The Cost of Quality and Accounting For Production Losses
The Cost of Quality and Accounting For Production Losses
The Cost of Quality and Accounting For Production Losses
MULTIPLE CHOICE
A 1. The quality costs that are associated with materials and products that fail to
meet quality standards and result in manufacturing losses are known as:
A. internal failure costs
B. external failure costs
C. prevention costs
D. appraisal costs
E. none of the above
D 2. The quality costs that are associated with designing, implementing, and
maintaining the quality system are known as:
A. appraisal costs
B. internal failure costs
C. external failure costs
D. prevention costs
E. none of the above
C 3. The quality costs that are incurred to ensure that materials and products meet
quality standards are known as:
A. external failure costs
B. prevention costs
C. appraisal costs
D. internal failure costs
E. none of the above
B 4. The quality costs that are incurred because inferior quality products are shipped
to customers are known as:
A. internal failure costs
B. external failure costs
C. prevention costs
D. appraisal costs
E. none of the above
82
83 Chapter 7
E 10 . All of the following accounts would be acceptable ones to credit at the time
scrap is sold except:
A. Scrap Sales
B. Cost of Goods Sold
C. Factory Overhead Control
D. Work in Process
E. all of the above would be acceptable
A 12 . When spoilage occurs because of some action taken by the customer, the
unrecoverable cost of the spoilage should be charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
C 13 . When spoilage occurs because of some internal failure, the unrecoverable cost
should be charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
A 14 . When rework occurs because of some action taken by the customer, the cost of
the rework should be charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
C 15 . When rework occurs because of some internal failure, the cost of the rework
should be charged to:
A. Work in Process
B. Spoiled Goods Inventory
C. Factory Overhead Control
D. Applied Factory Overhead
E. none of the above
C 16 . Newman Company's Job 1865 for the manufacture of 2,200 coats was completed
during August at the unit costs presented below. Due to an internal failure in
the production process, 200 coats were found to be spoiled during final
inspection that were sold to a jobber for $6,000.
What would be the unit cost of good coats produced on Job 1865?
A. $57.00
B. $55.00
C. $56.00
D. $58.00
E. none of the above
A 17 . During March, Vaughan Company incurred the following costs on Job 009 for the
manufacture of 200 motors:
SUPPORTING CALCULATION:
B 22 . In manufacturing its products for the month of March, Leo Co. incurred normal
production shrinkage of $10,000 and spoilage due to internal failure of $12,000.
How much spoilage cost should Leo charge to Factory Overhead Control for the
month of March?
A. $22,000
B. $12,000
C. $10,000
D. $0
E. none of the above
C 23 . Willis, Inc. instituted a new process in October. During October, 10,000 units
were started in Department A. Of the units started, 1,000 were lost in the
process due to normal production shrinkage, 7,000 were transferred to
Department B, and 2,000 remained in work in process at October 31. The work
in process at October 31 was 100% complete as to materials costs and 50%
complete as to conversion costs. Materials costs of $27,000 and conversion
costs of $40,000 were charged to Department A in October. What were the total
costs transferred to Department B?
A. $46,900
B. $53,600
C. $56,000
D. $57,120
E. none of the above
SUPPORTING CALCULATION:
During the week, 2,100 baseballs were completed; 2,000 passed inspection.
There was no ending work in process. The cost of the spoilage charged to
Factory Overhead is:
A. $33
B. $22
C. $1,100
D. $55
E. none of the above
SUPPORTING CALCULATION:
SUPPORTING CALCULATION:
SUPPORTING CALCULATION:
PROBLEMS
PROBLEM
1.
Journal Entrie s for Scrap. Munoz Metal Products accumulates metal shavings from the
shop floor and sells them periodically to a nearby scrap dealer. Scrap sales, on account, for
the period just ended total $2,300.
SOLUTION
PROBLEM
2.
Spoilage in a Job Order Cost Syste m . Walker Inc. manufactures custom wood products.
During the current period, an order for 2,000 workbenches was begun on Job 1994. After
the job was completed, the benches were inspected and 100 units were determined to be
defective. The customer has agreed to accept the order with only 1,900 units instead of
the quantity originally ordered. The spoiled units can be sold as seconds for $25 each.
Spoiled goods are kept in a separate inventory account from finished goods. Total costs
charged to
Job 1994 follow:
Required:
(1) Assuming that the defective units were the result of an internal failure (i.e., an
employee error or a machine failure), prepare the appropriate general journal entries
to record the transfer of the defective units to a separate inventory account and the
completion and shipment of Job 1994 to the customer.
(2) Assuming that the defective units were the result of a change in design specified by
the customer after the units were completed, prepare the appropriate general
journal entries to record the transfer of the defective units to the separate inventory
account and the completion and shipment of Job 1994 to the customer.
