` Doc No : FM-DUTA-REPT-01

PT. DUTA UTAMA TEHNIK ABADI Page :1


MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : March 11, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : March 11, 2019 TOMORROW : March 12, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Mobilization Scaffolding T-34 C 30% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 1 9
2 2 Supervisor 1 prs 1 9 1 9
3 3 Foreman 1 prs 1 9 1 9
4 4 Safety Man 1 prs 1 9 1 9
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 5 45
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 7 63
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 5 45
11 11 Mech./Elect. 1 prs 1 9 1 9
12 12 Tool Keeper 1 prs 1 9 1 9
13 Total 23 prs 23 207 23 207
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : March 13, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : March 13, 2019 TOMORROW : March 14, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 5% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 2 18
2 2 Supervisor 1 prs 1 9 2 18
3 3 Foreman 1 prs 1 9 2 18
4 4 Safety Man 1 prs 1 9 2 18
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 10 90
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 14 126
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 10 90
11 11 Mech./Elect. 1 prs 1 9 2 18
12 12 Tool Keeper 1 prs 1 9 2 18
13 Total 23 prs 23 207 46 414
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : March 14, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : March 14, 2019 TOMORROW : March 15, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 10% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 3 27
2 2 Supervisor 1 prs 1 9 3 27
3 3 Foreman 1 prs 1 9 3 27
4 4 Safety Man 1 prs 1 9 3 27
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 15 135
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 21 189
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 15 135
11 11 Mech./Elect. 1 prs 1 9 3 27
12 12 Tool Keeper 1 prs 1 9 3 27
13 Total 23 prs 23 207 69 621
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : March 15, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : March 15, 2019 TOMORROW : March 16, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 15% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 4 36
2 2 Supervisor 1 prs 1 9 4 36
3 3 Foreman 1 prs 1 9 4 36
4 4 Safety Man 1 prs 1 9 4 36
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 20 180
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 28 252
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 20 180
11 11 Mech./Elect. 1 prs 1 9 4 36
12 12 Tool Keeper 1 prs 1 9 4 36
13 Total 23 prs 23 207 92 828
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : March 18, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : March 18, 2019 TOMORROW : March 19, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 20% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 5 45
2 2 Supervisor 1 prs 1 9 5 45
3 3 Foreman 1 prs 1 9 5 45
4 4 Safety Man 1 prs 1 9 5 45
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 25 225
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 35 315
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 25 225
11 11 Mech./Elect. 1 prs 1 9 5 45
12 12 Tool Keeper 1 prs 1 9 5 45
13 Total 23 prs 23 207 115 1035
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 1, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 1, 2019 TOMORROW : April 2, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 35% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 6 54
2 2 Supervisor 1 prs 1 9 6 54
3 3 Foreman 1 prs 1 9 6 54
4 4 Safety Man 1 prs 1 9 6 54
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 30 270
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 42 378
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 30 270
11 11 Mech./Elect. 1 prs 1 9 6 54
12 12 Tool Keeper 1 prs 1 9 6 54
13 Total 23 prs 23 207 138 1242
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 2, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 2, 2019 TOMORROW : April 3, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 40% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 7 63
2 2 Supervisor 1 prs 1 9 7 63
3 3 Foreman 1 prs 1 9 7 63
4 4 Safety Man 1 prs 1 9 7 63
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 35 315
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 49 441
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 35 315
11 11 Mech./Elect. 1 prs 1 9 7 63
12 12 Tool Keeper 1 prs 1 9 7 63
13 Total 23 prs 23 207 161 1449
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 4, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 4, 2019 TOMORROW : April 5, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 45% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 8 72
2 2 Supervisor 1 prs 1 9 8 72
3 3 Foreman 1 prs 1 9 8 72
4 4 Safety Man 1 prs 1 9 8 72
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 40 360
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 56 504
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 40 360
11 11 Mech./Elect. 1 prs 1 9 8 72
12 12 Tool Keeper 1 prs 1 9 8 72
13 Total 23 prs 23 207 184 1656
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 5, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 5, 2019 TOMORROW : April 6, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 50% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 9 81
2 2 Supervisor 1 prs 1 9 9 81
3 3 Foreman 1 prs 1 9 9 81
4 4 Safety Man 1 prs 1 9 9 81
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 45 405
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 63 567
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 45 405
11 11 Mech./Elect. 1 prs 1 9 9 81
12 12 Tool Keeper 1 prs 1 9 9 81
13 Total 23 prs 23 207 207 1863
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 8, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 8, 2019 TOMORROW : April 9, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 55% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 10 90
2 2 Supervisor 1 prs 1 9 10 90
3 3 Foreman 1 prs 1 9 10 90
4 4 Safety Man 1 prs 1 9 10 90
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 50 450
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 70 630
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 50 450
11 11 Mech./Elect. 1 prs 1 9 10 90
12 12 Tool Keeper 1 prs 1 9 10 90
13 Total 23 prs 23 207 230 2070
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 9, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 9, 2019 TOMORROW : April 10, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 60% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 11 99
2 2 Supervisor 1 prs 1 9 11 99
3 3 Foreman 1 prs 1 9 11 99
4 4 Safety Man 1 prs 1 9 11 99
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 55 495
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 77 693
