The JSA document outlines safety procedures for operating a bobcat at the Nissan construction site. It identifies potential hazards at each phase of operation including inspection, start up, travel, grading, refueling, and parking. Control measures are provided to mitigate hazards such as conducting pre-trip inspections, maintaining a safe distance from the bobcat, checking for stable and level ground, wearing PPE, and avoiding smoking when refueling. The document was prepared by R. Ramesh Babu on January 21, 2014 to ensure bobcat operation is performed safely.
The JSA document outlines safety procedures for operating a bobcat at the Nissan construction site. It identifies potential hazards at each phase of operation including inspection, start up, travel, grading, refueling, and parking. Control measures are provided to mitigate hazards such as conducting pre-trip inspections, maintaining a safe distance from the bobcat, checking for stable and level ground, wearing PPE, and avoiding smoking when refueling. The document was prepared by R. Ramesh Babu on January 21, 2014 to ensure bobcat operation is performed safely.
The JSA document outlines safety procedures for operating a bobcat at the Nissan construction site. It identifies potential hazards at each phase of operation including inspection, start up, travel, grading, refueling, and parking. Control measures are provided to mitigate hazards such as conducting pre-trip inspections, maintaining a safe distance from the bobcat, checking for stable and level ground, wearing PPE, and avoiding smoking when refueling. The document was prepared by R. Ramesh Babu on January 21, 2014 to ensure bobcat operation is performed safely.
Date of the JSA – 21/01/2014 Name of the Preparation – R.Ramesh Babu
S.No Scope of Activity Hazard Control Measures Requested By
1) Inspection 1) mechanical problems 1) Conduct pre-trip inspection. P&M/Safety 2) vandalism, tampering 2) Maintain 3-point contact when mounting officer 3) Slipping Hazard or dismounting. 4) Falling Hazard 3) Check steps and platforms for slip resistance. 4) Ensure back-up alarm is functional. 2) Start up 1) Unstable ground 1) Assess ground condition. P&M/Safety 2) work crew 2) Make sure crew and public are safe officer 3) mechanical problems distance from bobcat 4) vandalism, tampering 3) start machine when safe 5) Slipping Hazard 4) Travel to start area. 1) Uneven ground 1) Be aware of whereabouts of crew. P&M/Safety 2) Unstable ground 2) Check mirrors. officer 3) work crew 3) Travel at safe speed. 4) mechanical problems 4) Use extra caution when backing up. 5) Be aware of the traveling public. 5) Slipping Hazard 6) Falling Hazard 5) grading for parking 1) Contact with buildings 1) Make sure width and height of machine is P&M/Safety lot 2) Unstable ground away from building. officer 3) mechanical problems 2) Always be aware of perimeters of bobcat 4) vandalism, tampering 3) Be aware of pedestrians and surroundings 5) Slipping Hazard 6) Falling Hazard 6) Re-fuelling 1) Fire Hazard 1) Stop on level ground. P&M/Safety JSA FOR BOBCAT OPERATION Name of the site – Nissan (2asdu project) Date of the JSA – 21/01/2014 Name of the Preparation – R.Ramesh Babu
2) skin contact 2) Apply parking brake. officer
3) spillage 3) Stop engine and turn off ignition. 4) Unstable ground 4) No smoking. 5) work crew 5) Do not over fill. 6) Wear PPE to avoid contact. 6) mechanical problems 7) Ensure location of spill kit 7) Slipping Hazard 7) Parking bobcat 1) Machine gets stuck 1) Stop on level stable ground area off of the P&M/Safety 2) Vandalism roadway. officer 3) Fire Hazard 2) Mark with proper cones or barricades 4) spillage when needed. 3) Park out of way of sight lines for traveling 5) Unstable ground public. 6) mechanical problems 4) Brake on, block wheels on hills and lock up. 7) Slipping Hazard 5) Activate night switch