SOLUTION
(1) Spoiled Goods Inventory (10 units x $25 salvage) ................. 250
Factory Overhead Control ............................................................ 250
Work in Process (10 units x $50* cost) .............................. 500
(2) Spoiled Goods Inventory (10 units x $25 salvage) ................. 250
Work in Process ...................................................................... 250
PROBLEM
3.
Entries for Chargi ng Rewo r k Costs Caus e d by Intern al Failure and by Chan g e in
Custo m e r Specificatio n. Albany Appliances manufactured 100 microwave ovens in a
recent production run and discovered that 10 ovens were defective and required reworking
as follows:
Required:
(1) Prepare the journal entries to record (a) the normal production costs, (b) the rework
costs, and (c) the transfer of the job costs to Finished Goods assuming that rework
costs were caused by an internal failure.
(2) Prepare the same journal entries as in (1), assuming that rework costs were caused
by a change in customer specifications.
SOLUTION
Debit Credit
(1) (a) Work in Process ................................................................... 20,000
Materials ......................................................................... 5,000
Payroll ............................................................................. 7,500
Applied Factory Overhead .......................................... 7,500
PROBLEM
4.
Comp u t a ti o n of Equiv ale nt Units With Produc ti o n Losse s. Potter Paint Company
manufactures paint in three departments using a process cost system with an average cost
flow assumption. Selected cost and production data for the Blending Department, the
second department in the production process, for the month just ended, are as follows:
The paint is inspected at the end of the process in the Blending Department to detect any
spoiled batches. Ending inventory is 75% complete as to materials and 25% complete as to
conversion costs.
Required:
(1) Compute the equivalent units of production for each cost element in the Blending
Department for the month just ended.
(2) Determine the average cost per equivalent unit for each cost element.
SOLUTION
PROBLEM
5.
Spoilage With a Salvag e Value in a Proce ss Cost Syste m Using an Avera g e Cost
Flow Assu m p ti o n . Carter Company manufactures a single product in two departments,
Cutting and Finishing. Units of a product are started in the Cutting Department and then
transferred to the Finishing Department where they are completed. Units are inspected at
the 80% stage of completion in the Finishing Department. Good units are transferred to
finished goods inventory when completed and spoiled units are transferred to a separate
inventory account. Spoiled units are inventoried at their salvage value of $3 each, and the
unrecoverable cost of spoilage, which was caused by an internal failure, should be charged
to the appropriate account.
Materials are added at the beginning of the production process. At the end of June,
2,000 units were still in process in the Finishing Department, 100% complete as to
materials and 60% complete as to conversion costs. During July, 20,000 units were
transferred from the Cutting Department to the Finishing Department and 15,000 were
transferred from the Finishing Department to finished goods inventory. At the end of July,
the Finishing Department still had 4,000 units in process, 100% complete as to materials
and 20% complete as to conversion costs. Cost data related to July operations in the
Finishing Department follow:
Beginning Added
Costs charged to the department: ........................................................... Inventory This Period
Cost from preceding department ...................................................... $6,050 $54,450
Materials ................................................................................................. 3,410 30,690
Labor ....................................................................................................... 1,638 14,742
Factory overhead .................................................................................. 2,184 19,656
Required: Complete the following cost of production report for the Finishing Department
based on the data presented for July, assuming the company uses a process cost system
with average costing to account for its production.
The Cost of Quality and Accounting for Production Losses 94
SOLUTION
Carter Corporation
Finishing Department
Cost of Production Report
For July, 19- -
% Unit Total
Cost Acco un t e d for as Follows Units Complete Cost Cost
Transferred to
finished goods ......................... 15,000 100% $ 6.40 $96,000
Transferred to spoiled goods
inventory at salvage value ... 3,000 3.00 9,000
Charge to factory overhead
for spoilage:
Cost from preceding
department ........................ 3,000 100% $ 2.75 $ 8,250
Materials ................................... 3,000 100% 1.55 4,650
Labor. ....................................... 3,000 80% .90 2,160
Factory overhead ................... 3,000 80% 1.20 2,880
$ 17,940
Less salvage value of
spoiled units ...................... 3,000 3.00 9,000 8,940
Work in process,
ending inventory:
Cost from preceding
department ........................ 4,000 100% $ 2.75 11,000
Materials ................................... 4,000 100% 1.55 6,200
Labor. ....................................... 4,000 20% .90 720
Factory overhead ................... 4,000 20% 1.20 960 18,880
Total cost accounted for ............. $132,820
* Total number of equivalent units required in the cost accounted for section determined as
follows:
Prior
Dept. Cost Materials Labor Overhead
Equivalent units transferred out ................ 15,000 15,000 15,000 15,000
Equivalent units in ending inventory ........ 4,000 4,000 800 800
Equivalent units of spoilage ....................... 3,000 3,000 2,400 2,400
Total equivalent units .................................. 22,000 22,000 18,200 18,200
The Cost of Quality and Accounting for Production Losses 96
PROBLEM
6.
