.
A specific level of probability is commonly related to the uncertainty of observations. In
this research project 95% uncertainty is the range within which it is 95% likelihood that
the error of measurement will lie. According to ICSM SP1 v2.1 uncertainty is “an indication
45
of how wrong a value may be and is used in this Standard to quantify the level of survey
quality.” The ICSM Standards categorise three types of uncertainty which include:
4.4 TRAVERSING
46
other known points are said to be “open,” meaning that there is no automatic check on
the validity of the work.”(Bernard, Solomon & Britton, 1992).
An open traverse geometric close in the survey and there needs to be verification on the
field work. Open traverses are used on a daily basis at MICO and the check survey process
is a method of verifying the traverses.
All types of adjustments are based on the assumption that all systematic and gross errors
in the survey have been removed. Adjustments are designed to only adjust random errors
which is errors that persist after the correct procedure, technique and equipment have
been implemented.
The Least Squares method produces the best adjustment by altering the observations by
the least possible quantity. All observations will be adjusted simultaneously when using
the Least Squares. Essentially the aim of the adjustment is to minimise the sum of the
squares of the residuals.
4.5.1 ITERATION
Non-linear least squares is known as an iteration. Each iteration new values for the
coordinates are incorporated for each iteration, where each set of values are the Most
47
Probable Values (MPV) resultant from the preceding calculation. Commonly when the
input data has no gross errors the solution will converge in a few iterations.
In a model there is (𝑚) unknown variables which means there will have to be (𝑚)
independent observations to adequately determine these parameters. If ( 𝑟𝑖 )
observations were made to estimate (𝑚) variables and (𝑛 > 𝑚) then the redundancies or
degrees of freedom (𝑓) is (𝑛 − 𝑚). The redundancy of the network is equal to the amount
of observations subtract the amount of unknowns. The process of the least squares
adjustment allows the estimation of the (𝑚) variables when there is (𝑓) redundant
observations obtainable. Repeated observations which are measured to estimate an
unknown variable the additional observations are redundant. By increasing the
redundancy in the survey network the confidence of the adjustment is increased.
x i
x i 1
The MPV is the mean if the observations have the same precision.
48
4.5.4 RESIDUALS
Simply, the residual is the difference between what was observed and the value that best
fits into the adjustment. The residual is determined from the Most Probable Value (MPV)
where:
ri x xi
i xi x
( x x)
i
2
When x in theory is the ‘true value’ and xi x represents the ‘true error’.
s 2
(x x ) i
2
n 1
s s2
xx ) i
2
n 1
49
( x x)
i
2
Where xi x is the error.
n
s
(x x ) i
2
Where x xi is the residual.
n 1
Essentially, a smaller standard deviation will portrays a more accurate position whereas a
larger standard deviation will indicate a less accurate position.
The research project considers a derived Root Mean Square (RMS) deviation which is a
weighted deviation that takes into account the estimated predicted errors in the survey.
The predicted errors entered into CompNet were obtained from instrument specifications
and calibrations.
Ideally, the standardised residual should be close to one and in this research project will
examine standardised residuals (>3 σ) for mistakes. This is based on the assumption that
if an observation is greater than 3 from the mean it may be an error. The 3 σ rule of
thumb is that it is a 99.7% probability of fallen in the range of 3 σ.
Chi-square and Fisher distribution are implemented to assess the confidence level of the
variance. By applying these tests we can analyse the accuracy of the network and the
adjustment. If the tests do not fall within this range then it fails the test which specifies
that the adjustment is not satisfactory.
50
4.6.1 CHI-SQUARE TEST
The Chi-square test is intended to accept or reject the hypothesis that the predicted errors
have been accurately estimated. A probability percentage is calculated which is the level
of significance for the adjusted network and if this is less than 95%, the reference factor
will not pass the test.
The Chi-square test is made by comparing a 2 value calculated from the observations,
with that obtained from tables for the desired confidence level.
2 2
r2
Where,
r 2
= the sum of the squares of the residuals resultant from an adjustment,
Now as, s r 2
n 1
Rearranged to, r 2
(n 1) s 2
Where,
Therefore,
fs 2
2
2
51
A two-sided Chi-Square test at 5% significance level is performed on the adjustment to
determine if the residuals are potentially due to random errors.
The chi square range is calculated to test if the variance factor s02 lies within the allowable
range.
fs 2 fs 2
s02
2 2
,f 1 , f
2 2
Where,
This research project has incorporated a significance level of 5% meaning that the two
sided Chi-Squared test will determine if a particular 2 value is within the 95% area of all
2 values. If it does the test will pass if does not and falls into the remaining lower and
upper 2.5% areas then the test will fail. When this test fails it is assumed that it is caused
by non-random errors. This statistic test in essence considers the quality of fit that the
adjustment has made. It is important to realise that the Chi-Squared test is not an absolute
test of the accuracy of the observations in the survey.
s2
F0.05, f ,
2
Where, (𝑓) represents the number of redundancies of observations which the sample
variance (𝑠 2 ) is calculated. The infinity symbol represents the degrees of freedom of the
normal distribution population with variance ( 2 ). It is important to understand the
population that is sampled from is infinite.
52
4.7 CONCLUSION
The traverse and adjustment of the survey network were discussed in detail. Least squares
is a common processing procedure for analysis and adjustment of survey data. The results
outputted by CompNet have been explained and basic statistics were described to give
meaning to the results attained.
The least squares adjustment process consists of complex mathematical formulae and are
difficult for the profession of surveying to assess their results. However, statistical
information can clearly depict the results of the quality of the network and adjustment.
Analysis of the results obtained in the least squares adjustment will be assessed in the
next chapter.
53
5. CHAPTER 5 – DISCUSSION
5.1 INTRODUCTION
In this chapter, the results obtained in the previous chapter will be analytically discussed.