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 55 495
11 11 Mech./Elect. 1 prs 1 9 11 99
12 12 Tool Keeper 1 prs 1 9 11 99
13 Total 23 prs 23 207 253 2277
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 10, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 10, 2019 TOMORROW : April 11, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 65% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 12 108
2 2 Supervisor 1 prs 1 9 12 108
3 3 Foreman 1 prs 1 9 12 108
4 4 Safety Man 1 prs 1 9 12 108
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 60 540
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 84 756
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 60 540
11 11 Mech./Elect. 1 prs 1 9 12 108
12 12 Tool Keeper 1 prs 1 9 12 108
13 Total 23 prs 23 207 276 2484
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 11, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 11, 2019 TOMORROW : April 12, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 70% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 13 117
2 2 Supervisor 1 prs 1 9 13 117
3 3 Foreman 1 prs 1 9 13 117
4 4 Safety Man 1 prs 1 9 13 117
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 65 585
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 91 819
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 65 585
11 11 Mech./Elect. 1 prs 1 9 13 117
12 12 Tool Keeper 1 prs 1 9 13 117
13 Total 23 prs 23 207 299 2691
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 12, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 12, 2019 TOMORROW : April 13, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 75% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 14 126
2 2 Supervisor 1 prs 1 9 14 126
3 3 Foreman 1 prs 1 9 14 126
4 4 Safety Man 1 prs 1 9 14 126
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 70 630
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 98 882
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 70 630
11 11 Mech./Elect. 1 prs 1 9 14 126
12 12 Tool Keeper 1 prs 1 9 14 126
13 Total 23 prs 23 207 322 2898
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 15, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 15, 2019 TOMORROW : April 16, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 80% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 15 135
2 2 Supervisor 1 prs 1 9 15 135
3 3 Foreman 1 prs 1 9 15 135
4 4 Safety Man 1 prs 1 9 15 135
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 75 675
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 105 945
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 75 675
11 11 Mech./Elect. 1 prs 1 9 15 135
12 12 Tool Keeper 1 prs 1 9 15 135
13 Total 23 prs 23 207 345 3105
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 16, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 16, 2019 TOMORROW : April 17, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 85% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 16 144
2 2 Supervisor 1 prs 1 9 16 144
3 3 Foreman 1 prs 1 9 16 144
4 4 Safety Man 1 prs 1 9 16 144
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 80 720
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 112 1008
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 80 720
11 11 Mech./Elect. 1 prs 1 9 16 144
12 12 Tool Keeper 1 prs 1 9 16 144
13 Total 23 prs 23 207 368 3312
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 22, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 22, 2019 TOMORROW : April 23, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 87% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 17 153
2 2 Supervisor 1 prs 1 9 17 153
3 3 Foreman 1 prs 1 9 17 153
4 4 Safety Man 1 prs 1 9 17 153
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 85 765
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 119 1071
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 85 765
11 11 Mech./Elect. 1 prs 1 9 17 153
12 12 Tool Keeper 1 prs 1 9 17 153
13 Total 23 prs 23 207 391 3519
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 23, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 23, 2019 TOMORROW : April 24, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 90% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 18 162
2 2 Supervisor 1 prs 1 9 18 162
3 3 Foreman 1 prs 1 9 18 162
4 4 Safety Man 1 prs 1 9 18 162
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 90 810
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 126 1134
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 90 810
11 11 Mech./Elect. 1 prs 1 9 18 162
12 12 Tool Keeper 1 prs 1 9 18 162
13 Total 23 prs 23 207 414 3726
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 24, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 24, 2019 TOMORROW : April 25, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 93% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 19 171
2 2 Supervisor 1 prs 1 9 19 171
3 3 Foreman 1 prs 1 9 19 171
4 4 Safety Man 1 prs 1 9 19 171
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 95 855
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 133 1197
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 95 855
11 11 Mech./Elect. 1 prs 1 9 19 171
12 12 Tool Keeper 1 prs 1 9 19 171
13 Total 23 prs 23 207 437 3933
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 25, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 25, 2019 TOMORROW : April 26, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 95% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 20 180
2 2 Supervisor 1 prs 1 9 20 180
3 3 Foreman 1 prs 1 9 20 180
4 4 Safety Man 1 prs 1 9 20 180
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 100 900
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 140 1260
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 100 900
11 11 Mech./Elect. 1 prs 1 9 20 180
12 12 Tool Keeper 1 prs 1 9 20 180
13 Total 23 prs 23 207 460 4140
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : April 26, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : April 26, 2019 TOMORROW : April 27, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 C 97% 1 Install Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 21 189
2 2 Supervisor 1 prs 1 9 21 189
3 3 Foreman 1 prs 1 9 21 189
4 4 Safety Man 1 prs 1 9 21 189
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 105 945
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 147 1323
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 105 945
11 11 Mech./Elect. 1 prs 1 9 21 189
12 12 Tool Keeper 1 prs 1 9 21 189
13 Total 23 prs 23 207 483 4347
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area :
Client : PT. Vopak Terminal Merak Date : May 3, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : May 3, 2019 TOMORROW : May 4, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Install Scaffolding T-34 F 100%

