Grid-Intertie Photovoltaic System Sizing Worksheet

Electric Load Estimation & System Sizing

Project Name BPSMV, Sonipat, Haryana. - ACNO : S32BS020102 4/10/2021 8:50


ENTER HISTORICAL ELECTRICAL CONSUMPTION ver. SAEL06012020-R0
Ref. Solar Ginc 1871.2 KWh/sq.m
Annual Usage (kWh) 2857368.0 kWh / year Enter Data Into Yellow Shaded Cells
*Monthly
No. of Solar Gen. Green Cells are Write Protected
Monthly Usage(kWh) Billing kWh
Days
1-Jan-19 200424 31 92300
1-Feb-19 194544 28 117400 State Haryana Roof Space. 13000 Sq.meter
1-Mar-19 31 Connected load/sanctioned
232800 154300 90.0% % of power to be generated from PV system load (kWp). 2107 kW
1-Apr-19 169488 30 151400
1-May-19 240624 31 142800 7828.4 Kilowatt-hrs/day 90% of prower from PV
1-Jun-19 308304 30 86600
1-Jul-19 191520 31 110000 Yearly Consumption 2857368 kWh / year
1-Aug-19 270912 31 120500 Avg Monthly 238114.0 kWh / month
1-Sep-19 286392 30 129000 Avg Daily 7828.4 kWh / day
1-Oct-19 357432 31 133500
1-Nov-19 223704 30 109800
1-Dec-19 181224 31 98200 = 7045.6 (kWh) PV System Kilowatt-hrs/day
TOTAL 2857368 365 1445800
% Energy Consumption full fill by Solar Plant 50.6

Array Sizing

2 Determine average sun hours per day. 4.0 sun-hours/day

3 Calculate initial PV array size assuming 100% efficiency.

7045.6 PV System Kilowatt-hrs/day ÷ 4.0 average peak sun hours/day

= 1778.7 PV System Design Capacity (kW)


4 Calculate system inefficiencies / derating factor.
Derating Factors Input Values Typ. Range
Overall DC to AC derate factor 0.880 .60 - .75

5 Calculate array sizing factoring in derating factor. 1001.0 PV System Design Capacity (kW)

6 Confirm array sizing as per roof Space. 1083.3 System is ok

7 %age of power to be generated sanctioned load(kW) 100% System is ok


8 Final System size 1001 PV Array In Kilowatts (DC)
15% Grid penetration % of distribution transformer capacity
System is OK