The theory of errors, effects of external factors in relation to underground mining, global
precisions, instrument settings, and the results will be outlined and discussed in detail.
Statistical behaviour will be analysed to thoroughly understand the check survey.
Errors in observations can inherent from many different causes and should be reduced or
overcome. There are generally three types of errors that surveyors are concerned with:
- Systematic
- Random
- Gross/ Mistakes
Least squares adjustment does not eliminate bad observations which means quality
observations are important.
- Natural errors
54
o Temperature, refraction, slope, sag, tension
- Instrumental errors
o Adjustments comparative to the total station
o Systematic positioning of an automatic compensator in an automatic
level
- Periodic errors
o Diurnal Refraction
o Electronic Distance Measurement (EDM) cyclic errors
Systematic errors are more commonly caused by field procedures and the instrument
used. It is important to realise the least squares adjustment will adjust random errors but
will not adjust systematic errors.
Statistical testing of the observations in the survey can aid in representing the presence
of systematic errors in the survey. The adjustment passed statistical based tests meaning
the survey achieved its desired accuracy.
55
5.2.3 GROSS ERRORS
Gross errors is any blunders caused from the field techniques in the survey. The survey
has sufficient checks throughout and no gross errors should be present.
5.3.1 ILLUMINATION
When working in an underground mine artificial lighting is incorporated to be able to view
and observe survey wall stations. “Artificial light is necessary in order to illuminate the
point of sight and the cross hairs. Such light is generally very poor, and this fact greatly
hampers work with the instrument.” (Young, 2012). Problems with lack of natural light
can effect the accuracy of sighting and recognizing wall stations. Problems with
illumionation and wall station sighting can lead to gross errors through the survey.
5.3.2 REFRACTION
Refraction of light rays out of the vertical plane is due to presence of layers and currents
of air at different temperatures and pressures along the line of sight. “Lateral refraction
is the biggest source of systematic error that can be encountered in underground surveys.
Every effort should be made to avoid its effect. …” (Fowler, 2006).
56
Refraction is not the same as shimmer in observations. When there is errors caused by
shimmering the error is commonly cancelled out by increasing observations. When six
sets of angles is more than sufficient to eliminate the error of shimmer.
5.3.4 MECHANICAL
When setting up the total stations and fore and back sights ideally the centre of the drive
is desired. At the start and end of the check survey “Surveyor’s at Work” signs were
displayed along the drives to warn ongoing traffic. Heavy machinery did pass by the
vicinity of the survey on a few occasions. Using cap lamps signals, hand signals and radios
to slow the machinery’s speed down was a way to minimise the effect on the set ups.
5.3.5 VENTILATION
The flows of ventilation in the mine’s drives can impact the centring of the total station
and fore sight and back sight set ups. The survey was over a large distance and variations
in the ventilations occurred when the survey got nearer to air ventilators. To minimise
any centring errors ventilation was turned off in some scenarios.
Predicted errors are expected observational errors that may be achieved based on the
field procedures followed and the quality of the instrument and equipment used. It is an
approximation of the standard deviation of observations. By increasing the predicted
errors it specifies that the observations taken aren’t as accurate.
57
5.4.1 PREDICTED ERROR CONSTANTS
Horizontal and vertical pointing is an angular error which is in seconds. It is an estimate of
the error attached to the total station pointing to the target. This error is influenced by
the atmospheric errors, the optics of the instrument and if the instrument has been taken
care of. In humid environments such as an underground mine the pointing error is
increased to account for heat waves. As the Leica total station used had Automatic Target
Recognition (ATR) turned on for the pointing error shall be increased as greater accuracy
is achieved by manual sighting techniques.
Horizontal and vertical reading constant errors in the angular reading errors which is
related to the theodolites reading precision. For the survey the Leica MS 50 one second
instrument was used.
The distance constant and distance Parts per Million (PPM) is obtained from the EDM
variables determined when the calibration was completed on the total station.
Instrument plumbing standard error relates to the centring of the instrument. The
amount of error will be increased as centring of the instrument is expected to have some
error when setting up in an underground environment.
Statistical analysis will examine the behavioural characteristics of the observations. The
least squares adjustment process consists of complex mathematical formulae and are
difficult for the profession of surveying to assess their results. However, statistical
information can clearly depict the results of the quality of the network and adjustment.
58
By observing the graph below it is evident that none of the standardised residuals
exceeded the limitation of 3 σ. When a standardised residual exceeds 3 σ it is expected to
be an error. The 3 σ rule of thumb is that it is a 99.7% probability of fallen in the range of
3 σ.
2.5
Standardised Residuals (σ)
1.5
0.5
0
0 20 40 60 80 100 120 140 160 180 200
Slope Distance (m)
Shorter and longer observations were included in the check survey for purposes of the
research project. The predicted errors that are applied to the adjustment will have greater
influence on a shorter distance in comparison to a longer distance. For example a 1”
predicted pointing error will influence a 2 metre observation greater than a 100m
observation.
The standardised residuals are used to easily interpret the data. When the standard
deviation of the slope distances is analysed it is seen there is little to no deviation from
the mean with all measurements being the same. When plotted on a normal distribution
curve the measurements specify that the slope distance measurements are precise and
depict no or very little deviation from the mean.
The linking observations between the instrument station set up and the forward and back
sights on tripods are critically important to retaining the high order of the survey. For
59
example it was observed that a combination of a short backsight and a long foresight is a
combination that produces higher angular uncertainty.
0.0026
Standard Deviation (m)
0.00255
0.0025
0.00245
0.0024
0.00235
0.0023
0.00225
0 20 40 60 80 100 120 140 160 180 200
Slope Distance (m)
The derived RMS deviations for the slope distances increase slightly as the slope distance
is lengthened. The variations are extremely small and was expected that the difference in
predicted and observed over the single measures will increase slightly as distance
lengthens. When analysing the derived RMS deviations of direction and vertical angles
there statistical behaviour is similar to each other.