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 22 198
2 2 Supervisor 1 prs 1 9 22 198
3 3 Foreman 1 prs 1 9 22 198
4 4 Safety Man 1 prs 1 9 22 198
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 5 prs 5 45 110 990
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 7 prs 7 63 154 1386
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 110 990
11 11 Mech./Elect. 1 prs 1 9 22 198
12 12 Tool Keeper 1 prs 1 9 22 198
13 Total 23 prs 23 207 506 4554
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : July 24, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : July 24, 2019 TOMORROW : July 25, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 10% 1 Remove Scaffolding T-34

Weather & Hour Notes : Stop Working Because tranfer PX to T-34 (24:00~14:00 WIB)
Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 23 207
2 2 Supervisor 1 prs 1 9 23 207
3 3 Foreman 1 prs 1 9 23 207
4 4 Safety Man 1 prs 1 9 23 207
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 112 1008
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 157 1413
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 115 1035
11 11 Mech./Elect. 1 prs 1 9 23 207
12 12 Tool Keeper 1 prs 1 9 23 207
13 Total 16 prs 16 144 522 4698
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : July 26, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : July 26, 2019 TOMORROW : July 27, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 15% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 24 216
2 2 Supervisor 1 prs 1 9 24 216
3 3 Foreman 1 prs 1 9 24 216
4 4 Safety Man 1 prs 1 9 24 216
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 114 1026
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 160 1440
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 120 1080
11 11 Mech./Elect. 1 prs 1 9 24 216
12 12 Tool Keeper 1 prs 1 9 24 216
13 Total 16 prs 16 144 538 4842
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : July 27, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : July 27, 2019 TOMORROW : July 28, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 20% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 25 225
2 2 Supervisor 1 prs 1 9 25 225
3 3 Foreman 1 prs 1 9 25 225
4 4 Safety Man 1 prs 1 9 25 225
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 116 1044
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 163 1467
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 125 1125
11 11 Mech./Elect. 1 prs 1 9 25 225
12 12 Tool Keeper 1 prs 1 9 25 225
13 Total 16 prs 16 144 554 4986
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : July 29, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : July 29, 2019 TOMORROW : July 30, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 25% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 26 234
2 2 Supervisor 1 prs 1 9 26 234
3 3 Foreman 1 prs 1 9 26 234
4 4 Safety Man 1 prs 1 9 26 234
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 118 1062
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 166 1494
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 130 1170
11 11 Mech./Elect. 1 prs 1 9 26 234
12 12 Tool Keeper 1 prs 1 9 26 234
13 Total 16 prs 16 144 570 5130
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : July 30, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : July 30, 2019 TOMORROW : July 31, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 30% 1 Remove Scaffolding T-34