Produc ti o n Shrink a g e in a Proce s s Cost Syste m Using an Averag e Cost Flow
Assu m p ti o n . Carrera Chemical Inc. uses a process cost system with an average cost flow
assumption to account for the production of its only product. The product is manufactured
in two departments. Units of product are started in the Cooking Department and then
transferred to the Blending Department where they are completed. Because of the intense
heat applied in the Cooking Department, some of the production volume is lost to
evaporation. Labor and overhead are treated as one element of cost in the Cooking
Department (i.e., conversion cost). Data related to May operations in the Cooking
Department follow:
Beginning Added
Costs charged to the department: ........................................................... Inventory This Period
Materials .................................................................................................. $4,375 $11,795
Conversion cost ..................................................................................... 2,975 6,181
Required: Prepare a cost of production report for the Cooking Department based on the
data presented for May.
97 Chapter 7
SOLUTION
Conversion
Quantity Sche d ule .................................................... Materials Cost Quantity
Beginning inventory ..................................................... 10,000
Started in process this period ..................................... 45,000
55,000
% Unit Total
Cost Acco un t e d for as Follows Units Complete Cost Cost
Transferred to Blending
Department ............................. 40,000 100% $.54 $21,600
Work in process,
ending inventory:
Materials ................................... 9,000 100% $.33 $2,970
Conversion cost ...................... 9,000 40% .21 756 3,726
Total cost accounted for ............. $25,326
* Total number of equivalent units required in the cost accounted for section determined as
follows:
Conversion
Materials Cost
Equivalent units transferred out .............................................................. 40,000 40,000
Equivalent units in ending inventory ...................................................... 9,000 3,600
Total equivalent units ................................................................................. 49,000 43,600
The Cost of Quality and Accounting for Production Losses 98
PROBLEM
7.
Spoilage With a Salvag e Value in a Proce ss Cost Syste m With a Fifo Cost Flow
Assu m p ti o n . School Craft Petroleum Company uses a process cost system with a fifo cost
flow assumption to account for production, which is manufactured in two departments.
Units of product are started in the Cracking Department and then transferred to the
Refining Department where they are completed. Units are inspected at the end of the
production process in the Refining Department. Good units are transferred to finished
goods inventory and spoiled units are transferred to a separate inventory account. Spoiled
units are inventoried at their salvage value of $8 each, and the unrecoverable cost of
spoilage resulting from an internal production failure is charged to the appropriate account.
Data related to September operations in the Refining Department follow:
Units in beginning inventory (60% materials, 30% labor, 30% overhead) ............... 2,800
Units received from Cracking Department this period .................................................. 8,400
Units transferred to the finished goods inventory this period ..................................... 7,600
Units transferred to special inventory account this period .......................................... 1,100
Units in ending inventory (100% materials, 50% labor, 50% overhead) ................... 2,500
Beginning Added
Costs charged to the department: ........................................................... Inventory This Period
Cost from preceding department ....................................................... $17,889 $68,040
Materials .................................................................................................. 2,733 11,900
Labor ........................................................................................................ 7,278 30,063
Factory overhead .................................................................................. 12,350 51,016
Required: Prepare a cost of production report for the Refining Department based on the
data presented for September.
99 Chapter 7
SOLUTION
% Unit Total
Cost Acco un t e d for as Follows Units Complete Cost Cost
Transferred to finished goods:
From beginning inventory ...... $ 40,250
Cost to complete this
period:
Materials ......................... 2,800 40% $ 1.25 $ 1,400
Labor ............................... 2,800 70% 3.30 6,468
Factory overhead .......... 2,800 70% 5.60 10,976 $ 59,094
Started and completed
this period ............................ 4,800 100% $ 18.25 87,600
Total cost transferred to
Finishing Department ........ $ 146,694
Transferred to spoiled goods
inventory at salvage value ..... 1,100 $ 8.00 8,800
Charged to factory overhead for
spoilage:
Cost of completed spoiled
units ...................................... 1,100 100% $ 18.25 $ 20,075
Less salvage value of spoiled
units ...................................... 1,100 8.00 8,800 11,275
Work in process,
ending inventory:
Cost from preceding
department .......................... 2,500 100% $ 8.10 $ 20,250
Materials ..................................... 2,500 100% 1.25 3,125
Labor. ......................................... 2,500 50% 3.30 4,125
Factory overhead ..................... 2,500 50% 5.60 7,000 34,500
Total cost accounted for ............... $ 201,269
* Number of equivalent units of cost added during the current period determined as
follows:
Prior
Dept. Cost Materials Labor Overhead
To complete beginning inventory ......... 0 1,120 1,960 1,960
Started and completed this period ....... 4,800 4,800 4,800 4,800
Ending inventory ...................................... 2,500 2,500 1,250 1,250
Spoiled units ............................................. 1,100 1,100 1,100 1,100
Total equivalent units ............................. 8,400 9,520 9,110 9,110