60
Standard Deviation (Seconds of Arc) Derived RMS Deviation Direction
140
120
100
80
60
40
20
0
0.0000 50.0000 100.0000 150.0000 200.0000
Slope Distance (m)
90
80
70
60
50
40
30
20
10
0
0.0000 50.0000 100.0000 150.0000 200.0000
Slope Distance (m)
Both of the direction and vertical angle derived RMS deviation graphs follow a similar
pattern. The difference between an observed and the best fit on a single measurement
will have a higher seconds of arc difference on a shorter observation length.
61
Figure 5-5 Effect of Derived RMS Deviation
When the slope distance from the instrument to the point increases the +/- 20 seconds of
arc is going to be a greater error over a longer distance. The global precisions which are
the estimation of standard deviation of errors will have greater impact on shorter
observational lengths. However, when the offsets are determined the high seconds of a
short distance will calculate a similar offset compared to a smaller seconds of arc over a
longer distance. The RMS deviations of vertical angles and direction is predicted as the
seconds of arc is proportional to the slope distance.
140
120
100
80
60
40
20
0
1.5 2 2.5 3 3.5 4 4.5 5 5.5
Slope Distance (m)
SD Direction SD Vertical
62
Standard Deviations (Seconds of Arc) 5-20 metres Derived RMS Deviations
50
40
30
20
10
0
4.5 6.5 8.5 10.5 12.5 14.5 16.5 18.5 20.5
Slope Distance (m)
SD Vertical SD Direction
The graphs indicate that the difference between the adjusted and observed readings for
the single measure. It is clear that the direction has larger derived RMS deviation than
vertical angles over shorter distances. By observing the graph above, at approximately the
20 metre observation length the seconds of arcs stabilise and seem to be a similar value
from 20 metres to 100 metres.
63
Direction and Vertical Angle Standardised Residuals
9
8
Standardised Residuals (σ)
7
6
5
4
3
2
1
0
Start to End Travere
It is seen that the standardised residuals for slope distances and direction are all under
the limit of 3 σ apart from one or two measurements. However, the vertical angles seem
to have numerous measurements which exceed the 3 σ limitation. Both the direction and
vertical angle standardised residuals are greatest at the start and end of the traverse. The
observations where the standardised residuals were greatest were then investigated. The
conclusion as to why the standardised residuals are high at the closure of the traverse is
because of the fixed stations used in the adjustment.
The survey has greatest differences between observed and adjusted at the start and end
of the traverse. The traverse is a closed traverse but it is not closing back onto itself it is
closing back onto a different fixed control station. As the traverse is not closing back onto
the same point we are seeing deviation between observed and adjusted at the start and
end of the traverse.
The reasoning behind this behaviour has come down to the fixed stations at the start of
the network are forcing the entire adjustment to produce a best fit based on the fixed
stations. The twelve fixed stations at the start of the network may have moved over time.
The integrity and reliability of the stations which are fixed is in doubt. With the fixed
stations of the network being on an incline which is subject to high traffic and machinery
passing through the wall stations are prone to movement.
64
The vertical angle standardised residuals seemed to be high in comparison to slope
distance and direction standardised residuals. As many of the standardised residuals for
vertical angle exceeded the 3 σ limit the standardised residuals greater than 3 σ were
investigated. The vertical angle offsets between observed and adjusted for standardised
residuals greater than 3 σ were interrogated.
0.005
0.004
0.003
0.002
0.001
0
3 4 5 6 7 8 9
Standardised Residuals (σ)
The vertical angle standardised residuals greater than 3 σ have been compared to their
offset between the observed and adjusted. The greatest vertical angle standardised
residual is 7.9 σ and its offset is 8mm between the observed and adjusted. As the check
survey was performed in an underground environment an 8mm offset for such a high
standardised residual is not overly concerning.
The direction standardised residuals has one result that exceeds the 3 σ limitation. Its
standardised residual is 3σ and its direction offset between observed and adjusted is
3mm. When analysing the results obtained from the least squares adjustment it is evident
that slope and bearing measurements have a higher degree of accuracy than the vertical
angles.
65
5.6 PRECISION MEASURES
The standard deviation of the two coordinates for each point indicate the precision of the
northing and easting coordinate values respectively. These values can be positive and
negative which can be easily graphed and a rectangle can be drawn around the values to
represent the area of error.
Graphing the values using a rectangle to portray the area of error is based on the
geometry of the coordinate system. When using an error ellipse to show the area of error
it represents the geometry of the survey network rather than the geometry of the
coordinate system.
The maximum standard deviation is the semi- major axis (a) and the minimum is the semi-
minor axis (b) of the ellipse which is at a right angle to the semi-major axis. The orientation
of the semi-major axis is defined by the azimuth. The ellipse azimuth gives the orientation
of the ellipse based from the coordinate system.
66
Essentially, the error ellipse is two normal distribution curves intersected on a three-
dimensioned plane. The values used in the error ellipse are calculated from the
observations but the design. This means that the error ellipse don’t not portray actual
errors made in the survey but instead portrays the probable errors.
In this research project, error ellipses will be examined with a confidence level of 95%.
That means that there is a 95% confidence that the adjusted point is in the extents of the
ellipse’s dimensions used. The size of the ellipse represents the measurement of reliability
of the adjusted point. These error ellipses are used to evaluate the strength of the survey
network and the reliability of the adjusted points calculated.
67
Figure 5-11 Absolute Error Ellipses
By observing the absolute error ellipses on CompNet visual comparisons can be made of
the shape, size and orientation of the ellipses. There are twelve fixed stations in the
network which are at the start of the network. When the distance between a fixed station
and a free station increases the size of the absolute ellipse will increase. At the end of the
network which is South of the network the absolute error ellipses are greatest as the
further a traverse is away from the known control the less confidence you have in the
position.