Weather & Hour Notes : Stop Working Because tranfer PX to T-34 (13:00~17:00 WIB)
Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 27 243
2 2 Supervisor 1 prs 1 9 27 243
3 3 Foreman 1 prs 1 9 27 243
4 4 Safety Man 1 prs 1 9 27 243
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 120 1080
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 169 1521
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 135 1215
11 11 Mech./Elect. 1 prs 1 9 27 243
12 12 Tool Keeper 1 prs 1 9 27 243
13 Total 16 prs 16 144 586 5274
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : July 31, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : July 31, 2019 TOMORROW : August 1, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 35% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 28 252
2 2 Supervisor 1 prs 1 9 28 252
3 3 Foreman 1 prs 1 9 28 252
4 4 Safety Man 1 prs 1 9 28 252
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 122 1098
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 172 1548
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 140 1260
11 11 Mech./Elect. 1 prs 1 9 28 252
12 12 Tool Keeper 1 prs 1 9 28 252
13 Total 16 prs 16 144 602 5418
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 1, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 1, 2019 TOMORROW : August 2, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 38% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 29 261
2 2 Supervisor 1 prs 1 9 29 261
3 3 Foreman 1 prs 1 9 29 261
4 4 Safety Man 1 prs 1 9 29 261
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 124 1116
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 175 1575
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 145 1305
11 11 Mech./Elect. 1 prs 1 9 29 261
12 12 Tool Keeper 1 prs 1 9 29 261
13 Total 16 prs 16 144 618 5562
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 2, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 2, 2019 TOMORROW : August 3, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 43% 1 Remove Scaffolding T-34

