Civil Engineering Multiple Choice Questions
Civil Engineering Multiple Choice Questions
2. If the soil is dry, DPC for ground floor consists of layer of:
a) Metal
b) Coarse sand
c) Fine sand
d) Concrete
Answer: b
Explanation: Coarse sand layer of about 75-100mm thickness is provided over the entire area
under the floor. Over this, a layer of plain concrete with a ratio of 1:4:8 of 100mm thickness is
laid.
Civil Engineering. Joseph Asphdin founded Portland cement. Francois Coignet was a French
industrialist and the first to use iron-reinforced concrete.
8. In which beam tension capacity of steel is greater than combined compression capacity of
steel and concrete?
a) Over-reinforced
b) Under-reinforced
c) Singly reinforced
d) Doubly reinforced
Answer: a
Explanation: Over-reinforced beams have higher tension capacity. So, these beams fail by
crushing of compression zone concrete, without any warning.
Answer: d
Explanation: Creep is small deformation that is formed due to loading on concrete. It is a slow,
time dependent process. An increase in temperature and decrease in humidity can cause this.
5. Shear cracks between main wall and cross wall can be corrected using:
a) Grouting
b) Rebuilding
c) Guining
d) Toothing
Answer: d
Explanation: The place where the main and cross wall join, there can be cracks developed. It is
due to poor bonding between walls. Bonding can be increased by toothing, where a projection of
brick is done into the other wall, interlocking it.
directly read from the instrument through telescope. Target staff consists of moving target
against which reading is to be taken.
Answer: b
Explanation: To check if the readings are written properly, an arithmetic check is done. The sum
of back sight (BS) and Fore sight (FS) are subtracted. It should be equal to the difference of the
last and first reduced level (RL).
2. Contour Maps are not mandatory in civil engineering projects like road works, dams, canals,
etc.
a) True
b) False
Answer: b
Explanation: To identify a suitable site for these projects, to study the nature of ground and
slopes and to make an estimate for earth work, a contour map of that region is required.
4. The curves used for drawing lines between points in a contour line is:
a) Radial curve
b) French curve
c) C-curve
d) Inverted curve
Answer: b
Explanation: The contour points are first located. Corresponding points are joined by a smooth
line and for curves, a French curve is used.
6. The line which separates the catchment basin from the rest of the area is:
a) Ridge line
b) Dam line
c) Catchment line
d) Watershed line
Answer: d
Explanation: The area where rain water drains into the river is the catchment area of the river.
The watershed line is then marked. The area inside this line is measured in order to study flood
levels.
Answer: d
Explanation: He was an Austrian civil engineer and geologist. Most of the findings in
geotechnical engineering and soil properties are done by him.
7. Fine particles are those particles with size less than —- mm diameter.
a) 0.023
b) 0.090
c) 0.075
d) 4.75
Answer: c
Explanation: Fine particles should pass through 75μ IS sieve. Fine particles include clay, silt and
organic content in a soil mass.
Answer: c
Explanation: For each country, the administration of highway projects is different. But there are
three factors common to all countries – social, political and economic.
4. A prime coat is low viscosity asphalt emulsion used to create bond between existing
pavement and new asphalt overlay.
a) True
b) False
Answer: b
Explanation: A tack coat is used to bond existing pavement surface to the new asphalt overlay. A
prime coat is applied to base course prior to laying HMA course.
2. In absorption test on brick, how many hours it has to be soaked in cold water?
a) 19 hours
b) 5 hours
c) 6 hours
d) 24 hours
Answer: d
Explanation: The sample brick is oven dried, cooled and then soaked in water at room
temperature for 24 hours.