68
When observing the absolute error ellipses it is evident that most are orientated in the
same direction. When many ellipses are in the same direction it means that the survey
network is unbalanced in that direction. There is an azimuth deficiency and one side of
the network has minimal resistance to rotation.
In the figure below it portrays the semi-minor and semi-major axis of the wall stations.
0.015
0.01
0.005
0
Start to End Wall Stations
At the beginning of the graph lines are flat which represents the twelve fixed stations
incorporated in the adjustment. These twelve fixed stations will have no error in their axis
as they are used as the reference control throughout the network. The maximum
standard deviation is the semi- major axis (a) and the minimum is the semi-minor axis (b)
of the ellipse which is at a right angle to the semi-major axis. When analysing the two axis
on the line graph there is a particularly large difference between each other which
indicates the absolute error ellipses will be elongated. This means that there is greater
uncertainty in one of the coordinates. The graph below portrays the standard deviations
in easting and northings for the adjusted coordinates in the network.
69
Adjusted Coordinates
0.01
0.009
0.008
Standard Deviation (m)
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Start to End Wall Stations
The assumption as to why the standard deviation of the height component is low is the
positioning of the wall station prism sits at the lowest point in the sleeve each time it is
inserted. Whereas, horizontally the prism can move around and can sit at a different point
each time the prism is inserted.
Observing the standard deviations of the adjusted coordinates it represents that there is
a greater uncertainty in the Easting coordinates. This difference is quite significant and
confirms why the error ellipses are elongated and have similar azimuths. Elongated
ellipses represent an azimuth distortion in the survey adjustment.
70
Figure 5-14 Orientation of Fixed Stations
In the above figure, the red circles represent the twelve fixed stations. It is evident that
the strength of the network is constrained adequately along the Northern axis yet in
Eastern direction the fixed stations are poorly braced. Along the Northern axis the fixed
stations are stretched for 180 metres in comparison to the Eastern axis which is over 10
metres. The orientation of the fixed control has caused an azimuth distortion in the
Eastern direction which has been confirmed by the standard deviations in the adjusted
coordinates. The fixed stations of the network are all running along the same direction
which is a straight line. The ideal geometry of a network should form closed figures which
are braced.
The orientation of the fixed control in an underground mine with narrow tunnels is
difficult to achieve the ideal geometry of fixed stations that is braced in all axis. Instead,
using the sets of angles program was used to increase the redundancy in the network. By
increasing the number of observations will reduce the size of the error ellipse since
redundancy increases confidence.
71
5.6.1.2 RELATIVE ELLIPSES
Relative ellipses represent the precision of the relative position of the two different
coordinates of the point. “The uncertainty between the horizontal and/or vertical
coordinates of any two survey control marks” (Inter-governmental Committee on
Surveying and Mapping (SP1) v2.1, 2014). Relative Uncertainty “can be expressed in SI
units at the 95% confidence level, or in a proportional form such as a ratio of uncertainty
per unit length or survey misclosure” (Inter-governmental Committee on Surveying and
Mapping (SP1) v2.1, 2014).
The check survey network must comply with the requirements of a class “D” survey. An
easy method to compare the uncertainty of the survey to the standards is by examining
the relative error ellipses. The 95% confidence relative uncertainties for the network used
an error ellipsoid factor of 2.796 where all ellipsoid semi-major axes and height precisions
were within the relative uncertainty limit of 50mm. The greatest relative semi-major axes
is 27mm which is well under the limitation required by the standards. The ICSM relative
uncertainties at 95% confidence interval are attached in Appendix G.
The concept of a resection is to determine the position of the setup by observing known
points. Theoretically the number of wall stations in the resection will be analysed and the
redundant observations will be examined.
The amount of wall stations which are observed and the geometric association with the
total station and the wall stations is dependent on the formation of the mine. By
increasing the number of wall stations included in the resection the observations
redundancy is increased. By increasing the redundancy of the resection the confidence of
the observations is increased.
72
When examining a two point resection the two wall stations in the resection have known
coordinates. This means that the bearing and distance between these two wall stations is
known. When there is two wall stations there is two distance measurement from the total
station to the wall stations. The total station can determine its location when a two-point
resection is performed by triangulation.
The unique solutions of a two point resection is displayed in the following table. This
means that a two station resection has two unique solutions.
1X2 1-X-2 X to 1
1X2 1-X-2 X to 2
When a three point resection is observed the coordinates of three wall stations is known
which means there is three known bearing and distances between stations. Three
73
measurements are observed to each wall station to determine a triangulation solution of
the set up location.
When the position of three wall stations is known are observed in a resection, three
measured distances and angles make up greater combinations which increases the
redundancies. With a three wall station configuration seven unique (including one
resection) solutions for the location of the total station set up are determined.
74
Table 5-4 Three Point Resection Solutions
When a four station resection is conducted four coordinates of the wall stations is known.
When using four wall stations it will provide the coordinates to determine six join and four
distances measured to the known wall station and the location of the total station.
Meaning, four angle measurements will be observed from the total station to the wall
stations.
75
Table 5-5 Four Point Resection Options
Bearing 1 to 2 1-X-2 1 to 2
Bearing 1 to 3 1-X-3 1 to 3
Bearing 2 to 4 3-X-4 2 to 4
Bearing 4 to 3 4-X-2 3 to 4
Bearing 1 to 4 1 to 4
Bearing 3 to 2 2 to 3
X to 1
X to 2
X to 3
X to 4
When there is four wall stations in the resection the measurements will provide sixteen
unique solutions of the location of the total station.