Weather & Hour Notes : Stop Working Because tranfer PX to T-34 (08:00~24:00 WIB)
Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 30 270
2 2 Supervisor 1 prs 1 9 30 270
3 3 Foreman 1 prs 1 9 30 270
4 4 Safety Man 1 prs 1 9 30 270
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 126 1134
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 178 1602
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 150 1350
11 11 Mech./Elect. 1 prs 1 9 30 270
12 12 Tool Keeper 1 prs 1 9 30 270
13 Total 16 prs 16 144 634 5706
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 3, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 3, 2019 TOMORROW : August 4, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 48% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 31 279
2 2 Supervisor 1 prs 1 9 31 279
3 3 Foreman 1 prs 1 9 31 279
4 4 Safety Man 1 prs 1 9 31 279
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 128 1152
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 181 1629
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 155 1395
11 11 Mech./Elect. 1 prs 1 9 31 279
12 12 Tool Keeper 1 prs 1 9 31 279
13 Total 16 prs 16 144 650 5850
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 5, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 5, 2019 TOMORROW : August 6, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 50% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 32 288
2 2 Supervisor 1 prs 1 9 32 288
3 3 Foreman 1 prs 1 9 32 288
4 4 Safety Man 1 prs 1 9 32 288
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 130 1170
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 184 1656
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 160 1440
11 11 Mech./Elect. 1 prs 1 9 32 288
12 12 Tool Keeper 1 prs 1 9 32 288
13 Total 16 prs 16 144 666 5994
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 6, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 6, 2019 TOMORROW : August 7, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 54% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 33 297
2 2 Supervisor 1 prs 1 9 33 297
3 3 Foreman 1 prs 1 9 33 297
4 4 Safety Man 1 prs 1 9 33 297
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 132 1188
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 187 1683
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 165 1485
11 11 Mech./Elect. 1 prs 1 9 33 297
12 12 Tool Keeper 1 prs 1 9 33 297
13 Total 16 prs 16 144 682 6138
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 7, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 7, 2019 TOMORROW : August 8, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 57% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 34 306
2 2 Supervisor 1 prs 1 9 34 306
3 3 Foreman 1 prs 1 9 34 306
4 4 Safety Man 1 prs 1 9 34 306
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 134 1206
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 190 1710
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 170 1530
11 11 Mech./Elect. 1 prs 1 9 34 306
12 12 Tool Keeper 1 prs 1 9 34 306
13 Total 16 prs 16 144 698 6282
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 8, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 8, 2019 TOMORROW : August 9, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 60% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 35 315
2 2 Supervisor 1 prs 1 9 35 315
3 3 Foreman 1 prs 1 9 35 315
4 4 Safety Man 1 prs 1 9 35 315
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 136 1224
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 193 1737
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 175 1575
11 11 Mech./Elect. 1 prs 1 9 35 315
12 12 Tool Keeper 1 prs 1 9 35 315
13 Total 16 prs 16 144 714 6426
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 9, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 9, 2019 TOMORROW : August 10, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 62% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 36 324
2 2 Supervisor 1 prs 1 9 36 324
3 3 Foreman 1 prs 1 9 36 324
4 4 Safety Man 1 prs 1 9 36 324
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 138 1242
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 196 1764
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 180 1620
11 11 Mech./Elect. 1 prs 1 9 36 324
12 12 Tool Keeper 1 prs 1 9 36 324
13 Total 16 prs 16 144 730 6570
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 10, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 10, 2019 TOMORROW : August 11, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 68% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 37 333
2 2 Supervisor 1 prs 1 9 37 333
3 3 Foreman 1 prs 1 9 37 333
4 4 Safety Man 1 prs 1 9 37 333
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 140 1260
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 199 1791
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 185 1665
11 11 Mech./Elect. 1 prs 1 9 37 333
12 12 Tool Keeper 1 prs 1 9 37 333
13 Total 16 prs 16 144 746 6714
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 12, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 12, 2019 TOMORROW : August 13, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 72% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 38 342
2 2 Supervisor 1 prs 1 9 38 342
3 3 Foreman 1 prs 1 9 38 342
4 4 Safety Man 1 prs 1 9 38 342
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 142 1278
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 202 1818
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 190 1710
11 11 Mech./Elect. 1 prs 1 9 38 342
12 12 Tool Keeper 1 prs 1 9 38 342
13 Total 16 prs 16 144 762 6858
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 13, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 13, 2019 TOMORROW : August 14, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 87% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 39 351
2 2 Supervisor 1 prs 1 9 39 351
3 3 Foreman 1 prs 1 9 39 351
4 4 Safety Man 1 prs 1 9 39 351
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 144 1296
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 205 1845
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 195 1755
11 11 Mech./Elect. 1 prs 1 9 39 351
12 12 Tool Keeper 1 prs 1 9 39 351
13 Total 16 prs 16 144 778 7002
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 14, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 14, 2019 TOMORROW : August 15, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 89% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 40 360
2 2 Supervisor 1 prs 1 9 40 360
3 3 Foreman 1 prs 1 9 40 360
4 4 Safety Man 1 prs 1 9 40 360
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 146 1314
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 208 1872
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 200 1800
11 11 Mech./Elect. 1 prs 1 9 40 360
12 12 Tool Keeper 1 prs 1 9 40 360
13 Total 16 prs 16 144 794 7146
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 15, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 15, 2019 TOMORROW : August 16, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 92% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 41 369
2 2 Supervisor 1 prs 1 9 41 369
3 3 Foreman 1 prs 1 9 41 369
4 4 Safety Man 1 prs 1 9 41 369
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 148 1332
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 211 1899
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 205 1845
11 11 Mech./Elect. 1 prs 1 9 41 369
12 12 Tool Keeper 1 prs 1 9 41 369
13 Total 16 prs 16 144 810 7290
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 16, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 16, 2019 TOMORROW : August 17, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 95% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 42 378
2 2 Supervisor 1 prs 1 9 42 378
3 3 Foreman 1 prs 1 9 42 378
4 4 Safety Man 1 prs 1 9 42 378
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 150 1350
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 214 1926
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 210 1890
11 11 Mech./Elect. 1 prs 1 9 42 378
12 12 Tool Keeper 1 prs 1 9 42 378
13 Total 16 prs 16 144 826 7434
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 19, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 19, 2019 TOMORROW : August 20, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 C 96% 1 Remove Scaffolding T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 43 387
2 2 Supervisor 1 prs 1 9 43 387
3 3 Foreman 1 prs 1 9 43 387
4 4 Safety Man 1 prs 1 9 43 387
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 152 1368
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 217 1953
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 215 1935
11 11 Mech./Elect. 1 prs 1 9 43 387
12 12 Tool Keeper 1 prs 1 9 43 387
13 Total 16 prs 16 144 842 7578
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 20, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 20, 2019 TOMORROW : August 21, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Remove Scaffolding T-34 F 100% 1 Cleaning area T-34