76
Table 5-6 Four Point Resection Solutions
It is evident that the theoretical analysis of the resection method to calculate the position
of the set up shows the importance of the number of wall stations used. By increasing the
number of unique solutions in the resection the degree of confidence increases. When
forwarding new control from two and three point resections there can be significant
problems with azimuth control. This theoretical analysis outlines the importance of the
number of points used in resections. Ideally four points used in a resection is most suitable
for underground surveying when using wall stations to increase confidence in the
instruments position.
A two point resections has minor effect on the precision of the wall station and the
distance to the foresight but heavily impacts the precision of the forward bearing which
directly impacts azimuth control. Whereas, when using three stations in the resection
distance strength is similar and there is an improvement in the precision of the stations
and the forward bearing improves. It is vital when resections are implemented to forward
control to incorporate more than two stations with adequate geometry to maintain
azimuth integrity.
77
5.8 GEOMETRY OF STATIONS IN RESECTION
The geometric relationship between the wall stations and the total station is controlled
by the layout of the mine and the surroundings in the work environment. It is not always
possible to put in wall stations in a position which is optimal for observational geometry.
When installing wall stations the placement relies on wall conditions, visibility, and
likelihood of the wall station being damaged.
The ideal geometry of wall stations has been discussed in literature and differs from each
paper. Assessing the ideal geometry for a resection is difficult to compare and analyse.
However, the previous literature conclude that the accuracy of wall stations is not
affected significantly by the geometry of wall stations or the distance of the forwarded
control. However, “it is apparent that while the geometry of the resection has minor
effect upon the station precision and a negligible effect upon that of the distance to the
foresight, it has major impact upon the forward bearing precision and thus azimuth
control” (Grocock, 2014).
The setup position of the instrument is very important when carrying wall station control.
The instrument should be set up inside a minimum of three good wall stations using two
faced observations. The purpose of being inside the existing wall stations means that the
network solution generated will effectively be braced by the existing control. If a good
free station solution is not calculated, more wall stations need to be surveyed in and
analysis of the network solution investigated. Serious thought should be employed as to
whether forward stations should be surveyed from what is likely to be a poor network of
existing wall stations. If a station is found to have moved, or has been damaged, it should
be remove from the primary control network and then destroyed.
The ideal geometry of a resection has varied through literature which makes it hard to
assess. In regards to distances the first wall station to be surveyed in during setup is to be
the furthest (up to 100m), line of sight station that can be used. This will help stabilise the
carried bearing. The other stations should include a medium length shot (25-50m) and a
short length shot (between 5 -10m). With a quality network solution established, forward
78
wall stations can be carried with confidence. Forward stations are surveyed in two faces
and should be staggered along both sides of the drive (subject to ground/wall conditions)
Errors can either accumulate, cancel or reduce and should be detected in the survey
network. In this research project the check survey network will contain errors that have
been propagated while advancing the traverse. By performing six sets of angles at each
station set up the confidence of the positions of the wall stations will be increased.
Propagation of errors is disturbed with behaviour of small errors which are commonly
random propagating through a traverse. The least squares adjustment eliminates the
random errors in the survey which limits the propagation of random errors.
Error propagation can be predicted by incorporating statistical tests and models. Random
variation in the fixed stations is transformed by the model into corresponding random
variation in the resulting free stations. This uncertainty in the adjusted free stations can
be scaled to a probability such as 95% and presented in error ellipses.
The primary control network of wall stations will have errors that have been propagated.
Each time a mine surveyor visits a site they commonly resect off wall stations. Errors that
are accumulated from each visit from a surveyor can lead to deviation in the true position.
A major problem with the wall station resection method is errors can be propagated
extensively in bearing. “Any error in measuring distance would be carried throughout the
entire traverse, but that error would not compound. Errors in turning an angle would be
magnified by the further traverse from that point.” (McCormack, 2002).
The wall station furthest away from the fixed points that were checked by a previous
check survey is approximately 900 metres. That means that 900 metres of traversing and
forwarding control into the walls was required. As the distance from a checked wall
station increases it will have an impact on shape and size of the angles observed.
Numerous instrument set ups and resections would have been implemented to forward
wall stations. Over that substantial distance of traversing and where number and
79
geometry of the resections might not have been optimal we can expect distortion in
azimuth. It is clear that bearing errors can be produced by uncertainty in resections.
5.10 CONCLUSION
The chapter has analysed the results of the least squares adjustment and discussed
statistical behaviour. The important considerations analysed was the types of errors
expected in an underground check survey and the external factors that can cause
deviation in observations.
Slope distance, direction and vertical angles were analysed to assess the quality of the
check survey. It was observed that the greatest standardised residuals were located at the
start and end of the survey. The assumption is that the traverse is closing onto another
fixed control point which will lead to variation. Integrity of the original fixed control points
was questioned as the fixed stations were verified in a check survey three years ago. Over
three years wall stations are expected to move due to the nature of the mine.
The absolute and relative error ellipses were analyse at a 95% confidence interval. It was
observed that there was an azimuth deficiency in the Eastern direction which was caused
by the orientation of the fixed control. The relative ellipses semi-major ellipses were in
compliance with class “D” ICSM standards which was required.
The next chapter will consider important requirements that mine surveyors should
consider when completing a check survey. These requirements were based from the field
work completed and the behaviour of the results.
80
6. CHAPTER 6 – CONCLUSION
6.1 INTRODUCTION
Check survey control was required to be extended to replace unchecked wall stations
within X41 mine at MICO. The high order check survey control was to be verified and
compliant with ICSM SP1 Mines Class D Standard. As a surveyor it is a professional duty
to comply with legislation and provide accurate and adequate data. The requirements of
legislation such as ICSM SP1 v2.1, Survey and Mapping Infrastructure Act 2014 and the
Surveyor Code of Practice, ensure a reliable and accurate survey control network is
available. This legislation determines the standards of accuracy and consistency of survey
work performed within Queensland, Australia.
This research project focused on assessing the statistical results obtained by the
adjustment and particularly investigate slope distances, angular observations and error
ellipses. The network was assessed in terms of accuracy and precision and its uncertainty
was evaluated. By assessing the results obtained considerations for future surveyors
have been outlined when completing a check survey.
Check surveys are an essential procedure in underground mine surveying and should be
planned and performed on a regular basis. Some of the important considerations to
consider when completing a check survey include:
- It is advised to use survey equipment that is in a clean and equipment that has
not been disturbed. It is advised all survey equipment be calibrated and checked
to reduce any potential errors in the check survey.
- By completing at least four rounds of sets of angles it will improve the confidence
in the accuracy of network as redundancy will be increased.
81
- To check the accuracy of the survey when shorter distances are surveyed is to
take longer observations which bypass intermediate survey stations to minimise
the propagation of error by decreasing the number of stations observed.
- The geometry of the fixed stations is ideally balanced in the East and North
direction to avoid azimuth distortions in certain directions. In a narrow tunnel
environment it is difficult to get an even spread of fixed stations due to the layout
of the mine.
- Wall stations are expected to have some movement in an underground mine so
it is essential for the mine surveyor to install wall stations in areas that will have
least amount of disturbance to the surveyor’s best ability.
- When it is feasible it is recommended that the check survey should be closed on
a base of origin.
- When closing the traverse is not feasible it is recommended to apply a check on
different levels of the mine to verify the survey network.
- Wall stations when not occupied and are in an area of the mine with high activity
should be covered with a plastic sleeve to protect the station from being removed
or covered by shotcrete.
- The baseline of the check survey should ideally be at the start and end of the
check survey as well as connections on each level of the mine and be in stable
area of the mine when possible.
- The check survey should be in compliance with the SP1 standards.
- Mine surveyors should make conscious effort to use at least three wall stations in
resections when forwarding new control. By having adequate geometry and
number of wall stations in the resection where feasible the risk of error in the
positional fix by poor observations will be avoided. The wall station method can
have major error propagation problems in bearings when poor observations are
obtained to get a positional fix of the instrument.
- As errors in bearings is propagated greater degree in comparison to distance
measurements it is recommended to verify the azimuth of the baseline used by
taking gyroscope observations to check the bearing.
82
6.3 CONCLUSION
Mine surveyors are using wall stations into their daily processes to orientate the position
of their total station by resection. As wall stations are used so often and are critical to
staking out information for the operations of the mine there needs to be a verification on
the wall stations.
The main weakness of the wall station method has been recognized as the potential error
in positional due to poor observations. The research indicated the likelihood of error
propagation especially in the angle component. In saying this, it is vital to verify the
integrity of the primary survey control which is used on a daily basis.
Over the length of the dissertation ideas for potential and further work were considered
that relates to the check survey method. The next chapter, will outline further research
that could be completed on this dissertation and propose recommendations that have
not been analysed in the past.
83
7. CHAPTER 7 –
RECOMMENDATIONS
7.1 INTRODUCTION
This chapter of the dissertation will aim to recommend further work that can lead from a
basis of this research project. By completing the check survey and examining an analysis
of the survey network further work that can be completed that would build on this
dissertation were identified. No previous literature was found that specifically examined
the check survey method so potential work in this study area should be further assessed.
Some of the recommendations have been discussed in the following chapter.
In an underground mine with deep levels such as MICO the rock and tunnels are expected
to have some movement and deformation. Research could be completed on movement
84
of the rock and what effect that will have on the primary control network of wall stations.
Rock movement will cause a dislocation in the position and evaluation of the wall stations.
The impacts of tunnel deformation needs to fully assess to examine the impacts it can
have on the primary control network of wall stations.
The research has specified the possibility of error propagation in the bearing of the survey
network. It is very important to verify the integrity of the survey network to different
levels of the mine. In underground mines, accuracy of survey networks on independent
levels cannot be verified unless there is a closure between two levels. Deviation of error
which has been propagated by the survey network can be recognized when azimuth is
checked by a gyroscope reading. When using a gyroscope the error in bearing transfer
and error propagation of the survey network can be checked. The azimuth observed from
the gyroscope is compared to the check survey over a baseline. The gyroscope
observations should be repeated to increase the accuracy of the observations.
PRISM
By completing the check survey and completing an analysis it has been observed that
observations to wall station prisms can result in errors in the position of the wall station.
The calculation of the wall station position is dependent on the connections and size of
the prism. A potential line of research would be to examine the effects on misalignment
of using wall station prisms which have not been intended to be a true 360 degree wall
station prism. The optical centre of a wall station prism does not continue to be true when
the prism is rotated.
85
7.6 PLANNING OF UNDERGROUND SURVEY NETWORKS
Planning of underground survey networks in new and existing mines seems to not be
given the specific attention and thought it desires. By planning and budgeting the survey
networks in an underground mine it would optimise the establishment of survey networks
within the mine. Distances between survey networks, when gyroscope observation
checks need to be completed and the dates that they should be expected to be completed
should be planned. By implementing network analysis within planning of development
the survey networks can be optimised. The planning could overcome potential error in
propagation and plan to prevent the magnification of the error.
7.7 CONCLUSION
This dissertation has achieved the aims and objectives by field testing and a thorough
statistical analysis. The dissertation has aimed to outline the importance for check survey
networks in underground mines and provide important requirements that should be
considered when completing. Due to the limited literature on wall station surveying in
mining, recommendations have been discussed for further work.
86
8. REFERENCES
Bannister, A. (2006). Surveying. Pearson Education India.
Bruce, D., Burdett, M. and P. Corcoran (eds.), Proceedings of the Surveying & Spatial
Sciences Institute Biennial
Cawood, F., & Richards, W. (2007). A review of the role of the coal mine surveyor in South
Africa. JOURNAL-SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY, 107(2), 109.