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 44 396
2 2 Supervisor 1 prs 1 9 44 396
3 3 Foreman 1 prs 1 9 44 396
4 4 Safety Man 1 prs 1 9 44 396
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 154 1386
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 220 1980
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 220 1980
11 11 Mech./Elect. 1 prs 1 9 44 396
12 12 Tool Keeper 1 prs 1 9 44 396
13 Total 16 prs 16 144 858 7722
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :
` Doc No : FM-DUTA-REPT-01
PT. DUTA UTAMA TEHNIK ABADI Page :1
MECHANICAL -ELECTRICAL - CONSTRUCTION
DAILY REPORT Date : 1 Nov 2013
Rev No :0

Project Name : Install Scaffolding T-34 Location : Jln. Raya Merak Km-3, Merak-Banten
Working Area : T-34
Client : PT. Vopak Terminal Merak Date : August 21, 2019
Owner : PT. Vopak Terminal Merak Working Time : 08.00 - 18.00 WIB 9 hour

TO DAY : August 21, 2019 TOMORROW : August 22, 2019


No. DESCRIPTION STATUS PROG'S REMARKS No. DESCRIPTION REMARKS

1 Cleaning area T-34 F 100%

Weather & Hour Notes :


Shinny Hour Till : F= Finish
Cloudly Hour Till : C= Continue
Rainy Hour Till : UP = Under Progress
P= Postpone
Realization Up to date Cumm ED
No. Qt'y No. Manpower Today No EQUIPMENT
Material Request Manday Manhour Manday Manhour up todate today cumm.
1 1 Site Manager 1 prs 1 9 45 405
2 2 Supervisor 1 prs 1 9 45 405
3 3 Foreman 1 prs 1 9 45 405
4 4 Safety Man 1 prs 1 9 45 405
5 5 Administration 0 prs 0 0 0 0
6 6 Skill Worker 2 prs 2 18 156 1404
7 7 QC NDT 0 prs 0 0 0 0
8 8 Semi Skill Worker 3 prs 3 27 223 2007
9 9 Welder 0 prs 0 0 0 0
10 10 Helper 5 prs 5 45 225 2025
11 11 Mech./Elect. 1 prs 1 9 45 405
12 12 Tool Keeper 1 prs 1 9 45 405
13 Total 16 prs 16 144 874 7866
Prepared by : Approved by :
PT. DUTA UTAMA TEHNIK ABADI

Name : Ade Hendrik Name :


Position : Supervisor Position :