Dima, N., Herbei, O., & Vereș, J. (1999). The theory of errors and method of least squares:
Universitas Publishing House, Petroșani. Retrieved rom URL
Fowler, S. (2006). Design and Preanalysis of Underground Control Networks for Tunnel
Construction. Lisans Tezi.
Grocock, B. (2014, August 31). Frank Smith Final Presentation. Retrieved October 11,
2016, from Slide Share, http://www.slideshare.net/brett_grocock/frank-smith-final-
presentation
Harvey, B., & Rüeger, J. (1992). Theodolite observations and least squares. Australian
surveyor, 37(2), 120-128.
87
International Conference, Adelaide 2009, Surveying & Spatial Sciences Institute, pp. 559-
575. ISBN: 978-0-9581366-8-6.
Leica Heerbrugg, Leica Flexline TS02/TS06/TS09 User Manual Version 1.0 English,
Heerbrugg, Switserland: Leica Geosystems AG Heerbrugg, 2009.
McCormack, B. (2002). Wall Stations (Reference Points): The Use of resection to Replace
conventional Underground Traversing. In Proceedings, National Mine Surveying
Conference, Darwin, Australia
Mining surveyor. (2016, October 12). Retrieved October 11, 2016, from Surveyors Board
Queensland, http://sbq.com.au/about-surveyors/mining-surveyor/
Mount Isa Mines Rotary Rodeo. (2016). Retrieved October 11, 2016, from
http://www.isarodeo.com.au/plan-your-trip/the-facts/
R. Stengele and I. Shätti-Stählin, "Geodetic basis and main control surveys in the Gotthard
base tunnel," Alp transit Gotthard, pp. 15-23, Accessed 2016.
Roberts, C., Ozdemir, S., & McElroy, S. (2009). Where is Positional Uncertainty. In
Proceedings of SSC
Shepherd, L., & Jarosz, A. (2006). An error analysis of the wall station resection method of
underground control traversing. Western Australia: Curtin University of technology,
Western Australlian School of Mines, Mine Surveying Program kalgoorlie, 8.
88
VERES, I. The Accurate Determination of the Orientations in an Underground Traverse
through Indirect Measurements. A A, 1, 0.
Wei, L., & Chuan, H. (2006). Study on construction influence of shield tunnels traversing
adjacently under underground large-scale structure. Chinese Journal of Geotechnical
Engineering, 28(10), 1277-1282.
W. S. Bernard, J. M. Solomon and S. G. Britton, "Chapter 8.2 Mine surveying and Aerial
mapping," in SME Mining Engineering Handbook, 2nd Edition, Volume 1, 1992, ,, Society
for Mining, Metallurgy and Exploration, 1992, pp. 538-550.
Young, L. E. (2012). A study of mine surveying methods and their applications to mining
engineering. HardPress Publishing.
89
9. APPENDICES
Project Specification
Major: Surveying
Project Aim: A high order check survey will be carried out to verify the quality of
existing wall stations and provide accurate control to further advance into
the mine. A least squared adjustment will be computed and an analytical
study will be investigated on the variables.
90
6. Recommend important considerations that should be considered when
conducting a check survey based on the results obtained.
If times and resources permit:
91
Appendix B: EDM CALIBRATION
92
Appendix C: KESTREL CALIBRATION
93
Appendix D: ATMOSPHERIC DATA
94
RS020216I INST 0 35.1 1033.9
*RS020216J INST 0 35.9 1032.7
*RS020216J INST 0 35.7 1032.7
RS020216K INST 0 36.7 1032.8
RS020216L INST 0 35.0 1033.6
RS020216M INST 0 34.4 1033.5
RS020216N INST 0 33.1 1034.1
95
Appendix E: FIELD SHEETS OF SITE
96
97
98
99
Appendix F: ADJUSTED COORDINATES
100
CTS6652 0.0051 0.0023 0.0003
CTS6699 0.0055 0.0023 0.0003
CTS6855 0.0047 0.0019 0.0003
CTS6863 0.0048 0.0015 0.0003
CTS6864 0.0048 0.0013 0.0003
CTS6865 0.0046 0.001 0.0003
CTS4298 0.0041 0.001 0.0003
CTS4299 0.0039 0.001 0.0003
CTS6904 0.0033 0.001 0.0004
CTS7037 0.003 0.0011 0.0004
CTS7036 0.0031 0.001 0.0004
CTS6903 0.0036 0.001 0.0004
CTS6876 0.0043 0.0011 0.0004
CTS7054 0.0031 0.0012 0.0004
CTS4301 0.0037 0.0013 0.0004
CTS7099 0.0034 0.0011 0.0004
CTS4300 0.003 0.0011 0.0004
CTS7253 0.0046 0.0015 0.0004
CTS7255 0.0053 0.0016 0.0004
CTS7182 0.0041 0.0013 0.0004
CTS7282 0.0062 0.0018 0.0004
CTS7385 0.0067 0.0019 0.0004
CTS4302 0.0064 0.0017 0.0004
CTS7281 0.0057 0.0016 0.0004
CTS7254 0.005 0.0015 0.0004
CTS7342 0.0069 0.0025 0.0004
CTS4303 0.007 0.0028 0.0004
CTS7399 0.0077 0.0039 0.0004
CTS7371 0.0074 0.003 0.0004
CTS7341 0.0069 0.0022 0.0004
CTS7357 0.0066 0.0017 0.0004
101
CTS4304 0.008 0.0044 0.0004
CTS7401 0.0082 0.0046 0.0004
CTS7400 0.0079 0.0041 0.0004
CTS4305 0.0088 0.0047 0.0006
102
Appendix G: RELATIVE ELLIPSES 95%
103
CTS6549 0.0075 0.0015 64ー 06' 58.86" 0.0008
CTS6550 0.009 0.0015 64ー 55' 01.58" 0.0008
190116G 0.0086 0.0014 66ー 12' 11.11" 0.0007
CTS6546 0.0064 0.0015 66ー 15' 49.56" 0.0008
CTS6600 0.0108 0.0016 65ー 39' 45.72" 0.0008
190116H 0.0139 0.0014 67ー 12' 30.65" 0.0008
CTS4297 0.0143 0.0016 67ー 57' 45.02" 0.0008
CTS6601 0.012 0.0017 67ー 29' 51.94" 0.0008
CTS6837 0.0138 0.0015 63ー 44' 28.77" 0.0009
CTS6652 0.0156 0.0019 66ー 31' 12.31" 0.0009
CTS6699 0.0165 0.0019 68ー 03' 29.35" 0.0009
CTS6855 0.0141 0.0015 68ー 41' 47.59" 0.0009
CTS6863 0.014 0.0015 73ー 09' 50.89" 0.0008
190116I 0.0139 0.0016 75ー 21' 01.61" 0.0008
CTS6864 0.0138 0.0016 76ー 39' 06.36" 0.0008
CTS6865 0.013 0.0019 80ー 37' 30.57" 0.0009
20216A 0.0139 0.0015 67ー 12' 36.95" 0.0008
20216B 0.0139 0.0016 75ー 17' 25.46" 0.0008
20216C 0.0131 0.0019 79ー 58' 13.80" 0.0009
CTS4298 0.0117 0.0022 80ー 45' 07.73" 0.001
CTS4299 0.011 0.0022 80ー 28' 27.41" 0.001
20216D 0.0112 0.002 79ー 26' 37.27" 0.0009
CTS6904 0.0095 0.0024 79ー 27' 10.55" 0.001
CTS7037 0.0085 0.0022 76ー 43' 01.27" 0.001
20216E 0.0086 0.002 76ー 57' 46.31" 0.001
CTS7036 0.0088 0.0021 77ー 27' 22.06" 0.001
CTS6903 0.0102 0.0021 78ー 31' 47.64" 0.001
CTS6876 0.0122 0.0021 79ー 43' 39.43" 0.001
CTS7054 0.0091 0.0023 74ー 27' 58.15" 0.0011
CTS4301 0.0107 0.0021 74ー 02' 52.45" 0.001
104
20216F 0.0104 0.002 75ー 03' 40.72" 0.001
CTS7099 0.0098 0.0021 75ー 23' 46.05" 0.001
CTS4300 0.0086 0.0021 75ー 54' 26.00" 0.001
CTS7253 0.0133 0.0022 74ー 04' 10.01" 0.0011
CTS7255 0.0152 0.0022 74ー 25' 49.87" 0.0011
20216G 0.0147 0.0021 75ー 32' 28.87" 0.001
CTS7182 0.012 0.0021 75ー 33' 51.78" 0.001
CTS7282 0.018 0.0023 75ー 12' 47.32" 0.0011
CTS7385 0.0193 0.0023 75ー 48' 23.67" 0.0011
20216H 0.0188 0.0021 76ー 02' 17.56" 0.0011
CTS4302 0.0185 0.0022 76ー 36' 40.83" 0.0011
CTS7281 0.0163 0.0023 76ー 15' 13.27" 0.0011
CTS7254 0.0143 0.0022 75ー 53' 02.21" 0.0011
CTS7342 0.0202 0.0024 71ー 10' 48.74" 0.0012
CTS4303 0.0209 0.0026 69ー 22' 55.52" 0.0012
CTS7399 0.0239 0.0031 63ー 37' 08.86" 0.0012
20216I 0.0237 0.003 64ー 13' 55.24" 0.0011
CTS7371 0.0221 0.0027 68ー 25' 40.34" 0.0012
CTS7341 0.0201 0.0024 73ー 12' 23.70" 0.0012
CTS7357 0.0189 0.0022 76ー 49' 41.48" 0.0012
CTS4304 0.0253 0.0034 61ー 53' 43.74" 0.0012
CTS7401 0.0262 0.0034 61ー 28' 48.74" 0.0012
20216J 0.0259 0.0033 61ー 48' 16.10" 0.0011
CTS7400 0.0246 0.0032 63ー 34' 45.56" 0.0012
CTS4305 0.0277 0.0038 62ー 39' 42.08" 0.0015
20216K 0.0236 0.003 64ー 20' 10.65" 0.0011
20216L 0.0189 0.0021 76ー 10' 33.17" 0.0011
20216M 0.0146 0.0021 75ー 33' 58.22" 0.001
20216N 0.0103 0.0021 74ー 59' 37.57" 0.001
50216A 0.0147 0.0021 74ー 51' 10.89" 0.001
105
50216B 0.0104 0.0021 74ー 18' 30.05" 0.001
50216C 0.0086 0.002 77ー 00' 33.58" 0.0009
50216D 0.0112 0.0021 80ー 10' 26.59" 0.0009
50216E 0.0129 0.0019 80ー 25' 17.98" 0.0009
50216F 0.0139 0.0016 74ー 49' 01.54" 0.0008
50216G 0.0139 0.0014 67ー 07' 38.27" 0.0007
50216H 0.0085 0.0013 66ー 08' 02.38" 0.0007
50216I 0.0043 0.0012 63ー 23' 48.70" 0.0006
50216J 0.0012 0.0011 170ー 16' 43.06" 0.0006
50216K 0.001 0.0008 98ー 42' 27.03" 0.0005
50216L 0.0006 0.0004 165ー 45' 50.20" 0.0003
50216M 0.0006 0.0004 158ー 49' 54.88" 0.0003
50216N 0.0006 0.0005 178ー 50' 14.51" 0.0003
106